Contracts&DisputesHT5

download Contracts&DisputesHT5

of 41

Transcript of Contracts&DisputesHT5

  • 8/14/2019 Contracts&DisputesHT5

    1/41

    Tenders & Contracts.

    Clauses & Conditions.

    Recent Developments

  • 8/14/2019 Contracts&DisputesHT5

    2/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &

    Dispute Resolution 2

    Purpose of a Tender

    Get offers from alternate parties

    who have the competency &capabilityTender evaluation C & C First Step

    Establish equality or clears a set benchmark

    Tender pricing -to be from parties of equal C & Cto be on common platform based on

    Specifications, BOQ and price schedules

    Payment, intermediate & finalTechnology & Time for completion & Quality

    Selected tenderer becomes contractor on acceptanceof tender and signing of the contract

  • 8/14/2019 Contracts&DisputesHT5

    3/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 3

    Purpose of a contract

    Bring two parties together to work for acommo n obj ectiveBoth parties to benefit as a result of the activity

    Parties ---- Owner & Contractor

    Parties ---- Developer & ArchitectParties ---- User & Regulator

    Do these parties have a common objective???

    Each party has its own private goal.Contra ct is to t ie the par ties to thecommo n goa l by satis fy ing the priva tego al of each par ty.

  • 8/14/2019 Contracts&DisputesHT5

    4/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 4

    Tenders & ContractsInfrastructure work contracts constantly gets blamedfor cost & time overruns.

    Most of the contracts result in disputes either duringthe contract period or at the end of it.

    Conditions in tenders, which on acceptance become

    contract conditions are designed or drafted to avoidoverruns and disputes.

    Costi ng or estima ti ng the project cost &mea sur ement & pa yme nts are very criticalactivities responsible for the healthy operation of acontract.

    Projects are complex & Unknown elements either existor crop up during the life of the project.

  • 8/14/2019 Contracts&DisputesHT5

    5/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 5

    PROCESS

    Tenders & Contracts

    SKETCH DESIGN

    Room

    Demands

    Terminal

    Device

    Spec

    Room

    Design

    Co-Ordination

    Equipment

    Selection

    Installation, Testing & Commissioning

    Network

    Design

    Riser and

    Void

    Design

    Fabricatio

    n

    Drawings

    Building

    Demands

    Plant

    Spec

    Plant

    Room

    Design

    Plant

    Selection

  • 8/14/2019 Contracts&DisputesHT5

    6/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 6

    Tenders & Contracts

    Project Brief

    Concept Design

    Detail Design

    Production Info

    Construction

    Testing & Comm

    Occupation

    By

    Employer

    By

    Contractor

    By

    Employer

    By

    Contractor

  • 8/14/2019 Contracts&DisputesHT5

    7/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 7

    Change & Cost of Change

    Tenders & Contracts

  • 8/14/2019 Contracts&DisputesHT5

    8/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 8

    Tenders & ContractsAll contracts basically involve an element of risk

    transfer from one party to the other contractingparty.

    The coverage for picking up the risk is theprofit.

    Conditions in tenders, particularly the non-specific ones such as Any other costs arisingdue to event xxx are to be borne by the

    contractor are the ones which create problem.Errors in Co sti ng o r es ti mat ing the projectcost result in an implied risk.

  • 8/14/2019 Contracts&DisputesHT5

    9/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 9

    Tenders & Contracts

    TIME

    COSTQUALITY

    QuickestMost Certain Earliest Start

    on Site

    Lowest to Buy

    Most Certain

    Lowest in UseDesign

    Client

    Controlled

    Products

    CONTRACT PROFILE

    12

    34

    5

    12

    34

    5

  • 8/14/2019 Contracts&DisputesHT5

    10/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 10

    Tenders & Contracts

    TIME

    COSTQUALITY

    QuickestMost Certain Earliest Start

    on Site

    Lowest to Buy

    Most Certain

    Lowest in UseDesign

    Client

    Controlled

    Products

    D&B CONTRACT PROFILE

    12

    34

    5

    12

    34

    5

  • 8/14/2019 Contracts&DisputesHT5

    11/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 11

    Tenders & Contracts

    TIME

    COSTQUALITY

    QuickestMost Certain Earliest Start

    on Site

    Lowest to Buy

    Most Certain

    Lowest in UseDesign

    Client

    Controlled

    Products

    MANAGEMENT CONTRACT PROFILE

    12

    34

    5

    12

    3

    54

  • 8/14/2019 Contracts&DisputesHT5

    12/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 12

    Tenders & Contracts

    TIME

    COSTQUALITY

    QuickestMost Certain Earliest Start

    on Site

    Lowest to Buy

    Most Certain

    Lowest in UseDesign

    ClientControlled

    Products

    TRADITIONAL CONTRACT PROFILE

    12

    34

    5

    12

    3

    54

  • 8/14/2019 Contracts&DisputesHT5

    13/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 13

    Infrastructure ProjectsInfrastructure projects require inputs from at

    least about 22 different entities for its success.Non cooperation from any-one will cause delay.

    Project success - benefits a few out of the 22.

    -- causes loss or problems to some.-- few are unaffected.

    -- few beneficiaries have no voice.

    -- few have capacity to put spokes.

    Categorization of the 22

  • 8/14/2019 Contracts&DisputesHT5

    14/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 14

    Tenders & Contracts

    M/E Design

    Passive

    Design

    Elements

    ToiletCores

    Horiz/Vert

    Circulation

    Basement

    Planning

    Structure

    CladdingCeilings

    Partitioning

    Floors

    Voids &

    Risers

    Reception

    Joinery

    Catering/

    Refrigeration

  • 8/14/2019 Contracts&DisputesHT5

    15/41

    Project & Contracts

    Their role &the emerging changes in their rolewith changes in construction

    contracting practices.

    Employer

    Employers

    Agent

    Contractor

    ME A CS

    SC1 SC2 SC3 SC4

    QSTheir role &the emerging changes in their rolewith changes in construction

    contracting practices.

  • 8/14/2019 Contracts&DisputesHT5

    16/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 16

    Contract Manager - Functions

    Manage and control costs

    within construction projectsUse a wide range of

    management procedures and

    technical tools to achieve thisgoal.

  • 8/14/2019 Contracts&DisputesHT5

    17/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 17

    Change over the years

    Costs have become dynamic; Fast Changes.

    Technology change, Mechanization.

    From primarily civil engineering work

    to a mix of work of different disciplines, particularly

    Electrical, Air-Conditioning, Plumbing, Electronics,Fire detection & protection-----

    Corresponding to change from single & double storyconstruction

    to multistory complexes.

    Energy costs and Environmental requirements.

  • 8/14/2019 Contracts&DisputesHT5

    18/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 18

    Change over the yearsEnerg y cost s have also brought in a changein the outlook of the architectural design of

    buildings.We cannot afford to overlook the opera tingcost of t he b uil di ng as a whole.Closely associated with the energy are theenvi ronmenta l f actors associated withenergy usage.

  • 8/14/2019 Contracts&DisputesHT5

    19/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 19

    Energy & EnvironmentGlobal Warming which was considered to be adistant dream of a pessimistic scientist is now

    identified to be a reality staring at us.Energy consumption is directly associatedwith the production of green house gassesand global warming.

    We cannot afford to face the consequenceson the environment

    B ildi & E

  • 8/14/2019 Contracts&DisputesHT5

    20/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 20

    Building & Energy

    Our building designs should keep energy in all

    its forms and stages of utilizationEnergy that goes into the formation of thebuilding materials.

    Energy that is utilized in the construction.

    Energy that will be spent during the life time ofthe building.

    CDM (Clean Development) & Green Buildingsare also becoming important.

    S d f C t ti &

  • 8/14/2019 Contracts&DisputesHT5

    21/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 21

    Speed of Construction &Maintainability

    The speed of construction has also beenassuming importance.

    Speed of construction is dependent on the

    method adopted and the type of structure.Maintainability is another aspect.

    Today with the gradual but continuous

    increase in the labor costs it is essential thatthe design is such that the requirements ofresources are kept to the minimum.

    Computers, IT & Automation.

  • 8/14/2019 Contracts&DisputesHT5

    22/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 22

    Requirement Today

    Contract administrator is required to know(?)

    Basic civil work processes & costing.

    Component materials.

    Services work processes & components.

    Material selection & Equipment Selection andeffect on costs.

    Building operation costs based on theaspects of Energy efficiency, Environmentfriendliness, Maintainability.

  • 8/14/2019 Contracts&DisputesHT5

    23/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 23

    Drivers for the Change

    Changes driven by energy, environment, IT,

    fire, natural hazards like earthquake, floods,cyclone, tsunami have influencedconstruction in a big way.

    Major change in technology, materials.Standards & Codes.

    Regulatory bodies, Local Byelaws, pollution,

    Manpower availability, shortage of trained &skilled workers

    d f b l

  • 8/14/2019 Contracts&DisputesHT5

    24/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 24

    Wide range of responsibility

    Cost controller, Material ManagementProcurement of material & equipment

    Work coordination strategy

    Life cycle costingTaxation & Tax planning

    Outsourcing & sub contracting

    Work break-down & package development

    Special work packages and costing

    Dispute resolution

  • 8/14/2019 Contracts&DisputesHT5

    25/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 25

    Contract systems

    Item Rate, Percentage rate, Lump sum

    Labour only, turn key, composite

    Design & Build, Construct,

    Design, Finance, Build, Operate & TransferBuild & Operate

    Build, Operate, Transfer,

    Build, own, operate & transferPropose, design, build, own, run, share

    Fi i l & L l

  • 8/14/2019 Contracts&DisputesHT5

    26/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 26

    Financial & Legal aspects

    Process financial controls, inventory control

    Dispute resolution ADR, Concilliation, Arbitration

    Labour welfare management, worker training

    Valuation of assets

    Asset managementPlant & Machinery, materials, equipment

    N S bj t I C i l

  • 8/14/2019 Contracts&DisputesHT5

    27/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 27

    New Subjects In Curriculum

    Economics, Derivatives,Financing

    Risk Evaluation & Management

    International contracting,exports

    Intellectual property rightsHealth & Safety regulations

    Case Study

  • 8/14/2019 Contracts&DisputesHT5

    28/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 28

    Case StudyHeathrow Airport Extension

    Europes largest and most complexconstruction projects.

    HEATHROW TERMINAL 5

    4.3 billion Pound; Nov 2001 start; March 2008finish

    260 Hectare site; 16 projects; 140 sub projects

    1500 contracts; Monthly 80 million Poundswork; over 8000 workers.

    Gives 50% additional capacity to the terminal.

    U i L d k C t t

  • 8/14/2019 Contracts&DisputesHT5

    29/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 29

    Unique Landmark ContractThe T5 agreement is a unique legal contract in

    the construction industry in essence itis a cost reimbursable form of contract inwhich suppliers profits are ring-fenced and

    the client retains the risk.

    non-adversarial style on the causes of risk and

    risk management through integrated teamapproaches.

    no claims for additional payments and nopayment disputes so far on the project

    Will save 24 months of construction time!!!

    BAA uses cost information from other

  • 8/14/2019 Contracts&DisputesHT5

    30/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 30

    BAA uses cost information from otherprojects, validated independently, to set costtargets. If the out-turn cost is lower than the

    target, the savings are shared with therelevant partners.

    This incentivises the teams to work togetherand innovate. It is the only way to improve

    profitability: all other costs, including theprofit margin, are on a transparent open-bookbasis

    Agreement focuses on managing the causeand not the effect and ensures success in anuncertain environment. High performancelevels and high benchmarking standards are

    demanded from all parties. The idea is to

  • 8/14/2019 Contracts&DisputesHT5

    31/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 31

    BAA selected a consultancy frameworkfor cost consultancy on the T5 project

    comprising the Turner & Townsend Groupand EC Harris Group Ltd (known as

    TechT).

    Both companies were selected under thesame terms of commission and eachprovided 50% of the staff.

    On this project these two majorconsultancy companies became one teamjoined at the hip. At its peak the cost

    consultancy team comprised 120 staff.

  • 8/14/2019 Contracts&DisputesHT5

    32/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 32

    ConclusionsPreparing development appraisals

    Development of the business caseand master planning.

    Producing the facility cost model

    allowing option appraisals within themaster planning phase and functionallybased cost planning.

    Executing the business case

    sensitivity analysis to test each optionsrates of return on investment.

    International benchmarking of airport

    indicators (operational and construction

    Conclusions

  • 8/14/2019 Contracts&DisputesHT5

    33/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 33

    Conclusions

    2. Advising clients on project brief,

    preferred procurement route and cashflow

    Design of the incentivised procurementstrategy and resultant contract terms andconditions involving the development of aninnovative strategy and framework agreementagainst which contracts could be let.

    TechT and Laing ORourke providedcomprehensive commercial benchmarkingacross the whole T5 programme to enable BAAto judge whether the Anticipated Final Cost(AFCs) provided good/poor value for money

    compared to other BAA and non BAA projects.

    Conclusions

  • 8/14/2019 Contracts&DisputesHT5

    34/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 34

    Conclusions3. Analysing whole life costs

    Implementation and management of aninnovative value improvement process whichsecures cost and time based on themes ofdesigning, buying and delivering better.

    4. Planning the construction process Project management of the PlanningSupervision process.

    Project planning undertaken jointly between

    BAA/Laing ORourke based on overall T5Strategic Plan using Primavera; however QSrole minimal.

    Sub-Project Planning - each sub-project (75-

    100m) has its own cost and programme-

    Conclusions

  • 8/14/2019 Contracts&DisputesHT5

    35/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 35

    Conclusions5. Monitoring control of cost during pre-contract stage

    TechT cost managers engaged withsuppliers cost managers to verify the costplans and ensure alignment with the schedule.

    The aim was to achieve a cost plan that was95% bottom up i.e. based on figures fromsuppliers by BAAs D Day (the milestonebefore the site assembly starts but when most

    of the manufacture is complete and design is95% complete).

    Contractors were required to monitor their

    pre-contract costs and continually update BAA

    Conclusions

  • 8/14/2019 Contracts&DisputesHT5

    36/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 36

    Conclusions6. Preparing tender and contractualdocumentation

    TechT supported BAAs Supply Chain teamto negotiate and periodically review

    the Commercial Model Agreements (CMAs)

    between BAA and each of the 1st

    tier suppliers.

    TechT supported BAAs Supply Chain in

    providing advice on appropriateprocurement routes and choice of Supply foreach work package then utilised

    the CMAs as a basis for agreeing the AFC.

    7 Ad i i t t

  • 8/14/2019 Contracts&DisputesHT5

    37/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 37

    7. Advising on payments tocontractors, cost control and

    settlement of final accountsMajority of 1st tier contractors reimbursed on anactual cost based form of contract; interim paymentsand final account based on actual cost.

    TechT work in conjunction with BAAs cost verificationteam to check, audit and then verify that the costsapproved for payment are valid.

    used COINS (accounting package) to collate costs;BAA/TechT had read-onlyaccess to COINS to verify that

    costs were properly incurred. BAA ran the project using Oracle/Artemis; contractorsfeed information into Artemis using comma separatedvariable (CSV) files on a weekly basis, updating costs,progress and forecasts on a work breakdown structure(WBS) basis.

    L i OR k d l d th i d t b t

  • 8/14/2019 Contracts&DisputesHT5

    38/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 38

    Laing ORourke developed their own data-base systemof weekly capturing costs against WBSs, recordingprogress and forecasting final costs, this was loadedelectronically into BAAs Artemis system everyWednesday for the previous week.

    8. Controlling the project on behalf of theiremployer

    Supporting BAAs integrated team in the preparationof the project process and procedures andimplementation of a project control system andsoftware including change control and riskmanagement.

    Introduction of performance management systemwith KPIs based on cost, time and quality criteria.

    Provision of monthly earned value analyses (linkingtime and cost) and schedule performance indices.

    TechT have driven the production of and are the

    9 N ti ti ith li t b t t

  • 8/14/2019 Contracts&DisputesHT5

    39/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 39

    9. Negotiating with client or subcontractors

    TechT work with BAA in agreeing AFC targetsthroughout the duration of the programme; each

    project and sub-project has its own AFC target,progress against which is reported on and discussedon a monthly basis.

    TechT together with BAAs supply chain and 1st tiercontractors work as collaborative teams.

    10. Reporting on the programme and financialmatters

    The TechT cost managers are integrated within their

    project and sub-project teams, they report to theproject leader, who in turn reports to the T5 Directors;TechT are also represented at Programme Office level.

    The Heads of Cost Management, CommercialManagement and Performance Measurement are allsenior TechT people reporting to BAA Directors.

    Conclusions

  • 8/14/2019 Contracts&DisputesHT5

    40/41

    JNB

    INSTRUCT

    Program on Emerging Trends In Contract Management &Dispute Resolution 40

    Conclusions11. Risk and value management

    Ongoing option appraisal and valueengineering of construction systems.

    On going value improvement initiativefocusing on productivity improvements

    and global acquisition combiningleverage and partnering based buying.

    Development of bespoke Risk

    Management Process aligned to the T5insurance cover.

    12. Giving contractual advice incase of dispute

    Minimal dis ute due to collaborative

    Conclusions

  • 8/14/2019 Contracts&DisputesHT5

    41/41

    JNB

    INSTRUCT

    P E i T d I C M &

    Conclusions

    The example of the present running

    project gives an overview ofContract Management withoutdisputes in the context of the megaprojects that are coming up withgreat complexity.

    Thank You