Cryo Capture Cavity II Progress

20
Cryo Capture Cavity II Progress Mike McGee April 6, 2005

description

Cryo Capture Cavity II Progress. Mike McGee April 6, 2005. DESY will Provide. 1.3 GHz cavity. Helium vessel. Magnet shielding (short). 2 VAT valves. Input coupler assembly. Status at Fermilab. Finalizing US AND DS warm-to-cold transition and VAT valve to cavity spool design. - PowerPoint PPT Presentation

Transcript of Cryo Capture Cavity II Progress

Page 1: Cryo Capture Cavity II Progress

Cryo Capture Cavity II Progress

Mike McGee April 6, 2005

Page 2: Cryo Capture Cavity II Progress

DESY will Provide

•Input coupler assembly

•2 VAT valves

•Magnet shielding (short)

•Helium vessel

•1.3 GHz cavity

Page 3: Cryo Capture Cavity II Progress

Status at Fermilab

•Designing VAT valve supports, shipping/installation fixture (to be made of 316 L)

•316 LN material and tube ready to order

•316 L bellows specified and ordered (to arrive 4/24)

•Finalizing US AND DS warm-to-cold transition and VAT valve to cavity spool design

Page 4: Cryo Capture Cavity II Progress

US warm-to-cold transition

Page 5: Cryo Capture Cavity II Progress

DS warm-to-cold transition

Page 6: Cryo Capture Cavity II Progress

Fermilab will Provide•To be send to DESY

•Cleaned US and DS warm-to-cold transitions (w/isolation flanges on ends and slight positive Ar pressure)

•Drawing and procedure for assembly with fixture to be shipped

•Shipping/installation fixture

•Cleaned VAT valve supports

•Cleaned helium vessel support clamps

•Cleaned spool between cavity and VAT valve (also capped on ends)

Page 7: Cryo Capture Cavity II Progress

Fermilab will Provide•Currently at Fermilab

•Vacuum vessel and instrumentation•80 K shielding•5 K manifold•Tuner •2 Spare VAT valves

Page 8: Cryo Capture Cavity II Progress

Process•Send to DESY (May 2005)

•Cleaned US and DS warm-to-cold transitions and spool

•Under argon positive pressure

valvew/filter

blankflange

Page 9: Cryo Capture Cavity II Progress

Process cont…

•2 helium vessel support clamps

Page 10: Cryo Capture Cavity II Progress

Process cont…•VAT valve supports

Page 11: Cryo Capture Cavity II Progress

Process cont…•Shipping/installation fixture with temporary supports for bellows with crate

Page 12: Cryo Capture Cavity II Progress

Process cont…•Work at DESY (May-June 2005)

•Warm-to-cold transition•Magnet shielding

•VAT valves with supports

•Cavity and helium vessel•Assemble

•Clean US and DS warm-to-cold transitions

•Spool between VAT valve and cavity

Page 13: Cryo Capture Cavity II Progress

Process cont…•Send to Fermilab (July 2005)

•Assembled cavity with VAT valves, shielding, spool and transitions

Page 14: Cryo Capture Cavity II Progress

Process cont…•Work at Fermilab (July-August 2005)

•Modify helium return

•Install cavity assembly into vacuum vessel

•Pressure test helium vessel

•Make up cryogenic connections

•Test fit feedcan and leak check circuits

Page 15: Cryo Capture Cavity II Progress

Process cont…•Install cavity assembly into vacuum vessel

Page 16: Cryo Capture Cavity II Progress

Layout

Page 17: Cryo Capture Cavity II Progress

Layout

Page 18: Cryo Capture Cavity II Progress

Process cont…

•Make up cryogenic connections

•Test fit feedcan and leak check circuits

•Commission Cryo Capture Cavity II

Page 19: Cryo Capture Cavity II Progress

Questions and RequestsNeed DESY cleaning procedure

Need to confirm critical measurements

Page 20: Cryo Capture Cavity II Progress

ScheduleMicrosoft Excel

Worksheet