Digital Interactivity: Unanticipated Consequences for Markets ...
CORRECTIVE ACTION PLAN ON UNANTICIPATED IMPACTS ... - SUDIP
Transcript of CORRECTIVE ACTION PLAN ON UNANTICIPATED IMPACTS ... - SUDIP
CORRECTIVE ACTION PLAN ON UNANTICIPATED IMPACTS
LARP1 AND LARP3
Armenia: Sustainable Urban Development Investment Program Tranche 1
Project Number: 42417
Loan Number: L2752
Prepared: July 2015
Prepared by the Yerevan Municipality
Yerevan Project Implementation Unit
ABBREVATIONS
ADB Asian Development Bank
AF Affected Family
AP Affected Person
AH Affected Household
AMD Armenian Dram
DESC Detailed Engineering and Construction Supervision Consultant
DMS Detailed Measurement Survey
LAR Land Acquisition and Resettlement
LARF Land Acquisition and Resettlement Framework
LARP Land Acquisition and Resettlement Plan
YM Municipality of Yerevan
PIU Project Implementation Unit
RA Republic of Armenia
SES Socioeconomic Survey
SPS Safeguard Policy Statement
SRS Social and Resettlement Specialist
USD American Dollar
TABLE OF CONTENTS
1 INTRODUCTION ...................................................................................................... 4 1.1 Procedures to be initiated due to new project impact cases (changes) emerged during the LARP implementation ................................................................................... 4 1.2 Background to the design changes ...................................................................... 5
2 IMPACT ASSESSMENT AND CENSUS OF AFFECTED HOUSEHOLDS ............. 7 2.1 Background ............................................................................................................ 7 2.2 Survey Methodology .............................................................................................. 7 2.3 Impact on Land ....................................................................................................... 8
2.3.1 Land classification by the Armenian Land Code...................................................... 8 2.3.2 Land Losses ........................................................................................................... 8
2.4 Impact on Building and Structures ....................................................................... 9 2.4.1 Permanent and Movable Structures ........................................................................ 9 2.4.2 Fences and Improvements ..................................................................................... 9
2.5 Crops ..................................................................................................................... 10 2.6 Trees ..................................................................................................................... 10 2.7 Census of Affected Households and Affected Persons .................................... 11
2.7.1 Gender and Ethnicity of APs ..................................................................................12 2.7.2 Impact on Poor and Vulnerable Groups .................................................................12
3 RESSETLEMENT BUDGET .................................................................................. 13 3.1 Background .......................................................................................................... 13 3.2 Sources and Allocation of Funds ........................................................................ 13 3.3 Compensation for Acquired Land ....................................................................... 13
3.3.1 Valuation Approach ...............................................................................................13 3.4 Compensation for Buildings, Structures and Improvements ............................ 14
3.4.1 Non Residential Buildings ......................................................................................14 3.4.2 Fences and Improvements ....................................................................................14
3.5 Compensation for Crops and Trees .................................................................... 15 3.5.1 Crops .....................................................................................................................15 3.5.2 Fruit Trees .............................................................................................................15 3.5.3 Wood Trees ...........................................................................................................17
3.6 Relocation Allowances ........................................................................................ 18 3.7 Budget (Cost) Summary ...................................................................................... 19
4 CONSULTATION AND INFORMATION DISCLOSURE ....................................... 19 4.1 Meeting with APs .................................................................................................. 19 4.2 Signing of Protocol, Agreements and Contract ................................................. 20
1.1 Procedures to be initiated due to new project impact cases (changes)
emerged during the LARP implementation
1. Due to some changes in design or/and issues not envisaged during the project preparation, some additional land acquisition cases emerged at the Artashat Highway Section covered by LARP 1 and the New Shirak Street Section, covered by LARP 3. The following paragraphs (1-4) summarize steps that will be taken by the PIU when the impacts defined by LARP 1 and LARP 3 are changed during the LARP implementation:
(i) Surface of land plots to be acquired is changed:
(ii) The recalculation of compensation price will be based on the same unit price for 1m
2 used for valuation of assets acquired under LARP (Valuation report) and
multiplied by the new affected area.
(iii) There are fixed improvements (crops, trees etc.) on the affected land:
2. Extent of impact and recalculation of the compensation amount will be based on measured and verified affected surface and valuated by using the established methodology and the unit rates used for other assets acquired under the LARPs 1 and 3. A new map (plan) will be prepared to define the verified acquired part of the land.
3. New private lands to be acquired during the project implementation stage are subject to the requirements set under the Negotiation Resettlement or Eminent Domain Government Decree, which will be initiated for the new lands. Appropriate procedures will be carried out as defined by the “RA Law on Alienation of the property for public and state purposes”, in particular:
(i) Public consultation will be organized for new APs (including the notification on Eminent Domain)
(ii) DMS/Census/SES will be initiated for the newly affected lands or other assets (such as, private trees on public land) and their owners
(iii) Appropriate maps (plans) will be prepared based on a detailed measurement
(iv) Description protocols will be developed and signed with the APs
(v) Valuation of assets will be done according to the valuation methodology approved for this LARP
(vi) Draft acquisition contracts will be notified and negotiated with APs to sign the contracts, otherwise the PIU will initiate an expropriation.
4. If other unforeseen issues/changes which would trigger new impact and due compensation, the appropriate mechanism to address it, will be developed and agreed with ADB. Such unforeseen changes will be verified and recorded by the external monitoring expert/firm in the compliance reports.
1 INTRODUCTION
1.2 Background to the design changes
5. Unanticipated impacts found under LARP1 and LARP3 in Artashat highway are caused by the design changes needed for the relocation of utilities and for providing accesses to the not-directly-affected properties.
6. Artashat highway: During the construction works in Artashat, a new industrial sewage pipeline was found. As the relevant information was not available during preparation of the utility design, relocation of the pipeline were not envisaged at that stage. The pipeline was buried deep 4m underground. It is 330m long and 4-5m wide which caused temporary effect on additional land area. As a result of pipe relocation, 2 land plots illegally used by 2 AHs, are temporary impacted. There are 8 fruit trees affected on these two land plots. Out of this, 6 trees are fruit-bearing and 2 are not-yet productive tree.
7. The utility design envisaged the water pipeline (see the blue line) to run under the Railway (see yellow lines) at Artashat highway (km 0+280 - km 0+320). The existing duct was fixed under the bridge (see the red circle) according to the Initial Survey conducted during the design preparation stage. The utility survey conducted prior to the construction works, revealed that the duct actually needs to be positioned a bit more to the right from the designed part (see the blue circle) on the relocation line (see green line). This caused a temporary effect on an illegally used land plot and resulted in cutting of 3 fruit-bearing trees. The affected trees belong to one household.
8. These new impacts are located at the area covered by LARP1. The land plots were temporarily affected during the placement of pipes; thus, only the inventory and valuation of permanently affected trees were conducted.
Figure 1-1 Water pipeline relocation Map
9. Artashat highway-New Shirak roundabout (km 0+100-km 0+180): It has become necessary to shift the alignment of the bridge at Km 0+140 оn Artashat highway in order to accommodate а service road to provide access to adjacent owners. This area refers to LARP 3. The change in the alignment resulted in an impact on 1 owned and 2 illegally used land-plots with 1,775.9 m
2
affected area, 1 permanent affected (34.97 m2) and 2 movable structures, 56 l.m fence, 34.1 m
2
concrete area, 192 m2 cable In total, 343 fruit trees, 56 wood trees and 400m
2 crop are affected
on 2 illegally held land plots used as an orchard.
Figure 1-2 Map of shifted design
2.1 Background
10. For this document, the data was prepared in May - June 2015. As the impact under LARP 1 is a temporary impact on illegally used land which became usable immediately after the placement of the pipes, only the inventory and valuation of permanently affected trees were conducted. In order to accurately assess the extent of the unanticipated impacts under LARP3, the following surveys were undertaken:
(i) Detailed Measurement Survey (DMS) - to measure the affected area of the lands, buildings space and the number and types of affected assets.
(ii) Inventory of Losses- to identify and evaluate the characteristics of the land, buildings and assets to be acquired.
(iii) Valuation of Replacement Cost of the Affected Assets - to identify the cost of compensation of lost assets, income and other livelihood sources and allowances for development of the LAR budget.
(iv) Census Survey - to identify the exact number of AHs and their members, including some elementary social characteristics such as gender and ethnicity.
2.2 Survey Methodology
11. The scope of the DMS and assets inventory included identification, classification, measurement and valuation of the following assets, or attributes:
(i) Land (agricultural, residential, industrial and commercial plots), including improvements on affected land
(ii) Buildings/structures (non-residential structures, including classification by building category and construction type)
(iii) Legal status of the AP land occupancy
(iv) Area and type of crops
(v) Number and type of trees
2 IMPACT ASSESSMENT AND CENSUS OF AFFECTED
HOUSEHOLDS
2.3 Impact on Land
2.3.1 Land classification by the Armenian Land Code
12. Based on the actual usage, the affected land categories are grouped into commercial and agricultural categories.
(i) Agricultural Land, which is used to grow some fruit or wood/ decorative trees and bushes.
(ii) Commercial Land, which is used for businesses such as shops, car repair stations and petrol stations.
2.3.2 Land Losses
13. Affected land-plots are located in Artashat highway covered by LARP 3. In total, there are 3 land plots covering surface area of 1,775.90 m². Two land plots (1,461.50 m2) are categorized as agriculture land as are used to grow orchards. The third land plot is used for the commercial purposes. Overall, 3 households are affected by impact on land. (Table 2-1)
14. Based on the legal status, the affected land plots are categorized as private and community land:
(i) Private-titled land - 1 land plot belongs to a person having a legal title over the affected land parcels;
(ii) Community land - this is the land that belongs to the communities. The survey found that 2 land plots are illegally used by 2 APs without any legal title.
Table 2-1 Land impact
LARP 3
Type of Land
Commercial Agriculture Total
No of AH
No of Land plots
m2
No of AH
No of Land plots
m2
No of AH
No of Land plots
m2
Private 1 1 314.40 - - - 1 1 314.40
Community land (illegally used)
- - - 2 2 1,461.50 2 2 1,461.50
Total 1 1 314.40 2 2 1,461.50 3 3 1,775.90
2.4 Impact on Building and Structures
2.4.1 Permanent and Movable Structures
15. In total, two1 households will have some impact on structures. Two households have a temporary
impact as their structures are movable (Table 2-3). There is only one affected illegal structure with an area of 34.97m
2. The structure is a metal shed located on the legally used land plot.
(Table 2-2).
Table 2-2 Impact on Permanent Structure
LARP 3
Type of affected structure
Construction type
Building Affected surface
Land plots AH Legal Illegal total
No m2 m
2 m
2 No Usage type No
Shed Metal 1 - 34.97 34.97 1 owned 1
16. Two movable structures, one shop and one non-operating greenhouse, will be affected. Dismantling and assembling as well as the transportation costs as per the LARP entitlements, will be provided to the APs to relocate structures. (Table 2-3)
Table 2-3 Impact on Movable Structure
LARP 3
Type of affected structure
Construction type
Building Affected surface
Land plots AH
No m2 No Usage type No
Shop Metal 1 22.16 1 Legally used 1
Non-operating greenhouse
Metal 1 140 1 Illegally used 1
Total 2 162.16 2 - 2
2.4.2 Fences and Improvements
17. A total of 56 linear meters of fence and 226.1m² of improvements made by the AP on 1 land plot is measured and valuated for compensation. These are 34.1m
2 concrete area 42m of metal pillar
and 150m Cable. (Tables 2-3, 2-4)
Table 2-4 Impact on Fence
LARP 3
Material Length Land plots AH
M No No
Metal fence 56.0 1 1
1 1 AH has a 1 permanent affected shed and 1 movable shop.
Table 2-5 Impact on Improvements
LARP 3
Type Material Land plots Area Length AH
No m2 l.m No
Area Concrete
1
34.1 -
1 Cable - - 150
Pillar Metal - 42
Total 1 34.1 192 1
2.5 Crops
18. There will be 400 m2 of greens (seed) on 1 plots used by 1AH under LARP 3. There were not any
crops affected on the land plots under LARP 1.
Table 2-6 Impact on Crops
LARP 3
Type of crop
Affected
area
Annual
productivity Land plots AH
m² kg/ m² No No
Greens (seed) 400 0.3 1 1
Total 400 - 1 1
2.6 Trees
19. Total 354 fruit trees will be affected, 295 of which are productive. Out of this, 343 fruit trees are included in LARP 3 and 11 fruit trees are included in LARP 1.
20. Most of the affected bushes are dewberries and grapes and of the affected trees are Dwarf (Malus pumila) apples, peaches and cherries. In total, 2 households under LARP 3 and 3 households under LARP 1 will be affected by fruit trees and bushes loss. A summary of information on the affected fruit bushes and trees is presented in the following table.
Table 2-7 Impact on Fruit Trees
Type of tree Seedling
Not yet productive
Productive Total Land plot
AH
No No No No No No
LARP 3
Cherry - 1 24 25
2 2
Peach - 19 7 26
Walnut - 8 6 14
Fig - - 3 3
Mulberry 1 1 4 6
Grape 4 8 27 39
Apple 1 - 10 11
Type of tree Seedling
Not yet productive
Productive Total Land plot
AH
No No No No No No
LARP 3
Apricot - 1 5 6
Dwarf apple (Malus Pumila)
12 - 71 83
Dewberry - - 120 120
Plum (shlor) - - 1 1
Plum - - 3 3
Quince - - 3 3
Pear - - 1 1
Hazelnut - 1 1 2
Subtotal 18 39 286 343
LARP 1
Pear - 1 - 1
3 3
Apple - 1 1 2
Apricot - - 3 3
Plum(shlor) - - 1 1
Quince - - 1 1
Mulberry - - 2 2
Walnut - - 1 1
Subtotal - 2 9 11
Grand Total 18 41 295 354 5 5
21. There will be 56 wood trees affected by the LARP 3 section. The most affected is poplar (43). Of all affected trees, about 76.8% are seedlings. 2 households will be affected by loss of wood trees. There are no affected wood trees on the land plots under LARP 1.
Table 2-8 Impact on Wood Trees
LARP 3
Type Seedling
Medium growth
Full growth
Total Land plot
AH
No No No No No No
Ash tree 6 7 - 13
2 2 Poplar 40 - 3 43
Total 46 7 3 56
2.7 Census of Affected Households and Affected Persons
22. The Census identified 6 affected families with a total of 30 members. 3 AHs were already included in the LARP 1. Remaining 3 AHs are newly affected.
Table 2-9 Affected AH and APs
Section AH AP
No No
LARP 3 3 13
LARP 1 3 17
Total 6 30
2.7.1 Gender and Ethnicity of APs
23. The Census data shows that the number of female APs is 16 (53%) of the total number of APs and male 14 (47%). All APs are Armenians.
Table 2-10 Gender Profile of Affected Persons
Gender AH Members
No % of the total
Male 14 47
Female 16 53
Total 30 100
2.7.2 Impact on Poor and Vulnerable Groups
24. The Census data shows that there are no poor2, woman and elderly headed households affected
by these unforeseen impacts.
2 As defined in the LARF.
3.1 Background
25. This chapter describes the methodology adopted for the determination of unit rates, cost of LAR and compensation that will be paid to APs for the unanticipated impacts caused by sections of LARP 3 and LARP 1. The compensation entitlements of different categories of APs presented in this chapter have been defined according to the principles adopted in the LARF. The compensation rates were determined by a certified independent evaluator using transparent methodology that was accepted by the ADB, the PIU/YM and GoA.
3.2 Sources and Allocation of Funds
26. As the LARP 1 Project is closed, all compensation costs of unanticipated impacts measured and valuated under LARP 3 and LARP 1 will be covered by the funds of LARP 3. The compensation costs will be financed from the following sources:
27. The PIU should undertake measures to request funds from the relevant financing sources needed for implementation of LARP 3 and timely allocate them to APs transferring to the AP's individual account opened in his/her name in a commercial bank operating in the RA.
3.3 Compensation for Acquired Land
3.3.1 Valuation Approach
28. For the valuation of all unanticipated impacts was applied the same methodology defined in the previous LARPs. Compensation to Legal Land Owners and Rehabilitation Allowance for Illegally Used Land
29. The compensation to be paid to legal land owners was calculated at replacement cost plus addition of 15% which is in accordance with the RA Law on Eminent Domain. The total cost for the compensation to legal landowners is 10,521,396.00 AMD.
30. The rehabilitation allowance for illegally used land will amount to 25% of the market value of the land. In total 1,806,092.19 AMD for 1,461.50 m² will be paid to illegal users of Yerevan Municipality land as a rehabilitation allowance for their livelihood losses.
Table 3-2 Compensation for Private and Community land
LARP 3
3 RESSETLEMENT BUDGET
Land category
Type
Land plot
Affected area
Unit price
Total cost Total
compensation (+15%)
Total compensation
(+25%) Total
No m2 AMD AMD AMD AMD AMD
Commercial Private 1 314.40 29,100.0 9,149,040.0 10,521,396.00 - 10,521,396.00
Agriculture Community
land 2 1,461.50 4,943.12 7,224,368.78 - 1,806,092.19 1,806,092.19
Total 3 1,775.90 - 16,373,408.8 10,521,396.00 1,806,092.19 12,327,488.19
3.4 Compensation for Buildings, Structures and Improvements
3.4.1 Non Residential Buildings
31. In total, 430,830AMD for 1 affected structure with an area of 34.97 m², will be paid to non-legal users of structures as a result of land acquisition.
Table 3-4 Compensation for Non-residential building LARP 3
Type of affected structure
Construction type
Building Affected surface Unit
price Total Cost
Total Compensation
Legal Illegal total
No m2 m
2 m
2 AMD/m
2 AMD AMD
Shed Metal 1 - 34.97 34.97 15,400.0 538,538.0 430,830.0
3.4.2 Fences and Improvements
32. All improvements done by APs, regardless of their status, are subject to compensation. In total 782,650 AMD will be paid for different types of improvements. Compensation for affected fences amounts to 214,971 AMD.
Table 3-6 Compensation for Improvement LARP 3
Type Material Land plots Area Length Unit price Compensation
No m2 l.m AMD AMD
Area Concrete
1
34.1 - 6,500 221,650.00
Cable - - 150 1,500 225,000.00
Pillar Metal - 42 8,000 336,000.00
Total 1 34.1 192 - 782,650.00
Table 3-7 Compensation for Fence
LARP 3
Material Length
Land plots
Unit price
Market value Compensation for legal
(market value +15%)
M No AMD/m AMD AMD
Metal 56.0 1 3,338.0 186,931.0 214,971.0
3.5 Compensation for Crops and Trees
3.5.1 Crops
33. The crop compensation is 360,000AMD for greens/herbs (seed). Crop compensation will be paid in cash at market rate at the gross crop value of the expected annual harvest.
Table 3-8 Compensation for Crops
LARP 3
Type of crop
Affected area
Annual productivity
Price Sum
m² kg/ m² AMD/m² AMD
Greens (seed)
400 0.3 900 360,000
Total 400 - - 360,000
3.5.2 Fruit Trees
34. Compensation for fruit trees is different for productive, not yet productive trees and seedlings:
(i) Fruit bearing trees: compensation at replacement cost for lost income based on the net market value of one year’s income multiplied by the number of years needed to grow a fully productive tree.
(ii) Not-yet-fruit-bearing trees: regardless of their age these trees will be compensated at replacement cost of productive inputs for the number of years needed to grow a tree to the productive age.
(iii) Seedlings: compensation for the market value of the seedling
35. In total 18 fruit trees saplings will be compensated in the amount of 18,000 AMD. 41 not-yet productive trees will be compensated in amount of 284,243 AMD. 295 Fruit bearing trees and bushes will be compensated in amount of 8,497,327 AMD. The particulars of compensation for the affected seedlings and fruit-bearing trees are summarized in the following tables.
Table 3-9 Compensation for Seedling
LARP 3
Type Trees Seedling cost Total compensation
No AMD/tree AMD
LARP 3
Type Trees Seedling cost Total compensation
No AMD/tree AMD
Dwarf apple 12 1,000 12,000
Grape 4 750 3,000
Apple 1 1,000 1,000
Mulberry 1 2000 2000
Total 18 - 18,000
Table 3-10 Compensation for Not-yet Productive Trees
Not yet productive
Type of tree Trees
Not yet productive cost
Total compensation
No AMD/tree AMD
LARP 3
Cherry 1 5,610 5,610
Peach 19 3,211 61,009
Walnut 8 14,896 119,168
Mulberry 1 7,270 7,270
Grape 8 6,020 48,160
Apricot 1 10,610 10,610
Hazelnut 1 14,896 14,896
Subtotal 39 - 266,723
LARP 1
Apple 1 8,510 8,510
Pear 1 9,010 9,010
Grand Total 41 - 284,243
Table 3-11 Compensation for Fruit Bearing Trees Fruit bearing trees
Type of tree
Affected trees
Annual yield
Unit cost
Years to regrow to productive
level
Unit cost per tree
Total compensation
No kg AMD/kg No AMD AMD
LARP3
Cherry 24 20 308.1 4 24,648 591,552
Peach 7 40 327 3 39,240 274,680
Walnut 6 30 1118 6 201,219 1,207,314
Fig 3 25 700 4 70,000 210,000
Mulberry 4 90 400 4 144,000 576,000
Grape 27 25 321.5 4 32,150 868,050
Apple 10 50 333.7 6 100,110 1,001,100
Fruit bearing trees
Type of tree
Affected trees
Annual yield
Unit cost
Years to regrow to productive
level
Unit cost per tree
Total compensation
No kg AMD/kg No AMD AMD
LARP3
Apricot 5 80 374.75 6 179,880 899,400
Dwarf apple (Malus Pumila)
71 15 334 6 4,008 284,568
Dewberry 120 2 600 3 3,600 432,000
Plum(shlor) 1 25 250 5 31,250 31,250
Plum 3 30 321 4 38,520 115,560
Quince 3 25 824.1 6 123,615 370,845
Pear 1 60 642.15 6 231,174 231,174
Hazelnut 1 20 1000 6 120,000 120,000
Sub Total 286 - - - - 7,213,493
LARP 1
Apple 1 50 333.7 6 100,110 100,110
Apricot 3 80 374.75 6 179,880 539,640
Plum(shlor) 1 25 250 5 31,250 31,250
Quince 1 25 824.1 6 123,615 123,615
Mulberry 2 90 400 4 144,000 288,000
Walnut 1 30 1118 6 201,219 201,219
Sub Total 9 - - - - 1,283,834
Grand Total 295 - - - - 8,497,327
3.5.3 Wood Trees
36. The compensation for wood trees is different for seedlings, medium growth and fully grown trees:
(i) Saplings: compensation at replacement cost of productive inputs. Seedlings are defined as trees with a diameter up to 12 cm.
(ii) Medium and fully-grown trees: compensation at replacement cost of wood value of the tree to be calculated based on the volume of the wood. Medium growth trees are defined as trees with a 12-36 cm diameter and fully grown trees as those with a diameter greater than 36cm.
37. Wood trees compensation amounts to 96,180 AMD for seedlings, 51,450 AMD for medium growth trees, as well as 253,890 AMD for fully grown trees with an overall total compensation of 401,520 AMD, as indicated in the following table.
Table 3-12 Compensation for Fruit Bearing Trees
Type
Seedling (up to 12 cm diameter) Medium growth (13-22cm) Full growth (22cm+) Total
No Unit cost Diameter Subtotal
No Unit cost Diameter Subtotal
No Unit cost Diameter Subtotal
No AMD AMD sm AMD AMD sm AMD AMD sm AMD
Ash tree 6 630 7 3,780 7 7,350 14 51,450 - - - - 13 55,230
Poplar 40 2310 1 92,400 - - - - 3 84,630 50 253,890 43 346,290
Total 46 - - 96,180 7 - - 51,450 3 - - 253,890 56 401,520
3.6 Relocation Allowances
38. The relocation allowances were calculated taking into account the costs that will be incurred for the transportation of movable assets. Transportation costs were determined according to the average cost for such services offered by several freight shipping organizations accepted in the market. It was calculated in such a manner that the AP can move his/her property within a 20 km. radius. The allowance is calculated for all APs that need to relocate their assets. In total 426,750AMD will be paid for the relocation of the assets of AHs.
Table 3-13 Transportation cost for movable structures
LARP 3
Type of allowance Trips required Unit rate Total
AMD AMD
Shop 1 90,000 90,000
Unfinished greenhouse 1 90,000 90,000
Transportation costs, big gabarites 7 35,250 246,750
Total 2 - 426,750
3.7 Budget (Cost) Summary
39. The total implementation cost of unanticipated impacts amounts to 23,743,779.19AMD which is equivalent to USD 50,198.26 as shown in the following table.
40. Table below presents the budget summary per source of financing.
Table 3-14 Summary Budget
Item Source of Finance
Total/AMD
I. Compensation Budget, Including Allowances
Compensation for private land (Including 15% surcharge) YM 10,521,396.00
Rehabilitation allowance for illegal land usage YM 1,806,092.19
Compensation for Non-residential Buildings ADB Loan 430,830.00
Compensation for Fences ADB Loan 214,971.00
Compensation for Improvements ADB Loan 782,650.00
Compensation for Crops ADB Loan 360,000.00
Compensation for Seedlings ADB Loan 18,000.00
Compensation for Not-yet productive trees ADB Loan 284,243.00
Compensation for fruit bearing trees ADB Loan 8,497,327.00
Compensation for wood trees ADB Loan 401,520.00
Transportation costs ADB Loan 246,750.00
Movable structures transportation costs ADB Loan 180,000.00
Total LAR budget (AMD) 23,743,779.19
Total LAR budget (USD) 50,198.26
473 AMD, Exchange rate on May 22 2015, Central Bank of the Republic of Armenia
4 CONSULTATION AND INFORMATION DISCLOSURE
4.1 Meeting with APs
41. PIU conducted working discussion with 5 APs on 12th and 15
th of June 2015. The aim of the
meetings was to inform affected persons about unforeseen impacts which are the result of
the design changes. During the working discussions, the resettlement and social specialists of the Implementation team, presented to affected persons property description protocols, valuation reports and explained APs’ entitlements for compensation. The meeting was attended by the representatives of DESC and IMA.
4.2 Signing of Protocol, Agreements and Contract
42. The Description Protocols and compensation Agreements are signed with 5 APs, illegal land users, between 17-23 June, 2015. One Description protocol and Contract will be signed with the owner in the coming days.