Cost Allocation Proposals associated with MISO Transmission Expansion

14
Cost Allocation Cost Allocation Proposals associated Proposals associated with MISO Transmission with MISO Transmission Expansion Expansion WIEG Board Meeting WIEG Board Meeting May 6, 2010 May 6, 2010 Presented by: Presented by: Kavita Maini, Principal Kavita Maini, Principal KM Energy Consulting, LLC KM Energy Consulting, LLC Protecting Y our Bottom Line Protecting Y our Bottom Line

description

Cost Allocation Proposals associated with MISO Transmission Expansion WIEG Board Meeting May 6, 2010. Presented by: Kavita Maini, Principal KM Energy Consulting, LLC. Midwest Independent System Operator (MISO). MISO: 2010 Generation Capacity Breakdown. Designated Capacity: 131,284 MW - PowerPoint PPT Presentation

Transcript of Cost Allocation Proposals associated with MISO Transmission Expansion

Page 1: Cost Allocation Proposals associated with MISO Transmission Expansion

Cost Allocation Proposals associated Cost Allocation Proposals associated with MISO Transmission Expansionwith MISO Transmission Expansion

WIEG Board MeetingWIEG Board MeetingMay 6, 2010May 6, 2010

Presented by:Presented by:Kavita Maini, PrincipalKavita Maini, Principal

KM Energy Consulting, LLCKM Energy Consulting, LLC

Protecting Your Bottom LineProtecting Your Bottom Line

Page 2: Cost Allocation Proposals associated with MISO Transmission Expansion

Midwest Independent System Operator (MISO)

2

Page 3: Cost Allocation Proposals associated with MISO Transmission Expansion

MISO: 2010 Generation Capacity Breakdown

3

Designated Capacity:131,284 MW

Demand: 104,288 MW

Reserve Margin:25.9%

Page 4: Cost Allocation Proposals associated with MISO Transmission Expansion

2009 MISO Transmission Expansion Plan

Appendix A: Approved Projects ($903 M approved in 2009; $7.2 Billion to date)

Appendix B: Probable Projects, $1.5 Billion

Appendix C: Conceptual Projects, $23 Billion

4

Page 5: Cost Allocation Proposals associated with MISO Transmission Expansion

Current Cost Allocation Methodology

5

Reliability Based Transmission Upgrades – Methodology results in localized allocation of costs with 20% socialization for lines 345 KV and above

Economic Based Transmission Upgrades – Based on economics (production costs and energy prices) with 20% socialization for lines 345 KV and above; benefit/cost threshold to be at least 3:1

Generator Interconnections – 345KV and above used to be 50% to generator, 40% to transmission owner, 10% socialized; Temporary solution (2009) 90% generator, 10% socialized to fix the “Otter Tail Problem”

Page 6: Cost Allocation Proposals associated with MISO Transmission Expansion

Revisiting Cost Allocation

MISO needs to make a compliance filing on July 15, 2010 Provide a permanent solution to generation

interconnection related upgrades Resources located remotely from load result Now, even cost allocation methodologies associated

with reliability and economics open for debate and discussion

6

Page 7: Cost Allocation Proposals associated with MISO Transmission Expansion

Cost Allocation Principles and Methods

Beneficiaries /cost causers pay – License Plate High voltage benefits longer distances and

therefore, region wide benefits – Postage Stamp FERC was remanded on its approval of PJM’s

Postage Stamp method by Circuit Court of Appeals for 500 KV and above

7

Page 8: Cost Allocation Proposals associated with MISO Transmission Expansion

8

Current Initiatives Investigating Transmission Planning and Cost Allocation

CARP(Regulatory)

RECB(MISO

Stakeholders)

MISO Transmission Planning

CARP= Cost Allocation & Regional PlanningRECB = Reliability Expansion Costs & Benefits

MTEP/ Proposed Tariff Language for Cost Allocation

Page 9: Cost Allocation Proposals associated with MISO Transmission Expansion

Transmission Expansion - Cost Allocation Issues

9

What should be cost shared?

How should it be cost shared?

How should it be recovered?

•Reliability •Economic•RPS/other mandates

• Regional/Local• Generators/Load/ Export

• $/KWh• $/KW

Page 10: Cost Allocation Proposals associated with MISO Transmission Expansion

How MISO Discussion Started on Cost Allocation – Injection/Withdrawal

10

Injection/WithdrawalMethod –Annual RevenueRequirements

Regional ($/MWH)

ENG. ANALYSIS

Local($/MW

Load

Generators

Exports

Load

Generators

Planning/What goes into Appendix A

Page 11: Cost Allocation Proposals associated with MISO Transmission Expansion

How MISO Discussion Started on Cost Allocation – Mostly Withdrawal

11

Injection/WithdrawalMethod –Annual RevenueRequirements

Regional ($/MWH)

ENG. ANALYSIS

Local($/MW

Load

Generators

Exports

Load

Generators

Planning/What goes into Appendix A

Page 12: Cost Allocation Proposals associated with MISO Transmission Expansion

MISO Cost Allocation Proposal

12

ISSUE MISO TRANS. OWNERS REGULATORS

Cost Share Eligibility Reliability, Economics, Policy Mandates

Policy Mandates Economics and Policy Mandates

Cost Sharing Split Local and Regional determined by Eng. Analysis

Regional – Overlay and Underbuild

Regional – Overlay and Underbuild

Who Pays? Load and Export – RegionalLoad and Generators - Local

Load and Exports Load (80%) & Generation (20%)

Gen. Interconnection Higher of local access rate or local portion of network upgrade costs

Generators 80%;Load 20%

Higher of local access rate or local portion of network upgrade costs

Rate Design $/MWh - Regional$/MW - Local

$/MW $/MWh

Page 13: Cost Allocation Proposals associated with MISO Transmission Expansion

What are the relative cost impacts?

Cost bucket magnitude between proposals not certain RPS related transmission overlay plus underbuild =

$30 Billion for current RPS standards by 2024 MISO projects to date (2003-2009) $7.2 Billion ;

future reliability, economic, etc..???

13

Page 14: Cost Allocation Proposals associated with MISO Transmission Expansion

Guiding Principles

Cost and benefit threshold at the planning stage and feedback loop for assessing projects that should be eligible for cost sharing

A methodology where the right load pays internal and external to the footprint

Rate design where fixed costs are represented in a demand charge

14