CORE Executive Board
description
Transcript of CORE Executive Board
CORE Executive Board
September 22, 2010
Next CEB October 27, 2010
Agenda
SQL Requests/Problem Management Summary
Completed Projects
Portfolio
Budget Status
Priority
Execution Delivery Schedule
Projects in Movement
Program Status
HCM
Financials
Application Development Service Request Summary
Scorecard
Executive Issues
2
Problem Management SQL Requests
3
0
5
10
15
20
25
30
35
DBA/ System
Purchasing
ARBI
CRM
Procurement
HRMS
Financial
EPM
Summary Total
Problems
Resolved or
Resolution In Process
Investigating Resolved by
Future Functionality
DR to be Created
Monitor
Financial 15 9 2 4 0 0
PO 2 1 1 0 0 0
HCM 18 12 1 0 4 1
DBA/System 3 0 2 0 0 1
TOTAL 38 22 6 4 4 2
Problem Management Summary
4
Portfolio Priority
5
Project Name Project Manager Dept FunctionCurrent Project Phase
Priority within
Function
Backfill Developers for Production support and Enhancments 2011 Fred Cantrell COREFinancial mgmt
Human capital mgmtExecution 1
Time and Labor Pilot/ODOT Alex / Kim CORE Human capital mgmt Execution 2
DCS Vendor Registration Lisa McKeithan CORE Supply chain Management Execution 4
P-Card - BOA Transition Lisa McKeithan CORE Financial Mgmt Execution 5
Grants/Projects/Contract A/R Billing/T&L Extended Commerce/DEQ
Alex / Kim CORE Enterprise service automation Execution 6
Higher Education Interface Lisa McKeithan CORE Human capital mgmt Execution 7
PeopleTools 8.49 Mike Jorski AppDevCORE FIN
CORE CRM CORE EPM
Execution 8
Inventory-ODOT Alex / Kim CORE Supply chain mgmt Execution 9
Assets ODOT Alex CORE Financial Mgmt Execution 10
GPC - ODOT Alex / Kim CORE Enterprise Service Automation Execution 11
T&L Manager Self Service ODOT Pilot Alex / Kim CORE Enterprise service automation Execution 12
Treasury GL Implementation Alex CORE Financial mgmt Execution 13
PeopleSoft Extract Staging Environment Lisa McKeithan CORE Other Execution 14
Business Intelligence/Financials Analytics Lisa McKeithan CORE Other Planning 15
OpenBooks - Phase III Lisa McKeithan CORE Other Execution 16
Asset Mgmt-Rollout Michael Grisser CORE Assets Execution 17
Portfolio Priority
6
Project Name Project Manager Dept FunctionCurrent Project Phase
Priority within
Function
data.gov Lisa McKeithan CORE Transparency Initiation 18
Grants - Provisioning Lisa McKeithan CORE Other Planning 19
Licensing Lisa McKeithan CORE Other Planning 20
Enterprise Learning Management- Rollout Michael Grisser CORE Human capital mgmt Execution 21
Scanning and Bar-coding functionality for Phase II modules Alex CORE Assets Concept 22
Loans Processing Initiation 23
Expense Module Alex/Kim CORE Financial mgmt Planning 24
Budget Lisa McKeithan CORE OtherConcept> Initiation
25
7
Projects in Execution Delivery Schedule
J U N
J U L
A U G
S E P
O C T
N O V
D E C
J A N
F E B
M A R
A P R
M A Y
J U N
J U L
A U G
S E P
O C T
N O V
D E C
J A N
F E B
M A R
A P R
M A Y
J U N
J U L
A U G
S E P
O C T
N O V
D E C
Time and Labor Pilot/ODOT
Grants/Projects/Contract A/R Billing ODOT
Inventory ODOT
T&L Manager Self Service ODOT
PeopleSoft Extract Staging Environment
PeopleTools 8.49
DCS Vendor Registration
Assets ODOT
Grants/Projects/Contract A/R Billing/T&L Extended Commerce/DEQ
Treasury GL Implementation
OpenBooks - Phase III
P-Card - BOA Transition
FY11 Technical Backfill
ELM rollout
Asset Management Rollout
Higher Education Interface
2009 2010 2011
8
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Issues
ODOC HP System needs to be replaced
2010 / 2011
Roll out / Conversion
Project Start
2833 - ODOC Loans Processing
Prototype Review
Development
Integration Testing / User Acceptance Testing / Training
Two options for implementing the Contracts module functionality are presented in this document:Option # 1 involves the development of a conversion process to convert open contract (Loan) definitions into PeopleSoft. After the Contract definitions are loaded, Contract Billing and Receivable history will be converted using the standard CORE conversion methodology. Option # 2 involves the agency converting open Contract definitions manually.
Milestone Schedule +/- 50%
Program Status
HCM
9
CORE-1080 Higher Ed Payroll
Status: YELLOWYELLOW
Convert Higher Ed agencies from the legacy payroll system to the PeopleSoft system.
TASK Start Finish
Configuration – 95% complete 07/01/2010 11/01/2010
Conversion Scripts – 75% complete 07/01/2010 11/01/2010
Finish HR Interface Debugging/Testing 07/01/2010 11/01/2010
Complete PY Interface Coding/Debugging/Testing 09/10/2010 12/15/2010
UAT to begin with OU 01/01/2011 01/26/2011
Requires Awareness:
• Functional consultant left company, a Maximus replacement is on site.• Using remaining budget from Innovative and reducing the project backfill amount to fund functional consultant • Re-assessed, resources and timeline for implementing OU while maintaining the overall project schedule.• Loss of OU involvement in August and September• If OU does not meet minimum requirements in new Roles and Responsibilities, plan will slip
Key Activities
Key Overall Issues
10
CORE – 2666 Grants, Projects, Contracts with AR/Billing Monthly Extended Time & Labor
Status: GREENGREEN
The Team is in the process of finalizing Integration Testing and preparing for User Acceptance Testing.
TASK Start Finish
Integration Testing 08/04/2010 09/10/2010
Preparation for User Acceptance Testing 08/27/2010 09/17/2010
User Acceptance Testing (UAT) 09/13/2010 10/18/2010
Requires Awareness:
Concern regarding getting Legacy Conversion Extracts has been raised. DEQ and Commerce are both working on this.
Commerce will start UAT one week late, reducing their UAT by one week.
Key Activities
Key Overall Issues
11
CORE – 2637 ELM Rollout
12
Status: GREENGREEN
Rollout of ELM to agencies to be completed in 3 groups (original plan), Group A consisted of Career Tech (800), CompSource (390), ODOT (345), Courts (199, 219, 220, & 677), Oklahoma Developmental Disabilities Council (a division of 830). Group A go live date is 11/30/2010
Confirmed agencies – Group A: Career Tech (800), ODOT (345), OSEEGIB (516), Group B: OPM (548), State Dept of Health (340)
Declined Agencies – Firefighters (C), Courts (A)
Requires Awareness:
No decision from CompSource (A), ODDC (A), OSF (C), DCS (C).
Firefighters (C) has declined, OEM (C) may take their place
If other agencies back out, we will continue find others to replace them or move to the next Phase of the Project (SCORM)
Task Start End
Kickoff Meeting with Rollout Agencies 08/25/2010 08/25/2010
Set up Learning Environments 09/01/2010 10/15/2010
Load HCM Data in Prod for messaging to LM Prod (e-mail & reports to information) 09/20/2010 10/10/2010
Train agency SME’s on config and setup for testing 10/10/2010 11/30/2010
Set up Prod Environments 11/01/2010 11/25/2010
Go Live 11/30/2010 11/30/2010
Key Activities
Key Overall Issues
Program Status
Financials
Phase II Modules
13
CORE – 2611 PeopleTools 8.49
Status: GREENGREEN
Project started on time.
However we lost 4 days because the hard drive went out on Greg Linn’s PC. Greg’s PC has been rebuilt and he is progressing.
TASK % Complete Start Finish
Prepare Change Assistant & stage software 100% 08/30/2010 09/03/2010
Upgrade & test non-prod EPM environments 5% 09/07/2010 09/24/2010
Upgrade EPM production environment 09/25/2010 09/25/2010
Upgrade EPM development environment 09/27/2010 09/28/2010
Requires Awareness:
It will be tight with the loss of 4 days but if there aren’t a lot of issues to deal with during testing then we might be able catch up to the project schedule.
Key Activities
Key Overall Issues
14
CORE-2675 Data Staging Environment
Status: REDRED
Build staging environment containing PeopleSoft extracts that will be used by ODOT.
TASK Start Finish ODOT Access
Phase I extracts (6) signed off by ODOT 07/02/2010
Assets (0523) & Projects (0514) have been re-migrated to FSTST2 and is ready for functional testing
06/25/2010 TBD TBD
Contracts (0513) & Billing (0512) have been re-migrated to FSTST2 and is ready for functional testing
06/25/2010 TBD TBD
Sign-off on Phase II Modules TBD TBD
Requires Awareness:
• Waiting on testing resources from ODOT
Key Activities
Key Overall Issues
15
CORE-2681 DCS Vendor Registration
Status:REDRED
Build interfaces between OK.gov and PeopleSoft for validation and upload of vendor/bidder data into PeopleSoft.
TASK Start Target Finish Est. Finish
Go-live with vendor registration – Part I 07/19/2010
Development /Testing – Tech specs 0027 – OSF testing complete 09/02 – sent to DCS for testing;
06/04/2010 08/31/2010 09/30/2010
Development/Testing – Bidder to Vendor Update 05/10/2010 08/31/2010 10/15/2010
Review/Revise processes – OSF & DCS 07/31/2010 07/31/2010
Requires Awareness:
• Missed Phase I implementation by 19 days. •DCS is working on ‘Phase II’ for updated front-end. This will cause some reprogramming of the interface that will be tracked as a service request. Scheduled for the fall. •Status has changed to ‘Red’ due to two remaining items.
Key Activities
Key Overall Issues
16
CORE-2676 OpenBooks Phase III
Status: GREENGREEN
Utilize OBIEE for OpenBooks reporting. Update ARRA reporting per SB1759.
TASK Start Estimated Completion
Finish
ARRA Updates 07/01/2010 09/15/2010 08/26/2010
Expenditure & Funding (Build DIM/Create Rpts/Test) 10/01/2010 12/31/2010 Jan 2011
Pcard (Load/Build DIM/Create Rpts/Test/Automate) 06/01/2010 10/31/2010 Jan 2011
Vendor Payments (Build DIM/Create Rpts/Test) 08/01/2010 09/30/2010 Jan 2011
Payroll (Load/Build DIM/Create Rpts/Test/Automate) 08/01/2010 12/31/2010 Jan 2011
Go-Live Jan 2011
Requires Awareness:
• Determine approach for file transfer/load• Possible upgrade to v11 (XML export functionality)• Financials Analytics will not start until this is complete• Potential Conflicts:
ARRA Reporting (October); FFATA;
Key Activities
Key Overall Issues
17
CORE-2800 PCard Transition to BOA
Status: GREENGREEN
Build interfaces between OK.gov and PeopleSoft for validation and upload of vendor/bidder data into PeopleSoft.
TASK Start Finish
GL Export (0613) Segment values and combo code values 08/30/2010 09/30/2010
Voucher Build (0614) 08/30/2010 10/31/2010
1099 Processing (0xxx) 08/30/2010 12/31/2010
Requires Awareness:
• DCS will have some cardholders as a pilot starting in October. Their initial GL segment values and combo values have already been loaded into the production site.•Statewide implementation is scheduled for November/December.
Key Activities
Key Overall Issues
18
2665 – Asset Management Rollout
Status: GREENGREEN
Meetings to be held to prepare for Kickoff Session Replacement consultant is on board. Consultant will be working on ODOT Assets and the AM Rollout. Brenda is working with DCS to get a resource for 4 days a week. Looking at changing the plan to do small agencies (<100 assets first). If do small agencies we will be doing an incremental rollout.
TASK Start Finish
Prepare for / Conduct Project Kick-off TBD TBD
Configure/Verify Agency Conversion Data 09/16/2010 11/05/2010
Perform Test Loads 10/26/2010 11/15/2010
Train Agency Users 11/17/2010 12/05/2010
Requires Awareness:
•DCS Resource is not committed to the project – Brenda is working to get a resource committed (4 days a week). If no DCS resource rollout plan will need to be adjusted or possibly put the project on hold.•Brenda to also assist with agency buy in to rollout plan.•Evaluating the new AM consultant to be sure he meets the needs of the project.•Will need to re-verify the plan timelines once the resource issues are resolved.
Key Activities
Key Overall Issues
19
2692 – Treasury GL Implementation
Status: GREENGREEN
The Team is in the process of creating business process flows, validating design, finalizing configuration, and creating the development requests. Test Scripts are being written in preparation for business process testing.
The Team is currently behind schedule regarding requirements and configuration. A plan for getting back on track is being created.
TASK Start Finish
Create Business Process Flows, Reconciliation Points, Checklists
07/06/2010 08/19/2010
Create Development Requests 08/02/2010 08/20/2010
Preparing for Business Process Testing 08/27/2010 09/03/2010
Business Process Testing 09/07/2010 09/17/2010
Requires Awareness:
OST has requested that their Go-Live date be moved to a month-end. Rather than go-live on 11/15/2010 they would like to look at either 10/31/10 or 12/31/2010.
Key Activities
Key Overall Issues
20
CORE - 2810 Assets ODOT
Status: GREENGREEN
On schedule
TASK % Complete Start Finish
Clean-up and Format Asset Conversion Data for FY 2010 100 7/1/2010 8/13/2010
Prepare for Integration Testing 100 8/16/2010 8/27/2010
Perform Integration Testing 8/30/2010 9/24/2010
Prepare for User Acceptance Testing 9/27/2010 10/04/2010
Perform User Acceptance Testing 10/05/2010 10/22/2010
Requires Awareness:
Key Activities
Key Overall Issues
21
CORE – 2581 Time & Labor
Status: REDRED
This Project is to address Time & Labor functionality for bi-weekly agencies. The pilot agencies are OESC and ODOT. OESC went live on schedule May 17th.
Requires Awareness:
Integration and User Acceptance Testing for ODOT will be scheduled to coincide with a re-baselined plan.
Task Start End
Key Activities
Key Overall Issues
22
CORE – 2599 Grants, Projects, Contracts with AR/Billing
Status: REDRED
This Project is on hold.
TASK Start Finish
Functional Unit Testing – ODOT (see below)
Requires Awareness:
•ODOT cannot supply a date for conversion of legacy data.
Key Activities
Key Overall Issues
23
CORE – 2610 Inventory ODOT
Status: REDRED
On Hold.
TASK Start Finish
Integration Testing (see below)
Prepare for User Acceptance Testing
User Acceptance Testing
Go Live
Requires Awareness:
Key Activities
Key Overall Issues
24
CORE – 2674 Manager Self Service ODOT / Pilot
2525
Status: REDRED
Project was planned in two phases: (1) limited salary personnel April 24th (complete) and (2) all non Agile Asset personnel to coincide with ODOT GPC go-live date – on hold.
Requires Awareness:
Task % Start End
Go –live Limited Pilot - Complete 100 04/242010 04/24/2010
Requirements – Full Implementation - Complete 100 03/23/2010 04/07/2010
Key Activities
Key Overall Issues
Application Enhancement Service Requests
26
27
Application Enhancement Service Requests – Aug 2010
Functional ESRs Pending Config/Setup UAT Completed
CRM
ELM 1 2
EPM
FIN 1
HCM 25 12 2 5
Total 27 12 2 7
Technical ESRs Pending Dev UAT Completed
CRM 3 1
ELM 2 1
EPM 1
FIN 28 11 4 6
HCM 51 9 5 5
Total 85 20 9 13
Pending Dev UAT Completed
Total 112 32 11 20
Based on 60 Day PlanPlanned Enhancement Service Requests OnTime Completion
28
# ESRs completed # ESRs not completed # unplanned completed
January (FIN) February (HCM) March (FIN) 6 2 5April (HCM) May (FIN) 3 5 4June (HCM) July (FIN) 6 1 1August (HCM) 18 4 7September (FIN) October (HCM) November (FIN) December (HCM)
*Teachers Retirement mod was cancelled after the reporting period ended.
Program Status
Within 10% of plan Within 20% of Plan Over 20% of plan
29
Project NameCurrent Project Phase
Health Ind
Schedule
Project Phase Start Date
Project Phase Baseline
Completion
Project Phase Target
Completion
Health Ind
Budget
FY11 Technical Backfill Execution G 7/1/2010 6/30/2011 6/30/2011 G
Time and Labor Pilot/ODOT Execution R 3/1/2009 7/31/2010 7/31/2010 RDCS Vendor Registration Execution R 4/1/2010 8/31/2010 10/15/2010 GP-Card - BOA Transition Execution G 8/18/2010 12/31/2010 12/31/2010 GGrants/Projects/Contract A/R Billing/T&L Extended Commerce/DEQ
Execution G 3/1/2010 12/31/2010 12/31/2010 G
Higher education Interface Execution Y 4/1/2010 10/31/2011 10/31/2011 YPeopleTools 8.49 Execution G 8/30/2010 9/28/2010 9/28/2010 GInventory ODOT Execution R 8/1/2009 7/31/2010 7/31/2010 RAssets ODOT Execution G 8/1/2010 11/15/2010 11/15/2010 GGrants/Projects/Contract A/R Billing ODOT
Execution R 7/1/2009 7/31/2010 7/31/2010 R
T&L Manager Self Service ODOT
Execution R 3/1/2010 7/31/2010 7/31/2010 R
Program Status
Within 10% of plan Within 20% of Plan Over 20% of plan
30
Project NameCurrent Project Phase
Health Ind
Schedule
Project Phase Start Date
Project Phase Baseline
Completion
Project Phase Target
Completion
Health Ind Budget
PeopleSoft Extract Staging Environment
Execution R 1/14/2010 6/18/2010 8/31/2010 G
Business Intelligence - FS Analytics
Planning R 4/1/2009 7/31/2009 12/31/2010 G
OpenBooks - Phase III Execution G 6/1/2010 12/31/2010 12/31/2010 GAsset Management Rollout Execution G 4/19/2010 8/31/2011 8/31/2011 GGrants - Provisioning Planning R 7/31/2008 7/15/2009 9/30/2010 GLicensing Planning R 12/1/2008 8/15/2009 9/30/2010 GELM rollout Execution G 8/1/2010 7/31/2011 7/31/2011 GScanning and Barcoding functionality for Phase II Modules
Concept
Expense Module Planning G Gdata.gov Initiation G 8/1/2010 10/15/2011 10/15/2011 GBudget Concept>
InitiationG 8/2/2010 9/15/2010 10/30/2010 G
IssuesIssue Status
1) ODOT Phase II ( Projects, Grants, AR, Billing Inventory) have not committed to a date to start integration testing.
We need to determine if ODOT or other agencies (DPS, Health, Mental Health, etc) will be next in line for Phase II modules. This decision needs to be made by mid October.
3) Commerce will be going live on Phase 2 without a Grants Provisioning or Loans. They will utilize manual work around until we acquire a Grants Provisioning and/or Loans package.
Waiting on finalization of award so that we can start working with the vendor.
31
2) The fixed asset rollout plan has been completed and additional state resource is required to deliver on the current schedule
No state resource has been identified for this project.