Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options Project Number: 29370013 December 2011 Prepared for Bundaberg Regional Council

Transcript of Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost...

Page 1: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options

Project Number: 29370013

December 2011 Prepared for Bundaberg Regional Council

Page 2: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial
Page 3: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options

29370013 Version A 09.12.2011 Commercial in Confidence Page iii

TABLE OF CONTENTS

EXECUTIVE SUMMARY IV

1 INTRODUCTION 1

2 PRELIMINARY COST ESTIMATES 2

3 CONCLUSIONS 3

TABLES:

Table 1.1 Estimate of Cost Summary APPENDICES:

APPENDIX A PRELIMINARY DESIGN PLANS 4

APPENDIX B COST ESTIMATES OPTION A2, B2, C4 AND C6

Page 4: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options

29370013 Version A 09.12.2011 Commercial in Confidence Page iv

EXECUTIVE SUMMARY

This report has been prepared as supplementary report to the ‘Murdoch’s Road Drain – Preliminary Investigation of Drainage Outlets’ report prepared by Cardno for Bundaberg Regional Council. The purpose of this report is to provide a cost benefit analysis for the proposed drainage treatment options.

Of the 10 possible drainage options covered in the report, the four most suitable options were chosen to have the costs analysed. The four options had preliminary design plans created (appendix A) and costings were completed from these plans.

Below is a table of the cost estimate comparisons for the four options. A detailed breakdown of these preliminary cost estimates are shown in Appendix B.

Estimate of Cost Summary OPTION ESTIMATE OF COST

A2 $1,054,635 B2 $677,848 C4 $483,945 C6 $148,315

After conducting preliminary cost estimates on the four treatment options mentioned above the results varied from $148,315 to $1,054,635

The preliminary cost estimates further support the conclusions from the main drainage report that treatment options C4 and C6 are the lower cost options of the options investigated.

Of these two options C6 is the lowest cost and as detailed in the drainage report provides a faster reduction of water levels between Palm View Drive and Woodlands Lane.

Page 5: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options

Page 1

1 INTRODUCTION

Bundaberg Regional Council engaged Cardno to undertake an analysis of the Murdoch’s Road drain located at Moore Park. The drain is located within the residential area of the Moore Park township with is located within the Bundaberg Regional Council local government boundary. As part of the drainage analysis a number of improvement options were investigated. A full description of the options investigated and results are detailed in the Cardno Report ‘Preliminary Investigation of Drainage Outlets’.

The purpose of this supplementary report is to provide a cost benefit analysis of a number of options investigated in the main investigation report. After consultation with Bundaberg Regional Council it was decided that the following options were to be investigated as part of the cost benefit analysis:

Driveway

There are driveways that need upgrading along the drainage path upstream of Moore Park Road. These driveways are shown in Fig 1, 1.1 and 1.2. These driveways although described separately actually form part of the cost estimate of the other options.

Option A2

Open channel or piped drainage system (or contribution of both) between the area upstream of Moore Park Road and the Ocean. Figure 2 of Appendix A shows the preliminary design for option A2. The option has been costed using allowing for an open channel from the Maultby Street road reserve to the drainage outlet. This section of open channel is approximately 200m.

Option B2

Open channel or piped drainage system (or contribution of both) between the area upstream of the tidal bund and the Ocean. Figure 3 of Appendix A shows the preliminary design for option B2. This option has been costed using an open channel section between approximate chainages 200 and 300.

Option C4

Upgrade the culvert at the tidal bund to 4/ 900mm pipes. In addition to the culvert upgrade this option also includes de-Silting, vegetation removal and regrade of drain downstream of Tidal Bund as well as the excavation of the drain downstream of the tidal bund to uniform level of -1.0m AHD. Also included in this option is the upgrading a number of driveways that are located along the drainage path. Figure 4 of Appendix A shows the preliminary design for option C4.

Option C6

Remove the tidal bund altogether, and install flap-gates on the downstream side of the existing 4/900mm pipes at Moore Park Road. Figure 5 of Appendix A shows the preliminary design for option C6.

Preliminary designs of the above options are shown in Appendix A.

Page 6: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options

Page 2

2 PRELIMINARY COST ESTIMATES

A preliminary cost estimate has been undertaken on the all of the options listed above. The preliminary designs that are being costed are based on the parameters utilised in the modelling of the drainage options. A detailed cost breakdown of each option is included in Appendix B.

The preliminary cost estimates have made allowance for treatment of acid sulphate soils (ASS). The determination on Acid Sulphate Soil quantities are based on Preliminary Acid Sulphate Soil investigations undertaken by Cardno Bowler. It should be noted that the testing regime used in this preliminary investigation has identified that Option A2 and B2 don’t contain treatable levels of ASS and as such they have been costed accordingly. However it should be noted during a detailed design a more stringent ASS testing regime will be required for DERM approval. This additional testing may indentify treatable areas of ASS. Option C4 has been based on the ASS levels identified in the preliminary ASS investigation. Option C6 requires minimal excavation (100m3) and therefore no ASS treatment has been allowed for.

No allowance has been made in this estimate of cost for the any Local, State or Federal Government Application Fees or Charges. No allowance has been made for any reporting or ongoing negotiation for any environmental issues relating to construction in a tidal waterway.

Page 7: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options

Page 3

3 CONCLUSIONS

After conducting a preliminary costing estimate on the proposed drainage options the following costs were established:

Table 3.1 Estimate of Cost Summary OPTION ESTIMATE OF COST (inc GST)

A2 $1,054,635 B2 $677,848 C4 $483,945 C6 $148,315

After conducting preliminary cost estimates on the four treatment options mentioned above the results varied from $148,315 to $1,054,635 inc GST

The preliminary cost estimate further supports the conclusions from the main drainage report that treatment options C4 and C6 are the lower cost options of the options investigated.

Of these two options C6 is the lowest cost and as detailed in the drainage report provides a faster reduction of water levels between Palm View Drive and Woodlands Lane.

Page 8: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options

Page 4

Appendix A

Preliminary Design Plans

Page 9: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Driveway CrossingsFigure 1

Scale 1:2500

Murdochs Road, Moore ParkMoore Park Drainage Study

Bundaberg Regional Council

Lot 29RP814879

Lot 13SP212156

Lot 27RP814879

Lot 15SP215844

Lot 25RP814879 Lot 24

RP814879

Lot 23RP814879 Lot 22

RP814879

Lot 83RP841664

PALM

VIE

W D

RIVE

MURDOCHS ROAD

Page 10: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Driveway CrossingsFigure 1.1

Scale 1:1000

Murdochs Road, Moore ParkMoore Park Drainage Study

Bundaberg Regional Council

Lot 29RP814879

Lot 13SP212156

Lot 27RP814879

Lot 15SP215844

PALM

VIE

W D

RIVE

MURDOCHS ROAD

Raise existing driveway by0.12m to RL1.7 and upgradeexisting culvert to 2 x Ø600mmRCP's - IL 0.8m AHD

Raise existing driveway by0.09m to RL1.7 and upgradeexisting culvert to 2 x Ø600mmRCP's - IL 0.8m AHD

Raise existing driveway by0.34m to RL1.7 and upgradeexisting culvert to 2 x Ø600mmRCP's - IL 0.8m AHD

Lot 25RP814879

Page 11: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Driveway CrossingsFigure 1.2

Scale 1:1000

Murdochs Road, Moore ParkMoore Park Drainage Study

Bundaberg Regional Council

Lot 25RP814879

Lot 24RP814879

Lot 23RP814879

Lot 22RP814879

MURDOCHS ROAD

Raise existing driveway by0.45m to RL1.7 and upgradeexisting culvert to 2 x Ø600mmRCP's - IL 0.8m AHD

Lower existing driveway by0.20m to RL1.7 and upgradeexisting culvert to 2 x Ø600mmRCP's - IL 0.8m AHD Raise existing driveway by

0.02m to RL1.7 and upgradeexisting culvert to 2 x Ø600mmRCP's - IL 0.8m AHD

Lake

Lot 83RP841664

Lower existing drivewayby 0.17m to RL1.7.Existing Ø900mm culvert toremain.

Lower existing drivewayby 0.08m to RL1.7.Existing Ø900mm culvertto remain.

Page 12: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Option A2Figure 2

Scale 1:2500

ă

ă

Murdochs Road, Moore ParkMoore Park Drainage Study

Bundaberg Regional Council

OHLAF S

TREET

MOORE PARK ROAD

LAGOON D

RIVE

MAU

LTBY

STR

EET

Ø900mm Pipe

3.0m WideOpen Channel

Page 13: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Option B2Figure 3

Scale 1:2500

Murdochs Road, Moore ParkMoore Park Drainage Study

Bundaberg Regional Council

GENGERS ROAD

MO

OR

E PA

RK

RO

AD

Ø900mm Pipe

Ø900mm Pipe

3.0m Wide OpenChannel Section

Approx. Chainage200 to 300

ă

ă

Page 14: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Option C4Figure 4

Scale 1:2500

Murdochs Road, Moore ParkMoore Park Drainage Study

Bundaberg Regional Council

ă

ă

ăă

ă

ă

ă

ă

ăă

ă

ă

ă

ăUpgrade existing culvert to4 x Ø900mm with flood gates

Provide de-silting, vegetation removaland regrade of drain downstream ofthe tidal bund.

5.0m WideOpen Channel

Page 15: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Option C6Figure 5

Scale 1:2500

Murdochs Road, Moore ParkMoore Park Drainage Study

Bundaberg Regional Council

GENGERS ROAD

MO

OR

E PA

RK

RO

AD

Install flood gates on outlet ofexisting 4 x Ø900mm culvertsunder Moore Park Drive

Remove existing tidal bundstructure and culverts

Page 16: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options

Page 5

Appendix B

Cost Estimates Option A2, B2, C4 and C6

Page 17: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 25/11/2011

Summary EstimateAmount

Option A2- Earthworks & Civil Works

Section A - Option A2 - Preliminaries $129,269.30

Section B - Option A2 - Stormwater Drainage $703,990.00

Section C - Option A2 - Earthworks $56,000.00

Section D - Option A2 - Driveways $69,500.00

Sub Total - Option A2 $958,759.30Plus 10% GST $95,875.93

TOTAL $1,054,635.23

P:\2937\00\2937 00 13\Design\Option A2 EOC.xlsx Page 1 of 5

Page 18: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 25/11/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION A - Option A2- Preliminaries

A1 Design and Documentation (based on 7% of Construction Cost) LS 1 $56,769.30 $56,769.30

A2 Survey LS 1 $15,000.00 $15,000.00

A3 Establishment on site of Plant, Equipment, Site Facilities LS 1 $10,000.00 $10,000.00

A4 Traffic Control Plan :-preparation by authorised person, submission to BRC for approval and implementation during construction incl all signs etc. LS 1 $7,500.00 $7,500.00

A5 Vegetation Clearing Ha 2 $20,000.00 $40,000.00

Section 1 - Option A2- Preliminaries - Total $129,269.30

P:\2937\00\2937 00 13\Design\Option A2 EOC.xlsx Page 2 of 5

Page 19: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 25/11/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION B - Option A2 - Stormwater Drainage

B1 Excavate, bed, lay, joint, backfill and restoration of surface reinforced concrete stormwater drainage pipes including HS 3 installation, metal bedding & sub soil drainage connections to downstream structure :-

a) Drainagei) 900mm dia Class 2 m 550 $1,200.00 $660,000.00

B2 Construction of manholes complete with Class D trafficable lids :-a) 1050mm dia each 7 $2,470.00 $17,290.00

B3 Supply and install Stormwater Outlet Headwall incl run off drain

a) 900mm dia each 1 $3,200.00 $3,200.00

B4a) Supply and Install Flood Gates 900mm dia each 1 $6,500.00 $6,500.00

B5 Underbore State Controlled Road Item 1 $17,000.00 $17,000.00

SECTION B - Option A2- Stormwater Drainage - Total $703,990.00

P:\2937\00\2937 00 13\Design\Option A2 EOC.xlsx Page 3 of 5

Page 20: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 25/11/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION C - Option B2 -Earthworks

C1 Excavate and grade open channel from Maultby Street Road Reserve to outlet approximately 200m m3 2,000 $28.00 $56,000.00

SECTION D -Option A2 - Driveways- Total $56,000.00

P:\2937\00\2937 00 13\Design\Option A2 EOC.xlsx Page 4 of 5

Page 21: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 25/11/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION D - Option A2 - Driveways

C1 Upgrading of driveways along the drainage path upstream of Moore Park Road as described in Drainage Report :- Item 1 $69,500.00 $69,500.00

SECTION D -Option A2 - Driveways- Total $69,500.00

P:\2937\00\2937 00 13\Design\Option A2 EOC.xlsx Page 5 of 5

Page 22: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011

Summary EstimateAmount

Option B2- Earthworks & Civil Works

Section A - Option B2 - Preliminaries $80,945.60

Section B - Option B2 - Stormwater Drainage $440,580.00

Section C - Option B2 - Earthworks $25,200.00

Section D - Option B2 - Driveways $69,500.00

Sub Total - Option B2 $616,225.60Plus 10% GST $61,622.56

TOTAL $677,848.16

P:\2937\00\2937 00 13\Design\Option B2 EOC.xlsx Page 1 of 5

Page 23: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION A - Option B2- Preliminaries

A1 Design and Documentation (based on 7% of Construction Cost) LS 1 $37,945.60 $37,945.60

A2 SurveyLS 1 $11,000.00 $11,000.00

A3 Establishment on site of Plant, Equipment, Site Facilities LS 1 $10,000.00 $10,000.00

A4 Traffic Control Plan :-preparation by authorised person, submission to BRC for approval and implementation during construction incl all signs etc. LS 1 $2,000.00 $2,000.00

A5 Vegetation Clearing Ha 1 $20,000.00 $20,000.00

Section 1 - Option B2- Preliminaries - Total $80,945.60

P:\2937\00\2937 00 13\Design\Option B2 EOC.xlsx Page 2 of 5

Page 24: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION B - Option B2 - Stormwater Drainage

B1 Excavate, bed, lay, joint, backfill and restoration of surface reinforced concrete stormwater drainage pipes including HS 3 installation, metal bedding & sub soil drainage connections to downstream structure :-

a) Drainagei) 900mm dia Class 2 m 350 $1,200.00 $420,000.00

B2 Construction of manholes complete with Class D trafficable lids :-a) 1050mm dia each 4 $2,470.00 $9,880.00

B3 Supply and install Stormwater Outlet Headwall incl run off drain

a) 900mm dia each 3 $1,400.00 $4,200.00

B4a) Supply and Install Flood Gates 900mm dia each 1 $6,500.00 $6,500.00

SECTION B - Option B2- Stormwater Drainage - Total $440,580.00

P:\2937\00\2937 00 13\Design\Option B2 EOC.xlsx Page 3 of 5

Page 25: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 25/11/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION C - Option B2 -Earthworks

C1 Excavate and grade open channel from approximate chainage 200 to 300. m3 900 $28.00 $25,200.00

SECTION C -Option B2 - Earthworks- Total $25,200.00

P:\2937\00\2937 00 13\Design\Option B2 EOC.xlsx Page 4 of 5

Page 26: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION D - Option B2 - Driveways

D1 Upgrading of driveways along the drainage path upstream of Moore Park Road as described in Drainage Report :- Item 1 $63,000.00 $69,500.00

SECTION D -Option B2 - Driveways - Total $69,500.00

P:\2937\00\2937 00 13\Design\Option B2 EOC.xlsx Page 5 of 5

Page 27: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011

Summary EstimateAmount

Option C4- Earthworks & Civil Works

Section A - Option C4 - Preliminaries $92,450.00

Section B - Option C4 - Stormwater Drainage $104,000.00

Section C - Option C4 - Earthworks $174,000.00

Section D - Option C4 - Driveways $69,500.00

Sub Total - Option C4 $439,950.00Plus 10% GST $43,995.00

TOTAL $483,945.00

P:\2937\00\2937 00 13\Design\Option C4 EOC.xlsx Page 1 of 5

Page 28: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION A - Option C4- Preliminaries

A1 Design and Documentation (Based on 7% of Construction Cost) LS 1 $26,950.00 $26,950.00

A2 SurveyLS 1 $8,000.00 $8,000.00

A3 Establishment on site of Plant, Equipment, Site Facilities LS 1 $14,000.00 $14,000.00

A4 Traffic Control Plan :-preparation by authorised person, submission to BRC for approval and implementation during construction incl all signs etc. LS 1 $3,500.00 $3,500.00

A5 Vegetation Clearing Ha 2.00 $20,000.00 $40,000.00

Section 1 - Option C4- Preliminaries - Total $92,450.00

P:\2937\00\2937 00 13\Design\Option C4 EOC.xlsx Page 2 of 5

Page 29: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION B - Option C4 - Stormwater Drainage

B1 Excavate, bed, lay, joint, backfill and restoration of surface reinforced concrete stormwater drainage pipes including HS 3 installation, metal bedding & sub soil drainage connections to downstream structure :-

a) Drainagei) 900mm dia Class 2 m 40 $1,200.00 $48,000.00

B2 Supply and install Stormwater Outlet Headwall incl run off drain

a) 4/900mm dia each 2 $15,000.00 $30,000.00

B3

a) Supply and Install Flood Gates 900mm dia each 4 $6,500.00 $26,000.00

SECTION B - Option C4- Stormwater Drainage - Total $104,000.00

P:\2937\00\2937 00 13\Design\Option C4 EOC.xlsx Page 3 of 5

Page 30: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION C - Option C4 - Stormwater Drainage

C1 De-Silt and re-grade down stream table drain. m3 3,000 $26.00 $78,000.00

C2 Treatment of Acid Sulphate Soil m3 3,000 $32.00 $96,000.00(assuming a 2 km maximum haul distance to suitable treatment site)

SECTION C - Option C4- Earthworks - Total $174,000.00

P:\2937\00\2937 00 13\Design\Option C4 EOC.xlsx Page 4 of 5

Page 31: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION D - Option C4 - Driveways

D1 Upgrading of driveways along the drainage path upstream of Moore Park Road as described in Drainage Report :- Item 1 $69,500.00 $69,500.00

SECTION D -Option C4 - Driveways - Total $69,500.00

P:\2937\00\2937 00 13\Design\Option C4 EOC.xlsx Page 5 of 5

Page 32: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011

Summary EstimateAmount

Option C6- Earthworks & Civil Works

Section A - Option C6 - Preliminaries $36,532.00

Section B - Option C6- Stormwater Drainage $26,000.00

Section C - Option C6 - Earthworks $2,800.00

Section D - Option C6 - Driveways $69,500.00

Sub Total - Option C6 $134,832.00Plus 10% GST $13,483.20

TOTAL $148,315.20

P:\2937\00\2937 00 13\Design\Option C6 EOC.xlsx Page 1 of 5

Page 33: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION A - Option C6- Preliminaries

A1 Design and Documentation LS 1 $7,532.00 $7,532.00

A2 Survey LS 1 $4,000.00 $4,000.00

A3 Establishment on site of Plant, Equipment, Site Facilities LS 1 $10,000.00 $10,000.00

A4 Traffic Control Plan :-preparation by authorised person, submission to BRC and DTMR for approval and implementation during construction incl all signs etc. LS 1 $5,000.00 $5,000.00

A5 Vegetation Clearing Ha 0.5 $20,000.00 $10,000.00

Section 1 - Option C6 Preliminaries - Total $36,532.00

P:\2937\00\2937 00 13\Design\Option C6 EOC.xlsx Page 2 of 5

Page 34: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION B - Option C6 - Stormwater Drainage

B1a) Supply and Install Flood Gates 900mm dia each 4 $6,500.00 $26,000.00

SECTION B - Option C6- Stormwater Drainage - Total $26,000.00

P:\2937\00\2937 00 13\Design\Option C6 EOC.xlsx Page 3 of 5

Page 35: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION C - Option C6 - Stormwater Drainage

C1 Take up and remove Bund Wall Section 10 metres wide m3 100 $28.00 $2,800.00

SECTION C - Option C6- Earthworks - Total $2,800.00

P:\2937\00\2937 00 13\Design\Option C6 EOC.xlsx Page 4 of 5

Page 36: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 29370013Construction of Earthworks & Civil WorksMurdoch Road Drainage

DATE: 9/12/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION D - Option C6 - Driveways

D1 Upgrading of driveways along the drainage path upstream of Moore Park Road as described in Drainage Report :- Item 1 $69,500.00 $69,500.00

SECTION D -Option C6 - Driveways - Total $69,500.00

P:\2937\00\2937 00 13\Design\Option C6 EOC.xlsx Page 5 of 5

Page 37: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 2937 0013Construction of Earthworks & Civil WorksMurdoch's Road Drainage

DATE: 25/11/2011Tender Review

Summary EstimateAmount

Driveways

Section A - Driveways - Preliminaries $7,500.00

Section B - Driveways - Earthworks $30,786.00

Section C - Driveways- Stormwater Drainage $31,172.00

Sub Total - Driveways $69,458.00Plus 10% GST $6,945.80

TOTAL $76,403.80

P:\2937\00\2937 00 13\Design\Driveways EOC.xlsx Page 1 of 4

Page 38: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 2937 0013Construction of Earthworks & Civil WorksMurdoch's Road Drainage

DATE: 25/11/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION A - Driveways - Preliminaries

A1Establishment on site of Plant, Equipment, Site Facilities and Insurances LS 1 $0.00 $4,000.00

A2 Survey Setout for All Works PC Item $3,500.00

Section A - Driveways - Preliminaries - Total $7,500.00

P:\2937\00\2937 00 13\Design\Driveways EOC.xlsx Page 2 of 4

Page 39: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 2937 0013Construction of Earthworks & Civil WorksMurdoch's Road Drainage

DATE: 25/11/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION B-Driveway - Earthworks

B1 Import CBR 15 fill material to construct driveways are detailed in report m 3 606 $31.00 $18,786.00

B2 Remove weir in lot 24 RP814879 Item 1 $12,000.00 $12,000.00

Section B - Driveway Earthworks - Total $30,786.00

P:\2937\00\2937 00 13\Design\Driveways EOC.xlsx Page 3 of 4

Page 40: Cost Benefit Analysis of Drainage Outlet Options Road Drain Cost...Murdoch’s Road Drain Cost Benefit Analysis of Drainage Outlet Options 29370013 Version A 09.12.2011 Commercial

Bundaberg Regional CouncilContract Nº 2937 0013Construction of Earthworks & Civil WorksMurdoch's Road Drainage

DATE: 25/11/2011The preliminary quantities issued are for guidance and are not guaranteed.

Item Description Unit Qty Rate Amount

SECTION D - Stage 17A - Stormwater Drainage

D1 Excavate, bed, lay, joint, backfill and restoration of surface reinforced concrete stormwater drainage pipes including HS 3 installation, metal bedding & sub soil drainage connections to downstream structure :-

a) Driveway Crossingsi) 600mm dia Class 3 m 60 $286.20 $17,172.00

D5 Supply and install Stormwater Outlet Headwall incl run off drain

a) 600mm dia each 10 $1,400.00 $14,000.00

SECTION C -Driveways - Stormwater Drainage - Total $31,172.00

P:\2937\00\2937 00 13\Design\Driveways EOC.xlsx Page 4 of 4