Country Presentation. Ukraine Presentation. Ukraine 25thMeeting of the IAEA Technical Working Group...
Transcript of Country Presentation. Ukraine Presentation. Ukraine 25thMeeting of the IAEA Technical Working Group...
Country Presentation. Ukraine
25th Meeting of the IAEA Technical Working Group on Nuclear
Power Plant Instrumеntation and Control (TWG -NPPIC)
May 27-29, 2015, Vienna, Austria
Vladimir Sklyar, RPC Radiy
2
TOP5 of Europe
TOP10 of the World
About 50% of national power
generation
One utility:
national company NAEC
“Energoatom”
http://www.energoatom.kiev.ua/
Regulatory Authority: State Nuclear
Regulatory Inspectorate of Ukraine
http://www.snrc.gov.ua/nuclear
Ukrainian NPPs. Fast factsTotal Gross Capacity: 13,835 MW
4 sites
15 units
2 units under construction
South-Ukrainian NPP
3×VVER-1000
Khmelnitsky NPP2×VVER-1000
2×VVER-1000
under construction
Rivne NPP
2×VVER-1000
2×VVER-440
Kyiv
Zaporizhzhya NPP –
The biggest NPP in Europe
6×VVER-1000
May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Ukrainian NPPs. Fleet details
Site, Unit Capacity, MW Unit type Commissioning year Decommissioning year
Zaporizhzhya NPP
1
2
3
4
5
6
1000
1000
1000
1000
1000
1000
V-320
V-320
V-320
V-320
V-320
V-320
1984 (1985)
1985 (1986)
1986 (1987)
1987 (1988)
1989 (1990)
1995 (1996)
2015
2016
2017
2018
2020
2026
South-Ukrainian NPP
1
2
3
1000
1000
1000
V-302
V-338
V-320
1982
1985
1989
2012 → 2023
2015 → 2025
2019
Rivne NPP
1
2
3
4
420
415
1000
1000
V-213
V-213
V-320
V-320
1980
1981
1986 (1987)
2004 (2005)
2010 → 2030
2011 → 2031
2017
2035
Khmelnitsky NPP
1
2
3
4
1000
1000
1000
1000
V-320
V-320
V-320
V-320
1987 (1988)
2004 (2005)
-
-
2018
2035
-
-
3May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
� Running of Consolidated program of increased safety of Ukrainian NPP units
(December 2011) with financial issues update (September 2013); Term of program is
2012-2017
� Life extension permission for Unit 1, South-Ukraine NPP (commissioned in 1982) has
been issued in December 2013; an operation has been extended for 10 additional years
(2023)
� Actions for life extension for Unit 2, South-Ukraine NPP (commissioned in 1985, shut
downed on May 10, 2015); a plan is to extend operation for 10 additional years (2025)
� Actions for life extension for Unit 1, Zaporizhzhya NPP (commissioned in 1984,
industrial operation since 2015, shut down deadline is December 2015).
� A strategy for new builds Khmelnitsky 3,4 has been changed
� Adaptation of IEC nuclear standards to Ukrainian needs
� EBRD’s Nuclear Power Plant Safety Upgrade Program is starting
Ukrainian NPPs. What has been new since 2013?
4May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Peculiarities of FPGA from the point of view of licensing (2)� Impulse, Severodonetsk
�Design, manufacturing and installation of new types of I&C systems (PAMS etc.)
�Westron, Kharkiv
�Design and installation of new HMI (symptom-based operator procedures etc.)
�Manometr-Kharkiv
�Enforcement activities at international markets
�Radiy, Kirovograd
�Certification of FPGA-based safety platform RadICS against functional safety requirements of IEC 61508 (SIL3)
� Initiation of the U.S. NRC application process for FPGA-based safety platform RadICS
5May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Ukrainian I&C vendors. What has been new since 2013?
1. I&C modernization projects in operating NPPs.
2. I&C systems being installed in NPPs under
construction.
3. Country's plan to build new NPPs.
I&C technologies in new NPP designs.
4. I&C research and development projects.
New I&C technologies.
5. Recommendation to the IAEA regarding the
content and format of future I&C activities.
Presentation Agenda
6May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
I&C modernization projects in operating NPPs
7May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
� Life cycle extension (from 30
to 40 or 50 years).
� NPP safety improvement.
Consolidated program of
increased safety of Ukrainian
NPP units was approved in
December 2011.
NPP I&C systems modernization reasons
8May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Systems modernization (in accordance with
Consolidated program of increased safety of Ukrainian NPP units) (1)
� #14201. Prevention of ESFAS and Reactor Trip System
Common Cause Failure due to absence of physical separation
of impulse lines.
� #14202. Modernization of Neutron Flux Monitoring Systems.
� #14203. Modernization of Reactor Trip Systems.
� #14204. Modernization of Reactor Power Control and Limitation
System.
� #14205. Modernization of Rod Control Systems, including
Electric Power Supply System of Rod Drives.
� #14206. Modernization of Rod Drives including electromagnet
modules and position detectors.
� #14301. Modernization of ESFAS.
9May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
� #14101. Instrumentation assurance during accidents.
� #14102. Implementation of systems for pipe position monitoring
in the primary loop.
� #14103. Modernization Process Information Systems (PIS) and
their integration with Radiation Monitoring System and SPDS.
� #14104. Modernization of systems for hydrogen cooling
monitoring of generator.
� #14105. Modernization of Reactor Island Control System of
Normal Operation.
� #14106. Modernization of Conventional Island Control System of
Normal Operation.
10
Systems modernization (in accordance with
Consolidated program of increased safety of Ukrainian NPP units) (2)
May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
� #14401. Modernization of Radiation Monitoring Systems.
� #14402. Modernization of In-Core Monitoring Systems with
implemented reactor simulator and extended core monitoring
and diagnostics.
� #14403. PAMS implementation.
� #14404. Modernization of Diesel Generators Control Systems.
� #14405. Modernization of Control System for Refueling Machine.
� #14406. Modernization of Chemical Monitoring System.
� #14407. Modernization of turbine control systems.
11
Systems modernization (in accordance with
Consolidated program of increased safety of Ukrainian NPP units) (3)
May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
� Reason for modernization: to extend life
cycle of units for additional 10 years
� Outage was started in March 2013
� Regulatory decision was expected in
October 2013
� Involved I&C vendors: Radiy (Ukraine)
and Westron (Ukraine).
� Safety I&C systems was modernized by
2011, non-safety I&C systems was
modernized during 2012-2013
� Licensing permission for extra 10 years
(to 2023) was issued in December 2013
12
Large I&C modernization project:
NPP South-Ukrainian-1 (VVER-1000) life extension (1)
May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Modernization scope (1):
� Reactor Trip System,
� Neutron Flux Monitoring System,
� Rod Control System,
� Reactor Power Control and
Limitation System,
� Engineered Safety Features
Actuation System,
� Sensors and transmitters
replacement,
� Cables replacement.
13
Large I&C modernization project:
NPP South-Ukrainian-1 (VVER-1000) life extension (2)
May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Modernization scope (2):
� MCR & ECR,
� Electric Power Supply Systems
replacement,
� Reactor Island System of Normal
Operation,
� Conventional Island System of
Normal Operation,
� Diesel Generator Control System,
� Radiation Monitoring System,
� Post Accident Monitoring System.
14
Large I&C modernization project:
NPP South-Ukrainian-1 (VVER-1000) life extension (3)
May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Switchgears modernization
15
Large I&C modernization project:
NPP South-Ukrainian-1 (VVER-1000) life extension (4)
May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
� Reason for modernization: to extend life
cycle of units for additional 10 years
� Safety Evaluation Report has been issued
in March 2015
� Outage has been started in May 2015
� Regulatory decision is expected in
December 2015
� Involved I&C vendors: Impuls (Ukraine),
Radiy (Ukraine) and Westron (Ukraine).
� I&C systems were modernized during
2005-2014
� Turbine Island Control System will be
modernized during the actual outage
16
Large I&C modernization project:
NPP South-Ukrainian-2 (VVER-1000) life extension
May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Peculiarities of FPGA from the point of view of licensing (2)
� Increase safety of the NPP
� Increase NPP availability
�Assure long-term operation
� Improve human-machine interface for control, diagnostic and maintenance
� Improve of electrical and physical separation between safety divisions
�Assure lifetime service and maintenance
�Comply with regulatory requirements
�Assure fast implementation of modernization project
�Assure minimization of on-site premises reconfiguration
17May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Large I&C modernization project:
Main targets
Country's plan to build new
NPPs.
I&C technologies in new NPP
designs
Khmelnitsky NPP, Units 3
Khmelnitsky NPP, Units 4
18May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
� Originally there was a plan to build four VVER-1000 units at
Khmelnitsky NPP site.
� Units 3 and 4 building was stopped in 1990 in accordance with
Ukrainian Moratorium to build new NPPs.
� Construction of units was in 1990: Unit 3 – 75%, Unit 4 – 28%.
� June 2005 – Government Regulation on preparation to build
new units.
� 2006-2007 – technical analysis of Units 3,4 was performed by
KIEP (Ukrainian design company).
� January 2011 – Ukraine with Russia signed an agreement for
cooperation to build Units 3 and 4 (VVER-1000 / V-392).
Khmelnitsky NPP, Units 3,4. History
19May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
� Reactor unit equipment PWR-100 / V-320, Skoda JS.
� The upgraded turbine K 1000 60/1500 2M, Turboatom.
� Project proposal includes all modifications and improvements of
PWR-100 / V-320 baseline design , implemented at the NPP Temelin
in order to bring the safety level to the rate of nuclear industry
international standards
� Power supply units construction without sacrificing of conceptual
layout arrangements for the main building and usage of existing
building structures with consideration of repair and renewal
operations as defined by the results of technical condition survey and
evaluation
Khmelnitsky NPP, Units 3,4. Actual Status
20May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
I&C research and development projects.
New I&C technologies
21May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
FPGA Technology issues (1)
� About 50 FPGA-based Applications have been
installed at Ukrainian NPPs since 2004 (Reactor
Trip Systems, Neutron Flux Monitoring System,
Rector Power Control and Limitation Systems,
Reactor Control Systems, ESFAS, Reactor and
Conventional Island Control Systems of Normal
Operation).
� 6 FPGA-based ESFASs have been commissioned
at Kozloduy-5,6 (Bulgaria) during 2008-2010 by
Ukrainian vendor.
� Two FPGA-based products for Embalse (Argentina)
has been deliver by Ukrainian vendor in
cooperation with Candu Enegy Inc. in 2013-2014.
22May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
FPGA Technology issues (2)
� Operation experience learning.
� Experience transfer for CANDU and another types of reactors (not only
PWR).
� Improvement of regulations and procedures concerning FPGA-based
platforms and applications development, V&V, operation and licensing.
� Implementation of SIL (IEC 61508:2010) and IEC 62566:2011 based
approach to qualification of FPGA-based platforms and applications.
� Participation in development of IAEA technical document related to
application of FPGAs in NPP I&C systems.
� Learning cybersecurity issues of FPGA-based systems.
23May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Diversity issues (1)
� Ukrainian regulations
requires to implement
diversity for Reactor Trip
System.
� Original VVER-1000
design included two
redundant RTS trains
with three channels in
each train.
� Original VVER-440
design included one RTS
train with three channels.
� RPC Radiy is the sole
national vendor of RTS.
24May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Diversity issues (2)
� A regulatory decision was made to
implement the main RTS and the
diverse RTS from the same
vendor (FPGAs vs FPGAs+CPUs).
� Since 2004 RTSs have been
modernized for 15 Ukrainian NPP
units (for both VVER-1000 and
VVER-440).
� No Common Cause Failure in
modernized RTS.
� Implementation of RTS diversity
with using of SIL3 certified
platform
25May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Cybersecurity issues
� State Nuclear Regulatory Inspectorate of Ukraine
includes both:
�Department of safety regulation of nuclear
installations (responsibilities for I&C systems
safety regulation),
�Department of security regulation.
� New Ukrainian safety and security regulations were
approved in 2008 and 2010.
� Ukrainian cybersecurity regulations are uder
development.
� Cybersecurity regulation adoption is possible only in
cooperation between the above two departments.
26May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
Chernobyl issues
� The Ark building is in progress
� A stage of Final Closing and
Conservation is permitted to start
in 2015 (expected target time is
2028)
27May 27-29, 2015 | 25th Meeting of IAEA TWG -NPPIC,
Vienna
May 22-24, 2013 | 24th Meeting of IAEA TWG -NPPIC,
Vienna
Recommendation to the IAEA regarding the content and
format of future I&C activities
� “Peopleware” support and development:
� Knowledge management for safety culture supporting,
� Key Performance Indicators (KPIs) for knowledge management assessment.
� Harmonization of standards requirements and regulations, safety classifications,
definitions.
� Information management and sharing:
� Experts communications development and improvement,
� Awareness about best practices and success stories in new I&C
technologies implementations (FPGAs, wireless etc.).
� Cybersecurity:
� Safety – Security relations,
� Cybersecurity defensive measures.
28
Thank you for your attention!
Research & Production Corporation Radiy
29, Geroyiv Stalingrada Street, Kirovograd 25006, Ukraine
e-mail: [email protected]
http://www.radiy.com