SERVE-ING TIPPERARYRESULTS & LESSONS
PAUL KENNY
SERVE REGION
© SERVE Project, 2010
Rural Region
CORE PROJECT ACTIVITIES
Retrofitting for Existing Houses and Buildings
New Buildings
Renewable Energy Supply
Monitor and prove results
Research on socio-economic impacts
and sustainable electricity options
Train/Educate people
© SERVE Project, 2010
© SERVE Project, 2010
400Retrofits
50New Builds
73,000m2
© SERVE Project, 2010
600 Wood Stoves
950 m2 Solar Panels
2,000kW Biomass
© SERVE Project, 2010
40,000,000 pieces of
Energy Data
100’s of House Visits
Many Cups of Tea
RESULTS
© SERVE Project, 2010
€4.1m in Grant Aid
11% IRR
13% increase in Biomass
Use
© SERVE Project, 2008
A1 A2 A3 B1 B2 B3 C1 C2 C3 D1 D2 E1 E2 F G0%
5%
10%
15%
20%
25%
NationalTipperarySERVE Pre Upgrade
SERVE MONITORED HOUSES – PRE UPGRADE
EXCELLENT GOOD VERY POOR
SERVE MONITORED HOUSES – POST UPGRADE
© SERVE Project, 2008
A1 A2 A3 B1 B2 B3 C1 C2 C3 D1 D2 E1 E2 F G0%
5%
10%
15%
20%
25%
30%
35%
40%
National
Tipperary
SERVE Post Upgrade
Notable Shift towards B3 / C1
Using National & SERVE BER Databases
EXCELLENT GOOD VERY POOR
NOW AND THEN
• Now a National Retrofit Programme and Grant Supports which have many similarities to SERVE structures• No supports for retrofitting of homes
• 200 construction people trained on quality standards• No training on retrofitting
• SERVE has 40 million data points on energy consumption in dwellings (retrofitted and new buildings)• No data on energy performance of dwellings
• 1.5MW of biomass heating in place on Heat Supply Contracts. ESCO Model Development• No Biomass Heat Supply Contracts in Place© SERVE Project, 2010
LESSONS LEARNED
• Understand what needs to be done.
• Understand why it is not being done.
Then work hard on eliminating barriers!
© SERVE Project, 2010
√√
SMART PROCUREMENT
• Public sector evolving to procure services vs product
• Procure ‘Heat Supply’ or ‘Energy Service’
• One of first in Ireland• Benchmark for full
ESCO development in Ireland
• National Fund Developed
© SERVE Project, 2010
SMART MANAGEMENT
© SERVE Project, 2010
• SERVE – Data and process management key.• SERVE – Retrofit 400 Dwellings in 3 years.• 2013 Social housing Retrofit 500 dwellings in 4
months.• Systems needed to increase pace – integrate:
• Owner/ Tenant• Surveyor/ designer• Procurement• Timeline• Health & Safety• Quality• Financial management
Tipp Energy Agency Solution
Building Professional-BER Assessor- PI insurance- Surveyor/ Civil/ Arch.tech- PSDP
Panel of Contractors:-Annual contractor tender-Standard specification-Schedule of rates (per meter etc)
Housing DatabaseBuilding Survey- Energy Requirements- Rented housing
standards- Condition survey- Measurement
Funding Availability
Inspection process with Building Professional
Automatic Management of TCC/ C2
QA Management of each contractor
P.O. / payment admin
Tenant Liaison
List of Upgrade Requirements
Social Housing Upgrade
Management System(WEB-Based)
SMART MANAGEMENT
© SERVE Project, 2010
SMART FINANCING
• Public & Private Bodies may need finance.• Understand where risk is - Put it where it can be
managed.• SERVE domestic retrofit 11% IRR – not
financeable.• ESCO applicability smaller than many hope
• Low payback, Low finance costs and Low transaction costs are needed.
• ESCO useful for expertise – or where traditional finance unavailable
© SERVE Project, 2010
SMART FINANCING
0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10%0
5
10
15
20
25Simple Payback (yrs) With Rising Interst rates
12345678910
Interest Rate
Actu
al P
ayb
ack
Discounted Payback
© SERVE Project, 2010
CONCLUSIONS
• What needs to be done is clear • We need to be very smart about how to
do it.• We need to subsidise (obligation) and/ or
Tax alternative, as golden rules will ensure failure.
• We need to add scale +200% per year for 10 years!
THANK YOU