Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

download Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

of 18

Transcript of Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    1/18

    Employer : THE GENERAL MANAGER

    CEYLON ELECTRICITY BOARD

    P.O box,Sir Chittampalam A. Gardiner Mw,CMB 2

    Contractor : Ranasiha Lanka Construction (PVT) LTD

    Engineer : Deputy general Manager (Mahaweli Complex)

    40/20 Ampitiya Road,Kandy

    JUNE 2014

    CEYLON ELECTRICITY BOARD

    DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA

    DESILTING OF TUNNEL INTAKE AREA AND RAWAN OYA

    DESILTING OF TUNNEL INTAKE AREA AND RAWAN OYA

    (0+000M TO 0+950M) AT POLGOLLA DIVERSION KANDY

    CONTRACT NO: DGM/MC/23/POLGOLLA/2013/01

    PROGRESS REPORT NO. 4

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    2/18

    MONTH ENDING: JUNE 2014

    DETAILS OF THE CONTRACT

    PROJECT STAFF

    PROJECT ORGANIZATION CHART

    GUARANTEES AND INSURANCE POLICY

    GENERAL DESCRIPTION OF WORKS PERFORMED DURING

    THE MONTH OF JUNE 2014

    PROBLEMS ENCOUNTERED

    PROGRESS UPTO THE END OF JUNE 2014 7,8,9

    SCHDULE OF MAN POWER DURING THE MONTH OF JUNE 2014

    CONTRACTOR'S PLANTS & EQUIPMENTS

    SAFETY PROGRAMME FOR THE MONTH OF JUNE 2014

    WEATHER REPORT FOR THE MONTH OF JUNE 2014 13

    PHOTO GRAPHS FOR MAIN WORK OPERATIONS IN

    THE MONTH JUNE 2014

    'S' CURVE

    PROGRESS OF THE MONTH OF JUNE 2014

    BILL AMOUNT 17

    16

    4

    5

    6

    10

    15

    14

    11

    12

    CONTENTS

    PAGE NO.

    1

    2

    3

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    3/18

    Project Name :

    Contract No. : DGM/MC/23/POLGOLLA/2013/01

    Location :

    Employer :

    The Engineer :

    Scope of Work : [i]

    [ii]

    [iii]

    [iv]Maintaining the temporary yards and dumping area

    Contract Period : 6 Months

    Period of Commencement Works :

    Period of construction : 12/02/2014-12/08/2014

    Performance Bond : 5% of the contract price

    Percentage of Retention Money : 10%

    Limit of Retention Money : 5% of the accepted contract amount

    2/12/2014

    Desilting of tunnel Intake area and Rawan oya (0+000m

    to 0+950m)

    The General Manager ,Ceylon Electricity Board

    P.O . Box-540,Sir Chittampalam A. Gardiner MW,

    Colombo -02

    Deputy General Manager (Mahaweli Complex)

    DETAILS OF THE CONTRACT

    Located at polgolla for a 950m stretch of rawan oya

    Desilting of Rawan oya By means of dredging.

    Formation of temporary yards to deposit the raw

    dredged materials.

    Transport the dredged materials to the temporary

    yards and then to dumping areas.

    3

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    4/18

    Construction Manager : C.K.B Seneviratne

    Engineer Assisstant : G.H.I.P Kumara

    Quantity Surveyor : Iresha Attanayake

    Technical officer : N.K Gamini

    Technical Officer : R.A.S Ranasinghe

    Supervisor : Sanjeewa R. Palihawadana

    Technical Officer

    (Access Engineering) : M.G.M.U Somadasa

    PROJECT STAFF

    2

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    5/18

    PROJECT ORGANIZATION CHART

    Construction

    Manager

    Engineer's

    AssisstantQuantity Surveyor

    Surveyor

    Supervisor

    Foreman

    Technical

    officer

    3

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    6/18

    Description Amount Remarks

    Performance Bond Rs. 2,867,000.00 Submitted on 07.02.2014

    Advance Payment Guarantee No.

    BTD/B034447

    Rs. 11,468,000.00 Submitted on 07.02.2014

    Contractors Insurance Pol icies

    Contractors All Risk Policy No.

    14HDO1ECR000137

    Submitted

    Workmens Compensation Policy No.

    14HDO4AWC000268

    Submitted

    Construction Manager's Requirements Completed

    GUARANTEES AND INSURANCE POLICY

    4

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    7/18

    GENERAL DESCRIPTION OF WORKS PERFORMED DURING THE MONTH OF JUNE 2014

    Dredging work of the tunnel intake area ,Rawan oya

    Survey of the site

    Loading and transporting of the dredged materials

    5

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    8/18

    6

    Mahaweli Authority has decided

    to deposit the dredged materials

    )on the left river bank only , it

    requires extra machine hrs andtime.

    Log Note-27/05/2014

    Dumping yard problem has not

    been sorted out yet,Dredged

    materials are being transported

    far away.(15Km)

    Mahaweli authority has

    commanded to remove the

    floating barrier ,therefore debris

    has been moved towards the

    intake gate.

    Reference - Log note 1

    28/04/2014 to 28/5/2014

    PROBLEMS ENCOUNTERED/ ISSUES

    Description Reference Comments

    Log note -25/04/2014 to the

    day

    Continues obstruction of Cutter

    Suction Dredger due to garbage

    and the debris clogged in the

    cutter and pump,occuring less

    productivity.

    18/03/2014

    18/03/2014

    26/04/2014

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    9/18

    he overall percentage of main items of the works.

    tem

    No. Description

    BOQ

    Item

    No.

    Unit BOQ Qty. Scheduled Work Completed Work Scheduled Completed

    PROGRESS UPTO THE END OF MAY 2014

    7Cleaning and repairing the damaged roads

    when transporting dredged materials7 Item 1.00 0.00%

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    10/18

    Comments

    8

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    11/18

    2014

    JUNE

    1 Construction Manager 1

    2 Engineer's Assisstant 1

    3 Quantity Surveyor 1

    4 Technical officer 2

    6 Supervisor 2

    5 Surveyor 1

    6 Draughtsman 1

    7 Operator 5

    8 Mechanic 4

    9 Dredger Operator Helper 7

    10 Drivers 6

    11 Surveyor Helper 4

    12 Surveyor Assisstant 4

    13 Skilled workers 8

    14 Unskilled Workers 7

    Designation

    SCHDULE OF MAN POWER AT SITE DURING THE MONTH OF JUNE 2014

    10

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    12/18

    Equipment Type & Capacity No. Status

    DREDGING OF THE TUNNEL INTAKE

    JCB JCB 2 Good in Working Order

    Excavator CAT 40 1 Good in Working Order

    Long arm excavator KOBELCO 1 Good in Working Order

    Amphibious Dredger KOBELCO 1 Good in Working Order

    Cutter suction dredger 1 Good in Working Order

    Tipper TATA Good in Working Order

    CONTRACTOR'S PLANTS & EQUIPMENTS AT SITE

    11

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    13/18

    l Free of Accidents

    l Minor Accidents

    l Major Accidents

    l 1

    l 2

    l 3

    l 4

    l 5

    l 6

    l 7

    9 10 11 12 13 14 15 l 8

    l l l l l l l l l l l l l l

    23 l16 17 18 19 20 21 22

    24 l

    25 l

    26 l

    27 l

    28 l

    29 l

    30 l

    SAFETY PROGRAMME FOR THE MONTH OF JUNE 2014

    12

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    14/18

    MAX. TEMP. LIGHT RAIN

    MIN. TEMP. HEAVY RAIN

    CONTRACT NO-DGM/MC/23/POLGOLLA/2013/0127

    0C 32

    0C 27

    0C 30

    0C 27

    0C 33

    0C 27

    0C 34

    0C 27

    0C 30

    0C

    270C 32

    0C 27

    0C 33

    0C 27

    0C 33

    0C 27

    0C 32

    0C 27

    0C 30

    0C

    280C 33

    0C 27

    0C 33

    0C 27

    0C 33

    0C 27

    0C 34

    0C

    270C 33

    0C 28

    0C 32

    0C 27

    0C 33

    0C 27

    0C 30

    0C

    280C 30

    0C 27

    0C 34

    0C 28

    0C 34

    0C 27

    0C 30

    0C

    270C 33

    0C 27

    0C 34

    0C 24

    0C 28

    0C 27

    0C 30

    0C

    270C 32

    0C 27

    0C 33

    0C 28

    0C 33

    0C 27

    0C 30

    0C

    MON

    2

    WEATHER REPORT

    SUN

    1 8 2915 22

    WEATHER REPORT FOR THE MONTH OF JUNE 2014

    21 28

    3 10 17 24

    20 27

    4 11 18

    SAT

    7 14

    FRI

    6 13

    WED

    25

    9 16 30

    THU

    23

    TUS

    5 12 19 26

    13

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    15/18

    RING THE

    14

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    16/18

    S curve

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    17/18

  • 8/11/2019 Copy of Neww-polgolla Progress Report No 1-Month of Mayyyy

    18/18

    PROVISION CLAIMED AMOUNT CERTIFIED AMOUNT BALANCE AMOUNTNO

    A/1.00

    2.00

    3.00

    4.00

    5.00

    6.00

    7.00

    8.00

    B/1.00

    2.00

    3.00

    4.00

    5.00

    6.00

    7.00

    SSR 1

    SSR2

    SSR3

    W/ RETENTION

    Advance

    recovery and

    VAT

    BILL AMOUNT