Critical Path Analysis Presented by
Mushahid KhatriJaysinh Shukla
Nimish Doshi
![Page 2: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/2.jpg)
“A project is a series of activities directed to accomplishment of a desired objective.”
Project
Plan your work first…..then work your plan
![Page 3: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/3.jpg)
Each event has two important times associated with it :
Earliest time , Te , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times
Latest time , TL , which is the latest time the event can occur without delaying the subsequent events and completion of project.
Difference between the latest time and the earliest time of an event is the slack time for that event
Activity Slack
![Page 4: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/4.jpg)
Float
Negative Zero Positive
Floats
![Page 5: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/5.jpg)
Node
![Page 6: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/6.jpg)
Activity
![Page 7: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/7.jpg)
Starting Event Completion Event
Activity
![Page 8: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/8.jpg)
A
Activity A
![Page 9: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/9.jpg)
A
Activity B must follow A
B
![Page 10: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/10.jpg)
M.R(Mind Refreshment)
![Page 11: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/11.jpg)
BLUE
![Page 12: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/12.jpg)
RED
![Page 13: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/13.jpg)
WHITE
![Page 14: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/14.jpg)
BLACK
![Page 15: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/15.jpg)
YELLOW
![Page 16: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/16.jpg)
ORANGE
![Page 17: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/17.jpg)
BLUE
![Page 18: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/18.jpg)
RED
![Page 19: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/19.jpg)
WHITE
![Page 20: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/20.jpg)
BLACK
![Page 21: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/21.jpg)
YELLOW
![Page 22: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/22.jpg)
ORANGE
![Page 23: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/23.jpg)
BLUE
![Page 24: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/24.jpg)
RED
![Page 25: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/25.jpg)
WHITE
![Page 26: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/26.jpg)
BLACK
![Page 27: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/27.jpg)
YELLOW
![Page 28: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/28.jpg)
ORANGE
![Page 29: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/29.jpg)
Activity
Description Predecessors
Duration (days)
A Organize sales office - 6B Hire salesmen A 4C Train salesmen B 7D Select advertising agency A 2E Plan advertising campaign D 4F Conduct advertising
campaignE 10
G Design package - 2H Setup packaging facilities G 10I Package initial stocks J,H 6J Order stock from
manufacturer- 13
K Select distributors A 9L Sell to distributors C,K 3M Ship stocks to distributors I,L 5
Example
![Page 30: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/30.jpg)
![Page 31: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/31.jpg)
1
4
3
2
7
8
10
5
6 9
A(6)
E(4)D(2)
F(10)
I(6)
M(5)
H(10)J(13)
G(2)
K(9)
B(4)
C(7)
L(3)
![Page 32: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/32.jpg)
1
4
3
2
7
8
10
5
6 9
A(6)
E(4)D(2)
F(10)
I(6)
M(5)
H(10)J(13)
G(2)
K(9)
B(4)
C(7)
L(3)
E4=13L4=14
E1=0L1=0
E9=20L9=20
E3=2L3=4
E2=6L2=6
E5=10L5=10
E6=17L6=17
E7=8L7=11
E8=12L8=15
E10=25L10=25
![Page 33: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/33.jpg)
1
4
3
2
7
8
10
5
6 9
A(6)
E(4)D(2)
F(10)
I(6)
M(5)
H(10)J(13)
G(2)
K(9)
B(4)
C(7)
L(3)
E4=13L4=14
E1=0L1=0
E9=20L9=20
E3=2L3=4
E2=6L2=6
E5=10L5=10
E6=17L6=17
E7=8L7=11
E8=12L8=15
E10=25L10=25
![Page 34: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/34.jpg)
Useful at many stages of project management
Mathematically simple
Give critical path and slack time
Provide project documentation
Useful in monitoring costs
Benefits of CPM
![Page 35: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/35.jpg)
Completion date?
On Schedule?
Within Budget?
Critical Activities?
How can the project be finished early at the least cost?
Questions Answered by CPM
![Page 36: Critical path analysis11](https://reader035.fdocuments.in/reader035/viewer/2022062503/548b159db47959516a8b4a0e/html5/thumbnails/36.jpg)
Thank You for attending short and sweet presentation……