    Schedule of Values

    School District

    SFB Project Number

    Architect Name SD

    CM @ Risk Name DDCounty GMP

    Grade Configuration

    Square Footage sq.ft. (enter only thenumber in F11

    Number of Buildings

    Student Capacity

    Acres of Land

    Permitting (Name of County/City)

    SFB Board Approved Budget AW-Y

    Grand GMP (Total ofSFB Base Cost and District Cost)

    $0.00 #DIV/0! AW-N

    SFB Cost per SF #DIV/0! #DIV/0! #DIV/0! #DIV/0!

    Cost per Other On-Site

    SFB Unit SFB District Funding Off-SiteQuantity (no markup) Base Cost Cost (Adjacent Ways, etc.) Adjacent Wa

    Div 1 GENERAL CONDITIONS #DIV/0!

    Div 2 SITE WORK

    site demolition/removal #DIV/0!

    survey #DIV/0!

    dust control #DIV/0!

    drywells #DIV/0!

    track off pads #DIV/0!

    earthwork/mass excavation #DIV/0!

    unusal site conditions #DIV/0!

    lift station #DIV/0!

    retaining walls #DIV/0!import/export dirt #DIV/0!

    stormwater/drainage #DIV/0!

    asphalt/paving #DIV/0!

    parking #DIV/0!

    soil treatment #DIV/0!

    site electrical #DIV/0!

    striping/signage #DIV/0!

    site concrete #DIV/0!

    sidewalks #DIV/0!

    site masonry #DIV/0!

    site utilities #DIV/0!

    septic system #DIV/0!

    wells #DIV/0!

    trash enclosures #DIV/0!

    ballfield backstop #DIV/0!

    site basketball courts #DIV/0!

    sports fields #DIV/0!

    chainlink fencing #DIV/0!

    wrought iron fencing #DIV/0!

    block fencing #DIV/0!

    landscaping/irrigation #DIV/0!

    #DIV/0! Division 2 total #DIV/0! $0.00 $0.00 $0.00 $0

    Div 3 BUILDING CONCRETE

    footings/walls #DIV/0!

    slabs #DIV/0!

    building #DIV/0!

    rebar #DIV/0!

    precast concrete #DIV/0!

    Division 3 total #DIV/0! $0.00 $0.00 $0.00 $0

    Div 4 BUILDING MASONRY

    masonry walls #DIV/0!

    masonry columns #DIV/0!

    stonework #DIV/0!

    rebar #DIV/0!

    Division 4 total #DIV/0! $0.00 $0.00 $0.00 $0

    District Funded SF:

    Construction Schedule (number of days):

    Prepared by:

    Prepared by Company:

    SCHOOL FACILITIES BOARD

    SFB NC 600-06

    NEW CONSTRUCT

    SCHEDULE OF VALU

    SFB Meeting Date:

    Total GMP incld. SFB, District & Adj. Ways

  • 8/13/2019 Cost Breakdown Sheet

    2/4

    Schedule of Values

    SFB Cost per SF #DIV/0! #DIV/0! #DIV/0! #DIV/0!

    Cost per Other On-Site

    SFB Unit SFB District Funding Off-Site

    Quantity (no markup) Base Cost Cost (Adjacent Ways, etc.) Adjacent Ways

    Div 5 METALS

    structural steel #DIV/0!

    stairs #DIV/0!

    metal decking #DIV/0!

    architectural steel #DIV/0!

    miscellaneous steel #DIV/0!

    Division 5 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Div 6 CARPENTRY

    rough carpentry structure #DIV/0!

    wood decking #DIV/0!

    finish carpentry #DIV/0!

    millwork/casework #DIV/0!plastic/glass fiber #DIV/0!

    Division 6 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Div 7 THERMAL/MOISTURE

    waterproofing/dampproofing #DIV/0!

    building insulation #DIV/0!

    membrane roofing #DIV/0!

    foam roof #DIV/0!

    metal roof #DIV/0!

    roof shingles #DIV/0!

    roof tiles #DIV/0!

    general sheet metal #DIV/0!

    roof accessories #DIV/0!

    sprayed fireproofing #DIV/0!

    firestopping #DIV/0!

    roof expansion joint #DIV/0!

    joint sealants #DIV/0!

    Division 7 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Div 8 DOORS/GLASS

    doors & frames #DIV/0!

    hardware #DIV/0!

    storefronts #DIV/0!

    automatic doors #DIV/0!

    overhead doors #DIV/0!

    windows #DIV/0!

    skylights #DIV/0!

    curtain walls #DIV/0!

    glass & glazing #DIV/0!

    Division 8 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Div 9 FINISHESstucco/EIFS systems #DIV/0!

    interior metal studs/gypsum board #DIV/0!

    exterior metal stud framing #DIV/0!

    decorative plaster #DIV/0!

    acoustical ceilings #DIV/0!

    ceramic tile #DIV/0!

    resilient flooring #DIV/0!

    carpet #DIV/0!

    wood floors #DIV/0!

    epoxy #DIV/0!

    sealed floors #DIV/0!

    sound panels #DIV/0!

    painting #DIV/0!fiberglass reinforced panels #DIV/0!

    Division 9 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    P 2 f 4

  • 8/13/2019 Cost Breakdown Sheet

    3/4

    Schedule of Values

    SFB Cost per SF #DIV/0! #DIV/0! #DIV/0! #DIV/0!

    Cost per Other On-Site

    SFB Unit SFB District Funding Off-Site

    Quantity (no markup) Base Cost Cost (Adjacent Ways, etc.) Adjacent Ways

    Div 10 SPECIALTIES

    visual display boards #DIV/0!

    toilet partitions & accessories #DIV/0!

    projection screens #DIV/0!

    wall protection #DIV/0!

    operable partitions/walls #DIV/0!

    flagpoles #DIV/0!

    cubicle track & curtain #DIV/0!

    signage #DIV/0!

    lockers #DIV/0!

    fire exttinguishers & cabinets #DIV/0!

    knox box #DIV/0!

    awnings #DIV/0!

    storage shelving #DIV/0!

    Division 10 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Div 11 EQUIPMENT

    stage curtain/equipment #DIV/0!

    library equipment #DIV/0!

    audio/visual equipment #DIV/0!

    kitchen equipment #DIV/0!

    sports/PE equipment #DIV/0!

    playground equipment #DIV/0!

    canopy/ramada #DIV/0!

    bike racks #DIV/0!

    floor safe #DIV/0!

    Division 11 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Div 12 FURNISHINGS

    metal casework #DIV/0!plastic laminate casework #DIV/0!

    fume hoods #DIV/0!

    auditorium seating #DIV/0!

    window coverings #DIV/0!

    Division 12 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Div 13 SPECIAL CONST

    shelters #DIV/0!

    metal buildings #DIV/0!

    bleachers #DIV/0!equipment/storage enclosures #DIV/0!

    swimming pools #DIV/0!surveillance/alarm #DIV/0!

    Division 13 total #DIV/0! $0.00 $0.00 $0.00 $0.00Div 14 CONVEYING

    elevators #DIV/0!

    wheelchair lifts #DIV/0!material handling #DIV/0!

    Division 14 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Div 15 MECHANICAL

    mechanical insulation #DIV/0!

    fire protection/sprinklers #DIV/0!

    plumbing fixtures #DIV/0!

    water treatment #DIV/0!

    HVAC - central plant #DIV/0!

    HVAC - package units #DIV/0!HVAC - split system #DIV/0!

    HVAC - evaporative #DIV/0!

    Division 15 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Page 3 of 4

  • 8/13/2019 Cost Breakdown Sheet

    4/4

    Schedule of Values

    SFB Cost per SF #DIV/0! #DIV/0! #DIV/0! #DIV/0!

    Cost per Other On-Site

    SFB Unit SFB District Funding Off-Site

    Quantity (no markup) Base Cost Cost (Adjacent Ways, etc.) Adjacent Ways

    Div 16 ELECTRICAL

    electrical #DIV/0!

    fire alarm system #DIV/0!security system #DIV/0!

    data cabling #DIV/0!

    intercom #DIV/0!

    communications/phone #DIV/0!

    TV cabling #DIV/0!

    exterior lighting #DIV/0!

    generators #DIV/0!

    Division 16 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Div 17 SPECIAL SYSTEMS

    EMS #DIV/0!

    Division 17 total #DIV/0! $0.00 $0.00 $0.00 $0.00

    Subtotal $0.00 $0.00 $0.00 $0.00 $0.00Contractor Fee #DIV/0!

    Contactor Contingency #DIV/0!

    Builders Risk/Liability Insurance #DIV/0!

    Performance & Payment Bonds #DIV/0!

    Sales Tax #DIV/0!

    Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

    Grand Guaranteed

    Maximum Price (GMP)(Total of SFB Base Cost and District Cost)$0.00

    Page 4 of 4