Corrected Environmental Impact and Mitigation Measures(Final)

download Corrected Environmental Impact and Mitigation Measures(Final)

of 8

Transcript of Corrected Environmental Impact and Mitigation Measures(Final)

  • 8/11/2019 Corrected Environmental Impact and Mitigation Measures(Final)

    1/8

    CHAPTER 6

    ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

    6.1. Preamble

    The proposed Thevara-Perandoor canal project envisages the rejuvenation of the existing canals

    equipping them for safe navigation and for promoting recreation facilities along the bank for

    tourism promotion.The impact identification process covers two phases of the project,

    1. The construction phase

    2. The operational phase

    An Environmental Impact can be defined as an alteration of the existing environmentalconditions or the creation of new set of beneficial or adverse environmental consequences caused

    by the proposed activity

    6.1.1. IMPACT ON THE EXISTING WATER RESOURCES

    The Water requirement for this project is expected to emerge from two areas listed below:

    1. The water required for construction of embankements and reconstruction of bridges

    across the canals and the connecting roads.2. The irrigation requirements to sustain the greenery along the canal banks during the

    operational phase.

    This is expected to be catered from the existing water resources of KWA and bore wells.

    6.1.2. WATER QUALITY IMPACTS & THE PROTECTION OF

    AQUATIC ECOLOGY

    The primary concern with regard to water quality would be earthworks, demolition works and the

    control of construction site runoff and drainage. The water quality assessment concluded

    that the identified water quality impacts could be controlled by implementing there

    commended mitigation measures. Any effluent discharges from the site would

    be required to comply with the terms and conditions of a discharge licence. It was

  • 8/11/2019 Corrected Environmental Impact and Mitigation Measures(Final)

    2/8

    recommended that regular site inspections be undertaken toinspect the construction

    activities and works areas in order to ensure the recommended mitigation measures

    are properly implemented.The entire area forms a part of the wet lands that fall adjacent

    to the Vembanad Backwater system.These wet lands plays the role of Natures

    Kidneys.During the proceeding phases,due care is to be taken to protect the wet lands

    from damage .No discharge of pollutants is to be allowed into these areas. The natural

    rain water run off paths are not to be choked with waste materials.

    6.1.3. ECOLOGICAL IMPACTS

    There will be a minimal ecological impacts from proposed works and no long-term

    residual impact on ecology would be expected with implementation of proper mitigation

    measures recommended in the EIA Report for the Project.

    6.1.4. LANDSCAPE AND VISUAL IMPACTS

    It has recommended that the implementation and maintenance of landscape andvisual

    measures within the construction site including protection of existing resources,mitigation planting and surface treatment of structures be included.

    6.1.5. IMPACT ON CULTURAL HERITAGE

    The assessment of potential impact on cultural heritage concluded that no areas of

    archaeological interest were identified. As such, mitigation measures would notbe required .As the maj or it y of her it age resources are loca ted qu it e far from the

    proposed works, no adverse impacts associa ted wi th the cons truct ion works

    would be expected.

    6.1.6. WASTE MANAGEMENT IMPACT

    Waste management would be the contractors responsibility to ensure that all wastesproduced duringthe const ruction of the Project are handled, stored and di spo sed

    of in accordance with good waste management

    p r a c t i c e s , a n d G o v e r n m e n t r e g u l a t i o n s a n d r e q u i r e m e n t s .Waste generated during the construction activities should be audited periodically todetermine if wastes are being managed in accordance with approved procedures and the

    site Waste Management Plan. The audits should look at all aspects of waste management

    including waste generation, storage, transport and disposal. An appropriate audit programwould be to undertake a first audit near the commencement of the construction works,

    and then to audit on a quarterly basis thereafter. In addition, the routine site inspections

  • 8/11/2019 Corrected Environmental Impact and Mitigation Measures(Final)

    3/8

    should check the implementation of the recommended good site practices and other waste

    management mitigation measures.

    6.2.MITIGATION MEASURES

    The dredged material should not be allowed to accumulate along the canal banks.Arrangement

    are to be made for shifiting the dreged material immediately to an isolated location,where it will

    be disinfected and used as land fill. The dredged material has to be properly covered before

    being transported.

    During the construction phase, the dust generation from the earthwork, vehicular emissions and

    the occasional use of DG sets, in the event of power failure, are the sources of air pollution

    anticipated from the Project site. These are expected to be transient in nature and also localized

    to a limited area. Hence no impact on the air quality is anticipated during the construction phase

    and the Operational phase .Presently the putrification taking place in the water bodies is

    generating methane gas,which is polluting the air in the vicinity of the canals. the overall

    improvement to the environment around the canals,after rejuvenation, is expected to improve the

    air quality during the operational phase.

    6.2.1

    SEWAGE GENERATION,TREATMENT AND REUSE

    The project will become sustainable only if the flow of sewage into the canal network is

    stopped permanently. Discharge of the untreated sewage into the canal will cause

    environmental damage of the highest order and will continue to keep the canals in thepresent state of disrepair.

    6.2.1.1.Mitigation measure:

    The success of the proposed Thevara-perandoor waterway project hinges on the implementationof sewage network and creation of STPs for the population living in Ernakulam area of Kochi

    city.The flow of raw sewage into the canal network is to be prevented completely. The

    provisions of septic tank, proper sewerage connections etc should be linked to each and every

    houses and buildings. Installation of a small waste water treatment system to the community

    helps decrease the pollution and make use of water effectively. Its recommended that the

    authorities in charge should go on with proper checkings in a regular interval of time andimplementation of fines, taking immediate actions etc in case of any violation will help.

    6.2.2

    SOLID WASTE MANAGEMENT

    Solid waste is the unwanted or useless solid materials generated from combined residential,

    industrial and commercial activities in a given area. It may be categorised according to its origin

  • 8/11/2019 Corrected Environmental Impact and Mitigation Measures(Final)

    4/8

    ,according to its contents or according to its hazard potential. It is estimated that a fairly large

    quantity of bio-degradable and plastic wastes gets dumped into the canal, chocking it. The solid

    wastes accumulated in the canal resist the flow of the canal and hence the water in it is observed

    to have changed its natural colour to blackish brown and also produces disgusting smell. The

    cleaning of canals cannot be done due to the possibility of epidemics, presence of poisonous

    gases etc.

    Waste that is not properly managed, especially excreta and other liquid and solid waste

    from households and the community, are a serious health hazard and lead to the spread of

    infectious diseases.Unattended waste lying around attracts flies, rats, and other creatures that in

    turn spread disease. Normally it is the wet waste that decomposes and releases a bad odour. This

    leads to unhygienic conditions and thereby to a rise in the health problems.organic domestic

    wasteposes a serious threat, since they ferment, creating conditions favourable to the survival

    and growth of microbial pathogens. Direct handling of solid waste can result in various types of

    infectious and chronic diseases with the waste workers and the rag pickers being the most

    vulnerable.

    6.2.2.1 Mitigation measure:

    Management of solid waste reduces or eliminates adverse impacts on the environment and

    human health and supports economic development and improved quality of life. The studiesmust include protection of the natural environment and occupational health and safety aspects,

    taking the possibilities of sustainable development into consideration. As it seldom is possible to

    solve all problems at one time, it is important at the planning stage to note that it is helpful to set

    up a list of priorities. The first step in solving environmental and occupational hazards is torecognize the existence of the hazards. A number of processes are involved in effectively

    managing waste for a municipality. These include monitoring, collection, transport, processing,

    recycling and disposal.All of the methods of waste prevention mentioned require public participation. In order to get the

    public onboard, training and educational programmes need to be undertaken to educate the

    public about their role in the process. Also the government may need to regulate the types andamount of packaging used by manufacturers and make the reuse of shopping bags mandatory.

    Proper arrangements are to be made to collect and process the solid waste generated in the

    project region so as to prevent the dumping of solid waste into the canal. Providing proper

    boundaries along the side of the canal decreases the rate of encrochements and throwing of wasteto the canal. Proper inspection by the ruling authority is recommended. In case of any violation

    of rules meant for protecting the canal implementation of fines and moving with legal orders will

    be effective. Systems such as Dumping at designated location, Shared container , Block

    collection,

    Curbside collection,

    Door to door collection etc will help.

    6.2.3 NOISE POLLUTION DURING CONSTRUCTION AND

    OPERATIONAL PHASES

    http://edugreen.teri.res.in/explore/solwaste/health.htm#disehttp://edugreen.teri.res.in/explore/solwaste/health.htm#dise
  • 8/11/2019 Corrected Environmental Impact and Mitigation Measures(Final)

    5/8

    Prolonged exposure to noise pollution is known to cause impairment of the hearing system in all

    living beings, leading to permanent deafness. Noise pollution could occur during the

    constructional phase due to the continuous operation of noisy construction equipments. Thoughthis is a transient activity , the construction workers could be continuously exposed to the high

    level noise.

    6.2.3.1

    Mitigation measure:

    It is recommended that construction machinery maybe provided with noise dampening devices,sound proofing enclosures, etc. Construction workers exposed to noisy environment should use

    Ear muffs and provided with remote operating devices. Silencers can be provided wherever

    necessary. Acoustic standard are to be prescribed for all possible equipments.

    6.2.4

    TERRESTIAL ECOLOGY

    Construction activity are proposed to be carried out for rejuvenating the canal network, widening

    the canals to navigable width and deepening the canals. This could bring various significantchanges to the components of terrestrial ecosystem. To compensate it, adequate protective

    mechanisms are to be put in place.

    6.2.4.1

    Mitigation measures

    Precautionary measures are to be planned to avoid damages due to large scale construction

    activities. The cost benefit analysis of undertaking the Thevara-Perandoor Canal project, vis-a-

    vis the negative impacts is to be carried out before embarking on the project.

    6.2.5. FORESTS, NATIONAL PARKS,SANCTUARIES

    The project location is the midst of the urban agglomeration of Kerala. Hence there are noForests or National Parks or Sanctuaries within a radius of 25 kilometers from the Project site.

    No land is proposed to be acquired within a forest zone or a National park. Any major

    deforestation is considered as a permanent impact. Since there is no proposal for the utilizationof forest land, there is no deforestation. Hence, there would be no impact by the project on this

    ground.

    6.2.6

    IMPACT ON THE LAND USE IN THE AREA

    Heavy construction activity is slated to take place in the vicinity of the canals. Large parcels of

    land are required to be acquired for the widening the canals to the minimum navigable

    width.Presently the land is densely populated with large scale residential and commercialprojects located along most stretches of the canal banks. The land parcels are situated in the most

    expensive regions of the state and would require large sum of money for land acquisition,

    resettlement and rehabilitation of the displaced project affected people

  • 8/11/2019 Corrected Environmental Impact and Mitigation Measures(Final)

    6/8

    6.2.6.1 Mitigation measures:

    Suitable R&R schemes are to be made to accommodate the population that will get

    displaced. A thorough social cost-benefit analysis is to be carried out before commencingthe project to evaluate the relative benefits of the project and costs.

    6.2.7

    DEMOGRAPHIC,ECONOMIC&SOCIOLOGICAL IMPACT

    Large scale construction is expected to take place in the vicinity of the canals. These

    activities are expected to have both favourable and adverse demographic, economic and

    sociological impacts on the entire region.

    The land acquisition could cause adverse impact due to the related R&R issues. The

    demographic profile of the region will undergo change with the influx of the more peopleto the banks of the canal,in view of the improved physical connectivity, if the

    transportation goal could be achieved. This will contribute to the growth of the economy

    of the region.Increased population and commercial activity could contribute to thebetterment of the demographic, economic and sociological aspects of the region.

    6.2.8

    IMPACTS ON HUMAN SAFETY & HEALTH

    Impact:The general Water environment is poor due to a high level of faecalcoli. The

    construction and operation of the pilot project will not result in any significant changeother than a small increase in the throwing of the human defecation directly into the

    water body.Clearing of water hyacinth for an effective navigation will reduce themosquito breeding and will impact positively to the general environment.

    Noise levelAssessments also suggest that the noise levels with the proposed project

    will be slightly higher as the number of new boats would increase more noise levels.

    Contamination of local water supplies:Due consideration has been given to the

    possibility of temporary labour camps and the water supply and disposal associated

    with them during the construction period to ensure that the potential for adverseimpacts are avoided.

    Pollution during Transportation of Building Materials:All building material should be

    covered while transportation to avoid spillage of the material,leading to dust pollutiondue to exposure to wind.

    Concrete mixing plants: should be carefully located to avoid any disturbance to the

    locals.All materials should be collected,transported and used in an environmental

    healthy manner.

    Sanitation and solid waste generation and disposal in theworkers camp:The campsshould be properly located to avoid social nuisance to the local community.

  • 8/11/2019 Corrected Environmental Impact and Mitigation Measures(Final)

    7/8

    6.2.8.1 Mitigation measures:

    There will be provisions for clearing the water hyacinth for effective navigation.This willbe included in the engineering cost.The human waste from vessels operating in the area

    will be suitably disposed off in a separate sewerage system.the cost of septic tank have

    been incorporated in the social impact mitigation cost.With the strengthening of the basicinfrastructure and a better sewerage system the overall quality of life of all the peopleliving in the region will be improved.

    6.2.9

    WATER HYACINTH ALONG THE CANALS

    One of the most important step in the project is the removal of water hyacinth and its

    control.There is no observed definite pattern for its occurrence along the canals.Any mapping of

    the weed is thus a futile exercise.the nature of its appearance and disappearance isspontaneous.In monsoon due to heavy currents the hyacinths are not seen.Presence of the

    hyacinth presents a poor aesthetic sight for the tourists.Water hyacinth is a threat to the

    following;

    1. Serious threat to local communities:The flow of water decreases.Water become stagnant as aresult mosquito breeding increases.Dirty smell etc.

    2. Nuisance to Navigation and Fishing operation:Causes serious hindrance to Navigation.The

    propeller of the motorized vessels often became fouled with these,causing damages.3. Threat to Agricultural operations:They are constraints to aquatic productivity and disrupt

    agricultural operations when they invade the paddy fields.

    6.2.9.1

    Mitigation measures:

    o Water hyacinth can be used as a fodder to cattle.o

    Its dried form can be used as Biogas.o

    It was used as a packing material in the glass factory,since the spreading of hyacinth was

    uncontrollable such a plan is dropped.o

    Since it is an ornamental plant,it can be used for floral arrangements.o

    Experimental results shows that Water Hyacinth is a promising material for the

    production of fibre and insulation boardso

    Water Hyacinth is a good fertilizer for the growth of coconut palms.It s used as a

    compost in the coconut gardens.

    References

  • 8/11/2019 Corrected Environmental Impact and Mitigation Measures(Final)

    8/8

    1. Source: Development of water networks in Cochin Feasibility report : NATPAC,

    February 2010

    2. Sewerage and Solid Waste Project Unit. 2000. The solid waste management

    programme. Sewerage and Solid Waste Project Unit, Barbados.

    3. United Nations Environment Programme International Source Book on

    Environmentally Sound Technologies (ESTs)for Municipal Solid Waste Management

    4. American Public Health Association (APHA). 1995. Standard Methods for the

    Examination of Water and Wastewater. Alexandria, Va: Water Environment

    Federation.

    5. ARET Secretariat. 1995. Environmental Leaders 1, Voluntary Commitments to Action

    On Toxics Through ARET. Hull, Quebec: Environment Canadas Public Enquiry

    Office.

    6. Bishop, PL. 1983. Marine Pollution and Its Control. New York: McGraw-Hill.

    7. Brown, LC and TO Barnwell. 1987. Enhanced Stream Water Quality Models QUAL2E

    and QUAL2E-UNCAS: Documentation and User Manual. Athens, Ga: US EPA,

    Environmental Research Lab.

    8. Brown, RH. 1993. Pure Appl Chem 65(8):1859-1874.

    9. Calabrese, EJ and EM Kenyon. 1991. Air Toxics and Risk Assessment. Chelsea,

    Mich:Lewis.