cp2 - Baseline Schedule
-
Upload
harry-basada -
Category
Documents
-
view
214 -
download
1
Transcript of cp2 - Baseline Schedule
![Page 1: cp2 - Baseline Schedule](https://reader035.fdocuments.in/reader035/viewer/2022071810/577cce321a28ab9e788d8667/html5/thumbnails/1.jpg)
ID Task Name Est. Duration Est. Start - Base
1
Est. Finish -
Base 1
Baseline Start Baseline Finish Status
1 1 CONTRACT PACKAGE CP2 CONSTRUCTION SCHEDULE 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
2 1.1 PROJECT MILESTONE 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 Late
3 1.1.1 COMMENCEMENT DATE 0 days Mon 7/1/13 Mon 7/1/13 Mon 7/1/13 Mon 7/1/13 Complete
4 1.1.2 COMPLETION DATE 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task
5 1.1.3 COMPLETE CONSTRUCTION OF FACILITIES 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task
6 1.1.4 COMPLETE EARTHWORKS 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task
7 1.1.5 COMPLETE SUBBASE AND BASE COURSE 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task
8 1.1.6 COMPLETE SURFACE COURSE 0 days Thu 3/31/16 Thu 3/31/16 Sun 1/31/16 Sun 1/31/16 Future Task
9 1.1.7 COMPLETE BRIDGE CONSTRUCTION 0 days Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Future Task
10 1.1.8 COMPLETE DRAINAGE AND SLOPE PROTECTION STRUCTURES 0 days Thu 3/31/16 Thu 3/31/16 Sat 10/24/15 Sat 10/24/15 Future Task
11 1.1.9 MISCELLANEOUS STRUCTURES 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task
12 1.1.10 COMPLETE RELOCATION OF ELECTRICAL DISTRIBUTION SYSTEM 0 days Thu 3/31/16 Thu 3/31/16 Sat 1/30/16 Sat 1/30/16 Future Task
13 1.2 PRELIMINARY WORK/PREPARE/SUBMIT/APPROVE/ SHOP DRAWINGS/DESIGN MIX305 days Mon 7/1/13 Thu 5/1/14 Mon 7/1/13 Thu 5/1/14 On Schedule
14 1.2.1 As Stake Survey 153 days Mon 7/1/13 Sat 11/30/13 Mon 7/1/13 Sat 8/31/13 Complete
15 1.2.2 Survey for Drainage and Slope Protection Structures 47 days Mon 12/16/13 Fri 1/31/14 Thu 8/15/13 Mon 9/30/13 Complete
16 1.2.3 Survey for Water Utilities 52 days Mon 3/10/14 Wed 4/30/14 Thu 8/15/13 Mon 9/30/13 Future Task
17 1.2.4 Survey for Electrical Utilities 36 days Mon 3/17/14 Mon 4/21/14 Thu 8/15/13 Mon 9/30/13 Future Task
18 1.2.5 Topographic Survey for Bridges 34 days Wed 1/15/14 Mon 2/17/14 Thu 8/15/13 Mon 9/30/13 On Schedule
19 1.2.6 Prepare and Submit Shop Drawing of Road Cross Section and Profile 267 days Wed 8/7/13 Wed 4/30/14 Mon 7/8/13 Thu 10/10/13 On Schedule
20 1.2.7 Review by Engineer of Shop Dwg of Road Cross Section and Profile 228 days Sun 9/15/13 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 On Schedule
21 1.2.8 Prepare response & resubmit Shop Dwg of Road Cross Section and Profile 164 days Mon 11/18/13 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 On Schedule
22 1.2.9 Approve Shop Drawing Roads 66 days Mon 2/24/14 Wed 4/30/14 Thu 10/31/13 Thu 10/31/13 Future Task
23 1.2.10 Prepare and Submit Shop Drawing for Drainage and Slope Protection Structures212 days Tue 10/1/13 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 On Schedule
24 1.2.11 Review by Engineer of Shop Dwg of Drainage and Slope Protection Structures 206 days Mon 10/7/13 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 On Schedule
25 1.2.12 Prepare response & resubmit Shop Dwg of Drainage and Slope Protection Structures178 days Mon 11/4/13 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 On Schedule
26 1.2.13 Approve Shop Drawing Drainage/Slope Protection 155 days Wed 11/27/13 Wed 4/30/14 Fri 11/1/13 Fri 11/1/13 On Schedule
27 1.2.14 Prepare and Submit Shop Drawing for Water Utilities 30 days Tue 4/1/14 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 Future Task
28 1.2.15 Review by Engineer of Shop Dwg for Water Utilities 24 days Mon 4/7/14 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 Future Task
29 1.2.16 Prepare response & resubmit Shop Dwg of Water Utilities 17 days Mon 4/14/14 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 Future Task
30 1.2.17 Approve Shop Drawing Water Utilities 10 days Mon 4/21/14 Wed 4/30/14 Thu 10/31/13 Thu 10/31/13 Future Task
31 1.2.18 Prepare and Submit Shop Drawing for Electrical Utilities 50 days Wed 3/12/14 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 Future Task
32 1.2.19 Review by Engineer of Shop Dwg for Electrical Utilities 45 days Mon 3/17/14 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 Future Task
33 1.2.20 Prepare response & resubmit Shop Dwg of Electrical Utilities 38 days Mon 3/24/14 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 Future Task
34 1.2.21 Approve Shop Drawings Electrical Utilities 30 days Tue 4/1/14 Wed 4/30/14 Thu 10/31/13 Thu 10/31/13 Future Task
35 1.2.22 Prepare and Submit Shop Drawing for Bridges 66 days Mon 2/24/14 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 Future Task
36 1.2.23 Review by Engineer of Shop Dwg for Bridges 59 days Mon 3/3/14 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 Future Task
37 1.2.24 Prepare response & resubmit Shop Dwg of Bridges 57 days Wed 3/5/14 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 Future Task
38 1.2.25 Approve Shop Drawings Bridges 45 days Mon 3/17/14 Wed 4/30/14 Fri 11/8/13 Fri 11/8/13 Future Task
39 1.2.26 Submit Concrete Mix Design 30 days Fri 11/1/13 Sat 11/30/13 Fri 11/1/13 Sat 11/30/13 Complete
40 1.2.27 Review by Engineer of Concrete Mix Design 14 days Sun 12/1/13 Sat 12/14/13 Sun 12/1/13 Sat 12/14/13 Complete
41 1.2.28 Prepare response & resubmit Concrete Mix Design 7 days Sun 12/15/13 Sat 12/21/13 Sun 12/15/13 Sat 12/21/13 Complete
42 1.2.29 Approve Concrete Mix Design 1 day Sun 12/22/13 Sun 12/22/13 Sun 12/22/13 Sun 12/22/13 Complete
43 1.2.30 Prepare and Submit Shop Drawing for Engineers Quarters, Laboratory and Field Office15 days Mon 7/1/13 Mon 7/15/13 Mon 7/1/13 Mon 7/15/13 Complete
44 1.2.31 Review by Engineer of Shop Dwg for Engineers Quarters, Laboratory and Field Office14 days Tue 7/16/13 Mon 7/29/13 Tue 7/16/13 Mon 7/29/13 Complete
45 1.2.32 Prepare response and resubmit Shop Dwg for Engineers Quarters, Laboratory
and Field Office
7 days Tue 7/30/13 Mon 8/5/13 Tue 7/30/13 Mon 8/5/13 Complete
46 1.2.33 Approve Shop Drawings Engineers Quarters, Laboratory and Field Office 1 day Mon 8/5/13 Mon 8/5/13 Mon 8/5/13 Mon 8/5/13 Complete
47 1.2.34 Submit Soil Quality Test/Stabilization Mix Design 67 days Thu 8/1/13 Sun 10/6/13 Thu 8/1/13 Sun 10/6/13 Complete
48 1.2.35 Review by Engineer of Soil Quality Test/Stabilization Mix Design 14 days Mon 10/7/13 Sun 10/20/13 Mon 10/7/13 Sun 10/20/13 Complete
49 1.2.36 Prepare response & resubmit Soil Quality Test/Stabilization Mix Design 7 days Mon 10/21/13 Sun 10/27/13 Mon 10/21/13 Sun 10/27/13 Complete
50 1.2.37 Approve Soil Quality Test/Stabilization Mix Design 1 day Sun 10/27/13 Sun 10/27/13 Sun 10/27/13 Sun 10/27/13 Complete
51 1.2.38 Prepare and Submit Shop Drawing for Miscellaneous Structures 230 days Thu 8/22/13 Tue 4/8/14 Thu 8/22/13 Tue 4/8/14 On Schedule
52 1.2.39 Review by Engineer of Shop Dwg for miscellaneous Structures 14 days Wed 4/9/14 Tue 4/22/14 Wed 4/9/14 Tue 4/22/14 Future Task
53 1.2.40 Prepare response & resubmit Shop Dwg for Miscellaneous Structures 7 days Thu 4/24/14 Wed 4/30/14 Thu 4/24/14 Wed 4/30/14 Future Task
54 1.2.41 Approve Shop Drawing Miscellaneous Structures 0 days Thu 5/1/14 Thu 5/1/14 Thu 5/1/14 Thu 5/1/14 Future Task
55 1.3 FACILITIES FOR THE ENGINEERS 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 Late
56 1.3.1 Provide Temp. Field off, Laboratory and Living Quarters for the Engineer (Rental)92 days Mon 7/1/13 Mon 9/30/13 Mon 7/1/13 Mon 9/30/13 Complete
57 1.3.2 Construction of combined Field Office & Laboratory Building and Quarter
Building for the Engineer
56 days Tue 8/6/13 Mon 9/30/13 Tue 8/6/13 Mon 9/30/13 Complete
58 1.3.3 Operate/maintain field Office, Laboratory & quarters for the Engineer 871 days Mon 7/1/13 Tue 12/29/15 Tue 10/1/13 Wed 3/30/16 On Schedule
59 1.3.4 Provide Equipment, Furnitures, Fixtures and Appliances for Field office,
Laboratory and Quarters for the Engineer
46 days Mon 7/1/13 Thu 8/15/13 Mon 7/1/13 Thu 8/15/13 Complete
60 1.3.5 Provide Laboratory Testing Equipment and Apparatus for the Engineer on
Rental Basis
30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete
61 1.3.6 Provide , Operate and Maintain Communication Equipment/Office
Supplies/Consummables for the Engineer
1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
62 1.3.7 Provide Service Vehicle to the Engineer 46 days Mon 7/1/13 Thu 8/15/13 Mon 7/1/13 Thu 8/15/13 Complete
63 1.3.8 Provide and Maintain 4w D Pickup Service Vehicle for the Engineer 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
64 1.3.9 Provide and maintain Survey Instrument/Equipment for Assist. to the Engineer 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
65 1.3.10 Provision of Survey Personnel 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
66 1.3.11 Progress Photographs 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
67 1.3.12 End of Facilities to the Engineers 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task
68 1.4 OTHER GENERAL REQUIREMENTS 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
69 1.4.1 Construction Program 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
70 1.4.1.1 Prepare and Submit Construction Program 31 days Mon 7/1/13 Wed 7/31/13 Mon 7/1/13 Wed 7/31/13 Complete
71 1.4.1.2 Review by Engineer of Construction Program 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete
72 1.4.1.3 Prepare response & resubmit Const. Program 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete
73 1.4.1.4 Update/Report on Construction Program 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule
74 1.4.2 Quality Assurance Management System Manual 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
75 1.4.2.1 Prepare and Submit Quality Assurance Management System Manual 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete
76 1.4.2.2 Review by Engineer of QAMSM 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete
77 1.4.2.3 Prepare response & resubmit QAMSM 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete
78 1.4.2.4 Update/Report on QAMSM 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule
79 1.4.3 Environmental and Social Safeguards 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
80 1.4.3.1 Prepare and Submit Environmental and Social Management Plan (ESMP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete
81 1.4.3.2 Review by Engineer of ESMP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete
82 1.4.3.3 Prepare response & resubmit ESMP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete
83 1.4.3.4 Update/Report on ESMP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule
84 1.4.4 Traffic Control 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
85 1.4.4.1 Prepare and Submit Traffic Management Plan (TMP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete
86 1.4.4.2 Review by Engineer of TMP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete
87 1.4.4.3 Prepare response & resubmit TMP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete
88 1.4.4.4 Update/Implement TMP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule
89 1.4.5 Project Implementation 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
90 1.4.5.1 Prepare and Submit Project Implementation Plan (PMP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete
91 1.4.5.2 Review by Engineer of PMP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete
92 1.4.5.3 Prepare response & resubmit PMP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete
93 1.4.5.4 Update/implement PMP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule
94 1.4.6 Construction Health and Safety incl. Materials and First Aid Facilities 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
7/1
3/31
3/31
3/31
3/31
3/31
9/30
3/31
3/31
3/31
50%
100%
100%
0%
0%
50%
67%
61%
46%
0%
58%
57%
50%
43%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
71%
0%
0%
5/1
100%
100%
20%
100%
100%
21%
100%
21%
21%
21%
21%
3/31
100%
100%
100%
17%
21%
100%
100%
100%
17%
21%
100%
100%
100%
17%
21%
100%
100%
100%
17%
21%
100%
100%
100%
17%
21%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2014 2015 2016
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
Baseline 1
SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule
![Page 2: cp2 - Baseline Schedule](https://reader035.fdocuments.in/reader035/viewer/2022071810/577cce321a28ab9e788d8667/html5/thumbnails/2.jpg)
ID Task Name Est. Duration Est. Start - Base
1
Est. Finish -
Base 1
Baseline Start Baseline Finish Status
95 1.4.6.1 Prepare and Submit Health and Safety Plan (HSP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete
96 1.4.6.2 Review by Engineer of HSP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete
97 1.4.6.3 Prepare response & resubmit HSP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete
98 1.4.6.4 Update/Report/ Implement HSP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule
99 1.4.7 Project Billboard/Signs 31 days Mon 7/1/13 Wed 7/31/13 Mon 7/1/13 Wed 7/31/13 Complete
100 1.4.7.1 Prepare and Submit Shop Drawing of Billboard/Signs 15 days Mon 7/1/13 Mon 7/15/13 Mon 7/1/13 Mon 7/15/13 Complete
101 1.4.7.2 Review by Engineer of Shop Drawing 14 days Mon 7/15/13 Sun 7/28/13 Mon 7/15/13 Sun 7/28/13 Complete
102 1.4.7.3 Prepare response & resubmit Shop Drawing 3 days Mon 7/29/13 Wed 7/31/13 Mon 7/29/13 Wed 7/31/13 Complete
103 1.4.7.4 Install Billboard/Signs 3 days Mon 7/29/13 Wed 7/31/13 Mon 7/29/13 Wed 7/31/13 Complete
104 1.4.8 Complete Other General Requirements 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task
105 1.5 EARTHWORKS 730 days Tue 10/1/13 Wed 9/30/15 Thu 10/31/13 Thu 3/31/16 On Schedule
106 1.5.1 SECTION 3: STA 888+500 - STA 873+500 (15.00km) 396 days Tue 10/1/13 Fri 10/31/14 Tue 10/1/13 Fri 10/31/14 On Schedule
107 1.5.1.1 Clearing and Grubbing/Removal of Trees 151 days Sun 10/6/13 Thu 3/20/14 Tue 10/1/13 Fri 2/28/14 On Schedule
108 1.5.1.2 Excavation(Incl. pipe culvert/drain excav.)/Embankment 275 days Sat 11/2/13 Wed 10/1/14 Mon 11/4/13 Mon 7/21/14 On Schedule
109 1.5.1.3 Removal of structures and obstructions 149 days Sun 2/16/14 Tue 9/30/14 Wed 11/4/15 Tue 9/30/14 Future Task
110 1.5.1.4 Removal of AC/PCCP/RCPC/RCBC 181 days Tue 1/7/14 Fri 7/25/14 Sat 10/3/15 Fri 7/25/14 On Schedule
111 1.5.1.5 Subgrade Preparation 246 days Tue 12/17/13 Tue 8/19/14 Tue 12/17/13 Tue 8/19/14 On Schedule
112 1.5.1.6 Complete Earthworks Sta 888+500- Sta 873+500 0 days Wed 9/30/15 Wed 9/30/15 Thu 3/31/16 Thu 3/31/16 Future Task
113 1.5.2 SECTION 2: STA 873+500 - STA 858+500 (15.000km) 372 days Mon 11/25/13 Tue 12/2/14 Sat 3/1/14 Tue 12/2/14 On Schedule
114 1.5.2.1 Clearing and Grubbing/Removal of Trees 121 days Mon 11/25/13 Tue 3/25/14 Sat 3/1/14 Sun 6/29/14 On Schedule
115 1.5.2.2 Excavation(Incl. pipe culvert/drain excav.)/Embankment 74 days Sun 3/2/14 Wed 5/14/14 Tue 3/4/14 Tue 11/18/14 Future Task
116 1.5.2.3 Removal of structures and obstructions 116 days Fri 2/21/14 Mon 6/16/14 Tue 3/4/14 Wed 7/30/14 Future Task
117 1.5.2.4 Removal of AC/PCCP/RCPC/RCBC 162 days Fri 2/21/14 Fri 8/1/14 Sat 3/8/14 Thu 9/4/14 Future Task
118 1.5.2.5 Subgrade Preparation 246 days Mon 3/31/14 Mon 12/1/14 Mon 3/31/14 Mon 12/1/14 Future Task
119 1.5.2.6 Complete Earthworks Sta 873+500- Sta 858+500 0 days Tue 12/2/14 Tue 12/2/14 Tue 12/2/14 Tue 12/2/14 Future Task
120 1.5.3 SECTION 1: STA 858+500 - STA 843+500 (15.000km) 381 days Mon 2/17/14 Thu 3/5/15 Mon 6/2/14 Thu 3/5/15 Future Task
121 1.5.3.1 Clearing and Grubbing/Removal of Trees 161 days Mon 2/17/14 Sun 7/27/14 Mon 6/2/14 Tue 9/30/14 Future Task
122 1.5.3.2 Excavation(Incl. pipe culvert/drain excav.)/Embankment 164 days Mon 2/24/14 Wed 8/6/14 Thu 6/5/14 Thu 2/19/15 Future Task
123 1.5.3.3 Removal of structures and obstructions 145 days Fri 2/21/14 Fri 7/18/14 Thu 6/5/14 Fri 10/31/14 Future Task
124 1.5.3.4 Removal of AC/PCCP/RCPC/RCBC 181 days Mon 4/14/14 Sat 10/11/14 Mon 6/9/14 Sat 12/6/14 Future Task
125 1.5.3.5 Subgrade Preparation 246 days Wed 7/2/14 Wed 3/4/15 Wed 7/2/14 Wed 3/4/15 Future Task
126 1.5.3.6 Complete Earthworks Sta 858+500- Sta 843+500 0 days Thu 3/5/15 Thu 3/5/15 Thu 3/5/15 Thu 3/5/15 Future Task
127 1.5.4 SECTION 4: STA 888+500 - STA 907+281.82 (18.78km) 452 days Mon 4/21/14 Thu 7/16/15 Wed 10/1/14 Thu 3/31/16 Future Task
128 1.5.4.1 Clearing and Grubbing/Removal of Trees 105 days Mon 4/21/14 Tue 9/9/14 Wed 10/1/14 Sat 2/28/15 Future Task
129 1.5.4.2 Excavation(Incl. pipe culvert/drain excav.)/Embankment 346 days Sun 6/8/14 Tue 5/19/15 Sat 10/4/14 Mon 9/14/15 Future Task
130 1.5.4.3 Removal of structures and obstructions 186 days Sun 6/15/14Wed 12/17/14 Sat 10/4/14 Tue 4/7/15 Future Task
131 1.5.4.4 Removal of AC/PCCP/RCPC/RCBC 226 days Sun 6/22/14 Mon 2/2/15 Wed 10/8/14 Thu 5/21/15 Future Task
132 1.5.4.5 Subgrade Preparation 334 days Sun 8/17/14 Thu 7/16/15 Sun 5/3/15 Thu 3/31/16 Future Task
133 1.5.4.6 Complete Earthworks Sta 888+500- Sta 907+281.82 0 days Thu 7/16/15 Thu 7/16/15 Thu 3/31/16 Thu 3/31/16 Future Task
134 1.6 SUBBASE/BASE COURSE/SURFACE COURSE 761 days Wed 1/1/14 Sun 1/31/16 Wed 1/1/14 Sun 1/31/16 On Schedule
135 1.6.1 SECTION 3: STA 888+500 - STA 873+500 (15.00km) 259 days Wed 1/1/14 Tue 9/16/14 Wed 1/1/14 Tue 9/16/14 On Schedule
136 1.6.1.1 subbase and base course 240 days Mon 2/24/14 Fri 8/29/14 Wed 1/1/14 Thu 8/28/14 On Schedule
137 1.6.1.2 Placing of PCC Pavement 13 days Fri 2/21/14 Wed 3/5/14 Sun 1/5/14 Sat 9/6/14 Future Task
138 1.6.1.3 Materials Test 198 days Fri 2/21/14 Sat 9/6/14 Sun 1/5/14 Sat 9/6/14 Future Task
139 1.6.1.4 Complete Surface Course Sta 888+500 -Sta 873+500 0 days Sat 9/6/14 Sat 9/6/14 Sat 9/6/14 Sat 9/6/14 Future Task
140 1.6.2 SECTION 2: STA 873+500 - STA 858+500 (15.000km) 393 days Sun 4/6/14 Sun 5/3/15 Sun 8/17/14 Sun 5/3/15 Future Task
141 1.6.2.1 subbase and base course 240 days Sun 4/6/14 Mon 12/1/14 Sun 8/17/14 Mon 4/13/15 Future Task
142 1.6.2.2 Placing of PCC Pavement 246 days Sun 5/4/14 Sun 1/4/15 Sun 8/24/14 Sun 4/26/15 Future Task
143 1.6.2.3 Materials Test 245 days Sun 5/11/14 Sat 1/10/15 Mon 8/25/14 Sun 4/26/15 Future Task
144 1.6.2.4 Complete Surface Course Sta 873+500 -Sta 858+500 0 days Sun 5/3/15 Sun 5/3/15 Sun 5/3/15 Sun 5/3/15 Future Task
145 1.6.3 SECTION 1: STA 858+500 - STA 843+500 (15.000km) 355 days Sun 7/6/14 Thu 6/25/15 Thu 10/16/14 Thu 6/25/15 Future Task
146 1.6.3.1 subbase and base course 240 days Sun 7/6/14 Mon 3/2/15 Thu 10/16/14 Fri 6/12/15 Future Task
147 1.6.3.2 Placing of PCC Pavement 245 days Sun 8/3/14 Sat 4/4/15 Fri 10/24/14 Thu 6/25/15 Future Task
148 1.6.3.3 Materials Test 245 days Sun 8/3/14 Sat 4/4/15 Fri 10/24/14 Thu 6/25/15 Future Task
149 1.6.3.4 Complete Surface Course Sta 858+500 -Sta 843+500 0 days Thu 6/25/15 Thu 6/25/15 Thu 6/25/15 Thu 6/25/15 Future Task
150 1.6.4 SECTION 4: STA 888+500 - STA 907+281.82 (18.78km) 428 days Sun 11/30/14 Sun 1/31/16 Fri 4/24/15 Sun 1/31/16 Future Task
151 1.6.4.1 subbase and base course 251 days Sun 11/30/14 Fri 8/7/15 Fri 4/24/15 Wed 12/30/15 Future Task
152 1.6.4.2 Placing of PCC Pavement 278 days Sun 1/25/15 Thu 10/29/15 Tue 4/28/15 Sat 1/30/16 Future Task
153 1.6.4.3 Materials Test 275 days Sun 1/25/15Mon 10/26/15 Fri 5/1/15 Sat 1/30/16 Future Task
154 1.6.4.4 Complete Surface Course Sta 888+500 -Sta 907+281.82 0 days Sun 1/31/16 Sun 1/31/16 Sun 1/31/16 Sun 1/31/16 Future Task
155 1.7 BRIDGE CONSTRUCTION 669 days Sun 12/1/13 Wed 9/30/15 Sun 12/1/13 Wed 9/30/15 On Schedule
156 1.7.1 Rehabilitation of Existing Bridges 564 days? Sun 3/16/14 Wed 9/30/15 Thu 1/2/14 Wed 9/30/15 Future Task
157 1.7.1.1 BALOTO Bridge 62 days Tue 4/29/14 Sun 6/29/14 Thu 1/2/14 Sun 3/2/14 Future Task
158 1.7.1.1.1 Seismic Retrofit 62 days Tue 4/29/14 Sun 6/29/14 Thu 1/2/14 Sun 3/2/14 Future Task
159 1.7.1.1.1.1 Slab Strengthening 15 days Sun 5/11/14 Sun 5/25/14 Sun 2/16/14 Sun 3/2/14 Future Task
160 1.7.1.1.1.2 Column Strengthening 50 days Tue 4/29/14 Tue 6/17/14 Thu 1/2/14 Sat 2/15/14 Future Task
161 1.7.1.1.1.3 Approach Slab 12 days Wed 6/18/14 Sun 6/29/14 Sun 2/16/14 Sun 2/23/14 Future Task
162 1.7.1.1.2 Non-Seismic Retrofit 30 days Sun 5/11/14 Mon 6/9/14 Thu 1/30/14 Fri 2/21/14 Future Task
163 1.7.1.1.2.1 Repair of Cracks/Concrete/Abutment Slope Protection 30 days Sun 5/11/14 Mon 6/9/14 Thu 1/30/14 Fri 2/21/14 Future Task
164 1.7.1.2 CAGBOBORAC Bridge 108 days Sat 4/19/14 Mon 8/4/14 Sun 2/16/14 Fri 5/9/14 Future Task
165 1.7.1.2.1 Seismic Retrofit 80 days Sat 4/19/14 Mon 7/7/14 Sun 2/16/14 Wed 4/23/14 Future Task
166 1.7.1.2.1.1 Slab Strengthening 23 days Sat 4/19/14 Sun 5/11/14 Tue 3/18/14 Wed 4/9/14 Future Task
167 1.7.1.2.1.2 Column Strengthening 29 days Sun 5/11/14 Sun 6/8/14 Sun 2/16/14 Mon 3/17/14 Future Task
168 1.7.1.2.1.3 Approach Slab 30 days Sun 6/8/14 Mon 7/7/14 Tue 3/25/14 Wed 4/23/14 Future Task
169 1.7.1.2.2 Non-Seismic Retrofit 30 days Sun 7/6/14 Mon 8/4/14 Thu 4/10/14 Fri 5/9/14 Future Task
170 1.7.1.2.2.1 Repair of Cracks/Concrete/Abutment Slope Protection 30 days Sun 7/6/14 Mon 8/4/14 Thu 4/10/14 Fri 5/9/14 Future Task
171 1.7.1.3 MANTANG Bridge 140 days Sat 3/29/14 Fri 8/15/14 Thu 4/24/14 Thu 7/24/14 Future Task
172 1.7.1.3.1 Seismic Retrofit 140 days Sat 3/29/14 Fri 8/15/14 Thu 4/24/14 Thu 7/24/14 Future Task
173 1.7.1.3.1.1 Slab Strengthening 31 days Sun 4/20/14 Tue 5/20/14 Thu 4/24/14 Sat 5/24/14 Future Task
174 1.7.1.3.1.2 Column Strengthening 30 days Sat 3/29/14 Sun 4/27/14 Sun 5/25/14 Mon 6/23/14 Future Task
175 1.7.1.3.1.3 Approach Slab 24 days Wed 7/23/14 Fri 8/15/14 Tue 7/1/14 Thu 7/24/14 Future Task
176 1.7.1.3.2 Non-Seismic Retrofit 61 days Sun 5/25/14 Thu 7/24/14 Sun 5/25/14 Thu 7/24/14 Future Task
177 1.7.1.3.2.1 Repair of Cracks/Concrete/Abutment Slope/Pier Protection 61 days Sun 5/25/14 Thu 7/24/14 Sun 5/25/14 Thu 7/24/14 Future Task
178 1.7.1.4 POLANGI Bridge 168 days Tue 6/24/14 Sun 10/19/14 Tue 6/24/14 Sun 10/19/14 Future Task
179 1.7.1.4.1 Seismic Retrofit 77 days Tue 6/24/14 Fri 9/12/14 Tue 6/24/14 Fri 9/12/14 Future Task
180 1.7.1.4.1.1 Concrete Shear Keys at Abutment 23 days Tue 6/24/14 Wed 7/16/14 Tue 6/24/14 Wed 7/16/14 Future Task
181 1.7.1.4.1.2 Girder Strengthening 23 days Thu 7/24/14 Fri 8/15/14 Thu 7/24/14 Fri 8/15/14 Future Task
182 1.7.1.4.1.3 Approach Slab 28 days Sat 8/16/14 Fri 9/12/14 Sat 8/16/14 Fri 9/12/14 Future Task
183 1.7.1.4.2 Non-Seismic Retrofit 84 days Fri 7/25/14 Sun 10/19/14 Fri 7/25/14 Sun 10/19/14 Future Task
184 1.7.1.4.2.1 Repair of Cracks/Concrete/Expansion Joint/Painting 33 days Fri 7/25/14 Tue 8/26/14 Fri 7/25/14 Tue 8/26/14 Future Task
185 1.7.1.4.2.2 Abutment Slope Protection 31 days Sat 9/13/14Mon 10/13/14 Sat 9/13/14 Mon 10/13/14 Future Task
186 1.7.1.4.2.3 Provision of Asphalt Overlay 4 days Sat 8/30/14 Tue 9/2/14 Sat 8/30/14 Tue 9/2/14 Future Task
187 1.7.1.4.2.4 Replacement of Approach Sidewalk and Railing 20 days Tue 9/30/14 Sun 10/19/14 Tue 9/30/14 Sun 10/19/14 Future Task
188 1.7.1.5 NABUANGAN BRIDGE 306 days Thu 5/1/14 Mon 3/2/15 Thu 5/1/14 Sat 11/15/14 Future Task
189 1.7.1.5.1 Seismic Retrofit 165 days Thu 5/1/14 Sun 10/12/14 Thu 5/1/14 Sat 11/15/14 Future Task
190 1.7.1.5.1.1 Concrete Shear Keys at Abutment/Pier 60 days Mon 6/2/14 Thu 7/31/14 Sat 9/13/14 Tue 11/11/14 Future Task
191 1.7.1.5.1.2 Girder Strengthening 44 days Thu 5/1/14 Fri 6/13/14 Fri 10/3/14 Sat 11/15/14 Future Task
192 1.7.1.5.1.3 Approach Slab 30 days Sat 9/13/14 Sun 10/12/14 Sat 9/13/14 Sun 10/12/14 Future Task
100%
100%
100%
17%
100%
100%
100%
100%
100%
3/31
7%
78%
12%
0%
10%
19%
9/30
9%
56%
0%
0%
0%
0%
12/2
0%
0%
0%
0%
0%
0%
3/5
0%
0%
0%
0%
0%
0%
7/16
1%
13%
0%
0%
9/6
0%
0%
0%
0%
5/3
0%
0%
0%
0%
6/25
0%
0%
0%
0%
1/31
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2014 2015 2016
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
Baseline 1
SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule
![Page 3: cp2 - Baseline Schedule](https://reader035.fdocuments.in/reader035/viewer/2022071810/577cce321a28ab9e788d8667/html5/thumbnails/3.jpg)
ID Task Name Est. Duration Est. Start - Base
1
Est. Finish -
Base 1
Baseline Start Baseline Finish Status
193 1.7.1.5.1.4 Installation of New Bearing Pad 29 days Thu 5/1/14 Thu 5/29/14 Tue 7/15/14 Fri 9/12/14 Future Task
194 1.7.1.5.1.5 Footing Retrofit 60 days Mon 5/5/14 Fri 7/18/14 Thu 5/1/14 Sun 6/29/14 Future Task
195 1.7.1.5.2 Non-Seismic Retrofit 262 days Sat 6/14/14 Mon 3/2/15 Sat 6/14/14 Tue 10/14/14 Future Task
196 1.7.1.5.2.1 Repair of Cracks/Concrete 20 days Fri 9/12/14 Wed 10/1/14 Sat 9/13/14 Thu 10/2/14 Future Task
197 1.7.1.5.2.2 Abutment Slope Protection 45 days Sun 6/15/14 Tue 7/29/14 Sat 6/14/14 Mon 7/28/14 Future Task
198 1.7.1.5.2.3 Provision of Asphalt Overlay 2 days Sun 3/1/15 Mon 3/2/15 Mon 10/13/14 Tue 10/14/14 Future Task
199 1.7.1.5.2.4 Backwall/Wingwall Reconstruction and Girder end Restoration 21 days Sat 6/14/14 Fri 7/4/14 Sat 6/14/14 Fri 7/4/14 Future Task
200 1.7.1.6 SULAT BRIDGE 255 days? Mon 6/30/14 Wed 3/11/15 Mon 6/30/14 Wed 3/11/15 Future Task
201 1.7.1.6.1 Seismic Retrofit 210 days? Mon 6/30/14 Sun 1/25/15 Mon 6/30/14 Sun 1/25/15 Future Task
202 1.7.1.6.1.1 Concrete Shear Keys at Abutment/Pier 60 days Thu 11/27/14 Sun 1/25/15 Thu 11/27/14 Sun 1/25/15 Future Task
203 1.7.1.6.1.2 Rod Restrainer/Column Strengthening 30 days Fri 8/29/14 Sat 9/27/14 Fri 8/29/14 Sat 9/27/14 Future Task
204 1.7.1.6.1.3 Approach Slab 30 days? Mon 10/13/14 Tue 11/11/14 Mon 10/13/14 Tue 11/11/14 Future Task
205 1.7.1.6.1.4 Installation of New Bearing Pad 45 days Mon 10/13/14Wed 11/26/14 Mon 10/13/14 Wed 11/26/14 Future Task
206 1.7.1.6.1.5 Footing Retrofit/Steel Shoe Bumper 60 days Mon 6/30/14 Thu 8/28/14 Mon 6/30/14 Thu 8/28/14 Future Task
207 1.7.1.6.2 Non-Seismic Retrofit 105 days Thu 11/27/14 Wed 3/11/15 Thu 11/27/14 Wed 3/11/15 Future Task
208 1.7.1.6.2.1 Repair of Cracks/Concrete 30 days Thu 11/27/14 Fri 12/26/14 Thu 11/27/14 Fri 12/26/14 Future Task
209 1.7.1.6.2.2 Abutment Slope Protection & Repair 45 days Mon 1/26/15 Wed 3/11/15 Mon 1/26/15 Wed 3/11/15 Future Task
210 1.7.1.6.2.3 Provision of Asphalt Overlay 2 days Mon 1/26/15 Tue 1/27/15 Mon 1/26/15 Tue 1/27/15 Future Task
211 1.7.1.6.2.4 Repair of Expansion Joint 2 days Wed 1/28/15 Thu 1/29/15 Wed 1/28/15 Thu 1/29/15 Future Task
212 1.7.1.7 TAFT BRIDGE 254 days? Fri 8/29/14 Sat 5/9/15 Fri 8/29/14 Sun 5/10/15 Future Task
213 1.7.1.7.1 Seismic Retrofit 149 days Fri 8/29/14 Sat 1/24/15 Fri 8/29/14 Fri 4/10/15 Future Task
214 1.7.1.7.1.1 Concrete Shear Keys at Abutment/Pier 45 days Fri 10/17/14 Sun 11/30/14 Wed 2/25/15 Fri 4/10/15 Future Task
215 1.7.1.7.1.2 Rod Restrainer/Column Strengthening 45 days Sat 9/27/14Mon 11/10/14 Sun 9/28/14 Tue 11/11/14 Future Task
216 1.7.1.7.1.3 Approach Slab 45 days Tue 11/11/14 Thu 12/25/14 Wed 11/12/14 Fri 12/26/14 Future Task
217 1.7.1.7.1.4 Installation of New Bearing Pad 60 days Wed 11/26/14 Sat 1/24/15 Thu 11/27/14 Sun 1/25/15 Future Task
218 1.7.1.7.1.5 Footing Retrofit/Steel Shoe Bumper 60 days Fri 8/29/14Mon 10/27/14 Fri 8/29/14 Mon 10/27/14 Future Task
219 1.7.1.7.2 Non-Seismic Retrofit 105 days? Sun 1/25/15 Sat 5/9/15 Mon 1/26/15 Sun 5/10/15 Future Task
220 1.7.1.7.2.1 Repair of Cracks/Concrete 30 days? Sun 1/25/15 Mon 2/23/15 Mon 1/26/15 Tue 2/24/15 Future Task
221 1.7.1.7.2.2 Abutment Slope Protection and repair 60 days Wed 3/11/15 Sat 5/9/15 Thu 3/12/15 Sun 5/10/15 Future Task
222 1.7.1.7.2.3 Provision of Asphalt Overlay 2 days Fri 4/10/15 Sat 4/11/15 Sat 4/11/15 Sun 4/12/15 Future Task
223 1.7.1.7.2.4 Repair of expansion joint 2 days Sun 4/12/15 Mon 4/13/15 Mon 4/13/15 Tue 4/14/15 Future Task
224 1.7.1.8 DANAO Bridge 61 days Sun 3/23/14 Thu 5/22/14 Wed 8/27/14 Wed 11/12/14 Future Task
225 1.7.1.8.1 Seismic Retrofit 33 days Sun 4/20/14 Thu 5/22/14 Sat 9/13/14 Wed 10/15/14 Future Task
226 1.7.1.8.1.1 Approach Slab 33 days Sun 4/20/14 Thu 5/22/14 Sat 9/13/14 Wed 10/15/14 Future Task
227 1.7.1.8.2 Non-Seismic Retrofit 58 days Sun 3/23/14 Mon 5/19/14 Wed 8/27/14 Wed 11/12/14 Future Task
228 1.7.1.8.2.1 Repair of Cracks/Concrete 31 days Sun 3/23/14 Tue 4/22/14 Wed 8/27/14 Fri 9/26/14 Future Task
229 1.7.1.8.2.2 Abutment Slope Protection 30 days Sun 4/20/14 Mon 5/19/14 Tue 10/14/14 Wed 11/12/14 Future Task
230 1.7.1.9 LAPA Bridge 129 days Sun 5/11/14 Tue 9/16/14 Thu 7/17/14 Fri 12/12/14 Future Task
231 1.7.1.9.1 Seismic Retrofit 66 days Sun 6/1/14 Tue 8/5/14 Thu 7/17/14 Sat 8/30/14 Future Task
232 1.7.1.9.1.1 Concrete Shear Keys at Abutment 30 days Sun 6/1/14 Mon 6/30/14 Thu 7/17/14 Fri 8/15/14 Future Task
233 1.7.1.9.1.2 Approach Slab 45 days Sun 6/22/14 Tue 8/5/14 Thu 7/17/14 Sat 8/30/14 Future Task
234 1.7.1.9.2 Non-Seismic Retrofit 129 days Sun 5/11/14 Tue 9/16/14 Thu 7/17/14 Fri 12/12/14 Future Task
235 1.7.1.9.2.1 Abutment Slope Protection 30 days Sun 5/11/14 Mon 6/9/14 Thu 11/13/14 Fri 12/12/14 Future Task
236 1.7.1.9.2.2 Repair Expansion Joint 45 days Sun 8/3/14 Tue 9/16/14 Sun 8/31/14 Tue 10/14/14 Future Task
237 1.7.1.9.2.3 Replacement of Superstructure 45 days Sun 6/15/14 Tue 7/29/14 Thu 7/17/14 Sat 8/30/14 Future Task
238 1.7.1.9.2.4 Replacement ofApproach Sidewalk & Railing 45 days Sun 6/22/14 Tue 8/5/14 Wed 8/6/14 Fri 9/19/14 Future Task
239 1.7.1.10 ABANG Bridge 188 days Sun 3/30/14 Fri 10/3/14 Sat 8/16/14 Sat 1/17/15 Future Task
240 1.7.1.10.1 Seismic Retrofit 50 days Fri 8/15/14 Fri 10/3/14 Sat 8/16/14 Mon 9/29/14 Future Task
241 1.7.1.10.1.1 Concrete Shear Keys at Abutment 50 days Fri 8/15/14 Fri 10/3/14 Sat 8/16/14 Sun 9/14/14 Future Task
242 1.7.1.10.1.2 Approach Slab 30 days Sat 8/30/14 Sun 9/28/14 Sun 8/31/14 Mon 9/29/14 Future Task
243 1.7.1.10.2 Non-Seismic Retrofit 93 days Sun 3/30/14 Mon 6/30/14 Tue 9/30/14 Sat 1/17/15 Future Task
244 1.7.1.10.2.1 Abutment Slope Protection 30 days Sun 4/27/14 Mon 5/26/14 Fri 12/19/14 Sat 1/17/15 Future Task
245 1.7.1.10.2.2 Pier Scour Protection 30 days Sun 3/30/14 Mon 4/28/14 Tue 9/30/14 Wed 10/29/14 Future Task
246 1.7.1.10.2.3 Replacement of Superstructure 30 days Tue 4/29/14 Wed 5/28/14 Thu 10/30/14 Fri 11/28/14 Future Task
247 1.7.1.10.2.4 Replacement of Approach Sidewalk & Railing 30 days Sun 6/1/14 Mon 6/30/14 Wed 11/19/14 Thu 12/18/14 Future Task
248 1.7.1.11 MANDARINE Bridge 202 days Tue 7/15/14 Sun 2/1/15 Mon 9/15/14 Wed 2/18/15 Future Task
249 1.7.1.11.1 Seismic Retrofit 105 days Tue 7/15/14Mon 10/27/14 Mon 9/15/14 Sun 11/16/14 Future Task
250 1.7.1.11.1.1 Concrete Shear Keys at Abutment 40 days Tue 7/15/14 Sun 8/24/14 Mon 9/15/14 Thu 10/2/14 Future Task
251 1.7.1.11.1.2 Girder Strengthening 32 days Sun 9/14/14Wed 10/15/14 Fri 10/3/14 Mon 11/3/14 Future Task
252 1.7.1.11.1.3 Approach Slab 30 days Sun 9/28/14Mon 10/27/14 Thu 10/16/14 Sun 11/16/14 Future Task
253 1.7.1.11.2 Non-Seismic Retrofit 99 days Sun 10/26/14 Sun 2/1/15 Sat 9/27/14 Wed 2/18/15 Future Task
254 1.7.1.11.2.1 Repair of Cracks/Concrete 30 days Sat 11/15/14 Sun 12/14/14 Sat 9/27/14 Fri 10/24/14 Future Task
255 1.7.1.11.2.2 Abutment Slope Protection 10 days Fri 1/23/15 Sun 2/1/15 Sun 1/18/15 Wed 2/18/15 Future Task
256 1.7.1.11.2.3 Pier Scour Protection/Painting 30 days Wed 12/24/14 Thu 1/22/15 Mon 11/17/14 Thu 12/18/14 Future Task
257 1.7.1.11.2.4 Provision of Asphalt Overlay 2 days Sun 10/26/14Mon 10/27/14 Mon 11/17/14 Tue 11/18/14 Future Task
258 1.7.1.11.2.5 Repair of expansion joint 2 days Sun 10/26/14Mon 10/27/14 Wed 11/19/14 Thu 11/20/14 Future Task
259 1.7.1.12 ACAS Bridge 254 days Sun 3/16/14Mon 11/24/14 Fri 10/10/14 Wed 2/18/15 Future Task
260 1.7.1.12.1 Seismic Retrofit 58 days Sun 3/16/14 Mon 5/12/14 Fri 10/10/14 Fri 11/14/14 Future Task
261 1.7.1.12.1.1 Concrete Shear Keys at Abutment 28 days Sun 3/16/14 Sat 4/12/14 Fri 10/10/14 Thu 11/6/14 Future Task
262 1.7.1.12.1.2 Approach Slab 30 days Sun 4/13/14 Mon 5/12/14 Thu 10/16/14 Fri 11/14/14 Future Task
263 1.7.1.12.2 Non-Seismic Retrofit 198 days Sun 5/11/14Mon 11/24/14 Sat 10/25/14 Wed 2/18/15 Future Task
264 1.7.1.12.2.1 Repair of Cracks 17 days Sun 5/11/14 Tue 5/27/14 Sat 10/25/14 Sun 11/16/14 Future Task
265 1.7.1.12.2.2 Abutment Slope Protection 30 days Sun 6/22/14 Mon 7/21/14 Tue 1/20/15 Wed 2/18/15 Future Task
266 1.7.1.12.2.3 Pier Scour Protection/Painting 32 days Sun 5/25/14 Wed 6/25/14 Mon 11/17/14 Thu 12/18/14 Future Task
267 1.7.1.12.2.4 Provision of Asphalt Overlay 2 days Sun 11/16/14Mon 11/17/14 Sat 11/22/14 Sun 11/23/14 Future Task
268 1.7.1.12.2.5 Repair of expansion joint 2 days Sun 11/23/14Mon 11/24/14 Mon 11/24/14 Tue 11/25/14 Future Task
269 1.7.1.13 LOOP DE LOOP BRIDGE 80 days Sat 11/22/14 Mon 2/9/15 Sat 11/22/14 Mon 2/9/15 Future Task
270 1.7.1.13.1 Seismic Retrofit 20 days Sat 11/22/14 Thu 12/11/14 Sat 11/22/14 Thu 12/11/14 Future Task
271 1.7.1.13.1.1 Concrete Shear Keys at Abutment 15 days Sat 11/22/14 Sat 12/6/14 Sat 11/22/14 Sat 12/6/14 Future Task
272 1.7.1.13.1.2 Approach Slab 20 days Sat 11/22/14 Thu 12/11/14 Sat 11/22/14 Thu 12/11/14 Future Task
273 1.7.1.13.2 Non-Seismic Retrofit 65 days Sun 12/7/14 Mon 2/9/15 Sun 12/7/14 Mon 2/9/15 Future Task
274 1.7.1.13.2.1 Repair of Concrete/Expansion Joint 15 days Sun 12/7/14 Sun 12/21/14 Fri 12/12/14 Fri 12/26/14 Future Task
275 1.7.1.13.2.2 Replacement of Superstructure 30 days Sun 12/7/14 Mon 1/5/15 Sun 12/7/14 Mon 1/5/15 Future Task
276 1.7.1.13.2.3 Replacement of Approach Sidewalk & Railing 45 days Sat 12/27/14 Mon 2/9/15 Sat 12/27/14 Mon 2/9/15 Future Task
277 1.7.1.14 CANJAGUIMET Bridge 92 days Sat 11/22/14 Sat 2/21/15 Sun 12/7/14 Thu 4/2/15 Future Task
278 1.7.1.14.1 Seismic Retrofit 25 days Sun 12/7/14Wed 12/31/14 Sun 12/7/14 Wed 12/31/14 Future Task
279 1.7.1.14.1.1 Concrete Shear Keys at Abutment 23 days Sun 12/7/14Mon 12/29/14 Sun 12/7/14 Mon 12/29/14 Future Task
280 1.7.1.14.1.2 Approach Slab 20 days Fri 12/12/14Wed 12/31/14 Fri 12/12/14 Wed 12/31/14 Future Task
281 1.7.1.14.2 Non-Seismic Retrofit 92 days Sat 11/22/14 Sat 2/21/15 Thu 1/1/15 Thu 4/2/15 Future Task
282 1.7.1.14.2.1 Repair of Cracks/Concrete 30 days Sat 11/22/14 Sun 12/21/14 Thu 1/1/15 Fri 1/30/15 Future Task
283 1.7.1.14.2.2 Abutment Slope Protection 30 days Fri 1/23/15 Sat 2/21/15 Wed 3/4/15 Thu 4/2/15 Future Task
284 1.7.1.14.2.3 Pier Scour Protection/Painting 32 days Mon 12/22/14 Thu 1/22/15 Sat 1/31/15 Tue 3/3/15 Future Task
285 1.7.1.14.2.4 Provision of Asphalt Overlay 2 days Fri 1/23/15 Sat 1/24/15 Wed 3/4/15 Thu 3/5/15 Future Task
286 1.7.1.14.2.5 Repair of expansion joint 2 days Sun 1/25/15 Mon 1/26/15 Fri 3/6/15 Sat 3/7/15 Future Task
287 1.7.1.15 PISAK Bridge 67 days? Tue 12/30/14 Mon 3/23/15 Tue 12/30/14 Sat 5/2/15 Future Task
288 1.7.1.15.1 Seismic Retrofit 32 days? Tue 12/30/14 Fri 1/30/15 Tue 12/30/14 Fri 1/30/15 Future Task
289 1.7.1.15.1.1 Concrete Shear Keys at Abutment 25 days? Tue 12/30/14 Fri 1/23/15 Tue 12/30/14 Fri 1/23/15 Future Task
290 1.7.1.15.1.2 Approach Slab 30 days? Thu 1/1/15 Fri 1/30/15 Thu 1/1/15 Fri 1/30/15 Future Task
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2014 2015 2016
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
Baseline 1
SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule
![Page 4: cp2 - Baseline Schedule](https://reader035.fdocuments.in/reader035/viewer/2022071810/577cce321a28ab9e788d8667/html5/thumbnails/4.jpg)
ID Task Name Est. Duration Est. Start - Base
1
Est. Finish -
Base 1
Baseline Start Baseline Finish Status
291 1.7.1.15.2 Non-Seismic Retrofit 51 days Sat 1/31/15 Mon 3/23/15 Sat 1/31/15 Sat 5/2/15 Future Task
292 1.7.1.15.2.1 Repair of Cracks/Restore Concrete/Painting 33 days Sat 1/31/15 Wed 3/4/15 Sat 1/31/15 Wed 3/4/15 Future Task
293 1.7.1.15.2.2 Abutment Slope Protection 30 days Sun 2/22/15 Mon 3/23/15 Fri 4/3/15 Sat 5/2/15 Future Task
294 1.7.1.15.2.3 Provision of Asphalt Overlay 2 days Thu 3/5/15 Fri 3/6/15 Thu 3/5/15 Fri 3/6/15 Future Task
295 1.7.1.15.2.4 Repair of expansion joint 2 days Mon 2/2/15 Tue 2/3/15 Sat 3/7/15 Sun 3/8/15 Future Task
296 1.7.1.16 CAMP 5 bridge 180 days Mon 12/22/14 Mon 6/1/15 Sat 1/24/15 Mon 6/1/15 Future Task
297 1.7.1.16.1 Seismic Retrofit 86 days Mon 12/22/14 Fri 2/27/15 Sat 1/24/15 Sun 3/1/15 Future Task
298 1.7.1.16.1.1 Concrete Shear Keys at Abutment/Pier 35 days Sat 1/24/15 Fri 2/27/15 Sat 1/24/15 Fri 2/27/15 Future Task
299 1.7.1.16.1.2 Approach Slab 30 days Mon 12/22/14 Tue 1/20/15 Sat 1/31/15 Sun 3/1/15 Future Task
300 1.7.1.16.2 Non-Seismic Retrofit 132 days Sun 2/8/15 Mon 6/1/15 Sat 2/28/15 Mon 6/1/15 Future Task
301 1.7.1.16.2.1 Abutment Slope Protection 30 days Sun 5/3/15 Mon 6/1/15 Sun 5/3/15 Mon 6/1/15 Future Task
302 1.7.1.16.2.2 Pier Scour Protection 30 days Sat 2/28/15 Sun 3/29/15 Sat 2/28/15 Sun 3/29/15 Future Task
303 1.7.1.16.2.3 Repair of Expansion joint 2 days Wed 2/18/15 Thu 2/19/15 Mon 3/30/15 Tue 3/31/15 Future Task
304 1.7.1.16.2.4 Replacement of Superstructure 30 days Sat 2/28/15 Sun 3/29/15 Sat 2/28/15 Sun 3/29/15 Future Task
305 1.7.1.16.2.5 Replacement of Approach Sidewalk & Railing 30 days Sun 2/8/15 Mon 3/9/15 Fri 3/20/15 Sat 4/18/15 Future Task
306 1.7.1.17 CARBON 2 Bridge 182 days Mon 1/19/15 Wed 7/1/15 Sat 2/28/15 Wed 7/1/15 Future Task
307 1.7.1.17.1 Seismic Retrofit 32 days Mon 1/19/15 Thu 2/19/15 Sat 2/28/15 Tue 3/31/15 Future Task
308 1.7.1.17.1.1 Concrete Shear Keys at Abutment 20 days Mon 1/19/15 Sat 2/7/15 Sat 2/28/15 Thu 3/19/15 Future Task
309 1.7.1.17.1.2 Approach Slab 30 days Wed 1/21/15 Thu 2/19/15 Mon 3/2/15 Tue 3/31/15 Future Task
310 1.7.1.17.2 Non-Seismic Retrofit 104 days Fri 3/20/15 Wed 7/1/15 Fri 3/20/15 Wed 7/1/15 Future Task
311 1.7.1.17.2.1 Repair of Concrete/Painting of steel component 25 days Fri 3/20/15 Mon 4/13/15 Fri 3/20/15 Mon 4/13/15 Future Task
312 1.7.1.17.2.2 Abutment Slope Protection 30 days Tue 6/2/15 Wed 7/1/15 Tue 6/2/15 Wed 7/1/15 Future Task
313 1.7.1.17.2.3 Provision of Asphalt Overlay 2 days Tue 4/14/15 Wed 4/15/15 Tue 4/14/15 Wed 4/15/15 Future Task
314 1.7.1.17.2.4 Repair of expansion joint 2 days Thu 4/16/15 Fri 4/17/15 Thu 4/16/15 Fri 4/17/15 Future Task
315 1.7.1.18 TIGA BRIDGE 64 days Fri 3/20/15 Fri 5/22/15 Fri 3/20/15 Fri 5/22/15 Future Task
316 1.7.1.18.1 Seismic Retrofit 37 days Fri 3/20/15 Sat 4/25/15 Fri 3/20/15 Sat 4/25/15 Future Task
317 1.7.1.18.1.1 Concrete Shear Keys at Abutment 20 days Fri 3/20/15 Wed 4/8/15 Fri 3/20/15 Wed 4/8/15 Future Task
318 1.7.1.18.1.2 Approach Slab 25 days Wed 4/1/15 Sat 4/25/15 Wed 4/1/15 Sat 4/25/15 Future Task
319 1.7.1.18.1.3 Cutting of Existing Concrete Structures 7 days Fri 3/20/15 Thu 3/26/15 Fri 3/20/15 Thu 3/26/15 Future Task
320 1.7.1.18.2 Non-Seismic Retrofit 44 days Thu 4/9/15 Fri 5/22/15 Thu 4/9/15 Fri 5/22/15 Future Task
321 1.7.1.18.2.1 Repair of Concrete/Painting of steel component 20 days Thu 4/9/15 Tue 4/28/15 Thu 4/9/15 Tue 4/28/15 Future Task
322 1.7.1.18.2.2 Abutment Slope Protection 25 days Tue 4/28/15 Fri 5/22/15 Tue 4/28/15 Fri 5/22/15 Future Task
323 1.7.1.18.2.3 Provision of Asphalt Overlay 2 days Sun 4/26/15 Mon 4/27/15 Sun 4/26/15 Mon 4/27/15 Future Task
324 1.7.1.18.2.4 Repair of expansion joint 2 days Tue 4/28/15 Wed 4/29/15 Tue 4/28/15 Wed 4/29/15 Future Task
325 1.7.1.19 CARBON 1 Bridge 157 days Sun 7/27/14 Tue 12/30/14 Thu 4/9/15 Sun 7/12/15 Future Task
326 1.7.1.19.1 Seismic Retrofit 58 days Sun 7/27/14 Mon 9/22/14 Thu 4/9/15 Fri 5/8/15 Future Task
327 1.7.1.19.1.1 Concrete Shear Keys at Abutment/Pier 30 days Sun 7/27/14 Mon 8/25/14 Thu 4/9/15 Fri 5/8/15 Future Task
328 1.7.1.19.1.2 Approach Slab 30 days Sun 8/24/14 Mon 9/22/14 Thu 4/9/15 Fri 5/8/15 Future Task
329 1.7.1.19.2 Non-Seismic Retrofit 111 days Thu 9/11/14 Tue 12/30/14 Sat 5/9/15 Sun 7/12/15 Future Task
330 1.7.1.19.2.1 Abutment Slope Protection 30 days Mon 12/1/14 Tue 12/30/14 Mon 6/8/15 Tue 7/7/15 Future Task
331 1.7.1.19.2.2 Pier Scour Protection 30 days Mon 12/1/14 Tue 12/30/14 Sat 5/9/15 Sun 6/7/15 Future Task
332 1.7.1.19.2.3 Replacement of Superstructure 30 days Thu 9/11/14 Fri 10/10/14 Sat 5/9/15 Sun 6/7/15 Future Task
333 1.7.1.19.2.4 Replacement of Approach Sidewalk & Railing 45 days Wed 10/1/14 Fri 11/14/14 Fri 5/29/15 Sun 7/12/15 Future Task
334 1.7.1.20 BAGACAY BRIDGE 156 days Thu 5/1/14 Fri 10/3/14 Sat 5/9/15 Wed 9/30/15 Future Task
335 1.7.1.20.1 Seismic Retrofit 45 days Thu 5/1/14 Sat 6/14/14 Sat 5/9/15 Mon 6/22/15 Future Task
336 1.7.1.20.1.1 Concrete Shear Keys at Abutment/Pier 22 days Thu 5/1/14 Thu 5/22/14 Sat 5/9/15 Mon 6/22/15 Future Task
337 1.7.1.20.1.2 Approach Slab 45 days Thu 5/1/14 Sat 6/14/14 Sat 5/9/15 Mon 6/22/15 Future Task
338 1.7.1.20.2 Non-Seismic Retrofit 104 days Sun 6/22/14 Fri 10/3/14 Tue 6/23/15 Wed 9/30/15 Future Task
339 1.7.1.20.2.1 Abutment Slope Protection 34 days Sun 8/31/14 Fri 10/3/14 Fri 8/28/15 Wed 9/30/15 Future Task
340 1.7.1.20.2.2 Pier Scour Protection 21 days Sun 8/10/14 Sat 8/30/14 Fri 8/7/15 Thu 8/27/15 Future Task
341 1.7.1.20.2.3 Replacement of Superstructure 45 days Sun 6/22/14 Tue 8/5/14 Tue 6/23/15 Thu 8/6/15 Future Task
342 1.7.1.20.2.4 Approach Sidewalk & Railing 45 days Sun 8/10/14 Tue 9/23/14 Mon 7/13/15 Wed 8/26/15 Future Task
343 1.7.1.21 Complete Rehabilitation of Existing Bridges 0 days Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Future Task
344 1.7.2 Construction of New Bridges 387 days Sun 3/23/14 Mon 4/13/15 Sun 12/1/13 Mon 9/14/15 Future Task
345 1.7.2.1 LUMATOD BRIDGE 174 days Sun 3/16/14 Fri 9/5/14 Sun 12/1/13 Sat 8/2/14 Future Task
346 1.7.2.1.1 Bridge Approach/Earthworks 20 days Sun 4/13/14 Fri 5/2/14 Sun 12/1/13 Fri 12/20/13 Future Task
347 1.7.2.1.2 Temporay Detour at Lumatod Bridge Site 13 days Sun 3/16/14 Fri 3/28/14 Sat 12/21/13 Fri 12/27/13 Future Task
348 1.7.2.1.3 Removal of Existing Lumatod Bridge 25.5 days Sun 3/30/14 Thu 4/24/14 Sat 12/28/13 Sun 1/26/14 Future Task
349 1.7.2.1.4 Substructure 80 days Sun 4/27/14 Tue 7/15/14 Mon 1/27/14 Wed 4/16/14 Future Task
350 1.7.2.1.5 Superstructure 60 days Sun 6/22/14 Wed 8/20/14 Thu 4/17/14 Sun 6/15/14 Future Task
351 1.7.2.1.6 River Widening/Abutment Bank Slope Protection 20 days Sun 8/17/14 Fri 9/5/14 Mon 7/14/14 Sat 8/2/14 Future Task
352 1.7.2.2 BURAK BRIDGE 186 days Sun 3/23/14 Wed 9/24/14 Sat 12/21/13 Wed 9/24/14 Future Task
353 1.7.2.2.1 Bridge Approach/Earthworks 20 days Sun 4/6/14 Fri 4/25/14 Sat 12/21/13 Thu 1/9/14 Future Task
354 1.7.2.2.2 Temporary Detour at Burak Bridge Site 10 days Sun 3/23/14 Tue 4/1/14 Fri 1/10/14 Sun 1/19/14 Future Task
355 1.7.2.2.3 Removal of Existing Burak Bridge 20 days Sun 4/6/14 Fri 4/25/14 Mon 1/20/14 Sat 2/8/14 Future Task
356 1.7.2.2.4 Substructure 69 days Thu 5/1/14 Tue 7/8/14 Sun 4/20/14 Tue 7/8/14 Future Task
357 1.7.2.2.5 Superstructure 30 days Wed 7/9/14 Thu 8/7/14 Wed 7/9/14 Thu 8/7/14 Future Task
358 1.7.2.2.6 River Widening/Abutment Bank Slope Protection 20 days Fri 9/5/14 Wed 9/24/14 Fri 9/5/14 Wed 9/24/14 Future Task
359 1.7.2.3 BAYO BRIDGE 171 days Thu 9/25/14 Sat 3/14/15 Thu 9/25/14 Wed 4/8/15 Future Task
360 1.7.2.3.1 Replacement of Superstructure/Approach Sidewalk & Railing 20 days Thu 9/25/14 Tue 10/14/14 Thu 9/25/14 Tue 10/14/14 Future Task
361 1.7.2.3.2 Temporary Detour at Bayo Bridge Site 10 days Wed 10/15/14 Fri 10/24/14 Wed 10/15/14 Fri 10/24/14 Future Task
362 1.7.2.3.3 Removal of Existing Bayo Bridge 20 days Sat 10/25/14 Thu 11/13/14 Sat 10/25/14 Thu 11/13/14 Future Task
363 1.7.2.3.4 Substructure 60 days Fri 11/14/14 Mon 1/12/15 Fri 11/14/14 Mon 1/12/15 Future Task
364 1.7.2.3.5 Superstructure 30 days Tue 1/13/15 Wed 2/11/15 Tue 1/13/15 Wed 2/11/15 Future Task
365 1.7.2.3.6 River Widening/Abutment Bank Slope Protection 20 days Mon 2/23/15 Sat 3/14/15 Fri 3/20/15 Wed 4/8/15 Future Task
366 1.7.2.4 BINALOAN BRIDGE 307 days Wed 6/11/14 Mon 4/13/15 Thu 9/25/14 Fri 5/8/15 Future Task
367 1.7.2.4.1 Bridge Approach/Earthworks 30 days Sun 12/21/14 Mon 1/19/15 Thu 9/25/14 Fri 10/24/14 Future Task
368 1.7.2.4.2 Temporary Detour at Binaloan Bridge Site 25 days Sun 7/13/14 Wed 8/6/14 Sat 10/25/14 Tue 11/18/14 Future Task
369 1.7.2.4.3 Removal of Existing Bayo Bridge 26 days Wed 6/11/14 Sun 7/6/14 Fri 11/14/14 Tue 12/9/14 Future Task
370 1.7.2.4.4 Substructure 125 days Mon 7/7/14 Sat 11/8/14 Wed 12/10/14 Sat 2/7/15 Future Task
371 1.7.2.4.5 Superstructure 60 days Sun 11/9/14 Wed 1/7/15 Sun 2/8/15 Wed 4/8/15 Future Task
372 1.7.2.4.6 River Widening/Abutment Bank Slope Protection 30 days Sun 3/15/15 Mon 4/13/15 Thu 4/9/15 Fri 5/8/15 Future Task
373 1.7.2.5 CANSOLABAO BRIDGE 191 days? Sun 8/10/14 Mon 2/16/15 Thu 2/12/15 Mon 9/14/15 Future Task
374 1.7.2.5.1 Bridge Approach/Earthworks 30 days Sun 8/24/14 Mon 9/22/14 Thu 2/12/15 Fri 3/13/15 Future Task
375 1.7.2.5.2 Temporary Detour at Cansolabao Bridge Site 15 days Sun 8/10/14 Sun 8/24/14 Sat 3/14/15 Sat 3/28/15 Future Task
376 1.7.2.5.3 Removal of Existing Cansolabao Bridge 20 days? Sun 8/31/14 Fri 9/19/14 Sun 3/29/15 Fri 4/17/15 Future Task
377 1.7.2.5.4 Substructure 60 days Sun 9/21/14Wed 11/19/14 Sat 4/18/15 Tue 6/16/15 Future Task
378 1.7.2.5.5 Superstructure 60 days Sun 11/23/14 Wed 1/21/15 Wed 6/17/15 Sat 8/15/15 Future Task
379 1.7.2.5.6 River Widening/Abutment Bank Slope Protection 30 days? Sun 1/18/15 Mon 2/16/15 Sun 8/16/15 Mon 9/14/15 Future Task
380 1.7.3 COMPLETE BRIDGE WORKS 0 days Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Future Task
381 1.8 DRAINAGE AND SLOPE PROTECTION STRUCTURES 921 days Fri 8/23/13 Mon 2/29/16 Fri 11/1/13 Mon 2/29/16 On Schedule
382 1.8.1 SECTION 3: STA 888+500 - STA 873+500 (15.00km) 354.95 days Fri 8/23/13 Tue 8/12/14 Fri 11/1/13 Thu 7/31/14 On Schedule
383 1.8.1.1 Construction of Drainage Works (RCPC,RCBC, Headwalls, Wingwalls,Catch
Basin, Covered & Ditch Canal
191.95 days Sun 11/3/13 Tue 8/12/14 Fri 11/1/13 Thu 7/31/14 On Schedule
384 1.8.1.2 Slope Stability /Protection Works 212 days Wed 1/1/14 Thu 7/31/14 Wed 1/1/14 Thu 7/31/14 On Schedule
389 1.8.2 SECTION 2: STA 873+500 - STA 858+500 (15.00km) 305 days Wed 4/30/14 Sat 2/28/15 Wed 4/30/14 Sat 2/28/15 Future Task
390 1.8.2.1 Construction of Drainage Works (RCPC,RCBC, Headwalls, Wingwalls,Catch
Basin, Covered & Ditch Canal
215 days Wed 4/30/14 Sun 11/30/14 Wed 4/30/14 Sun 11/30/14 Future Task
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
9/30
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
9/30
6%
34%
10%
0%
0%
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2014 2015 2016
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
Baseline 1
SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule
![Page 5: cp2 - Baseline Schedule](https://reader035.fdocuments.in/reader035/viewer/2022071810/577cce321a28ab9e788d8667/html5/thumbnails/5.jpg)
ID Task Name Est. Duration Est. Start - Base
1
Est. Finish -
Base 1
Baseline Start Baseline Finish Status
391 1.8.2.2 Slope Stability /Protection Works 212 days Fri 8/1/14 Sat 2/28/15 Fri 8/1/14 Sat 2/28/15 Future Task
398 1.8.3 SECTION 1: STA 858+500 - STA 843+500 (15.00km) 717 days Sat 3/15/14 Mon 2/29/16 Sat 3/15/14 Mon 2/29/16 Future Task
399 1.8.3.1 Construction of Drainage Works (RCPC,RCBC, Headwalls, Wingwalls,Catch
Basin, Covered & Ditch Canal
215 days Fri 8/1/14 Tue 3/3/15 Fri 8/1/14 Tue 3/3/15 Future Task
400 1.8.3.2 Slope Stability /Protection Works 717 days Sat 3/15/14 Mon 2/29/16 Sat 3/15/14 Mon 2/29/16 Future Task
432 1.8.4 SECTION 4: STA 888+500 - STA 907+281.82 (18.78km) 285 days Mon 12/1/14 Fri 9/11/15 Mon 12/1/14 Fri 9/11/15 Future Task
433 1.8.4.1 Construction of Drainage Works (RCPC,RCBC, Headwalls, Wingwalls,Catch
Basin, Covered & Ditch Canal
285 days Mon 12/1/14 Fri 9/11/15 Mon 12/1/14 Fri 9/11/15 Future Task
434 1.8.5 Complete Drainage and Slope Protection Structures 0 days Mon 2/29/16 Mon 2/29/16 Mon 2/29/16 Mon 2/29/16 Future Task
435 1.9 MISCELLANEOUS STRUCTURES 883 days Mon 9/30/13 Mon 2/29/16 Thu 5/1/14 Mon 2/29/16 On Schedule
436 1.9.1 ROAD STRUCTURES/SIGNAGES/MARKINGS 579 days Mon 9/30/13 Mon 2/29/16 Thu 5/1/14 Mon 2/29/16 On Schedule
437 1.9.2 LANDSCAPING 170 days Sun 9/13/15 Mon 2/29/16 Sun 9/13/15 Mon 2/29/16 Future Task
438 1.9.3 STREET LIGHTING SYSTEM 661 days Thu 5/1/14 Sun 2/21/16 Thu 5/1/14 Sun 2/21/16 Future Task
439 1.9.3.1 Excavation works 193 days Thu 5/1/14 Sun 11/9/14 Thu 5/1/14 Sun 11/9/14 Future Task
440 1.9.3.2 Installation of necessary appurtenances for foundation 200 days Mon 5/5/14 Thu 11/20/14 Mon 5/5/14 Thu 11/20/14 Future Task
441 1.9.3.3 Erection of Pedestal and Posts 207 days Wed 6/4/14 Sat 12/27/14 Wed 6/4/14 Sat 12/27/14 Future Task
442 1.9.3.4 Concrete Ducting works 100 days Wed 6/11/14 Thu 9/18/14 Wed 6/11/14 Thu 9/18/14 Future Task
443 1.9.3.5 Backfilling works 199 days Fri 7/11/14 Sun 1/25/15 Fri 7/11/14 Sun 1/25/15 Future Task
444 1.9.3.6 Installation of necessary appurtenances to complete 230 days Tue 9/9/14 Sun 4/26/15 Tue 9/9/14 Sun 4/26/15 Future Task
445 1.9.3.7 Installation of roadlight luminaire 240 days Mon 4/27/15 Tue 12/22/15 Mon 4/27/15 Tue 12/22/15 Future Task
446 1.9.3.8 Testing and commissioning 60 days Tue 11/3/15 Fri 1/1/16 Tue 11/3/15 Fri 1/1/16 Future Task
447 1.9.3.9 Complete Street Lighting System 0 days Sun 2/21/16 Sun 2/21/16 Sun 2/21/16 Sun 2/21/16 Future Task
448 1.10 PROVISIONAL SUMS 486 days Wed 10/1/14 Sat 1/30/16 Wed 10/1/14 Sat 1/30/16 Future Task
449 1.10.1 RELOCATION OF ELECTRICAL DISTRIBUTION SYSTEM 486 days Wed 10/1/14 Sat 1/30/16 Wed 10/1/14 Sat 1/30/16 Future Task
450 1.10.1.1 Relocation works (With ESAMELCO) 486 days Wed 10/1/14 Fri 1/29/16 Wed 10/1/14 Fri 1/29/16 Future Task
451 1.10.1.2 Complete Relocation 0 days Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Future Task
452 1.10.2 Removal and Relocation of Existing Barangay Markers 180 days Mon 8/3/15 Sat 1/30/16 Mon 8/3/15 Sat 1/30/16 Future Task
453 1.10.2.1 Removal and Relocation of Markers 180 days Mon 8/3/15 Fri 1/29/16 Mon 8/3/15 Fri 1/29/16 Future Task
454 1.10.2.2 Complete Removal and Relocation of Markers 0 days Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Future Task
455 1.10.3 PROVISIONAL SUMS 486 days Wed 10/1/14 Sat 1/30/16 Wed 10/1/14 Sat 1/30/16 Future Task
456 1.10.3.1 Provisional Sum 486 days Wed 10/1/14 Fri 1/29/16 Wed 10/1/14 Fri 1/29/16 Future Task
457 1.10.3.2 Complete Provisional Sum 0 days Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Future Task
458 1.11 DAYWORK 514 days Tue 11/4/14 Thu 3/31/16 Tue 11/4/14 Thu 3/31/16 Future Task
459 1.11.1 Daywork 514 days Tue 11/4/14 Thu 3/31/16 Tue 11/4/14 Thu 3/31/16 Future Task
460 1.12 MOBILIZATION/DEMOBILIZATION 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule
461 1.12.1 Mobilization 215 days Mon 7/1/13 Fri 1/31/14 Mon 7/1/13 Mon 9/30/13 Complete
462 1.12.2 Demobilization 59 days Mon 2/1/16 Wed 3/30/16 Mon 2/1/16 Wed 3/30/16 Future Task
463 1.12.3 As-Built 62 days Sat 1/30/16 Thu 3/31/16 Sat 1/30/16 Thu 3/31/16 Future Task
464 1.13 COMPLETE CP2 PROJECT 0 days Thu 3/31/16 Thu 3/31/16 Wed 3/30/16 Wed 3/30/16 Future Task
0%
0%
0%
0%
2/29
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
2/21
0%
0%
0%
1/30
0%
0%
1/30
0%
0%
1/30
0%
0%
64%
100%
0%
0%
3/31
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2014 2015 2016
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
Baseline 1
SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule