Cours File-Industrial Management(2)

download Cours File-Industrial Management(2)

of 157

Transcript of Cours File-Industrial Management(2)

  • 8/2/2019 Cours File-Industrial Management(2)

    1/157

    INDUSTRIAL MANAGEMENT

    EHU-601

    Course File

    1

  • 8/2/2019 Cours File-Industrial Management(2)

    2/157

    UNIT-I

    Introduction : Concept, Development, application and scope of Industrial Management.

    Productivity : Definition, measurement, productivity index, types of production system, Industrial

    Ownership.

    MANAGEMENT

    Traditional Author says that management is an art of getting things done through people where as modern

    authors says that management is a process of accomplishing certain objectives through the utilization of human

    and other resource.

    IMPORTANCE OF MANAGEMENT

    For the accomplishment of the goals.

    For effective utilization of the resources.

    Sound Organization.

    Providing vision &Foresight.

    For the harmony in work.

    To help employees in achieving personal objective.

    Development of the society and nation.

    2

  • 8/2/2019 Cours File-Industrial Management(2)

    3/157

    INDUSTRIAL MANGEMENT

    Industrial management is now a branch of engineering which facilitates creation of management system

    and integrates same with people and their activities to utilize the resources.

    Industrial management is structured approach to manage the operational activities of the organization.

    SCOPE OF INDUSTRIAL MANGEMENT

    1. Related to Designing of the production system.(see notes)

    2. Relating to analysis & control of production operation.(see notes)

    APPLICATION OF THE INDUSTRIAL MANGEMNT

    1. Planning Function

    For Designing Conversion System

    For Scheduling Conversion System

    2. Organizing Function

    Organizing for conversion

    Structuring of Operation Staffing

    Job & Work Design.

    For Production & Operation Standard.

    3

  • 8/2/2019 Cours File-Industrial Management(2)

    4/157

  • 8/2/2019 Cours File-Industrial Management(2)

    5/157

    Performance Achieved (Effectiveness)

    PRODUCTIVITY INDEX=

    Input Resources Consumed (Efficiency)

    Efficiency is the ratio of actual output attained to the standard expected output. It measures of

    how well the resources are utilized to accomplish the target or result.

    Effectiveness is the degree of accomplishing the objectives

    Production System

    The production system can be viewed as a framework or skeleton of activities within which the creation

    of value can occur.

    The difference between the value of input and the value of output represent the value created through

    production activities.

    At the one end of the production system are the input and at the other end are output.

    Connecting the input and output are a series of operations or processes, storage and inspections represent

    the simplified production system.

    Figure : PRODUCTION SYSTEM

    Input Receiving Reports

    5

  • 8/2/2019 Cours File-Industrial Management(2)

    6/157

    Row material Inventory Reports

    Operation - 1 Schedules

    Production Manager

    Operation 2 Route Sheets

    Production Reports

    Operation 3 Time and Cost Record

    Final inspection Inspection Reports

    Finished goods storage Inventory Reports

    Output Shipping Orders

    INPUT OUTPUT MODEL (ANALYSIS OF PRODUCTION SYSTEM)

    It is one of the basic models of the production system.

    Production system is the set of interconnected input output element.

    It is made up of three component parts namely Input, Output and Process.

    A wide variety of inputs are transformed so that they give out a set of output.

    The transforming process can be complicated and the design of an actual input and output system for

    manufacturing may be expensive and difficult.

    6

  • 8/2/2019 Cours File-Industrial Management(2)

    7/157

    Purpose to Increase Productivity

    FOR MANAGEMENT

    To produce good earning (profit).

    To clear the debt or loans acquired from different sources.

    To sell more.

    To stand better in the market.

    FOR WORKERS

    HIGHER WAGES.

    Better Working Conditions.

    7

    MATERIAL

    MEN

    ENERGY

    PLANT &

    FACILITIES

    GOODES &

    SERVICES

    INPUTOUTPUT

    PRODUTION

    PROCESS

  • 8/2/2019 Cours File-Industrial Management(2)

    8/157

    Higher standard of living.

    Job Security and Satisfaction

    FOR CUSTOMER

    To reduced price of the article.

    Sole Proprietorship

    Sole Proprietorship is that form of Industrial ownership in which Individual Exercise & enjoy all rights related

    to business in his own interest.

    Merits

    Easy Formation

    Easy to Operate

    Secrecy

    Simplicity

    Demerits

    Limited Resources

    Lack of Continuity

    Unlimited Liability

    8

  • 8/2/2019 Cours File-Industrial Management(2)

    9/157

    Limited Managerial Ability

    Partnership

    Partnership may be defined as the relation between person who has agreed to share the profits of a business

    carried on by all or any of them acting for all.

    Merits

    Legal Entity

    Risk Sharing

    More Funds

    Continuity

    Mutual Agency

    Demerits

    Unlimited Liability

    Limited Resources

    Possibility Of Conflict

    Lack of Public Interest

    Joint Stock Company

    A joint stock Company means an association of several people who contributed money or moneys worth to a

    joint or common stock & employ it in same business & share among themselves the profit or loss arising from

    it.

    Merits

    Limited Liability

    Transfer of Interest

    9

  • 8/2/2019 Cours File-Industrial Management(2)

    10/157

    Perpetual Existence

    Scope for Management

    Professional Management

    Demerits

    Complexity in Formation

    Lack of Secrecy

    Impersonal Work Environment

    Numerous Regulation

    Delay In Decision Making

    Co Operative Undertaking

    The Co Operative society is voluntary association of person, who join together with the motive of welfare of

    the members and society.

    Merits

    Limited liability

    Economy in Operation

    Support From Government

    Stable Existence

    Ease of Formation

    Demerits

    Limited Resources

    Inefficiency in Management

    Lack Of Secrecy

    10

  • 8/2/2019 Cours File-Industrial Management(2)

    11/157

    Government Control

    Difference Of Opinion

    UNIT-II

    Management Function : Principles of Management- Management Tools time and motion study, worksimplification- process charts and flow diagrams, Production Planning, Specification of Production

    requirements.

    Management Function: Management

    Management is generic. Management principles are general rather than specific to a type of firm or

    organization. However, management is universal only if the manager has become familiar with the specificsituation in which it is applied. Production technology, customer characteristics and the culture of the industry

    are examples of specifics that managers need to learn to be effective in applying their generic management

    skills.

    11

  • 8/2/2019 Cours File-Industrial Management(2)

    12/157

    Management is creative problem solving. This creative problem solving is accomplished through four

    functions of management: planning, organizing, leading and controlling. The intended result is the use of

    an organization's resources in a way that accomplishes its mission and objectives.

    Planning is the ongoing process of developing the business' mission and objectives and determining

    how they will be accomplished. Planning includes both the broadest view of the organization, e.g., itsmission, and the narrowest, e.g., a tactic for accomplishing a specific goal.

    Organizing is establishing the internal organizational structure of the organization. The focus is on

    division, coordination, and control of tasks and the flow of information within the organization. It is in

    this function that managers distribute authority to job holders.

    Staffing is filling and keeping filled with qualified people all positions in the business. Recruiting,

    hiring, training, evaluating and compensating are the specific activities included in the function. In the

    family business, staffing includes all paid and unpaid positions held by family members including the

    owner/operators.

    Directing is influencing people's behavior through motivation, communication, group dynamics,

    leadership and discipline. The purpose of directing is to channel the behavior of all personnel to

    accomplish the organization's mission and objectives while simultaneously helping them accomplish

    their own career objectives.

    Controllingis a four-step process of establishing performance standards based on the firm's objectives,

    measuring and reporting actual performance, comparing the two, and taking corrective or preventive

    action as necessary.

    The American Luther Gulick and Brit Lydnall Urwick expanded Fayol's list to seven executive management

    activities summarized by the acronym POSDCORB:

    12

    http://www.ag.ohio-state.edu/~mgtexcel/Planning.htmlhttp://www.ag.ohio-state.edu/~mgtexcel/Organize.htmlhttp://www.ag.ohio-state.edu/~mgtexcel/Staffing.htmlhttp://www.ag.ohio-state.edu/~mgtexcel/Direct.htmlhttp://www.ag.ohio-state.edu/~mgtexcel/Control.htmlhttp://www.ag.ohio-state.edu/~mgtexcel/Planning.htmlhttp://www.ag.ohio-state.edu/~mgtexcel/Organize.htmlhttp://www.ag.ohio-state.edu/~mgtexcel/Staffing.htmlhttp://www.ag.ohio-state.edu/~mgtexcel/Direct.htmlhttp://www.ag.ohio-state.edu/~mgtexcel/Control.html
  • 8/2/2019 Cours File-Industrial Management(2)

    13/157

    planning: determine objectives in advance and the methods to achieve them;

    organizing: establish a structure of authority for all work;

    staffing: recruit, hire and train workers; maintain favourable working conditions;

    directing: make decisions, issue orders and directives;

    coordinating: interrelate all sectors of the organisation;

    reporting: inform hierarchy through reports, records and inspections;

    budgeting: depend on fiscal planning, accounting and control.

    Each of these functions involves creative problem solving. (Figure 4.2 from Higgins, page 118) Creative

    problem solving is broader than problem finding, choice making or decision making. It extends from analysis

    of the environment within which the business is functioning to evaluation of the outcomes from the alternative

    implemented.

    Principles of Management

    Henri Fayol, the father of the school of Systematic Management, was motivated to create a theoretical

    foundation for a managerial educational program based on his experience as a successful managing director of

    a mining company. In his day, managers had no formal training and he observed that the increasing complexity

    of organisations would require more professional management.

    13

  • 8/2/2019 Cours File-Industrial Management(2)

    14/157

    A principle refers to a fundamental truth. It establishes cause and effect relationship between two or more

    variables under given situation. They serve as a guide to thought & actions. Therefore, management principles

    are the statements of fundamental truth based on logic which provides guidelines for managerial decision

    making and actions. These principles are derived: -

    a. On the basis of observation and analysis i.e. practical experience of managers.b. By conducting experimental studies.

    There are 14 Principles of Management described by Henri Fayol.

    1. Division of Labor

    a. Henry Fayol has stressed on the specialization of jobs.

    b. He recommended that work of all kinds must be divided & subdivided and allotted to various

    persons according to their expertise in a particular area.

    c. Subdivision of work makes it simpler and results in efficiency.

    d. It also helps the individual in acquiring speed, accuracy in his performance.

    e. Specialization leads to efficiency & economy in spheres of business.

    2. Party of Authority & Responsibility

    a. Authority & responsibility are co-existing.

    b. If authority is given to a person, he should also be made responsible.

    c. In a same way, if anyone is made responsible for any job, he should also have concerned

    authority.

    d. Authority refers to the right of superiors to get exactness from their sub-ordinates whereas

    responsibility means obligation for the performance of the job assigned.

    e. There should be a balance between the two i.e. they must go hand in hand.

    f. Authority without responsibility leads to irresponsible behavior whereas responsibility without

    authority makes the person ineffective.

    3. Principle of One Boss

    a. A sub-ordinate should receive orders and be accountable to one and only one boss at a time.

    b. In other words, a sub-ordinate should not receive instructions from more than one person

    because

    - It undermines authority

    - Weakens discipline

    14

  • 8/2/2019 Cours File-Industrial Management(2)

    15/157

    - Divides loyalty

    - Creates confusion

    - Delays and chaos

    - Escaping responsibilities

    - Duplication of work

    - Overlapping of efforts

    c. Therefore, dual sub-ordination should be avoided unless and until it is absolutely essential.

    d. Unity of command provides the enterprise a disciplined, stable & orderly existence.

    e. It creates harmonious relationship between superiors and sub-ordinates.

    4. Unity of Direction

    a. Fayol advocates one head one plan which means that there should be one plan for a group of

    activities having similar objectives.

    b. Related activities should be grouped together. There should be one plan of action for them and

    they should be under the charge of a particular manager.

    c. According to this principle, efforts of all the members of the organization should be directed

    towards common goal.

    d. Without unity of direction, unity of action cannot be achieved.

    e. In fact, unity of command is not possible without unity of direction.

    Basis Unity of command Unity of direction

    Meaning It implies that a sub-ordinate should receive

    orders & instructions from only one boss.

    It means one head, one plan for a group of

    activities having similar objectives.

    Nature It is related to the functioning of personnels. It is related to the functioning of departments,

    or organization as a whole.

    Necessity It is necessary for fixing responsibility of each

    subordinates.

    It is necessary for sound organization.

    Advantage It avoids conflicts, confusion & chaos. It avoids duplication of efforts and wastage

    15

  • 8/2/2019 Cours File-Industrial Management(2)

    16/157

    of resources.

    Result It leads to better superior sub-ordinate

    relationship.

    It leads to smooth running of the enterprise.

    Therefore it is obvious that they are different from each other but they are dependent on each other i.e. unity of

    direction is a pre-requisite for unity of command. But it does not automatically comes from the unity of

    direction.

    5. Equity

    a. Equity means combination of fairness, kindness & justice.

    b. The employees should be treated with kindness & equity if devotion is expected of them.c. It implies that managers should be fair and impartial while dealing with the subordinates.

    d. They should give similar treatment to people of similar position.

    e. They should not discriminate with respect to age, caste, sex, religion, relation etc.

    f. Equity is essential to create and maintain cordial relations between the managers and sub-

    ordinate.

    g. But equity does not mean total absence of harshness.

    h. Fayol was of opinion that, at times force and harshness might become necessary for the sake of

    equity.

    6. Order

    a. This principle is concerned with proper & systematic arrangement of things and people.

    b. Arrangement of things is called material order and placement of people is called social order.

    c. Material order- There should be safe, appropriate and specific place for every article and every

    place to be effectively used for specific activity and commodity.

    d. Social order- Selection and appointment of most suitable person on the suitable job. There

    should be a specific place for every one and everyone should have a specific place so that they

    can easily be contacted whenever need arises.

    7. Discipline

    a. According to Fayol, Discipline means sincerity, obedience, respect of authority & observance

    of rules and regulations of the enterprise.

    b. This principle applies that subordinate should respect their superiors and obey their order.

    16

  • 8/2/2019 Cours File-Industrial Management(2)

    17/157

    c. It is an important requisite for smooth running of the enterprise.

    d. Discipline is not only required on path of subordinates but also on the part of management.

    e. Discipline can be enforced if -

    - There are good superiors at all levels.

    - There are clear & fair agreements with workers.- Sanctions (punishments) are judiciously applied.

    8. Initiative

    a. Workers should be encouraged to take initiative in the work assigned to them.

    b. It means eagerness to initiate actions without being asked to do so.

    c. Fayol advised that management should provide opportunity to its employees to suggest ideas,

    experiences& new method of work.

    d. It helps in developing an atmosphere of trust and understanding.

    e. People then enjoy working in the organization because it adds to their zeal and energy.

    f. To suggest improvement in formulation & implementation of place.

    g. They can be encouraged with the help of monetary & non-monetary incentives.

    9. Fair Remuneration

    a. The quantum and method of remuneration to be paid to the workers should be fair, reasonable,

    satisfactory & rewarding of the efforts.

    b. As far as possible it should accord satisfaction to both employer and the employees.

    c. Wages should be determined on the basis of cost of living, work assigned, financial position of

    the business, wage rate prevailing etc.

    d. Logical & appropriate wage rates and methods of their payment reduce tension & differences

    between workers & management creates harmonious relationship and pleasing atmosphere of

    work.

    e. Fayol also recommended provision of other benefits such as free education, medical &

    residential facilities to workers.

    10. Stability of Tenure

    a. Fayol emphasized that employees should not be moved frequently from one job position to

    another i.e. the period of service in a job should be fixed.

    17

  • 8/2/2019 Cours File-Industrial Management(2)

    18/157

    b. Therefore employees should be appointed after keeping in view principles of recruitment &

    selection but once they are appointed their services should be served.

    c. According to Fayol. Time is required for an employee to get used to a new work & succeed to

    doing it well but if he is removed before that he will not be able to render worthwhile services.

    d. As a result, the time, effort and money spent on training the worker will go waste.

    e. Stability of job creates team spirit and a sense of belongingness among workers which

    ultimately increase the quality as well as quantity of work.

    11. Scalar Chain

    a. Fayol defines scalar chain as The chain of superiors ranging from the ultimate authority to the

    lowest.

    b. Every orders, instructions, messages, requests, explanation etc. has to pass through Scalar chain.

    c. But, for the sake of convenience & urgency, this path can be cut shirt and this short cut is

    known as Gang Plank.

    d. A Gang Plank is a temporary arrangement between two different points to facilitate quick &

    easy communication as explained below:

    In the figure given, if D has to communicate with G he will first send the communication upwards with the help

    of C, B to A and then downwards with the help of E and F to G which will take quite some time and by that

    time, it may not be worth therefore a gang plank has been developed between the two.

    Gang Plank clarifies that management principles are not rigid rather they are very flexible. They can be

    moulded and modified as per the requirements of situations

    12. Sub-Ordination of Individual Interest to General Interest

    18

  • 8/2/2019 Cours File-Industrial Management(2)

    19/157

    a. An organization is much bigger than the individual it constitutes therefore interest of the

    undertaking should prevail in all circumstances.

    b. As far as possible, reconciliation should be achieved between individual and group interests.

    c. But in case of conflict, individual must sacrifice for bigger interests.

    d. In order to achieve this attitude, it is essential that -

    - Employees should be honest & sincere.

    - Proper & regular supervision of work.

    - Reconciliation of mutual differences and clashes by mutual agreement. For example,

    for change of location of plant, for change of profit sharing ratio, etc.

    13. Espirit De Corps (can be achieved through unity of command)

    a. It refers to team spirit i.e. harmony in the work groups and mutual understanding among the

    members.

    b. Spirit De Corps inspires workers to work harder.

    c. Fayol cautioned the managers against dividing the employees into competing groups because it

    might damage the moral of the workers and interest of the undertaking in the long run.

    d. To inculcate Espirit De Corps following steps should be undertaken -

    There should be proper co-ordination of work at all levels

    Subordinates should be encouraged to develop informal relations among themselves.

    Efforts should be made to create enthusiasm and keenness among subordinates so that

    they can work to the maximum ability.

    Efficient employees should be rewarded and those who are not up to the mark should be

    given a chance to improve their performance.

    Subordinates should be made conscious of that whatever they are doing is of great

    importance to the business & society.

    e. He also cautioned against the more use of Britain communication to the subordinates i.e. face to

    face communication should be developed. The managers should infuse team spirit &

    belongingness. There should be no place for misunderstanding. People then enjoy working in

    the organization & offer their best towards the organization.

    14. Centralization & De-Centralization

    a. Centralization means concentration of authority at the top level. In other words, centralization is

    a situation in which top management retains most of the decision making authority.

    19

  • 8/2/2019 Cours File-Industrial Management(2)

    20/157

    b. Decentralization means disposal of decision making authority to all the levels of the

    organization. In other words, sharing authority downwards is decentralization.

    c. According to Fayol, Degree of centralization or decentralization depends on no. of factors like

    size of business, experience of superiors, dependability & ability of subordinates etc.

    d. Anything which increases the role of subordinate is decentralization & anything which

    decreases it is centralization.

    e. Fayol suggested that absolute centralization or decentralization is not feasible. An organization

    should strike to achieve a lot between the two.

    20

  • 8/2/2019 Cours File-Industrial Management(2)

    21/157

    Management tools

    Classic Tools

    There's an elusive balance between chasing after each new management tool or method, and ignoring the fact

    that we have actually learned some things about management over the past 100,000 years. The best tools are

    those which stand the test of time, and which give you a lot of leverage over common problems.

    Pie Charts

    21

    Quality Control Charts Other Quality Management Tools

    Pie charts

    Bar charts

    Run Charts

    Radar Charts

    Scatter Plots

    Histograms

    Pareto Charts

    Normal Test Plots

    Process Capability Calculations

    Control Charts

    Relations Diagram

    Pathway

    Affinity Diagrams

    Brainstorms

    Building Consensus

    Cause and Effect Diagrams

    Flowcharts

    Force Field Diagrams

    Tree Diagrams

    http://www.skymark.com/resources/tools/pie_charts.asphttp://www.skymark.com/resources/tools/bar_charts.asphttp://www.skymark.com/resources/tools/run_charts.asphttp://www.skymark.com/resources/tools/radar_charts.asphttp://www.skymark.com/resources/tools/scatter_plots.asphttp://www.skymark.com/resources/tools/histograms.asphttp://www.skymark.com/resources/tools/pareto_charts.asphttp://www.skymark.com/resources/tools/normal_test_plot.asphttp://www.skymark.com/resources/tools/process_capability.asphttp://www.skymark.com/resources/tools/control_charts.asphttp://www.skymark.com/resources/tools/relations_diagram.asphttp://www.skymark.com/resources/tools/pathway.asphttp://www.skymark.com/resources/tools/affinity_diagram.asphttp://www.skymark.com/resources/tools/brainstorming.asphttp://www.skymark.com/resources/tools/building_consensus.asphttp://www.skymark.com/resources/tools/cause.asphttp://www.skymark.com/resources/tools/flowchart.asphttp://www.skymark.com/resources/tools/force_field_diagram.asphttp://www.skymark.com/resources/tools/tree%20diagram.asphttp://www.skymark.com/resources/tools/pie_charts.asphttp://www.skymark.com/resources/tools/bar_charts.asphttp://www.skymark.com/resources/tools/run_charts.asphttp://www.skymark.com/resources/tools/radar_charts.asphttp://www.skymark.com/resources/tools/scatter_plots.asphttp://www.skymark.com/resources/tools/histograms.asphttp://www.skymark.com/resources/tools/pareto_charts.asphttp://www.skymark.com/resources/tools/normal_test_plot.asphttp://www.skymark.com/resources/tools/process_capability.asphttp://www.skymark.com/resources/tools/control_charts.asphttp://www.skymark.com/resources/tools/relations_diagram.asphttp://www.skymark.com/resources/tools/pathway.asphttp://www.skymark.com/resources/tools/affinity_diagram.asphttp://www.skymark.com/resources/tools/brainstorming.asphttp://www.skymark.com/resources/tools/building_consensus.asphttp://www.skymark.com/resources/tools/cause.asphttp://www.skymark.com/resources/tools/flowchart.asphttp://www.skymark.com/resources/tools/force_field_diagram.asphttp://www.skymark.com/resources/tools/tree%20diagram.asp
  • 8/2/2019 Cours File-Industrial Management(2)

    22/157

    Pie charts are used to show classes or groups of data in proportion to the whole data set. The entire pie

    represents all the data, while each slice represents a different class or group within the whole.

    Bar Charts

    Bar Charts, like pie charts, are useful for comparing classes or groups of data. In bar charts, a class or group can

    have a single category of data, or they can be broken down further into multiple categories for greater depth of

    analysis.

    Run Charts

    Run charts (often known as line graphs outside the quality management field) display process performance over

    time. Upward and downward trends, cycles, and large aberrations may be spotted and investigated further. In a

    run chart, events, shown on they axis, are graphed against a time period on thex axis. For example, a run chart

    in a hospital might plot the number of patient transfer delays against the time of day or day of the week. The

    22

  • 8/2/2019 Cours File-Industrial Management(2)

    23/157

    results might show that there are more delays at noon than at 3 p.m. Investigating this phenomenon could

    unearth potential for improvement. Run charts can also be used to track improvements that have been put into

    place, checking to determine their success. Also, an average line can be added to a run chart to clarify

    movement of the data away from the average.

    Radar Charts

    Radar charts are useful when you want to look at several different factors all related to one item. Radar charts

    have multiple axes along which data can be plotted. For example, you could use a radar chart to compile data

    about a wide receiver on a professional football team. On one axis, you could plot the percentage of passes

    caught. Another axis would show his yards per completion; another, his completions per 100 plays; another,

    blocks made; and a final axis might show his interceptions.

    Scatter Plots

    Scatter Plots (also called scatter diagrams) are used to investigate the possible relationship between two

    variables that both relate to the same "event." A straight line of best fit (using the least squares method)

    is often included.

    23

  • 8/2/2019 Cours File-Industrial Management(2)

    24/157

    Histograms

    A histogram is a specialized type of bar chart. Individual data points are grouped together in classes, so that you

    can get an idea of how frequently data in each class occur in the data set. High bars indicate more points in a

    class, and low bars indicate less points. In the histogram show above, the peak is in the 40-49 class, where there

    are four points.

    Pareto Charts

    Vilfredo Pareto, a turn-of-the-century Italian economist, studied the distributions of wealth in different

    countries, concluding that a fairly consistent minority about 20% of people controlled the large

    majority about 80% of a society's wealth. This same distribution has been observed in other areas

    and has been termed the Pareto effect.

    24

  • 8/2/2019 Cours File-Industrial Management(2)

    25/157

    Normal Test Plot

    Normal Test Plots (also called Normal Probability Plots or Normal Quartile Plots) are used to investigate

    whether process data exhibit the standard normal "bell curve" or Gaussian distribution.

    Process Capability

    The capability of a process is some measure of the proportion of in-specification items the process produces

    when it is in a state of statistical control.

    For valid process capability calculations, all data must be from an in-control process, with respect to both the

    mean and standard deviation. Make sure to check this data in a variables control chart to make sure that all

    25

  • 8/2/2019 Cours File-Industrial Management(2)

    26/157

    points in the x bar, s or R charts are in control. If they aren't, your capability indices in the statistics dialog box

    are not valid.

    Control Charts

    Every process varies. If you write your name ten times, your signatures will all be similar, but no two

    signatures will be exactly alike. There is an inherent variation, but it varies between predictable limits. If, as

    you are signing your name, someone bumps your elbow, you get an unusual variation due to what is called a

    "special cause". If you are cutting diamonds, and someone bumps your elbow, the special cause can be

    expensive. For many, many processes, it is important to notice special causes of variation as soon as they occur.

    Other Quality Management Tools

    Relations Diagram (or Interrelationship Digraph)

    Relations Diagrams are drawn to show all the different relationships between factors, areas, or processes. Why

    are they worthwhile? Because they make it easy to pick out the factors in a situation which are the ones which

    are driving many of the other symptoms or factors. For example, a relations diagram of urban poverty might

    start out something like this:

    Instead of one item following another in a logical sequence, each item is connected to many other pieces,

    showing that they have an impact on each one. Once all the relevant connections between items have been

    drawn, the connections are counted. Those with the most connections will usually be the most important factors

    to focus on.

    26

  • 8/2/2019 Cours File-Industrial Management(2)

    27/157

    Project Pathways for Management

    One of the common features of modern management thinking is its focus on methodologies for problem-

    solving. Dr. Deming used the Plan-Do-Check-Act cycle. Marshall-Qualtec espouses a seven-step problem

    solving model. The Juran Institute has a slightly different method. So does Executive Learning Inc. That said,

    all the approaches, while different in the details, are very similar overall.The pathway, embodied in software, is

    a key means of keeping a team focused and on-track. It also provides an easy way for managers of many

    projects or departments to keep tabs on the status and progress of work.

    Affinity Diagram

    The affinity diagram, or KJ method (after its author, Kawakita Jiro), wasn't originally intended for quality

    management. Nonetheless, it has become one of the most widely used of the Japanese management and

    planning tools. The affinity diagram was developed to discovering meaningful groups of ideas within a raw list.

    In doing so, it is important to let the groupings emerge naturally, using the right side of the brain, rather than

    according to preordained categories.

    27

  • 8/2/2019 Cours File-Industrial Management(2)

    28/157

    To create an affinity diagram, you sort the brainstormed list, moving ideas from the brainstorm into affinity

    sets, and creating groups of related ideas. As you sort ideas:

    1. Rapidly group ideas that seem to belong together.

    2. It isn't important to define why they belong together.

    3. Clarify any ideas in question.4. Copy an idea into in more than one affinity set if appropriate.

    5. Look for small sets. Should they belong in a larger group?

    6. Do large sets need to be broken down more precisely?

    7. When most of the ideas have been sorted, you can start to enter titles for each affinity set.

    Brainstorming

    Creative thinking requires tools such as the brainstorm and the affinity diagram. Brainstorming is simply listing

    all ideas put forth by a group in response to a given problem or question. In 1939, a team led by advertising

    executive Alex Osborn coined the term "brainstorm." According to Osborn, " Brainstorm means using the

    brain to storm a creative problem and to do so "in commando fashion, each stormer audaciously attacking the

    same objective." Creativity is encouraged by not allowing ideas to be evaluated or discussed until everyone has

    run dry. Any and all ideas are considered legitimate and often the most far-fetched are the most fertile.

    Structured brainstorming produces numerous creative ideas about any given "central question". Done right, it

    taps the human brain's capacity for lateral thinking and free association.

    Brainstorms help answer specific questions such as:

    What opportunities face us this year?

    What factors are constraining performances in Department X?

    What could be causing problem Y?

    What can we do to solve problem Z?

    Building Consensus

    The word consensus comes to us from Latin roots meaning "shared thought". Consensus does not imply

    complete agreement, but does involve seeking a decision with which everyone is reasonably comfortable. To

    accomplish this, everyone will need a fair opportunity to be heard and latent issues must be explored to the

    satisfaction of the group. Many different tools can be used to build consensus. In fact, all the tools used in

    quality management contribute to consensus. For example, a well-run brainstorming session can get lots of

    ideas out onto the table and give everyone a chance for input. Still, most groups approach a point where they

    28

  • 8/2/2019 Cours File-Industrial Management(2)

    29/157

    must choose between options, or try to narrow a list from many items to just a few. For this, effective tools

    specifically for building consensus are used.

    Cause & Effect Diagram

    The cause & effect diagram is the brainchild of Kaoru Ishikawa, who pioneered quality management processes

    in the Kawasaki shipyards, and in the process became one of the founding fathers of modern management.

    The C&E diagram is also known as the fishbone diagram because it was drawn to resemble the skeleton of a

    fish, with the main causal categories drawn as "bones" attached to the spine of the fish, as shown below.

    Flowcharting

    Flowcharts are maps or graphical representations of a process. Steps in a process are shown with symbolic

    shapes, and the flow of the process is indicated with arrows connecting the symbols. Computer programmers

    popularized flowcharts in the 1960's, using them to map the logic of programs. There are many varieties of

    flowcharts and scores of symbols that you can use. Experience has shown that there are three main types thatwork for almost all situations:

    High-level flowcharts map only the major steps in a process for a good overview.

    Detailed flowcharts show a step-by-step mapping of all events and decisions in a process.

    29

  • 8/2/2019 Cours File-Industrial Management(2)

    30/157

    Deployment flowcharts which organize the flowchart by columns, with each column representing a

    person or department involved in a process.

    The trouble spots in a process usually begin to appear as a team constructs a detailed flowchart.

    Although there are many symbols that can be used in flowcharts to represent different kinds of steps, accurate

    flowcharts can be created using very few (e.g. oval, rectangle, diamond, delay, cloud).

    Force Field Analysis

    Force Field Analysis is a simple but powerful technique for building an understanding of the forces that will

    drive and resist a proposed change. It consists of a two column form, with driving forces listed in the first

    column, and restraining forces in the second.

    30

  • 8/2/2019 Cours File-Industrial Management(2)

    31/157

    The force field diagram is derived from the work of social psychologist Kurt Lewin. According to Lewins

    theories, human behavior is caused by forces beliefs, expectations, cultural norms, and the like within the

    "life space" of an individual or society. These forces can be positive, urging us toward a behavior, or negative,

    propelling us away from a behavior. A force field diagram portrays these driving forces and restraining

    forces that affect a central question or problem. A force field diagram can be used to compare any kind of

    opposites, actions and consequences, different points of view, and so on.

    Tree Diagram

    The tree diagram is one of the 7 Management and Planning Tools described by Shigeru Mizuno. It is used to

    figure out all the various tasks that must be undertaken to achieve a given objective. If you use it carefully and

    thoroughly, it will give you a better understanding of the true scope of a project, and will help your team

    focuses on specific tasks that are needed to get something done.

    Time and motion study

    A time and motion study (or time-motion study) is a business efficiency technique combining the Time

    Study work of Frederick Winslow Taylor with the Motion Study work of Frank and Lillian Gilbreth (not to be

    confused with their son, best known through the biographical 1950 film and book Cheaper by the Dozen). After

    its first introduction, time study developed in the direction of establishing standard times, while motion study

    evolved into a technique for improving work methods. The two techniques became integrated and refined into a

    widely accepted method applicable to the improvement and upgrading of work systems. This integrated

    approach to work system improvement is known as methods engineering.

    Time and motion study have to be used together in order to achieve rational and reasonable results. It is

    particularly important that effort be applied in motion study to insure equitable results when time study is used.

    In fact, much of the difficulty with time study is a result of applying it without a thorough study of the motion

    pattern of the job. Motion study can be considered the foundation for time study. The time study measures the

    time required to perform a given task in accordance with a specified method and is valid only so long as the

    method is continued. Time studies are applied today to industrial as well as service organizations, including

    banks, schools and hospitals. Once a new work method is developed, the time study must be changed to agree

    with the new method.

    Methods-Time Measurement (MTM) is a predetermined motion time system that is used primarily in

    industrial settings to analyse the methods used to perform any manual operation or task and, as a byproduct of

    that analysis, set the standard time in which a worker should complete that task.

    31

    http://en.wikipedia.org/wiki/Predetermined_motion_time_systemhttp://en.wikipedia.org/wiki/Standard_time_(manufacturing)http://en.wikipedia.org/wiki/Predetermined_motion_time_systemhttp://en.wikipedia.org/wiki/Standard_time_(manufacturing)
  • 8/2/2019 Cours File-Industrial Management(2)

    32/157

    Methodology

    The rating, or Levelling, system used was the Westinghouse or LMS system so called after its originators

    Lowry, Maynard and Stegemerten. This system considers four factors independently:

    Skill Proficiency in following the given method

    Effort The will to work Conditions The general work surroundings

    Consistency of performance

    Each factor is assigned an alpha rating, e.g. B-, C+, A, etc. which has a numeric value which is applied

    later. This reduces the possibility of clock rating and ensures that all factors are considered in the composite

    rating. Appendix 1 shows the model for Causes of Difference in Output on which the LMS system is based.

    Layout, distances, sizes of parts and tools and tolerances were accurately measured and recorded on the shop

    floor to complement the later analyses.

    The films were then projected frame-by-frame and analysed and classified in to a predetermined format of

    Basic Motions. These Basic Motions were Reach, Grasp, Move, Position, Release, etc. A motion was taken to

    begin on the frame in which the hand first started performing the motion and was taken to end on the frame in

    which the motion was completed. This allowed a time for each recorded motion to be calculated in seconds, by

    means of a frame count, and then levelled to a common performance.

    Plots of the levelled times for the various motions were drawn. Analysis determined the best definitions of

    limits of motions and their major, time-determining variables, and resulted in, more or less, the structure which

    the manual motions of MTM-1 have today. Later work, using Time Study, gave the table of Body Motions.

    MTM is complementary to other Industrial Engineering charting analytical techniques; it does not replace

    them. It should be used after broader techniques have established the Necessity and Purpose, Place, Sequence,

    Person and Means of the tasks to be evaluated.

    Unit

    The unit in which movements are measured for MTM is TMU (time measurement unit): 1 TMU = 36

    milliseconds ; 1 hour = 100,000 TMU

    1 TMU = 0.036 second

    32

  • 8/2/2019 Cours File-Industrial Management(2)

    33/157

    Work Simplification

    Work simplification describes the making of daily tasks easier in order to reduce strain, or to decrease the

    amount energy required to complete an activity. Work Simplification is a scientific approach to study work

    processes with a view to simplifying the process such that the work process becomes more efficient and

    effective and thereby raises productivity and reduces wastage of labor effort, materials, space, time and energy

    in the process of producing a good or delivering a service.

    Work simplification techniques range from low-tech (such as using no-scrub cleaners) to high-tech (such as

    using voice recognition software for typing).

    Some examples include:

    Using an automated can opener instead of the manual version

    Lengthening a short handle on a dustpan to avoid bending

    Using pre-pressed clothes that eliminate the need for ironing

    Sliding heavy objects or using a wheeled cart to avoid lifting

    Putting an automatic toilet cleaner in the bowl

    Work simplification can be useful for people who wish to remain independent for as long as possible, even if

    they have a chronic health condition.

    Allow for Flexibility Simplification and Harmonization by its very definition allows for flexibility for the UNCountry Team and national partners to apply those Simplification and Harmonization measures that are

    appropriate to their country situation and that take into account the financial management capacities available

    for implementation and that empower recipient countries.

    Contribute to Capacity Building The Simplification and Harmonization must be an instrument towards

    increased national capacities. It needs to be built around national systems and processes and must complement

    the directions on aid coordination that governments in programme countries are pursuing.

    Link with other Simplification and Harmonization Initiatives Simplification and Harmonization process

    envisages close collaboration with country offices and national partners, and must factor in and mutually build

    on the various efforts at Simplification and Harmonization, notably of the OECD-DAC, World Bank and

    Regional Banks, the EU and others. This will ensure synergy and complementarities.

    33

  • 8/2/2019 Cours File-Industrial Management(2)

    34/157

    Include other agencies while the various Simplification and Harmonization measures pertain largely to the

    four ExCom agencies that have adopted a common Country Programme approach, a number of the

    recommendations could apply to all the UN funds and programmes and specialized agencies at the country

    level. The gradual adoption of some of the elements of the programme approach by the various other agencies

    might enable them to align with the other measures.

    Work Simplification has generated billions of dollars through effectiveness and efficiency for organizations

    that focused on their people and gave them tools for continuous improvement. Over the past two decades, the

    glamour of electronics has seduced many organizations into treating their people as expenses rather than

    resources. For those organizations whose leaders truly believe that their people are their most valuable

    resource, the tools of Work Simplification are still available - and better than ever.

    In 1946, ASME did something that was even then a long time in the making. They established a set of symbols

    as the ASME Standard for Operation and Flow Process Charts. Twenty-five years earlier Frank and Lillian

    Gilbreth had presented "Process Charts - First Steps in Finding the One Best Way" at the Annual Meeting of

    ASME in 1921. By the time the symbols were standardized they had evolved into a solid set of five symbols

    that covered every aspect of work, in any work environment, that can be used with very little confusion. The

    first process charts appeared as a series of symbols strung down a page in sequential order. This was (and still

    is) a simple and effective way to track the flow of a person or a piece of material through a work process.

    - Operation. An operation occurs when an object is arranged or prepared for another step, assembled ordisassembled or intentionally changed.

    - Transportation. A transportation occurs when an object is moved from one location to another.

    -Inspection. An inspection occurs when an object is verified for quality or quantity in any of its characteristics.

    -Delay. A delay occurs when an object waits for the next planned action.

    -Storage. A storage occurs when an object is kept and protected against unauthorized removal.

    These days, processes change so fast that many organizations have failed to keep up. Their work is

    undocumented and as changes are made the complexity mounts. The simple and effective approach of Work

    Simplification has more to offer than it ever had. However, its use is not widespread. It appears that many

    organizations are focusing their attention on purchasing solutions for their business rather than mastering their

    work themselves. Where the purchased solutions lead to downsizing, the corporate memory is discarded

    34

  • 8/2/2019 Cours File-Industrial Management(2)

    35/157

    leaving the organization dependent on those from whom they purchased their processes.

    The Work Simplification approach utilizes the corporate memory rather than discarding it. It counters

    increasing complexity with continuous improvement and enables the work force to be the masters of their

    processes. It is on the program at many universities and it is being applied in increasing numbers of

    organizations across the US and Canada; in South America, Europe and Australia as these companies seek to

    regain control of their operations.

    New methods for studying work are introduced on a regular basis. Usually they focus effectively on one or

    another aspect of improvement but they often fail because they do not deal rigorously with the work itself. This

    is a good time to look back and discover again a simple tool that visually displays processes in a universal

    language that can be readily understood by anyone who wants to understand.

    Today, if you are pursuing six sigma or lean manufacturing; if you are using Kazan or value stream mapping, if

    you are managing your supply chain, developing a b2b strategy, establishing an electronic commerce presence,

    managing day to day internal operations or documenting your processes for certification or audit, understanding

    the fundamental steps in your work processes will help you get those things done. Work Simplification helps

    you get therefaster, cheaper and better!

    Flowchart

    A flowchart is a type ofdiagram that represents an algorithm orprocess, showing the steps as boxes of various

    kinds, and their order by connecting these with arrows. This diagrammatic representation can give a step-by-step solution to a given problem. Process operations are represented in these boxes, and arrows connecting

    them represent flow of control. Data flows are not typically represented in a flowchart, in contrast with data

    flow diagrams; rather, they are implied by the sequencing of operations. Flowcharts are used in analyzing,

    designing, documenting or managing a process or program in various fields.

    Flowcharts used to be a popular means for describing computer algorithms and are still used for this purpose.

    Modern techniques such as UMLactivity diagrams can be considered to be extensions of the flowchart. In the

    1970s the popularity of flowcharts as an own method decreased when interactive computer terminals and third-

    generation programming languages became the common tools of the trade, since algorithms can be expressed

    much more concisely and readably as source code in such a language, and also because designing algorithms

    using flowcharts was more likely to result in spaghetti code because of the need forgotos to describe arbitrary

    jumps in control flow. Often pseudo-code is used, which uses the common idioms of such languages without

    strictly adhering to the details of a particular one.

    35

    http://en.wikipedia.org/wiki/Diagramhttp://en.wikipedia.org/wiki/Algorithmhttp://en.wikipedia.org/wiki/Processhttp://en.wikipedia.org/wiki/Knowledge_representation_and_reasoninghttp://en.wikipedia.org/wiki/Problem_solvinghttp://en.wikipedia.org/wiki/Datahttp://en.wikipedia.org/wiki/Data_flow_diagramhttp://en.wikipedia.org/wiki/Data_flow_diagramhttp://en.wikipedia.org/wiki/Computer_algorithmhttp://en.wikipedia.org/wiki/Unified_Modeling_Languagehttp://en.wikipedia.org/wiki/Activity_diagramhttp://en.wikipedia.org/wiki/Computer_terminalhttp://en.wikipedia.org/wiki/Third-generation_programming_languagehttp://en.wikipedia.org/wiki/Third-generation_programming_languagehttp://en.wikipedia.org/wiki/Computer_programminghttp://en.wikipedia.org/wiki/Source_codehttp://en.wikipedia.org/wiki/Programming_languagehttp://en.wikipedia.org/wiki/Spaghetti_codehttp://en.wikipedia.org/wiki/Gotohttp://en.wikipedia.org/wiki/Pseudo-codehttp://en.wikipedia.org/wiki/Diagramhttp://en.wikipedia.org/wiki/Algorithmhttp://en.wikipedia.org/wiki/Processhttp://en.wikipedia.org/wiki/Knowledge_representation_and_reasoninghttp://en.wikipedia.org/wiki/Problem_solvinghttp://en.wikipedia.org/wiki/Datahttp://en.wikipedia.org/wiki/Data_flow_diagramhttp://en.wikipedia.org/wiki/Data_flow_diagramhttp://en.wikipedia.org/wiki/Computer_algorithmhttp://en.wikipedia.org/wiki/Unified_Modeling_Languagehttp://en.wikipedia.org/wiki/Activity_diagramhttp://en.wikipedia.org/wiki/Computer_terminalhttp://en.wikipedia.org/wiki/Third-generation_programming_languagehttp://en.wikipedia.org/wiki/Third-generation_programming_languagehttp://en.wikipedia.org/wiki/Computer_programminghttp://en.wikipedia.org/wiki/Source_codehttp://en.wikipedia.org/wiki/Programming_languagehttp://en.wikipedia.org/wiki/Spaghetti_codehttp://en.wikipedia.org/wiki/Gotohttp://en.wikipedia.org/wiki/Pseudo-code
  • 8/2/2019 Cours File-Industrial Management(2)

    36/157

    Flowchart building blocks

    Symbols

    A typical flowchart from older basic computer science textbooks may have the following kinds of symbols:

    Start and end symbols

    Represented as circles, ovals or rounded rectangles, usually containing the word "Start" or "End", or

    another phrase signaling the start or end of a process, such as "submit enquiry" or "receive product".

    Arrows

    Showing what's called "flow of control" in computer science. An arrow coming from one symbol and

    ending at another symbol represents that control passes to the symbol the arrow points to.

    Generic processing steps

    Represented as rectangles. Examples: "Add 1 to X"; "replace identified part"; "save changes" or similar.

    Subroutines

    Represented as rectangles with double-struck vertical edges; these are used to show complex processing

    steps which may be detailed in a separate flowchart. Example: PROCESS-FILES. One subroutine may have

    multiple distinct entry points or exit flows (see coroutine); if so, these are shown as labeled 'wells' in the

    rectangle, and control arrows connect to these 'wells'.

    Input/output

    Represented as a parallelogram. Examples: Get X from the user; display X.

    Prepare conditionalRepresented as a hexagon. Shows operations which have no effect other than preparing a value for a

    subsequent conditional or decision step (see below).

    Conditional or decision

    Represented as a diamond (rhombus) showing where a decision is necessary, commonly a Yes/No

    question or True/False test. The conditional symbol is peculiar in that it has two arrows coming out of

    it, usually from the bottom point and right point, one corresponding to Yes or True, and one

    corresponding to No or False. (The arrows should always be labeled.) More than two arrows can be

    used, but this is normally a clear indicator that a complex decision is being taken, in which case it may

    need to be broken-down further or replaced with the "pre-defined process" symbol.

    Junction symbol

    Generally represented with a black blob, showing where multiple control flows converge in a single exit

    flow. A junction symbol will have more than one arrow coming into it, but only one going out.

    36

    http://en.wikipedia.org/wiki/Control_flowhttp://en.wikipedia.org/wiki/Rectangleshttp://en.wikipedia.org/wiki/Coroutinehttp://en.wikipedia.org/wiki/Parallelogramhttp://en.wikipedia.org/wiki/Rhombushttp://en.wikipedia.org/wiki/Control_flowhttp://en.wikipedia.org/wiki/Rectangleshttp://en.wikipedia.org/wiki/Coroutinehttp://en.wikipedia.org/wiki/Parallelogramhttp://en.wikipedia.org/wiki/Rhombus
  • 8/2/2019 Cours File-Industrial Management(2)

    37/157

    In simple cases, one may simply have an arrow point to another arrow instead. These are useful to

    represent an iterative process (what in Computer Science is called a loop). A loop may, for example,

    consist of a connector where control first enters, processing steps, a conditional with one arrow exiting

    the loop, and one going back to the connector.

    For additional clarity, wherever two lines accidentally cross in the drawing, one of them may be drawn

    with a small semicircle over the other, showing that no junction is intended.

    Labeled connectors

    Represented by an identifying label inside a circle. Labeled connectors are used in complex or multi-

    sheet diagrams to substitute for arrows. For each label, the "outflow" connector must always be unique,

    but there may be any number of "inflow" connectors. In this case, a junction in control flow is implied.

    Concurrency symbol

    Represented by a double transversal line with any number of entry and exit arrows. These symbols are

    used whenever two or more control flows must operate simultaneously. The exit flows are activatedconcurrently when all of the entry flows have reached the concurrency symbol. A concurrency symbol

    with a single entry flow is afork; one with a single exit flow is ajoin.

    It is important to remember to keep these connections logical in order. All processes should flow from top

    to bottom and left to right.

    Data-flow extensions

    A number of symbols have been standardized to represent data flow, rather than control flow. These

    symbols may also be used in control flow charts (e.g. to substitute for the parallelogram symbol), but they

    generally have little currency:

    ADocumentrepresented as a rectangle with a wavy base;

    AManual inputrepresented by quadrilateral, with the top irregularly sloping up from left to right. An

    example would be to signify data-entry from a form;

    AManual operation represented by a trapezoid with the longest parallel side at the top, to represent an

    operation or adjustment to process that can only be made manually.

    AData File represented by a cylinder.

    Types of flowchart

    37

    http://en.wikipedia.org/wiki/Iterationhttp://en.wikipedia.org/wiki/Control_flow#Loopshttp://en.wikipedia.org/wiki/Rectanglehttp://en.wikipedia.org/wiki/Quadrilateralhttp://en.wikipedia.org/wiki/Trapezoidhttp://en.wikipedia.org/wiki/Iterationhttp://en.wikipedia.org/wiki/Control_flow#Loopshttp://en.wikipedia.org/wiki/Rectanglehttp://en.wikipedia.org/wiki/Quadrilateralhttp://en.wikipedia.org/wiki/Trapezoid
  • 8/2/2019 Cours File-Industrial Management(2)

    38/157

    Sterneckert (2003) suggested that flowcharts can be modeled from the perspective of different user groups

    (such as managers, system analysts and clerks) and that there are four general types:

    Document flowcharts, showing controls over a document-flow through a system

    Data flowcharts, showing controls over a data flows in a system

    System flowcharts showing controls at a physical or resource level Program flowchart, showing the controls in a program within a system

    Notice that every type of flowchart focuses on some kind of control, rather than on the particular flow itself. In

    addition, many diagram techniques exist that are similar to flowcharts but carry a different name, such as UML

    activity diagrams.

    Example of System flow chart diagram as follows:

    Software

    Any drawing program can be used to create flowchart diagrams, but these will have no underlying data model

    to share data with databases or other programs such as project management systems or spreadsheets. Some

    tools offer special support for flowchart drawing. Many software packages exist that can create flowcharts

    38

    http://en.wikipedia.org/wiki/Unified_Modeling_Languagehttp://en.wikipedia.org/wiki/Activity_diagramhttp://en.wikipedia.org/wiki/Project_managementhttp://en.wikipedia.org/wiki/Spreadsheethttp://en.wikipedia.org/wiki/Unified_Modeling_Languagehttp://en.wikipedia.org/wiki/Activity_diagramhttp://en.wikipedia.org/wiki/Project_managementhttp://en.wikipedia.org/wiki/Spreadsheet
  • 8/2/2019 Cours File-Industrial Management(2)

    39/157

    automatically, either directly from source code, or from a flowchart description language. On-line Web-based

    versions of such programs are available.

    Functional flow block diagram

    A Functional Flow Block Diagram (FFBD) is a multi-tier, time-sequenced, step-by-step flow diagram of a

    systems functional flow.The FFBD notation was developed in the 1950s, and is widely used in classical

    systems engineering. FFBDs are one of the classic business process modeling methodologies, along with flow

    charts, data flow diagrams, control flow diagrams, Gantt charts, PERT diagrams, and IDEF.

    Functional Flow Block Diagram Format as follows:

    FFBDs are also referred to asFunctional Flow Diagrams,functional block diagrams, andfunctional flows.

    39

    http://en.wikipedia.org/wiki/Systemhttp://en.wikipedia.org/wiki/Systems_engineeringhttp://en.wikipedia.org/wiki/Business_process_modelinghttp://en.wikipedia.org/wiki/Flow_charthttp://en.wikipedia.org/wiki/Flow_charthttp://en.wikipedia.org/wiki/Data_flow_diagramhttp://en.wikipedia.org/wiki/Control_flow_diagramhttp://en.wikipedia.org/wiki/Gantt_charthttp://en.wikipedia.org/wiki/PERThttp://en.wikipedia.org/wiki/IDEFhttp://en.wikipedia.org/wiki/Systemhttp://en.wikipedia.org/wiki/Systems_engineeringhttp://en.wikipedia.org/wiki/Business_process_modelinghttp://en.wikipedia.org/wiki/Flow_charthttp://en.wikipedia.org/wiki/Flow_charthttp://en.wikipedia.org/wiki/Data_flow_diagramhttp://en.wikipedia.org/wiki/Control_flow_diagramhttp://en.wikipedia.org/wiki/Gantt_charthttp://en.wikipedia.org/wiki/PERThttp://en.wikipedia.org/wiki/IDEF
  • 8/2/2019 Cours File-Industrial Management(2)

    40/157

    Development of functional flow block diagrams

    FFBDs can be developed in a series of levels. FFBDs show the same tasks identified through functional

    decomposition and display them in their logical, sequential relationship. For example, the entire flight

    mission of a spacecraft can be defined in a top level FFBD, as shown in Figure 2. Each block in the first

    level diagram can then be expanded to a series of functions, as shown in the second level diagram for

    "perform mission operations." Note that the diagram shows both input (transfer to operational orbit) and

    output (transfer to space transportation system orbit), thus initiating the interface identification and

    control process. Each block in the second level diagram can be progressively developed into a series of

    functions, as shown in the third level diagram on Figure 2.

    Figure 2: Development of Functional Flow Block Diagrams

    These diagrams are used both to develop requirements and to identify profitable trade studies. For example,

    does the spacecraft antenna acquire the tracking and data relay satellite (TDRS) only when the payload data are

    to be transmitted, or does it track TDRS continually to allow for the reception of emergency commands or

    40

    http://en.wikipedia.org/w/index.php?title=Flight_mission&action=edit&redlink=1http://en.wikipedia.org/w/index.php?title=Flight_mission&action=edit&redlink=1http://en.wikipedia.org/wiki/Spacecrafthttp://en.wikipedia.org/wiki/File:Development_of_Functional_Flow_Block_Diagrams.jpghttp://en.wikipedia.org/w/index.php?title=Flight_mission&action=edit&redlink=1http://en.wikipedia.org/w/index.php?title=Flight_mission&action=edit&redlink=1http://en.wikipedia.org/wiki/Spacecraft
  • 8/2/2019 Cours File-Industrial Management(2)

    41/157

    transmission of emergency data? The FFBD also incorporates alternate and contingency operations, which

    improve the probability of mission success. The flow diagram provides an understanding of total operation of

    the system, serves as a basis for development of operational and contingency procedures, and pinpoints areas

    where changes in operational procedures could simplify the overall system operation. In certain cases, alternate

    FFBDs may be used to represent various means of satisfying a particular function until data are acquired, which

    permits selection among the alternatives.[8]

    Building blocks

    An overview of the key FFBD attributes:

    Graphical explanation of a "function block" used in these diagrams. Flow is from left to right.

    Function block: Each function on an FFBD should be separate and be represented by single box (solid

    line). Each function needs to stand for definite, finite, discrete action to be accomplished by system

    elements.

    Function numbering: Each level should have a consistent number scheme and provide information

    concerning function origin. These numbers establish identification and relationships that will carry

    through all Functional Analysis and Allocation activities and facilitate traceability from lower to top

    levels.

    Functional reference: Each diagram should contain a reference to other functional diagrams by using a

    functional reference (box in brackets).

    Flow connection: Lines connecting functions should only indicate function flow and not a lapse in time

    or intermediate activity. Flow direction: Diagrams should be laid out so that the flow direction is generally from left to right.

    Arrows are often used to indicate functional flows.

    Summing gates: A circle is used to denote a summing gate and is used when AND/OR is present. AND

    is used to indicate parallel functions and all conditions must be satisfied to proceed. OR is used to

    indicate that alternative paths can be satisfied to proceed.

    41

    http://en.wikipedia.org/wiki/Functional_flow_block_diagram#cite_note-NASA95-7http://en.wikipedia.org/wiki/File:Function_block.jpghttp://en.wikipedia.org/wiki/Functional_flow_block_diagram#cite_note-NASA95-7
  • 8/2/2019 Cours File-Industrial Management(2)

    42/157

    GO and NO-GO paths: G and bar G are used to denote go and no-go conditions. These

    symbols are placed adjacent to lines leaving a particular function to indicate alternative paths.

    Function symbolism

    A function shall be represented by a rectangle containing the title of the function (an action verb followed by a

    noun phrase) and its unique decimal delimited number. A horizontal line shall separate this number and the

    title, as shown in see Figure 3 above. The figure also depicts how to represent a reference function, which

    provides context within a specific FFBD. See Figure 9 for an example regarding use of a reference function.

    Figure 3. Function Symbol

    Figure 4. Directed Lines

    Directed lines

    A line with a single arrowhead shall depict functional flow from left to right, see Figure 4.

    42

    http://en.wikipedia.org/wiki/File:4_Directed_Lines.jpghttp://en.wikipedia.org/wiki/File:3_Function_Symbol.jpg
  • 8/2/2019 Cours File-Industrial Management(2)

    43/157

    Logic Symbols

    The following basic logic symbols shall be used.

    AND: A condition in which all preceding or succeeding paths are required. The symbol may contain a

    single input with multiple outputs or multiple inputs with a single output, but not multiple inputs and

    outputs combined (Figure 5). Read the figure as follows: F2 AND F3 may begin in parallel aftercompletion of F1. Likewise, F4 may begin after completion of F2 AND F3.

    Figure 5. "AND" Symbol Figure 6. "Exclusive OR" Symbol

    Exclusive OR: A condition in which one of multiple preceding or succeeding paths is required, but not

    all. The symbol may contain a single input with multiple outputs or multiple inputs with single output,

    but not multiple inputs and outputs combined (Figure 6). Read the figure as follows: F2 OR F3 may

    begin after completion of F1. Likewise, F4 may begin after completion of either F2 OR F3.

    Inclusive OR: A condition in which one, some, or all of the multiple preceding or succeeding paths arerequired. Figure 7 depicts Inclusive OR logic using a combination of the AND symbol (Figure 5) and

    the Exclusive OR symbol (Figure 6). Read Figure 7 as follows: F2 OR F3 (exclusively) may begin after

    completion of F1, OR (again exclusive) F2 AND F3 may begin after completion of F1. Likewise, F4

    may begin after completion of either F2 OR F3 (exclusively), OR (again exclusive) F4 may begin after

    completion of both F2 AND F3

    43

    http://en.wikipedia.org/wiki/File:6_Exclusive_OR_Symbol.jpghttp://en.wikipedia.org/wiki/File:5_AND_Symbol.jpg
  • 8/2/2019 Cours File-Industrial Management(2)

    44/157

    Figure 7. Inclusive OR Logic

    Contextual and Administrative Data

    Each FFBD shall contain the following contextual and administrative data:

    Date the diagram was created

    Name of the engineer, organization, or working group that created the diagram

    Unique decimal delimited number of the function being diagrammed

    Unique function name of the function being diagrammed.

    Figure 8 and Figure 9 present the data in an FFBD. Figure 9 is a decomposition of the function F2 contained in

    Figure 8 and illustrates the context between functions at different levels of the model.

    Figure 8. FFBD Function 0 Illustration

    Figure 9. FFBD Function 2 Illustration

    44

    http://en.wikipedia.org/wiki/File:8_FFBD_Function_0_Illustration.jpghttp://en.wikipedia.org/wiki/File:7_Inclusive_OR_Logic.jpg
  • 8/2/2019 Cours File-Industrial Management(2)

    45/157

    PRODUCTION PLANNING AND SCHEDULING

    After taking decisions about the type of business, its location, layout etc. the entrepreneur steps into

    the shoe of production manager and attempts to apply managerial principles to the production function in

    an enterprise.

    Production is a process whereby raw material is converted into semi finished products and thereby

    adds to the value of utility of products, which can be measured as the difference between the value of

    inputs and value of outputs.

    Production function encompasses the activities of procurement, allocation and utilization of resources. The

    main objective of production function is to produce the goods and services demanded by the customers in

    the most efficient and economical way. Therefore efficient management of the production function is of

    utmost importance in order to achieve this objective.

    Production system is a system whose function is to convert a set of inputs into a set of desired outputs.

    Production system is depicted under with help of chart Production management involves the managerial

    decisions regarding design of the product and design of the production system i.e. determination of

    production processes and production planning and control.

    45

    http://en.wikipedia.org/wiki/File:9_FFBD_Function_2_Illustration.jpg
  • 8/2/2019 Cours File-Industrial Management(2)

    46/157

    PRODUCT DESIGN

    Product design is a strategic decision as the image and profit earning capacity of a small firm depends largely

    on product design. Once the product to be produced is decided by the entrepreneur the next step is to prepare its

    design. Product design consists of form and function. The form designing includes decisions regarding its

    shape, size, color and appearance of the product. The functional design involves the working conditions of the

    product. Once a product is designed, it prevails for a long time therefore various factors are to be considered

    before designing it. These factors are listed below: -

    (a) Standardization

    (b) Reliability

    (c) Maintainability

    (d) Servicing

    (e) Reproducibility

    (f) Sustainability

    (g) Product simplification

    (h) Quality Commensuration with cost

    (i) Product value

    (j) Consumer quality

    (k) Needs and tastes of consumers.

    Above all, the product design should be dictated by the market demand. It is an important decision and

    therefore the entrepreneur should pay due effort, time, energy and attention in order to get the best results.

    46

  • 8/2/2019 Cours File-Industrial Management(2)

    47/157

  • 8/2/2019 Cours File-Industrial Management(2)

    48/157

    (ii) Batch Production: - In this, limited quantities of each of the different types of products are

    manufactured on same set of machines. Different products are produced separately one after the

    other.

    (iii) Mass or flow production: Under this, the production run is conducted on a set of machines

    arranged according to the sequence of operations. A huge quantity of same product is manufactured at

    a time and is stocked for sale. Different product will require different manufacturing lines. Since

    one line can produce only one

    type of product, this process is also called as line flow.

    (iv) Process Production: Under this, the production run is conducted for an indefinite period.

    Factors Need To Be Considered Before Making A Choice Of Manufacturing Process.

    a) Effect of volume/variety: This is one of the major considerations in selection of manufacturing process.

    When the volume is low and variety is high, intermittent process is most suitable and with increase in

    volume and reduction in variety continuous process become suitable. The following figure indicates the

    choice of process as a function of repetitiveness. Degree of repetitiveness is determined by dividing volume of

    goods by variety.

    b) Capacity of the plant: Projected sales volume is the key factor to make a choice between batch and line

    process. In case of line process, fixed costs are substantially higher than variable costs. The reverse is

    true for batch process thus at low volume it would be cheaper to install and maintain a batch process and line

    process becomes economical at higher volumes.

    c) Lead time: - The continuous process normally yields faster deliveries as compared to batch process.

    Therefore lead-time and level of competition certainly influence the choice of production process.

    d) Flexibility and Efficiency: - The manufacturing process needs to be flexible enough to adapt

    contemplated changes and volume of production should be large enough to lower costs.

    Hence it is very important for entrepreneur to consider all above mentioned factors before taking a

    48

  • 8/2/2019 Cours File-Industrial Management(2)

    49/157

    decision regarding the type of manufacturing process to be adopted as for as SSI are concerned they usually

    adopt batch processes due to low investment.

    Production Planning And Control Can Facilitate The Small Entrepreneur In The Following Ways

    (1) Optimum Utilisation of Capacity: With the help of Production Planning and Control [PPC] the

    entrepreneur can schedule his tasks and production runs and thereby ensure that his productive capacity does

    not remain idle and there is no undue queuing up of tasks via proper allocation of tasks to the production

    facilities. No order goes unattended and no machine remains idle.

    (2) Inventory control: Proper PPC will help th entrepreneur to resort to just- in- time systems and thereby

    reduce the overall inventory. It will enable him to ensure that the right supplies are available at the right time.

    (3) Economy in production time: PPC will help the entrepreneur to reduce the cycle time and increase the

    turnover via proper scheduling.

    (4) Ensure quality: A good PPC will provide for adherence to the quality standards so that quality of output is

    ensured.

    To sum up we may say that PPC is of immense value to the entrepreneur in capacity utilization and inventory

    control. More importantly it improves his response time and quality. As such effective PPC contributes to time,

    quality and cost parameters of entrepreneurial success.

    PRODUCTION PLANNING AND CONTROL

    Once the entrepreneur has taken the decisions regarding the product design and production processes

    and system, his next task is to take steps for production planning and control, as this function is

    essentially required for efficient and economical production. One of the major problems of small scale

    enterprises is that of low productivity small scale industries can utilise natural resources, which are otherwise

    lying.

    Planned production is an important feature of the small industry. The small entrepreneur possessing the

    ability to look ahead, organize and coordinate and having plenty of driving force and capacity to lead

    and ability to supervise and coordinate work and simulates his associates by means of a programme of

    human relation and organization of employees, he would be able to get the best out of his small industrial unit.

    49

  • 8/2/2019 Cours File-Industrial Management(2)

    50/157

    Gorden and Carson observe production; planning and control involve generally the organization and

    planning of manufacturing process. Especially it consists of the planning of routing, scheduling, dispatching

    inspection, and coordination, control of materials, methods machines, tools and operating times. The

    ultimate objective is the organization of the supply and movement of materials and labour, machines utilization

    and related activities, in order to bring about the desired manufacturing results in terms of quality,

    quantity, time and place.

    Production planning without production control is like a bank without a bank manager, planning initiates

    action while control is an adjusting process, providing corrective measures for planned development.

    Production control regulates and stimulates the orderly how of materials in the manufacturing process

    from the beginning to the end.

    STEPS OF PRODUCTION PLANNING AND CONTROL

    Production Planning and Control (PPC) is a process that comprises the performance of some critical;

    functions on either side, viz., planning as well as control.

    Production planning: Production planning may be defined as the technique of foreseeing every step in

    a long series of separate operations, each step to be taken at the right time and in the right place and

    each operation to be performed in maximum efficiency. It helps entrepreneur to work out the quantity

    of material manpower, machine and money requires for producing predetermined level of output in

    given period of time.

    Routing: Under this, the operations, their path and sequence are established. To perform these

    operations the proper class of machines and personnel required are also worked out. The main aim of

    routing is to determine the best and cheapest sequence of operations and to ensure that this sequence is

    strictly followed. In small enterprises, this job is usually done by entrepreneur in self in a rather adhocmanner. Routing procedure involves following different activities.

    (1) An analysis of the article to determine what to make and what to buy.

    (2) To determine the quality and type of material

    (3) Determining the manufacturing operations and their sequence.

    (4) A determination of lot sizes

    50

  • 8/2/2019 Cours File-Industrial Management(2)

    51/157

    (5) Determination of scrap factors

    (6) An analysis of cost of the article

    (7) Organization of production control forms.

    Scheduling: It means working out of time that should be required to perform each operation and also

    the time necessary to perform the entire series as routed, making allowances for all factors concerned. It

    mainly concerns with time element and priorities of a job. The pattern of scheduling differs from one

    job to another which is explained as below:

    Production schedule: The main aim is to schedule that amount of work which can easily be handled by

    plant and equipment without interference. Its not independent decision as it takes into account following

    factors.

    (1) Physical plant facilities of the type required to process the material being scheduled.

    (2) Personnel who possess the desired skills and experience to operate the equipment and perform the

    type of work involved.

    (3) Necessary materials and purchased parts.

    51

  • 8/2/2019 Cours File-Industrial Management(2)

    52/157

    Master Schedule: Scheduling usually starts with preparation of master schedule which is weekly or

    monthly break-down of the production requirement for each product for a definite time period, by

    having this as a running record of total production requirements the entrepreneur is in better position to

    shift the production from one product to another as per the changed production requirements. This

    forms a base for all subsequent scheduling acclivities. A master schedule is followed by operator

    schedule which fixes total time required to do a piece of work with a given machine or which shows the

    time required to do each detailed operation of a given job with a given machine or process.

    Manufacturing schedule: It is prepared on the basis of type of manufacturing process involved. It is

    very useful where single or few products are manufactured repeatedly at regular intervals. Thus it

    would show the required quality of each product and sequence in which the same to be operated

    Scheduling of Job order manufacturing: Scheduling acquires greater importance in job order

    manufacturing. This will enable the speedy execution of job at each center point. As far as small scale

    industry is concerned scheduling is of utmost importance as it brings out efficiency in the operations

    and s reduces cost price. The small entrepreneur should maintain four types of schedules to have a close

    scrutiny of all stages namely an enquiry schedule, a production schedule, a shop schedule and an arrears

    schedule out of above four, a shop schedule is the most important most suited to the needs of small

    scale industry as it enables a foreman to see at a glance.

    1. The total load on any section

    2. The operational sequence

    3. The stage, which any job has reached.

    Loading: The next step is the execution of the schedule plan as per the route chalked out it includes the

    assignment of the work to the operators at their machines or work places. So loading determines who

    will do the work as routing determines where and scheduling determines when it shall be done. Gantt

    Charts are most commonly used in small industries in order to determine the existing load and also to

    foresee how fast a job can be done. The usefulness of their technique lies in the fact that they compare

    what has been done and what ought to have been done. Most of a small scale enterprise fail due to non-

    adherence to delivery schedules therefore they can be successful if they have ability to meet delivery

    order in time which no doubt depends upon production of quality goods in right time. It makes all themore important for entrepreneur to judge ahead of time what should be done, where and when thus to

    leave nothing to chance once the work has begun.

    Production control: Production control is the process of planning production in advance of operations,

    establishing the extract route of each individual item part or assembly, setting, starting and finishing for

    each important item, assembly or the finishing production and releasing the necessary orders as well as

    52

  • 8/2/2019 Cours File-Industrial Management(2)

    53/157

    initiating the necessary follow-up to have the smooth function of the enterprise. The production control

    is of complicated nature in small industries. The production planning and control department can

    function at its best in small scale unit only when the work manager, the purchase manager, the

    personnel manager and the financial controller assist in planning production activities. The production

    controller directly reports to the works manager but in small scale unit, all the three functions namely

    material control, planning and control are often performed by the entrepreneur himself production

    control starts with dispatching and ends up with corrective actions.

    Dispatching: Dispatching involves issue of production orders for starting the operations. Necessary

    authority and conformation is given for:

    1. Movement of materials to different workstations.

    2. Movement of tools and fixtures necessary for each operation.

    3. Beginning of work on each operation.

    4. Recording of time and cost involved in each operation.

    5. Movement of work from one operation to another in accordance with the route sheet.

    6. Inspecting or supervision of work

    Dispatching is an important step as it translates production plans into production.

    Follow up: Every production programme involves determination of the progress of work, removing

    bottlenecks in the flow of work and ensuring that the productive operations are taking place in

    accordance with the plans. It spots delays or deviations from the production plans. It helps to reveal

    detects in routing and scheduling, misunderstanding of orders and instruction, under loading or

    overloading of work etc. All problems or deviations are investigated and remedial measurer are

    undertaken to ensure the completion of work by the planned date.

    Inspection: This is mainly to ensure the quality of goods. It can be required as effective agency of

    production control.

    Corrective measures: Corrective action may involve any of those activities of adjusting the route,

    rescheduling of work changing the workloads, repairs and maintenance of machinery or equipment,

    control over inventories of the cause of deviation is the poor performance of the employees. Certain

    personnel decisions like training, transfer, demotion etc. may have to be taken. Alternate methods maybe suggested to handle peak loads.

    53

  • 8/2/2019 Cours File-Industrial Management(2)

    54/157

    REQUIREMENTS ANALYSIS

    Requirements analysis in systems engineering and software engineering, encompasses those tasks that go into

    determining