Critical Path Analysis

Transcript of Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be...

Page 1: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Critical Path Analysis

Page 2: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

There are no pre-requisites for this Achievement Standard so it can be placed in any course.No knowledge is pre-supposed.

Page 3: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Methods include a selection from those related to:

precedence tablesnetwork diagramscritical eventsschedulingfloat times

Page 4: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Critical Path Analysis (CPA)

A complex project must be well planned, especially if a number of people are involved.

CPA is used to ensure that the complete scheme is completed in the minimum time.

It is used to schedule the projects.

Page 5: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Any activity can be represented as a project:planning a partybuilding a house/factoryplanning a conference

So what is a project?

Page 6: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

What do the projects have in common?

Each project can be broken down into tasks.Each task takes time and uses resources.Tasks are structured

Page 7: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Step 1 – Precedence table

• To identify actual tasks that make up a project• To identify the order these tasks need to be in• To decide how long each task will take

Page 8: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example: Constructing a garageTask Duration (days)

A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8E Erect walls 10F Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3

Page 9: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Some of these activities must be completed before others can start.

Task Duration (days)A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8E Erect walls 10F Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3

Page 10: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

You can’t erect the roof (G) before you have erected the walls (E)

Task Duration (days)A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8E Erect walls 10F Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3

Page 11: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Precedence

Page 12: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

D must follow E

Task Duration (days)

A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10F Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3

Page 13: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

E must follow A and B

Task Duration (days)

A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3

Page 14: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

F must follow D and G

Task Duration (days)

A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3

Page 15: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

G must follow E

Task Duration (days)

A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8I Fit gutters and pipes 2J Paint outside 3

Page 16: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

H must follow G

Task Duration (days)

A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8 GI Fit gutters and pipes 2J Paint outside 3

Page 17: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

I must follow C, F

Task Duration (days)

A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8 GI Fit gutters and pipes 2 C, FJ Paint outside 3

Page 18: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

J must follow H and I

Task Duration (days)

A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8 GI Fit gutters and pipes 2 C, FJ Paint outside 3 I

Page 19: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

We call this a precedence table

Task Duration (days)

Precedence

A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8 GI Fit gutters and pipes 2 C, FJ Paint outside 3 I

Page 20: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

• Precedence diagrams are not that useful.

• A useful visual representation of a project is a network diagram.

Page 21: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Sequencethe most common sequences / dependencies

Task A Task B

Task ATask B

Task C

Task C

Task B

Task A

Task B depends upon Task A; B cannot start until A is finished

Task C depends upon Task A and B; C cannot start until both A and B are finished

Tasks B and C depend on Task A; neither can start until A is finished, but B and C are independent of each other

Page 22: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

more unusual links and relationships

so far all links have been finish-start links...

Task A Task B

Task A

Task C

Task C

Task A

Task B depends upon Task A, but with a 3 day delay; B cannot start until 3 days after A is finished

The finish of Task C depends upon the finish of Task A

The start of Task C depends on the start of Task A; this is a start-to-start link; it may also incorporate a delay

3 days

Page 23: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Drawing a NETWORK – how do we get here?

Page 24: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Algorithm

Page 25: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Draw in the links Task Precedence

ABCD EE A, BF D, GG EH GI C, FJ I

Page 26: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Draw in A, B, C on a rough diagram

Page 27: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on A, B, C and redraw as shownSTEP 3 - repeat iteration

Page 28: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.
Page 29: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on E and redraw as shownSTEP 3 - repeat iteration

Page 30: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.
Page 31: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on D, G and redraw as shownSTEP 3 - repeat iteration

Page 32: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.
Page 33: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on F and H and redraw as shownSTEP 3 - repeat iteration

Page 34: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.
Page 35: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on I and redraw as shownSTEP 3 - STOP

Page 36: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.
Page 37: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Converting to a usable diagram

Page 38: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Proposed method

Now draw the network diagram using boxes

task number and/or name

durationearly starttime

late starttime

early finishtime

late finishtimefloat

slack

Page 39: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example

Task A

7

Task B

2

Task C

15

Task E

10

Task D

8

Task G

5

Task F

2

Task H

8

Task I

2

Task J

3

Finish

Duration

Page 40: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Critical Path

• Find the earliest possible start for each activity, by going forwards through the network.

• Secondly, the latest possible start time for each activity is found by going backwards through the network.

• Activities which have equal earliest and latest start time are on the critical path.

Page 41: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

3Task 04

6

Task 03

3

Task 08

2

Task 02

4

Task 09

1Task 05

3Task 07

5

Page 42: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

30Task 04

6

Task 03

3

Task 08

2

Task 02

4

Task 09

1Task 05

3Task 07

5

Page 43: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

3 30Task 04

6

Task 03

3

Task 08

2

Task 02

4

Task 09

1Task 05

3Task 07

5

Page 44: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

3 30Task 04

63

Task 03

3

Task 08

2

Task 02

43

Task 09

1Task 05

3Task 07

5

3

Page 45: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

3 30Task 04

63 9

Task 03

3

Task 08

2

Task 02

43 7

Task 09

1Task 05

3Task 07

5

3 5

Page 46: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

3 30Task 04

63 9

Task 03

37

Task 08

25

Task 02

43 7

Task 09

1Task 05

39Task 07

5

3 5

Page 47: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

3 30Task 04

63 9

Task 03

3 107

Task 08

2 75

Task 02

43 7

Task 09

1Task 05

39 12Task 07

5

3 5

Page 48: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

3 30Task 04

63 9

Task 03

3 107

Task 08

2 75

Task 02

43 7

Task 09

1Task 05

39 12Task 07

512

3 5

Take the largest value

Page 49: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

3 30Task 04

63 9

Task 03

3 107

Task 08

2 75

Task 02

43 7

Task 09

1Task 05

39 12Task 07

512 17

3 5

Page 50: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Practice 1

Task 062

Task 01

3 30Task 04

63 9

Task 03

3 107

Task 08

2 75

Task 02

43 7

Task 09

1Task 05

39 12Task 07

512 17

3 5

Take the largest value

Page 51: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Forward pass complete

Duration = 18

Task 062

Task 01

3 30

3

Task 04

63 9

Task 03

3 107

5Task 08

2 75

Task 02

43 7

Task 09

1 1817Task 05

39 12Task 07

512 17

Page 52: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Backward pass

Task 062

Task 01

3 30

3

Task 04

63 9

Task 03

3 107

5Task 08

2 75

Task 02

43 7

Task 09

1 1817Task 05

39 12Task 07

512 17

18

Page 53: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Task 062

Task 01

3 30

3

Task 04

63 9

Task 03

3 107

5Task 08

2 75

Task 02

43 7

Task 09

1 1817Task 05

39 12Task 07

512 17

1817 0

Float

Page 54: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Task 062

Task 01

3 30

3

Task 04

63 9

Task 03

3 107

5Task 08

2 75

Task 02

43 7

Task 09

1 1817Task 05

39 12Task 07

512 17

1817 0

17

17

Page 55: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Task 062

Task 01

3 30

3

Task 04

63 9

Task 03

3 107

5Task 08

2 75

Task 02

43 7

Task 09

1 1817Task 05

39 12Task 07

512 17

1817 0

17

17

12

15

0

10

Page 56: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Task 062

Task 01

3 30

3

Task 04

63 9

Task 03

3 107

5Task 08

2 75

Task 02

43 7

Task 09

1 1817Task 05

39 12Task 07

512 17

1817 0

17

17

12

15

0

10

12

12

9

9 0

2

1513 10

9

93 0

5 2

Page 57: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Forward pass complete

Task 062

Task 01

3 30

3

Task 04

63 9

Task 03

3 107

5Task 08

2 75

Task 02

43 7

Task 09

1 1817Task 05

39 12Task 07

512 17

1817 0

17

17

12

15

0

10

12

12

9

9 0

2

1513 10

9

93 0

5 2

Take the smallest

Page 58: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Critical Path – float = 0

Task 0623 5

13 1510

Task 09

1 1817

1817 0

Task 07

512 17

1712 0Task 05

39 12

129 0

Task 04

63 9

93 0

Task 01

3 30

30 0

Task 08

2 75

1715 10

Task 03

3 107

129 2

Task 02

43 7

95 2

Page 59: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Your turn

Task A

7

Task B

2

Task C

15

Task E

10

Task D

8

Task G

5

Task F

2

Task H

8

Task I

2

Task J

3

Finish

Page 60: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Forward pass

Task A

70

Task B

20

Task C

150

Task E

10

Task D

8

Task G

5

Task F

2

Task H

8

Task I

2

Task J

3

Finish

Page 61: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Forward pass

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10

Task D

8

Task G

5

Task F

2

Task H

8

Task I

2

Task J

3

Finish

Page 62: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take the largest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

107

Task D

8

Task G

5

Task F

2

Task H

8

Task I

2?

Task J

3

Finish

Page 63: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take the largest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

817

Task G

517

Task F

2

Task H

8

Task I

2?

Task J

3

Finish

Page 64: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take the largest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2

Task H

8

Task I

2?

Task J

3

Finish

Page 65: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take the largest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

225

Task H

822

Task I

2?

Task J

3

Finish

Page 66: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Minimum 32

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

Page 67: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Backward pass

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

32

Page 68: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take lowest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

32

32

32

29 0

24 2

Page 69: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take lowest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

32

32

32

29 0

24 2

2927 0

Page 70: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take lowest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

32

32

32

29 0

24 2

2927 0

2725 0

Page 71: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take lowest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

32

32

32

29 0

24 2

2927 0

2725 02517 0

2419 2

Page 72: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take lowest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

32

32

32

29 0

24 2

2927 0

2725 02517 0

2419 2

177 0

Page 73: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Take lowest value

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

32

32

32

29 0

24 2

2927 0

2725 02517 0

2419 2

177 0

2712 12

70 0

7 5 5

Page 74: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Critical Path – zero float

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

32

32

32

29 0

24 2

2927 0

2725 02517 0

2419 2

177 0

2712 12

70 0

7 5 5

Page 75: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Example 1 – Critical Path – A-E-D-F-I-J

Task A

7 70

Task B

2 20

Task C

15 150

Task E

10 177

Task D

8 2517

Task G

5 2217

Task F

2 2725

Task H

8 3022

Task I

2 2927

Task J

3 3229

Finish32

32

32

32

29 0

24 2

2927 0

2725 02517 0

2419 2

177 0

2712 12

70 0

7 5 5

Page 76: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Using the outputs• Gantt Charts• optimising the schedule

Page 77: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Gantt: Critical path in red

Page 78: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Gantt: Critical path in red

Page 79: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Scheduling: Move the critical path along the top

Page 80: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Now fit the other activities like a puzzle

Page 81: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Now fit the other activities like a puzzle

Page 82: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Schedule

Page 83: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Any delay on the critical path causes a delay in the entire project

Page 84: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

There is a 2-day float on the non-critical path

Page 85: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

Definitions

• Critical Path Those activities that can not over run without effecting the total length of the project, are those where the EST = LFT (Total float = 0).

• Total Float LFT of the activity- the duration- EST of the activity. This shows how much ´slack´ there is on a particular route of the network. If the total float is 0 then an activity lies on the critical path.

• Free Float EST of the next activity – Duration – EST of this activity. This shows the ´slack´ on an individual activity before it delays the start of the next activity.

Page 86: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

• EES = Earliest early start time• LLF = latest late finish timeFree float: The amount of time that a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities.

Free Float = EESsuccessor – EF

Page 87: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.

• EES = Earliest early start time• LLF = latest late finish timeIndependent float is that portion of the total float within which an activity can be delayed for start without affecting the float of the preceding activities.

Independent Float = EESsuccessor-LLFpredecessor-duration