Copy of npv_irr

download Copy of npv_irr

of 6

Transcript of Copy of npv_irr

  • 7/30/2019 Copy of npv_irr

    1/6

    NPV AND IRR RULES

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    1819

    20

    21

    22

    A B C D E F G H

    NPV RULE FOR CAPITAL BUDGETING

    Choose a project if it costs less than the PV of its cash flows. More generally:

    take a project if its Net Present Value is positive.

    EXAMPLE

    Interest rate 10%

    Year 0 1 2 3

    Cash flow (600) 200 200 500

    PV factor 100% 91% 83% 75%

    PV of cash flow (600) 182 165 376

    Cumulative PV (600) (418) (253) 123

    Net Present Value 123

    Investors would have to invest 123 more (a total of 723) to get the cash flows of 200, 200,

    and 500 at an interest rate of 10%. Therefore the project has a value of 123 for investors.

    The interest rate is called the cost of capital, because it is the opportunity cost of funds - the

    rate investors can earn on alternative investments.

    Page 1

  • 7/30/2019 Copy of npv_irr

    2/6

    NPV AND IRR RULES

    1

    23

    4

    5

    6

    7

    8

    9

    10

    A B C D E F G

    IRR RULE

    For a standard project, NPV > 0 if and only if IRR > Cost of Capital

    IRR Rule: Choose a project if and only if IRR > Cost of Capital

    Standard means

    - cash outflows occur in early years and cash inflows in later years.

    - the alternative to the project is the status quo.

    Page 2

  • 7/30/2019 Copy of npv_irr

    3/6

    NPV AND IRR RULES

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    A B C D E F G

    NONSTANDARD PROJECTS MAY HAVE MORE THAN ONE INTERNAL RATE OF RETURN

    Cost of capital 12%

    Year 0 1 2

    Net cash flow (400,000) 960,000 (572,000)

    PV factor 100% 89% 80%

    PV of net cash flow (400,000) 857,143 (455,995)

    Cumulative PV (400,000) 457,143 1,148

    Net present value 1,148

    IRR (Internal Rate of Return) 10%

    For this project , varying the ini t ia l guess in th e IRR funct ion can cause the IRR to change.

    This is a good project (posi t ive NPV), but you can't tel l i t from th e IRR funct ion . The fol lowing

    chart show s that there are two break-even costs of capita l or IRR's. The NPV is posi t ive at the

    actual cost of capita l (12%), so it is a good project .

    Page 3

  • 7/30/2019 Copy of npv_irr

    4/6

    NPV AND IRR RULES

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    1920

    21

    22

    23

    24

    25

    A B C D E F G H

    Year 0 1 2

    Net cash flow (400,000) 960,000 (572,000)

    Discount Rate NPV

    2% (8,612)

    4% (5,769)

    6% (3,418)

    8% (1,509)

    10% -

    12% 1,148

    14% 1,970

    16% 2,497

    18% 2,758

    20% 2,778

    22% 2,580

    24% 2,185

    26% 1,612

    28% 87930% -

    32% (1,010)

    34% (2,139)

    36% (3,374)

    38% (4,705)

    40% (6,122)

    (10,000)

    (8,000)

    (6,000)

    (4,000)

    (2,000)

    -

    2,000

    4,000

    0% 20% 40% 60%

    NetPresentValue

    Discount Rate

    Page 4

  • 7/30/2019 Copy of npv_irr

    5/6

    NPV AND IRR RULES

    1

    2

    3

    4

    5

    67

    8

    9

    10

    11

    12

    13

    14

    15

    16

    1718

    19

    A B C D E

    AN EXAMPLE OF MUTUALLY EXCLUSIVE PROJECTS

    Cost of capital 10%

    Year 0 1

    Project A Cash flow (10,000) 20,000

    PV factor 100% 91%

    PV of cash flow (10,000) 18,182

    NPV 8,182

    IRR 100%

    Project B Cash flow (20,000) 35,000

    PV factor 100% 91%

    PV of cash flow (20,000) 31,818

    NPV 11,818

    IRR 75%

    Project B is best, even though its IRR is lower.

    Page 5

  • 7/30/2019 Copy of npv_irr

    6/6

    NPV AND IRR RULES

    1

    2

    3

    4

    5

    67

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    A B C D E F G H

    PROJECTS CAN BE VALUED ON AN INCREMENTAL BASIS

    Cost of capital 10%

    Year 0 1

    Project A Cash flow (10,000) 20,000

    PV factor 100% 91%

    PV of cash flow (10,000) 18,182

    NPV 8,182

    Project B-A Cash flow (10,000) 15,000

    PV factor 100% 91%

    PV of cash flow (10,000) 13,636

    NPV 3,636

    Project B has a positive NPV relative to A (on an incremental basis) so should be taken.

    Page 6