Cost and Evaluation 111103
-
Upload
rich-rosario -
Category
Documents
-
view
220 -
download
0
Transcript of Cost and Evaluation 111103
-
7/31/2019 Cost and Evaluation 111103
1/16
WELCOME to Cost & Evaluation Workbookaccompanying Plant Design and Economics for Chemical Engineers, 5th edition,
by Peters, Timmerhaus and West.These spreadsheets are made available for convenient implementation of methodspresented in the text. The sheets are color coded to assist the user. A hypotheticalexample, 'Illustration 101', is included. The basis for all costs is Jan. 2002.
Steps to follow:
2. The sheets are intended for use in the sequence presented. However, any sheetmay be by-passed so long as the information skipped is input manually where needed
in subsequent sheets. Default values may be replaced by the user.
3. Purchased Equipment Costs may be obtained from the file "Equipment Costs,"the graphs in the text, or otherwise, and entered manually into cell H12 on the
Capital Inv.' spreadsheet.
4. On the sheet 'Capital Inv.' enter the estimated current total purchased cost of the
process equipment. For the proposed plant type, copy the corresponding "Fraction ofdelivered equipment" column entries into the tan
"User" column. The sheet then
calculates and transfers results to appropriate subsequent sheets.
5. On the sheet 'Materials & Labor' enter the product prices and flowrates, the raw
materials prices and flow rates, and the labor requirements and current ENR labor index.
6. On the sheet 'Utilities' the quantity of each utility needed annually must be enteredin appropriate units. The total annual utilities cost is transferred to sheet 'Annual TPC'.
7. The 'Depreciation' sheet is used only if the user wishes to change the default(5-year MACRS) depreciation method. To make a change, copy the appropriate MACRSrow to the 'Annual depreciation" row of sheets 'Evaluation' and 'Year-0 $', or, enter
constant annual (straight line) value into depreciation row of those sheets.
8. On the 'Annual TPC' sheet, all values are calculated from information available on
other sheets. The user may change defaults or enter preferred values. The calculatedannual TPC is transferred to 'Evaluation'.
9. The sheet 'Evaluation' uses values from other sheets to calculate the commonprofitability measures. The user may change defaults, or enter desired values
1. Please download the workbook to your computer.
-
7/31/2019 Cost and Evaluation 111103
2/16
(See Table 6-9)
Default Subtotal Result
Notes & comments
Fraction of delivered equipment
8.8000.10 0.10 0.10 0.10 0.880
9.680
0.45 0.39 0.47 0.47 4.550
0.18 0.26 0.36 0.36 3.485
0.16 0.31 0.68 0.68 6.582
0.10 0.10 0.11 0.11 1.065
0.25 0.29 0.18 0.18 1.742
0.15 0.12 0.10 0.10 0.968
0.40 0.55 0.70 0.70 6.7761.69 2.02 2.60 2.60 34.848
0.33 0.32 0.33 0.33 3.194
0.39 0.34 0.41 0.41 3.969
0.04 0.04 0.04 0.04 0.387
0.17 0.19 0.22 0.22 2.130
0.35 0.37 0.44 0.44 4.259
1.28 1.26 1.44 1.44 13.939
48.787
Working capital (WC) 0.70 0.75 0.89 0.89 8.615
57.402
The investments are made over a period of time. This is represented on the basis that startup
(time 0) will be three years after the date of the estimate, that 15% of the fixed capital investmentis spent in the year beginning at the time of the estimate (year ending at time -2), 35% in thesecond year (ending at -1) and 50% in the third year (ending at time 0) These values may be
Total indirect costs
Purchased equipment installation
Subtotal: delivered equipment
Yard improvements
Service facilities (installed)Total direct costs
Engineering and supervision
Construction expensesLegal expenses
Fluidprocessingplant
Solid-fluidprocessingplant
Project Identifier: Illustration 101
plants. These values may differ depending on many factors such as location, process type, etc.
Purchased equipment, E'Delivery, fraction of E'
Buildings (including services)
Fixed capital investment (FCI)
Total capital investment (TCI)
Direct Costs
Indirect Costs
Piping (installed)Electrical systems (installed)
Instrumentation&Controls(installed)
Sent to 'Evaluation' and
'Year-0 $', there adjusted
as described below
ESTIMATION OF CAPITAL INVESTMENT BY PERCENTAGE OF DELIVERED EQUIPMENT METHOD
Contingency
User: copy
from valuesat left or
insert
Calculated
values,million $
Solid-processingplant
Contractor's fee
The fractions in the cells below are approximations applicable to typical chemical
Required, from a linked sheet or entered manually
Required user input
-
7/31/2019 Cost and Evaluation 111103
3/16
ANNUAL OPERATING LABOR COSTS
Process Identifier: Illustration 101 Process Identifier: Illustration 101
Required user input Notes & comments Required user input Notes & comments
Default, may be changed Default, may be changed
RESULT RESULT
Main 1.60 30.000 48.00 3 3 33.67 0.885 Sent to 'Annual TPC'
Byproduct 0.25 12.000 3.00 *See Tables 6-13 and Fig. 6-9.
0.00 **Default = 3 for continuous process.
0.00 Enter appropriate value for batch operation.
0.00#
To obtain current, local value, enter (latest local0.00 1
51.00
1 0.45 20.000 9.002 0.25 12.000 3.00
3 0.05 13.000 0.65
0.00
0.00
0.00
12.65
Annual raw
materials
cost, million
$/y
Annual
Amount,
million
kg/y
Operator
rate, $/h#
Annual
value of
product,
million $/y
Total annual cost of raw materials = Sent to sheet 'Annual
TPC'
Shifts per
day**
ENR skilled labor index)/6067 =
Sent to 'Evaluation'
and 'Year-0 $'
Total annual value of products =
Raw Materials
Name of
Material
Price,
$/kg
Annual
Amount,
million
kg/y
ANNUAL RAW MATERIAL COSTS AND PRODUCTS VALUES
Products, Coproducts and Byproducts
Number of
operators per
shift*
Operating Labor
Name of
Material
Price,
$/kg
Annual
operating
labor cost,
million $/y
-
7/31/2019 Cost and Evaluation 111103
4/16
UTILITY COSTS
See Table 6-14 and Table B-1 for ranges of utility unit costs and sources of information. Default
values are rough averages and may be changed. Utility costs can differ widely with location.Required user input
Result
TOTAL UTILITY COST million $/y
Process air 0.45 $/100m3 #
100 m3#/y
Instrument air 0.90 $/100m3 #
100 m3#/y
Purchased, U.S. average 0.045 $/kWh 1800000 kWh/y 0.081
Self-generated 0.05 $/kWh kWh/y
Coal 1.66 $/GJ GJ/y
Fuel oil 3.30 $/GJ GJ/y
Natural gas 3.00 $/GJ 360000 GJ/y 1.080
Manufactured gas 12.00 $/GJ GJ/y
15oC 4.00 $/GJ GJ/y
5 C 5.00 $/GJ GJ/y-20
oC 8.00 $/GJ GJ/y
-50oC 14.00 $/GJ GJ/y
3550 kPa 8.00 $/1000 kg 1000 kg/y
790 kPa 6.00 $/1000 kg 40000 1000 kg/y 0.240
Exhaust (150 kPa) 2.00 $/1000 kg 1000 kg/y
Disposal 0.53 $/m3
m3/y
Annual utility
requirement, in
appropriate units
Sent to sheet 'Annual TPC'
2.025
Default units
of utility
requirementAir, compressed
Electricity
Fuel
Utility
Notes & comments
Default, may be changed
Process Identifier: Illustration 101
Annual utility
cost, million
$/y
Default
cost unitsDefault
un
itcost
Refrigeration, to temperature
Steam, saturated
Waste water
-
7/31/2019 Cost and Evaluation 111103
5/16
Default = 5-y MACRS.
To use a different recovery period, copy the entire row into the depreciation row ofsheets 'Evaluation' and 'Year-0 $' (add columns to these sheets as needed).
User may elect straight-line depreciation and period (d = FCI/period), andsubstitute the value into the depreciation row on sheets'Evaluation' and'Year-0 $'.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
3-year 0.333 0.444 0.148 0.074f 0.200 0.320 0.192 0.115 0.115 0.058
7-year 0.143 0.245 0.175 0.125 0.089 0.089 0.089 0.04510-year 0.100 0.180 0.144 0.115 0.092 0.074 0.066 0.066 0.066 0.066 0.03315-year 0.050 0.095 0.086 0.077 0.069 0.062 0.059 0.059 0.059 0.059 0.059 0.059 0.059 0.059 0.059 0.03020-year 0.038 0.072 0.067 0.062 0.057 0.053 0.049 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.022
DEPRECIATION
YEARRecoveryperiod
Entry = MACRS depreciationas fraction/y of FCI
Default is in place in sheets 'Evaluation' and 'Year-0 $'.
-
7/31/2019 Cost and Evaluation 111103
6/16
Default, may be changed Subtotal Notes & comments
User input RESULT
30 106
kg per year
Fixed Capital Investment, FCI 50.114 million $
12.650
0.885
0.15 of operating labor 0.885 0.133
2.025
0.06 of FCI 50.114 3.007
0.15 of maintenance & 3.007 0.451
0.15 of operating labor 0.885 0.133
0.01 ofc o 26.674 0.267
0 -- 0.000
19.550
0.02 of FCI 50.114 1.002 'Year-0 $'
0 of FCI 50.114 0.000
0.01 of FCI 50.114 0.501
0 of FCI 50.114 0.000
Calculated separately 1.503
Plant overhead, general 0.6 of labor, supervisi 4.024 2.415
2.415
23.468
0.2 of labor, supervisi 4.024 0.805
0.05 ofc o 26.674 1.334
0.04 ofc o 26.674 1.067
3.206
ItemBasis cost,million $/y
Administration
Distribution & selling
Manufacturing cost =
General Expense =
TOTAL PRODUCT COST WITHOUT DEPRECIATION = co
= 26.674
Catalysts and solvents
Basis
Maintenance and repairs
Operating supervision
Required, may be calculated here, in linked worksheet, or entered manually.
Raw materials
Operating labor
Cost,million $/y
Capacity
Defaultfactor, usermay change
ANNUAL TOTAL PRODUCT COST AT 100% CAPACITY
See Figure 6-7 and 6-8
Depreciation
Project identifier: Illustration 101
Utilities
Operating supplies
Laboratory charges
Royalties (if not on lump-sum basis)
Sent to 'Evaluation' and
Research & Development
Taxes (property)
Financing (interest)
Plant Overhead =
Fixed Charges =
Insurance
Rent
Variable cost =
-
7/31/2019 Cost and Evaluation 111103
7/16
Construction inflation rate, fraction/y = 0.02Expenditures, entries must be negative Product price inflation rate, fraction/y = 0
TPC inflation rate, fraction/y = 0.02
Annual-compounding discount rate, fraction/y = minimum acceptable rate of return, mar = 0.15
Continuous-compounding discount rate, fraction/y = minimum acceptable rate of return, rma= 0.14
Income tax rate = 0.35Comments and notes begin in column S RESULT
-3 -2 -1 0 1 2 3 4 5 6 7 8 9 10
0.00 0.00 0.00 0.00 0.00
2. Fixed Capital Investment, 106$ -7.32 -17.42 -25.38 -50.11
3. Working Capital, 106
$ (see notes) -8.85 8.85 0.004. Salvage Value, 10
6$ 0.00 0.00
5. Total Capital Investment, 106$ -7.32 -17.42 -34.23 -58.96
6. Annual Investment, 106$ 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7. Start-up cost, 106$ -5.01
8. Operating rate, fraction of capacity 0.50 0.90 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9. Annual sales, 106$ 25.50 45.90 51.00 51.00 51.00 51.00 51.00 51.00 51.00 51.00 479.40
-17.93 -26.76 -29.45 -30.04 -30.64 -31.25 -31.88 -32.51 -33.17 -33.83 -297.45
11. Annual depreciation factor, 1/y 0.20 0.320 0.192 0.115 0.115 0.058
12. Annual depreciation, 106
$/y 10.02 16.04 9.62 5.77 5.77 2.89 50.1113. Annual Gross Profit, 10
6$ -7.47 3.11 11.93 15.19 14.59 16.86 19.12 18.49 17.83 17.17 126.82
14. Annual Net Profit, 106$ -7.47 2.02 7.75 9.87 9.48 10.96 12.43 12.02 11.59 11.16 79.82
15. Annual operating cash flow,106$ 2.56 18.06 17.38 15.65 15.25 13.85 12.43 12.02 11.59 11.16 129.93
16. Total annual cash flow, 106$ 0.00 -7.32 -17.42 -34.23 2.56 18.06 17.38 15.65 15.25 13.85 12.43 12.02 11.59 11.16 70.97
17. Cumulative cash position, 106$ 0.00 -7.32 -24.74 -58.96 -56.41 -38.35 -20.98 -5.33 9.92 23.77 36.20 48.22 59.81 70.97
Profitability measures, time value of money NOT included:
18. Return on investment, ave. %/y 13.5
19. Payback period, y 3.9
-0.86 at mar = 15.0 %/y
Default values, can be changed
Required, user must supply
ECONOMIC EVALUATION CURRENT, i.e. INFLATED, DOLLARS
Required, may be calculated here, in linkedworksheet, or entered manually
Project identifier: Illustration 101
10. Annual Total Product Cost,
depreciation not included,106$
Year ending at time
20. Net return, 106$
1. Land, 106$ (see notes)
Row
Sum
-
7/31/2019 Cost and Evaluation 111103
8/16
Profitability measures including time value of money, with ANNUAL END-OF-YEAR cash flows and discounting
1.52 1.32 1.15 1.00 0.87 0.76 0.66 0.57 0.50 0.43 0.38 0.33 0.28 0.25
0.00 -9.68 -20.03 -34.23 2.22 13.65 11.42 8.95 7.58 5.99 4.67 3.93 3.30 2.76 0.53
0.53 at discount rate= 15.0 %/y
15.2
Iterated discount rate= 0.152
1.53 1.33 1.15 1.00 0.87 0.75 0.65 0.57 0.49 0.43 0.37 0.32 0.28 0.24
0.00 -9.71 -20.06 -34.23 2.22 13.61 11.37 8.89 7.52 5.93 4.62 3.88 3.25 2.71 0.00
Profitability measures including time value of money, with CONTINUOUS cash flows and discounting
1.63 1.42 1.23 1.07 0.93 0.81 0.71 0.61 0.53 0.46 0.40 0.35 0.31 0.27
0.00 -10.39 -21.50 -36.74 2.39 14.65 12.26 9.60 8.14 6.42 5.02 4.22 3.54 2.96 0.57
0.57 at discount rate= 14.0 %/y
14.1
Iterated discount rate= 0.141
1.64 1.43 1.24 1.07 0.93 0.81 0.70 0.61 0.53 0.46 0.40 0.35 0.30 0.26
0.00 -10.43 -21.55 -36.77 2.38 14.62 12.21 9.55 8.08 6.37 4.96 4.17 3.49 2.92 0.00
30. Discounted cash flow rate ofreturn, DCFR, %/y =
23. Net present worth, 106$ =
27. Present worth factor
24. Discounted cash flow rate of
return, DCFR, %/y =
25. Present worth factor26. Present worth of annual cash
flows, 106$
21. Present worth factor22. Present worth of annual cash
flows, 106$
31. Present worth factor
32. Present worth of annual cash
flows 106
To get DCFR, go to "Tools" and function "Solver." Set target cell as $R$41, to be made = 0 by
changing cell $C$39. Solver must be rerun after a change on any sheet.
To get DCFR, go to "Tools" and function "Solver." Set target cell as $R$51, to be made = 0 bychanging cell $C$49. Solver must be rerun after a change on any sheet.
28. Present worth of annual cash
flows 106$
29. Net present worth, 106$ =
-
7/31/2019 Cost and Evaluation 111103
9/16
-
7/31/2019 Cost and Evaluation 111103
10/16
COMMENTS & NOTES
Time -3 is default time of estimate, time -2 is the first inflation.
Time 0 is startup time.
Working capital (-) at time 0, (+) when recovered.Salvage value is (+) at time of recovery.
Planned investments (e.g. replacements) entered here at inflated value.
Startup default is 10% of FCI.Two year ramp-up of production.
Operating rate affects only variable part of TPC.
Depreciation default is 5-year MACRS.
Start costs subtracted here.
No income tax credit taken for losses.
=Annual operating cash flow + Annual investment
ROI, PBP and Net return do NOT include recovery amounts, by text definition.
Compare with ROI = 15.0 %/y
Compare with reference PBP = 3.6 y.
Compare with net return = 0.
Land can be included, default is 0.
-
7/31/2019 Cost and Evaluation 111103
11/16
NPW and DCFR include recovery amounts, by text definition.
Uses single-year present worth factor from Table 7-3.
Compare with net present worth = 0.
NPW and DCFR include recovery amounts, by text definition.
Uses 1-year present worth factor from Table 7-5.
Compare with net present worth =0.
"No value" results from a negative cash flow in R26.
Compare with R6
If there is more than one sign change in the annual cash flow, check DCFR value separately.
If there is more than one sign change in the annual cash flow, check DCFR value separately.
"No value" results from a negative total cash flow in R27.Compare with R5.
-
7/31/2019 Cost and Evaluation 111103
12/16
-
7/31/2019 Cost and Evaluation 111103
13/16
Construction inflation rate, fraction/y = 0.02Expenditures, entries must be negative Product price inflation rate, fraction/y = 0
Default values, can be changed TPC inflation rate, fraction/y = 0.02
Required, user must supply Annual-compounding discount rate, fraction/y = minimum acceptable rate of return, mar = 0.15
Continuous-compounding discount rate, fraction/y = minimum acceptable rate of return, rma= 0.14
Income tax rate = 0.35
Comments and notes begin in column S RESULT
Row
-3 -2 -1 0 1 2 3 4 5 6 7 8 9 10 Sum
0.00 0.00 0.00 0.00 0.00
2. Fixed Capital Investment, 106$ -7.61 -17.77 -25.38 -50.76
3. Working Capital, 10
6
$ (see notes) -8.96 8.96 0.004. Salvage Value, 10
6$ 0.00 0.00
5. Total Capital Investment, 106$ -7.61 -17.77 -34.34 -59.72
6. Annual Investment, 106$ 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7. Start-up cost, 106$ -4.98
8. Operating rate, fraction of capacity 0.50 0.90 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9. Annual sales, 106$ 25.00 44.12 48.06 47.12 46.19 45.29 44.40 43.53 42.67 41.84 428.21
-17.58 -25.72 -27.75 -27.75 -27.75 -27.75 -27.75 -27.75 -27.75 -27.75 -265.31
11. Annual depreciation factor, 1/y 0.20 0.320 0.192 0.115 0.115 0.058
12. Annual depreciation, 106
$/y 9.95 15.61 9.18 5.40 5.30 2.60 48.0413. Annual Gross Profit, 10
6$ -7.51 2.79 11.12 13.96 13.15 14.94 16.65 15.78 14.92 14.09 109.88
14. Annual Net Profit, 106$ -7.51 1.81 7.23 9.08 8.54 9.71 10.82 10.25 9.70 9.16 68.80
15. Annual operating cash flow,106$ 2.44 17.42 16.41 14.48 13.84 12.31 10.82 10.25 9.70 9.16 116.84
16. Total annual cash flow, 106$ 0.00 -7.61 -17.77 -34.34 2.44 17.42 16.41 14.48 13.84 12.31 10.82 10.25 9.70 9.16 57.12
17. Cumulative cash position, 106$ 0.00 -7.61 -25.38 -59.72 -57.28 -39.85 -23.44 -8.96 4.88 17.18 28.01 38.26 47.96 57.12
Profitability measures, time value of money NOT included:
18. Return on investment, ave. %/y 11.5
19. Payback period, y 4.3
-2.08 at mar = 15.0 %/y
ECONOMIC EVALUATION CONSTANT, YEAR-0 DOLLARS
Project identifier: Illustration 101
Required, may be calculated here, in linked
worksheet, or entered manually
Year ending at time
1. Land, 106$ (see notes)
10. Annual Total Product Cost,
depreciation not included,106$
20. Net return, 106$
-
7/31/2019 Cost and Evaluation 111103
14/16
Profitability measures including time value of money, with ANNUAL END-OF-YEAR cash flows and discounting
1.52 1.32 1.15 1.00 0.87 0.76 0.66 0.57 0.50 0.43 0.38 0.33 0.28 0.25
0.00 -10.07 -20.43 -34.34 2.12 13.18 10.79 8.28 6.88 5.32 4.07 3.35 2.76 2.26 -5.83-5.83 at discount rate= 15.0 %/y
12.9
Iterated discount rate= 0.129
1.44 1.27 1.13 1.00 0.89 0.78 0.69 0.62 0.54 0.48 0.43 0.38 0.34 0.30
0.00 -9.71 -20.06 -34.34 2.16 13.67 11.40 8.91 7.54 5.94 4.63 3.88 3.25 2.72 0.00
Profitability measures including time value of money, with CONTINUOUS cash flows and discounting
1.63 1.42 1.23 1.07 0.93 0.81 0.71 0.61 0.53 0.46 0.40 0.35 0.31 0.27
0.00 -10.81 -21.93 -36.86 2.28 14.14 11.58 8.88 7.39 5.71 4.37 3.60 2.96 2.43 -6.26
-6.26 at discount rate= 14.0 %/y
12.1
Iterated discount rate= 0.121
1.53 1.36 1.20 1.06 0.94 0.83 0.74 0.65 0.58 0.51 0.45 0.40 0.36 0.32
0.00 -10.32 -21.33 -36.51 2.30 14.53 12.12 9.47 8.02 6.32 4.92 4.13 3.46 2.89 0.00
To get DCFR, go to "Tools" and function "Solver." Set target cell as $R$41, to be made = 0 by
changing cell $C$39. Solver must be rerun after a change on any sheet.
To get DCFR, go to "Tools" and function "Solver." Set target cell as $R51, to be made = 0 by
changing cell $C$49. Solver must be rerun after a change on any sheet.
31. Present worth factor
23. Net present worth, 106$ =
22. Present worth of annual cash
flows, 106$
27. Present worth factor
24. Discounted cash flow rate of
return, DCFR, %/y =
25. Present worth factor26. Present worth of annual cash
flows 106$
21. Present worth factor
32. Present worth of annual cash
flows, 106$
28. Present worth of annual cash
flows 106$
29. Net present worth, 106$ =
30. Discounted cash flow rate of
return, DCFR, %/y =
-
7/31/2019 Cost and Evaluation 111103
15/16
COMMENTS & NOTES
Time -3 is default time of estimate, time -2 is the first inflation.
Time 0 is startup time.
Working capital (-) at time 0, (+) when recovered.Salvage value is (+) at time of recovery.
Planned investments (e.g. replacements) entered here at inflated value.
Startup default is 10% of FCI.Two year ramp-up of production.
Operating rate affects only variable part of TPC.
Depreciation default is 5-year MACRS.
No income tax credit taken for losses.
=Annual investment + Annual operating cash flow
ROI, PBP and Net return do NOT include recovery amounts, by text definition.
Compare with ROI = 15.0 %/y
Compare with reference PBP = 3.6 y.
Compare with net return = 0.
Land can be included by replacing the default 0. Land is (-) at time 0, (+) when recovered
-
7/31/2019 Cost and Evaluation 111103
16/16
NPW and DCFR include recovery amounts, by text definition.
Uses single-year present worth factor from Table 7-3.
Compare with net present worth = 0.
NPW and DCFR include recovery amounts, by text definition.
Uses 1-year present worth factor from Table 7-5.
Compare with net present worth =0.
"No value" results from a negative cash flow in R26.
Compare with R6
"No value" results from a negative total cash flow in R27.Compare with R5.
If there is more than one sign change in the annual cash flow, check DCFR value separately.
If there is more than one sign change in the annual cash flow, check DCFR value separately.