Corotweek n°9 - ESTEC December 6th, 2005 COROT PROJECT STATUS1
COROT PROJECT STATUS
Thien LAM TRONG
Corotweek n°9 - ESTEC December 6th, 2005 COROT PROJECT STATUS2
Launch Date
2006
At the fall of the year
OCTOBER 2006
Delay because of conflict with another mission sharing common resources (Proteus bus family)
This interaction has been limited and is now stabilized
Corotweek n°9 - ESTEC December 6th, 2005 COROT PROJECT STATUS3
Summary
Cooperation
Instrument events
Satellite events
System events
Planning
Roadmap
Conclusion
Corotweek n°9 - ESTEC December 6th, 2005 COROT PROJECT STATUS4
Signature of Agreements
With BrazilLe Bourget June the 14th, 2005
Sergio GAUDENZI & Yannick d’ESCATHA
With Austria Vienna, November the 22nd, 2005
Klaus PSEINER & Yannick d’ESCATHA
Corotweek n°9 - ESTEC December 6th, 2005 COROT PROJECT STATUS5
Payload events from last Corotweek
Baffle Flight Model : delivered by Belgium
Corotcase Flight Model (electronic equipment bay) delivered by LESIA
Flight Software delivered by DLR (version for the Instrument Integration)
Final assembly of the whole instrument at CNES : done
EMI/EMC tests : done
Vibration tests : done
Thermal Vaccuum : under test, things are going smoothly
The complete instrument shall be delivered by Christmas
Corotweek n°9 - ESTEC December 6th, 2005 COROT PROJECT STATUS6
Satellite events from last Corotweek
Large improvement of the regular Flight Software for COROT
Implementation of the interfaces with the launcher
Assembly & Test of the Corot (PROTEUS) bus
Preparation of the Satellite assembly & tests Disturbed by the conflict of resources with the CALIPSO mission
(same team & Ground Support Equipment)
Corotweek n°9 - ESTEC December 6th, 2005 COROT PROJECT STATUS7
System events
Launcher Preliminary Mission Analysis Review Exploration visit at Baïkonour
Mission Database Formal review of data (September) Under Configuration Control
Ground Segment Control Centre : delivered and accepted Mission Centre : acceptance under progress with the spanish industry (GMV) Ground Stations
Alcantara :operational scenario & interfaces are defined, facilities are under construction
CNES network configuration is setup An additional backup is under discussion : use of the MOST ground
station in Vienna
System & compatibility Tests Are going to start by soon
Corotweek n°9 - ESTEC December 6th, 2005 COROT PROJECT STATUS8
Roadmap
To complete the test of the Ground Segment To prepare the data processing chain To prepare the operations (organization &
procedures, fields for initial runs) To verify that all components are compatible at
System level To integrate and test the satellite 7 months To do the launch campaign at Baïkonour and to
launch the satellite To position the satellite on its nominal orbit To do the in-flight tests and calibration To start the initial runs
Corotweek n°9 - ESTEC December 6th, 2005 COROT PROJECT STATUS9
Conclusion
Technical status: we are in a good shape
Budget status : we are poor but we can survive
Planning : “couci-couça” (so-so) but globally satisfactory (reminder : the launch date was march 2006 3 years ago).