COST ESTIMATION SHEET
PROJECT : HYDRAULIC ROBOT (JCB)
NAME OF PART: BASE PLATE (18 MM)
PART NO:1
CLASS: MECHANICAL (6 TH SEM / 2NDSHIFT)
YEAR:2010 -2011
MATERIAL : WOOD
MATERIAL COST
LENGTH *WIDTH 3*2RATE/MM 44QTY 1TOTAL 260
MACHINING COST
PROCESS COST/ HOUR MINS NET COST
CUTTING 20 60 20SLOTTING 10 15 10DRILLINGTOTAL 75 30
LABOUR COST
LABOUR COST 50
TRANSPROTATION COST
TRANSPROTATION 20
(ALL DIMENSION IN FOOT)
COST ESTIMATION SHEET
PROJECT : HYDRAULIC ROBOT (JCB)
NAME OF PART: CIRCULER LINK(12MM)
PART NO:2
CLASS: MECHANICAL (6 TH SEM / 2NDSHIFT)
YEAR:2010 -2011
MATERIAL : WOOD
MATERIAL COST
LENGTH *WIDTH 2*2RATE/MM 45QTY 1TOTAL 180
MACHINING COST
PROCESS COST/ HOUR MINS NET COST
CUTTING 20 60 20TURNING 10 15 10DRILLINGTOTAL 75 30
LABOUR COST
LABOUR COST 50
TRANSPROTATION COST
TRANSPROTATION 20
(ALL DIMENSION IN FOOT)
COST ESTIMATION SHEETPROJECT : HYDRAULIC ROBOT (JCB)
NAME OF PART: VERTICAL LINK (18MM)
PART NO:3
CLASS: MECHANICAL (6 TH SEM / 2NDSHIFT)
YEAR:2010 -2011
MATERIAL : WOOD
MATERIAL COST
LENGTH *WIDTH 3*3RATE/MM 60QTY 2TOTAL 540
MACHINING COST
PROCESS COST/ HOUR MINS NET COST
CUTTING 20 60 20DRILLINGTOTAL 60 20
LABOUR COST
LABOUR COST 50
TRANSPROTATION COST
TRANSPROTATION 20
(ALL DIMENSION IN FOOT)
COST ESTIMATION SHEETPROJECT : HYDRAULIC ROBOT (JCB)
NAME OF PART: HORIZONTAL LINK-1 (8MM)
PART NO:4
CLASS: MECHANICAL (6 TH SEM / 2NDSHIFT)
YEAR:2010 -2011
MATERIAL : WOOD
MATERIAL COST
LENGTH *WIDTH 3*3RATE/MM 27QTY 2TOTAL 245
MACHINING COST
PROCESS COST/ HOUR MINS NET COST
CUTTING 20 60 20DRILLINGTOTAL 60 20
LABOUR COST
LABOUR COST 50
TRANSPROTATION COST
TRANSPROTATION 20
(ALL DIMENSION IN FOOT)
COST ESTIMATION SHEETPROJECT : HYDRAULIC ROBOT (JCB)
NAME OF PART: HORIZONTAL LINK-2 (6MM)
PART NO:5
CLASS: MECHANICAL (6 TH SEM / 2NDSHIFT)
YEAR:2010 -2011
MATERIAL : WOOD
MATERIAL COST
LENGTH *WIDTH 3*3RATE/MM 23QTY 2TOTAL 210
MACHINING COST
PROCESS COST/ HOUR MINS NET COST
CUTTING 20 60 20DRILLINGTOTAL 60 20
LABOUR COST
LABOUR COST 50
TRANSPROTATION COST
TRANSPROTATION 20
(ALL DIMENSION IN FOOT)
COST ESTIMATION SHEETPROJECT : HYDRAULIC ROBOT (JCB)
NAME OF PART: TOOL LINK-1(6MM)
PART NO:6
CLASS: MECHANICAL (6 TH SEM / 2NDSHIFT)
YEAR:2010 -2011
MATERIAL : WOOD
MATERIAL COST
LENGTH *WIDTH 2*2RATE/MM 7QTY 2TOTAL 30
MACHINING COST
PROCESS COST/ HOUR MINS NET COST
CUTTING 20 60 20SHAPING 20 15 20DRILLINGTOTAL 75 40
LABOUR COST
LABOUR COST 50
TRANSPROTATION COST
TRANSPROTATION 20
(ALL DIMENSION IN FOOT)
COST ESTIMATION SHEETPROJECT : HYDRAULIC ROBOT (JCB)
NAME OF PART: TOOL LINK-2 (6MM)
PART NO: 7
CLASS: MECHANICAL (6 TH SEM / 2NDSHIFT)
YEAR:2010 -2011
MATERIAL : WOOD
MATERIAL COST
LENGTH *WIDTH 0.5*0.5RATE/MM 7QTY 2TOTAL 30
MACHINING COST
PROCESS COST/ HOUR MINS NET COST
CUTTING 20 30 20DRILLINGTOTAL 30 20
LABOUR COST
LABOUR COST 50
TRANSPROTATION COST
TRANSPROTATION 20
(ALL DIMENSION IN FOOT)
COST ESTIMATION SHEETPROJECT : HYDRAULIC ROBOT (JCB)
NAME OF PART: CONNECTING LINK-1/2 (6MM)
PART NO:8
CLASS: MECHANICAL (6 TH SEM / 2NDSHIFT)
YEAR:2010 -2011
MATERIAL : WOOD
MATERIAL COST
LENGTH *WIDTH 1*1RATE/MM 7QTY 4TOTAL 45
MACHINING COST
PROCESS COST/ HOUR MINS NET COST
CUTTING 20 60 20DRILLINGTOTAL 60 20
LABOUR COST
LABOUR COST 50
TRANSPROTATION COST
TRANSPROTATION 20
(ALL DIMENSION IN FOOT)
COST ESTIMATION SHEET
PURCHASED PART ESTIMATION SHEET
PURCHASED MATERIAL QTY RS
SMALL GEAR PLASTIC 1 30
BIG GEAR PLASTIC 2 120
THREADED SHAFT M.S. 12 200
RACK PLASTIC 2 30
SYRINGE FIBER 12 350
FLEXIBLE PIPE (HARD) P.V.C 6 FOOT 60
BOLT NUT AND OTHER FASTERNES M.S. AS PER USE 30
HOOK M.S. 10 50
TOTAL 870