Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire...

49
UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Contractor Forum Overview of Contractor Safety Expectations FY18 1

Transcript of Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire...

Page 1: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Contractor Forum Overview of Contractor Safety

Expectations FY18

1

Page 2: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Outline

Welcome – Marta Salinas Hovar

Occupational Health and Safety Issues – Richard Costello

Environmental Issues – Richard Costello

Emergencies – Richard Costello

Security – Jorge Garza

2

Page 3: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Our Goals

• Comply with rules and regulations and best management practices applicable to the workplace and the environment.

• Protect the worker (both UTRGV and Contractor)

• Protect the environment

• Protect the UTRGV community

3

Page 4: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Key Players

Department Name Title

ASFC Marta Salinas Hovar Associate VP for Facilities Planning and Operations

ASFC Abraham Hernandez Director of Campus Facilities Operations

ASFC Oscar Villarreal Director of Campus Facilities Operations

ASFC Jorge Garza Director of Construction Services

EHSRM Richard Costello Director of EHSRM

EHSRM Laura De Jesus Program Manager - Occupational Health and Safety

EHSRM Saul Jauregui Program Manager - Fire Safety

4

Page 5: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Construction Environmental Health and Safety Related Issues

5

Page 6: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Contractors are expected to:

Comply with local, state, and federal rules and regulations and best management practices applicable to the workplace and the environment.

6

Page 7: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 7

Page 8: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Construction Industry Fatal Four (2014)

1. Falls – 359 of 899 total deaths in construction in the year 2014 (39.9%)

2. Electrocutions - 74 (8.2%)

3. Struck by object - 73 (8.1%)

4. Caught-in/between* - 39 (4.3%)

8

*This category includes construction workers killed when caught-in or compressed by equipment or objects; and struck, caught, or crushed in collapsing structure, equipment, or material.

Page 9: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Statistics

1. One in ten construction workers are injured every year. (Source: The Occupational Safety and Health Administration)

2. Over the course of a 45-year career, a construction worker has a 1 in 200 chance of dying. (Source: Safety + Health.)

3. Falls are the greatest cause of fatal construction injuries. (Source: The Center for Construction Research and Training.)

9

Page 10: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Fatal Falls

10

Page 11: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Program Basis

Citing construction workers for non-compliance with applicable rules and regulations increases liability to the institution, consequently, concentrate on those rules and regulations and best management practices that:

– have the potential to directly impact the UTRGV community

– increase liability to the institution

The institution has a responsibility to the Rio Grande Valley construction community.

11

Page 12: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Outstanding Issues

• Sub-Contractor Oversight

• Occupational Health and Safety Issues

– Signage

– Housekeeping

– Indoor Air Quality

– Fire Protection/Egress

– Lighting

– Hazard Communication

• Environmental Issues

12

Page 13: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Occupational Health and Safety Issues

13

Page 14: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Contractor Oversight

Contractors are responsible for their sub-contractors from both a compliance and liability standpoint.

Ensure that sub-contractors comply with local, state, and federal rules and regulations applicable to the workplace and the environment.

14

Page 15: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Site Signage

OSHA requires that people on or near construction sites are warned of all hazardous activities taking place. Before any construction work begins, builders must ensure that an adequate number of general safety signs, depending on the size and complexity of the job site, are erected at the workplace.

15

Page 16: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Barriers and Liability

• Civilians and private citizens are not permitted to enter construction zones without the expressed permission or authorization to do so.

• Failure to delineate construction zones goes beyond the scope of safety rules and regulations and is easily demonstrable in the court of law as “negligent”.

• Undergraduates = Minors

16

A construction sign acts as an expression of notification through the application of physical, identifiable, and textual displays designating the required adherence to standards and practices within the perimeters of a construction zone.

Page 17: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Construction Signage

• Construction signs should be posted in order to convey the requirement of any individuals located within the perimeter of a construction site to wear protective gear and safety equipment, such as hard hats and safety glasses.

• Construction signs should be posted in order to convey the requirement for operators of machinery and equipment considered to pose the risk of injury or death through misuse to possess applicable licenses, training, and certification for operation.

• Construction signs should be posted in order to convey any potentially hazard materials or substances within the proximity of the notifying construction sign.

17

Page 18: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Housekeeping

• Accounts for 25% of all construction related injuries.

• During the course of construction, alteration, or repairs, form and scrap lumber with protruding nails, and all other debris, shall be kept cleared from work areas, passageways, and stairs, in and around buildings or other structures.

• Combustible scrap and debris shall be removed at regular intervals during the course of construction. Safe means shall be provided to facilitate such removal.

• Containers shall be provided for the collection and separation of waste, trash, oily and used rags, and other refuse. Containers used for garbage and other oily, flammable, or hazardous wastes, such as caustics, acids, harmful dusts, etc. shall be equipped with covers. Garbage and other waste shall be disposed of at frequent and regular intervals.

18

Page 19: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Indoor Air Quality

Contractors are expected to protect the indoor air quality of the occupied spaces adjacent to the construction area.

– Particulates (dust, welding, internal combustion engines)

– Volatile Organic Compounds - VOCs (painting)

– Noise (jack-hammers, etc.)

19

Methods to Enhance Indoor Air Qualityto reduce Indoor Air Pollution

Control source of pollution

Remove pollutants from air

Increasing ventilation/dilution

Air cleaning

Page 20: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Basic Thermodynamics

The flow of any liquid or gas will always flow in the direction of least resistance (less pressure).

UTRGV Thermodynamics

The area of least pressure is always located in the area where the most sensitive person in the building resides.

20

Page 21: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Dust Control

Implement dust control measures where processes that generate dust take place - construction, sanding, demolition, etc.

– Barriers

– Ventilation

– Water Trucks

21

Page 22: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Lighting

Construction areas, aisles, stairs, ramps, runways, corridors, offices, shops, and storage areas where work is in progress shall be lighted with either natural or artificial illumination. The minimum illumination requirements for work areas are contained in the Occupational Safety and Health Administration Regulations Part 1926, Subpart D.

22

Page 23: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Illumination Requirements

23

Table D-3 Minimum Illumination Intensities

Foot-Candles

Area of Operation

5 General construction area lighting.

3 General construction areas, concrete placement, excavation and waste areas, access ways, active storage areas, loading platforms, refueling, and field maintenance areas.

5 Indoors: warehouses, corridors, hallways, and exit ways.

5 Tunnels, shafts, and general underground work areas.

Exception: minimum of 10 foot-candles is required at tunnel and shaft heading during drilling, mucking, and scaling. Bureau of Mines approved cap lights shall be acceptable for use in the tunnel heading)

10 General construction plant and shops (e.g., batch plants, screening plants, mechanical and electrical equipment rooms, carpenter shops, rigging lofts and active store rooms, mess halls, and indoor toilets and workrooms.)

30 First aid stations, infirmaries, and offices.

Page 24: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Fire Safety

• Smoking is prohibited on all construction sites (even outside)

• Fire Drills/Alarms – contractors are required to exit the building when alarm goes off

• Housekeeping

• Evacuation aisles

• Avoid blocking exits

• Hot Work Permits (contact EHSRM at 956-665-3690)

• Fire extinguisher training required for contractor personnel if work involves processes which could result in fire (i.e. welding, soldering)

• Constructors should bring their own inspected fire extinguisher.

24

Page 25: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Fire Safety – Systems in Place

• Hot Work Permit

– Required for all open flames and inside work

• Wet Sprinkler Systems

– Drain the system if hazard exists

– Provide access to wet sprinkler system

– Emergency numbers

• Alarm System

– Cover smoke detectors

– Disengage alarm system if necessary in sprinklered building

• Fire Watch required for systems that are out for more than four hours

• Coordinate through Project Manager who will communicate with EHSRM.

25

Page 26: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Evacuation Egress

General: In every building or structure, exits shall be so arranged and maintained as to provide free and unobstructed egress from all parts of the building or structure at all times when it is occupied. No lock or fastening to prevent free escape from the inside of any building shall be installed except in mental, penal, or corrective institutions where supervisory personnel is continually on duty and effective provisions are made to remove occupants in case of fire or other emergency.

26

Exit marking: Exits shall be marked by a readily visible sign. Access to exits shall be marked by readily visible signs in all cases where the exit or way to reach it is not immediately visible to the occupants.

Maintenance and workmanship: Means of egress shall be continually maintained free of all obstructions or impediments to full instant use in the case of fire or other emergency.

Page 27: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Parking

• Parking is limited in areas on campus

• Parking is prohibited next to fire lane

• Parking is prohibited within 25 feet of an FDC

• Parking is prohibited 15 feet of a hydrant

• Yellow lanes denote an unloading zone. It is not an allowable parking zone.

27

Page 28: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Construction Environmental Related Issues

28

Page 29: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Water Releases - Storm Water

• MS4 Municipal Separate Storm Sewer System (MS4)

• UTRGV Storm Water Pollution Prevention Plan (SWPPP)

• Keep construction related dirt, silt, chemicals, and other undesirables out of the storm drain system and out of nearby natural water systems.

– Sandbag Berms

– Gravel Bags

– Silt Fences

– Fiber Rolls

– Erosion Control Blankets

– Hydro Seeding

– Mulching

– Proper Construction Entrances

• Required to comply regardless of the size of the site

• Both institution and contractor is subject to fine

• Contractor is responsible for UTRGV’s fines29

Page 30: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

UTRGV Permitting Requirements

Construction Site MS4 Compliance Permitting Responsibility

< 1 Acre Yes N/A

1-5 Acres Yes UTRGV Contractor

> 5 acres Yes Contractor

30

Page 31: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Strategies

• Construction Site Planning and Management Sediment Control

• Runoff Control

• Good Housekeeping

31

Page 32: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Water Releases – Waste Water Permit

• City of Edinburg Waste Water Permit

• UTRGV has three outfalls

– Analyzed four times a year

– Monitored at lift stations

• Prohibited Discharges to sanitary sewer

– All contaminants

• Volatile Organic Compounds

• 16 heavy metals

•Oil and grease

• Arrange for disposal of all contaminants through EHSRM

32

Page 33: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Wastewater Treatment Analysis

33

Page 34: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Regulated Waste

• UTRGV is ultimately responsible and liable for the disposal of all regulated waste generated from a construction site.

• Contractor is expected to properly dispose of all regulated waste streams

– Paint waste

– RCRA fluorescent lights

– Non-RCRA fluorescent lights

– PCB ballasts

– Non-PCB ballasts• Certificate of recycling is not a valid tracking or RCRA document

• Certificate of recycling needs to reference the Bill Of Lading (BOL) or manifest

34

Page 35: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Regulated Waste – Fluorescent Lights

• Bulbs shall not be left on the fixture for disposal by UTRGV

• Bulbs are not allowed to be disposed of in the landfill

• Bulbs should be handled to prevent breaking

• Store in an appropriate box and palletize for shipment

• Boxes should be labeled “Universal Waste: Fluorescent light bulbs” and accumulation date marked on label

• Shipment to an approved recycling contractor

• A Bill Of Lading (BOL) with a BOL number referencing date, quantity of pallets of bulbs shipped, shipper, transporter, and destination must be provided to shipper

• A certificate of receipt and recycling referencing the BOL number should be provided by recycling contractor to shipper

• Contractor must provide a copy of BOL and certificate of recycling to the UTRGV EHSRM.

35

Page 36: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Regulated Waste - Ballasts

• Non-PCB ballasts should be segregated from PCB ballasts

• Ballasts should be stored in a compatible container

• Container should be labeled “Universal Waste: Non-PCB Ballasts” or “PCB Ballasts” and accumulation date marked on label

• Shipment to an approved recycling contractor

• A Bill Of Lading (BOL) with a BOL number referencing date, quantity of containers shipped, shipper, and destination must be provided to shipper

• A certificate of receipt and recycling referencing the BOL number should be provided by recycling contractor to shipper

• Contractor must provide a copy of BOL and certificate of recycling to the UTRGV EHSRM.

36

Page 37: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

If you fail to manage lamps bulbs as a universal waste, it is regulated as a hazardous waste.

37

Page 38: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Asbestos

• EHSRM oversees asbestos projects

• All construction projects on buildings that currently have asbestos need to be abated prior to construction. If there is a chance for disturbance of asbestos, contact EHSRM.

• All projects are required to be evaluated by the EHSRM prior to construction to ensure

– compliance with State of Texas Asbestos rules and regulations

– that personnel are not exposed to asbestos.

• Encourage contractors to ask questions

38

Page 39: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Emergency Response

All incidents are required to be reported to UTRGV Facilities

– Work related injuries

– Chemical spills

Emergency Response

– Call 911

– UTRGV Campus

West Campuses (956) 665-7151

East Campuses (956) 882-8232

39

Page 40: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Security / Background Checks

40

Page 41: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 41

Page 42: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 42

Page 43: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 43

Page 44: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 44

Academic Services(EACSB)

Page 45: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 45

University Library(BLIBR)

Page 46: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Contractor ID

46

Page 47: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 47

Page 48: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18

Enforcement

• Routine Inspections will be conducted of all constructions sites on routine basis

• Depending on severity of violation

– Verbal warnings

– Written citation (local)

– Escalated to contactor management

• Repeated violations or conditions that are immediately dangerous to life or health (IDLH) will result in immediate cessation of activities.

48

Page 49: Contractor Forum Overview of Contractor Safety Expectations FY18€¦ · inspected fire extinguisher. 24. UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 Fire

UTRGV Contractor Forum: Overview of Contractor Safety Expectations FY18 49