Cost Concepts and Design Econ 2

27
Cost Concepts and Design Economics II CE22 Lecture 3 Ma. Brida Lea Diola Institute of Civil Engineering College of Engineering University of the Philippines Diliman

description

Source: Chan and Park (

Transcript of Cost Concepts and Design Econ 2

Page 1: Cost Concepts and Design Econ 2

Cost Concepts and Design Economics II

CE22 Lecture 3

Ma. Brida Lea Diola Institute of Civil Engineering College of Engineering University of the Philippines Diliman

Page 2: Cost Concepts and Design Econ 2

Discussion Topics

¤ Review of Cost Terminology

¤ Additional notes on general economic environment

¤ Cost-Driven Design Optimization

¤ Present Economy Studies

Page 3: Cost Concepts and Design Econ 2

Review of Cost Terminology

¤ Cash cost vs Book cost

¤ Direct vs Indirect costs

¤ Fixed vs Variable costs; INCREMENTAL costs

¤ Recurring vs Nonrecurring costs

¤ Opportunity and Sunk costs

¤ Lifecycle cost

Page 4: Cost Concepts and Design Econ 2

In General, Volume Varies With Price: The lower the price, the higher the volume

General Economic Environment: Revisited

Graph from MIT Opencourseware on Project Evaluation

Page 5: Cost Concepts and Design Econ 2

Total Revenue Also Varies With Price: Revenue Declines if Price is Too High or Too Low

General Economic Environment: Revisited

Graph from MIT Opencourseware on Project Evaluation

Page 6: Cost Concepts and Design Econ 2

A Company Will Produce Only if its Expected Market Share Will Allow It to Make a Profit for Some Range of Prices

General Economic Environment: Revisited

Graph from MIT Opencourseware on Project Evaluation

Page 7: Cost Concepts and Design Econ 2

If costs are very high, then a company will be unable to make a profit for any range of prices

General Economic Environment: Revisited

Graph from MIT Opencourseware on Project Evaluation

Page 8: Cost Concepts and Design Econ 2

Cost, Volume and Breakeven Point Relationships

Cost and Revenue

Volume (Demand)

CT

CF

CV

D’1 D’2 D*

Profit

Maximum Profit

PROFIT (loss) = Total Revenue – Total Costs

General Economic Environment: Revisited

Breakeven Points

Slide form Lecture 2

Page 9: Cost Concepts and Design Econ 2

Example: Which Site is Best for Asphalt Mixing Plant: Cheaper (A) or Closer (B)?

Cost Factor SITE A SITE B

Hauling Distance 6 miles 4.3 miles

Hauling Expense $1.15/cu yd/mi $1.15/cu yd/mi

Monthly Rental $1,000/mo $5,000/mo

Set-up/removal $15,000 $25,000

Flagman 0 $96/day

Total Volume 50,000 cu yds 50,000 cu yds

Duration 4 months (85 days) 4 months (85 days)

For the selected site, how many cubic yards of paving material needs to be delivered before starting to make a profit if paid $8.05 per cubic yard delivered to the job location?

Page 10: Cost Concepts and Design Econ 2

For SITE B, how many cubic yards of paving material needs to be delivered before starting to make a profit if paid $8.05 per cubic yard delivered to the job location?

Example (cont) Cost

Factor Fixed Variable SITE A SITE B

Rent 4 mo x $1000/mo

4 mo x $5,000/mo

Set-up/remove

$15,000 $25,000

Flagman $0 85 days x $96/day

Hauling 6 x 50,000 x $1.15

4.3 x 50,000 x $1.15

TOTAL FIXED COST: SITE A à $19,000 SITE B à $53,160

ANS = 17, 121 cubic yards

X

X

X

X

$364,000

$300,410

Page 11: Cost Concepts and Design Econ 2

COST-DRIVEN DESIGN OPTIMIZATION A basic design question may arise when some costs vary directly and others vary inversely with a particular, important design parameter (which is known as a "cost driver")

http://koreamusicwave.blogspot.com/2011/01/airplane-pictures-and-clipart.html

Page 12: Cost Concepts and Design Econ 2

COST-DRIVEN DESIGN OPTIMIZATION

Must maintain a life-cycle design perspective

Ensures engineers consider:

¤  Initial investment costs

¤ Operation and maintenance expenses

¤ Other annual expenses in later years

¤ Environmental and social consequences over design life

Page 13: Cost Concepts and Design Econ 2

COST-DRIVEN DESIGN OPTIMIZATION PROBLEM COST TYPES

1.  Fixed cost(s)

2.  Cost(s) that vary directly with the design variable

3.  Cost(s) that vary indirectly with the design variable

Page 14: Cost Concepts and Design Econ 2

GENERAL APPROACH FOR OPTIMIZING A DESIGN WITH RESPECT TO COST

1.  Identify primary cost-driving design variable

2.  Write an expression for the cost model in terms of the design variable

3.  Set first derivative of cost model with respect to continuous design variable equal to 0. (For discrete design variables, compute cost model for each discrete value over selected range).

4.  Solve equation in step 3 for optimum value of continuous design variables

5.  For continuous design variables, use the second derivative of the cost model with respect to the design variable to determine whether optimum corresponds to global maximum or minimum.

Page 15: Cost Concepts and Design Econ 2

Example The cost of operating a large ship (Co) varies as the square of its velocity (v); specifically, Co = knv2 , where n = trip length in miles and k = a constant of proportionality. It is known that at 12 miles/hour the average cost of operation is $100 per mile. The owner of the ship wants to minimize the cost of operation, but it must be balanced against the cost of the perishable cargo (Cc ) which the customer has set at $1,500 per hour. QUESTION: At what velocity should the trip be planned to minimize the total cost (CT ), which is the sum of the cost of operating the ship and the cost of perishable cargo?

Page 16: Cost Concepts and Design Econ 2

PRESENT Economy Studies Cost analyses where the influence of time on money is not a significant consideration.

Page 17: Cost Concepts and Design Econ 2

Examples

¤ Material Selection

¤ Make vs Purchase studies

¤ Alternative Machine Speeds

¤ Optimizing Design Parameters ¤  Bridge span length

¤  Design Tolerance and Quality

Page 18: Cost Concepts and Design Econ 2

RULE #1

¤ Maximize profit (revenues and/or profits are not constant)

Page 19: Cost Concepts and Design Econ 2

Example

Mining Aircraft Seating

Page 20: Cost Concepts and Design Econ 2

RULE #2

¤ Minimize costs/expenses (revenues are constant or non-existent)

Page 21: Cost Concepts and Design Econ 2

Examples

Page 22: Cost Concepts and Design Econ 2

Example: Material Selection

Page 23: Cost Concepts and Design Econ 2

Example: Material Selection

Choose Aluminum to minimize total cost

Page 24: Cost Concepts and Design Econ 2

Example: Make or Purchase

Page 25: Cost Concepts and Design Econ 2

Example (cont)

The incremental cost to make the product in-house is actually $3.75 per unit versus $7.50 to purchase.

Q: What happens if fixed overhead changes as a result of producing the product in house?

Page 26: Cost Concepts and Design Econ 2

Complicating Factors for Projects

¤ Unique projects ¤ Difficult to test supply and demand

¤ Long Lives ¤ Demand can change substantially ¤ Competition from other suppliers and new

technologies can be expected ¤ The time value of money becomes critical ¤ Externalities are important

Page 27: Cost Concepts and Design Econ 2

Thank You! References: Chan Park, Contemporary Engineering Economics 5th ed Sullivan et al, Engineering Economy 14th ed Blank and Tarquin Engineering Economy 6th ed

Next topic: Money-Time Relationships