Contract Types
![Page 2: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/2.jpg)
Forms of Contracts
• Completion – A product is delivered– Cost or Fixed Price– Product must be delivered– Contract completed on delivery and
acceptance
• Term – Level of Effort– Amount of labor delivered over time– Use personnel and facilities as spelled out
![Page 3: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/3.jpg)
General Rules
• Fixed Price– Perform work, deliver product, get paid– Contractor is at risk
• Cost– Contractor provides “best effort,” works to a
percentage of negotiated costs and then notifies the government
![Page 4: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/4.jpg)
Which Type?
• Nature and complexity of effort
• Urgency
• Period of performance
• Competition
• Difficulty in defining performance
• Availability of data
![Page 5: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/5.jpg)
General Budgeting Rule
• PMs must budget to the “most likely price”
• Most likely price– Varies by contract type
![Page 6: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/6.jpg)
Cost Reimbursement
• Establish an estimate of total cost for the purpose of obligating funds and establishing a ceiling that the contractor may not exceed except at his own risk
• Provide payment of ALLOWABLE incurred costs to the extent provided in the contract
![Page 7: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/7.jpg)
Cost-Plus-Fixed-Fee
• Pays all reasonably incurred and allowable costs plus a fixed dollar amount as a fee
• Fee based on the estimated cost of the contract and stays “fixed” regardless of actual costs
![Page 8: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/8.jpg)
CPFF
• Appropriate when estimates of cost, performance, and schedule are uncertain
• Flexibility is needed
• Monitoring needs are high
• Change is anticipated
![Page 9: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/9.jpg)
CPFF
• Contractors recover costs
• Provides least incentive to contractor to control costs and be efficient
• Incentive to underrun is because the fixed fee becomes a higher percentage
• Trade-offs between cost and technical excellence
• Budget to expected cost plus fixed fee
![Page 10: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/10.jpg)
Cost-Plus-Award-Fee
• Acts like a CPFF except the fixed fee is 0% or some small base fee
• Contractor earns more fee through and “Award Fee Plan”
• Award is the unilateral right of the government
![Page 11: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/11.jpg)
CPAF
• Appropriate when estimates of cost, performance, and schedule are uncertain
• More incentive is desired than CPFF
• Administrative capability is available
• Award is based on judgment of Award Determining Official
• Budget to expected costs plus entire available fee
![Page 12: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/12.jpg)
Cost-Plus-Incentive-Fee
• Shift cost risk to contractor
• Contractor should assume more risk:– More detailed specs– Less uncertainty– Better able to estimate costs
• Contractor now shares in overruns and underruns
![Page 13: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/13.jpg)
CPIF
• Negotiate certain items– Target cost– Target fee– Max fee – Min fee– Share line
• Regardless of cost the fee is never more than the max, nor less than the min
![Page 14: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/14.jpg)
CPIF
• Appropriate when uncertainties can be identified and quantified to some degree
• Used to incentivize the contractor when uncertainties still preclude Fixed Price
• Used in R&D when uncertainties can be resolved by $$
![Page 15: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/15.jpg)
Share Formula
• Expressed as a percentage with the government’s share first
• Example:– 80/20 share means that the government pays
80% of overruns or keeps 80% of underruns
– Contractor’s fee is reduced by 20 cents for every dollar of overrun
– Contractor’s fee is increased by 20 cents for every dollar of underrun
![Page 16: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/16.jpg)
CPIF
• Budget to expected cost and fee
Fee
Max
Target
Min
CostTarget
100/0
0/100
Effective range of Incentive80/20
![Page 17: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/17.jpg)
Fixed Price Contracts
• Funding of cost overruns is not possible
• Contractor obligated to deliver specific product at the price negotiated regardless of cost
• Appropriate when cost, performance, and schedule uncertainty is low of manageable
![Page 18: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/18.jpg)
Firm-Fixed-Price
• Contractor must manage cost within price
• Highest profit potential– More cost means less profit
• Completion form– Can have FP elements of a contract
• Level of Effort can be at a fixed price
• Budget to final negotiated price
![Page 19: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/19.jpg)
Fixed Price Incentive Firm
• Uncertainty too great for FFP
• Completion form
• Contractor must perform
• Contractor performs at own expense when costs exceed ceiling price
![Page 20: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/20.jpg)
FPIF
• Negotiate– Target Cost– Target Profit– Ceiling Price– Share line
• Profit is more than target if final cost is less than target cost and decreased if final cost is more than target cost
• Regardless, the ceiling is firm
![Page 21: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/21.jpg)
FPIFProfit
Target Profit
TargetCost
CostAt
PTA
Contract price lineBased on Share
Point of Total Assumption
Ceiling Price
![Page 22: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/22.jpg)
FPIF
• Budget to the target price of the contract– Budgeting to the ceiling price indicates that
the government does not believe that the incentives will change contractor performance
![Page 23: Contract Types. Forms of Contracts Completion – A product is delivered –Cost or Fixed Price –Product must be delivered –Contract completed on delivery.](https://reader036.fdocuments.in/reader036/viewer/2022062515/56649d0d5503460f949e182d/html5/thumbnails/23.jpg)
FP w/Economic Price Adjustment
• Price negotiate on assumptions regarding economic prices of materials or labor
• EPA clause kicks in if assumptions fail and some trigger is set-off
• Can be pre-negotiated or based on an index
• Budged to anticipated price– Does not include EPA– EPA adjustment should be unlikely