Crews ventures lab council of advisors meeting 10.17 updated

11
Council of Advisors October 17, 2012

Transcript of Crews ventures lab council of advisors meeting 10.17 updated

Page 1: Crews ventures lab council of advisors meeting 10.17 updated

Council of Advisors October 17, 2012

Page 2: Crews ventures lab council of advisors meeting 10.17 updated

Agenda• Introductions• Timeline of CVL • Progress on Crews Ventures Lab building

– Demolition– Next steps

• Progress on Program– Application and process– Potential Training Programs– Mentors– Seed Grant Option Exploration

• Recruitment Efforts – Students– Faculty

• Fundraising Status– Update– Need to complete goal of $2 million

• Set next meeting date• Closing

* Triumph Bank: Programming Gift

Page 3: Crews ventures lab council of advisors meeting 10.17 updated

Progress

Page 4: Crews ventures lab council of advisors meeting 10.17 updated

CVL Building – next stepsDocumentation•July 10th Design Development package ready for review-completed•July 10-Sept 5 University review and comments.

– Comments finalized and HVAC system decision

•Sept 6-Oct 29: Construction documents– Architecture and Structure 60-75% complete currently– MP&E sets completed design development Sept 5

•Oct 29-Nov 29: Final reviews, 4 week estimate– University and TBR-concurrent review, 1-2 week estimate– State Fire Marshal submittal, 3-4 week estimate– Local code enforcement, 2-3 week estimate

•Selective Demolition with oversight by the University is tentatively set to begin on or before October 5th

– Demolition scope will remain as part of construction document package and note for the bidders to evaluate conditions during prebid conference

Page 5: Crews ventures lab council of advisors meeting 10.17 updated

CVL Building – next stepsBidding•November 26: Bidding period begins, 3 weeks

– Changes/revisions due to code reviews could be issued, if received, during the first half of the bid period

•December 18: Bids received•January 4, 2013: Bid awarded•January 8: Preconstruction meeting and mobilizationConstruction•January 9: Mobilization, construction begins, 7 month duration•August, 2013 Substantial Completion

Page 6: Crews ventures lab council of advisors meeting 10.17 updated

CVL – the Program• Applications and Process

– Review Application– Interviews– Approval Process

• Potential Training Programs– Pre-Incubation– Incubation

• Mentors– Overview

• Seed Grant Option Explorations– Assisting “clients”

Page 7: Crews ventures lab council of advisors meeting 10.17 updated

CVL Program Recruitment Efforts• Faculty• Students• Community

Page 8: Crews ventures lab council of advisors meeting 10.17 updated

Fundraising Status• $1.76 million raised• Goal $2 million• Proposals Out• Opportunities still available

Page 9: Crews ventures lab council of advisors meeting 10.17 updated

Fundraising status

Page 10: Crews ventures lab council of advisors meeting 10.17 updated

Fundraising Status

Page 11: Crews ventures lab council of advisors meeting 10.17 updated

Conclusion• Set next meeting date• Closing