Date : October 1, 2012Project : Sea Residences Phase 1Subject : COST BREAKDOWN
COST BREAKDOWN FOR PAPER SCREEN INSTALLATION AT TOWERS A AND B
ITEM DESCRIPTIONAPG PROPOSAL DCI EVALUATION RECONCILED
QTY UNIT UNIT COST AMOUNT QTY UNIT UNIT COST AMOUNT QTY UNIT UNIT COST AMOUNT
A. 8.86 m² Php 316.44 Php 2,803.66 5.38 m² Php 316.44 Php 1,702.45 5.38 m² Php 316.44 Php 1,702.45
B.
1. Tower A. 1.4m x 2.20m 4.52 m²2. Tower B. 1.4m x 2.10m 4.34 m² Php 3,037.01 Php 13,180.62 0.72 m² Php 3,037.01 Php 2,186.65 0.72 m² Php 3,037.01 Php 2,186.65
C. Painting of Niche 0.90 m² Php 3,037.01 Php 2,733.31 0.81 m² Php 3,037.01 Php 2,459.98 0.81 m² Php 3,037.01 Php 2,459.98
Total Amount (Additive) Php20,963.70 Php 6,349.08 Php 6,349.08
Prepared by:Design Coordinates, Inc.Construction Project Managers
Gerry V. LiwagConstruction Project Engineer
Noted by:Design Coordinates, Inc.Construction Project Managers
Cid V. OrbetaConstruction Project Manager
Confome:
Melchor A. B. TinioAPG Designs
Dismantling and preparation of drywall, ready to receive nicheFabrication of niche including angular support, ready to receive paper screen
Cost Breakdown
Date : October 1, 2012Project : Sea Residences Phase 1Subject : COST BREAKDOWN
COST BREAKDOWN FOR ELEVATOR CAR FIT OUT OF TOWERS A AND B
ITEM DESCRIPTIONAPG PROPOSAL DCI EVALUATION RECONCILED
QTY UNIT UNIT COST AMOUNT QTY UNIT UNIT COST AMOUNT QTY UNIT UNIT COST AMOUNT
A. WALLS
82.00 ft² Php 366.13 Php 30,022.66 80.50 ft² Php 366.13 Php 29,473.47 80.50 ft² Php 366.13 Php 29,473.47 2. Supply and installation of new tint
22.00 ft² Php 513.37 Php 11,294.14 21.50 ft² Php 513.37 Php 11,037.46 21.50 ft² Php 513.37 Php 11,037.46
B. FLOOR
17.92 m² Php 106.66 Php 1,911.35 17.92 m² Php 106.66 Php 1,911.35 17.92 m² Php 106.66 Php 1,911.35
C. OTHERS
1.00 lot Php 2,500.00 Php 2,500.00 1.00 lot Php 2,000.00 Php 2,000.00 1.00 lot Php 2,000.00 Php 2,000.00
Total Amount (Additive) Php51,215.52 Php44,422.27 Php44,422.27
Prepared by:Design Coordinates, Inc.Construction Project Managers
Gerry V. LiwagConstruction Project Engineer
Noted by:Design Coordinates, Inc.Construction Project Managers
Cid V. OrbetaConstruction Project Manager
Confome:
Melchor A. B. TinioAPG Designs
1. Scraping of existing damaged tint including cleaning and preparation
3. Scraping off existing damaged sticker accent
4. Cleaning and regrouting of existing floor tiles
5. Improvement of padded leatherette hanger support at service elevator
Cost Breakdown