Cost Estimation System CES Implementation at NDOR TUG 2006.
Transcript of Cost Estimation System CES Implementation at NDOR TUG 2006.
Cost Estimation System CES
Implementation at NDOR
TUG 2006
NEBRASKANEBRASKA
Diverse RoadwaysDiverse Roadways
BackgroundBackground
• Nebraska’s State Highway program is an estimated $350,000,000
• Nebraska’s Lettings consist of 250+
contracts per year
• Nebraska has 400+ active contracts at
any given time
BackgroundBackground
• Centralized Estimating section5 Estimators
50 + years of experience
• Bid Based Estimates Currently using PES generate bid based prices
Only able to use one bid history
• NDOR is having to adjust schedule of program due to price instabilities
• Management wanted to factor inflation at the project level into decision making processUse inflation to get a better idea of total project
price as you move projects in the schedule
• Open up possibility to use cost sheets to validate prices
NeedsNeeds
• CES is a tool for the complete life cycle of the estimation of a project
• Ability to use multiple Bid Histories and group items based on type of Contract
• Allows the estimator to work more efficiently
• Integral component of Trns•port systemmaintains the integrity of the estimate prices
allows for snapshot capability at any point in the life cycle
Why CESWhy CES
Trns•port Modules Trns•port Modules
SiteManagerSiteManager
Estimation
BAMS/DSS Data Warehouse
Bid LettingsProjects & Proposals
ExpediteExpedite
CESCES
Construction
LASLASPESPES
SiteManagerMaterials
SiteManagerMaterials
Project begins in CESLong Range estimates - project-level
estimates based on project work types and their major cost groups
Item-level estimates - bid item estimates derived from bid histories
• Export to PES
• Snapshots taken to track evolution of the estimate
WorkflowWorkflow
• Called Info TechKathy Yelle and troops
• Developed Contract Agreement 1.75 service units
Pre-work on developing bid histories
3 days on-site implementation and discussion
3 days on-site training and discussion
Who ya gonna call…Who ya gonna call…
• Market areas help define your price indexes
Same types of items - Same types of jobs
• Market Types (redefined in 2004)Asphalt
Concrete
Structures
Districts
Market Areas - DSSMarket Areas - DSS
• Project begins in CESLong Range estimates - project-level estimates based
on project work types and their major cost groups
Item-level estimates - bid item estimates derived from bid histories
• Export to PES
• Snapshots taken to track evolution of the estimate
Market Areas - DSSMarket Areas - DSS
Market Areas - DSSMarket Areas - DSS
• Project begins in CESLong Range estimates - project-level estimates based
on project work types and their major cost groups
Item-level estimates - bid item estimates derived from bid histories
• Export to PES
• Snapshots taken to track evolution of the estimate
Market Areas - DSSMarket Areas - DSS
Market Areas - DSSMarket Areas - DSS
Bid Histories - DSSBid Histories - DSS
• Using HIREG to develop based on Market area and Time - Input
Time - 3 year, 2 year, 18 months, 1 year
• Determined type of observations to include - Input
low bid, low 3 bids, all bids
minimum of occurrences
• Bid Histories -OutputWeighted Averages
Regressions
• Two Days UserHigh level - Navigation, Shortcuts, best
practices
More detailed level – Utilizing multiple libraries, standard task, snapshots
• One Day System AdministratorHigh level - Navigation, User Roles
More detailed level – Creating and maintaining libraries
Basic TrainingBasic Training
Basic TrainingBasic Training
Basic TrainingBasic Training
Retirement…???Retirement…???
• CES to PES ExportWorking with TTF, Info Tech and other
Agencies
• Customize Screens
• Create ReportsDetail estimate report with inflation
To DoTo Do
QuestionsQuestions