Contracting for Power Purchase

download Contracting for Power Purchase

of 22

Transcript of Contracting for Power Purchase

  • 8/8/2019 Contracting for Power Purchase

    1/22

    Contracting for power purchase-Ensuring a fair

    deal for the private investor as well as the power

    purchaser

    Lata Chakravarthy

    Faculty Member

    ICFAI Business School

    Bangalore

  • 8/8/2019 Contracting for Power Purchase

    2/22

  • 8/8/2019 Contracting for Power Purchase

    3/22

    Lata Chakravarthy 3

    Objective of study

    To identify best practices in power contracting to

    encourage more private sector participation in

    power generation.

    To identify scope for reduction in cost of power

    purchased from existing IPPs, by analyzing the

    various fixed and variable components of purchase

    cost and their impact on total tariff.

  • 8/8/2019 Contracting for Power Purchase

    4/22

    Lata Chakravarthy 4

    Scope of study

    Study covers the following IPPs whose PPAs

    were available in public domain and which are

    operating in South India:

    1. GVK Power Corporation Ltd.

    2. Spectrum Power Generation Ltd.

    3. Kondapalli Power Corporation Ltd.

    4. Madurai (Balaji) Power Corporation Ltd.

    5. Tanir Bavi Power Corporation Ltd.

  • 8/8/2019 Contracting for Power Purchase

    5/22

    Lata Chakravarthy 5

    Methodology

    The basis for computing the fixed costs, variable

    costs and incentives as laid out in the Power

    Purchase Agreements (PPAs) were compared

    and analyzed.

    Terms of PPA which were amended/renegotiated

    were studied to see the impact on tariff.

  • 8/8/2019 Contracting for Power Purchase

    6/22

    Lata Chakravarthy 6

    Particulars GVK Spectrum Kondapalli Balaji Tanir

    bavi

    Project

    awarded

    through

    MoU route MoU route Bid route MoU route Bid route

    CompletedCapital cost

    Rs.1025cr.

    Rs.972.60cr.

    Rs.1112 cr. Rs.429.03 cr. Rs.880 cr.

    Installed

    Capacity in

    MW

    216.824 208 368.144 106 220

    Capital cost per

    MW

    Rs.4.73 cr. Rs.4.68 cr. Rs.3.02 cr. Rs.4.05 cr Rs.4 cr.

    Term of PPA 18 years 18 years 15 years 15 years 7 years

    Primary Fuel Gas Gas Gas (switched

    over from

    naphtha

    In Sep 2002).

    LSFO Naphtha

    Commercial

    Operation Date

    June 1997 April 1998 October 2000 September

    2001

    July

    2001

  • 8/8/2019 Contracting for Power Purchase

    7/22

    Lata Chakravarthy 7

    Components of fixed charge in MOU projects

    Interest on term loans

    Interest on working capital

    Depreciation

    Return on Equity

    Insurance 1% of capital cost

    O&M expenses of 2% of capital cost

    Foreign exchange variation on interest, debtrepayment and Return on Equity

  • 8/8/2019 Contracting for Power Purchase

    8/22

    Lata Chakravarthy 8

    Components of fixed charge in bid route projects

    Foreign Debt Service Charge (typicallyquoted in $ per kwh) towards,

    Payment of interest on foreign currency loans

    Repayment of foreign currency loans

    Return on foreign equity Other Fixed Charge (typically quoted in Rs.

    per kwh) towards,

    Payment of interest on rupee loans

    Repayment of rupee loans Return on rupee equity

    O&M and insurance charges

  • 8/8/2019 Contracting for Power Purchase

    9/22

    Lata Chakravarthy 9

    Comparison of price risk to utility in the two methods of

    calculating fixed cost

    MoU cases Risk of increase in capital cost after signing of PPA (Tariff can be

    based on actual higher capital cost subject to approval)

    This has impact on

    Interest on debt

    Return on Equity Incentive payment

    Depreciation

    O & M expenses

    Insurance expenses

    Foreign exchange variation in interest, debt repayment and ROE

    Bid route cases No such risk as a fixed amount is paid per unit of energy generated,

    no matter what was the actual cost of completion of the project.

  • 8/8/2019 Contracting for Power Purchase

    10/22

    Lata Chakravarthy 10

    Comparison of price risk to utility in the two methods of

    calculating fixed cost

    MoU cases-other issues

    Increased burden on utility to constantly verify

    the current sources of debt- IPPs keep swapping

    high cost debt with low cost debt as a cost

    reduction measure.

    Utility has to track the interest charged by banks

    from time to time on working capital loans

    each bank in the consortium may lend atdifferent rates.

  • 8/8/2019 Contracting for Power Purchase

    11/22

    Lata Chakravarthy 11

    How fixed costs were reduced for GVKby renegotiating

    PPA terms

    Project cost of Rs.816 crores as per TEC wasfixed as ceiling though actual completed cost was

    Rs.1025 crores.

    This saving of Rs.209 crores has positive impact

    on all the fixed charge components interest,

    depreciation, ROE, O & M and insurance

    charges.

    The levelized tariff with Rs.1025 cr. of projectcost is Rs.2.6904 per Kwh vis--vis Rs. 2.6275

    per Kwh with Rs.816 cr. of project cost.

  • 8/8/2019 Contracting for Power Purchase

    12/22

    Lata Chakravarthy 12

    How fixed costs were reduced for GVKby renegotiating

    PPA terms

    Reduction in O & M charges from 2.5% to 2% -this reduces the payment to IPP by Rs.40.8 cr

    p.a.

    The effect on levelized tariff is a reduction by

    2.54 paise per kwh.

    The term of PPA was reduced from 30 years to

    18 years by an amendment to PPA.

    Amendment provided for a rebate of 2.5% to beallowed to the utility if it settles a bill within 5

    days reduces levelized tariff by 0.27 paise.

  • 8/8/2019 Contracting for Power Purchase

    13/22

    Lata Chakravarthy 13

    Actual Fixed Costs for 2001-02

    Name of IPP Fixed cost

    In Rs. Per kwh

    GVK 1.52

    Spectrum 1.61

    Kondapalli 1.22

    Balaji 1.52

    Tannirbavi 1.98

  • 8/8/2019 Contracting for Power Purchase

    14/22

    Lata Chakravarthy 14

    Incentive payment

    Basis of payment

    GVK

    For every 1% increase in PLF from 68.5% to 85%, .0525% of

    additional ROE.

    Incentive payable on notional generation also.

    PPA was amended to reduce rate of incentive from .6% to

    .525% and also to cap incentive payment at 85% PLF.

    Effect is to reduce maximum ROE payment including

    incentives to 25% from 35%. Applied to equity of

    Rs.243.23 crores, this amounts to a saving of Rs.24.32 cr

    p.a.

  • 8/8/2019 Contracting for Power Purchase

    15/22

    Lata Chakravarthy 15

    Incentives

    Spectrum Power

    Basis of payment

    68.5% to 80.5% .4% for every 1% increase in PLF

    80.5% to 85.5% .5% for every 1% increase in PLF

    above 68.5%

    > 85.5% .6% for every 1% increase in PLF

    above 68.5%

    Kondapalli Power

    80% to 85% PLF 2% of Other Fixed Charges (OFC)

    85% to 90% PLF 10% + 3% for every 1% increase inROE above 85%

    > 90% Same as for 90% i.e 25% of OFC

  • 8/8/2019 Contracting for Power Purchase

    16/22

    Lata Chakravarthy 16

    Comparison ofIncentives

    GVK Spectrum Kondapalli

    Maximumpossible ROE

    including

    incentives

    25% 34.9% 26.7%

  • 8/8/2019 Contracting for Power Purchase

    17/22

    Lata Chakravarthy 17

    Scope for further reduction in fixed cost

    Floor for incentives should be at around 80% and

    not at 68.5%

    No incentive on deemed/notional generation

    Term loans which are in strong currencies likeEuro should be swapped.

    Repayment of debt should be reimbursed rather

    than depreciation.

  • 8/8/2019 Contracting for Power Purchase

    18/22

    Lata Chakravarthy 18

    Repayment of debt instead of depreciation

    PPAs of MoU projects provide for recovery of

    capital by way of reimbursement of depreciation

    Entire project cost (including land cost in some

    cases) is taken as comprising of depreciable fixedassets

    Assets are depreciated on straight line basis over a

    12 year period up to 90% of original value.

  • 8/8/2019 Contracting for Power Purchase

    19/22

    Lata Chakravarthy 19

    Why not depreciation?

    Depreciation is recovery of capital

    Reimbursing depreciation as part of fixed charges

    amounts to recovery of not only debt but also

    equity Power price is meant to include only return on

    equity and not return of equity,

    Major portion of equity is also returned to investor

    in the process.

  • 8/8/2019 Contracting for Power Purchase

    20/22

  • 8/8/2019 Contracting for Power Purchase

    21/22

    Lata Chakravarthy 21

    Conclusion

    It is possible to bring down cost of power generated evenby existing IPPs.

    IPP not a bad word!

    Negotiate-benchmark against the most competitive bid

    received. Utility should set payment track record to generate

    confidence among IPPs, rather than setting up payment

    security mechanisms.

    Set up infrastructure on priority basis to distribute gas andconvert liquid fuel based projects to gas.

    Key role for regulator and utility in the entire process.

  • 8/8/2019 Contracting for Power Purchase

    22/22

    Lata Chakravarthy 22