Costing of Paperscreen Installation of Tower a and b

4
Date : October 1, 2012 Project : Sea Residences Phase 1 Subject : COST BREAKDOWN COST BREAKDOWN FOR PAPER SCREEN INSTALLATION AT TOWERS A AND B ITEM DESCRIPTION APG PROPOSAL DCI EVALUATION QTY UNIT UNIT COST AMOUNT QTY UNIT UNIT COST AMOUNT QTY UNIT A. 8.86 Php 316.44 Php 2,803.66 5.38 Php 316.44 Php 1,702.45 5.38 B. 1. Tower A. 1.4m x 2.20m 4.52 2. Tower B. 1.4m x 2.10m 4.34 Php 3,037.01 Php 13,180.62 0.72 Php 3,037.01 Php 2,186.65 0.72 C. Painting of Niche 0.90 Php 3,037.01 Php 2,733.31 0.81 Php 3,037.01 Php 2,459.98 0.81 Total Amount (Additive) Php 20,963.70 Php 6,349.08 Prepared by: Design Coordinates, Inc. Construction Project Managers Gerry V. Liwag Construction Project Engineer Noted by: Design Coordinates, Inc. Construction Project Managers Cid V. Orbeta Construction Project Manager Confome: Melchor A. B. Tinio APG Designs Dismantling and preparation of drywall, ready to receive niche Fabrication of niche including angular support, ready to receive paper screen C

description

a

Transcript of Costing of Paperscreen Installation of Tower a and b

Page 1: Costing of Paperscreen Installation of Tower a and b

Date : October 1, 2012Project : Sea Residences Phase 1Subject : COST BREAKDOWN

COST BREAKDOWN FOR PAPER SCREEN INSTALLATION AT TOWERS A AND B

ITEM DESCRIPTIONAPG PROPOSAL DCI EVALUATION RECONCILED

QTY UNIT UNIT COST AMOUNT QTY UNIT UNIT COST AMOUNT QTY UNIT UNIT COST AMOUNT

A. 8.86 m² Php 316.44 Php 2,803.66 5.38 m² Php 316.44 Php 1,702.45 5.38 m² Php 316.44 Php 1,702.45

B.

1. Tower A. 1.4m x 2.20m 4.52 m²2. Tower B. 1.4m x 2.10m 4.34 m² Php 3,037.01 Php 13,180.62 0.72 m² Php 3,037.01 Php 2,186.65 0.72 m² Php 3,037.01 Php 2,186.65

C. Painting of Niche 0.90 m² Php 3,037.01 Php 2,733.31 0.81 m² Php 3,037.01 Php 2,459.98 0.81 m² Php 3,037.01 Php 2,459.98

Total Amount (Additive) Php20,963.70 Php 6,349.08 Php 6,349.08

Prepared by:Design Coordinates, Inc.Construction Project Managers

Gerry V. LiwagConstruction Project Engineer

Noted by:Design Coordinates, Inc.Construction Project Managers

Cid V. OrbetaConstruction Project Manager

Confome:

Melchor A. B. TinioAPG Designs

Dismantling and preparation of drywall, ready to receive nicheFabrication of niche including angular support, ready to receive paper screen

Cost Breakdown

Page 2: Costing of Paperscreen Installation of Tower a and b

Date : October 1, 2012Project : Sea Residences Phase 1Subject : COST BREAKDOWN

COST BREAKDOWN FOR ELEVATOR CAR FIT OUT OF TOWERS A AND B

ITEM DESCRIPTIONAPG PROPOSAL DCI EVALUATION RECONCILED

QTY UNIT UNIT COST AMOUNT QTY UNIT UNIT COST AMOUNT QTY UNIT UNIT COST AMOUNT

A. WALLS

82.00 ft² Php 366.13 Php 30,022.66 80.50 ft² Php 366.13 Php 29,473.47 80.50 ft² Php 366.13 Php 29,473.47 2. Supply and installation of new tint

22.00 ft² Php 513.37 Php 11,294.14 21.50 ft² Php 513.37 Php 11,037.46 21.50 ft² Php 513.37 Php 11,037.46

B. FLOOR

17.92 m² Php 106.66 Php 1,911.35 17.92 m² Php 106.66 Php 1,911.35 17.92 m² Php 106.66 Php 1,911.35

C. OTHERS

1.00 lot Php 2,500.00 Php 2,500.00 1.00 lot Php 2,000.00 Php 2,000.00 1.00 lot Php 2,000.00 Php 2,000.00

Total Amount (Additive) Php51,215.52 Php44,422.27 Php44,422.27

Prepared by:Design Coordinates, Inc.Construction Project Managers

Gerry V. LiwagConstruction Project Engineer

Noted by:Design Coordinates, Inc.Construction Project Managers

Cid V. OrbetaConstruction Project Manager

Confome:

Melchor A. B. TinioAPG Designs

1. Scraping of existing damaged tint including cleaning and preparation

3. Scraping off existing damaged sticker accent

4. Cleaning and regrouting of existing floor tiles

5. Improvement of padded leatherette hanger support at service elevator

Cost Breakdown