Renewable Energy Access to the Ghana National Interconnected Transmission System • William Amuna, CEO - GRIDCo
• Chris Mensah-Bonsu, Ph.D., Principal Consulting Advisor - GRIDCo
• Bernard Modey, Director, System Operations – GRIDCo
Ghana Grid Company Limited (GRIDCo)
Presentation outline
• Brief overview of the Ghana Grid Company
• Ghana’s 2020 renewable energy policy target and incentives
• Generator connection process
• Generator connection studies, agreements and commercial operation
• Connection facilities, network upgrades and cost responsibility
• Challenges to renewable energy development
• Conclusions
Ghana Grid Company - overview
• Ghana Grid Company is wholly owned by the Government of Ghana
• GRIDCo began operation in 2008 in accordance with the – Ghana Energy Commission Act, 1997 (Act 541)
– Volta River Development (Amendment) Act, 2005 (Act 692)
• Governed by a government appointed Seven Member Board
• GRIDCo is the independent system and market operator of the Ghana National Interconnected Transmission System (NITS)
GRIDCo overview – core functions
• Acquire, own and manage transmission assets
• Develop, promote and facilitate fair and
competitive wholesale electricity market
• Provide transparent and open access for all market
participants
• Serve as the main artery between bulk electric
system customers and generation companies
• Facilitate development and connection of new
assets to the NITS including renewable energy
• GRIDCo is a major power utility industry player
within the West Africa Power Pool (WAPP)
GRIDCo overview – Ghana NITS • 2,361 MW record system peak demand
(2016)
• 4,300 MW load forecast (2020)
• 28 Bulk electric customers
• 7 Generation companies (incl. IPPs)
• Volta River Authority is the state-owned
power generation company
• 3,739 MW installed generation
capacity (3 hydros & 11 thermals)
• 4,100 MVA transformer capacity across
65 Substations
• 5,500 Circuit-km of transmission lines
(69 kV – 330 kV) with about 50% fiber-
optically equipped Control area inter-ties and service areas
• West - Cote D’Ivoire
• North - Burkina Faso (service area)
• East - Togo and Benin (service area)
Ghana’s 10% by 2020 renewable
energy target and incentives Regulatory and legal instruments
• Renewable Energy Act, 2011 (Act 832)
• Renewable Energy Sub-code
Incentives
• Provide enabling environment, good price signal and reasonable
rate of return on investment
• Guaranteed 10-year FIT rate
• Duty-free import taxes on renewable system equipment
• Renewable energy fund
• Net metering allows for compensation
Key renewable energy sources
• Solar photovoltaic
• Small run-off the river hydro
• Wind, biogas, biomass
Ghana renewables map Hydro potential Solar irradiance
Courtesy of the Ghana Energy Commission
Generator connection process
Step 1 – Connection Application
Connection Applicant notifies GRIDCo by
submitting new Generator Connection
Application Form (GCAF) containing
information about the:
• Connection Applicant
• Project location and site ownership
• Deposit the connection study fees
• Technical data and electrical
characteristics of the project for modeling
and studies
New Connection Application
Grid Study, Report & Meetings
Connection Agreement &
Execution
Commercial Operation
GCAF URL:
http://www.gridcogh.com/medi
a/photos/forms/market/Applicat
ion_Form_-
__Wholesale_Suppliers_-
_February_2016.pdf
Generator connection process
New Connection Application
Grid Study, Report & Meetings
Connection Agreement &
Execution
Commercial Operation
Step 2 – Technical Studies, Study Report
and Meetings
GRIDCo engineers perform study to identify
generator impacts to the NITS and solutions to
address the problem and issue study report to the
Connection Applicant
• GRIDCo identifies Connection Facilities,
Reliability & Delivery Network Upgrades and least
cost option to address any grid issues
• Connection Applicant is responsible for mitigation
cost
• GRIDCo meets with customer to discuss the
study report and results
Generator connection process
New Connection Application
Grid Study, Report & Meetings
Connection Agreement
& Execution
Commercial Operation
Step 3 – Connection Agreement
Connection Applicant will be issued an agreement
documenting the conditions, study results and
costs
• Agreement document will include terms of
connection to the NITS, construction schedules
and milestones
• Connection Applicant agrees to abide by
GRIDCo’s engineering, operational and
reporting requirements and applicable codes
• Required facilities and upgrades will be built
according to GRIDCo connection standards and
requirements
Generator connection process
New Connection Application
Grid Study, Report & Meetings
Connection Agreement &
Execution
Commercial Operation
Step 4 – Commercial Operation
Safe and reliable generator connection
and synchronization to the NITS is
guaranteed
• Commercial operation date should
be scheduled to accommodate
GRIDCo’s system demand
conditions and outages
• The new generator is market-ready
and can now participate in the
GRIDCo’s electricity market upon
achieving commercial operation
Generator connection studies
and meetings • Preliminary feasibility study
• Scoping meeting
• Grid study and study reports
• Study results meeting
• Report may serve as supporting documents for MOU
• Facilities assessment study to finalize connection
facilities, network upgrades and costs
• Connection agreement
• Reassessment/revision study due to project withdrawals
• Commercial operation
• Reconciling study fee deposit and cost responsibility
Generator modeling, study
assumptions, report and meeting
Your project is here!
Study, Results &
Report
Study Results
Meeting
Means of connecting new generator to the NITS
Transmission line tapping
Switching station (substation)
Challenges to renewable energy
development
• Access to credit to pre-finance renewable projects
• Acceptance of renewables in the energy portfolio mix as a viable option for meeting the load
• Developing technical know-how, supply chain and expertise for system operations
• Understanding the impacts of renewables on system operations and the grid
Conclusions • The Generator Connection Application Form streamlines
the connection process and provides uniform, and
transparent guidance to all Connection Applicants
• Grid study identifies connection facilities and network
upgrades to ensure safe and reliable connection, least
cost option and cost responsibility
• Generator connection is a shared responsibility between
GRIDCo and the Connection Applicant
• Balanced portfolio mix of hydro, thermal and renewables
will be needed to meet our growing electricity needs
• GRIDCo is strategically facilitating energy Collector
Stations to proactively accommodate RE connections
• GRIDCo is committed to Ghana’s 10% by 2020
renewable energy target and its electricity market
What to take away