CP_109 Mothballing Pipelines.pdf
-
Upload
mohd-khairul -
Category
Documents
-
view
143 -
download
66
Transcript of CP_109 Mothballing Pipelines.pdf
-
TO CP-LIST
-
Table of Contents Page
1. INTRODUCTION
4
1.1 Scope 4 1.2 Coverage 4 1.3 Terminology 4 1.4 Referenced Documents 5 2. GENERAL REQUIREMENTS
5
3. CRUDE OIL PIPELINE
6
3.1 New Crude Oil Pipelines 6 3.2 In-Service Piggable Crude Oil Pipelines 7 3.3 In-Service Non-Piggable Crude Oil Pipelines
8
4. GAS PIPELINES
9
4.1 New Gas Pipelines 9 4.2 In-Service Piggable Gas Pipelines 9 4.3 In-Service Non-Piggable Gas Pipelines
10
5. WATER PIPELINES
11
5.1 New Water Pipelines 11 5.2 In-Service Piggable Water Pipelines 11 5.3 In-Service Non-Piggable Water Pipelines
12
6. PROCEDURE FOR MOTHBALLING WITH TREATED WATER
13
6.1 Mothballing of Non-Piggable Pipelines & all pipelines to be safely kept for upto 1 month
13
6.2 Mothablling of Piggable Pipelines for Periods Up to 6 Months 14 6.3 Mothballing of Piggable Pipelines for Periods 6-18 Months 16 6.4 Mothballing of Piggable Pipelines for Periods 18 Months - 5 Years 17 6.5 Mothballing of new Pipelines
17
7. PROCEDURE FOR MOTHBALLING WITH CRUDE OIL
18
8. PROCEDURE FOR MOTHBALLING WITH PRODUCED GAS
21
9. MONITORING AND TESTING
21
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 2
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CP LIST
-
Table of Contents (Contd) Page 10. CHEMICAL INJECTION REQUIREMENTS
25
10.1 Batch Treatment 25 10.2 Continuous Injection
25
11. COMMISSIONING AND DISPOSAL
26
12. DELIVERY, STORAGE AND HANDLING 28 APPENDICES
A. Mothballing Chemicals & Dosage Rates for Crude Oil Lines 30 B. Mothballing Chemicals & Dosage Rates for Gas Lines 40 C. Mothballing Chemicals & Dosage Rates for Water Lines 50 D. List of Approved Chemicals and Disposal Category 54 E. List of Suitable Typical Cleaning Pigs 55 F. Maximum Flushing Time for Mothballing of Pipelines 56 G. Pipelines Nominal Size and Diameters 57 H. Pipeline Asset Mothballing Report 58 I. Corrosion Inhibitors Batch Size/KM Length for Various Pipeline Diameters 61 J. Referenced Codes & Standards
62
EXCLUSIVE ATTACHMENTS EA-1 Test Procedures for Identification of Chemicals Residual - Procedures for Tros
Chemicals 63
EA-2 Test Procedures for Identification of Chemicals Residual - Procedures for Petrolite Chemicals
79
EA-3 Test Procedures for Identification of Chemicals Residual - Procedures for Ceca Chemicals
84
EA-4 ADNOC Environmental Emissions Guidelines Limits 88 EA-5 Notification Scheme for the Selection of Chemicals for Use Offshore 90 EA-6 Approved Products Safety Data - Tros Chemicals 110 EA-7 Approved Products Safety Data - Petrolite Chemicals 152 EA-8 Approved Products Safety Data - Ceca Chemicals 181
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 3
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CP LIST
-
1. INTRODUCTION
1.1 Scope
This Code of Practice details the necessary requirements to ensure carbon steel pipelines are protected from internal corrosion under Mothball, or when Non-Operational conditions as defined below is intended for use by ADMA-OPCO only.
1.2 Coverage
1.2.1 This Code of Practice covers the requirements for corrosion and biological inhibition of crude oil, gas and sea water carbon steel pipelines.
1.2.2 This Code of Practice does not cover mothballing of vessels nor tanks. 1.2.3 This document covers the mothballing procedures using treated sea water, dry
oil or produced gas only. It does not cover purging and mothballing by inert gas.
1.2.4 This Code of Practice additionally covers the required corrosion and condition
monitoring for the relevant mothballed facility, chemicals storage and handling, specifications and list of suitable typical pigs for cleaning of pipelines.
1.3 Terminology
a. MOTHBALLING : Methodology for safe keeping of the pipeline to sustain
its integrity and condition for a defined period of time prior to re-entry into service
b. NON-OPERATIONAL : Not in operation c. PIGGABLE : Lines which can be cost effectively pigged irrespective
of whether or not permanent pigging facilities exist d. NON-PIGGABLE : Lines that cannot be pigged due to operational or cost
constraints e. NEW PIPELINES : Lines that are newly installed and not commissioned f. INSERVICE : Lines that have been operational but require to be PIPELINES mothballed or kept safely during non operation.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 4
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
1. INTRODUCTION (CONTD)
1.4 Referenced Documents
The latest editions of the Codes, Specifications and drawings listed in Appendix J shall
to the extent specified herein represent part of this Code of Practice. 2. GENERAL REQUIREMENTS
2.1 Pipelines shall be mothballed or made non-operational in accordance with the guidelines in this Section and to the specific procedures identified in the appropriate sections of this Code of Practice.
2.2 This document also outlines the required temporary plant and equipment including
gauging pigs, cleaning pigs, launchers/receivers, pumps, test instruments and fittings necessary for safe keeping of pipelines where it is deemed that pigging can be carried out cost effectively as part of this Code of Practice.
2.3 Where pressure testing and mothballing operations are combined, the specified
requirements of ADMA-OPCO Specification SP-1016 Part 2 are mandatory and must be adhered to.
2.4 The mothballing methodology should ensure that the plant can be re-commissioned in
the shortest possible time by considering the following:- 2.4.1 If any re-conditioning and/or replacement of equipment is necessary these
operations will be identical to the As Built design unless otherwise waived by the plant operating authority.
2.4.2 Removal of major items of equipment for storage offsite during the
mothballing period should be minimised in the interest of expedient operation and cost.
2.4.3 Re-commissioning of mothballed items shall be carried out by the normal site
maintenance and operations workforce wherever possible rather than by a specially mobilised construction team if at all possible.
2.5 Injection of treatment chemicals should be carried out using proper injection facilities
as described and detailed in ADMA-OPCO Drawing No. AD8-STD-M-0015-1. Any deviation must be endorsed by the appropriate technical authority prior to its implementation.
2.6 All chemicals should be added separately without dilution into the system through
separate injection systems.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 5
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
2. GENERAL REQUIREMENTSU (CONTD)
2.7 Safe disposal of chemicals as detailed in Section 11 of this document must be
observed before selection of the appropriate chemical treatment and/or disposal of a mothballing medium.
2.8 The recommended brands and dosage rates of the chemicals detailed in Appendices
A to C are based on the responded Chemical Suppliers recommendations. At the time of mothballing other appropriate chemical cocktails may be proposed if they prove more techno-economically cost effective and therefore should be employed provided the concentration/dosage rate are approved by the technical authority and in the case of open disposal meet the requirements of Section 11.
2.9 A pipeline with a tie-in connected to it can be considered piggable if any of the
following measures are satisfied. a. Tie-ins barred at all connection points. b. Subsea valving facilities exist at tie-in. c. Flow in non-barred tie-in is reversed. 2.10 A line may be considered clean or the minimum level of cleanliness achieved if the
quantity of removed deposit by the last hard brushed mechanical pig run is 10% of that removed during the previous run. This criteria is based on current experience and may be revalidated in light of future data collected
3. CRUDE OIL PIPELINES 3.1 New Crude Oil Pipelines 3.1.1 All new pipelines shall be assumed to be piggable. The practice of batch
dosing, using a train of a minimum of two batching pigs to establish a generally corrosion inhibitor film barrier of nominally 100 micron, will be adopted unless otherwise stated as a requirement. Chemical dosing/injection requirements are considered further in Section 10.
3.1.2 Safe keeping of new oil lines may be carried out using either dry crude or
treated sea water depending on the operational requirements. The relevant procedure as detailed hereafter should be followed.
3.1.3 All conditions and requirements noted in this section should be satisfied prior
to applying the relevant mothballing procedure.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 6
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
3.1 New Crude Oil Pipelines (Contd)
3.1.4 Tables A.1 and A.4 of Appendix A should be observed for the specified type
of chemicals and batch size as determined by the mothballing medium and period. In general, use of treated seawater can be considered to provide up to three years protection without replenishment, while dry crude oil for time frames greater than this. Actual mothballing medium shall be defined and justified together with the time scale in which the Asset will be mothballed (safe keeping period).
3.1.5 It is normally practicable to utilise the hydrotest fluid for mothballing if the
latter is operationally deemed necessary. 3.1.6 In view of Clause 3.1.5 above, the specified chemical type dosage and
treatment shall be dictated by the safe keeping period.
3.2 In-Service Piggable Crude Oil Pipelines 3.2.1 All conditions noted in this Section should be satisfied prior to adopting the
relevant mothballing procedure. 3.2.2 Irrespective of the number of cleaning runs needed to achieve the required
level of surface cleanliness prior to mothballing, one cleaning run using soft flexible wire bristle steel bodied brush pig should be carried out as the final run prior to mothballing.
3.2.3 The minimum complete cleaning cycle prior to mothballing should comprise of
a poly pig run, 2 hard brush steel bodied mechanical pig runs and soft flexible bristle brush steel bodied pig run.
3.2.4 A line can be considered adequately clean for the final soft bristle steel bodied
pig run if the quantity of removed deposit with the last hard brushed mechanical pig run does not exceed 10% of that removed during the previous run.
3.2.5 List of suitable/typical pig types are attached as Appendix E. 3.2.6 Irrespective of their intended duty, the selected pigs must be suitable to clean
the intended line taking into account the pipeline design such as number and radius of bends, length of pipeline, valving connections, tie-ins if existing, internal bore, size of available (if any) pig receiver and launcher, etc.
3.2.7 The recommended chemical dosage rates and type are as listed in Tables A.2 or
A.5 of Appendix A for the respective pipeline size, mothballing medium and period.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 7
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
3.3 In-Service Non-Piggable Crude Oil Pipelines
3.3.1 The use of high density hydrocarbon dissolvers composed of materials with
high surfactant properties for cleaning in service oil lines is not addressed fully in this Code of Practice. Therefore, potential use of chemical removal of hydrocarbons should be considered on a case by case basis. In general, these chemicals shall be considered in instances where mechanical pigging cannot be carried out and where presence of residual hydrocarbon on the pipewall is considered to hinder effective safe keeping of the pipeline in question. They may in certain instances precede mechanical pigging
3.3.2 All in-service oil lines particularly old ones are considered to contain
appreciable quantities of deposits. 3.3.3 All lines should be mothballed ideally with dry crude oil. Use of treated water
for mothballing is not recommended and may only be considered after sound justification to all concerned parties. Dry crude oil is defined as below limit of detection of conventional Basic Salt & Water (BS&W) determination. If wet crude oil is considered its water content should be known by actual measurement and chemical treatment modified accordingly.
3.3.4 It is recommended that a mixture of biocide and corrosion inhibitor is injected.
See Section 10. 3.3.5 The recommended types of chemical and dosage rates are listed in Table A.3 of
Appendix A for mothballing with crude oil.
3.3.6 Special attention must be given to the adequacy of the chemical inhibitor injection facilities for proper dispersion within the mothballing medium. Chemical injection arrangements should be subject to technical review prior to implementation.
3.3.7 Subject to individual review (Clause 3.3.1 above) the use of surfactants may be
required subject to compatibility (nature, polarity and non-interference properties) with the recommended corrosion prevention chemical to be injected for mothballing.
3.3.8 Long term pipeline safe keeping in excess of 12 months may prove detrimental
to the mothballed line integrity through localised corrosion attack. The particular procedure for monitoring in Section 9 should therefore be closely followed to address the line status.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 8
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
4. GAS PIPELINES
4.1 New Gas Pipelines For short period safe keeping of up to one month, either dehydrated dry produced
gas or wet gas slug dosed with corrosion inhibitor may be used as the medium instead of treated water to prevent unnecessary operational complications.
4.1.1 All conditions and requirement noted in this section should be satisfied prior to
applying the relevant mothballing procedure. 4.1.2 New gas lines shall be mothballed using treated water unless otherwise
specified by ADMA-OPCO. 4.1.3 It is normally practicable to employ the hydrotest fluid for mothballing. Safe
keeping duration of the pipeline should dictate the chemical treatment. 4.1.4 Tables B.1 and B.4 of Appendix B list the recommended chemical type,
dosage, batch size and concentration for the required mothballing period. See Section 10 for chemical injection requirements.
4.1.5 Mothballing with inert gas such as nitrogen under a positive pressure is not
covered by this Code of Practice. 4.2 In-Service Piggable Gas Pipelines 4.2.1 The requirements and conditions noted in Clauses 4.1.1 through 4.1.5 above
are applicable. 4.2.2 Tables B.2 and B.5 of Appendix B list the recommended chemical type dosage,
batch size and concentration for the required mothballing period. See Section 10 for chemical injection requirements. 4.2.3 All in-service lines should receive one cleaning cycle as detailed in Clauses
3.2.2 through 3.2.6 prior to commencement of safe keeping.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 9
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
4.3 In-Service Non-Piggable Gas Pipelines
4.3.1 In-service gas lines are assumed to contain adherent deposited iron sulphide
films. 4.3.2 Non-piggable gas pipelines are common within ADMA-OPCO onshore
processing and treatment facilities. In certain instances insufficient quantities of gas flow prevent proper corrosion inhibitor carry over to long distances. Safe keeping of these pipelines should be considered on a case by case basis.
4.3.3 In view of Clause 4.3.2 above proper dispersion of the injected corrosion
inhibitor by atomisation is deemed necessary in an attempt to achieve the maximum possible internal chemical protection at line end. Similarly it may be necessary to consider process fluid flow considerations in the safe keeping procedure.
4.3.4 The mothballing medium will in all cases be the produced gas slug dosed with
corrosion inhibitor at the dosage rates noted in the respective Sections of Table B.3 of Appendix B, unless hydrotesting of the pipeline is required as part of Scope of Work in which case treated sea water shall be used.
4.3.5 It must be noted that because of the non-piggable nature of these lines
adequate internal protection may not be achieved unless due consideration of flow velocities is made.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 10
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
5. WATER PIPELINES
5.1 New Water Pipelines 5.1.1 It is normal practice to utilise the hydrotest treated water medium for
mothballing should the latter be operationally required. 5.1.2 The mothballing medium in all cases will be treated water the treatment for
which will be dictated by the safe keeping period. 5.1.3 In conjunction with Clauses 5.1.1 & 5.1.2 above, the mothballing procedure
inhibitor dosage rate or batch size detailed in Subsection 6.1 and Table C.1 of Appendix C thereafter should be observed prior to hydrotesting.
5.1.4 Table C.1 of Appendix C lists the recommended inhibitor dosage rates or batch
size for the respective mothballing period and procedure. 5.1.5 For mothballing non-piggable new branched lines, the full portion including
the main line should be treated. 5.2 In-Service Piggable Water Pipelines 5.2.1 Conditions and requirements noted hereafter in this section must be satisfied
prior to commencement of the mothballing exercise. 5.2.2 In all cases the mothballing medium will be treated seawater. 5.2.3 Irrespective of the number of cleaning cycles/runs needed to achieve the
required level of surface cleanliness prior to mothballing, a minimum of one cleaning run using soft flexible steel bodied wire bristle brushes pig should be carried out as the final run prior to mothballing.
5.2.4 The minimum complete cleaning cycle should comprise of the following
sequential runs:- - One run using criss-cross poly pig. - One run using bi-directional steel bodied reversible mechanical pig with
hard brushes. - One run using reversible steel bodied mechanical pig with soft flexible wire
bristle brushes.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 11
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
5.2 In-Service Piggable Water Pipelines (Contd)
5.2.5 One complete cycle will be considered sufficient if the quantity of deposits
removed by the hard brushes mechanical pig is less than 30% of that removed by the poly pig.
5.2.6 List of selected typical pigs types is given in Appendix E. 5.2.7 Irrespective of their efficiencies, the selected pigs must be suitable to clean the
intended line taking into account the pipeline design such as number and radius of bends, valving connections, tie-ins if exist, internal bore, size of available (if any) pig receiver and launcher, etc.
5.2.8 The recommended dosage rate of chemicals and type are as listed in Table C.2
of Appendix C for the respective line size and mothballing period. 5.2.9 The required monitoring and testing procedure detailed in the respective
clauses of Section 9 must be observed. 5.3 In-Service Non-Piggable Water Pipelines 5.3.1 Non-piggable water injection lines include non-barred tie-ins with no subsea
valving facilities at the tie-in connection and lines on which installation of pigging facilities are operationally impracticable and/or cost prohibitive.
5.3.2 Unless operationally deemed otherwise, mothballing medium shall be by
treated sea water continuously slug dosed with a compatible blend of biocide, oxygen scavenger and corrosion inhibitor as recommended in Table C.3 of Appendix C.
5.3.3 The use of surfactants should be considered in instances where large quantities
of adherent debris are known to exist and should be selected based on nature and polarity so as not to interfere with the recommended corrosion prevention chemicals to be injected for mothballing.
5.3.4 Water soluble based chemicals only shall be used as the mothballing treatment. 5.3.5 Proper injection facilities must be provided for any supplemental additives to
inject in addition to the existing facilities for biocide and oxygen scavenger. See Section 10.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 12
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
5.3 In-Service Non-Piggable Water Pipelines (Contd)
5.3.6 Should it be deemed operationally necessary to inject aldehyde based biocides
and oxygen scavenger the latter must be injected at a minimum of 10 metres upstream of the biocide injection point and at optimum dosage rate to avoid adverse interference.
5.3.7 Long term mothballing in excess of 18 months may prove detrimental to the
line integrity. Results of condition monitoring and corrosion monitoring may therefore indicate the necessity for regeneration and/or renewal of the mothballing medium and hence should be closely observed in accordance with the requirements noted in Section 9 hereafter.
6. PROCEDURE FOR MOTHBALLING WITH TREATED WATER Whenever practicable, treated sea water taken from the Complex Sea Water Injection
System downstream of the vacuum tower should be employed to minimise additional chemical treatment.
6.1 Mothballing of Non-Piggable Pipelines & all Pipelines to be Safely kept for Upto
1 Month 6.1.1 This section covers all non-piggable lines and all lines to be safely kept for
periods up to 1 month. 6.1.2 Install injection point for appropriate chemicals and mobilise injection skid to
point of injection if no permanent operational injection facilities exist. 6.1.3 Test for correct injection pressure and dosage rate in accordance with the
required injection rate as noted in the respective Appendices A to C. 6.1.4 Isolate line to be mothballed from the remaining system. 6.1.5 Ensure that all flushing facilities such as flushing chokes etc. at line end
including those of tie-ins (if they exist) are open. 6.1.6 Commence injection of hydrotest/mothballing water and injection of
mothballing chemical(s). 6.1.7 Continuous injection at the chemical treatment dose rates listed in the
appropriate Tables of Appendices A to C should be employed taking into consideration the safe keeping period for the pipeline.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 13
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
6.1 Mothballing of Non-Piggable Pipelines & all Pipelines to be Safely kept for Upto
1 Month (Contd) 6.1.8 Injection of treated water and chemicals should be continued until the
recommended mothballing chemical concentration is detected at line end. As a general rule, the estimated quantity of treated water to be injected to achieve the required level of chemical concentration is approximately 120% of that required to fill the line.
6.1.9 Close flushing facilities and any fittings such as sampling points fitted on
facilities. 6.1.10 Supplemental corrosion and condition monitoring is not necessary for periods
upto 3 months. However, it is considered essential for periods in excess of 3 months.
6.2 Mothballing of Piggable Pipelines for Periods up to 6 Months 6.2.1 Clauses 6.2.1 to 6.2.22 covers all piggable water injection, oil and gas lines. 6.2.2 Ensure suitable permanent chemical injection facilities exist or temporary ones
are installed. 6.2.3 Test for correct injection pressure and rate in accordance with the required
injection rate as noted in the respective Appendices A to C. 6.2.4 Isolate line to be mothballed from the remaining system. 6.2.5 Ensure that all flushing facilities such as flushing chokes etc. at line end
including those of the tie-ins (if they exist) are open. 6.2.6 Launch and run a criss-cross poly cleaning pig with chemically treated raw sea
water (the respective chemicals and dosage rates are listed in Appendices A to C).
6.2.7 On receipt of polypig inspect for any possible geometrical damage and report
to Technical Authority. 6.2.8 If the polypig is damaged follow conditional alternative techniques for cleaning
as described in Clauses 6.2.18 to 6.2.22. 6.2.9 If received polypig was not mechanically damaged, launch and run any of the
selected hard brush mechanical pig (listed in Appendix E) using chemically treated raw sea water.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 14
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
6.2 Mothballing of Piggable Pipelines for Periods up to 6 Months (Contd)
6.2.10 Continuous injection at the slug dose rates listed in the appropriate Tables of
Appendices A, B or C should be employed. 6.2.11 For each run the quantities of arriving deposits with the pig should be
measured and recovered for scales and debris subsequent analysis as detailed in Section 9.
6.2.12 Once the measured quantity of debris and scales is less than 10% of that
removed during the last pig run, launch and run the soft bristle brush pig using 500 ppm chemically treated raw sea water as the mothballing medium. (Chemical treatment and dosage rates are as recommended in Appendices A to C).
6.2.13 Injection of treated water and chemicals should be continued until the
recommended mothballing chemical concentration is detected at line end. As a general rule, the estimated quantity of treated water to be injected to achieve the required level of chemical concentration is approximately 120% of that required to fill the line.
6.2.14 For water injection lines only, the operationally in use treated water for
injection is to be used for running of the cleaning pigs. 6.2.15 For water injection lines only and where it is operationally and economically
more feasible, the required treated water for mothballing shall be slug dosed at the respective water injection module/header. The in-use treatment chemicals may be employed for this purpose, dosages as advised by the Technical Authority.
6.2.16 At the end of works close flushing facilities and any other facilities such as
sampling points. 6.2.17 Apply the appropriate corrosion and condition monitoring as noted and
detailed in Section 9.
6.2.18 Conditional Alternative to Mechanical Cleaning (To be Verified with the Technical Authority)
a. Where mechanical cleaning is proven economically and/or operationally
not feasible, alternative approved chemical soaking techniques followed by vigorous flushing may replace the requirements noted in Clauses 6.2.6 through 6.2.12 depending on duty.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 15
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
6.2.18 Conditional Alternative to Mechanical Cleaning (To be Verified with the
Technical Authority) (Contd)
b. Soaking and flushing cycles should be continued until the quantity of removed debris/scales and deposits are less than 10% of that removed during the previous cycle.
c. Injection treated sea water shall be the medium for flushing. d. Treated sea water with the recommended chemical dosage rate as detailed
in the relevant Appendices shall be the mothballing medium. e. Apply Clauses 6.2.13 to 6.2.17.
6.3 Mothballing of Piggable Pipelines for Periods 6-18 Months 6.3.1 This section applies to all lines noted in Clause 6.2.1 above. 6.3.2 All conditions and requirements detailed in Subsection 6.2 above are
applicable, unless otherwise superseded hereunder. 6.3.3 The chemical dosage rate for the mothballing medium shall be as
recommended in the appropriate tables of Appendices A to C. 6.3.4 For mothballing of water injection lines, the optional conditional
deviations noted in Clause 6.2.18 are not recommended and all efforts should be exerted to include mechanical cleaning by pigging.
6.3.5 For mothballing of piggable crude oil and gas lines in excess of 12 months,
batch treatment between two pigs is recommended as the treatment technique in the following manner.
a. Launch and displace 1st batching pig by the chemical and diluent batch mix
(for batch size refer to the appropriate tables of Appendices A or B). b. Launch and run by treated sea water, the second pig. c. On receipt of the 2nd pig at receiver, isolate line including any sampling
facilities.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 16
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
6.4 Mothballing of Piggable Pipelines for Periods 18 Months - 5 Years
6.4.1 This procedure shall apply to all the lines noted in Clause 6.2.1 above. 6.4.2 All conditions and requirements detailed in Subsections 6.2 and 6.3 above are
applicable unless otherwise superseded hereunder. 6.4.3 For all lines, as dictated by monitoring practices (Section 9) or at a maximum
period of 3 years the mothballing medium shall be regenerated by vigorous flushing where applicable with the same mothballing fluid unless otherwise waived in the corrosion and condition monitoring report.
6.4.4 Where treated water is the mothballing medium, flushing may be carried out
with normal injection quality treated water. 6.4.5 The required testing and analysis as defined in Section 9 during flushing must
be observed closely. 6.4.6 Refill line with the same mothballing medium by observing the recommended
chemical dosage rates in the appropriate tables of Appendices A to C unless an alternative treatment and or chemical dosage rate is advised in the corrosion and condition monitoring report.
6.5 Mothballing of New Pipelines 6.5.1 This Section assumes that all new lines are piggable lines. 6.5.2 Isolate pipeline to be mothballed from remaining system. 6.5.3 Launch and displace 1st batching pig by the chemical and diluent batch mix
(for batch size refer to the appropriate tables of Appendices A to C). 6.5.4 Launch and run by treated sea water, the second pig. 6.5.5 On receipt of the 2nd pig at receiver, isolate line including any sampling
facilities.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 17
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
7. PROCEDURE FOR MOTHBALLING WITH CRUDE OIL
7.1 This procedure applies only to crude oil lines 7.2 Non-Piggable Oil Pipelines 7.2.1 Where possible dry crude is recommended to be the mothballing medium. 7.2.2 Check that proper chemical injection facilities exists. Mobilise temporary
injection skid if permanent facilities are not available. Injection point must be equipped with proper injection facilities as detailed in ADMA-OPCO Drawing No. AD8-STD-M-0015-1. Each treatment chemical should be added separately into the system.
7.2.3 For periods in excess of 1 month, mobilise test vessel at line end if back flow is
necessary to produce dry crude. 7.2.4 The relevant operating parameters such as well conditions, flow rates,
operating pressures, etc. will be defined by Production Operation as appropriate and should be recorded.
7.2.5 Flow crude through the line. 7.2.6 Monitor BS & W until 0% water cut is achieved. 7.2.7 Commence inhibitor chemical injection at the rate shown in the appropriate
Table of Appendix A. 7.2.8 Monitor corrosion inhibitor concentration at line end. If this proves impractical
continue flow until 120% of the quantity required to fill the line is injected. 7.2.9 When line is fully mothballed, depressurize line to a positive pressure of
maximum 50 psi. 7.2.10 For mothballing periods in excess of 1 month, the relevant monitoring and
testing procedures detailed in Section 9 shall be observed.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 18
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
7.2 Non-Piggable Oil Pipelines (Contd)
7.2.11 Depending on the recommendation to be made in the corrosion and condition
monitoring reports, mothballing medium replacement may be required for periods in excess of 12 months.
Note: For mothballing periods in excess of 6 months, the option of line chemical
cleaning prior to mothballing should be considered on a case by case basis as per Clause 6.2.18.
7.3 Piggable Crude Oil Pipelines 7.3.1 This Section covers Clauses 7.3.2 to 7.3.17 inclusive. For mothballing period of
less than 1 month, pigging and cleaning may not be cost effective and hence could be waived. The same procedure detailed in Subsection 7.2 above may therefore be applied for these periods of mothballing.
7.3.2 For mothballing periods in excess of 1 month the following clauses apply to
piggable crude oil pipeline. 7.3.3 If no permanent chemical injection facilities exist, mobilise temporary chemical
injection skid. 7.3.4 All efforts must be exerted to ensure presence of proper chemical injection
points with a suitable quill for adequate dispersion of the chemical. Each chemical shall be added separately into the system. Alternative chemical injection arrangements subject to Technical Authority approval.
7.3.5 For mothballing periods in excess of 6 months, if Clauses 7.3.3 and 7.3.4
cannot be satisfied, batching of chemicals between two batching pigs shall be the method to adopt for inhibition against corrosion followed by the inhibited fluids. Chemicals inhibition requirements for the batch and driver fluid are contained in Appendices A to C inc.
7.3.6 Launch and run a bi-directional criss-cross poly pig with treated crude oil, as
specified in Table A.1 of Appendix A. 7.3.7 On receipt of the criss-cross poly pig, inspect pig for any possible geometrical
damage.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 19
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
7.3 Piggable Crude Oil Pipelines (Contd)
7.3.8 If the pig indicates the presence of possible line geometrical irregularities report
to Technical Authority. 7.3.9 If the poly pig run indicates clear pig passage launch and run a hard brush
mechanical pig driven by chemically treated crude oil as defined in Appendices A to C.
7.3.10 On receipt of brush pig assess and record quantity of scale removed as defined
in Section 9. 7.3.11 If the quantity of scale is less than 30% of that removed by the poly pig, launch
soft bristle pig as in Clause 7.3.13. 7.3.12 If the quantity of removed scale is more than 30%, carry out another
mechanical pig run until the removed scale is less than 10% of that removed during the last mechanical pig run.
7.3.13 Launch and run a soft bristle brush pig driven by chemically treated crude oil.
Continue dosing with chemicals until the correct concentration is attained at line end. In general the pipeline should pass at least 120% of the theoretical volume to fill the line.
7.3.14 Isolate line and all sampling etc. facilities and maintain pipeline at a minimum
positive pressure of 50 psi. 7.3.15 The necessary corrosion and condition monitoring requirements as detailed in
Section 9 shall be observed.
7.3.16 Optional Clauses The following clauses replace Clauses 7.3.9 through 7.3.15 and may apply in
instance where geometrical damage has occurred and (Clause 7.3.7 above) where debris removal is deemed paramount.
a. Launch and run gel pigs (to be defined) until line is clean followed by the
appropriate batch chemical treatment between two gel pigs. (Refer to Appendix A).
b. On receipt of the second gel pig, isolate line and conduct the necessary
corrosion and condition monitoring as detailed in Section 9.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 20
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
8. PROCEDURE FOR MOTHBALLING WITH PRODUCED GAS
8.1 This procedure covers all non-piggable gas lines and all gas lines to be mothballed for
safe keeping. 8.2 If no suitable permanent injection facilities exist mobilise a suitable chemical injection
skid to point of injection, ensuring that proper chemical injection facilities with provision for corrosion inhibitor atomisation are made available. Chemical injection system is subject to technical authority approval.
8.3 Test for correct injection pressure and rate in accordance with the required dosage rate
noted in the appropriate Table of Appendix B. 8.4 Commence injection of gas treated with corrosion inhibitor as defined in Table B.3 of
Appendix B and Subsection 10.2. Inhibitor should be added for a period equivalent to displacing 3 pipeline volumes.
8.5 Isolate line to be mothballed for safe keeping from the system maintaining a minimum
pressure of 50 psi in the pipeline. 8.6 Corrosion and condition monitoring is mandatory for all mothballing periods and shall
be closely adhered to as defined in Section 9. 9. MONITORING AND TESTING 9.1 Mothballing with Treated Water for Periods 3 Months and Above 9.1.1 The time of arrival of the mothballing chemical slug should be calculated. 9.1.2 A minimum of three 500ml water samples at 30 minutes interval, shall be taken
starting at one hour prior to theoretical slug arrival for laboratory analysis (chemical concentration) and microbiological counts. Thereafter sampled at 2 minutes intervals and analysed for chemical residuals until the required mothballing chemical concentration level is reached. (Refer to Exclusive Attachments EA-1, EA-2 & EA-3).
Note:- Chemical Vendor should supply or validate residual chemical determination methods. An alternative but less accurate option to determine the level of chemical concentration will be by adding a known concentration of dye material and visually observe water colouration supported by colourometrical analysis using a spectrometer.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 21
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
9.1 Mothballing with Treated Water for Periods 3 Months and Above (Contd)
9.1.3 Close flushing choke and all other sampling points etc. and isolate line. 9.1.4 Renew any existing corrosion monitoring coupons at the end of the line to be
mothballed. If E/R probes exist do not replace. Continue to take readings as usual noting mothballing commencement date and chemical treatment utilised.
9.1.5 If a bioprobe exists renew at least one stud (preferably two). 9.1.6 Using the Rapid Check II kit, measure and record the sulphate reducing
bacteria activity on the removed stud(s). Dissolved oxygen determination utilising Chemets shall apply to water at inlet and outlet.
9.1.7 Pipeline isolation shall be carried out once water quantity greater than 115% of
pipeline volume has been passed in accordance with the following formulae:- t = (F D) 2 L) 1.15 = 5.271 x 10 3 (FD) 2 L V4 V Where t = Total time taken to fill the line and flush 15% of line volume
(min) D = External pipeline diameter (In) (e.g. 12 pipe = 12.75) L = Pipeline length (km) V = Volumetric flow rate (bbls/day) F = Correction factor for scaling A 10% nominal reduction in pipeline diameter due to scaling is assumed for up
to 10 diameter pipelines and 5% for larger diameter radials. Appendix F lists the estimated times in min/km for line sizes 6 - 24 at various
flow rates. Also for ease of reference Appendix G lists the nominal pipelines OD sizes.
9.1.8 As appropriate Monitor corrosion rate using weight loss corrosion coupons
and or electrical resistance probes. The latter may be equipped with continuous data logging unit.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 22
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
9.1 Mothballing with Treated Water for Periods 3 Months and Above (Contd) 9.1.9 Prepare at least annually corrosion control and condition monitoring report to
include but not be limited to the following details:- a. Pipeline data such as material, pipe dia, route, wall thickness, length. b. Full history of the line. This may be available from other previously
prepared reports on the same line. c. Details of adopted mothballing procedure including intended period, type
of medium, type of treatment chemicals and dosage rate, date of commencement, recommended date for discharge or if necessary replacement of mothballing medium, injection flow rates, pressure and temperature.
d. Details of implemented pigging operation including type of pigs and
brands, number of runs, type and brand of pigging launcher and receiver. e. If pigging operations are carried out, full details of scales and debris
removed including type of scales, weight of scales removed per run, sampling procedures (as defined in the appropriate monitoring and testing clauses), chemical analysis of scales, total weight of scales and debris removed. Time and date of all activities must be recorded.
f. If previous mothballing or pigging operation were carried out on the same
line, the report shall refer to all such activities under separate clause defined as history profile illustrating graphically a comparison chart of nature of scales removed, weight of removed scales, type and number of pigging runs and measured corrosion and condition monitoring data. This will be used as a fine tune guide for future pigging and mothballing operations.
g. Utilised corrosion and condition monitoring methods, their respective
locations, frequency of monitoring, measured corrosion rates and wall thickness and interpretation of recorded data.
h. Tables of all chemical analysis carried out during and after the mothballing
operation including sampling points identification, time and intervals of samples recovery, volume of each sample.
i. Details of any deviation from the specified requirements for mothballing or
testing procedures as defined in this document. The report shall incorporate the justifications for such deviations.
A typical report form is attached as Appendix H.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 23
TO CONTENTS
-
9.2 Mothballing with Crude Oil/Gas Medium
9.2.1 The time of arrival of the mothballing chemical slug should be calculated using
the formulae of Clause 9.1.7. 9.2.2 A minimum of three 500ml liquid samples at 30 minutes intervals, shall be
taken starting at one hour prior to theoretical slug arrival for laboratory analysis (chemical concentration). Thereafter sampled at 2 minutes intervals and analysed for chemical residuals until the required mothballing chemical concentration level is reached. (Refer to Exclusive Attachments EA-1, EA-2 & EA-3) validated by the chemical vendor.
9.2.3 Close connected valves and all other sampling points etc. and isolate line,
maintaining a minimum pressure of 50 psi in the pipeline. 9.2.4 Renew any existing corrosion monitoring coupons at the end of the line to be
mothballed. If E/R probes exist do not replace. Continue to take readings as usual noting mothballing commencement date and chemical treatment utilised.
Appendix F lists the estimated times in min/km for line sizes 6" - 24" at various
flow rates. Also for ease of reference Appendix G lists the nominal pipelines OD sizes.
9.2.5 As appropriate monitor corrosion rate using weight loss corrosion coupons and
or electrical resistance probes. The latter may be equipped with continuous data logging unit.
9.2.6 Prepare corrosion control and condition monitoring report in line with the
applicable requirements noted in Clause 9.1.9.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 24
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
10. CHEMICAL INJECTION REQUIREMENTS
10.1 Batch Treatment 10.1.1 This section details the requirement to batch chemical treat facilities. 10.1.2 The recommended type of treatment chemicals and approved commercial
brands are tabulated in the relevant tables of Appendices A to C for the respective line duty. Refer to Appendix I for sizing of batch treatment.
10.1.3 All calculated batch sizes were based on neat chemical quantities required to
treat 1 km pipelength with 100 microns thick inhibitor film. The batch sizes also include allowance of 8% for pig and 15% for sphere slipage. Note that for certain products of Appendix B greater thicknesses are specified.
10.1.4 To maximise surface wetting hence efficiency of chemical distribution and
surface coverage, the treatment chemical should always be batched in the form of a 50:50 mix in a suitable diluent. For each recommended chemical type, the respective compatible diluent is recommended by the chemical supplier.
10.1.5 It should be ensured that batch treatment is preferably carried out between a
minimum of two swabbing/batching pigs or alternatively two spheres. 10.1.6 For in service oil and gas lines, batch inhibition must be preceded by
dewatering and desludging of the line to provide maximum surface exposure for treatment.
10.1.7 For used water injection lines, treatment is covered by increasing continuous
addition rates as defined in Subsection 10.2 hereunder. 10.2 Continuous Injection 10.2.1 This section covers the required chemical treatment referred to as continuous
injection in the relevant sections of this document. 10.2.2 The recommended dosage rates for continuous injection are tabulated in the
appropriate Appendices A to C for the respective line duty. 10.2.3 Recommended dosage rates shall be adhered to at all times.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 25
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
10.2 Continuous Injection (Contd)
10.2.4 Where injection of the mothballing medium is carried out from a service
vessel, the required mothballing chemical dosage rate shall be calculated as a slug dose and properly mixed with the mothballing medium prior to injection into the line.
Example: To mothball a 1km long pipeline of 10 dia. With a recommended
treatment chemical dosage rate of 500 ppm, the required slug dose = (9.874)2 x 103 x 500 x 1.15 4 x 1550 106 = 28.4 litre say 30 litres 10.2.5 For mothballing water injection lines, slug dosing from the respective water
injection module shall be used including a 20% excess for possible wastage and/or filming out of chemicals as they transport through the pipeline.
Note:- If oxygen scavenger is to be injected separately, the method of injection should
be approved by the technical authority. 11. COMMISSIONING AND DISPOSAL 11.1 This section covers the requirements preceding mothballing for the application of the
necessary corrosion control measures and safe disposal of the mothballing medium. 11.2 Disposal of the mothballing medium (usually water) shall be carried out in accordance
with the applicable safety and environmental control codes and practices (Refer also to Appendix D). Specifically the disposal consents noted in exclusive attachments should be strictly adhered to. Any hydrotest or mothballing chemicals considered outwith this document should be notifiable and disposed of in accordance with UK Dept. of Trade & Industry - safe dopen disposal of offshore chemicals and conform to ADNOC Environmental Guideline limit values, refer to EA-4 & EA-5.
11.3 In general, it is recommended at all times that where permissible the mothballing
medium, irrespective of its nature, is displaced with a dewatering pig or a sphere prior to commissioning/demothballing.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 26
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
11.4 Oil and Gas Pipelines
11.4.1 Where the mothballing medium is treated water, it should be displaced by a
train consisting of swabbing pig with a minimum of 4 seal cups followed by an appropriately sized batch of corrosion inhibitor and batching pig. The train to be driven by the normally treated production stream. Requirements of Subsection 11.2 shall apply.
11.4.2 Where oil or gas is the mothballing medium it shall be displaced using the
production stream treated continuously at 3 times the rate of the normally injected continuous dosage rate for 24 hours, unless otherwise advised by the technical authority.
11.4.3 The required data noted in Subsections H.8 through H.10 of Appendix H
(mothballing report) shall be observed and recorded. 11.5 Water Injection Lines 11.5.1 Water injection lines shall be demothballed in accordance with the following:- Displace the mothballing medium with injection quality water. Under normal
conditions no special chemical treatment regime is required for this process. 11.5.2 Observe and record the required data noted in Subsections H.8 through H.10 in
Appendix H (mothballing report).
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 27
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
12. DELIVERY, STORAGE AND HANDLING
12.1 Delivery The supplied chemicals and diluents if appropriate, shall be supplied in ADMA-OPCO
approved tanks. These Chemicals shall be packaged and labelled in accordance with ADMA-OPCO
Specification SP-1004. Each tank shall be clearly marked with the following:- a. Product Name and Reference; b. Suppliers Name; c. Suppliers Address; d. Suppliers Telephone, Facsimile and Telex Numbers; e. Material Flash Point; f. Hazchem Labels as required by UAE Legislation. 12.2 Documentation for Storage and Handling The Vendor supplied chemicals and diluents shall be accompanied by but not be
limited to the following documents. a. Product Name and Reference; b. Batch Number and Volume; c. Specific Gravity; d. Flash Point; e. Date of Manufacture; f. Date of Despatch; g. Copy of Certificate of Approval for the Tank, Supplied by an Approved Certifying
Authority; h. Viscosity Range over the Temperature Range 0C-70C; i. Requirements for Personnel Protection during Handling; j. First Aid in the Event of Accidental Skin or Eye Contact, or Ingestion; k. Methods of Firefighting; l. Methods of Safely Dealing with Spillages; m. Permitted Concentrations for Discharge to the Sea as Categorised by the UK
Department of Trade and Industry; n. Detailed Safety Data Sheet of the Supplied Chemical(s); o. Step by Step Procedure for Safe Handling and Storage of the Supplied
Chemical(s); p. Completed ADMA-OPCO HSEP Data Sheet.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 28
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
12.3 Compliance
a. In addition to satisfying the requirements detailed in Subsections 12.1 and 12.2
above, the Vendor shall also comply with the accompanied commercial conditions and requirements as stated on the purchase order.
b. In addition to satisfying the requirements detailed in Subsections 12.1 and 12.2
above, all concerned parties involved in delivery, handling and storage of the supplied chemicals shall observe ADMA-OPCO General Safety Procedures and Regulations for safe handling and storage of chemicals.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 29
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
APPENDIX A
MOTHBALLING CHEMICALS & DOSAGE RATES
FOR CRUDE OIL LINES
TABLE A.1 - DRY OIL MEDIUM - NEW LINES TABLE A.2 - DRY OIL MEDIUM - PIGGABLE LINES TABLE A.3 - DRY OIL MEDIUM - NON-PIGGABLE LINES TABLE A.4 - WATER MEDIUM - NEW LINES TABLE A.5 - WATER MEDIUM - PIGGABLE LINES TABLE A.6 - WATER MEDIUM - NON-PIGGABLE LINES
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 30
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
APPENDIX B
MOTHBA LLING CHEMICALS & DOSAGE RATES
FOR GAS LINES TABLE B.1 - PRODUCED GAS MEDIUM - NEW LINES TABLE B.2 - PRODUCED GAS MEDIUM - PIGGABLE LINES TABLE B.3 - PRODUCED GAS MEDIUM - NON-PIGGABLE LINES TABLE B.4 - WATER MEDIUM - NEW LINES TABLE B.5 - WATER MEDIUM - PIGGABLE LINES TABLE B.6 - WATER MEDIUM - NON-PIGGABLE LINES
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 40
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
APPENDIX C
MOTHBALLING CHEMICALS & DOSAGE RATES
FOR WATER LINES TABLE C.1 - WATER MEDIUM NEW LINES TABLE C.2 - WATER MEDIUM PIGGABLE LINES TABLE C.3 - WATER MEDIUM NON-PIGGABLE LINES
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 50
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
APPENDIX D
LIST OF APPROVED CHEMICALS AND OPEN DISPOSAL CATEGORY
CHEMICAL
NAME
GENERIC
DESCRIPTION
DISPOSAL
CATEGORY
TROS TC 1000 AMMONIUM BISULPHITE OXYGEN SCAVENGER CATEGORY 0
TROS TH 7062A IMIDAZOLINE BASED CORROSION INHIBITOR CATEGORY 2*
TROS TK 460A QUAT. AMINE BASED BIOCIDE/C.INHIBITOR CATEGORY 2*
TROS TK 3406 AMINE/PHOSPHONIUM QUAT BASED BIOCIDE CATEGORY 2*
TROS TK 455 QUAT AMINE/ALDEHYDE BASED BIOCIDE CATEGORY 2*
TROS 650 QUAT AMINE/AMONIUM BISULPHITE BASED
HYDROTEST CHEMICAL
CATEGORY 2
TROS TH 804 POLY ACRYLATE BASED SCALE INHIBITOR CATEGORY 1
TROS CT 3707 IMIDAZOLINE/AMINE BASED CORROSION
INHIBITOR
CATEGORY 2*
TROS C77 MIXED AMINE BASED CORROSION INHIBITOR CATEGORY 1
PETROLITE XC-2809 DIAMINE ACETATE/QUATERNARY BLEND BIOCIDE 3*
PETROLITE KW-2140 QUARTERNARY AMINE CORR. INHIBITOR 3*
PETROLITE WF-2020 DIAMINE ACETATE/AMONIUM BISULPHITE
PYRIDINE QUATERNARY COCKTAIL
3*
PETROLITE KP-2414 IMADAZOLINE CORROSION INHIBITOR 3*
PETROLITE PD-11 COMBINATION OF OXYALKYLATED PHENOL
FORMALDEHYDE RESINS IN HEAVY AROMATIC
NAPTHA
3*
PETROLITE K-490 AMMONIUM BISULPHITE OXYGEN SCAVENGER 1
CECA NO RUST PA 23D FATTY AMINE DERVATIVE CORROSION INHIBITOR N/A
CECA NO RUST 420M FATTY AMINE DERVATIVE CORROSION INHIBITOR 2
CECA NO RUST SC43 AMMONIUM BISULPHITE OXYGEN SCAVENGER 2
CECA NO RUST IG 91C AMIN IN ALCOHOLIC SOLUTION CORR. INHIBITOR N/A
* Anticipated classifications based on similar known classified products. Disposal categories are as defined by the UK Department of Trade & Industry and ADNOC Guidelines (refer
to EA-4 & EA-5). This Appendix should be read in conjunction with Section 11 of this Code of Practice.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 54
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
APPENDIX E
LIST OF SUITABLE TYPICAL CLEANING PIGS
MANUFACTURER SUPPLIER PIG TYPE
POLY PIG
HARD WIRE BRUSH/PAD
MECHANICAL PIG
SOFT BRISTLE BRUSH
PIG
KNAPP
CRISSCROSS
BA3 BRD3 STIFF WIRE
BA3 BRD3 LONG THIN WIRE
PIPELINE ENGINEERING
PE WIRE BRUSH
PESP1 SCRAPER FOR WATER LINES. PEUG 1 OR 2 FOR OIL & GAS
SLCS-6 (WITH TWIN CLIP HIGH GRADE S.STEEL BRISTLES
PIPETRONIX
CIRCULAR WIRE BRUSH LT TYPE
M.H. MALONEY
(FOR OIL & GAS ONLY) B1-D1 SL CLEANING OR B1-D1 FLEX MAG
PERRY EQUIPMENT
B5 FOR OIL & GAS C5 FOR WATER
PSRF
KOPP
CIRCULAR WIRE BRUSH LIT TYPE
INTL. PIPELINE
PRODUCTS (INPIPE)
LONG RUN
IPRCN (UPTO 18) OR IPUG 1 OR 2 (FOR OIL & GAS ONLY)
OTHER POTENTIAL PIG SUPPLIERS WHO MAY BE APPROACHED ARE:-
T.D. WILLIAMSON ENDURO PIPELINE NOTE:- 1. POLY PIGS SHOULD IN GENERAL INCLUDE WIRE BRUSHES. 2. ACTUAL PIGS UTILISED SHOULD BE SUBJECT TO APPROVAL OF TECH55NICAL
AUTHORITY.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 55
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
APPENDIX F
MAXIMUM FLUSHING TIME
FOR MOTHBALLING OF PIPELINES
Maximum times required to flush pipelines with treated water for mothballing. Times are in minutes per km length of pipeline.
TIMES TO FLUSH PIPELINE PER KM LENGTH (MINUTES)
FLOWRATE NOMINAL PIPELINE DIAMETER (INCH)
(MBWPD) 6 8 10 12 14 24
5 28 50 79 113 155 482
7.5 19 33 53 75 103 322
10 14 25 40 57 77 241
12.5 11 20 32 45 62 193
15 9 17 26 38 52 161
17.5 8 14 23 32 44 138
20 7 12 20 28 39 121
25 6 10 16 23 31 96
30 5 8 13 19 26 80
35 4 7 11 16 22 69
40 4 6 10 14 19 60
45 3 6 9 13 17 54
50 3 5 8 11 15 48
60 2 4 7 9 13 40
70 2 4 6 8 11 34
80 2 3 5 7 10 30
90 2 3 4 6 9 27
Scale Factor: 10% for pipelines with diameters below 14-inch and 5% for 14-inch and above.
To obtain the flushing time required multiply the above times by the length of the pipeline in kilometers. For example for a 5.2 km pipeline of 12-inch diameter for a flow rate of 20,000 barrels of water per day the flushing time is 5.2 x 28 = 146 minutes.
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 56
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
APPENDIX G
PIPELINES NOMINAL SIZE AND DIAMETERS
NOM. SIZE
(IN)
O.D. (IN)
W.T. (IN)
I.D. (IN)
24 24 0.625 22.75
14 14 0.75 12.5
12 12.75 0.562 11.626
10 10.75 0.465 9.82
8 8.625 0.322 7.981
6 6.625 0.28 6.065
4 4.5 0.237 4.026
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 57
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
APPENDIX H
PIPELINE ASSET MOTHBALLING REPORT
H.1 LOCATION & IDENTIFICATION 1. Pipeline Win No. : 2. Field : 3. Line Name : 4. Route : H.2 SPECIFICATION DATA 5. Size : 6. Length : 7. Grade : 8. Wall Thickness : H.3 OPERATIONAL HISTORY 9. Date of Installation : 10. Date of Commissioning : 11. Hydrotest Fluid : 12. Hydrotest Chemical : 13. Duty : 14. Pressure & Temp. : H.4 STREAM NATURE/OPERATING CONDITIONS 15. Oil, Gas or Water : 16. Sour ? : Yes ( ) No ( ) 17. Wet ? : Yes ( ) No ( ) 18. H2S Level : MOL % ( ) N/A ( ) 19. Water Cut : % ( ) N/A ( ) 20. CO2 Level : MOL % ( ) N/A ( ) 21. Operating Pressure : 22. Operating Temp. : H.5 MOTHBALLING & PIGGING PROFILE 23. Is Line Previously Mothballed : Yes ( ) No ( ) 24. Medium : 25. Chemicals : 26. Concentration :
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 58
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
Sheet: 1 of 3
TO CONTENTS
-
APPENDIX H
PIPELINE ASSET MOTHBALLING REPORT
27. Duration & Date of Initial : Mothballing 28. Chemical Analysis Carried : Out (Attach if yes) 29. Has Line been Pigged or Flushed : Pigged ( ) Flushed ( ) No ( ) prior to Mothballing 30. No. of Pigging Cycles : 31. No. of Runs per Cycle : 32. Type of Pigs Used : 33. No. of Pigs Used per Cycle : 34. Measured Corrosion Rates : 35. If Flushed or Pigged State Quantity of Debris Recovered per run and nature of
debris as follows:- Cycle/Run No. Quantity & *Nature Date/Time Note: *Attach Chemical Analysis 36. Type of Corr. Monitoring : 37. No. of Points : 38. Location : H.6 MOTHBALLING PROCEDURE LOG 39. Mothballing Period & : Starting Date 40. Medium : 41. Is Line Piggable : 42. Pre-Mothballing Cleaning : ( ) Flushing ( ) Pigging If Flushing: 43. Recorded Quantity of Flushing : Water 44. Quantity of Removed Debris : 45. No. of Flushing Cycles : If Pigging: 46. No. of Runs : 47. Type of Pigs :
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 59
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
Sheet: 2 of 3
TO CONTENTS
-
APPENDIX H
PIPELINE ASSET MOTHBALLING REPORT
48. Quantity of Debris/Scales : Recorded per Run/*Nature Run No. Type of Pig Qty & * Nature Date/Time Note: *Attach Chemical Analysis Mothballing Chemicals 49. Type of Chemicals : 50. Mode of Injection - ( ) Continuous ( ) Batch ( ) Both 51. Dosage Rate/Batch Size : 52. Date/Time of Injection : 53. Sampling Point Location : 54. Sampling Intervals, : Date & Time of 1st Sample Sampling Period Inhibitor Residual Level Flow Rate H.7 CORROSION & CONDITION MONITORING DURING MOTHBALLING 55. Recorded Temp. & Pressure : 56. Corrosion Monitoring Data: Date Corr. Rate Bacterial Counts Device Type Water Chemistry
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 60
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
Sheet: 3 of 3
TO CONTENTS
-
APPENDIX I
CORROSION INHIBITORS BATCH SIZE/KM LENGTH
FOR VARIOUS PIPELINE DIAMETERS
Based on 100 MICRONS (0.004") Film Thickness of Inhibitor in 50:50 mix with Diluent Batch Size = P1 () DLT where; D - Pipeline Diameter, L = 1 Km Length, T = Inhibitor Film Thickness
PIPELINE DIA. BATCH SIZE/1 KM 6 12.9 8 17.1 10 21.4 12 25.7 14 30.0 16 34.3 18 38.6 20 42.8 22 47.1 24 51.4 26 55.7 28 60.0 30 64.3 32 68.5 34 72.8 36 77.1 38 81.4 40 85.7 42 90.0 44 94.2 46 98.5 48 102.8 52 11.14
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 61
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
APPENDIX J
REFERENCED CODES & STANDARDS
The latest editions of the Codes, Specifications and drawings listed below shall to the extent specified herein represent part of this Code of Practice. DTI UK Department of Trade and Industry classification for
chemicals safe disposal - Offshore Chemical Notification Scheme
ADMA-OPCO SP-1004 Specification for Packaging & Labelling of Dangerous
Substances SP-1016 Part 2 Specification for Hydrostatic Testing of Subsea Pipelines Drawing No. AD8-STD-M-0015-1 Chemical Injection Point Valve Support G.A and Details.
ADMA-OPCO Safety Regulations
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 62
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
EA - 1
TEST PROCEDURES FOR IDENTIFICATION OF
CHEMICALS RESIDUAL
PROCEDURES FOR TROS CHEMICALS
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 63
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
EA - 2
TEST PROCEDURES FOR IDENTIFICATION OF
CHEMICALS RESIDUAL
PROCEDURES FOR PETROLITE CHEMICALS
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 79
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
EA - 3
TEST PROCEDURES FOR IDENTIFICATION OF
CHEMICALS RESIDUAL
PROCEDURES FOR CECA CHEMICALS
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 84
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
EA - 4
ADNOC ENVIRONMENTAL EMISSION GUIDELINES LIMITS
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 88
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
EA - 5
NOTIFICATION SCHEME FOR THE SELECTION
OF CHEMICALS FOR USE OFFSHORE
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 90
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
EA - 6
APPROVED PRODUCTS SAFETY DATA
TROS CHEMICALS
PRODUCT TITLE
Troskil 1 Biocide
Tro TK-460 Biocide
Troskil 3406 Biocide
Tros C 70 Corrosion Inhibitor
Tros TH-7062 A Corrosion Inhibitor
Tros TC 1000 Oxygen Scavenger
Tros Sea Dye
Tros 650 Combination Hydrotest Product
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 110
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
EA - 7
APPROVED PRODUCTS SAFETY DATA
PETROLITE CHEMICALS
PRODUCT TITLE
KW 2140 Corrosion Inhibitor
K 490 Oxygen Scavenger
WF 2020 Hydrostatic Test Chemical
KP 2414 Corrosion Inhibitor
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 152
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
EA - 8
APPROVED PRODUCTS SAFETY DATA
CECA CHEMICALS
PRODUCT TITLE
Norust IG 91 C Corrosion Inhibitor
Norust PA 23 D Corrosion Inhibitor
Norust 420 M Corrosion Inhibitor
0 Oct-96 Issued for Implementation
Rev. Date Description / Text Affected
ADMA-OPCO CP - 109 PAGE 181
Standard Form QAD/04/124 Rev. 0 Sheet 1 of 1
TO CONTENTS
-
CP_109 rev 0.pdfFront SheetTable of Contents1-Introduction2-General Requirements3-Crude Oil Pipelines4-Gas Pipelines5-Water Pipelines6-Procedure for Mothballing with treated water7-Procedure for Mothballing with crude oil8-Procedure for Mothballing with produced gas9-Monitoring & Testing10-Chemical Injection Requirements11-Commissioning & Disposal12-Delivery, Storage & HandlingAppendicesAppendix AAppendix BAppendix CAppendix DAppendix EAppendix FAppendix GAppendix HAppendix IAppendix J
AttachmentsEA-IEA-2EA-3EA-4EA-5EA-6EA-7EA-8