COSTCO, SAN FRANCISCO - Cal Poly
Transcript of COSTCO, SAN FRANCISCO - Cal Poly
COSTCO, SAN FRANCISCOA PRESCRIPTIVE AND PERFORMANCE BASED ANALYSIS OF FIRE PROTECTION SYSTEMS AND DESIGN
Presented by Ian LevineJune, 2016
Photo courtesy of Google Maps
PRESENTATION OVERVIEW
BUILDING DESCRIPTION
STRUCTURAL DESIGN
ALARM AND DETECTION
EGRESS
SPRINKLER SYSTEM ANALYSIS
PERFORMANCE BASED ANALYSIS
Photo credit to FrenchiesGigiandLola via youtube
Photo courtesy of Google Maps
BUILDING OVERVIEW
TRUE NORTHPLAN NORTH
• Mixed OccupancyMercantileHigh Piled StorageRestaurantKitchen, BakeryOffice
• ConstructionConcrete slabExposed, noncombustible
• Area: 122,000 sq.ft.• Ceiling Height: 30 ft.• Open floor plan
Satellite Image courtesy of Google Maps
3
Presented by Ian LevineWinter 2016
Photo courtesy of Google Maps
A LOOK INSIDE
Concrete floor
Rack storage
Wide aisles
Steel deck
Steel open web truss
Wide flange steel column
Details shown typical of all Costco stores
Steel wide flange beam
4
Draft curtains
Ventilation
Presented by Ian LevineWinter 2016
Photo courtesy of Google Maps
STRUCTURAL DESIGN: What type of construction is allowed for this 122,000 sq.ft. structure?
Building Area: 122,000 sq.ft.Factor of increase based on frontage and automatic fire protection: 3.48
Maximum floor area per IBC 2012 Table 503:35,000 sq.ft.
California Building Code 2012
Allowable construction type: I-A, I-B
5
DETECTION AND ALARM - OVERVIEW
Combination heat/ smoke detector
Backup power source
Horn Strobe Notification Appliance
Central monitoring station
Emergency Response
Fire alarm control panel
Automatic fire sprinkler system
7
DETECTION RESPONSE – ANALYSISHEAT RELEASE RATES OF POTENTIAL FUEL LOADS
SOURCES: SFPE Handbook, 4th ed; AIAA 2000-0722
9
HEAT DETECTOR RESPONSE – DETACT
Response Time = 53sHRR = 1250 kW
Input Parameters
DETACT Results
10
Note: Sprinkler response time = 95sManual pull stations are requiredIs this layout cost effective?
NOTIFICATIONRequired NA sound level:
40 dB + 15 dB = 55 dB(15 dBA above ambient)
Requirement met using 99 dBA alarm (6 dBA Rule)
Required strobe candela intensity per NFPA 72, Table 18.5.5.4.1(b)
Note: EVACS is not recommended for this building
12
DECISION MAKING DURING EGRESS
1. Recognition: Become aware of some danger. (smoke, alarm, seeing fire)
2. Validation: Gather more information (talk to others, look for smoke/fire)
3. Definition: Assess the threat, understand its seriousness
4. Evaluation: Decide how to respond (behaviors of others? Exit locations?)
5. Commitment: Take action
6. Reassessment: If necessary, take additional action. Stress levels rise.
NFPA Fire Protection Handbook, ed. 20
15
SPRINKLER RESPONSE – DETACT
Response Time = 95sHRR = 4500 kW
11
TYCO ELO-231Standard Spray Upright11.2 k-factor¾” orifice
PRESCRIPTIVE APPROACH SUMMARYSTRUCTURAL:• Fire resistance ratings
requirements are satisfied• Foams sprays, protective
membranes, concrete wraps if additional protection is required
A&D:• Heat/Smoke detectors not
required• Manual pull stations
o Occupancy > 500• Horn-strobes spaced to 68 ft
o 6 dB rule• Heat detection by sprinklers
o 53s vs. 95s response time
EGRESS:• Occupant load = 3,208• Egress capacity = 4,340• Total exit time = 4 min
SPRINKLERS:• 4 systems• Extremely high demand• Large orifice sprinklers• System redesign to lower
pressure and flow required from the source
• Pump with secondary water source if necessary
PERFORMANCE BASED DESIGN (PBD)
• Past vs. Future• Specific to building, location, occupancy, and use
NFPA 101 – Life Safety Code (LSC)Goals and Objectives – Prescriptive:
o Protection of occupants not intimate with initial fire development
o Improvement of survivability of occupants intimate with initial fire development
o Added benefit to non-fire emergencies and crowd movement
o Provide occupant protection during time to evacuate, relocate, or defend in place
o Maintain structural integrity
PBD - OVERVIEW• Meet prescriptive goals and objectives
• Limit exposure to “instantaneous or cumulative untenable conditions” (4 methods)
• Establish design specifications, inputs, assumptions, building safety features
• Determine design fireo Realistico Challenging with respect to initial fire location,
early rate of growth in fire severity, and/or smoke generation
• Design Fire Scenarios (8 Scenarios)
PBD FIRE SCENARIO• Performance Criteria: Method 2, LSC
o Complete building evacuation before hot gas layer extends less than 6 ftabove floor (ASET > RSET?)
• Design Scenario: Scenario 2, LSCo Ultrafast-developing fire in the
primary means of egress with interior doors open at the start of the fire
o Focus on reduction in number of means of egress
o Can all occupants escape before being exposed to smoke?
Design Fire: electronics section in front of primary entrance and exit
PBD – EGRESS: NFPA CALCULATION
Methodology and data from NFPA Handbook, 20th edition
Increase by 100: confusion, searching for new exit
Decrease to 0 due to inaccessibility
PBD – EGRESS: PATHFINDER• Calculation of movement time,
not including premovement time• 3208 occupants randomly
spread throughout room• Single doors: 36”• Double doors: 72”• Walls placed around tables,
displays, and racks as obstructions
• All interior doors open
FIRE BLOCKING EXIT
OCCUPANTS
t = 0s
PBD – EGRESS: PATHFINDER• Occupants moving toward doors• Jams occurring at doors
FIRE BLOCKING EXIT
OCCUPANTS
t = 30s
PBD – EGRESS: PATHFINDER• Most occupants have reached an
escape route
FIRE BLOCKING EXIT
OCCUPANTS
t = 60s
PBD – EGRESS: PATHFINDER• All occupants are experiencing
jamming at doors• Floor is completely cleared
FIRE BLOCKING EXIT
t = 120s
PBD – EGRESS: PATHFINDER RESULTS
0
500
1000
1500
2000
2500
3000
3500
0 20 40 60 80 100 120 140 160 180 200
Occ
upan
ts
Time (s)
Occupants Inside Costco During Evacuation OBSERVATIONS• Evacuation complete 3.2 min after begins• Including 1.7 min maximum pre-movement
time and 1.2 factor of safety, total time = 5.3 minutes
• Close agreement with NFPA method results (5.5 min)
Note: linear evacuation rate supports egress time is limited by exit capacity of exits rather than travel time to exits
PBD – CFAST ENVIRONMENT & LAYOUT
MAIN ENTRY AND EXIT
SINGLE-WIDE AND DOUBLE-WIDE EMERGENCY EXITS AROUND PERIMETER
LOCATION OF FIRE
DETECTION DEVICES
DESIGN FIRE – FIRE INPUT PARAMETERSP6 FIRE
• Full scale test• 2 pallets of 12 boxed
computer monitors• 1m x 1m x 1m, side by side• Soot and CO yields from
polystyrene• Ignition using 50-200 kW
line burner• Modeled as t2 fire reaching
steady burning after 25s
SFPE Handbook – Table 3-1.51
PBD – DETECTION AND ALARM
0
100
200
300
400
500
600
700
0 5 10 15 20 25 30 35 40 45 50 55 60
Tem
pera
ture
(⁰C)
Time (s)
Heat Detector Temperatures in Design Fire - CFAST
Hot Gas
Heat Detector 1
Heat Detector 2
Heat Detector 3
Heat Detector 4
HEAT DETECTOR ACTUATION = 5s• Delay has negligible impact on 1.7 min
pre-movement time
PEAK HRR REACHED
STEADY STATE BURNING
DESIGN FIRE – CFAST SIMULATION
T = 0s T = 10s
• Plume develops quickly• Hot gas layer forms immediately
• Initial temperature at 22 ⁰C
DESIGN FIRE – CFAST SIMULATION
• Peak HRR is reached• Temperature of hot gas layer
rapidly increasing• Interface height: 8.87m
T = 20s T = 30s
• Hot gas layer has reached ceiling• Smoke already gathering at the ceiling
DESIGN FIRE – CFAST SIMULATION
• Smoke layer remains high• Interface height: 8.3m• Alarm and pre-movement time
periods have passed. Occupants are now moving to exits. Some have exited already.
T = 60s T = 120s
• Temperature of hot gas layer continues to increase
• Interface height: 8.67m
DESIGN FIRE – CFAST SIMULATION
• Interface height: 7.32m• After 5 minutes, all occupants
have reached an exit and are evacuating
T = 240s T = 300s
• Average lower layer temperature increasing (29 ⁰C)
• Interface height: 7.63m
DESIGN FIRE – CFAST SIMULATION
T = 330s
• All occupants have exited building• Final interface height: 7.18m• Final lower layer temperature: 32.2 ⁰C
0
20
40
60
80
100
120
140
160
180
200
0
1
2
3
4
5
6
7
8
9
10
0 60 120 180 240 300 360 420 480 540 600
Tem
pera
ture
(C)
Laye
r Hei
ght (
m)
Time (s)
Hot Gas Layer Height and Layer Temperatures in Design Fire 1 - CFAST Simulation
Layer Height Upper Layer Temperature Lower Layer Temperature
PERFORMANCE BASED DESIGN – SUMMARY
ASET > RSET: SUCCESS• Extremely rapid heat and smoke production offset by massive
volume of compartment• Impact of smoke development unlikely to put occupants at risk• Overall performance from life safety perspective: very good
ASSUMPTIONS• Sprinklers do not activate – demonstrate safe egress is possible given
worst case scenario• Peak HRR maintained during steady burning period
o Fuel source large enough to supply continuous burning for entire duration of building egress
• Occupants spread evenly to all available exits during egresso If gathering occurs near one exit with another exit available,
occupants travel to available exit
CONCLUSIONPrescriptive requirements for structural design, alarm and detection system, egress, and sprinkler system were considered.
• Structural, A&D, egress requirements were satisfied• Recommendations made for sprinkler compliance (system
redesign, pump, secondary water source)
Performance-based analysis using Pathfinder egress modeling software and CFAST 7 with real-life (albeit, exaggerated) fire test data showed that the life safety criteria of ASET>RSET was satisfied with large margin, even with highly challenging design fire.
RECOMMENDATIONS• Determine if pump is required for sprinkler system• Examine impact of staff trained to help with egress
• Explore more complex modeling in Pathfinder: response times, seeking new exits, travel speeds
• Compare CFAST and FDS smoke height interface results• Performance based design for protection of property and valuables
FDS to model alternative suppression systems, examine cost impact