Schneider: Discourse1 CHAPTER 12: DISCOURSE READ 656 Dr. Schneider.
CQ725A1 M504 to Schneider CL20000-25000 inverters wiring M504 to Schneider CL… · SEL 3505 RTAC...
Transcript of CQ725A1 M504 to Schneider CL20000-25000 inverters wiring M504 to Schneider CL… · SEL 3505 RTAC...
SMART GRID ENERGY
INTERNET
SolarVu Servers
Client Access
3G Cellular
SolarVu GATEWAY
SolarVu Enclosure
FIT Meter
Buffalo N300 Router
ROOFTOP ELECTRICAL ROOM
SEL 3505 RTAC
Modbus Communnication Setup
1. In the inverter front panel, navigate to “Setting” and press OK
2. Navigate to “Comm Settings” and press OK
3. Navigate to “Modbus Settings” and press OK
4. Change Baudrate to “9600"
5. Change “Modbus Address” to match its inverter number, i.e. Assign Modbus Address 1 to inverter #1, Modbus Address 2 to inverter #2 etc.
6. Verify setting is correct and press “ESC” to return
Jun 02, 2015 NW/TH
725CQ725A1 M504 to Schneider CL20000-25000 inverters wiring
A1 Jun 02, 2015 SolarVu
Production - As Built© Cachelan Proprietary Information
# 3505XDEX0XAXX 211X0XXXXXX KEY 2706
Client Access
UPS500VAUPS 32
COM1 COM2
COM4COM3 ETH1 ETH2
(Cu & Cu)
SEL3505 RTAC# 3505XDEX3XAX X213X0XXXXXX KEY 2765
COM1 COM2
COM4COM3 ETH2 ETH1
(Cu & Fibre)
SEL 735 Energy Meter # 0735AX00941EX XXXXX16101XXKEY 2215
SEL 2725 Switch# 2725S23X0 KEY 2730
100Base-LX10 SMF
LC-Tx/Rx
USB
ETH1
ETH2
CO
M1
CO
M3
CO
M2
CO
M4
OUT IN
OUT101
1
2
3
LAMP TEST
ETHERCAT
PORT 1
PORT 2
1 +/H2 -/N3 GND
A B C D
Empty Slots E to J
SEL-2242 ChassisSEL-2242 Chassis
SEL-2242 Chassis1: Slot A: SEL-2242 RTAC2: Slot B: SEL-2243 RTAC3: Slot C: SEL-2244-3 Digital Output Module4: Slot D: SEL-2244-2 Digital Input Module5: Slot E to J: Unused
CG50WeatherTrak
T T panel amb
Irradiance
WeatherTrak
Buffalo N300 Router
YF 405 3G Router
YF 405 3G Router
Acuvim II Energy Meter
5-Port Switch
8-Port Switch
Acuvim L Energy Meter
24VDC
30W
120VAC~
24VDC Power Supply
UPS
900 MHzWiMax
Antenna
GE MDS SD09MD-ECES-NNSNN928-960MHz WiMaxRadio/Modem(supplied by THESL,external enclosure)
Terminal
Plug
120VAC UPSCONTROL POWER
Made by APC # BE550G
SOLAR PVDNP3 DATABASE
MEASUREDSTATUSINPUTS
OUTPUTS
LDC Central Office
EnwinSCADA
From CustomerIPP Solar PV Site
Data Query
SCADA DATA Transfer Flow Diagram
ARUBA - RAPRemote Access Point
RAP - WG2
ARUBA For Enwin SCADA
GE MDS Radio / Modem
Receptacle
SolarVu SnocamJunction Box
SnoCamSnoCam
Terminal Board
Digi WR21 Cellular Router
ETH1ETH0
Digi WR21 For HONI SCADA
SolarVu Portal Data Transfer Diagram
Solar Panels
Inverter
AC Recombiner
480/600 VAC
Y Y
Solar Panel, String, Inverter 120 VAC COIL
Contactor
SEL735Energy Meter INPUT
Position SenseOUTPUTActuation
120 VAC Coil
SCADA Meter/Shutdown Enclosure
3x PT 360:120
3x CT 400:53
120VAC From UPS
64
SEL 735 # 0735AX00941EX XXXXX16101XXKEY 2215
INPUTPosition Sense
OUTPUTActuation
120 VAC Coil
3x PT 360:120
3x CT 400:5
64
M
64
M
Disconnect
350A / 600V
PCC
Y-Y Transformer
1
Drawing Note
450A
SolenoidActuator & Breaker
600VFused @ 450A
Fused DisconnectSwitch
SolarVuGateway
SolarVu GATEWAY
SolarVuGateway
K135
S ID=1
M
SolarVu M504-485 Comm Board - GE114
M504 to Schneider CL20000-25000 inverters wiring
1 2 3 4 17 18 19 205 6 7 8 9 10 11 12 13 14 15 16
Port1 Port2 Port3 Port4 To IO Power
Port4 R232
1D+ 1D- 1C 1G 2D+ 2D- 2C 2G 3D+ 3D- 3C 3G 4D+ 4D- 4C 4G G VinGVo
SolarVu Gateway Comm Board
DB9
RJ45 RJ45 RJ45 RJ45
SolarVuGateway
M504
P1 P2 P3 P4
RJ45
*Not all devices inside SolarVu enclosure are shown
MODBUS ETHERNET
Schneider CL25000Inverter #1
MODBUS ETHERNET
Schneider CL25000Inverter #2
MODBUS ETHERNET
Schneider CL25000Inverter #N
RJ45
RJ45
RJ45
RJ45
RJ45
RJ45
RJ45
RJ45
RJ45
RJ45
RJ45
RJ45
Pin 1 1 2 3 4 5 6 7 81 2 3 4 5 6 7 8
T-568B T-568A
1
blu
e
blu
e-w
hite
bro
wn
Ĭ ÒŊŌMÕ Pin Color To M504 Terminal
D+ 4 blue 1
D‐ 5 blue‐white 2
GND 8 brown 3
T‐568B
Ĭ ÒŊŌMÕ Pin Color To M504 Terminal
D+ 4 blue 1
D‐ 5 blue‐white 2
GND 8 brown 3
T‐568A
1
......
Use blue (D+), blue-white (D-) andbrown (GND) for both T-568A and T-568Btype cable
Ethernet
Ethernet Ethernet
Modbus Terminator, plug it in to the last inverter in the network
2Refer to Modbus Communication Setup to setupcommunication settings for each inverter
2
Signal
Signal
ENG/DRAWISSUED
3575 14th Avenue Unit #7Markham, ON L3R 0H6, Canada905.470.8400 cachelan.com
REV
FILE
REV DATE PROJECT
SMART GRID ENERGY