TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report – To Saturday 20 June 2015 Issued 21 June 2015
![Page 2: CPUC - Typhoon Maysak - Restoration Report To 20 June 2015](https://reader035.fdocuments.in/reader035/viewer/2022081818/58eda2751a28abe2758b469d/html5/thumbnails/2.jpg)
TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015
Page 2 of 11
TABLE OF CONTENTS
1 ACTIONS & OPERATIONS – 7th June to 20th June 2015 ................................................................ 3
1.1 Power Restoration .............................................................................................................. 3
1.2 Water Restoration ............................................................................................................... 3
1.3 Sewer System ...................................................................................................................... 3
1.4 Procurement ....................................................................................................................... 3
1.5 Operations Financing .......................................................................................................... 3
2 PROGRESS .................................................................................................................................. 3
3 MISCELLANEOUS ........................................................................................................................ 4
3.1 Restoration Progress: ......................................................................................................... 4
3.2 Liaison with other agencies ................................................................................................. 5
3.2.1 IOM .............................................................................................................................. 5
3.2.2 Pohnpei Utility Corporation ......................................................................................... 5
3.2.3 National Government .................................................................................................. 5
3.3 Weather Advisory From National Weather Service Tiyan Guam ......................................... 5
3.4 Work Program ..................................................................................................................... 5
Annex 1 – Feeder Restoration & Solar System Condition Summaries ................................ 8
ANNEX 2 – Customer Meter Restoration Progress ............................................................. 9
ANNEX 3 – Restoration Summary Graphs ......................................................................... 10
![Page 3: CPUC - Typhoon Maysak - Restoration Report To 20 June 2015](https://reader035.fdocuments.in/reader035/viewer/2022081818/58eda2751a28abe2758b469d/html5/thumbnails/3.jpg)
TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015
Page 3 of 11
1 ACTIONS & OPERATIONS – 7th June to 20th June 2015
1.1 Power Restoration
Primary line recovery efforts in the period have been directed in Wichap and Epinup over the period.
A further 3,250 feet (2.9% of total line length) of line has been reconstructed and energized during
the period. Total line operational to date is 98,700 feet or 89.4% of total line length.
Pole construction from Wichap repeater to the end of Epinup was completed on the 19th June and
restringing of the Epinup single phase line will be completed by the end of w/c 22 June.
Support to tree trimming at the Governor’s office was also provided during the period – this work
will be completed by 29th June.
The peak load remains around 2.1 MW or 95% of peak prior to the typhoon with night-time load
around 1.3 MW. CPUC generation load profile from 30th March to 31st May is shown in Annex 3.
At 20th June all three phase customers and 85.8% (1,491 number) of single phase customers have
been reconnected. Details are shown in Annex 2.
1.2 Water Restoration
Well restoration is complete across Weno.
1.3 Sewer System
Daily pumping operations continued on all lift stations;
1.4 Procurement
Essential materials have now started to arrive in Weno from the first purchase orders placed. CPUC is
still awaiting confirmation of USAID funding balance from IOM/USAID – further procurement is on
hold until that point.
1.5 Operations Financing
Operations continues to be financed from revenues – a detailed update on CPUC financial position
will be included in the June monthly report.
2 PROGRESS
Progress to date versus initial target is indicated in the Annexes 1 to 3 below.
Restoration progress summary charts are shown in Annex 2 & 3.
![Page 4: CPUC - Typhoon Maysak - Restoration Report To 20 June 2015](https://reader035.fdocuments.in/reader035/viewer/2022081818/58eda2751a28abe2758b469d/html5/thumbnails/4.jpg)
TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015
Page 4 of 11
3 MISCELLANEOUS
3.1 Restoration Progress:
Summary of progress made in restoration is tabled below:
Feet As % of
NetworkFeet
As % of
NetworkFeet
As % of
NetworkFeet
As % of
Network
Total System Length: 110,305 110,305 110,305 110,305
Total Restored - 3 Phase 83,706 75.9% 86,192 78.1% 95,411 86.5% 98,666 89.4%
Total Ok but Off 6,675 6.1% 6,053 5.5% 3,248 2.9% 0 0.0%
Total Damaged 19,924 18.1% 18,060 16.4% 11,646 10.6% 11,639 10.6%
Restored LengthsPP to WTP 3,565 3,565 3,565 3,565COM to LS8A 933 933 933 933PP to Tunnuk 13,285 13,285 13,285 13,285Aiprort to WWTP 1,037 1,037 1,037 1,037PP to Municipal 6,005 6,005 6,005 6,005Back Road past Shigeto 1,882 1,882 1,882 1,882V6K ot L5 1,490 1,490 1,490 1,490Old Mormon corner to well 20 681 681 681 681Municipal to Dump site corner 5,999 5,999 5,999 5,999Dummp site to SDA 6,080 6,080 6,080 6,080Blue Lagoon Spur 266 266 266 266Blue Lagoon junct to LS 19 1,243 1,243 1,243 1,243Tunnuk to LS 7 464 464 464 464Tunnuk towards Pou Bay 723 723 723 723Tunnuk to Peniesene - Single phase only 5,400 5,400 5,400 5,400Upper Nantaku 1,075 1,075 1,075 1,075F3 Weno Port Spur 550 550 550 550LS8 to Well 15 460 460 460 460Nepukos Jnct to 83-07 500 500 500 500Nepukos Jnct to TH-09 320 320 320 320mechitiw to ADB 4 1500 1500 1500 1500Wichen Spur to ADB 10 1000 1000 1000 1000F4 J Robert to Wichen Spur 1000 1000 1000 1000Peniesene to Xavier Junction Sapuk 7300 7300 7300 7300Xavier Jnctn to Kansou Bakery 590 590 590 590ADB4 to F1: 30 1492 1492 1492 1492F3: LS18 to LS19 2977 2977 2977 2977Kurassa to Tonachau Mast 2857 2857 2857 2857LS8 to Tunnuk Back Road Switch 520 520 520 520Back road to Pink Apartment Tank 1342 1342 1342 1342Pou Bay to Tunnuk Back Road 4309 4309 4309 4309Well 15 to Hill to Mechitiw road 825 825 825 825Link to Education past Governor office 725 725 725 725Sapuk Kansou Bakery past KORDI 4811 4811 4811 4811Nantaku Behind Governor's office 500 500 500 500Xavier Jnctn to Xavier School 2486 2486 2486N Sapuk Extension 580 580Xavier Back Jnct to B Killion (east) 2588 2588Sapuk Seaside West spur 3842 3842Nepukos Back road left side 2209 2209Blue Lagoon Corner to Wichap Repeater 3255Total Restored 83,706 86,192 95,411 98,666
30-May23-May 06-Jun 19-Jun
![Page 5: CPUC - Typhoon Maysak - Restoration Report To 20 June 2015](https://reader035.fdocuments.in/reader035/viewer/2022081818/58eda2751a28abe2758b469d/html5/thumbnails/5.jpg)
TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015
Page 5 of 11
To date full supply has been restored to 89.4% of the network – the three phase line from Blue
Lagoon corner in Neauo to Wichap Repeater has been rebuilt..
3.2 Liaison with other agencies
3.2.1 IOM
IOM will be acting as the contact agency for CPUC procurement of emergency materials under the
USAID funding program. The disbursement methodology is still being worked out between USAID
and OIM
3.2.2 Pohnpei Utility Corporation
PUC are supporting CPUC with 2 no. 4 man crews. A request has been made to retain one crew for
the first two weeks in July by which time it is anticipated that full system coverage will have been
restored.
3.2.3 National Government
CPUC CFO is liaising with FSM National Finance to disburse funds for the ongoing procurement.
Purchase contracts have been forwarded along with an anticipated disbursement plan.
3.3 Weather Advisory From National Weather Service Tiyan Guam
The latest weather advisory updates from NOAA can be obtained from the link below: http://www.prh.noaa.gov/guam/MicroHazards.php
There is currently no tropical storm activity in the region.
A six day weather summary for Weno can be found at the link below: http://www.tide-forecast.com/locations/Moen-Island-Chuuk-FederatedStatesofMicronesia/forecasts/latest/six_dayp
3.4 Work Program
A work program from 22nd June to 11th July is under preparation and will be issued on 22nd June. This
will be posted on CPUC website: http://www.cpuc.fm/typhoon-maysak-recovery/work-programs/
Note – CPUC Sewer and Water Systems are fully restored to pre-typhoon conditions. Relevant maps
of these systems have now been deleted from the report.
![Page 6: CPUC - Typhoon Maysak - Restoration Report To 20 June 2015](https://reader035.fdocuments.in/reader035/viewer/2022081818/58eda2751a28abe2758b469d/html5/thumbnails/6.jpg)
TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 20 June 2015 Issued 21 June 2015
Page 6 of 11
Primary Cable Status as of 5:00 pm 20 June 2o15
Yellow – Primary 3 Phase restored – 89.4% of system
length;Green Primary in place but off;Red – Primary down;Pink - Line rebuilding ongoing in Epinup;
CPUC Service crews are working re-establish supply in primary restored areas – significant damage to services has
occurred;
CPUC Power System Recovery Progress – 5:00 pm 20 June 2015
![Page 7: CPUC - Typhoon Maysak - Restoration Report To 20 June 2015](https://reader035.fdocuments.in/reader035/viewer/2022081818/58eda2751a28abe2758b469d/html5/thumbnails/7.jpg)
TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 6 June 2015 Issued 8 June 2015
Page 7 of 11
Initial Damage Assessment – (minor revision from 4th April)
Feet As %
Total System Length 110,305
Total Restored 28,197 25.6%
Total Ok but Off 33,019 29.9%
Total Damaged 49,089 44.5%
Restored Lengths
PP to WTP 3,565
COM to LS8A 933
PP to Tunnuk 13,285
Aiprort to WWTP 1,037
PP to Municipal 6,005
Back Road past Shigeto 1,882
V6K ot L5 1,490
Total Restored 28,197
Unrestored Areas Primary Line Status
OK Down ok Straighten Replace
Tunnuk to Sapuk 18,874 11,936 88 6 41
Peniesene along Wichen river 0 1,963 0 0 8
Municipal to Epinup 11,713 14,263 118 6 20
Nepukos Backroad 0 6,648 0 0 44
Behind Governor office 0 1,070 4 6
F1 Pou Bay CSHS to Mechitiw 550 4,272 11 6 8
F2 Pou Bay CSHS to Tunnuk 1,882 5,010 19 10 7
Nantaku Hill to WTP 0 1,070 6 0 0
Kurassa to Telecome Mast 0 2,857 0 0 10
Total Unrestored 33,019 49,089 246 28 144
Pole Status
![Page 8: CPUC - Typhoon Maysak - Restoration Report To 20 June 2015](https://reader035.fdocuments.in/reader035/viewer/2022081818/58eda2751a28abe2758b469d/html5/thumbnails/8.jpg)
TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 6 June 2015 Issued 8 June 2015
Page 8 of 11
Annex 1 – Feeder Restoration & Solar System Condition Summaries
Target ActualFeeder 1Power Plant to Hospital 30 March 2015 30 March 2015Hospital to Nantaku WTP 03 April 2015 11 April 2015
Feeder 2Power Plant to Governors Office 31 March 2015 31 March 2015Governors office to CSHS 01 April 2015 31 March 2015CSHS to Mechitiw backroad (Pou Bay West) 18 April 2015 18 April 2015CHSH to Tunnuk backrooad (Pou Bay East) 06 May 2015 06 May 2015CSHS to Pink Apt Tank 05 May 2015 05 May 2015
Feeder 3Power Plant to Downtown gas Station 31 March 2015 31 March 2015Downtown Gas Station to Municipal Office 03 April 2015 03 April 2015Municipal Office to Mizpah 07 April 2015 06 April 2015Nepukos Backroad - Yamaha to Nepukos jnctn 04 April 2015 04 April 2015Nepukos Jnctn to Mizpah 07 July 2015 Partial - TH-09; and 83-07 15 AprilMizpah to dump site road jnctn 07 April 2015 06 April 2015Dump site road jnctn to Blue Lagoon - back road 07 April 2015 07 April 2015Dump site road jnctn to Blue Lagoon corner - main road 02 May 2015 01 May 2015Blue Lagoon corner to Quarry 20 June 2015 20 June 2015Quarry to Wichap 20 June 2015 20 June 2015Wichap to Epinup 28 June 2015
Feeder 4Power plant to Airport 30 March 2015 30 March 2015Airport to WWTP 30 March 2015 30 March 2015Airport to Kurassa 01 April 2015 31 March 2015Kurassa to telecom Tower 03 April 2015 02 May 2015Kurassa to Mechitiw corner 03 April 2015 01 April 2015Mechitiw corner to Tunnuk (Pou Bay Causeway) 06 April 2015 01 April 2015Tunnuk to Penia 15 April 2015 15 April 2015Penia to Peniesene 27 April 2015 24 April 2015Peniesene spur 02 May 2015 19 April 105 Partial to Well ADB-10Peniesene to Xavier Jnctn 02 May 2015 24 April 2015Xavier Jnctn to Sapuk 23 May 2015 22 May 2105Xavier jnctn to Xavier HS 30 May 2015 30 May 2015Xavier sea side to Sapuk 02 June 2015 04 June 2015 Patched line/extension from KSORC Side;
SOLAR PV SYSTEMSGrid Connected:
Weno - Chuuk State High School - 200 kWp 8% panel damage - system repair schedule for early July 2015Weno - Chuuk International Airport - 65 kWp System fully restored - 2 April 2015
Stand Alone (schools and Dispensaries):Moch - Mortlocks Region Operational Satowan - Mortlocks Region Operational Lechinioch - Mortlocks Region Operational Oneop - Mortlocks Region Inoperational - Equipment failure pre-typhoonOnoun - Northwest Operational Fanapanges - Faichuk Region Operational Central Wonip - Faichuk Region Operational Munian - Faichuk Region Operational Udot -- Faichuk Region Operational Uman - Southern Namoneas Operational Fefan (Sapore and West Fefan) - Southern Namoneas Operational
Restore DateFeeder Section Comments
![Page 9: CPUC - Typhoon Maysak - Restoration Report To 20 June 2015](https://reader035.fdocuments.in/reader035/viewer/2022081818/58eda2751a28abe2758b469d/html5/thumbnails/9.jpg)
TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 6 June 2015 Issued 8 June 2015
Page 9 of 11
ANNEX 2 – Customer Meter Restoration Progress
SINGLE PHASE METER RESTORATION PROGRESS - 19 June 2015
Weno Villages With Primary Power RestoredVillage Connections Restored Balance Restore %
IRAS 283 262 21 92.6%MECHITIW 259 232 27 89.6%
MWAN 203 175 28 86.2%NANTAKU 13 13 0 100.0%
NEAUO 107 95 12 88.8%NEPUKOS 498 466 32 93.6%
PENIA 32 31 1 96.9%PENIESENE 67 54 13 80.6%
SAPUK 101 73 28 72.3%TUNNUK 102 90 12 88.2%
WICHAP 58 0 58 0.0%Total 1,723 1,491 232 86.5%
Weno Villages Without Primary Power Restored
Village Connections Restored Balance Restore %EPINUP 15 0 15 0.0%
Total 15 0 15 0.0%
System Total 1,738 1,491 247 85.8%
Three phase meter restoration is now fully complete
![Page 10: CPUC - Typhoon Maysak - Restoration Report To 20 June 2015](https://reader035.fdocuments.in/reader035/viewer/2022081818/58eda2751a28abe2758b469d/html5/thumbnails/10.jpg)
TYPHOON MAYSAK - 29 MARCH 2015 Restoration Report to Saturday 6 June 2015 Issued 8 June 2015
Page 10 of 11
ANNEX 3 – Restoration Summary Graphs
The graphs below show restoration progress towards achieving 100% system restoration
0
20,000
40,000
60,000
80,000
100,000
120,000
29-M
ar31
-Mar
02-
Ap
r0
4-A
pr
06
-Ap
r0
8-A
pr
10-A
pr
12-A
pr
14-A
pr
16-A
pr
18-A
pr
20-A
pr
22-A
pr
24-A
pr
26-A
pr
28-A
pr
30-A
pr
02-
May 04
-…0
6-…
08
-…10
-May
12-M
ay14
-May
16-M
ay18
-May
20-M
ay22
-May
24-M
ay26
-May
28-M
ay30
-May
01-
Jun
03-
Jun
05-
Jun
07-
Jun
09
-Ju
n11
-Ju
n13
-Ju
n15
-Ju
n17
-Ju
n19
-Ju
n
Pri
mar
y Li
ne
Le
ng
th R
est
ore
d In
Fe
et
CPUC - Primary Line Restoration Progress
Total Primary Line Length
Primary Line Restored
0
200
400
600
800
1000
1200
1400
1600
1800
2000
30-M
ar
01-
Ap
r0
3-A
pr
05-
Ap
r0
7-A
pr
09
-Ap
r
11-A
pr
13-A
pr
15-A
pr
17-A
pr
19-A
pr
21-A
pr
23-A
pr
25-A
pr
27-A
pr
29-A
pr
01-
May
03-
May
05-
May
07-
May
09
-May
11-M
ay
13-M
ay15
-May
17-M
ay19
-May
21-M
ay
23-M
ay25
-May
27-M
ay29
-May
31-M
ay
02-
Jun
04
-Ju
n0
6-J
un
08
-Ju
n10
-Ju
n
12-J
un
14-J
un
16-J
un
18-J
un
No
. of
Co
nn
ect
ion
s R
est
ore
d
CPUC - Single Phase Power Connection Restoration Progress
Total Connections
Restored Connections