CREATE ProgramChicago Region Environmental and Transportation
Efficiency (CREATE) Program
Overview
August 2018
![Page 2: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/2.jpg)
2
What is CREATE?
A $4.4 billion Public-Private Partnership (PPP) designed to
improve transportation flow through Chicago focusing on:
• Increased capacity, speed, reliability for freight train traffic
• Separation of freight & commuter trains at 6 key junctions
• Elimination of 25 road/rail grade crossings (grade separations)
CREATE is a cooperative project involving:
• US Department of Transportation (FHWA & FRA)
• Illinois Department of Transportation (IDOT)
• Chicago Department of Transportation (CDOT)
• Cook County
• 6 major North American freight rail carriers and 2 switching railroads
• 2 passenger carriers (Amtrak and Metra)
![Page 3: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/3.jpg)
3
CREATE Partners
![Page 4: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/4.jpg)
4
Why CREATE?
• Freight rail trade (by value) within Chicago will more than
double from 2012 to 2045*
• Passenger, freight and motorist delays are experienced
daily on the current system
• The region must improve freight movement and mitigate
negative impacts
• Freight movements in Chicago are a NATIONAL and
INTERNATIONAL issue, not just a regional one
“Global trade follows the path of least resistance. It will go where there are the fewest impediments.” -UPS
*U.S. DOT Freight Analysis Framework 4.0
![Page 5: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/5.jpg)
5
The U.S. Rail Network Depends on Chicago
• 25 percent of all U.S. rail traffic touches Chicago
• 46 percent of all intermodal units in the U.S. touch Chicago
• 54 percent of intermodal units to/from the ports of Seattle/Tacoma touch Chicago
• 26 percent of intermodal units to/from Los Angeles/Long Beach touch Chicago
Source: 2006 Waybill Sample, based on traffic analysis by ALK Assoc.
![Page 6: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/6.jpg)
6
CREATE: Keeping the Nation’s Economy Moving
![Page 7: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/7.jpg)
7
Top Global Container Ports, 2014
Source: Chicago – Chicago Metropolitan Agency for
Planning Freight Snapshot; American Association of Port
Authorities, 2014
0
5
10
15
20
25
30
35
4035.20
33.87
23.8022.37
19.4518.42
16.62 16.16 15.40 15.16 14.75
Twen
ty F
oo
t Eq
uiv
ale
nt
Un
ite
s (T
EU)
Mill
ion
s
Ports
![Page 8: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/8.jpg)
8
Top U.S. Container Ports, 2014
Source: Chicago – Chicago Metropolitan Agency for
Planning Freight Snapshot; American Association of Port
Authorities, 2014
0
2
4
6
8
10
12
14
16 15.40
8.34
6.82
5.77
3.46 3.35
2.39 2.391.95 1.79Tw
en
ty-F
oo
t Eq
uiv
ale
nt
Un
its
Mill
ion
s
![Page 9: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/9.jpg)
9
CREATE Program – 70 Projects
• 25 road/rail grade separations
• 6 passenger/freight rail grade
separations
• Railroad projects to improve rail
infrastructure and upgrade
technologies
• Viaduct improvement program
• Grade crossing safety enhancements
• Rail operations and visibility improvements
![Page 10: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/10.jpg)
10
Four Corridors
• Passenger Corridors
• East-West Corridor
• Beltway Corridor
• Western Ave. Corridor
![Page 11: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/11.jpg)
11
![Page 12: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/12.jpg)
12
Project Status Summary
![Page 13: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/13.jpg)
13
INFRA Grant Award
$474 million will complete design of the entire 75th Street CIP,
build half of 75th Street CIP and build the Argo BRC Connection
CREATE partners committed $28 million above and beyond
their original intent to push forward & accomplish this phase
$132 million federal INFRA funds closes the gap and pushes
this next phase of the project toward the finish line
75% publicly funded project
![Page 14: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/14.jpg)
14
National Support
• Ford Motor Company
• UPS
• Caterpillar
• Ingredion
• Walgreens
• Wisconsin Electric Power Company ( WEC
Group)
• Illinois Corn Growers Association
• Illinois Petroleum Council
• Midwest Soybean Association
• Indiana Chamber of Commerce
• Ohio Chamber of Commerce
• Indiana Dept of Transportation
• Iowa Dept of Transportation
• Kansas Dept of Transportation
• Michigan Dept of Transportation
• Minnesota Dept of Transportation
• Wisconsin Dept of Transportation
• Northwestern Indiana Regional Planning
Commission
• Southwest Michigan Planning Commission
The Entire Bipartisan Illinois Congressional Delegation
![Page 15: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/15.jpg)
15
75th Street CIP – Existing Conditions
Four Environmentally Linked Projects:
Forest Hill Junction & 71st Street Grade Crossing
• North-south CSX tracks cross
three other east-west tracks
and one city street
Belt Junction
• Five tracks cross paths and
converge into two tracks
• Multiple freight & passenger
routes cross paths
80th Street Junction
• Six tracks cross paths and
converge into two tracks
Environmental Impact Statement (EIS) is complete
![Page 16: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/16.jpg)
16
Rail Operations Map – Existing Conflicts
![Page 17: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/17.jpg)
17
Rail Operations Map – Proposed Final Conditions
![Page 18: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/18.jpg)
18
Review of Project
• Local Mobility
(Viaducts)
• Forest Hill
Junction
• Metra
Reliability
Columbus Ave.
• Metra Rock
Island
Connection
• 80th Street
Junction
• Belt Junction
![Page 19: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/19.jpg)
19
Benefits, Impacts and Mitigation
Benefits of Meeting Purpose and Need for the 75th St. CIP
Reduces rail-rail crossing
conflicts
1. Decreased train idling
2. Decreased air emissions from
locomotives
3. Improved safety and security
Reduces road-rail crossing
conflicts
1. Elimination of the at-grade crossing at
71st Street and CSX tracks
2. Eliminates 3 ½ hours of daily road
closure3. Improved safety
Improves Rail Passenger Service
Reliability
Faster and more reliable Metra and Amtrak
service
Reduces Local Mobility Problems 1. Major improvements at 36 viaducts in
the project area
2. Improved mobility, safety, and security
for drivers, pedestrians, and cyclists3. Improved appearance of viaducts
![Page 20: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/20.jpg)
20
Project Delivery
![Page 21: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/21.jpg)
21
Partners Keep CREATE Moving
• Columbus Ave Grade
Separation – CDOT,
on behalf of CREATE
partners, awarded
Competitive State
Freight Grant ($49 M),
June 2018
![Page 22: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/22.jpg)
22
WA4 – BNSF/CN/NS/CSX
Chicago
• Crossovers
• Connection
• Bridge upgrades
• In progress
• Scheduled to be completed
2018
Reduce rail/rail conflicts
![Page 23: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/23.jpg)
23
Union Pacific Third Mainline (B2)
• Location: Melrose Park, IL
• 60 freight trains & 59 Union Pacific
Metra trains affected
• Actions
▪ Constructed 3.5-mile third main track on UP
▪ Constructed railroad bridge over Addison Creek
▪ Constructed flyover connection from the
Indiana Harbor Belt to the UP
▪ Control points reconfigured
▪ Track between the UP and IHB upgraded
▪ Metra’s Berkeley and Bellwood passenger
stations improved; pedestrian underpasses
constructed
Before
After
![Page 24: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/24.jpg)
24
Englewood Flyover (P1)
METRA/NS/Amtrak – Chicago
• Removes conflict point
between commuter,
passenger, and freight trains,
alleviating delay for
commuters and Amtrak’s
most severe delay point in the
Midwest.
• Completed 2014
Reduce rail/rail conflicts
![Page 25: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/25.jpg)
25
Englewood Flyover (P1)
South Looking North
Before 2011 After 2014
![Page 26: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/26.jpg)
26
71st St Grade Separation, (GS14)
CSX-IHB , Bridgeview
• Grade separation of
71st Street and the
IHB/CSX tracks just
west of Harlem Avenue
• Road underpass
• Completed November
2013
Eliminated road/rail conflict
![Page 27: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/27.jpg)
27
GS14 -- 71st Street/CSX Grade Separation
Before 2011 After 2013
![Page 28: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/28.jpg)
28
130th & Torrence NS –
Chicago (GS15a)
• Eliminates the at-grade crossings
of the two Norfolk Southern main
tracks with 130th Street and
Torrence Ave.
• Eliminates conflict between
railroad and access to Ford Plant
• Road Underpass
• Completed June 2015
Will eliminate road-rail conflicts
![Page 29: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/29.jpg)
29
GS15a– 130th Street & Torrence Ave. /NS Grade Separation
Before 2011 After 2015
![Page 30: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/30.jpg)
30
Viaduct Program
• Locations in the City of Chicago
• Improved roadways, sidewalks
and drainage under railroad
viaducts
• Enhanced safety and security for
motorists, pedestrians, and
bicyclists
• 37 locations completed in 2006
• 14 locations completed in 2012
(USDOT TIGER funding, $5 million)
• 11 completed in 2015/2016
(State of Illinois funding)
![Page 31: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/31.jpg)
31
Viaduct Improvement Program
Before
After
Example: 1530 S Loomis Street
After
Example: 1530 S Racine Avenue
Before
![Page 32: CREATE Programcreateprogram.org/linked_files/2018_CREATE overview_website.pdf•Beltway Corridor •Western Ave. Corridor. 11. 12 Project Status Summary. 13 ... build half of 75th](https://reader035.fdocuments.in/reader035/viewer/2022081612/5f1b5e9c157ffc6c9f3fce48/html5/thumbnails/32.jpg)
32
CREATE Next Steps
•Continue to leverage all funding opportunities
•Execute 75th St. CIP grant & other grant funded projects
•Complete:
▪ Remaining Rail Corridor Projects
▪ Remaining Passenger-Freight Rail Flyover Projects
▪ Remaining Grade Separation Projects