Contracts&DisputesHT5
Transcript of Contracts&DisputesHT5
-
8/14/2019 Contracts&DisputesHT5
1/41
Tenders & Contracts.
Clauses & Conditions.
Recent Developments
-
8/14/2019 Contracts&DisputesHT5
2/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &
Dispute Resolution 2
Purpose of a Tender
Get offers from alternate parties
who have the competency &capabilityTender evaluation C & C First Step
Establish equality or clears a set benchmark
Tender pricing -to be from parties of equal C & Cto be on common platform based on
Specifications, BOQ and price schedules
Payment, intermediate & finalTechnology & Time for completion & Quality
Selected tenderer becomes contractor on acceptanceof tender and signing of the contract
-
8/14/2019 Contracts&DisputesHT5
3/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 3
Purpose of a contract
Bring two parties together to work for acommo n obj ectiveBoth parties to benefit as a result of the activity
Parties ---- Owner & Contractor
Parties ---- Developer & ArchitectParties ---- User & Regulator
Do these parties have a common objective???
Each party has its own private goal.Contra ct is to t ie the par ties to thecommo n goa l by satis fy ing the priva tego al of each par ty.
-
8/14/2019 Contracts&DisputesHT5
4/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 4
Tenders & ContractsInfrastructure work contracts constantly gets blamedfor cost & time overruns.
Most of the contracts result in disputes either duringthe contract period or at the end of it.
Conditions in tenders, which on acceptance become
contract conditions are designed or drafted to avoidoverruns and disputes.
Costi ng or estima ti ng the project cost &mea sur ement & pa yme nts are very criticalactivities responsible for the healthy operation of acontract.
Projects are complex & Unknown elements either existor crop up during the life of the project.
-
8/14/2019 Contracts&DisputesHT5
5/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 5
PROCESS
Tenders & Contracts
SKETCH DESIGN
Room
Demands
Terminal
Device
Spec
Room
Design
Co-Ordination
Equipment
Selection
Installation, Testing & Commissioning
Network
Design
Riser and
Void
Design
Fabricatio
n
Drawings
Building
Demands
Plant
Spec
Plant
Room
Design
Plant
Selection
-
8/14/2019 Contracts&DisputesHT5
6/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 6
Tenders & Contracts
Project Brief
Concept Design
Detail Design
Production Info
Construction
Testing & Comm
Occupation
By
Employer
By
Contractor
By
Employer
By
Contractor
-
8/14/2019 Contracts&DisputesHT5
7/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 7
Change & Cost of Change
Tenders & Contracts
-
8/14/2019 Contracts&DisputesHT5
8/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 8
Tenders & ContractsAll contracts basically involve an element of risk
transfer from one party to the other contractingparty.
The coverage for picking up the risk is theprofit.
Conditions in tenders, particularly the non-specific ones such as Any other costs arisingdue to event xxx are to be borne by the
contractor are the ones which create problem.Errors in Co sti ng o r es ti mat ing the projectcost result in an implied risk.
-
8/14/2019 Contracts&DisputesHT5
9/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 9
Tenders & Contracts
TIME
COSTQUALITY
QuickestMost Certain Earliest Start
on Site
Lowest to Buy
Most Certain
Lowest in UseDesign
Client
Controlled
Products
CONTRACT PROFILE
12
34
5
12
34
5
-
8/14/2019 Contracts&DisputesHT5
10/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 10
Tenders & Contracts
TIME
COSTQUALITY
QuickestMost Certain Earliest Start
on Site
Lowest to Buy
Most Certain
Lowest in UseDesign
Client
Controlled
Products
D&B CONTRACT PROFILE
12
34
5
12
34
5
-
8/14/2019 Contracts&DisputesHT5
11/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 11
Tenders & Contracts
TIME
COSTQUALITY
QuickestMost Certain Earliest Start
on Site
Lowest to Buy
Most Certain
Lowest in UseDesign
Client
Controlled
Products
MANAGEMENT CONTRACT PROFILE
12
34
5
12
3
54
-
8/14/2019 Contracts&DisputesHT5
12/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 12
Tenders & Contracts
TIME
COSTQUALITY
QuickestMost Certain Earliest Start
on Site
Lowest to Buy
Most Certain
Lowest in UseDesign
ClientControlled
Products
TRADITIONAL CONTRACT PROFILE
12
34
5
12
3
54
-
8/14/2019 Contracts&DisputesHT5
13/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 13
Infrastructure ProjectsInfrastructure projects require inputs from at
least about 22 different entities for its success.Non cooperation from any-one will cause delay.
Project success - benefits a few out of the 22.
-- causes loss or problems to some.-- few are unaffected.
-- few beneficiaries have no voice.
-- few have capacity to put spokes.
Categorization of the 22
-
8/14/2019 Contracts&DisputesHT5
14/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 14
Tenders & Contracts
M/E Design
Passive
Design
Elements
ToiletCores
Horiz/Vert
Circulation
Basement
Planning
Structure
CladdingCeilings
Partitioning
Floors
Voids &
Risers
Reception
Joinery
Catering/
Refrigeration
-
8/14/2019 Contracts&DisputesHT5
15/41
Project & Contracts
Their role &the emerging changes in their rolewith changes in construction
contracting practices.
Employer
Employers
Agent
Contractor
ME A CS
SC1 SC2 SC3 SC4
QSTheir role &the emerging changes in their rolewith changes in construction
contracting practices.
-
8/14/2019 Contracts&DisputesHT5
16/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 16
Contract Manager - Functions
Manage and control costs
within construction projectsUse a wide range of
management procedures and
technical tools to achieve thisgoal.
-
8/14/2019 Contracts&DisputesHT5
17/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 17
Change over the years
Costs have become dynamic; Fast Changes.
Technology change, Mechanization.
From primarily civil engineering work
to a mix of work of different disciplines, particularly
Electrical, Air-Conditioning, Plumbing, Electronics,Fire detection & protection-----
Corresponding to change from single & double storyconstruction
to multistory complexes.
Energy costs and Environmental requirements.
-
8/14/2019 Contracts&DisputesHT5
18/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 18
Change over the yearsEnerg y cost s have also brought in a changein the outlook of the architectural design of
buildings.We cannot afford to overlook the opera tingcost of t he b uil di ng as a whole.Closely associated with the energy are theenvi ronmenta l f actors associated withenergy usage.
-
8/14/2019 Contracts&DisputesHT5
19/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 19
Energy & EnvironmentGlobal Warming which was considered to be adistant dream of a pessimistic scientist is now
identified to be a reality staring at us.Energy consumption is directly associatedwith the production of green house gassesand global warming.
We cannot afford to face the consequenceson the environment
B ildi & E
-
8/14/2019 Contracts&DisputesHT5
20/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 20
Building & Energy
Our building designs should keep energy in all
its forms and stages of utilizationEnergy that goes into the formation of thebuilding materials.
Energy that is utilized in the construction.
Energy that will be spent during the life time ofthe building.
CDM (Clean Development) & Green Buildingsare also becoming important.
S d f C t ti &
-
8/14/2019 Contracts&DisputesHT5
21/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 21
Speed of Construction &Maintainability
The speed of construction has also beenassuming importance.
Speed of construction is dependent on the
method adopted and the type of structure.Maintainability is another aspect.
Today with the gradual but continuous
increase in the labor costs it is essential thatthe design is such that the requirements ofresources are kept to the minimum.
Computers, IT & Automation.
-
8/14/2019 Contracts&DisputesHT5
22/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 22
Requirement Today
Contract administrator is required to know(?)
Basic civil work processes & costing.
Component materials.
Services work processes & components.
Material selection & Equipment Selection andeffect on costs.
Building operation costs based on theaspects of Energy efficiency, Environmentfriendliness, Maintainability.
-
8/14/2019 Contracts&DisputesHT5
23/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 23
Drivers for the Change
Changes driven by energy, environment, IT,
fire, natural hazards like earthquake, floods,cyclone, tsunami have influencedconstruction in a big way.
Major change in technology, materials.Standards & Codes.
Regulatory bodies, Local Byelaws, pollution,
Manpower availability, shortage of trained &skilled workers
d f b l
-
8/14/2019 Contracts&DisputesHT5
24/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 24
Wide range of responsibility
Cost controller, Material ManagementProcurement of material & equipment
Work coordination strategy
Life cycle costingTaxation & Tax planning
Outsourcing & sub contracting
Work break-down & package development
Special work packages and costing
Dispute resolution
-
8/14/2019 Contracts&DisputesHT5
25/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 25
Contract systems
Item Rate, Percentage rate, Lump sum
Labour only, turn key, composite
Design & Build, Construct,
Design, Finance, Build, Operate & TransferBuild & Operate
Build, Operate, Transfer,
Build, own, operate & transferPropose, design, build, own, run, share
Fi i l & L l
-
8/14/2019 Contracts&DisputesHT5
26/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 26
Financial & Legal aspects
Process financial controls, inventory control
Dispute resolution ADR, Concilliation, Arbitration
Labour welfare management, worker training
Valuation of assets
Asset managementPlant & Machinery, materials, equipment
N S bj t I C i l
-
8/14/2019 Contracts&DisputesHT5
27/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 27
New Subjects In Curriculum
Economics, Derivatives,Financing
Risk Evaluation & Management
International contracting,exports
Intellectual property rightsHealth & Safety regulations
Case Study
-
8/14/2019 Contracts&DisputesHT5
28/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 28
Case StudyHeathrow Airport Extension
Europes largest and most complexconstruction projects.
HEATHROW TERMINAL 5
4.3 billion Pound; Nov 2001 start; March 2008finish
260 Hectare site; 16 projects; 140 sub projects
1500 contracts; Monthly 80 million Poundswork; over 8000 workers.
Gives 50% additional capacity to the terminal.
U i L d k C t t
-
8/14/2019 Contracts&DisputesHT5
29/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 29
Unique Landmark ContractThe T5 agreement is a unique legal contract in
the construction industry in essence itis a cost reimbursable form of contract inwhich suppliers profits are ring-fenced and
the client retains the risk.
non-adversarial style on the causes of risk and
risk management through integrated teamapproaches.
no claims for additional payments and nopayment disputes so far on the project
Will save 24 months of construction time!!!
BAA uses cost information from other
-
8/14/2019 Contracts&DisputesHT5
30/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 30
BAA uses cost information from otherprojects, validated independently, to set costtargets. If the out-turn cost is lower than the
target, the savings are shared with therelevant partners.
This incentivises the teams to work togetherand innovate. It is the only way to improve
profitability: all other costs, including theprofit margin, are on a transparent open-bookbasis
Agreement focuses on managing the causeand not the effect and ensures success in anuncertain environment. High performancelevels and high benchmarking standards are
demanded from all parties. The idea is to
-
8/14/2019 Contracts&DisputesHT5
31/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 31
BAA selected a consultancy frameworkfor cost consultancy on the T5 project
comprising the Turner & Townsend Groupand EC Harris Group Ltd (known as
TechT).
Both companies were selected under thesame terms of commission and eachprovided 50% of the staff.
On this project these two majorconsultancy companies became one teamjoined at the hip. At its peak the cost
consultancy team comprised 120 staff.
-
8/14/2019 Contracts&DisputesHT5
32/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 32
ConclusionsPreparing development appraisals
Development of the business caseand master planning.
Producing the facility cost model
allowing option appraisals within themaster planning phase and functionallybased cost planning.
Executing the business case
sensitivity analysis to test each optionsrates of return on investment.
International benchmarking of airport
indicators (operational and construction
Conclusions
-
8/14/2019 Contracts&DisputesHT5
33/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 33
Conclusions
2. Advising clients on project brief,
preferred procurement route and cashflow
Design of the incentivised procurementstrategy and resultant contract terms andconditions involving the development of aninnovative strategy and framework agreementagainst which contracts could be let.
TechT and Laing ORourke providedcomprehensive commercial benchmarkingacross the whole T5 programme to enable BAAto judge whether the Anticipated Final Cost(AFCs) provided good/poor value for money
compared to other BAA and non BAA projects.
Conclusions
-
8/14/2019 Contracts&DisputesHT5
34/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 34
Conclusions3. Analysing whole life costs
Implementation and management of aninnovative value improvement process whichsecures cost and time based on themes ofdesigning, buying and delivering better.
4. Planning the construction process Project management of the PlanningSupervision process.
Project planning undertaken jointly between
BAA/Laing ORourke based on overall T5Strategic Plan using Primavera; however QSrole minimal.
Sub-Project Planning - each sub-project (75-
100m) has its own cost and programme-
Conclusions
-
8/14/2019 Contracts&DisputesHT5
35/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 35
Conclusions5. Monitoring control of cost during pre-contract stage
TechT cost managers engaged withsuppliers cost managers to verify the costplans and ensure alignment with the schedule.
The aim was to achieve a cost plan that was95% bottom up i.e. based on figures fromsuppliers by BAAs D Day (the milestonebefore the site assembly starts but when most
of the manufacture is complete and design is95% complete).
Contractors were required to monitor their
pre-contract costs and continually update BAA
Conclusions
-
8/14/2019 Contracts&DisputesHT5
36/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 36
Conclusions6. Preparing tender and contractualdocumentation
TechT supported BAAs Supply Chain teamto negotiate and periodically review
the Commercial Model Agreements (CMAs)
between BAA and each of the 1st
tier suppliers.
TechT supported BAAs Supply Chain in
providing advice on appropriateprocurement routes and choice of Supply foreach work package then utilised
the CMAs as a basis for agreeing the AFC.
7 Ad i i t t
-
8/14/2019 Contracts&DisputesHT5
37/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 37
7. Advising on payments tocontractors, cost control and
settlement of final accountsMajority of 1st tier contractors reimbursed on anactual cost based form of contract; interim paymentsand final account based on actual cost.
TechT work in conjunction with BAAs cost verificationteam to check, audit and then verify that the costsapproved for payment are valid.
used COINS (accounting package) to collate costs;BAA/TechT had read-onlyaccess to COINS to verify that
costs were properly incurred. BAA ran the project using Oracle/Artemis; contractorsfeed information into Artemis using comma separatedvariable (CSV) files on a weekly basis, updating costs,progress and forecasts on a work breakdown structure(WBS) basis.
L i OR k d l d th i d t b t
-
8/14/2019 Contracts&DisputesHT5
38/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 38
Laing ORourke developed their own data-base systemof weekly capturing costs against WBSs, recordingprogress and forecasting final costs, this was loadedelectronically into BAAs Artemis system everyWednesday for the previous week.
8. Controlling the project on behalf of theiremployer
Supporting BAAs integrated team in the preparationof the project process and procedures andimplementation of a project control system andsoftware including change control and riskmanagement.
Introduction of performance management systemwith KPIs based on cost, time and quality criteria.
Provision of monthly earned value analyses (linkingtime and cost) and schedule performance indices.
TechT have driven the production of and are the
9 N ti ti ith li t b t t
-
8/14/2019 Contracts&DisputesHT5
39/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 39
9. Negotiating with client or subcontractors
TechT work with BAA in agreeing AFC targetsthroughout the duration of the programme; each
project and sub-project has its own AFC target,progress against which is reported on and discussedon a monthly basis.
TechT together with BAAs supply chain and 1st tiercontractors work as collaborative teams.
10. Reporting on the programme and financialmatters
The TechT cost managers are integrated within their
project and sub-project teams, they report to theproject leader, who in turn reports to the T5 Directors;TechT are also represented at Programme Office level.
The Heads of Cost Management, CommercialManagement and Performance Measurement are allsenior TechT people reporting to BAA Directors.
Conclusions
-
8/14/2019 Contracts&DisputesHT5
40/41
JNB
INSTRUCT
Program on Emerging Trends In Contract Management &Dispute Resolution 40
Conclusions11. Risk and value management
Ongoing option appraisal and valueengineering of construction systems.
On going value improvement initiativefocusing on productivity improvements
and global acquisition combiningleverage and partnering based buying.
Development of bespoke Risk
Management Process aligned to the T5insurance cover.
12. Giving contractual advice incase of dispute
Minimal dis ute due to collaborative
Conclusions
-
8/14/2019 Contracts&DisputesHT5
41/41
JNB
INSTRUCT
P E i T d I C M &
Conclusions
The example of the present running
project gives an overview ofContract Management withoutdisputes in the context of the megaprojects that are coming up withgreat complexity.
Thank You