CONTRACT DOCUMENTS ASBESTOS ABATEMENT, DEMOLITION, …

258
CONTRACT DOCUMENTS ASBESTOS ABATEMENT, DEMOLITION, SITE CLEARANCE, BACKFILL AND GRADING OF 68 TEAMSTERS DRIVE LOCATED IN THE CITY OF YOUNGSTOWN, OHIO JOHN A. MCNALLY, MAYOR CHARLES T. SHASHO, DEPUTY DIRECTOR OF PUBLIC WORKS (For Bidder’s Use) PREPARED BY: ms consultants 333 E Federal Street Youngstown, Ohio 44503 VOLUME 2 OF 2 SEPTEMBER 2017 FOR INFORMATION USE ONLY NOT FOR BIDDING CONTACT CITY OF YOUNGSTOWN PURCHASING DEPARTMENT AT (330) 742-8729

Transcript of CONTRACT DOCUMENTS ASBESTOS ABATEMENT, DEMOLITION, …

CONTRACT DOCUMENTS

ASBESTOS ABATEMENT, DEMOLITION, SITE CLEARANCE,

BACKFILL AND GRADING OF

68 TEAMSTERS DRIVE LOCATED IN THE

CITY OF YOUNGSTOWN, OHIO

JOHN A. MCNALLY, MAYOR CHARLES T. SHASHO, DEPUTY DIRECTOR OF PUBLIC WORKS

(For Bidder’s Use) PREPARED BY: ms consultants 333 E Federal Street Youngstown, Ohio 44503

VOLUME 2 OF 2

SEPTEMBER 2017

FOR INFORMATIO

N USE O

NLY

NOT FOR BID

DING

CONTACT CITY O

F YOUNGSTOW

N

PURCHASING D

EPARTMENT AT

(330)

742-8

729

TECHNICAL SPECIFICATIONS

for

ASBESTOS ABATEMENT and DEMOLITION OF

68 TEAMSTERS DRIVE YOUNGSTOWN, OHIO

AUGUST 2017

Prepared by:

ms consultants, inc. 333 E. Federal Street

Youngstown, Ohio 44503

Table of Contents

Removal - Specification Sections Division 1 - General Requirements 01013 Summary of Work 01028 Application for Payment 01043 Coordination 01097 Reference Standards and Definitions - Asbestos Abatement 01098 Codes, Regulations and Standards - Asbestos Abatement 01301 Submittals - Asbestos Abatement 01503 Temporary Facilities - Asbestos Abatement 01513 Temporary Pressure Differential & Air Circulation System 01520 Utilities 01526 Temporary Enclosures 01527 Regulated Areas 01560 Worker Protection - Asbestos Abatement 01562 Respiratory Protection 01563 Decontamination Units 01601 Materials and Equipment - Asbestos Abatement 01701 Contract Closeout - Asbestos Abatement 01711 Project Decontamination 01712 Cleaning and Decontamination Procedures Division 2 - Site Work 02050 Building Demolition 02061 Building Component Demolition - Asbestos Abatement 02081 Removal of Asbestos-Containing Materials 02084 Disposal of Regulated Asbestos-Containing Material 02086 Hazardous Waste Management 02270 Environmental Protection 02272 Construction Storm Water Control 02801 Traffic Control 02810 Grading and Turfing 311100 Clearing and Grubbing

68 Teamsters Drive – Abatement & Demolition Summary of Work City of Youngstown 01013 - 1

SECTION 01013

SUMMARY OF WORK PART 1 GENERAL 1.1 DESCRIPTION A. The Contractor shall perform the Asbestos Abatement and Building Demolition activities at 68

Teamsters Drive in accordance with all federal, state and local laws, local ordinances. A copy of the asbestos survey reports (by others, supplemented by ms consultants, inc.) and the sampling results are provided at the end of this section. For purposes of this project the asbestos abatement and demolition specification sections are provided herein.

PART 2 PRODUCTS 2.1 REQUIREMENTS A. The Scope of Work Shall Include the Following Tasks:

a. Development of a Project Workplan, Health and Safety Plan, Construction Contingency Plan, and a Storm Water Pollution Prevention Plan.

b. Mobilization/Site Walkover c. Structural Evaluation of the Potential Common Wall (SE Wall) of Room#4 d. Asbestos Abatement and Disposal

e. Protection of Adjacent Building Roof top and walls, asphalt parking areas, and overhead

utilities

f. Clearing and Grubbing of property

g. Building Demolition h. “Hot Load” out Room#1 (Basement Contents Only), as RACM

i. Backfilling of Building Voids (eg. basements/cellars)

j. Temporary Seeding and Mulching

PART 3 EXECUTION 3.1 The Contractor shall furnish all equipment, personal protective equipment, and other devices to

perform the asbestos abatement and demolition activities. 3.2 Workplan strategy, the Workplan includes procedures and specifications required to implement the

asbestos/demolition activities set forth above. The Contractor shall prepare and submit to the

68 Teamsters Drive – Abatement & Demolition Summary of Work City of Youngstown 01013 - 2

Engineer a written Project Work Plan, Health and Safety Plan, Construction Contingency Plan and a Storm Water Pollution Prevention Plan for approval. In addition, landfill approval documentation and names of any Sub-Contractors the Contractor may use, must be submitted prior to initiating any work. The details of each task are presented below.

3.3 Special Fees: The contractors shall be responsible for any fees associated with disposal of excavated

materials, such as solid waste district fees, waste profile fees, county fees, storage fees, tipping fees, special permits, assessment fees, etc.

3.4 Contractor, including its employees, suppliers and subcontractors, shall use only the entrance

designated by Client and Engineer for its use. 3.5 Access by visitors will be restricted. Engineer and Client reserve the right to deny access or to

require execution of a “Complete Waiver of Risk and Release of Liability” Exhibit A, of any visitor, including the Contractor, its officers, employees, subcontractors and agents.

3.6 Contractor shall be responsible for the security of its work areas and shall at all times conduct its

operation in a manner to minimize the risk of loss by theft, damage, vandalism, sabotage, or other conditions. Upon discovery of a loss, Contractor shall notify Engineer and Client and provide a written report of the incident within 24 hours.

3.7 Contractor shall cooperate with Client and Engineer on all security matters. Such compliance shall

not relieve Contractor of its responsibilities as noted above. 3.8 All designs and data furnished by or on behalf of Client or Engineer shall be considered confidential

and shall be used only for performance of this Contract. 3.9 Prior to making any statements to the press or other public releases, Contractor shall first obtain

written approval from Client and Engineer.

68 Teamsters Drive – Abatement & Demolition Summary of Work City of Youngstown 01013 - 3

EXHIBIT A COMPLETE WAIVER OF RISK AND RELEASE OF LIABILITY FOR AND IN CONSIDERATION of receiving permission as a licensee or a business invitee, to enter into and upon project site near , the undersigned HEREBY WAIVES ALL RIGHTS TO FILE ANY CLAIM OR CLAIMS against, and hereby exempts and releases CITY OF YOUNGSTOWN, Youngstown, OH (CLIENT) and ms consultants, inc. (ENGINEER) (hereinafter referred to as "Permitters"), their respective officers, directors, agents and employees from ALL CLAIMS FOR INJURIES, ACCIDENTS, SICKNESS, AND DAMAGES OF WHATSOEVER NATURE SUSTAINED BY THE UNDERSIGNED whether due to negligence (including active and passive negligence) of said permitters, their respective officers, directors, agents, and employees, or otherwise, and the UNDERSIGNED FURTHER AGREES TO PROTECT, INDEMNIFY, AND HOLD HARMLESS said Permitters, their respective officers, directors, agents and employees, from any and all CLAIMS AND COSTS AND EXPENSES in connection therewith resulting from or growing out of any injury or alleged injury, accident, sickness, death or otherwise to the undersigned, no matter when occurring, HEREBY BINDING THE UNDERSIGNED, HIS HEIRS, ADMINISTRATORS AND ASSIGNEES firmly by these presents. WARNING The UNDERSIGNED HEREBY ACKNOWLEDGES THAT HE HAS BEEN INFORMED AND WARNED WITH RESPECT TO DANGERS that entrance upon the job site may entail and that there may be hidden as well as apparent dangers because of the use of large and powerful machines and equipment, high-voltage electrical equipment and lines, high-pressure air equipment and lines, because of any and all other factors. Firm Name Address Signature Title Date Attest by Seal

68 Teamsters Drive – Abatement & Demolition Summary of Work City of Youngstown 01013 - 4

3.10 HEALTH and SAFETY: Contractor acknowledges that the project site may involve hazardous materials. Contractor shall conduct all operations under the Contract in a manner to avoid risk of bodily harm to persons of damage to property and in full compliance with OSHA, NESHAP, MSHA, OAC, CERCLA, NIOSH, RCRA, at a minimum, requirements and any and all other applicable legal requirements. Further, Contractor shall continuously inspect its Work, material and equipment to identify any unsafe conditions and shall promptly take action to correct any condition, which presents such a risk.

Contractor represents and warrants that it is fully qualified and knowledgeable with respect to all health and safety requirements relating to the work and that as an independent Contractor, shall be solely responsible for compliance with those requirements. The Contractor shall provide and follow the Site Health & Safety Plan written by the Contractor. Additional site activities, (i.e., confined space entry, operating heavy equipment, etc.) are to be included in the Contractor's Health & Safety Plan. The Contractor is to present the Health & Safety Plan to the Engineer for acceptance prior to performance of the work. The Contractor will be responsible for ensuring that all Contractor employees and subcontractors on site are properly trained and have medical monitoring. Records supporting training and medical monitoring will be provided to the Client and Engineer prior to signing of the Contract.

Should Contractor fail to comply with the Health & Safety Program or with other applicable requirements as referenced above, such action or inaction shall be considered a material breach of the Contract. Should Contractor, upon notice thereof, neglect or refuse to take appropriate corrective action, Engineer or Client shall have the right, but not the duty, to stop the Contractor's work or any portion thereof, and/or correct the condition and back charge all incident costs to Contractor's account.

Contractor shall be responsible for all fines or penalties assessed due to its failure to comply with applicable laws, regulations or standards, including any fines or penalties assessed against Client or Engineer. Contractor agrees, to the fullest extent permitted by law, to indemnify and hold Client and Engineer harmless from any claim, liability, loss or expense resulting from Contractor's failure to comply with all applicable health and safety requirements.

In the event or accident, injury or incident involving health, safety, or damage to property, Contractor shall immediately notify Client and Engineer and shall submit a report on the incident in writing within 24 hours of such occurrence. Contractor shall maintain accurate records of all such occurrences and shall furnish Client and Engineer a weekly summary including man-hours lost due to injuries.

Nothing in these Special Conditions shall be interpreted as enlarging the legal duty of Client or Engineer to Contractor or to Contractor's agents, employees, subcontractors, or third parties or as altering the independent Contractor status of Contractor.

3.11 Materials, Equipment and Facilities to Be Furnished by Contractor: Contractor shall furnish all labor,

equipment, services and materials necessary to complete the work as a functional system for the use intended. Materials, equipment and supplies to be furnished by Contractor shall include, but shall not necessarily be limited to, the following:

1. All other items of material, supplies, equipment and labor not specifically stated as being

provided by Client and/or Engineer.

68 Teamsters Drive – Abatement & Demolition Summary of Work City of Youngstown 01013 - 5

2. Sanitary facilities for Contractor's personnel will be provided by Contractor. 3. Process and/or Potable water, if required, will be transported by the Contractor to the site from a

remote site location or hydrant as approved by the Youngstown Water Department. NOTE: The buildings have no running water and therefore the Contractor shall be required to contact the Youngstown Water Department to make arrangements to obtain water from a nearby hydrant.

4. Power and telephone services, if required.

5. Transport of workers, as necessary.

3.12 MOBILIZATION/SITE WALKOVER REQUIREMENTS: The Contractor shall provide a

sufficient number of toilet facilities designated as men and women, as appropriate. The toilet facilities shall be located adjacent to the Work Areas. Before initiation of site activities the Contractor shall be accompanied by the Engineer for a general site walkover.

3.13 PROTECTION of ADJACENT BUILDING ROOF TOP and WALLS, ASPHALT

PARKING AREAS and OVERHEAD UTILITY LINES: The Contractor shall provide the Engineer with a Roof Top, Walls, Asphalt Parking Areas and Overhead Utility Lines Protection Plan, describing how the aforementioned items shall be protected from damage during the demolition project and what materials shall be used to protect the items mentioned above.

3.14 STRUCTURAL EVALUATION OF THE POTENTIAL COMMON WALL (SE Wall) of

Room#4: The Contractor shall retain the services of a structural engineer to evaluate the potential common wall shared by Room #4 and the blue cinder block building, NOT PART OF THE DEMOLITION PROJECT. In addition, the structural engineer shall make recommendations to prevent the wall from collapsing should it be determined that the SE wall of Room #4 is a common wall between the two buildings.

3.15 SITE IMPROVEMENTS: Site improvements shall consist of the tasks that must be prepared by the

Contractor prior to initiating the project activities. The site improvements for the project include, but not limited to:

a. Roadway Improvements, as necessary

b. Installation of Temporary Work Area Fencing

c. Installation of Signs d. Permits

e. Portable sanitary facilities

f. Clearing and Grubbing

g. Potable water supply – Youngstown Water Department

3.16 INSTALLATION OF TEMPORARY ASBESTOS ABATEMENT WORK AREA FENCING: The Contractor shall install temporary fencing around the designated Buildings before beginning the asbestos abatement activities to prevent trespassers from entering the work area (s) during non-working hours.

68 Teamsters Drive – Abatement & Demolition Summary of Work City of Youngstown 01013 - 6

The contractor shall install an access gate; large enough to allow the largest piece of equipment to pass through it safely. The gate shall be a double-wide gate. The fencing shall consist of 6 feet high chain link fencing with stakes at the manufacturer’s recommendations or not to exceed 10 feet. The fencing shall be secured using wire ties affixed to 6' metal fence posts at three locations (top, middle, and bottom) at every post. The metal fence post shall be driven into the ground a minimum two (2) feet or placed into stands or equivalent in areas of concrete or asphalt pavement.

3.17 SIGNAGE:

The Contractor shall maintain the following signs at the site:

· The Sanitary Facilities shall have signs designating a “Mens” and “Womens” on the entrance door, as applicable.

· Signs shall be posted at 25-foot intervals with “Warning! No Trespassing!” along the site

temporary work area fencing, using wire ties. · Proper GHS compliant Asbestos signage shall be maintained at all asbestos abatement work areas.

3.18 ASBESTOS ABATEMENT

· Asbestos abatement must be performed in accordance with all applicable local, state, and federal

laws.

· Upon completion of the abatement, three copies of an Asbestos Abatement Report must be completed by the abatement contractor and submitted to the Engineer. The report must be prepared in full compliance with OAC 3745-20 which incorporates the National Emission Standards for Hazardous Air Pollutants (NESHAP) codified under 40 CFR 61.140 – 61.157.

· A waste manifest for each load of asbestos and/or asbestos containing material must be provided

to the Engineer to document the removal and proper disposal of all asbestos containing material from the site.

· Results of all air monitoring performed in compliance with NESHAP requirements during and

upon completion of the asbestos abatement must be provided by the abatement contractor to the Engineer.

· The Contractor shall use a State of Ohio licensed asbestos abatement contractor to remove

the Friable and Category II non-friable asbestos containing materials in accordance with federal, state and local regulations from the designated buildings/Rooms located along Teamsters Drive and Lilac Street, Youngstown, Ohio, a copy of the Asbestos Survey Report(s) are provided at the end of this section for reference.

68 Teamsters Drive – Abatement & Demolition Summary of Work City of Youngstown 01013 - 7

The following is a summary of the asbestos containing building materials identified in the designated buildings, below:

Location of ACBM Material Quantity (lin.ft./sq.ft.) 68 Teamsters Drive Room #1 Exterior of Building MISC – Tile Glue Dots 100 SF First Floor MISC – 12”x 12” Black & White F.T. 2,200 SF (Not Accessible) MISC – Window Glazing – Metal Frame Bay Windows 28 SF (6-Bays) Basement TSI – Black Tar Cloth Wrap 35 LF (known) TSI – Cementitious Elbows and Fittings (PACM) 40 LF NOTE: Due to NO access to Room#1, the first (ground level) flooring has failed and partially collapsed into the basement, lastly, the roofing system has failed, no access to basement, additional quantities of Suspect ACBM may be present. Due to the failure of the first floor which is covered with the 12”x12” Black and White Floor tile, the contractor shall remove the failing exterior brick walls and roofing system associated with Room#1, thus minimizing the amount of building materials containing ACBM to be HOT LOADED as RACM to the materials present in the basement of Room#1. Room #2 Thru-out Space TSI - Black Tar Cloth Wrap 650 LF (known) NOTE: Due to limited access to Room#2, roofing system has failed, additional quantities of Suspect ACBM may be present, which were not able to be accessed during the building survey. Room #3 – NO ACCESS to the Space NOTE: Due to NO access to Room#3, flooring has failed, roofing system has failed, no access to basement, if present, additional quantities of Suspect ACBM may be present in areas which were not able to be accessed during the building survey. Room #4 NO IDENTIFIED Asbestos Containing Building Materials (ACBM) NOTE: Due to limited access to Room#4, flooring has failed, roofing system has failed, the second floor has partially collapsed, no access to basement if present, additional quantities of Suspect ACBM may be present in areas which were not able to be accessed during the building survey. NOTE: Contractor responsible for verifying the quantities.

68 Teamsters Drive – Abatement & Demolition Summary of Work City of Youngstown 01013 - 8

3.19 HAZARDOUS WASTE AND OTHER REGULATED MATERIALS · Hazardous waste and other regulated materials were noted during the building inspections. The

Contractor shall characterize and dispose of the miscellaneous chemicals, paints, solvents, and any unidentified materials remaining within the buildings as part of this contract.

All chemical wastes (e.g., cleaners, paints, solvents, petroleum products, etc.) must be properly removed and disposed of at a properly licensed facility and copies of all waste manifests for these wastes must be provided to the Engineer.

· The Contractor shall remove the mercury containing thermostats and fluorescent bulbs and

ballasts from the identified building(s) and dispose of them in accordance with federal, state, and local regulations.

3.20 POLYCHLORINATED BIPHENYLS BALLASTS / FLUORESCENT BULBS · Polychlorinated biphenyls ballasts and fluorescent bulbs may be encountered in the building

structures. The Contractor shall dispose of the polychlorinated biphenyls ballasts and fluorescent bulbs remaining within the buildings as part of this contract.

· The Contractor shall remove and dispose of the any PCB containing lighting ballasts from the

buildings in accordance with applicable federal, state, and local regulations.

· The Contractor shall remove the fluorescent bulbs from the lighting fixtures intact and dispose of them in accordance with federal, state, and local regulations.

· The Contractor is responsible for verifying the number of lighting ballasts and bulbs.

3.21 BUILDING DEMOLITION

· Once the asbestos abatement/hazardous waste removal activities are completed, the Contractor

shall remove and dispose of the buildings demolition debris in accordance with the federal, state and local regulations. All building foundations and floor slabs, shall be removed to native soils unless otherwise directed by the Engineer. Lastly, due to the condition of building structure at 68 Teamsters Drive (Room#1), the first floor (partially collapsed into the basement and unsafe) of the structure which is covered with 12”x12” Black and White tile and the associated comingled debris will be required to be a “HOT Loadout” as asbestos containing material (RACM). Note: The contractor shall leave the front basement wall and partial sidewalls in place along Teamsters Drive to prevent sidewalk and roadway from collapsing into the building void. In addition, the same shall apply to Room#4, the contractor shall leave the basement wall(s) and sidewalls along Lilac Street, the parking lot area (Mc Royal Industries) and the wall of the immediately adjacent building (blue cinder block building) to the East, SE, of Room#4, which is NOT PART OF THE DEMOLITION PROJECT.

3.22 BACKFILL

· The Contractor shall backfill and/or grade all building voids in accordance with the ODOT Construction and Materials Specifications (CMS 203) (2016) to match the existing grade. The Contractor shall retain the services of an independent testing laboratory to document the backfill compaction requirements for the project, which 98% or the minimum compaction requirements in percent of maximum dry density, as stated in the ODOT CMS 203.

68 Teamsters Drive – Abatement & Demolition Summary of Work City of Youngstown 01013 - 9

3.23 TEMPORARY SEEDING AND MULCHING · The Contractor shall temporarily seed and mulch the areas of disturbance caused by demolition

activities including but not limited to building footprints, driveways, retaining walls, etc.

END OF SECTION

SUPPLEMENTAL ASBESTOS SAMPLING RESULTS 

FOR  

68 TEAMSTERS DRIVE 

YOUNGSTOWN, OHIO 

 

 

 

 

 

 

 

 

 

 

PERFORMED BY: 

ms consultants, inc. 333 E. Federal Street 

Youngstown, Ohio 44503   

 

PHOTO 1: Asbestos Containing Glue Dots on Room #1 exterior. 

 

PHOTO 2: View of the interior of Room #1, roofing system has failed and the flooring system has failed. 

 

PHOTO 3: View of the flooring system, which has failed in Room#1, note the 9‐inch by 9‐inch black and 

white floor tile, which was confirmed to contain asbestos. 

 

PHOTO 4: View of the interior of Room #1, the plaster wall material was determined to be non‐asbestos 

containing. 

 

PHOTO 5: View of the interior of Room #2. 

 

PHOTO 6: View of the remaining half of Room #2, note the black pipe insulation, which was determined 

to be asbestos containing. 

 

PHOTO 7: View of the black pipe insulation, located on piping thru‐out Room #2. 

 

PHOTO 8: View of the black pipe insulation, located on piping thru‐out Room #2. 

 

PHOTO 9: View of Room #3, roofing system has collapsed, therefore no access to Room #3 during the 

asbestos survey. 

 

PHOTO 10: View of the interior of Room #4, limited access due to collapsed flooring systems and roofing 

system. 

 

PHOTO 11: View of the spray‐on foam insulation located on the second floor of the Room #4. The foam 

was determined to be non‐asbestos containing. 

 

PHOTO 12: View of the second floor of Room #4, note, areas of the roofing system, which has failed in 

some areas. 

 

PHOTO 13: View of the failed stairs to the second floor of Room #4, note failed roofing system. 

 

PHOTO 14: View of the failed stairs to the second floor, roofing system has failed. 

 

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\09 - 01028S96 - Applications For Payment.doc 01028 - 1

SECTION 01028

APPLICATIONS FOR PAYMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements governing the Contractor's

Applications for Payment.

1. Coordinate the Schedule of Values and Application for Payment with the Contractor’s Construction Schedule, Submittal Schedule, and List of Subcontracts.

B. Related Sections - The following Sections contain requirements that relate to this Section.

1. Contractor’s Construction Schedule: The Contractor's Construction Schedule is

specified in Division 1 Section "Coordination."

2. Submittal Schedule: The Submittal Schedule is specified in Division 1 Section "Submittals."

1.3 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of the

Contractor's Construction Schedule.

1. Correlate line items in the Schedule of Values with other required administrative schedules and forms, including: a. Contractor's Construction Schedule. b. Application for Payment forms, including Continuation Sheets. c. List of subcontractors. d. Schedule of allowances. e. Schedule of alternates. f. List of products. g. List of principal suppliers and fabricators. h. Schedule of submittals.

2. Submit the Schedule of Values to the Owner /Engineer at the earliest possible date but no

later than 7 days before the date scheduled for submittal of the initial Applications for Payment.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\09 - 01028S96 - Applications For Payment.doc 01028 - 2

3. Subschedules: Where Work is separated into phases requiring separately phased

payments, provide subschedules showing values correlated with each phase of payment.

B. Format and Content: Submit a Schedule of Values that is based on functional, measurable, observable portions of the Work. Where appropriate breakdown the Work into phases, building areas or floors.

1. Identification: Include the following Project identification on the Schedule of Values:

a. Project name and location. b. Name of the Owner/Engineer. c. Project number. d. Contractor's name and address. e. Date of submittal.

2. Breakdown Contract Sum into each of the following items:

a. Mobilization b. Preparation of Work Area c. Asbestos Abatement d. Project Decontamination e. Project Closeout

3. Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed: a. Related Specification Sections or Divisions b. Description of Work. c. Name of subcontractor. d. Name of manufacturer or fabricator. e. Name of supplier. f. Change Orders (numbers) that affect value. g. Dollar value.

1) Percentage of Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.

4. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued

evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Where appropriate, break principal subcontract amounts down into several line items.

5. Round amounts to nearest whole dollar; the total shall equal the Contract Sum.

1.4 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as

certified by the Engineer and paid for by the Owner.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\09 - 01028S96 - Applications For Payment.doc 01028 - 3

1. The initial Application for Payment, the Application for Payment at time of Substantial

Completion, and the final Application for Payment involve additional requirements. B. Payment-Application Times: The date for each progress payment is the 15th day of each month.

The period covered by each Application for Payment starts on the day following the end of the preceding period and ends 15 days prior to the date for each progress payment.

C. Payment-Application Forms: Application for payment as provided by the Engineer. D. Application Preparation: Complete every entry on the form. Include notarization and

execution by a person authorized to sign legal documents on behalf of the Contractor. The Owner/Engineer will return incomplete applications without action.

1. Entries shall match data on the Schedule of Values and the Contractor's Construction

Schedule. Use updated schedules if revisions were made. 2. Include amounts of Change Orders and Construction Change Directives issued prior to the

last day of the construction period covered by the application. E. Transmittal: Submit 5 signed and notarized original copies of each Application for Payment to

the Engineer by a method ensuring receipt within 24 hours. One copy shall be complete, including waivers of lien and similar attachments, when required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate

information related to the application, in a manner acceptable to the Engineer.

F. Waiver Delays: Submit each Application for Payment with the Contractor's waiver of mechanics lien for the period of construction covered by the application.

1. Submit final Applications for Payment with or preceded by final waivers from every entity

involved with performance of the Work covered by the application who is lawfully entitled to a lien.

G. Waiver Forms: Submit waivers of lien on forms, and executed in a manner, acceptable to the Owner.

H. Initial Application for Payment: Administrative actions and submittals, that must precede or

coincide with submittal of the first Application for Payment, include the following: 1. Submittals designated as required Before Start of Work by individual specification

sections. 2. List of subcontractors. 3. Schedule of Values. 4. Contractor's Construction Schedule (preliminary if not final). 5. Schedule of principal products. 6. Schedule of unit prices. 7. Submittal Schedule (preliminary if not final). 8. List of Contractor's staff assignments.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\09 - 01028S96 - Applications For Payment.doc 01028 - 4

9. Contractor’s personnel licenses, fit testing records, and medical monitoring records 10. List of Contractor's principal consultants. 11. Copies of building permits. 12. Copies of authorizations and licenses from governing authorities for performance of the

Work. 13. Initial progress report. 14. Report of preconstruction meeting. 15. Certificates of insurance and insurance policies. 16. Performance and payment bonds. 17. Initial settlement survey and damage report, if required.

B. Application for Payment at Substantial Completion: Following issuance of the Certificate of

Substantial Completion, submit an Application for Payment.

1. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

2. Administrative actions and submittals that shall precede or coincide with this application

include: 1. Final Air Clearance Reports 2. Hazardous waste disposal manifests 3. Asbestos Disposal receipts. 4. Final cleaning Inspection forms.

C. Final Payment Application: Administrative actions and submittals that must precede or

coincide with submittal of the final Application for Payment include the following: 1. Completion of Project closeout requirements. 2. Completion of items specified for completion after Substantial Completion. 3. Transmittal of required Project construction records to the Owner. 4. Proof that taxes, fees, and similar obligations were paid. 5. Removal of temporary facilities and services. 6. Removal of surplus materials, rubbish, and similar elements. 7. Disposal receipts, bills of lading and other required documentation of transportation and

disposal of asbestos-containing waste and hazardous/non-hazardous waste. PART 2 - PRODUCTS (Not Applicable). PART 3 - EXECUTION (Not Applicable). END OF SECTION 01028

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\09 - 01028S96 - Applications For Payment.doc 01028 - 5

SCHEDULE OF VALUES: Project: _______________________ Date: _____________________ _______________________

_______________________ Contractor: ______________________ Owner's: ____________________ ______________________ Rep. ____________________ Description Related Work Sections Amount Preparation for Work 01013 Summary of Work: (Development of Project Workplan, Health and Safety Plan, Construction Contingency Plan, Storm water Pollution Prevention Plan, signage, restrooms, etc.) Preparation of Work Area 01503 Temporary Facilities - Asbestos Abatement

01513 Temporary Pressure Differential & Air Circulation System

01526 Temporary Enclosures 01563 Decontamination Units

Asbestos Abatement 01013(3.17) Asbestos Abatement Summary 02081 Removal of Asbestos-Containing Materials

02084 Disposal of Regulated Asbestos-Containing Material

Project Decontamination 01711 Project Decontamination 01712 Cleaning & Decontamination Procedures

Hazardous Waste 01013 Summary of Work (Sections 3.18 & 3.19) 02086 Hazardous Waste Management Building Demolition 02050 Building Demolition Project Closeout 01701 Project Closeout

Total

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\10 - 01043S96 - Coordination - bkf.doc 01043 - 1

SECTION 01043

COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and supervisory requirements necessary for coordinating construction operations including, but not necessarily limited to, the following: 1. General project coordination procedures. 2. Conservation. 3. Plan of Action. 4. Contingency Plan. 5. Project Directory. 6. Notifications. 7. Pre-Construction Inspection. 8. Contractors Construction Schedule. 9. Administrative and supervisory personnel. 10. Pre-Construction Conference 11. Progress Meetings 12. Coordination meetings. 13. Record Keeping. 14. Special Reports.

B. Related Sections: The following Sections contain requirements that relate to this Section:

1. Section 01301 - Submittals - Asbestos Abatement for administrative procedures regarding

submittals. 2. Section 01601 - Materials and Equipment - Asbestos Abatement for coordinating general

installation. 1.3 COORDINATION

A. Owner Occupancy: All designated building(s) for demolition are VACANT. Coordinate demolition operations and scheduling with requirements of the Engineer and the Owners of utilities.

B. Coordinate construction operations included in various Sections of these Specifications to

assure efficient and orderly completion of each part of the Work. Coordinate construction operations included under different Sections that depend on each other for proper installation, connection, and operation.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\10 - 01043S96 - Coordination - bkf.doc 01043 - 2

1. Schedule construction operations in the sequence required to obtain the best results where execution of one part of the Work depends on execution of other components, before or after its own execution.

C. Where necessary, prepare memoranda for distribution to each party involved, outlining special

procedures required for coordination. Include such items as required notices, reports, and attendance at meetings. 1. Prepare similar memoranda for the Engineer and separate contractors where coordination

of their work is required.

D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and assure orderly progress of the Work. Such administrative activities include, but are not limited to, the following: 1. Preparation of schedules. 2. Installation and removal of temporary facilities. 3. Delivery and processing of submittals. 4. Progress meetings. 5. Project closeout activities.

1.4 CONTINGENCY PLAN:

A. Contingency Plan: Prepare a contingency plan for emergencies or any other event that may require breaching of work area containment or modification or abridgement of decontamination or work area isolation procedures. Include in this plan procedures for performing electrical and mechanical repairs inside containment after abatement work has begun. Include in plan specific procedures for decontamination or work area isolation. Note that nothing in this specification should impede safe exiting or providing of adequate medical attention in the event of an emergency. Items to be addressed in the plan include, but are not limited to the following: 1. Fire 2. Accident 3. Life threatening injury 4. Non life threatening injury 5. Rescue 6. Power Failure 7. Pressure differential system failure 8. Breach of containment 9. Electrical faults or shock 10. Excessive heat / cold (if/when such limits are specified) 11. Supplied air system failure 12. Water leaks 13. Waste spills 14. Unauthorized entry into work area 15. Elevated air samples outside of containment 16. Repairs inside containment 17. Toxic releases

1.5 PROJECT DIRECTORY

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\10 - 01043S96 - Coordination - bkf.doc 01043 - 3

A. Develop a directory of all entities involved in the project. Include the Contractor's principal staff

assignments, including the Superintendent and other personnel in attendance at the site. Identify individuals, their duties and responsibilities. List business name, contact person, normal business and emergency telephone, pager and fax numbers and addresses of: 1. Owner, Designer, and Project Administrator 2. Contractors General Superintendent, supervisory personnel and Contractors home office 3. Emergency services including but not limited to fire, ambulance, doctor, hospital, police,

power company, telephone company. 4. Local, state, and federal agencies with jurisdiction over the project.

B. Post: Post copies of the Project Directory in the project meeting room, the temporary field office,

each temporary telephone, and at entrance to clean room of Personnel Decontamination Unit 1.6 NOTIFICATIONS

A. Notify other entities at the job site of the nature of the asbestos abatement activities, location of asbestos-containing materials (ACM), requirements relative to asbestos set forth in these specifications and applicable regulations. Advance notification will be made to: 1. Employees who will perform asbestos abatement work or related activities, or who will be

in the work area during the course of the work of this contract. 2. Employers of employees who work and/or will be working in adjacent areas during the

course of the work of this contract.

B. Notify emergency service agencies including fire, ambulance, police or other agency that may service the abatement work site in case of an emergency. Notification is to include methods of entering work area, emergency entry and exit locations, modifications to fire notification or fire fighting equipment, and other information needed by agencies providing emergency services.

C. Notifications of Emergency: Any individual at the job site may notify emergency service

agencies if necessary without effect on this Contract or the Contract Sum. 1.7 PRE-CONSTRUCTION INSPECTION: (NOT USED)

A. Inspect areas in which work will be performed, prior to commencement of work. Prepare a listing of damage to structure, surfaces, equipment or of surrounding properties which could be misconstrued as damage resulting from the work. Photograph or videotape existing conditions as necessary to document conditions. Submit to Project Representative for record purposes prior to starting work.

1.8 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Bar-Chart Schedule: Prepare a fully developed, horizontal bar-chart-type, contractor's construction schedule. Submit within 30 days after the date established for "Commencement of the Work."

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\10 - 01043S96 - Coordination - bkf.doc 01043 - 4

1. Provide a separate time bar for each significant construction activity. Provide a continuous vertical line to identify the first working day of each week. Use the same breakdown of units of the Work as indicated in the "Schedule of Values."

2. Within each time bar, indicate estimated completion percentage in 10 percent increments. As Work progresses, place a contrasting mark in each bar to indicate Actual Completion.

3. Prepare the schedule on a sheet, or series of sheets, of stable transparency, or other reproducible media, of sufficient width to show data for the entire construction period.

4. Secure time commitments for performing critical elements of the Work from parties involved. Coordinate each element on the schedule with other construction activities; include minor elements involved in the sequence of the Work. Show each activity in proper sequence. Indicate graphically the sequences necessary for completion of related portions of the Work.

5. Coordinate the Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittal Schedule, progress reports, payment requests, and other schedules.

6. Indicate Clearance of each Work Area in advance of the dates established for Clearance. 7. Indicate completion in advance of the date established for Substantial Completion.

Indicate Substantial Completion on the schedule to allow time for the Project Representative procedures necessary for certification of Substantial Completion.

B. Work Stages: Indicate important stages of construction for each major portion of the Work,

including submittal review, testing, and installation. 1. Non-asbestos demolitions. 2. Preparation of the Work Area. 3. Asbestos removal. 4. Clearance testing. 5. Substantial Completion.

C. Area Separations: Provide a separate time bar to identify each major construction area for each

major portion of the Work. Indicate where each element in an area must be sequenced or integrated with other activities.

1.9 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. Project Supervisor: Provide a full-time Project Supervisor at the work site who is experienced in

administration and supervision of asbestos abatement projects including work practices, protective measures for building and personnel, disposal procedures, project scheduling, management, etc. This person is the Contractor`s Representative, and will function as the competent person at the work site responsible for compliance with all applicable federal, state and local regulations, particularly those relating to ACM. 1. Training: The General Superintendent must have a current certification from a state

approved trainer for a course that meets the requirements of the EPA Model Accreditation Plan for asbestos abatement contractor/supervisor (40 CFR part 763, Subpart E, Appendix C).

2. Experience: The General Superintendent must have demonstrable experience in the

successful management of asbestos abatement projects that are similar to the work of this contract.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\10 - 01043S96 - Coordination - bkf.doc 01043 - 5

a. The General Superintendent must have had responsible charge of a minimum of ten

(10) asbestos abatement projects in Mahoning County similar in size and type to the work of this contract.

3. Competent Person: The General Superintendent is to be a Competent Person as required

by OSHA in 29 CFR 1926. B. Supervisors / Forepersons: Provide full-time Supervisors / Forepersons who are experienced in the

supervision of asbestos abatement work areas including work practices, building and personnel, disposal practices, etc. These persons are contractor employees directly responsible to the General Superintendent.

C. Accreditation: The General Superintendent, Supervisors and Forepersons are to be accredited as

an Asbestos Abatement Supervisor in accordance with the AHERA regulation 40 CFR Part 763, Subpart E, Appendix C.

1.10 PRE-CONSTRUCTION CONFERENCE:

A. An initial progress meeting, recognized as "Pre-Construction Conference" will be convened by

the Project Representative (Engineer) prior to start of any work. The preconstruction conference will be scheduled before start of construction, at a time convenient to the Owner and the Project Representative, but no later than 15 days after execution of the Agreement. Meet at the project site, or as otherwise directed, with General Superintendent, Owner, Designer, Project Administrator, and other entities concerned with the asbestos abatement work.

B. Attendees: Authorized representatives of the Owner, Designer, and their consultants will be in

attendance. An authorized representative of the Contractor and its superintendent; major subcontractors; manufacturers; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work. 1. 72 hours advance notice will be provided to all participants prior to convening Pre-

Construction Conference.

C. Agenda: This is an organizational meeting, to review responsibilities and personnel assignments, to locate regulated areas and temporary facilities including power, light, water, etc. Items of significance that could affect progress will be discussed, including the following: 1. Tentative construction schedule. 2. Critical work sequencing. 3. Designation of responsible personnel. 4. Procedures for processing field decisions and Change Orders. 5. Procedures for processing Applications for Payment. 6. Distribution of Contract Documents. 7. Preparation of record documents. 8. Use of the premises. 9. Parking availability. 10. Office, work, and storage areas.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\10 - 01043S96 - Coordination - bkf.doc 01043 - 6

11. Equipment deliveries and priorities. 12. Safety procedures. 13. First aid. 14. Security. 15. Housekeeping. 16. Working hours.

1.11 PROGRESS MEETINGS:

A. General: In addition to specific coordination and pre-installation meetings for each element of

work, and other regular project meetings held for other purposes, the Engineer/Owner’s Representative will hold general progress meetings as required. These meeting will be scheduled, where possible, at time of preparation of payment request.

B. Attendees: Representatives of the Owner and Project Monitor will attend these meetings. In

addition to representatives of the Contractor, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the work. Require each entity then involved in planning, coordination or performance of work to be properly represented at each meeting.

C. Agenda: Be prepared to discuss the following items at the progress meetings. Review other items

of significance that could affect progress. 1. Contractor's Construction Schedule: Review progress since the last meeting. Determine

where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to insure that current and subsequent activities will be completed within the Contract Time.

2. Review the present and future needs of each entity present, including the following:

a. Interface requirements. b. Time. c. Sequences. d. Status of submittals. e. Deliveries. f. Access. g. Site utilization. h. Temporary facilities and services. i. Hours of work. j. Hazards and risks. k. Housekeeping. l. Quality and work standards. m. Change Orders. n. Documentation of information for payment requests.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\10 - 01043S96 - Coordination - bkf.doc 01043 - 7

D. Reporting: Revise the Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue the revised schedule no later than 3 days after each meeting. Include a brief summary, in narrative form, of progress since the previous meeting and report.

1.12 COORDINATION MEETINGS

A. Attend project coordination meetings that will be conducted by the Engineer/Owner’s

Representative at regular intervals convenient for all parties involved. Project coordination meetings are intended to coordinate the work of all contractors performing work on the site, and are in addition to specific meetings held for other purposes, such as regular progress meetings.

1.13 RECORD KEEPING:

A. Daily Log: Maintain a Daily Log (in an area accessible to the Owner, Project Monitor and

Project Administrator) as a bound, sequential, hand-written record carefully prepared daily that documents but is not limited to the following items: 1. Meetings; purpose, attendees, brief discussion 2. Special or unusual events, i.e. barrier breeching, equipment failures, accidents 3. Documentation of Contractor's completion of the following: a. Inspection of work area preparation prior to start of removal and daily thereafter.

b. Removal of any sheet plastic barriers c. Contractor's inspections prior to spray back, lock back, encapsulation, enclosure or

any other operation that will conceal the condition of ACM or the substrate from which such materials have been removed.

d. Removal of waste materials from work area e. Decontamination of equipment (list items) f. Contractors final inspection/final air test analysis.

B. Entry/Exit Log: Maintain within the Decontamination Unit a daily log documenting the dates

and time of but not limited to, the following items: 1. Visitations; authorized and unauthorized with the following information

a. Name b. Organization c. Entry time d. Exit Time e. Respiratory protection

2. Personnel, by name, entering and leaving the work area with the following information

a. Printed Name b. Identification Number c. Entry Time d. Exit Time e. Respiratory Protection

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\10 - 01043S96 - Coordination - bkf.doc 01043 - 8

C. Air Monitoring Results: Post personnel and area air monitoring results in Decontamination Unit within 24 hours of sample collection. Post the respiratory protection requirements for the work in progress.

D. Records in Decontamination Unit: Maintain the following documentation in the

Decontamination Unit, in a location accessible to workers. 1. Documentation of inspections by OSHA, EPA or local authority 2. Respiratory Protection Program.

E. Other records: Maintain other documentation in a location that is accessible to the Owner,

Engineer/Owner’s Representative, and Project Administrator including: 1. Waste Manifests and shipping records 2. Landfill receipts. 3. Accident reports.

1.14 SPECIAL REPORTS:

A. General: Except as otherwise indicated, submit special reports directly to Owner within one day

of occurrence requiring special report, with copy to Engineer/Owner’s Representative and others affected by occurrence.

B. Reporting Unusual Events: When an event of unusual and significant nature occurs at site

(examples: failure of pressure differential system, rupture of temporary enclosures), prepare and submit report. List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. When such events are known or predictable in advance, advise Owner in advance at earliest possible date.

C. Reporting Accidents: Prepare and submit reports of significant accidents, at site and anywhere

else work is in progress. Record and document data and actions; comply with industry standards. For this purpose, a significant accident is defined to include events where personal injury is sustained, property loss of substance is sustained, or where the event posed a significant threat of loss or personal injury, or where work was stopped for over four hours during a scheduled shift.

D. Report Discovered Conditions: When an unusual condition of the building is discovered during

the work (e.g. leaks, termites, corrosion) prepare and submit a special report indication condition discovered.

1.45 SUBMITTALS

A. Before the Start of Work: Submit the following to the Engineer/Owner’s Representative in the

same manner as product data. Do not begin work until these submittals are returned with an action stamp indicating that all submittals have been received-not reviewed.

1. Plan of Action. 2. Contingency Plans. 3. Project Directory. 4. Notifications: copy of notification sent to other entities at the work site, and to emergency

service agencies. 5. Pre-Construction Inspection: Report on inspection carried out as required by this section.

Include copies of all photographs, video tapes, etc.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\10 - 01043S96 - Coordination - bkf.doc 01043 - 9

6. Contractors Construction Schedule. 7. Accreditation: Submit evidence in the form of training course certificates for the General

Superintendent, Supervisors, and Forepersons as asbestos abatement supervisors in accordance with AHERA requirements. Submit evidence in the form of training course certificates that each worker is trained as an asbestos abatement worker in accordance with AHERA requirements.

8. Resume: Submit resume of General Superintendent

B. Submit daily: Provide two (2) copies for information purposes of all documents indicated in the following sub-sections to Engineer/Owner’s Representative by end of the next working day after the day they are received by Contractor. 1. Section on Record Keeping. 2. Section on Special Reports.

C. Project Close-out: Submit two (2) copies for information purposes of all documents indicated in

the following sections at final closeout of project as a project close-out submittal. 1. Section on Record Keeping. 2. Section on Special Reports.

PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 1

SECTION 01097

REFERENCE STANDARDS AND DEFINITIONS - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 1 Specification Sections, apply to this Section. 1.2 DEFINITIONS

A. General: Basic contract definitions are included in the Conditions of the Contract.

1. "Indicated": The term "indicated" refers to graphic representations, notes, or schedules on

the Drawings, or other paragraphs or Schedules in the Specifications, and similar requirements in the Contract Documents. Terms such as "shown," "noted," "scheduled," and "specified" are used to help the reader locate the reference. Location is not limited.

2. "Directed": Terms such as "directed," "requested," "authorized," "selected," "approved,"

"required," and "permitted" mean directed by the Designer, requested by the Designer, and similar phrases.

3. "Approved": The term "approved," when used in conjunction with the Designer's action on

the Contractor's submittals, applications, and requests, is limited to the Designer's duties and responsibilities as stated in the Conditions of the Contract.

4. "Regulations": The term "regulations" includes laws, ordinances, statutes, and lawful

orders issued by authorities having jurisdiction, as well as rules, conventions, and agreements within the construction industry that control performance of the Work.

5. "Furnish": The term "furnish" means supply and deliver to the Project Site, ready for

unloading, unpacking, assembly, installation, and similar operations.

6. "Install": The term "install" describes operations at the Project Site including the actual unloading, unpacking, assembly, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.

7. "Provide": The term "provide" means to furnish and install, complete and ready for the

intended use. 8. "Installer": An installer is the Contractor or another entity engaged by the Contractor,

either as an employee, subcontractor, or contractor of lower tier, to perform a particular construction activity, including installation, erection, application, or similar operations. Installers are required to be experienced in the operations they are engaged to perform. a. The term "experienced," when used with the term "installer," means having a

minimum of 10 previous projects similar in size and scope to this Project, being

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 2

familiar with the special requirements indicated, and having complied with requirements of authorities having jurisdiction.

b. Trades: Using terms such as "carpentry" does not imply that certain construction

activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to trades persons of the corresponding generic name.

9. "Project Site" is the space available to the Contractor for performing construction activities,

either exclusively or in conjunction, with others performing other work as part of the Project. The extent of the Project Site is shown on the Drawings and may or may not be identical with the description of the land on which the Project is to be built.

10. "Testing Agencies": A testing agency is an independent entity engaged to perform specific

inspections or tests, either at the Project Site or elsewhere, and to report on and, if required, to interpret results of those inspections or tests.

11. "Designer": This is the entity described as the "Architect" in AIA Document A201

"General Conditions of the Contract for Construction," or is the entity described as "Engineer" in Engineers Joint Contract Document Committee (EJCDC) Document 1910-8 "Standard General Conditions of the Construction Contract." All references to Architect or Engineer in the Contract Documents in all cases refer to the Project Manager. The Engineer will represent the Owner during construction and until final payment is due. The Designer will advise and consult with the Owner. The Owner's instructions to the Contractor will be forwarded through the Engineer/Owner’s Representative.

12. "Construction Administrator": This is the entity described as the "Project Representative"

in AIA Document A201 "General Conditions of the Contract for Construction," or is the entity described as "Engineer" in Engineers Joint Contract Document Committee (EJCDC) Document 1910-8 "Standard General Conditions of the Construction Contract." The Engineer/Owner’s Representative is a full time representative of the Owner at the job site with authority to stop the work upon written or verbal order if requirements of the Contract Documents are not met, or if in the sole judgement of the Engineer, Designer, or Owner, the interests of the Owner, safety of any person or the Owner's property are jeopardized by the work.

13. Stop Work Order: is a written order to cease asbestos removal, encapsulation or

enclosure activities. The Contractor must maintain work area enclosure, pressure differential isolation and ventilation of the work area, and decontamination units during the period that a Stop Work Order is in affect.

14. "General Superintendent": This is the Contractor's Representative at the work site. This

person must be a Competent Person as defined by OSHA in 29 CFR 1926.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 3

B. Definitions Relative to Asbestos Abatement: 1. “Adequately Wet”: means to sufficiently mix or penetrate with liquid to prevent the release

of particulates. If visible emissions are observed coming from the asbestos-containing material (ACM), then that material has not been adequately wetted. However, the absence of visible emissions is not sufficient evidence of being adequately wetted.

2. "Asbestos": The asbestiform varieties of chrysotile (serpentine), amosite (cummingtonite-

grunerite), crocidolite (riebeckite), tremolite, anthophyllite, actinolite, and any of these minerals that has been chemically treated and/or altered. For purposes of the contract documents materials described in the contract documents as asbestos are to be considered as asbestos.

3. "Asbestos-Containing Material (ACM)": Any material containing more than 1% asbestos

as determined using the methods specified in appendix A, subpart F, 40 CFR part 763, section 1, Polarized Light Microscopy.

4. "Asbestos-Containing Waste Material": any waste that contains asbestos. This term

includes filters or other materials contaminated with asbestos. This term also includes regulated asbestos-containing material waste and materials contaminated with asbestos including disposable equipment and clothing.

5. "Asbestos debris": pieces of ACM that can be identified by color, texture, or composition,

or dust, if the dust is determined by an accredited inspector to be ACM.

6. "Certified Industrial Hygienist (C.I.H.)": one certified in the practice of industrial hygiene by the American Board of Industrial Hygiene.

7. "Competent person": an individual who meets the requirements of OSHA as a competent

person for the specific activity involved in the work. The competent person must meet the requirements of 29 CFR 1926.32(f), and 29 CFR 1926.1101.

8. "Filter": A media component used to remove solid or liquid particles from air and water.

9. "Friable Asbestos": any asbestos-containing material that when dry, can be crumbled,

pulverized, or reduced to powder by hand pressure.

10. "Grinding": to reduce to powder or small fragments and includes manual or mechanical chipping or drilling.

11. "HEPA Filter": A High Efficiency Particulate Air (HEPA) filter capable of trapping and

retaining 99.97% of all mono-dispersed particles of 0.3 microns in diameter.

12. "HEPA Filter Vacuum Collection Equipment (or vacuum cleaner)": High efficiency particulate air filtered vacuum collection equipment with a HEPA filter.

13. "Intact" : that the ACM has not crumbled, been pulverized, or otherwise deteriorated so

that the asbestos is no longer likely to be bound with its matrix.

14. "Leak-tight": that solids or liquids cannot escape or spill out. It also means dust-tight.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 4

15. "Negative Pressure Enclosure (NPE) ": A pressure differential and ventilation system

where the work area is maintained at a negative pressure relative to air pressure outside the work area.

16. "Nonfriable Material": any material that, when dry, cannot be crumbled, pulverized, or

reduced to powder by hand pressure and has not been rendered friable.

17. "Personal Monitoring": Sampling of the asbestos fiber concentrations within the breathing zone of an employee.

18. "Surfacing material": material that is sprayed, troweled-on or otherwise applied to surfaces

(such as acoustical plaster on ceilings and fireproofing materials on structural members, or other materials on surfaces for acoustical, fireproofing, and other purposes).

19. "Thermal system insulation (TSI)": insulation applied to pipes, fittings, boilers, breeching,

tanks, ducts or other components to prevent heat loss or gain.

20. "Time Weighted Average (TWA)": The average concentration of a contaminant in air during a specific time period as determined by the method prescribed in Appendix A of 29 CFR part 1926.1101.

21. "Visible Emissions": Any emissions containing particulate material that are visually

detectable without the aid of instruments. This does not include condensed uncombined water vapor.

22. "Working Day": Monday through Friday and includes holidays that fall on any of the days

Monday through Friday as indicated in the notification requirements. 1.3 SPECIFICATION FORMAT AND CONTENT EXPLANATION

A. Specification Format: These Specifications are organized into Divisions and Sections based on

CSRF's 16-Division format and MasterFormat's numbering system. B. Specification Content: This Specification uses certain conventions regarding the style of

language and the intended meaning of certain terms, words, and phrases when used in particular situations or circumstances. These conventions are explained as follows: 1. Abbreviated Language: Language used in Specifications and other Contract Documents

is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be interpolated as the sense requires. Singular words will be interpreted as plural and plural words interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Streamlined Language: The Specifications generally use the imperative mood and

streamlined language. Requirements expressed in the imperative mood are to be performed by the Contractor. At certain locations in the Text, subjective language is used for clarity to describe responsibilities that must be fulfilled indirectly by the Contractor or by others when so noted.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 5

1.4 INDUSTRY STANDARDS

A. Applicability of Standards: Except where the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

B. Publication Dates: Comply with the standards in effect as of the date of the Contract

Documents. C. Conflicting Requirements: Where compliance with 2 or more standards is specified and the

standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer to the Designer before proceeding for a decision on requirements that are different but apparently equal, and where it is uncertain which requirement is the most stringent. 1. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified

shall be the minimum acceptable. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of the requirements. Refer uncertainties to the Designer for a decision before proceeding.

D. Copies of Standards: Each entity engaged in construction on the Project is required to be

familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents. 1. Where copies of standards are needed to perform a required construction activity, the

Contractor shall obtain copies directly from the publication source.

E. Standards: which apply to asbestos abatement work or hauling and disposal of asbestos waste materials include but are not limited to the following: 1. American National Standards Institute (ANSI)

1430 Broadway New York, New York 10018 (212)354-3300

a. Fundamentals Governing the Design and Operation of Local Exhaust Systems

Publication Z9.2 b. Practices for Respiratory Protection Publication Z88.2

2. American Society for Testing and Materials (ASTM)

100 Bar Harbor Drive West Conshocken, PA 19428-2959 (610) 832-9585 a. Safety and Health Requirements Relating to Occupational Exposure to Asbestos

E 849 b. ASTM Standard Practice for Encapsulants for Spray-or-Trowel-Applied Friable

Asbestos-Containing Building Materials E1494

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 6

c. ASTM Standard Practice for Visual Inspection of Asbestos Abatement Projects

E1368

F. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. The following acronyms or abbreviations, as referenced in the Contract Documents, are defined to mean the associated names. Names and addresses are subject to change and are believed, but are not assured, to be accurate and up-to-date as of the date of the Contract Documents. 1. ACI American Concrete Institute

P.O. Box 19150 Detroit, MI 48219 (313) 532-2600

2. ACIL American Council of Independent Laboratories

1629 K St., NW Washington, DC 20006 (202) 887-5872

3. ACPA American Concrete Pipe Assoc.

8300 Boone Blvd., Suite 400 Vienna, VA 22182 (703) 821-1990

4. ACGIH American Conference of Governmental Industrial Hygienists

1330 Kemper Meadow Dr. Cincinnati, OH 45240 (513) 742-2020

5. AIA The American Institute of Architects

1735 New York Ave., NW Washington, DC 20006 (202) 626-7300

6. AIHA American Industrial Hygiene Assoc.

2700 Prosperity Ave., Suite 250 Fairfax, VA 22031 (703) 849-8888

7. ANSI American National Standards Institute

11 West 42nd St., 13th Floor New York, NY 10036 (212) 642-4900

8. ASHRAE American Society of Heating,

Refrigerating and Air-Conditioning Engineers 1791 Tullie Circle, NE Atlanta, GA 30329 (404) 636-8400

9. ASME American Society of Mechanical Engineers

345 East 47th St. New York, NY 10017 (212) 705-7722

10. ASPE American Society of Plumbing Engineers

3617 Thousand Oaks Blvd., Suite 210 Westlake, CA 91362 (805) 495-7120

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 7

11. ASTM American Society for Testing and Materials

100 Barr Harbor Drive West Conshohocken, PA 19428-2959 (610) 832-9585

12. CGA Compressed Gas Assoc.

1725 Jefferson Davis Highway, Suite 1004 Arlington, VA 22202-4100 (703) 412-0900

13. FM Factory Mutual Systems

1151 Boston-Providence Turnpike P.O. Box 9102 Norwood, MA 02062 (617) 762-4300

14. GA Gypsum Association

810 First St., NE, Suite 510 Washington, DC 20002 (202) 289-5440

15. IEEE Institute of Electrical and Electronic Engineers

345 E. 47th St. New York, NY 10017 (212) 705-7900

16. IETA International Electrical Testing Assoc.

P.O. Box 687 Morrison, CO 80465 (303) 697-8441

17. IRI Industrial Risk Insurers

P.O. Box 5010 85 Woodland St. Hartford, CT 06102-5010 (203) 520-7300

18. ISA Instrument Society of America

P.O. Box 12277 67 Alexander Dr. Research Triangle Park, NC 27709 (919) 549-8411

19. ISO International Standards Organization 20. NEC National Electrical Code (from NFPA)

21. NECA National Electrical Contractors Assoc.

3 Bethesda Metro Center, Suite 1100 Bethesda, MD 20814 (301) 657-3110

22. NEMA National Electrical Manufacturers Assoc.

2101 L St., NW, Suite 300 Washington, DC 20037 (202) 457-8400

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 8

23. NFPA National Fire Protection Assoc. One Batterymarch Park P.O. Box 9101 Quincy, MA 02269-9101 (617) 770-3000 (800) 344-3555

24. NRCA National Roofing Contractors Assoc.

10255 W. Higgins Rd., Suite 600 Rosemont, IL 60018-5607 (708) 299-9070

25. RFCI Resilient Floor Covering Institute

966 Hungerford Dr., Suite 12-B Rockville, MD 20805 (301) 340-8580

26. UL Underwriters Laboratories

333 Pfingsten Rd. Northbrook, IL 60062 (708) 272-8800

27. White Lung Association

PO Box 1483 Baltimore, MD 21203

G. Federal Government Agencies: Names and titles of federal government standard- or Specification-producing agencies are often abbreviated. The following acronyms or abbreviations referenced in the Contract Documents indicate names of standard- or Specification-producing agencies of the federal government. Names and addresses are subject to change and are believed, but are not assured, to be accurate and up-to-date as of the date of the Contract Documents. 28. CE Corps of Engineers

(U.S. Department of the Army) Chief of Engineers - Referral Washington, DC 20314 (202) 272-0660

29. CFR Code of Federal Regulations

(Available from the Government Printing Office) N. Capitol St. between G and H St., NW Washington, DC 20402 (202) 783-3238 (Material is usually first published in the "Federal Register")

30. CPSC Consumer Product Safety Commission

5401 Westbard Ave. Bethesda, MD 20207 (800) 638-2772

31. CS Commercial Standard

(U.S. Department of Commerce) Government Printing Office Washington, DC 20402 (202) 783-3238

32. DOC Department of Commerce

14th St. and Constitution Ave., NW Washington, DC 20230 (202) 482-2000

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 9

33. DOT Department of Transportation 400 Seventh St., SW Washington, DC 20590 (202) 366-4000

34. EPA Environmental Protection Agency

401 M St., SW Washington, DC 20460 (202) 260-2090

35. FS Federal Specification (from GSA)

Specifications Unit (WFSIS) 7th and D St., SW Washington, DC 20407 (202) 708-9205

36. GSA General Services Administration

F St. and 18th St., NW Washington, DC 20405 (202) 708-5082

37. MIL Military Standardization Documents

(U.S. Department of Defense) Naval Publications and Forms Center 5801 Tabor Ave. Philadelphia, PA 19120

38. NIST National Institute of Standards and Technology

(U.S. Department of Commerce) Gaithersburg, MD 20899 (301) 975-2000

39. OSHA Occupational Safety and Health Administration

(U.S. Department of Labor) 200 Constitution Ave., NW Washington, DC 20210 (202) 219-6091

40. PS Product Standard of NBS

(U.S. Department of Commerce) Government Printing Office Washington, DC 20402 (202) 783-3238

41. USPS U.S. Postal Service

475 L'Enfant Plaza, SW Washington, DC 20260-0010 (202) 268-2000

H. Trade Union Jurisdictions: The Contractor shall maintain, and require subcontractors to

maintain, complete current information on jurisdictional matters, regulations and pending actions, as applicable to construction activities. The manner in which Contract Documents have been organized and subdivided is not intended to be indicative of trade union or jurisdictional agreements.

42. Discuss new developments at project meetings at the earliest feasible dates. Record

relevant information and actions agreed upon.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\11 - 01097S96 - Reference Stds & Definitions - bkf.doc 01097 - 10

43. Assign and subcontract construction activities, and employ tradesmen and laborers in a

manner that will not unduly risk jurisdictional disputes that could result in conflicts, delays, claims and losses.

PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable)

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\12 - 01098S96 - Codes, Regulations, Stds - bkf.doc 01098 - 1

SECTION 01098

CODES, REGULATIONS AND STANDARDS - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this section.

1.2 SUMMARY

A. This section sets forth governmental regulations which are included and incorporated herein by reference and made a part of the specification. This section also sets forth those notices and permits which are known to the Owner and which either must be applied for and received, or which must be given to governmental agencies before start of work. 1. Requirements include adherence to work practices and procedures set forth in applicable

codes, regulations and standards. 2. Requirements include obtaining permits, licenses, inspections, releases and similar

documentation, as well as payments, statements and similar requirements associated with codes, regulations, and standards.

1.3 CODES, REGULATIONS AND STANDARDS

A. General Applicability of Codes, Regulations and Standards: Except to the extent that more explicit or more stringent requirements are written directly into the Contract Documents, all applicable codes and regulations have the same force and effect (and are made a part of the contract documents by reference) as if copied directly into the Contract Documents, or as if published copies are bound herewith.

B. Contractor Responsibility: The Contractor shall assume full responsibility and liability for the

compliance with all applicable Federal, State, and local regulations pertaining to work practices, hauling, disposal, and protection of workers, visitors to the site, and persons occupying areas adjacent to the site. The Contractor is responsible for providing medical examinations and maintaining medical records of personnel as required by the applicable Federal, State, and local regulations. The Contractor shall hold the Owner and Engineer harmless for failure to comply with any applicable work, hauling, disposal, safety, health or other regulation on the part of the contractor, the contractor’s employees, or subcontractors.

C. Federal Requirements: which govern asbestos abatement work or hauling and disposal of

asbestos waste materials include but are not limited to the following:

1. OSHA: U.S. Department of Labor, Occupational Safety and Health Administration, (OSHA), including but not limited to:

a. Occupational Exposure to Asbestos, Tremolite, Anthophyllite, and Actinolite;

Final Rules Title 29, Part 1910, Section 1001 of the Code of Federal Regulations Final Rules Title 29, Part 1926, Section 1101 of the Code of Federal Regulations

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\12 - 01098S96 - Codes, Regulations, Stds - bkf.doc 01098 - 2

b. Respiratory Protection

Title 29, Part 1910, Section 134 of the Code of Federal Regulations Title 29, Part 1926, Section 103 of the Code of Federal Regulations

c. Personal Protective Equipment for General Industry

Title 29, Part 1910, Section 132 of the Code of Federal Regulations Title 29, Part 1926, Sections 95 - 107 of the Code of Federal Regulations

d. Access to Employee Exposure and Medical Records

Title 29, Part 1926, Section 33 of the Code of Federal Regulations

e. Hazard Communication Title 29, Part 1926, Section 59 of the Code of Federal Regulations

f. Specifications for Accident Prevention Signs and Tags

Title 29, Part 1910, Section 145 of the Code of Federal Regulations

g. Permit Required Confined Space Title 29, Part 1910, Section 146 of the Code of Federal Regulations

h. Construction Industry

Title 29, Part 1910, Section 1001 of the Code of Federal Regulations Title 29, Part 1926, Section 1101 of the Code of Federal Regulations

i. Construction Industry - General Duty Standards Title 29, Part 1926, Sections 20 through 35 of the Code of Federal Regulations

j. Shipyard Industry

Title 29 Part 1915 Section 1001 of the Code of Federal Regulations

2. DOT: U. S. Department of Transportation, including but not limited to:

a. Hazardous Substances Title 49, Part 171 and 172 of the Code of Federal Regulations

b. Hazardous Material Regulations

General Awareness and Training Requirements for Handlers, Loaders and Drivers Title 49, Parts 171-180 of the Code of Federal Regulations

c. Hazardous Material Regulations

Editorial and Technical Revisions Title 49, Parts 171-180 of the Code of Federal Regulations

3. EPA: U. S. Environmental Protection Agency (EPA), including but not limited to:

a. Asbestos Hazard Emergency Response Act (AHERA) Regulation

Title 40, Part 763, Sub-part E of the Code of Federal Regulations b. EPA Model Accreditation Plan - Asbestos Containing Materials Final Rule &

Notice

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\12 - 01098S96 - Codes, Regulations, Stds - bkf.doc 01098 - 3

Title 40, Part 763, Sub-part E, Appendix C of the Code of Federal Regulations

c. National Emission Standard for Hazardous Air Pollutants (NESHAP) National Emission Standard for Asbestos Title 40, Part 61, Sub-part A, and Sub-part M (Revised Sub-part B) of the Code of Federal Regulations

D. State Requirements: which govern asbestos abatement work or hauling and disposal of asbestos

waste materials include but are not limited to the following:

a. Ohio Department of Health – Asbestos Hazard Abatement Rules, Chapter 3701-34, Ohio Administrative Code, Amended February 1, 1993. Effective date: 11/13/2014.

E. Local Requirements: which govern asbestos abatement work or hauling and disposal of asbestos

waste materials include but are not limited to the following:

a. Ohio Department of Health – Asbestos Hazard Abatement Rules, Chapter 3701-34, Ohio Administrative Code, Amended February 1, 1993. Effective date: 11/13/2014.

1.4 NOTICES:

A. U.S. ENVIRONMENTAL PROTECTION AGENCY

1. Postmark or Deliver Written Notification as required by USEPA National Emission Standards for Hazardous Air Pollutants (NESHAP) Asbestos Regulations (40 CFR 61, Subpart M) to the regional Asbestos NESHAP Contact at least 10 working days prior to beginning any work on asbestos-containing materials (ACM). Send notification to the following address:

a. Mahoning – Trumbull County Air Pollution Control Agency Youngstown City Health District Oakhill Renaissance Place 345 Oakhill Avenue, Suite 200

Asbestos NESHAP Contact Youngstown, Ohio 44502 Ms.Tara Cioffi, Administrator (330) 743-3333, ext.283

2. There is a copy of the NESHAP form at the end of this section.

3. Notification: Include the following information in the notification sent to the NESHAP contact: a. Indication whether the notification is the original or revised notification b. Name, address, and telephone number of owner or operator. c. Name, address, and telephone number of contractor. d. Type of Operation (demolition or renovation).

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\12 - 01098S96 - Codes, Regulations, Stds - bkf.doc 01098 - 4

e. Description of the facility or affected part of the facility being demolished or renovated, including the size (square feet [square meters], number of floors), age, present and prior use of the facility.

f. Estimate of the approximate amount of RACM to be removed from the facility in terms of linear meters [linear feet] of pipe, and surface area in square meters [square feet] of other facility components. Also estimate the approximate amount of Category I and Category II nonfriable ACM in the affected part of the facility that will not be removed before demolition.

g. For facilities in which the amount of friable asbestos materials less than 80 linear meters (260 linear feet) on pipes and less than 15 square meters (160 square feet) or 1 cubic meter (35 cubic feet) if the length and width could not be measured. On other facility components, explain techniques of estimation.

h. Location and street address (including building number or name and floor or room number, if appropriate), city county, and state, of the facility being demolished or renovated.

i. Scheduled starting and completion dates of asbestos removal work (or any other activity, such as site preparation that would break up, dislodge, or similarly disturb asbestos material) in a demolition or renovation; planned renovation operations involving individual nonscheduled operations shall only include the beginning and ending dates of the report period as described in paragraph (a)(4)(iii) of 40 CFR 61.145.

j. Scheduled starting and completion dates of demolition or renovation. k. Nature of planned demolition or renovation and method(s) to be used, including

demolition or renovation techniques to be used and description of affected facility components.

l. Procedures to be used to comply with the requirements of USEPA National Emission Standards for Hazardous Air Pollutants (NESHAP) Asbestos Regulations (40 CFR 61 Subpart M).

m. Name and location of the waste disposal site where the asbestos containing waste material will be deposited.

n. A certification that at least one person trained as required by paragraph (c)(8) of 40 CFR 61.145 will supervise the stripping and removal described by this notification.

o. For emergency renovations described in paragraph (a)(4)(iv) of 40 CFR 61.145 , the date and hour that the emergency occurred, a description of the sudden, unexpected event, and an explanation of how the event caused an unsafe condition, or would cause equipment damage or an unreasonable financial burden.

p. Description of procedures to be followed in the event that the unexpected RACM is found or Category II nonfriable ACM becomes crumbled, pulverized, or reduced to powder.

q. Name, address, and telephone number of the waste transporter. B. STATE AND LOCAL AGENCIES:

3. Send written notification as required by state and local regulations prior to beginning any

work on ACM.

a. Ohio Department of Health – Asbestos Hazard Abatement Rules, Chapter 3701-34, Ohio Administrative Code, Amended February 1, 1993. Effective date: 11/13/2014.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\12 - 01098S96 - Codes, Regulations, Stds - bkf.doc 01098 - 5

1.5 PERMITS: A. Permit: All asbestos containing waste is to be transported by an entity maintaining a current

"Industrial waste hauler permit" specifically for ACM, as required for transporting of waste ACM to a disposal site.

B. Contractor is responsible for obtaining any demolition, building, renovation or other permits, and

for paying application fees, if any, where required by State or Local jurisdictions. 1.6 LICENSES:

A. Licenses: Maintain current licenses as required by applicable state or local jurisdictions for the

removal, transporting, disposal or other regulated activity relative to the work of this contract. 1.7 POSTING AND FILING OF REGULATIONS

A. Posting and Filing of Regulations: Post all notices required by applicable federal, state and local regulations. Maintain two (2) copies of applicable federal, state and local regulations and standard. Maintain one copy of each at job site. Keep on file in Contractor's office one copy of each.

1.8 SUBMITTALS:

A. Before Start of Work: Submit the following to the Construction Manager for review. No work shall begin until these submittals are returned with Designer's action stamp indicating that the submittal is returned for unrestricted use or final-but-restricted use.

3. Permits, Licenses, and Certificates: For the Owner's records, submit copies of permits,

licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, and similar documents, correspondence and records established in conjunction with compliance with standards and regulations bearing upon performance of the Work including: a. State and Local Regulations: Submit copies of codes and regulations applicable to

the work. 4. Notices: Submit notices required by federal, state and local regulations together with proof

of timely transmittal to agency requiring the notice. 5. Permits: Submit copies of current valid permits required by state and local regulations. 6. Licenses: Submit copies of all State and local licenses and permits necessary to carry out

the work of this contract. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable)

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\13 - 01301S96 - Submittals - bkf.doc 01301 - 1

SECTION 01301

SUBMITTALS - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for submittals required for performance of the Work, including the following: 1. Submittal schedule. 2. Daily construction reports. 3. Shop Drawings. 4. Samples. 5. Quality Assurance Submittals

B. Administrative Submittals: Refer to other Division 1 Sections and other Contract Documents for

requirements for administrative submittals. Such submittals include, but are not limited to, the following: 1. Permits 2. Applications for payment 3. Performance and payment bonds 4. Insurance certificates 5. List of Subcontractors

C. RELATED SECTIONS

1. The following Sections contain requirements that relate to this Section:

a. Division 1 Section "Applications for Payment - Asbestos Abatement" specifies

requirements for submittal of the Schedule of Values. b. Division 1 Section "Coordination" specifies requirements governing submittal and

distribution of meeting and conference minutes.

1.3 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of

construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\13 - 01301S96 - Submittals - bkf.doc 01301 - 2

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

B. Submittal Preparation: Place a permanent label or title block on each submittal for

identification. Indicate the name of the entity that prepared each submittal on the label or title block. 1. Provide a space approximately 4 by 5 inches (100 by 125 mm) on the label or beside the

title block on Shop Drawings to record the Contractor's review and approval markings and the action taken.

2. Include the following information on the label for processing and recording action taken. a. Project name. b. Date. c. Name and address of the Engineer. d. Name and address of the Contractor. e. Name and address of the subcontractor. f. Name and address of the supplier. g. Name of the manufacturer. h. Number and title of appropriate Specification Section. i. Drawing number and detail references, as appropriate.

C. Submittal Transmittal: Package each submittal appropriately for transmittal and handling.

Transmit each submittal from the Contractor to the Engineer/Owner’s Representative using a transmittal form. The Engineer/Owner’s Representative will not accept submittals received from sources other than the Contractor. 1. On the transmittal, record relevant information and requests for data. On the form, or

separate sheet, record deviations from Contract Document requirements, including variations and limitations. Include Contractor's certification that information complies with Contract Document requirements.

1.4 SUBMITTAL SCHEDULE

A. Listing: At the end of this section is a listing of the principal submittals required for the work. This listing is not necessarily complete, nor does the listing reflect the significance of each submittal requirement. The listing is included only for the convenience of users of the Contract Documents.

B. Submittal Schedule: After development and acceptance of the Contractor's Construction

Schedule, prepare a complete schedule of submittals. Submit the schedule within 10 days of the date required for submittal of the Contractor's Construction Schedule. 1. Coordinate Submittal Schedule with the list of subcontracts, Schedule of Values, and the

list of products as well as the Contractor's Construction Schedule. 2. Prepare the schedule in chronological order. Provide the following information:

a. Scheduled date for the first submittal. b. Related Section number.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\13 - 01301S96 - Submittals - bkf.doc 01301 - 3

c. Submittal category (Shop Drawings, Product Data, or Samples). d. Name of the subcontractor. e. Description of the part of the Work covered. f. Scheduled date for resubmittal. g. Scheduled date for the Engineer/Owner’s Representative’s final release or approval.

C. Distribution: Following response to the initial submittal, print and distribute copies to the

Engineer/Owner’s Representative, Designer, Owner, subcontractors, and other parties required to comply with submittal dates indicated. Post copies in the Project meeting room and field office. 1. When revisions are made, distribute to the same parties and post in the same locations.

Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in construction activities.

D. Schedule Updating: Revise the schedule after each meeting or activity where revisions have

been recognized or made. Issue the updated schedule concurrently with the report of each meeting.

1.5 SHOP DRAWINGS (NOT USED).

1.6 PRODUCT DATA (NOT USED). 1.7 SAMPLES (NOT USED). 1.8 QUALITY ASSURANCE SUBMITTALS (NOT USED). 1.9 MISCELLANEOUS SUBMITTALS:

A. Safety Data Sheets: Process material safety data sheets as product data. These are submitted for

information purposes only, they will be returned with the action stamp, Received - Not Reviewed. B. Inspection and Test Reports: Classify each inspection and test report as being either "shop

drawings" or "product data" depending on whether the report is specially prepared for the project, or a standard publication of workmanship control testing at the point of production. Process inspection and test reports accordingly.

C. Records of Actual Work: Furnish 4 copies of records of actual work, one of which will be

returned for inclusion in the record documents as specified in section "Project Closeout".

D. Record Documents: Furnish set of original documents as maintained on the project site. Along with original marked-up record drawings provide 2 photographic copies of marked-up drawings, which, at the Contractor's option, may be reduced to not less than half size.

1.10 DESIGNER’S ACTION

A. Except for submittals for the record or information, where action and return is required, the

Designer will review each submittal, mark to indicate action taken, and return promptly. 1. Compliance with specified characteristics is the Contractor's responsibility.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\13 - 01301S96 - Submittals - bkf.doc 01301 - 4

B. Action Stamp: The Designer will stamp each submittal with a uniform, action stamp. The Designer will mark the stamp appropriately to indicate the action taken, as follows: 2. Final Unrestricted Release: When the Designer marks a submittal "Approved," the Work

covered by the submittal may proceed provided it complies with requirements of the Contract Documents. Final payment depends on that compliance.

3. Final-But-Restricted Release: When the Designer marks a submittal "Approved as Noted," the Work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the Contract Documents. Final payment depends on that compliance.

4. Returned for Resubmittal: When the Designer marks a submittal "Not Approved, Revise and Resubmit," do not proceed with Work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal according to the notations; resubmit without delay. Repeat if necessary to obtain different action mark. Do not use, or allow others to use, submittals marked "Not Approved, Revise and

Resubmit" at the Project Site or elsewhere where Work is in progress. 5. Received - Not Reviewed: When the Designer marks a submittal "Received - Not

Reviewed” this acknowledges that the submittal has been received. This action applies to materials that are to be submitted for information purposes only, and where no review or action by the Designer is required.

6. Other Action: Where a submittal is for information or record purposes or special processing or other activity, the Designer will return the submittal marked "Action Not Required."

C. Unsolicited Submittals: The Designer will return unsolicited submittals to the sender without

action. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable)

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\14 - 01513S96 - Temp Pressure Differential & Air Circulation - bkf.doc01513 - 1

SECTION 01513

TEMPORARY PRESSURE DIFFERENTIAL AND AIR CIRCULATION SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to work of this section.

1.2 RELATED SECTIONS

A. Heating and cooling requirements are set forth in Section 01503 Temporary Facilities -

Asbestos Abatement. 1.3 MONITORING

A. Continuously monitor and record the pressure differential between the Work Area and the building outside of the Work Area with a monitoring device incorporating a continuous recorder (e.g. strip chart).

1.4 SUBMITTALS

A. Before Start of Work: Submit design of pressure differential system to the Engineer/Owner’s Representative for review. Do not begin work until submittal is returned with the Designer's action stamp indicating that the submittal is returned for unrestricted use. Include in the submittal at a minimum: 1. Number of HEPA filtered fan units required and the calculations necessary to determine the

number of machines 2. Description of projected air flow within Work Area and methods required to provide

adequate air flow in all portions of the work area 3. Anticipated pressure differential across Work Area enclosures 4. Description of methods of testing for correct air flow and pressure differentials 5. Manufacturer's product data on the HEPA filtered fan units to be used 6. Location of the machines in the Work Area 7. Method of supplying adequate power to the machines and designation of building electrical

panel(s) which will be supplying the power. 8. Description of work practices to insure that airborne fibers travel away from workers 9. Manufacturer's product data on equipment used to monitor pressure differential between

inside and outside of Work Area. 10. Manufacturer's product data on auxiliary generator to be used

11. Manufacturer's product data on auxiliary power switch to be used 12. Schematic diagram of power and auxiliary power supply to HEPA filtered fan units

B. On a weekly basis: Submit printout from pressure differential monitoring equipment. Mark

printout with date and start of time for each day. Use printout paper that indicates elapsed time in intervals no greater than hours. Indicate on each days record times of starting and stopping abatement work, type of work in progress, breaks for lunch or other purposes, periods of stop

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\14 - 01513S96 - Temp Pressure Differential & Air Circulation - bkf.doc01513 - 2

work, and filter changes. Cut printout into segments by day, attach to 8 1/2" by 11" [ 215 X 280 mm ] paper. Label with project name, contractors name and date.

1.5 QUALITY ASSURANCE:

A. Monitor pressure differential at Personnel and Equipment Decontamination Units with a

differential pressure meter equipped with a continuous recorder. Meter shall be equipped with a warning buzzer which will sound if pressure differential drops below 0.02 inch [0.5 mm] of water.

PART 2 - PRODUCTS 2.1 HEPA FILTERED FAN UNITS:

A. General: Supply the required number of HEPA filtered fan units to the site in accordance with these specifications. Use units that meet the following requirements.

B. Cabinet: Constructed of durable materials able to withstand damage from rough handling and

transportation. The width of the cabinet should be less than 30 inches [0.76 meters] to fit through standard-size doorways. Provide units whose cabinets are: 1. Factory-sealed to prevent asbestos-containing dust from being released during use,

transport, or maintenance 2. Arranged to provide access to and replacement of all air filters from intake end 3. Mounted on casters or wheels

C. Fans: Rate capacity of fan according to usable air-moving capacity under actual operating

conditions.

D. HEPA Filters: Provide units whose final filter is the HEPA type with the filter media (folded into closely pleated panels) completely sealed on all edges with a structurally rigid frame. 1. Provide units with a continuous rubber gasket located between the filter and the filter

housing to form a tight seal. 2. Provide HEPA filters that are individually tested and certified by the manufacturer to have

an efficiency of not less than 99.97 percent when challenged with 0.3 um dioctylphthalate (DOP) particles when tested in accordance with Military Standard Number 282 and Army Instruction Manual 136-300-175A. Provide filters that bear a UL586 label to indicate ability to perform under specified conditions.

3. Provide filters that are marked with: the name of the manufacturer, serial number, air flow rating, efficiency and resistance, and the direction of test air flow.

4. Pre-filters, which protect the final filter by removing the larger particles, are required to prolong the operating life of the HEPA filter. Two stages of pre-filtration are required. Provide units with the following pre-filters: a. First-stage pre-filter: low-efficiency type (e.g., for particles 100 um and larger) b. Second-stage (or intermediate) filter: medium efficiency (eg., effective for particles

down to 5 um) c. Provide units with pre-filters and intermediate filters installed either on or in the

intake grid of the unit and held in place with special housings or clamps.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\14 - 01513S96 - Temp Pressure Differential & Air Circulation - bkf.doc01513 - 3

E. Instrumentation: Provide units equipped with: 1. Magnehelic gauge or manometer to measure the pressure drop across filters and indicate

when filters have become loaded and need to be changed 2. A table indicating the usable air-handling capacity for various static pressure readings on

the Magnehelic gauge affixed near the gauge for reference, or the Magnehelic reading indicating at what point the filters should be changed, noting Cubic Feet per Minute (CFM) (Liters / Second (LPS)) air delivery at that point

3. Elapsed time meter to show the total accumulated hours of operation

F. Safety and Warning Devices: Provide units with the following safety and warning devices: 1. Electrical (or mechanical) lockout to prevent fan from operating without a HEPA filter 2. Automatic shutdown system to stop fan in the event of a rupture in the HEPA filter or

blocked air discharge 3. Warning lights to indicate normal operation (green), too high a pressure drop across the

filters (i.e., filter overloading) (yellow), and too low of a pressure drop (i.e., rupture in HEPA filter or obstructed discharge) (red)

4. Audible alarm if unit shuts down due to operation of safety systems

G. Electrical components: Provide units with electrical components approved by the National Electrical Manufacturers Association (NEMA) and Underwriter's Laboratories (UL). Each unit is to be equipped with overload protection sized for the equipment. The motor, fan, fan housing, and cabinet are to be grounded.

H. Manufacturers: Subject to compliance with requirements, manufacturers offering products

which may be incorporated in the work include, but are not limited to, the following: 2.2 AUXILIARY GENERATOR:

A. Auxiliary Generator: Provide a gasoline or diesel-powered self-starting generator with a capacity adequate to power a minimum of 50% of the HEPA filtered fan units in operation at any time during the work.

2.3 AUXILIARY POWER SWITCH:

A. Auxiliary Power Switch: Provide a switching relay which will automatically start auxiliary generator and switch over power supplied to HEPA filtered fan units to auxiliary generator.

PART 3 - EXECUTION 3.1 PRESSURE DIFFERENTIAL ISOLATION

A. Isolate the Work Area from all adjacent areas or systems of the building with a Pressure Differential that will cause a movement of air from outside to inside at any breach in the physical isolation of the Work Area.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\14 - 01513S96 - Temp Pressure Differential & Air Circulation - bkf.doc01513 - 4

B. Relative Pressure in Work Area: Continuously maintain the work area at an air pressure that is lower than that in any surrounding space in the building, or at any location in the immediate proximity outside of the building envelope. This pressure differential when measured across any physical or critical barrier must equal or exceed a static pressure of: 1. 0.02 inches (0 .5 mm) of water.

C. Accomplish the pressure differential by exhausting a sufficient number of HEPA filtered fan

units from the work area. The number of units required will depend on machine characteristics, the seal at barriers, and required air circulation. The number of units will increase with increased make-up air or leaks into the Work Area. Determine the number of units required for pressure isolation by the following procedure:

1. Establish required air circulation in the work area, personnel and equipment

decontamination units. 2. Establish isolation by increased pressure in adjacent areas or as part of seals where

required. 3. Exhaust a sufficient number of units from the work area to develop the required pressure

differential. 4. The required number of units is the number determined above plus one additional unit. 5. Vent HEPA filtered fan units to outside of building unless authorized in writing by the

Engineer/Owner’s Representative. 6. Mount units to exhaust directly or through disposable ductwork. 7. Use only new ductwork except for sheet metal connections and elbows. 8. Use ductwork and fittings of same diameter or larger than discharge connection on fan unit. 9. Use inflatable, disposable plastic ductwork in lengths not greater than 100 feet (30 meters). 10. Use spiral wire-reinforced flex duct in lengths not greater than 50 feet (15 meters). 11. Arrange exhaust as required to inflate duct to a rigidity sufficient to prevent flapping. 12. If direction of discharge from fan unit is not aligned with duct use sheet metal elbow to

change direction. Use six feet (2 meters) of spiral wire reinforced flex duct after direction change.

D. Isolation of elevators, stair towers, and return air intakes: Erect seals with an air space at

doors to elevators and stair towers. Pressurize this space with HEPA-filtered air so that it is at a pressure greater than either the Work Area elevator shaft or stair tower. 1. Fabricate seal by first sealing door with duct tape and 6 mil polyethylene. Construct a

barrier from " (13 mm) gypsum board supported by 3-5/8" (92 mm) x 25 gauge metal studs at 16" (410 mm) on centers. Space face of barrier a minimum of 3" (76 mm) from face of door. Seal barrier with 6 mil (0.15 mm) sheet plastic and duct tape.

2. Pressurize space with exhaust from HEPA filtered fan unit. Continuously maintain a

pressure differential with this space a minimum of 0.02 inches (0.5 mm) of water higher in static pressure than any adjacent space.

3. Locate HEPA filtered fan unit outside of work area. Fabricate a manifold as required to distribute air to individual spaces to be isolated. Provide relief venting at unit as required to prevent shut down due to low air flow while still maintaining required air pressure.

E. Isolation of chases and enclosed stairs: Pressurize chases and enclosed stairs with HEPA

filtered air so that it is at a pressure greater than any adjacent work area.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\14 - 01513S96 - Temp Pressure Differential & Air Circulation - bkf.doc01513 - 5

1. Pressurize space with exhaust from HEPA filtered fan unit. Continuously maintain a pressure differential with this space a minimum of 0.02 (.5 mm ) inches of water higher in static pressure than any adjacent work area.

F. Isolation of return air ductwork: Return air duct work which must be kept operating is located

in the Work Area. This duct work is to be isolated from the Work Area by an enclosure forming an annular space around the duct which is positively pressurized with HEPA filtered air. 1. Wrap the duct with 6 mil (0.15 mm) polyethylene. Seal all polyethylene seams with spray

glue and duct tape. 2. Enclose wrapped duct with two layers of polyethylene. Fabricate inner layer from 6 mil

(0.15 mm) polyethylene with all seams sealed with spray glue and duct tape. Arrange outer layer to support inner layer. Fabricate out of reinforced sheet plastic with seams sealed with spray glue and duct tape and reinforced with staples. Support outer layer with a frame work fabricated from 2" x 4"s (51 mm x 102 mm) at 24" (610 mm) on center. Enclosures less than 2'-6' in diameter may be reinforced with box strapping in lieu of wood framing.

3.2 AUXILIARY GENERATOR

A. Provide auxiliary gasoline-powered generator located outside of the building in a location protected from the weather. Install the generator in a location so that the exhaust from the generator does not flow to any building ventilation or supplied air intakes. Arrange so that if a power failure occurs the generator automatically starts and supplies power to a minimum of 50% of the HEPA filtered fan units in operation.

3.3 AIR CIRCULATION IN THE WORK AREA:

A. Air Circulation: For purposes of this section air circulation refers to either the introduction of outside air to the Work Area or the circulation and cleaning of air within the Work Area.

B. Air circulation in the Work Area is a minimum requirement intended to help maintain airborne

fiber counts at a level that does not significantly challenge the work area isolation measures. The Contractor may also use this air circulation as part of the engineering controls in the worker protection program.

C. Determining the Air circulation Requirements: The air flow volume (cubic meters per minute)

exhausted (removed) from the workplace must exceed the amount of makeup air supplied to the enclosure. Provide a fully operational air circulation system supplying a minimum of the following air circulation rate: 1. 4 air changes per hour

D. Determine Number of Units needed to achieve required air circulation according to the following

procedure: 1. Determine the volume in cubic feet of the work area by multiplying floor area by ceiling

height. Determine total air circulation requirement in cubic feet per minute (CFM) for the work area by dividing this volume by 60 and multiplying by the air change rate.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\14 - 01513S96 - Temp Pressure Differential & Air Circulation - bkf.doc01513 - 6

2. Air Circulation Required in Cubic Feet of Air per Minute (CFM) = Volume of work area (cu. ft.) X Number of air changes per hour

60 (minutes per hour) 3.4 EXHAUST SYSTEM:

A. Pressure differential isolation and air circulation and pressure differential in the Work Area are to be accomplished by an exhaust system as described below. 1. Exhaust all units from the Work Area to meet air circulation requirement of this section. 2. Location of HEPA Filtered Fan Units: Locate fan unit(s) so that makeup air enters work

area primarily through decontamination facilities and traverses Work Area as much as possible. This may be accomplished by positioning the HEPA filtered fan unit(s) at a maximum distance from the worker access opening or other makeup air sources.

3. The end of the unit or its exhaust duct should be placed through an opening in the plastic barrier or wall covering. Seal plastic around the unit or duct with tape.

4. Vent to Outside of Building, unless authorized in writing by the Designer. 5. Air Handling Unit Exhaust: The exhaust plume from air handling units should be located

away from adjacent personnel and intakes for HVAC systems. 6. Decontamination Units: Arrange Work Area and decontamination units so that the

majority of make up air comes through the Decontamination Units. Use only personnel or equipment Decontamination Unit at any time and seal the other so that make up air passes through unit in use.

7. Supplemental Makeup Air Inlets: Provide where required for proper air flow through the Work Area in location approved by the Designer by making openings in the plastic sheeting that allow air from outside the building into the Work Area. Locate auxiliary makeup air inlets as far as possible from the fan unit(s) (e.g., on an opposite wall), off the floor (preferably near the ceiling), and away from barriers that separate the Work Area from occupied clean areas. Cover with flaps to reseal automatically if the pressure differential system should shut down for any reason. Spray flap and around opening with spray adhesive so that if flap closes meeting surfaces are both covered with adhesive. Use adhesive that forms contact bond when dry.

3.5 AIR CIRCULATION IN DECONTAMINATION UNITS:

A. Pressure Differential Isolation: Continuously maintain the pressure differential required for the

work area in the:

1. Personnel Decontamination Unit: across the Shower Room with the Equipment Room at a lower pressure than the Clean room.

2. Equipment Decontamination Unit: Across the Holding Room with the Wash Room at a

lower pressure than the Clean Room. B. Air Circulation: Continuously maintain air circulation in Decontamination Units at same level

as required for Work Area.

C. Air Movement: Arrange air circulation through the Personnel Decontamination Unit so that it produces a movement of air from the Clean Room through the Shower Room into the Equipment Room. At each opening, the air flow velocity must be sufficient to provide visible indications of

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\14 - 01513S96 - Temp Pressure Differential & Air Circulation - bkf.doc01513 - 7

air movement into the work area. The velocity of air flow within the enclosure must be adequate to remove airborne contamination from each worker's breathing zone without disturbing the asbestos-containing material on surfaces.

3.6 USE OF THE PRESSURE DIFFERENTIAL AND AIR CIRCULATION SYSTEM:

A. General: Each unit shall be serviced by a dedicated minimum 115V-20A circuit with ground

fault circuit interrupter (GFCI) supplied from temporary power supply. B. Air Flow Tests: Air flow patterns will be checked before removal operations begin, at least once

per operating shift and any time there is a question regarding the integrity of the enclosure. The primary test for air flow is to trace air currents with smoke tubes or other visual methods. Flow checks are made at each opening and at each doorway to demonstrate that air is being drawn into the enclosure and at each worker's position to show that air is being drawn away from the workers location and toward the HEPA filtration unit.

C. Demonstrate Condition of Equipment for each HEPA filtered fan unit and pressure differential

monitoring equipment including proper operation of the following: 1. Squareness of HEPA Filter 2. Condition of Seals 3. Proper operation of all lights 4. Proper operation of automatic shut down if exhaust is blocked 5. Proper operation of alarms 6. Proper operation of Magnehelic gauge 7. Proper operation and calibration on pressure monitoring equipment

D. Demonstrate Operation of the pressure differential system to the Engineer/Owner’s Representative will include, but not be limited to, the following: 1. Plastic barriers and sheeting move lightly in toward Work Area, 2. Curtain of decontamination units move lightly in toward Work Area, 3. There is a noticeable movement of air through the Decontamination Unit. 4. Use smoke tube to demonstrate air movement from Clean Room through Shower Room to

Equipment Room. 5. Use smoke tubes to demonstrate a definite motion of air across all areas in which work is to

be performed. 6. Use a differential pressure meter or manometer to demonstrate the required pressure

differential at every barrier separating the Work Area from the balance of the building, equipment, ductwork or outside.

7. Modify the Pressure Differential System as necessary to demonstrate successfully the above.

E. Use of System During Abatement Operations: 1. Start fan units before beginning work (before any asbestos-containing material is

disturbed). After abatement work has begun, run units continuously to maintain a constant pressure differential and air circulation until decontamination of the work area is complete. Do not turn off units at the end of the work shift or when abatement operations temporarily stop.

2. Monitoring Pressure within the Enclosure: After the initial air flow patterns have been checked, the static pressure must be monitored within the enclosure. Monitoring may be

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\14 - 01513S96 - Temp Pressure Differential & Air Circulation - bkf.doc01513 - 8

made using manometers, pressure gauges, or combinations of these devices. It is recommended that they be attached to alarms and strip chart recorders

3. Do not shut down air pressure differential system during encapsulating procedures, unless authorized by the Engineer/Owner’s Representative in writing. Supply sufficient pre-filters to allow frequent changes.

4. Start abatement work at a location farthest from the fan units and proceed toward them. If an electric power failure occurs, immediately stop all abatement work and do not resume until power is restored and fan units are operating again.

5. Corrective Actions: If the manometers or pressure gauges demonstrate a reduction in pressure differential below the required level, work should cease and the reason for the change investigated and appropriate changes made. The air flow patterns should be retested before work begins again.

6. At completion of abatement work, allow fan units to run as specified under section 01711, to remove airborne fibers that may have been generated during abatement work and cleanup and to purge the Work Area with clean makeup air. The units may be required to run for a longer time after decontamination, if dry or only partially wetted asbestos material was encountered during any abatement work.

F. Dismantling the System:

1. When a final inspection and the results of final air tests indicate that the area has been decontaminated, fan units may be removed from the Work Area. Before removal from the Work Area, remove and properly dispose of pre-filter, decontaminate exterior of machine and seal intake to the machine with 6 mil (0.15 mm) polyethylene to prevent environmental contamination from the filters.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\15 - 015113(01520) - Utilities.doc 01520-1

SECTION 01520

UTILITIES PART 1 GENERAL 1.01 DESCRIPTION

A. The Contractor will be responsible for the protection of all above and underground utilities.

Contractor will replace at his expense any damage done to the above, caused by the abatement of the building(s).

B. Locate all existing active utility lines traversing the site(s) and determine the requirements for

their protection. 1.02 DISCONNECTION OF UTILITIES

A. Before starting any site operations, arrange for the disconnection of all utility services, which service the building(s). All such work shall be performed in accordance with the requirements of the utility company or agency involved.

B. The Contractor will be responsible for the disconnection, removal, and relocation of any

utility line.

C. The Contractor will be responsible for any damage done to any active utility lines.

D. The information provided in this section is for the Contractor’s convenience and may not be complete or up-to-date. The Contractor is advised to verify all representations made herein.

1. Ameritech-SBC

50 West Bowery 6th Floor Akron, OH 44308

1-800-660-1000

2. City of Youngstown, Deputy Director of Public Works Mr. Chuck Shasho, 330-742-8800

3. City of Youngstown Water Department

Mr. Gene Leson, 330-743-5338

4. Ohio Edison Mr. Randy Renstrom, 330-740-7505

5. City of Youngstown Wastewater Treatment Plant

Mr. Tom Miranti, 330-742-8818

6. East Ohio Gas Construction and Engineering Department, 330-746-7611

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\15 - 015113(01520) - Utilities.doc 01520-1

Engineering Department, 330-742-8137

7. Youngstown Thermal Jim Mullen, 330-743-7712

1.03 PROTECTION OF UTILITIES

A. Preserve in operating condition all active utilities traversing the construction areas and designated to remain.

B. Before starting abatement, check to determine that all utilities services, such as water, gas,

electricity and telephone, have been disconnected at the service mains, in accordance with the rules and regulations governing the utility involved. Preserve all active utility mains traversing the project.

END OF SECTION - 01520

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 1

SECTION 01526

TEMPORARY ENCLOSURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to work of this section.

1.2 SUBMITTALS:

A. Before Start of Work submit the following to the Engineer/Owner’s Representative for review. Do not begin work until these submittals are returned with the Designer's action stamp indicating that the submittal has been “Received - Not Reviewed.” 1. Safety Data Sheet: Submit Safety Data Sheets, or equivalent, in accordance with the OSHA

Hazard Communication Standard (HCS) (29 CFR 1910.1200) and Globally Harmonized System of Classification and Labeling of Chemicals (GHS) for, but not limited to the following: a. Spray Cement.

PART 2 - PRODUCTS 2.1 SHEET PLASTIC:

A. Polyethylene Sheet: A single polyethylene film in the largest sheet size possible to minimize seams, 6.0 mil (0.15 mm) thick, clear, frosted, or black as indicated.

B. Reinforced Polyethylene Sheet: Where plastic sheet constitutes the only barrier between the

work area and the building exterior, provide translucent, nylon reinforced or woven polyethylene, laminated, flame-resistant, polyethylene film that conforms to requirements set forth by the National Fire Protection Association Standard 701, Small Scale Fire Test for Flame-resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mil (0.15 mm) thick, frosted or black as indicated.

2.2 MISCELLANEOUS MATERIALS:

A. Duct Tape: Provide duct tape in 2 inch or 3 inch (50 mm or 75 mm) widths as indicated, with an adhesive which is formulated to stick aggressively to sheet polyethylene.

B. Spray Cement: Provide spray adhesive in aerosol cans which is specifically formulated to stick

tenaciously to sheet polyethylene.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 2

PART 3 - EXECUTION 3.1 SEQUENCE OF WORK:

A. Carry out work of this section sequentially. Complete each of the following activities in accordance with requirements before proceeding to the next. 1. Provide emergency exits and emergency lighting. 2. Control access 3. Provide respiratory and worker protection. 4. Provide Critical Barriers. 5. Prepare Area. 6. Provide Primary Barriers. 7. Provide Isolation Areas as required. 8. Provide Secondary Barrier.

3.2 GENERAL:

A. Work Area: the location where asbestos abatement work occurs. The Work Area is a variable of the extent of work of the Contract. It may be a portion of a room, a single room, or a complex of rooms. A "Work Area" is considered contaminated during the work, and must be isolated from the balance of the building, and decontaminated at the completion of the asbestos control work.

B. Completely isolate the Work Area from other parts of the building so as to prevent asbestos-

containing dust or debris from passing beyond the isolated area. Should the area beyond the Work Area(s) become contaminated with asbestos-containing dust or debris as a consequence of the work, clean those areas in accordance with the procedures indicated in Section 01711. Perform all such required cleaning or decontamination at no additional cost to owner.

C. Construct enclosures to provide an air-tight seal around ducts and openings into existing

ventilation systems and around penetrations for electrical conduits, telephone wires, water lines, drain pipes, etc. Construct enclosures to be both airtight and watertight except for those openings designed to provide entry and/or air flow control.

D. Size: Construct enclosure with sufficient volume to encompass all of the working surfaces yet

allow unencumbered movement by the worker(s), provide unrestricted air flow past the worker(s), and ensure walking surfaces can be kept free of tripping hazards.

E. Shape: The enclosure may be any shape that optimizes the flow of ventilation air past the

worker(s).

F. Structural Integrity: The walls, ceilings and floors must be supported in such a manner that portions of the enclosure will not fall down during normal use.

G. Barrier Supports: Provide frames as necessary to support all unsupported spans of sheeting.

H. Openings: It is not necessary that the structure be airtight; openings may be designed to direct air

flow. Such openings are to be located at a distance from active removal operations. They are to be designed to draw air into the enclosure under all anticipated circumstances. In the event that negative pressure is lost, they are to be fitted with either HEPA filters to trap dust or automatic

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 3

trap doors that prevent dust from escaping the enclosure. Openings for exits are to be controlled by an airlock or a vestibule.

I. Place all tools, scaffolding, staging, etc. necessary for the work in the area to be isolated prior to

completion of Work Area isolation. J. Areas Within an Enclosure: Each enclosure consists of a work area, a decontamination area,

and waste storage area. The work area where the asbestos removal operations occur are to be separated from both the waste storage area and the contamination control area by physical curtains, doors, and/or airflow patterns that force any airborne contamination back into the work area.

K. Removing Mobile Objects: Clean movable objects and remove them from the work area before

an enclosure is constructed unless moving the objects creates a hazard. Mobile objects will be assumed to be asbestos contaminated and are to be either cleaned with amended water and a HEPA vacuum and then removed from the area or wrapped and then disposed of as asbestos-contaminated waste.

L. Disabling HVAC Systems: The power to the heating, ventilation, and air conditioning systems

that service the regulated area must be deactivated and locked out. All ducts, grills, access ports, windows and vents must be sealed off with two layers of plastic to prevent entrainment of contaminated air.

M. Operating HVAC Systems in the regulated Area: If components of a HVAC system located in

the regulated area are connected to a system that will service another zone during the project, the portion of the duct in the regulated area must be sealed and pressurized. Necessary precautions include caulking the duct joints, covering all cracks and openings with two layers of sheeting, and pressurizing the duct throughout the duration of the project by restricting the return air flow. The power to the fan supplying the positive pressure should be locked "on" to prevent pressure loss.

1. If fan providing positive pressure fails for any reason, immediately stop asbestos removal

work, mist the area to reduce airborne fiber levels. Notify the Engineer/Owner’s Representative. Do not re-start asbestos removal work until authorized by the Engineer.

N. Lockout power to Work Area by switching off all breakers serving power or lighting circuits in

work area. A lock and tag shall be placed on each breaker used to de-energize circuits and equipment with notation "DANGER circuit being worked on". Lock panel and have all keys under control of authorized person who has applied the locks.

O. Lockout power to circuits running through work area wherever possible by switching off all

breakers or removing fuses serving these circuits. Label breakers with tape over breaker with notation "DANGER circuit being worked on". Lock panel and have all keys under control of authorized person who applied locks. If circuits cannot be shut down for any reason, label at intervals 4 feet (1.22 m) on center with signs reading, "DANGER live electric circuit. Electrocution hazard." Label circuits in hidden locations but which may be affected by the work in a similar manner.

P. Inspection Windows: Install inspection windows in locations shown on the plans or as directed

by the Engineer. Each inspection window is to have a 24 inch X 24 inch (610 X 610 mm) viewing area fabricated from 1/4 inch (6.35 mm) acrylic or polycarbonate sheet. Install window

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 4

with top at 6 feet-6 inches (1.98 m) above floor height in a manner that provides unobstructed vision from outside to inside of the Work Area. Protect window from damage from scratching, dirt or any coatings used during the work. A sufficient number of windows are to be installed to provide observation of all portions of the Work Area that can be made visible from adjacent areas. Inspection windows that open into uncontrolled area are to be covered with a removable plywood hatch secured by lock and key. Provide keys to Engineer/Owner’s Representative for all such locks.

3.3 EMERGENCY EXITS:

A. Provide emergency exits and emergency lighting as set forth below: 1. Emergency Exits: At each existing exit door from the Work Area provide the following

means for emergency exiting: 2. Arrange exit door so that it is secure from outside the Work area but permits exiting from

the Work Area. 3. Mark outline of door on Primary and Critical Barriers with luminescent paint at least 1 inch

(25.4 mm) wide. Hang a razor knife on a string beside outline. Arrange Critical and Primary barriers so that they can be easily cut with one pass of razor knife. Paint words "EMERGENCY EXIT" inside outline with luminescent paint in letters at least one foot high and 2 inches (50.8 mm) wide.

4. Provide battery-operated emergency lighting that switches on automatically in the event of a power failure.

3.4 CONTROL ACCESS:

A. Isolate the Work Area to prevent entry by building occupants into Work Area or surrounding

controlled areas. Accomplish isolation by the following: 1. Submit to the Engineer/Owner’s Representative a list of doors and other openings that must

be secured to isolate Work Area. Include on list notation if door or opening is in an indicated exit route.

2. After receiving written authorization from the Engineer/Owner’s Representative, lock all doors into Work Area, or, if doors cannot be locked, chain shut. Notify the local fire department of the list of doors/or other openings which must be chained or otherwise secured shut. Cover any signs that direct emergency exiting, either outside or inside of Work Area, to locked doors. Do not obstruct doors required for emergency exits from Work Area or from building.

3. After receiving written authorization from the Engineer/Owner’s Representative, construct partitions or closures across any opening into Work Area. Partitions are to be a minimum of 8 feet (2.44 meters) high.

4. Fabricate partitions from 2 inch X 4 inch (50.8mm X 101.6mm) wood studs with inch (1.27 cm) plywood on both faces. Brace at intervals of 4 feet (1.25 m) on center.

5. Modify elevator controls to prevent elevators from stopping at doors in Work Areas. This

work is to be performed by a qualified elevator technician.

B. Locked Access: Arrange Work Area so that the only access into Work Area is through lockable doors to personnel and equipment decontamination units.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 5

1. Install temporary doors with entrance type locksets that are key lockable from the outside and always unlocked and operable from the inside. Do not use deadbolts or padlocks.

C. Visual Barrier: Where the Work Area is immediately adjacent to or within view of occupied

areas, provide a visual barrier of opaque polyethylene sheeting at least 6 mil (0.15 mm) in thickness so that the work procedures are not visible to building occupants. Where this visual barrier would block natural light, substitute frosted or woven rip-stop sheet plastic in locations approved by the Engineer/Owner’s Representative.

D. Demarcation. Demarcate the regulated area in any manner that minimizes the number of persons

within the area and protects persons outside the area from exposure to airborne concentrations of asbestos. Where critical barriers or negative pressure enclosures are used, they may demarcate the regulated area.

E. Access. Limit access to regulated areas to authorized persons as defined by OSHA, and to the

Owner, Designer, Engineer or a representative authorized by one of these entities. F. Provide Warning Signs at each locked door leading to Work Area reading as follows:

NOTE: PRIOR TO JUNE 1, 2016, employers may use the following signage 1. Print text in both English and Spanish

Legend Notation KEEP OUT 3 inch (77 mm) Sans Serif Gothic or Block BEYOND THIS POINT 1 inch (25.4 mm) Sans Serif Gothic or Block ASBESTOS ABATEMENT WORK 1 inch (25.4 mm) Sans Serif Gothic or Block IN PROGRESS 1 inch (25.4 mm) Sans Serif Gothic or Block BREATHING ASBESTOS DUST MAY BE 14 Point Gothic HAZARDOUS TO YOUR HEALTH

2. Immediately inside door and outside critical barriers post an approximately 20 inch by 14

inch (508 mm X 356 mm) manufactured caution sign displaying the following legend with letter sizes and styles of a visibility required by 29 CFR 1910.6:

Legend:

DANGER

ASBESTOS CANCER AND LUNG DISEASE HAZARD

AUTHORIZED PERSONNEL ONLY RESPIRATORS AND PROTECTIVE CLOTHING ARE REQUIRED IN THIS AREA

3. Provide spacing between respective lines at least equal to the height of the respective upper

line. NOTE: EFFECTIVE JUNE 1, 2016, ALL ASBESTOS SIGNS MUST BE GHS COMPLIANT AND READ AS FOLLOWS:

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 6

4. Provide Warning Signs required by 29 CFR 1910.1001 for regulated areas reading as follows:

Legend:

DANGER ASBESTOS

MAY CAUSE CANCER CAUSES DAMAGE TO LUNGS

AUTHORIZED PERSONNEL ONLY 5. Where the use of respirators and protective clothing is required in the regulated

area under section 29 CFR 1910.1001 (j)(4)(ii)(A), the warning signs shall include the following:

Legend:

DANGER ASBESTOS

MAY CAUSE CANCER CAUSES DAMAGE TO LUNGS

WEAR RESPIRATORY PROTECTIVE AND PROTECTIVE CLOTHING IN THIS AREA

AUTHORIZED PERSONNEL ONLY 3.5 ALTERNATE METHODS OF ENCLOSURE:

A. Alternate methods of containing the Work Area may be submitted to the Engineer/Owner’s Representative for approval in accordance with procedures set forth in Section 01632 Substitutions. Do not proceed with any such method(s) without prior written approval of the Engineer.

B. Notification: Before work which involves the removal of more than 25 linear or 10 square feet

(7.5 linear meters or 3 square meters) of thermal system insulation or surfacing material is begun using an alternative method which has been the subject of required evaluation and certification. Send a copy of such evaluation and certification to the national office of OSHA, Office of Technical Support, Room N3653, 200 Constitution Avenue, NW, Washington, DC 20210 and to the Mahoning – Trumbull County Air Pollution Control Agency.

C. Use a control method that encloses, contains or isolates the processes or source of airborne

asbestos dust, or otherwise captures or redirects such dust before it enters the breathing zone of employees.

3.6 RESPIRATORY AND WORKER PROTECTION:

A. Before proceeding beyond this point in providing Temporary Enclosures: 1. Provide Worker Protection per Section 01560 2. Provide Respiratory Protection per Section 01562 3. Provide Personnel Decontamination Unit per Section 01563

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 7

3.7 CRITICAL BARRIERS:

A. Completely Separate the Work Area from other portions of the building, and the outside by closing all openings with sheet plastic barriers at least 6 mil (0.15 mm) in thickness, or by sealing cracks leading out of Work Area with duct tape.

B. Individually seal all ventilation openings (supply and exhaust), lighting fixtures, clocks,

doorways, windows, convectors and speakers, and other openings into the Work Area with duct tape alone or with polyethylene sheeting at least 6 mil (0.15 mm) in thickness, taped securely in place with duct tape. Maintain seal until all work including Project Decontamination is completed. Take care in sealing of lighting fixtures to avoid melting or burning of sheeting.

C. Provide Sheet Plastic barriers at least 6 mil (0.15 mm) in thickness as required to seal openings

completely from the Work Area into adjacent areas. Seal the perimeter of all sheet plastic barriers with duct tape or spray cement.

D. Mechanically Support sheet plastic independently of duct tape or spray cement seals so that seals

do not support the weight of the plastic. Following are acceptable methods of supporting sheet plastic barriers. Alternative support methods may be used if approved in writing by the Designer.

1. Nylon or polypropylene rope or wire with a maximum unsupported span of 10 feet

(3.05 m), minimum 1/4 inch (6.35 mm) in diameter suspended between supports securely fastened on either side of opening at maximum 1 foot (304.8 mm) below ceiling. Tighten rope so that it has 2 inches (50.8 mm) maximum dip. Drape plastic over rope from outside Work Area so that a two foot long flap of plastic extends over rope into Work Area. Staple or wire plastic to itself 1 inch (25.4 mm) below rope at maximum 6 inches (152 mm) on centers to form a sheath over rope. Lift flap and seal to ceiling with duct tape or spray cement. Seal loop at bottom of flap with duct tape. Erect entire assembly so that it hangs vertically without a "shelf" upon which debris could collect.

E. Provide Pressure Differential System per Section 01513.

1. Clean housings and ducts of all overspray materials prior to erection of any Critical Barrier that will restrict access.

3.8 PREPARE AREA:

A. Scaffolding: If fixed scaffolding is to be used to provide access HEPA vacuum and wet clean area prior to scaffolding installation.

B. Remove all electrical and mechanical items, such as lighting fixtures, clocks, diffusers,

registers, escutcheon plates, etc. which cover any part of the surface to be worked on with the work.

C. Remove all general construction items such as cabinets, casework, door and window trim,

moldings, ceilings, trim, etc., which cover the surface of the work as required to prevent interference with the work. Clean and decontaminate all such materials, upon completion of all removal work.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 8

D. Clean all contaminated furniture, equipment, and or supplies with a HEPA filtered vacuum cleaner or by wet cleaning, as specified in Section 01712 Cleaning and Decontamination Procedures, prior to being moved or covered. All equipment furniture, etc. is to be deemed contaminated unless specifically declared as uncontaminated on the drawings or in writing by the Engineer/Owner’s Representative.

E. Clean All Surfaces In Work Area with a HEPA filtered vacuum or by wet wiping prior to the

installation of primary barrier.

F. Cleaning and Sealing Surfaces: After cleaning with water and a HEPA vacuum, surfaces of stationary objects should be covered with two layers of plastic sheeting. The sheeting should be secured with duct tape or an equivalent method to provide a tight seal around the object.

3.9 PRIMARY BARRIER:

A. Protect building and other surfaces in the Work Area from damage from water and high humidity or from contamination from asbestos-containing debris, slurry or high airborne fiber levels by covering with a primary barrier as described below. 1. Sheet Plastic: Protect surfaces in the Work Area with two (2) layers of plastic sheeting on

floor and walls, or as otherwise directed on the Contract Drawings or in writing by the Designer. Perform work in the following sequence. a. All seams in the sheeting should overlap, be staggered and not be located at corners

or wall-to-floor joints. b. Cover Floor of Work Area with 2 individual layers of clear polyethylene sheeting,

each at least 6 mil (0.15 mm) in thickness, turned up walls at least 12 inches (305 mm). Form a sharp right angle bend at junction of floor and wall so that there is no radius which could be stepped on causing the wall attachment to be pulled loose. Both spray-glue and duct tape all seams in floor covering. Locate seams in top layer six feet from, or at right angles to, seams in bottom layer. Install sheeting so that top layer can be removed independently of bottom layer.

c. Cover all walls in Work Area including "Critical Barrier" sheet plastic barriers with

one layer of polyethylene sheeting, at least 6 mil (0.15 mm) in thickness, mechanically supported and sealed with duct tape or spray-glue in the same manner as "Critical Barrier" sheet plastic barriers. Tape all joints including the joining with the floor covering with duct tape or as otherwise indicated on the Contract Documents or in writing by the Engineer/Owner’s Representative.

d. Elevator: Cover walls, floor and ceiling of elevator with 2 layers of 6 mil (0.15 mm)

polyethylene. Arrange entry to Work Area so that elevator door is in a positively pressurized space outside the clean room of the decontamination unit. At completion of work clean elevator as set forth in Section 01711. Refer to Section 01013 Summary of the Work for additional requirements for protection of elevator.

e. Stairs and Ramps: Do not cover stairs or ramps with unsecured sheet plastic.

Where stairs or ramps are covered with plastic, provide 3/4 inch (19.1 mm) exterior

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 9

grade plywood treads securely held in place, over plastic. Do not cover rungs or rails with any type of protective materials.

f. Repair of Damaged Polyethylene Sheeting: Remove and replace plastic sheeting

which has been damaged by removal operations or where seal has failed allowing water to seep between layers. Remove affected sheeting and wipe down entire area. Install new sheet plastic only when area is completely dry.

3.10 ISOLATION AREA:

A. Maintain isolation areas between the Work Area and adjacent building area:

B. Form isolation area by controlling access to the space in the same manner as a Work Area. Physically isolate the space from the Work Area and adjacent areas. Accomplish physical isolation by: 1. Installing critical barriers in unoccupied space.

2. Erecting a second Critical Barrier a minimum of 3 feet (1.0 m) away from Work Area.

3.11 STOP WORK:

A. If the Critical or Primary barrier falls or is breached in any manner stop asbestos removal work immediately and comply with Stop Work requirements of Section 01013 - Summary of Work - Asbestos Abatement. Do not start work until authorized in writing by the Engineer/Owner’s Representative.

3.12 EXTENSION OF WORK AREA:

A. Extension of Work Area: If the Critical Barrier is breached in any manner that could allow the passage of asbestos debris or airborne fibers, then add affected area to the Work Area, enclose it as required by this Section of the specification and decontaminate it as described in Section 01711 Project Decontamination.

3.13 SECONDARY BARRIER:

A. Secondary layer of plastic as a drop cloth to protect the primary layer from debris generated by the asbestos abatement work is specified in the appropriate work sections.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\16 - 01526S96 - Temp Enclosures - bkf.doc 01526 - 10

3.14 EXTERIOR ENCLOSURES: (As Applicable)

A. Construct exterior enclosures as a Critical Barrier as necessary to completely enclose the work. Fabricate from reinforced polyethylene sheeting and 2 inch x 4 inch (51mm X 102 mm) wood framework. Attach to existing building components or brace as necessary for lateral stability. Construct walls to meet all state and local regulations for construction of temporary buildings. Construct to resist a wind of 30 MPH (13.41 m/s), slope ceiling to permit drainage of rain water.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\17 - 01527S96 - Regulated Areas.doc 01527 - 1

SECTION 01527

REGULATED AREAS PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to work of this section.

1.2 RELATED WORK SPECIFIED ELSEWHERE:

A. Worker Protection: is specified in Section 01561 Worker Protection

B. Respiratory Protection: is specified in Section 01562 Respiratory Protection

1.3 DESCRIPTION OF WORK:

A. Work of this section consists of preparing a Regulated Area for work of the following specification sections only. Do not use procedures set forth in this section in connection with any other work. 1. Section 01529 Mini Enclosures and Glovebags

2. Section 01712 Cleaning and Decontamination Procedures

1.4 SUBMITTALS

A. Before the Start of Work: Submit the following to the Designer for review. Begin no work until these submittals are returned with Designer's action stamp indicating that the submittal is returned for unrestricted use or final-but-restricted use.

1. HEPA Filtered Vacuum Cleaners: Submit product data.

2. Signs: Submit samples of each type of sign to be used.

3. Warning Tape: Submit samples.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\17 - 01527S96 - Regulated Areas.doc 01527 - 2

PART 2 - EQUIPMENT 2.1 PRODUCTS

A. HEPA Filter Vacuum Cleaners:

1. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products which may be incorporated in the Work include, but are not limited to, the following:

Nilfisk of America, Inc. HEPA filtered 225 Great Valley Parkway Vacuums Malvern, PA 19355 (800) 645-3475

Minuteman International Minuteman 111 South Route 53 HEPA Vacuums Addison, IL 60101 (708) 627-6900

Pullman-Holt (White) Corp. HEPA Filtered PO Box 16647 Vacuums Tampa, FL 33617 (813) 645-3475

B. Plastic Sheet:

1. Plastic Sheet: A single polyethylene film in the largest sheet size possible to minimize

seams, 6.0 mil (0.15 mm) thick, clear, frosted, or black as indicated. PART 3 - EXECUTION 3.1 SECURING WORK AREA:

A. Secure work area from access by occupants, staff, users or trespassers of the building. Accomplish this where possible, by locking doors, windows, or other means of access to the area, by scheduling work for periods of time that the building in unoccupied, or by constructing temporary wood stud and plywood barriers.

3.2 DEMARCATION OF REGULATED AREA: NOTE: EFFECTIVE JUNE 1, 2016 Asbestos

Signage must comply with the GHS signage requirements per 29 CFR 1910.1001(j)(4)(ii)(A).

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\17 - 01527S96 - Regulated Areas.doc 01527 - 3

A. Demarcation. Demarcate the Regulated Area with a sheet plastic drop cloth, signs and barrier tape. Configure the regulated area in a manner that minimizes the number of persons within the area and protects persons outside the area from exposure to airborne concentrations of asbestos.

1. Drop Cloth: Cover floor in vicinity of Work Area and six (6) feet (1.82 meters) beyond,

with 6 mil (0.15 mm) polyethylene drop sheet. Where work is adjacent to wall, extend drop sheet up wall and secure at ceiling with duct tape. This drop sheet demarcates the boundary of the Regulated Area.

2. Signs: Post warning signs that carry the following legends in both English and Spanish:

a. First Sign: Provide warning signs at each locked door leading to the controlled area

reading as follows:

Legend Notation KEEP OUT 3 inch (76.2 mm )Block

b. Second Sign: Immediately inside the locked door and outside the controlled area

post an approximately 20 inch by 14 inch (508 mm x 356 mm) manufactured caution sign displaying the following legend with letter sizes and styles of a visibility required by 29 CFR 1926:

Legend:

DANGER

ASBESTOS

CANCER AND LUNG DISEASE HAZARD

AUTHORIZED PERSONNEL ONLY

RESPIRATORS AND PROTECTIVE CLOTHING ARE REQUIRED IN THIS AREA

3. Barrier Tape: Where the controlled area is in a large area such as on part of a boiler room

or open office area, delineate area with 3 inch (76.2 mm) wide polyethylene ribbon with the printed warning, "CAUTION ASBESTOS REMOVAL". Install this ribbon at between 3 and 4 feet (0.91 and 1.22 meters) above the floor.

3.3 SCHEDULING:

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\17 - 01527S96 - Regulated Areas.doc 01527 - 4

A. Work may be carried out during normal working hours in those areas which can be completely

secured by lockable doors from access by building occupants and staff, and which have HVAC equipment that can be shut down and locked off. Otherwise, work is to be carried out after building occupants and cleaning staff have left.

3.4 GENERAL PROCEDURES:

A. The following precautions and procedures have application to work of this section. Workers must exercise caution to avoid release of asbestos fibers into the air:

1. Setup and management of the controlled area is to be under the supervision of a OSHA

Competent Person as described in Section 01043 Project Coordination - Asbestos Abatement

. 2. Before start of work comply with requirement for worker protection in section 01561, and

respiratory protection in section 01562.

3. Do not allow eating, drinking, smoking, chewing tobacco or gum, or applying cosmetics in the Regulated Area.

4. Shut down any air handling equipment bringing air into or out of the Regulated Area.

5. Clean any existing dust or debris from the floor and walls, and other surface in the

immediate location of the work prior to commencing work by damp-mopping or by use of a High Efficiency Particulate Air (HEPA) filtered vacuum.

6. Cover floor in vicinity of Work Area and six (6) feet (1.82 meters) beyond, with 6 mil

(0.15 mm) polyethylene drop sheet. Where work is adjacent to wall, extend drop sheet up wall and secure at ceiling with duct tape. This drop sheet demarcates the boundary of the Regulated Area.

7. Seal all openings, supply and exhaust vents, and convectors within ten (10) feet (3.05

meters) of the Work Area with 6 mil (0.15 mm) polyethylene sheeting secured and completely sealed with duct tape.

8. Perform the work per the appropriate specification section while on plastic drop sheet.

9. Immediately remove any asbestos-containing debris which collects on the drop sheet either

by using a HEPA vacuum or by spraying with amended water or removal encapsulant, collecting with wet paper towels, placing in a disposal bag while still wet, and cleaning surface of plastic sheet with wet paper towels.

10. Complete the following at completion of work in an area before stepping off drop sheet

a. While standing on plastic sheet thoroughly HEPA vacuum ladder and any tools used

and pass to worker standing off sheet.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\17 - 01527S96 - Regulated Areas.doc 01527 - 5

b. Worker standing off the sheet HEPA vacuum thoroughly the worker standing on the

sheet.

c. Worker on the sheet thoroughly HEPA vacuum all surfaces of the plastic sheet, bags, and any other items on the sheet the workers feet.

11. If moving to the next Work Area in the same secured area: Worker on the drop sheet is to

don clean foot covers, placing each foot, in turn, off the sheet as the foot cover is put on. Remove clean foot covers at the next Work Area while standing on the sheet. Dispose of the used foot covers along with the plastic sheet at completion of work in that area. Do not reuse foot covers to move off the sheet.

12. If work day is complete or if next Work Area is in another secured area: all workers

remove paper suits turning them inside out while doing so. The person on the sheet steps with each foot off the sheet as the foot covers are removed.

13. Fold sheet and all its contents toward the center.

14. Place the sheet in a properly labeled disposal bag.

15. Neck down the bag and collapse it with the HEPA vacuum.

16. Twist the bag shut, bend over and seal with duct tape by wrapping around bag neck at least

3 times.

17. Clean all surfaces of the Work Area by use of a HEPA filter vacuum until no visible residue remains.

B. At completion of work all workers to complete decontamination procedures in accordance with

Section 01561 Worker Protection.

C. Remove respirators using the procedure in Section 01561 Worker Protection

END OF SECTION - 01527

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\17 - 01527S96 - Regulated Areas.doc 01527 - 6

This Page Intentionally Blank

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\18 - 01560S96 - Worker Protection - bkf.doc 01560 - 1

SECTION 01560

WORKER PROTECTION - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to work of this section.

1.2 DESCRIPTION OF WORK:

A. This section describes the equipment and procedures required for protecting workers against asbestos contamination and other workplace hazards except for respiratory protection.

1.3 RELATED WORK SPECIFIED ELSEWHERE:

A. Respiratory Protection: is specified in Section 01562. 1.4 WORKER TRAINING:

A. AHERA Accreditation: All workers are to be accredited as Abatement Workers as required by

the EPA Model Accreditation Plan (MAP) asbestos abatement worker training (40 CFR Part 763, Subpart E, Appendix C).

B. State and Local License: All workers are to be trained, certified and accredited as required by

state or local code or regulation. C. Training - Class I: Train in accordance with 29 CFR 1926.1101. Provide training for all workers

who will perform Class I operations that is the equivalent in curriculum, training method and length to the EPA Model Accreditation Plan (MAP) asbestos abatement worker training (40 CFR Part 763, Subpart E, Appendix C).

1.5 MEDICAL SURVEILLANCE:

A. Provide a medical surveillance program for all employees who are:

1. Engaged in Class I, II and III work for a combined total of 30 or more days per year or, a. For the purposes of this paragraph, any day in which a worker engages in Class II or

Class III work or a combination thereof for one hour or less (taking into account the entire time spent on the removal operation, including cleanup) and, while doing so, adheres fully to the work practices specified in the OSHA standard (29 CFR 1926.1101) is not counted.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\18 - 01560S96 - Worker Protection - bkf.doc 01560 - 2

2. are exposed at or above the permissible exposure limit or excursion limit or,

3. before an employee can be assigned to work requiring use of a respirator.

B. Provide a medical surveillance program and physician’s opinion before a respirator is assigned as required by 29 CFR 1910.134 and 29 CFR 1926.103(e)(10) .

C. Provide medical examination that as a minimum meets OSHA requirements as set forth in 29

CFR 1926.1101. In addition, require that the physician provide an evaluation of the individual's ability to work in environments capable of producing heat stress in the worker.

1.6 SUBMITTALS:

A. Before Start of Work: Submit the following to the CM for review. Do not start work until these submittals are returned with Designer's action stamp indicating that the submittal is returned for unrestricted use. 1. AHERA Accreditation: Submit copies of certificates from an EPA-approved AHERA

Abatement Workers course for each worker as evidence that each asbestos Abatement Worker is accredited as required by the EPA Interim Final Model Accreditation Plan (MAP) asbestos abatement worker training (40 CFR Part 763, Subpart E, Appendix C).

2. State and Local License: Submit evidence that all workers have been trained, certified

and accredited as required by state or local code or regulation.

3. Certificate Worker Acknowledgment: Submit an original signed copy of the Certificate of Worker's Acknowledgment found at the end of this section, for each worker who is to be at the job site or enter the Work Area.

4. Report from Medical Examination: conducted within last 12 months as part of

compliance with OSHA medical surveillance requirements for each worker who is to enter the Work Area. Submit, at a minimum, for each worker the following:

a. Name and Social Security Number

b. The physician's written opinion as to whether the employee has any detected

medical conditions that would place the employee at an increased risk of material health impairment from exposure to asbestos;

c. Any recommended limitations on the employee or on the use of personal protective

equipment such as respirators; and

d. A statement that the employee has been informed by the physician of the results of the medical examination and of any medical conditions that may result from asbestos exposure.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\18 - 01560S96 - Worker Protection - bkf.doc 01560 - 3

e. A statement that the employee has been informed by the physician of the increased risk of lung cancer attributable to the combined effect of smoking and asbestos exposure (29 CFR 1926.1101(m)).

f. A legible typed version of the physician’s name, the physician’s signature, and date

of examination.

5. Notarized Certifications: Submit certification signed by an officer of the abatement contracting firm and notarized that exposure measurements, medical surveillance, and worker training records are being kept in conformance with 29 CFR 1926.

PART 2 - EQUIPMENT 2.1 PROTECTIVE CLOTHING:

A. General. Provide and require the use of protective clothing, such as coveralls or similar whole-body clothing, head coverings, gloves, and foot coverings for any employee exposed to airborne concentrations of asbestos that exceed the TWA and/or excursion limit prescribed by 29 CFR 1926.1101 or for which a required negative exposure assessment is not produced, and for any employee performing Class I operations which involve the removal of over 25 linear or 10 square feet (7.5 linear meters or 3 square meters ) of TSI or surfacing ACM or PACM.

B. Coveralls: Provide disposable full-body coveralls and disposable head covers, and require that

they be worn by all workers in the Work Area. Provide a sufficient number for all required changes, for all workers in the Work Area.

C. Additional Protective Clothing: Provide each worker with the protective clothing as required by

Federal State and local regulations. This includes, but is not necessary limited by Hardhats, Cold weather gear, Glove, boots and goggles.

2.2 ADDITIONAL PROTECTIVE EQUIPMENT:

A. Disposable coveralls, head covers, and footwear covers shall be provided by the Contractor for the

Owner, CM, Project Administrator, and other authorized representatives who may inspect the job site. Provide six (6) complete coveralls per day.

PART 3 - EXECUTION 3.1 GENERAL:

A. Provide worker protection as required by the most stringent OSHA and/or EPA standards applicable to the work. The following procedures are minimums to be adhered to regardless of fiber count in the Work Area.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\18 - 01560S96 - Worker Protection - bkf.doc 01560 - 4

B. Each time Work Area is entered remove all street clothes in the Changing Room of the Personnel Decontamination Unit and put on new disposable coverall, new head cover, and a clean respirator. Proceed through shower room to equipment room and put on work boots.

3.2 DECONTAMINATION PROCEDURES:

A. Require all workers to adhere to the following personal decontamination procedures whenever they leave the Work Area: 1. Type C Supplied Air or Powered Air-Purifying Respirators: Require that all workers use

the following decontamination procedure as a minimum requirement whenever leaving the Work Area:

a. When exiting area, remove disposable coveralls, disposable head covers, and

disposable footwear covers or boots in the equipment room.

b. Still wearing respirators, proceed to showers. Showering is mandatory. Care must be taken to follow reasonable procedures in removing the respirator to avoid asbestos fibers while showering. The following procedure is required as a minimum:

c. Thoroughly wet body including hair and face. If using a Powered Air-Purifying

Respirator (PAPR) hold blower unit above head to keep canisters dry.

d. With respirator still in place thoroughly wash body, hair, respirator face piece, and all parts of the respirator except the blower unit and battery pack on a PAPR. Pay particular attention to seal between face and respirator and under straps.

e. Take a deep breath, hold it and/or exhale slowly, completely wet hair, face, and

respirator. While still holding breath, remove respirator and hold it away from face before starting to breath.

f. Carefully wash facepiece of respirator inside and out.

2. If using PAPR: shut down in the following sequence, first cap inlets to filter cartridges,

then turn off blower unit (this sequence will help keep debris which has collected on the inlet side of filter from dislodging and contaminating the outside of the unit). Thoroughly wash blower unit and hoses. Carefully wash battery pack with wet rag. Be extremely cautious of getting water in battery pack as this will short out and destroy battery.

a. Shower completely with soap and water.

b. Rinse thoroughly.

c. Rinse shower room walls and floor prior to exit.

d. Proceed from shower to Changing Room and change into street clothes or into new

disposable work items.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\18 - 01560S96 - Worker Protection - bkf.doc 01560 - 5

3. Air Purifying-Negative Pressure Respirators: Require that all workers use the following decontamination procedure as a minimum requirement whenever leaving the Work Area with a half or full face cartridge type respirator: a. When exiting area, remove disposable coveralls, disposable headcovers, and

disposable footwear covers or boots in the Equipment Room.

b. Still wearing respirators, proceed to showers. Showering is mandatory. Care must be taken to follow reasonable procedures in removing the respirator and filters to avoid asbestos fibers while showering. The following procedure is required as a minimum:

c. Thoroughly wet body from neck down.

d. Wet hair as thoroughly as possible without wetting the respirator filter if using an air purifying type respirator.

e. Take a deep breath, hold it and/or exhale slowly, complete wetting of hair,

thoroughly wetting face, respirator and filter (air purifying respirator). While still holding breath, remove respirator and hold it away from face before starting to breath.

f. Dispose of wet filters from air purifying respirator.

g. Carefully wash facepiece of respirator inside and out.

h. Shower completely with soap and water.

i. Rinse thoroughly.

j. Rinse shower room walls and floor prior to exit.

k. Proceed from shower to Changing Room and change into street clothes or into new

disposable work items. B. Within Work Area:

1. Require that workers NOT eat, drink, smoke, chew tobacco or gum, or apply cosmetics in

the Work Area. To eat, chew, drink or smoke, workers shall follow the procedure described above, then dress in street clothes before entering the non-Work Areas of the building.

3.3 CERTIFICATE OF WORKER'S ACKNOWLEDGEMENT: Following this section is a Certificate of Worker Training. After each worker has been included in the Contractor's Respiratory Protection Program, completed the training program and medical examination, secure a fully executed copy of this form.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\18 - 01560S96 - Worker Protection - bkf.doc 01560 - 6

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\18 - 01560S96 - Worker Protection - bkf.doc 01560 - 7

CERTIFICATE OF WORKER'S ACKNOWLEDGEMENT

PROJECT NAME________________________________ DATE__________________ PROJECT ADDRESS____________________________________________________ CONTRACTOR'S NAME__________________________________________________ WORKING WITH ASBESTOS CAN BE DANGEROUS. INHALING ASBESTOS FIBERS HAS BEEN LINKED WITH VARIOUS TYPES OF CANCER. IF YOU SMOKE AND INHALE ASBESTOS FIBERS THE CHANCE THAT YOU WILL DEVELOP LUNG CANCER IS GREATER THAN THAT OF THE NON-SMOKING PUBLIC. Your employer's contract with the Owner for the above project requires that: You be supplied with the proper respirator and be trained in its use. You be trained in safe work practices and in the use of the equipment found on the job. You receive a medical examination. These things are to have been done at no cost to you. RESPIRATORY PROTECTION: You must have been trained in the proper use of respirators, and informed of the type respirator to be used on the above referenced project. You must be given a copy of the written respiratory protection manual issued by your employer. You must be equipped at no cost with the respirator to be used on the above project. TRAINING COURSE: You must have been trained in the dangers inherent in handling asbestos and breathing asbestos dust and in proper work procedures and personal and area protective measures. This training must have been the equivalent in curriculum, training method and length to the EPA Model Accreditation Plan (MAP) asbestos abatement worker training (40 CFR Part 763, Subpart E, Appendix C). MEDICAL EXAMINATION: You must have had a medical examination within the past 12 months at no cost to you. This examination must have included: health history, pulmonary function tests and may have included an evaluation of a chest x-ray. By signing this document you are acknowledging only that the Owner of the building you are about to work in has advised you of your rights to training and protection relative to your employer. Signature____________________Social Security No___________________ Printed Name__________________Witness______________________________

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 1

SECTION 01562

RESPIRATORY PROTECTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to work of this section.

1.2 DESCRIPTION OF WORK:

A. Instruct and train each worker involved in asbestos abatement or maintenance and repair of friable asbestos-containing materials (ACM) in proper respiratory use and require that each worker always wear a respirator, properly fitted on the face in the Work Area from the start of any operation which may cause airborne asbestos fibers until the Work Area is completely decontaminated. Use respiratory protection appropriate for the fiber level encountered in the work place or as required for other toxic or oxygen-deficient situations encountered.

1.3 DEFINITIONS:

A. "Negative Pressure Respirator": A respirator in which the air pressure inside the respiratory-inlet covering is positive during exhalation in relation to the air pressure of the outside atmosphere and negative during inhalation in relation to the air pressure of the outside atmosphere.

B. "Protection Factor": The ratio of the ambient concentration of an airborne substance to the

concentration of the substance inside the respirator at the breathing zone of the wearer. The protection factor is a measure of the degree of protection provided by a respirator to the wearer.

C. "Respirator": A device designed to protect the wearer from the inhalation of harmful

atmospheres. 1.4 STANDARDS:

A. Except to the extent that more stringent requirements are written directly into the Contract

Documents, the latest edition of the following regulations and standards have the same force and effect (and are made a part of the Contract Documents by reference) as if copied directly into the Contract Documents, or as if published copies were bound herewith. Where there is a conflict in requirements set forth in these regulations and standards, meet the more stringent requirement. 1. OSHA - U.S. Department of Labor Occupational Safety and Health Administration,

Safety and Health Standards Section 29 CFR 1910.1001, Section 1910.134, and Section 29 CFR 1926.1101.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 2

2. CGA - Compressed Gas Association, Inc., New York, Pamphlet G-7, "Compressed Air for Human Respiration", and Specification G-7.1 "Commodity Specifica-tion for Air".

3. CSA - Canadian Standard Association, Rexdal, Ontario, Standard Z180.1, "Compressed Breathing Air".

4. ANSI - American National Standard Practices for Respiratory Protection, ANSI Z88.2.

5. NIOSH - National Institute for Occupational Safety and Health - NIOSH Respirator Decision Logic (May 1987) DHHS/NIOSH Publication

No. 87-108; - NIOSH/EPA, A Guide to Respiratory Protection for the Asbestos

Abatement Industry EPA-560-OPTS-86-001 (September 1986); - 42 CFR 84, NIOSH Standard for Certification of Non-Powered Air Purifying

Respirator filters; - 30 CFR 11, NIOSH - Certification of Respirators

6. MSHA - Mine Safety and Health Administration 1.5 SUBMITTALS:

A. Before Start of Work submit the following to the Engineer/Owner’s Representative for review. Do not begin work until these submittals are returned with the Designer's action stamp indicating that the submittal is returned for unrestricted use. 1. Product Data: Submit manufacturer's product information for each component used,

including NIOSH and MSHA Certifications for each component in an assembly and/or for entire assembly.

2. System Diagram: When a supplied air respiratory system is required by the work, submit

drawing showing assembly of components into a complete supplied air respiratory system. Include diagram showing location of compressor, filter banks, backup air supply tanks, hose line connections in Work Area(s), routing of air lines to Work Area(s) from compressor.

3. Operating Instruction: Submit complete operating and maintenance instructions for all

components and systems as a whole. Submittal is to be in bound manual form suitable for field use.

4. Respiratory Protection Program: Submit Contractor's written respiratory protection

program manual as required by OSHA 1926.1101, in accordance with 1910.134.

5. Initial Exposure Assessment: Submit level of respiratory protection intended for each operation required by the project. Base this selection on an Initial Exposure Assessment as required by OSHA 29 CFR 1926.1101. Submit information to support this "Initial Exposure Assessment on the form included at the end of this Section. a. Submit data from exposure monitoring for the PEL and EL from prior asbestos jobs

within 12 months; b. Submit monitoring and analysis that were performed in compliance with the OSHA

asbestos standard in effect; c. Submit data that was obtained under workplace conditions "closely resembling"

those that will exist during the Work;

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 3

d. Submit data from past asbestos jobs where the type of asbestos abatement and other work, material, control methods, work practices, and environmental conditions closely resemble those that will exist during the Work;

e. Submit exposure date from prior asbestos jobs where the work that was conducted by employees whose training and experience are no more extensive than that of employees performing the current job;

f. Based on the exposure data from the previous asbestos jobs, select respiratory protection for the Work that will, to a high degree of certainty, prevent worker exposures (inside the respirator) that exceed the Permissible Exposure Limits (PEL) set forth in this Section of the specifications.

6. Resume information: Submit resume and information on training for individual

monitoring the operation of supplied air respiratory systems. Submit training certifications where applicable.

1.6 AIR QUALITY FOR SUPPLIED AIR RESPIRATORY SYSTEMS:

A. Provide air used for breathing in supplied air respiratory systems that meets or exceeds standards set for C.G.A. type 1 (Gaseous Air) Grade D:

1.7 ALLOWABLE CONTAMINANTS:

A. Supply air that has an asbestos concentration no greater than outside ambient conditions.

B. Supply air that meets the level of contaminants allowed according to the air quality standard specified.

C. The following table sets forth the quantity of any given contaminant allowed according to the

referenced standards:

| CGA | CSA | Type 1 (Gaseous Air) | Z180.1

CONTAMINANT | Grade D Grade E Grade H |

Carbon Monoxide, PPM/v 20 10 5 5

Carbon Dioxide, PPM/v 1000 500 500 500

Condensed Hydrocarbons, 5 5 1 mg./cu. meter

Gaseous Hydrocarbons - 10 25

as methane, PPM/v Water Vapor - PPM/v (1) (1) (1) 27

dewpoint -50F -50F -50F -63F

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 4

Objectionable Odors None None None None

Nitrogen Dioxide, PPM/v - - 0.5 0.2

Nitrous Oxide, PPM/v - - - 5

Sulfur Dioxide, PPM/v - - 0.5 -

Halogenated solvents, PPM/v - - 1 - Other gaseous contaminants - - - (2)

Inorganic particulates, - - - 1

mg./cu. meter

- Indicates that the standard shows no limiting characteristics

(1) The CGA standards do not indicate a specific moisture limit when the ambient temperature

is above freezing. However, since a moisture content no greater than a -50 Degrees Fahrenheit (-45.56 Degrees Celsius) dewpoint (66 PPM/v) is necessary for carbon monoxide elimination, the CO limits could not be met unless the air were dried to a -50 Degrees Fahrenheit (-45.56 Degrees Celsius) dewpoint or better.

(2) Maximum allowable content of trichlorotrifluoroethane, dichlorodifluoromethane, and

chlorodifluoromethane is 2 PPM/v for each. Unlisted contaminants shall not exceed one-tenth of the Threshold Limit Values (TLV's) for Chemical Substances in Workroom air adopted by the American Conference of Governmental Industrial Hygienists (ACGIH).

1.8 DELIVERY:

A. Deliver replacement parts, etc., not otherwise labeled by NIOSH or MSHA to job site in manufacturer's containers.

PART 2 - EQUIPMENT 2.1 AIR PURIFYING RESPIRATORS

A. Respirator Bodies: Provide half face or full face type respirators. Equip full face respirators with a nose cup or other anti-fogging device as would be appropriate for use in air temperatures less than 32 degrees Fahrenheit (0 degrees Celsius).

B. Filter Cartridges: Provide, at a minimum, HEPA type filters labeled with NIOSH and MSHA

Certification for "Radionuclides, Radon Daughters, Dust, Fumes, Mists including Asbestos-Containing Dusts and Mists" and color coded in accordance with 42 CFR Part 84 and ANSI Z228.2. Also, additional cartridge sections may be added, if required, for solvents, etc., in use. In this case, provide cartridges that have each section of the combination canister labeled with the appropriate color code and NIOSH/MSHA Certification.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 5

C. Non-permitted respirators. Do not use single use, disposable or quarter face respirators. 2.2 SUPPLIED AIR RESPIRATOR SYSTEMS:

A. Provide equipment capable of producing air of the quality and volume required by the above reference standards applied to the job site conditions and crew size. Comply with provisions of this specification if more stringent than the governing standard.

B. Facepiece and Hose: Provide full facepiece and hose by same manufacturer that has been

certified by NIOSH/MSHA as an approved Type "C" respirator assembly operating in pressure demand mode with a positive pressure facepiece.

C. Auxiliary backup system: In atmospheres which contain sufficient oxygen (greater than or

equal to 19.5 percent oxygen) provide a pressure-demand full facepiece supplied air respirator equipped with an emergency back up HEPA filter.

D. Escape air supply: In atmospheres which are oxygen deficient (less than 19.5 percent oxygen)

provide a pressure-demand full facepiece supplied air respirator incorporating an auxiliary self-contained breathing apparatus (SCBA) which automatically maintains an uninterrupted air supply in pressure demand mode with a positive pressure face piece.

E. Backup air supply: Provide a reservoir of compressed air located outside the Work Area which

will automatically maintain a continuous uninterruptable source of air automatically available to each connected facepiece and hose assembly in the event of compressor shut-down, contamination of air delivered by compressor, power loss or other failure. Provide sufficient capacity in the back-up air supply to allow a minimum escape time of one-half hour times the number of connections available to the Work Area. Air requirement at each connection is the air requirement of the respirators in use plus the air requirement of an average-sized adult male engaged in moderately strenuous activity.

F. Warning device: Provide a warning device that will operate independently of the building's

power supply. Locate so that alarm is clearly audible above the noise level produced by equipment and work procedures in use, in all parts of the Work Area and at the compressor. Connect alarm to warn of: 1. Compressor shut down or other fault requiring use of backup air supply 2. Carbon Monoxide (CO) levels in excess of 5 PPM/V

G. Carbon Monoxide (CO) Monitor: Continuously monitor and record on a strip chart recorder

Carbon Monoxide (CO) levels. Place monitors in the air line between compressor and back-up air supply and between backup air supply and workers. Connect monitors so that they also sound an alarm as specified under "Warning Devices".

H. Compressor Shut Down: Interconnect monitors, alarms and compressor so that compressor is

automatically shut down and the alarms sound if any of the following occur: 1. Carbon Monoxide (CO) concentrations exceed 5 PPM/v in the air line between the filter

bank and backup air supply 2. Compressor temperature exceeds normal operating range

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 6

I. Compressor Motor: Provide a compressor driven by an electric motor. Do not use a gas or diesel engine to drive compressor. Insure that electrical supply available at the work site is adequate to energize motor.

J. Compressor Location: Locate compressor outside of building in location that will not impede

access to the building, and that will not cause a nuisance by virtue of noise or fumes to occupied portions of the building.

K. Air Intake: Locate air intake remotely from any source of automobile exhaust or any exhaust

from engines, motors, auxiliary generator or buildings.

L. After-Cooler: Provide an after-cooler at entry to filter system which is capable of reducing temperatures to outside ambient air temperatures.

M. Self Contained Breathing Apparatus (SCBA): Configure system to permit the recharging of

hour 2260 PSI (15.58 MPa) SCBA cylinders. PART 3 - EXECUTION 3.1 GENERAL:

A. Respiratory Protection Program: Comply with ANSI Z88.2 "Practices for Respiratory Protection" and OSHA 29 CFR 1910.314 and 1926.103.

B. Require that respirators be used in the following circumstances:

1. During all Class I asbestos jobs. 2. During all Class II work where the ACM is not removed in a substantially intact state, 3. During all Class II and III work which is not performed using wet methods. 4. During all Class II and III asbestos jobs where the employer does not produce a "negative

exposure assessment". 5. During all Class III jobs where TSI or surfacing ACM or PACM is being disturbed. 6. During all Class IV work performed within regulated areas where employees performing

other work are required to wear respirators. 7. During all work covered by this section where employees are exposed above the OSHA

PEL (TWA, or excursion limit). 8. In emergencies. During emergencies where the airborne asbestos fiber concentration is not

known, a self-contained breathing apparatus (SCBA) must be used.

C. Require that respiratory protection be used at all times that there is any possibility of disturbance of ACM whether intentional or accidental.

D. Require that a respirator be worn by anyone in a Work Area at all times, regardless of activity,

during a period that starts with any operation which could cause airborne fibers until the area has been cleared for re-occupancy in accordance with Section 01711.

E. Regardless of Airborne Fiber Levels: Require that the minimum level of respiratory protection

used be half-face air-purifying respirators with high efficiency filters.

F. Do not allow the use of single-use, disposable, or quarter-face respirators for any purpose.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 7

3.2 FIT TESTING:

A. Initial Fitting: Provide initial fitting of respiratory protection during a respiratory protection

course of training set up and administered by an individual qualified to do fit testing. Fit types and sizes of respirator to be actually worn by each individual. Allow an individual to use only those respirators for which training and fit testing has been provided.

B. Upon Each Wearing: Require that each time an air-purifying respirator is put on it be checked

for fit with a positive and negative pressure fit test in accordance with the manufacturer's instructions or ANSI Z88.2.

3.3 TYPE OF RESPIRATORY PROTECTION REQUIRED:

A. General: After reducing airborne asbestos levels to the lowest feasible level with engineering

controls and work practices, provide respiratory protection as necessary to ensure that workers are not exposed to an airborne concentration of asbestos in excess of the Specified Permissible Exposure Limits (SPEL) set forth in this Section.

B. Level of Respiratory Protection: Determine the proper level of respiratory protection by

dividing the expected or actual airborne fiber count in the Work Area by the "protection factors" given below. The level of respiratory protection which supplies an airborne fiber level inside the respirator, at the breathing zone of the wearer, at or below the Specified Permissible Exposure Limits (PEL) set forth in this Section is the minimum level of protection allowed.

C. Specific Respiratory Protection Requirements: Provide respiratory protection as indicated

below as a minimum requirement: 1. Half-face Negative Pressure Air-Purifying Respirators: Provide half-face negative

pressure air-purifying respirators during installation of Critical or Primary Barriers or other activities where there has been an Initial Exposure Assessment that has determined that airborne asbestos fiber levels will not exceed 0.1 fiber per cubic centimeter (0.1 f/cc). Provide a PAPR where a half-face negative pressure air-purifying respirator is allowed to any worker who so requests.

2. Powered Air-Purifying Respirators (PAPR): Provide powered air-purifying respirators

(PAPR) during removal of asbestos-containing thermal system insulation (TSI) or surfacing material where there has been an Initial Exposure Assessment that has determined that airborne asbestos fiber levels will not exceed 1.0 fiber per cubic centimeter (1.0 f/cc).

3. Type "C" Supplied-air respirators: full facepiece pressure demand supplied air

respirators are to be used by all workers engaged in the removal of thermal system insulation (TSI) or surfacing materials, or demolition of pipes, structures, or equipment covered or insulated with asbestos, or in the removal or demolition of asbestos insulation or coverings, or any other activity which results in or may result in airborne asbestos fiber levels above 1.0 fibers per cubic centimeter (1.0 f/cc).

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 8

D. Provide a full facepiece supplied air respirator operated in the pressure demand mode equipped with an auxiliary positive pressure self-contained breathing apparatus for all workers within a regulated area where Class I work is being performed and for which an initial exposure assessment has not been produced. After an initial exposure assessment is made, use the level of respiratory protection required by that assessment and requirements of this specification and the OSHA Asbestos Construction Standard 29 CFR 1926.1101.

3.4 SPECIFIED PERMISSIBLE EXPOSURE LIMITS (SPEL):

A. Specified Permissible Exposure Limits (SPEL): Ensure that no worker is exposed to an

airborne concentration of asbestos in excess of the Time-Weighted Average (TWA) limit, and Excursion Limit (EL) set forth below.

1. Time Weighted Average (TWA) limit - Concentration of airborne asbestos fibers to

which any worker may be exposed as an eight (8) hour time-weighted average (TWA) shall not exceed the following. a. 0.1 fibers per cubic centimeter

2. Excursion Limit (EL) - Concentration of airborne asbestos fibers to which any worker

may be exposed as averaged over a sampling period of thirty (30) minutes shall not exceed the following.

a. 1.0 fibers per cubic centimeter

B. Fibers: For purposes of this section, fibers are defined as all fibers regardless of composition as

counted in the OSHA Reference Method (ORM), or NIOSH 7400 procedure. 3.5 RESPIRATORY PROTECTION FACTOR:

A. Respirator Type Protection Factor

1. Air purifying: 10

Negative pressure respirator High efficiency filter Half facepiece

2. Air purifying: 50

Negative pressure respirator High efficiency filter Full facepiece

3. Powered Air Purifying (PAPR): 50

Positive pressure respirator High efficiency filter Half facepiece

4. Powered Air Purifying (PAPR): 1,000

Positive pressure respirator High efficiency filter

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 9

Full facepiece 5. Supplied air: 1,000

Positive pressure respirator Pressure demand or other positive pressure mode Full facepiece Equipped with an auxiliary HEPA cartridge or positive pressure Self-contained breathing apparatus (SCBA) for escape

3.6 AIR PURIFYING RESPIRATORS:

A. Negative pressure - half or full face mask: Supply a sufficient quantity of respirator filters approved for asbestos, so that workers can change filters during the work day. Require that respirators be wet-rinsed, and filters discarded, each time a worker leaves the Work Area. Require that new filters be installed each time a worker re-enters the Work Area. Store respirators and filters at the job site in the changing room and protect totally from exposure to asbestos prior to their use.

B. Powered air purifying - half or full face mask: Supply a sufficient quantity of high efficiency

respirator filters approved for asbestos so that workers can change filters at any time that flow through the facepiece decreases to the level at which the manufacturer recommends filter replacement. Require that regardless of flow, filter cartridges be replaced after 40 hours of use. Require that HEPA elements in filter cartridges be protected from wetting during showering. Require entire exterior housing of respirator, including blower unit, filter cartridges, hoses, battery pack, face mask, belt, and cords, be washed each time a worker leaves the Work Area. Caution should be used to avoid shorting battery pack during washing. Provide an extra battery pack for each respirator so that one can be charging while one is in use.

3.7 SUPPLIED AIR RESPIRATOR:

A. Air Systems Monitor: Continuously monitor the air system operation including compressor operation, filter system operation, backup air capacity and all warning and monitoring devices at all times that system is in operation. Assign an individual, trained by manufacturer of the equipment in use or by a Certified Industrial Hygienist, in the operation and maintenance of the system to provide this monitoring. Assign no other duties to this individual which will take him away from monitoring the air system.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\19 - 01562S96 - Respirtory Protection - bkf.doc 01562 - 10

INITIAL EXPOSURE ASSESSMENT Project No: Date: Project Name: Facility: Work Area(s): Reference Job: Description of Work: Asbestos Containing Materials Asbestos/Type Percentage

Personal Monitoring Level Respirator Comments Task High Low Average Worn Prep / Set up Removal of Surface Trt Removal of TSI Removal of Misc Mat. Bag Out Clean Up Other Experience Level of Work Force Reference Job: Description of Work: Asbestos Containing Materials Asbestos/Type Percentage

Personal Monitoring Level Respirator Comments Task High Low Average Worn Prep / Set up Removal of Surface Trt Removal of TSI Removal of Misc Mat. Bag Out Clean Up Other Experience Level of Work Force Expected Conditions of This Job Task Anticipated Level Respirator Comments Prep / Set up f/cc Removal of Surface Trt f/cc Removal of TSI f/cc Removal of Misc Mat. f/cc Bag Out f/cc Clean Up f/cc Other f/cc Experience Level of Work Force

01563 - 1 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

SECTION 01563

DECONTAMINATION UNITS PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification sections, apply to work of this section.

1.2 DESCRIPTION OF WORK:

A. Provide separate Personnel and Equipment Decontamination facilities. Require that the Personnel Decontamination Unit be the only means of ingress and egress for the Work Area. Require that all materials exit the Work Area through the Equipment Decontamination Unit.

1.3 RELATED WORK SPECIFIED ELSEWHERE:

A. Refer to Section 01503 Temporary Facilities - Asbestos Abatement for electrical requirements and requirements relative to connection of decontamination facilities to building systems such as water, sewer, and electrical.

1.4 SUBMITTALS

A. Before the Start of Work: Submit the following to the Engineer/Owner’s Representative for review. Do not begin work until these submittals are returned with Designer's action stamp indicating that the submittal is returned for unrestricted use or final-but-restricted use.

1. Personnel Decontamination Unit: Provide shop drawing showing location and assembly of

personnel decontamination units.

2. Equipment Decontamination Unit: Provide shop drawing showing location and assembly of equipment decontamination units.

3. Shower Pan: Provide shop drawing.

4. Shower Walls: Provide product data.

5. Shower Head and Controls: Provide product data.

6. Filters: Provide product data and shop drawing of installation on decontamination unit.

01563 - 2 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

7. Hose Bib: Provide product data.

8. Shower Stall: for Wash Down Station provide product data and shop drawing showing and modifications.

9. Lumber: Provide product data on fire resistance treatment.

10. Sump Pump: Provide product data.

91. Signs: Submit samples of signs to be used.

PART 2 - PRODUCTS 2.1 MATERIALS

A. Polyethylene Sheet: A single polyethylene film in the largest sheet size possible to minimize seams, 6.0 mil (0.15 mm) thick, clear, frosted, or black as indicated.

B. Reinforced Polyethylene Sheet: Where plastic sheet is the only separation between the Work

Area and building exterior, provide translucent, nylon reinforced, laminated, flame resistant, polyethylene film that conforms to requirements set forth by the National Fire Protection Association Standard 701, Small Scale Fire Test for Flame-resistant Textiles and Films. Provide largest size possible to minimize seams, 6.0 mil (0.15 mm) thick frosted or black as indicated.

C. Duct Tape: Provide duct tape in 2 inch or 3 inch (51mm or 76 mm ) widths as indicated, with an

adhesive which is formulated to stick aggressively to sheet polyethylene.

D. Spray Adhesive: Provide spray adhesive in aerosol cans which is specifically formulated to stick tenaciously to sheet polyethylene.

E. Shower Pan: Provide one piece waterproof shower pan 4 feet x 8 feet x 6 inches deep (102 mm X

204 mm x 152 mm deep). Fabricate from seamless fiberglass minimum 1/16 inch (1.59 mm) thick reinforced with wood, 18 ga. stainless or galvanized steel with welded seems, copper or lead with soldered seams, or equivalent.

F. Shower Walls: Provide 8 feet (2.44 m) long by approximately 7 feet (2.13 m) high walls

fabricated from rigid, impervious, waterproof material, either corrugated fiberglass roofing or equivalent. Structurally support as necessary for stability.

G. Shower Head and Controls: Provide a factory-made shower head producing a spray of water

which can be adjusted for spray size and intensity. Feed shower with water mixed from hot and cold supply lines. Arrange so that control of water temperature, flow rate, and shut off is from inside shower without outside aid.

H. Filters: Provide cascaded filter units on drain lines from showers or any other water source

carrying asbestos-contaminated water from the Work Area. Provide units with disposable filter

01563 - 3 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

elements as indicated below. Connect so that discharged water passes primary filter and output of primary filter passes through secondary filter. 1. Primary Filter - Passes particles 20 microns and smaller 2. Secondary Filter - Passes particles 5 microns and smaller

I. Hose Bib: Provide heavy bronze angle type with wheel handle, vacuum breaker, and 3/4 inch

(19.05 mm) National Standard male hose outlet.

J. Lumber: Provide kiln dried lumber of any grade or species.

K. Sump Pump: Provide totally submersible waterproof sump pump with integral float switch. Provide unit sized to pump 2 times the flow capacity of all showers or hoses supplying water to the sump, through the filters specified herein when they are loaded to the extent that replacement is required. Provide unit capable of pumping debris, sand, plaster or other materials washed off during decontamination procedures without damage to mechanism of pump. Adjust float switch so that a minimum of 3 inch (76 mm) remains between top of liquid and top of sump pan.

PART 3 - EXECUTION 3.1 PERSONNEL DECONTAMINATION UNIT:

A. Provide a Personnel Decontamination Unit consisting of a serial arrangement of connected

rooms or spaces, Changing Room, Drying Room, Shower Room, Equipment Room. Require all persons without exception to pass through this Decontamination Unit for entry into and exiting from the Work Area for any purpose. Do not allow parallel routes for entry or exit. Do not remove equipment or materials through Personnel Decontamination Unit. Provide temporary lighting within Decontamination Units as necessary to reach a lighting level of 100 foot candles (1076 lumens / sq meter).

B. Changing Room (clean room): Provide a room that is physically and visually separated from

the rest of the building for the purpose of changing into protective clothing.

1. Construct using polyethylene sheeting, at least 6 mil (0.15 mm) in thickness, to provide an airtight seal between the Changing Room and the rest of the building.

2. Locate so that access to Work Area from Changing Room is through Shower Room.

3. Separate Changing Room from the building by a sheet plastic flapped doorway.

4. Require workers to remove all street clothes in this room, dress in clean, disposable

coveralls, and don respiratory protection equipment. Do not allow asbestos-contaminated items to enter this room. Require Workers to enter this room either from outside the structure dressed in street clothes, or naked from the showers.

5. An existing room may be utilized as the Changing Room if it is suitably located and of a

configuration whereby workers may enter the Changing Room directly from the Shower

01563 - 4 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

Room. Protect all surfaces of room with sheet plastic as set forth in Section 01526 Temporary Enclosures. Authorization for this must be obtained from the Designer in writing prior to start of construction. Submit written request in accordance with Section 01632 "Substitutions" detailing layout and protective measures proposed.

6. Maintain floor of changing room dry and clean at all times. Do not allow overflow water

from shower to wet floor in changing room.

7. Damp wipe all surfaces twice after each shift change with a disinfectant solution.

8. Provide posted information for all emergency phone numbers and procedures.

9. Provide 1 storage locker per employee. 10. Provide all other components indicated on the contract drawings.

C. Airlock: Provide an airlock between Drying Room and Changing Room. This is a transit area

for workers.

1. Separate this room from Drying Room and Changing Room by sheet plastic flapped doorways.

2. Separate this room from the rest of the building with airtight walls fabricated of 6 mil (0.15

mm) polyethylene.

3. Separate this room from the Drying and Changing Rooms with airtight walls fabricated of 6 mil (0.15 mm) polyethylene.

D. Drying Room: Provide a drying room as an airlock and a place for workers to dry after

showering.

1. Construct room by providing a pan continuous with or draining to Shower Room pan. Install a freely draining wooden or non-skid metal floor in pan at elevation of top of pan.

2. Separate this room from the rest of the building with airtight walls fabricated of 6 mil (0.15

mm) polyethylene.

3. Separate this room from the Changing Room and Shower Room with airtight walls fabricated of 6 mil (0.15 mm) polyethylene.

4. Separate from Changing Room by a sheet plastic flapped doorway.

5. Provide a continuously adequate supply of disposable bath towels.

E. Shower Room: Provide a completely watertight operational shower to be used for transit by

cleanly dressed workers heading for the Work Area from the Changing Room, or for showering by workers headed out of the Work Area after undressing in the Equipment Room.

01563 - 5 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

1. Construct room by providing a shower pan and 2 shower walls in a configuration that will

cause water running down walls to drip into pan. Install a freely draining wooden floor in shower pan at elevation of top of pan.

2. Separate this room from the rest of the building with airtight walls fabricated of 6 mil (0.15

mm) polyethylene.

3. Separate this room from the Drying Room and Airlock with airtight walls fabricated of 6 mil (0.15 mm) polyethylene.

4. Provide splashproof entrances to Drying Room and Airlock with doors arranged in the

following configuration:

5. Provide shower head and controls.

6. Provide temporary extensions of existing hot and cold water and drainage, as necessary for a complete and operable shower.

7. Provide a soap dish and a continuously adequate supply of soap and maintain in sanitary

condition.

8. Arrange so that water from showering does not splash into the Changing or Equipment Rooms.

9. Arrange water shut off and drain pump operation controls so that a single individual can

shower without assistance from either inside or outside of the Work Area.

10. Provide flexible hose shower head. 11. Pump waste water to drain or to storage for use in amended water. If pumped to drain,

provide 20 micron and 5 micron waste water filters in line to drain or waste water storage. Change filters daily or more often if necessary. Locate filters inside shower unit so that water lost during filter changes is caught by shower pan.

12. Provide hose bib.

F. Equipment Room (contaminated area): Require work equipment, footwear and additional

contaminated work clothing to be left here. This is a change and transit area for workers.

1. Separate this room from the Work Area by a 6 mil (0.15 mm) polyethylene flapped doorway.

2. Separate this room from the rest of the building with airtight walls fabricated of 6 mil (0.15

mm) polyethylene.

01563 - 6 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

3. Separate this room from the Shower Room and Work Area with airtight walls fabricated of 6 mil (0.15 mm) polyethylene.

4. Provide a drop cloth layer of sheet plastic on floor in the Equipment Room for every shift

change expected. Roll drop cloth layer of plastic from Equipment Room into Work Area after each shift change. Replace before next shift change. Provide a minimum of two (2) layers of plastic at all times. Use only clear plastic to cover floors.

G. Airlock: Provide an airlock between Equipment Room and Work Area. This is a transit area for

workers.

1. Separate this room from Equipment Room and Work Area by a sheet plastic flapped doorways.

2. Separate this room from the rest of the building with airtight walls fabricated of 6 mil (0.15

mm) polyethylene.

3. Separate this room from the Equipment Room and Work Area with airtight walls fabricated of 6 mil (0.15 mm) polyethylene.

F. Work Area: Separate Work Area from the Equipment Room by polyethylene barriers. If the

airborne asbestos level in the Work Area is expected to be high, as in dry removal, add an intermediate cleaning space between the Equipment Room and the Work Area. Damp wipe clean all surfaces after each shift change. Provide one additional floor layer of 6 mil (0.15 mm) polyethylene per shift change and remove contaminated layer after each shift.

G. Decontamination Sequence: Require that all workers adhere to the following sequence when

entering or leaving the Work Area.

1. Entering Work Area: Worker enters Changing Room and removes street clothing, puts on clean disposable overalls and respirator, and passes through the Shower Room into the Equipment Room.

2. Any additional clothing and equipment left in Equipment Room needed by the worker are

put on in the Equipment Room.

3. Worker proceeds to Work Area.

H. Exiting Work Area:

1. Before leaving the Work Area, require the worker to remove all gross contamination and debris from overalls and feet.

2. The worker then proceeds to the Equipment Room and removes all clothing except respira-

tory protection equipment.

01563 - 7 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

3. Extra work clothing such as boots, hard hats, goggles, gloves are to be stored in contaminated end of the Equipment Room.

4. Disposable coveralls are placed in a bag for disposal with other material.

5. Require that Decontamination procedures found in Section 01560 be followed by all

individuals leaving the Work Area.

6. After showering, the worker moves to the Changing Room and dresses in either new coveralls for another entry or street clothes if leaving.

3.2 EQUIPMENT DECONTAMINATION UNIT:

A. Provide an Equipment Decontamination Unit consisting of a serial arrangement of rooms,

Clean Room, Holding Room, Wash Room for removal of equipment and material from Work Area. Do not allow personnel to enter or exit Work Area through Equipment Decontamination Unit.

B. Arrange with airlocks between rooms as required below.

C. Wash Down Station: Provide an enclosed Shower Unit located in Work Area just outside Wash

Room as an equipment, bag and container cleaning station. 1. Waterproof membrane is to be fabricated from minimum 10 mil (.254 mm) polyethylene.

2. Do not allow water to collect on waterproof membrane. Remove continuously with a wet

vacuum or mops.

D. Wash Room: provide wash room for cleaning of bagged or containerized asbestos-containing waste materials passed from the Work Area. 1. Construct wash room of nominal 2 inch x 4 inch (51 X 102 mm) wood framing and

polyethylene sheeting, at least 6 mil (0.15 mm) in thickness and located so that packaged materials, after being wiped clean, can be passed to the Holding Room.

2. Separate this room from the Work Area by a single flapped door of 6 mil (0.15 mm)

polyethylene sheeting.

3. Provide a drop cloth layer of plastic on floor in the Wash Room for every load-out operation. Roll this drop cloth layer of plastic from Wash Room into Work Area after each load-out. Provide a minimum of two (2) layers of plastic at all times. Use only clear plastic to cover floors.

E. Airlock: Provide an airlock between Wash Room and Holding Room. This is a transit area.

1. Separate this room from adjacent spaces by a sheet plastic flapped doorway.

01563 - 8 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

2. Separate this room from the rest of the building and adjacent spaces with airtight walls fabricated of 6 mil (0.15 mm) polyethylene.

F. Holding Room: Provide Holding Room as a drop location for bagged asbestos-containing

materials passed from the Wash Room. Construct Holding Room of nominal 2 inch x 4 inch (51 X 102 mm ) wood framing and polyethylene sheeting, at least 6 mil (0.15 mm) in thickness and located so that bagged materials cannot be passed from the Wash Room through the Holding Room to the Clean Room.

1. Separate this room from the adjacent rooms by flap doors fabricated from 6 mil (0.15 mm)

sheet plastic.

G. Airlock: Provide an airlock between Holding Room and Clean Room. This is a transit area.

1. Separate this room from adjacent spaces by a sheet plastic flap doorway.

2. Separate this room from the rest of the building and adjacent spaces with airtight walls fabricated of 6 mil (0.15 mm) polyethylene.

H. Clean Room: provide Clean Room to isolate the Holding Room from the building exterior. If

possible locate to provide direct access to the Holding Room from the building exterior.

1. Erect Critical and Primary Barriers as described in Section 01526 "Temporary Enclosures" in an existing space. If no space exists construct Clean Room of 2 x 4 (51 X 102 mm) wood framing and polyethylene sheeting, at least 6 mil (0.15 mm) in thickness.

2. Separate this room from the exterior by a single flap door of 6 mil (0.15 mm) polyethylene

sheeting.

I. Load-out Area: The load-out area is the transfer area from the building to a truck or dumpster. It may be the Clean Room of the Equipment Decontamination unit or a separate room or loading dock area. Erect Critical and Primary barriers as described in Section 01526 "Temporary Enclosures" in load-out area.

1. During transfer of material from load-out area erect primary barriers as described in

Section 01526 "Temporary Enclosures" as necessary to seal path from load-out area to truck or dumpster.

J. Decontamination Sequence: Take all equipment or material from the Work Area through the

Equipment Decontamination Unit according to the following procedure:

2. At washdown station, thoroughly wet clean contaminated equipment or sealed polyethylene bags and pass into Wash Room.

3. When passing equipment or containers into the Wash Room, close all doorways of the

Equipment Decontamination Unit, other than the doorway between the Washdown Station

01563 - 9 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

and the Wash Room. Keep all outside personnel clear of the Equipment Decontamination Unit.

4. Once inside the washroom, wet clean the bags and/or equipment.

5. When cleaning is complete pass items into Holding Room. Close all doorways except the

doorway between the Holding room and the Clean Room.

6. Workers from the building exterior enter Holding Area and remove decontaminated equipment and/or containers for disposal.

7. Require these workers to wear full protective clothing and appropriate respiratory

protection.

8. At no time is a worker from an uncontaminated area to enter the enclosure when a removal worker is inside.

3.3 CONSTRUCTION OF THE DECONTAMINATION UNITS:

A. Walls and Ceiling: Construct airtight walls and ceiling using polyethylene sheeting, at least 6 mil (0.15 mm) in thickness. Attach to existing building components or a temporary framework.

B. Floors: Use 2 layers (minimum) of 6 mil (0.15 mm) polyethylene sheeting to cover floors in all

areas of the Decontamination Units. Use only clear plastic to cover floors.

C. Flap Doors: Fabricated from three (3) overlapping sheets with openings a minimum of three feet (3') (0.91 meters ) wide. Configure so that sheeting overlaps adjacent surfaces. Weights at bottom of sheets as required so that they quickly close after being released. Put arrows on sheets to indicate direction of overlap and/or travel. Provide a minimum of six feet (6') (1.22 meters) between entrance and exit of any room. Provide a minimum of three feet (3') (0.91 meters ) between doors to airlocks.

D. If the Decontamination area is located within an area containing friable asbestos on overhead

ceilings, ducts, piping, etc., provide the area with a minimum 1/4 inch (6.4 mm) hardboard or 1/2 inch (12.7 mm) plywood "ceiling" with polyethylene sheeting, at least 6 mil (0.15 mm) in thickness covering the top of the "ceiling".

E. Visual Barrier: Where the Decontamination area is immediately adjacent to and within view of

occupied areas, provide a visual barrier of opaque polyethylene sheeting at least 6 mil (0.15 mm) in thickness so that worker privacy is maintained and work procedures are not visible to building occupants. Where the area adjacent to the Decontamination area is accessible to the public, construct a solid barrier on the public side of the sheeting to protect the sheeting. Construct barrier with wood or metal studs covered with minimum 1/4 inch (6.4 mm) thick hardboard or 1/2 inch (12.7 mm) plywood. Where the solid barrier is provided, sheeting need not be opaque.

F. Alternate methods of providing Decontamination facilities may be submitted to the

Engineer/Owner’s Representative for approval. Do not proceed with any such method(s) without written authorization of the Designer.

01563 - 10 n:\61\environmental managers\brian fischer\68 teamsters drive\specs\20 - 01563s96 - decontamination units - bkf.doc

G. Electrical: Provide subpanel at Changing Room to accommodate all removal equipment. Power

subpanel directly from a building electrical panel.

9. Connect all electrical branch circuits in Decontamination unit and particularly any pumps in shower room to a ground-fault circuit protection device.

3.4 CLEANING OF DECONTAMINATION UNITS:

A. Clean debris and residue from inside of Decontamination Units on a daily basis or as otherwise indicated on Contract Drawings. Damp wipe or hose down all surfaces after each shift change. Clean debris from shower pans on a daily basis.

B. If the Changing Room of the Personnel Decontamination Unit becomes contaminated with

asbestos-containing debris, abandon the entire Decontamination Unit and erect a new Decontamination Unit. Use the former Changing Room as an inner section of the new Equipment Room.

3.5 SIGNS: NOTE: EFFECTIVE JUNE 1, 2016, SIGNAGE MUST COMPLY WITH THE GHS

REQUIREMENTS UNDER SECTION 29 CFR 1910.1001(j)(4)(ii)(A).

A. Post an approximately 20 inch by 14 inch (508 mm x 356 mm) manufactured caution sign at each entrance to the Work Area displaying the following legend with letter sizes and styles of a visibility required by 29 CFR 1926: 10. Provide signs in both English and Spanish.

11. Legend:

DANGER

ASBESTOS

CANCER AND LUNG DISEASE HAZARD

AUTHORIZED PERSONNEL ONLY

RESPIRATORS AND PROTECTIVE CLOTHING ARE REQUIRED IN THIS AREA

12. Provide spacing between respective lines at least equal to the height of the respective upper

line.

END OF SECTION - 01563 This Page Inentionally Blank

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\21 - 01601S96 - Materials & Equipment - bkf.doc 01601 - 1

SECTION 01601

MATERIALS AND EQUIPMENT - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements governing the Contractor's selection of products for use in the Project.

B. Related Sections: The following Sections contain requirements that relate to this Section:

1. The Contractor's Construction Schedule is included under Section 01043 Coordination -

Asbestos Abatement.

2. The Contractor’s Schedule of Submittals is included under Section 01301 Submittals - Asbestos Abatement.

3. The applicability of industry standards to products specified is included under Section

01097 Reference Standards and Definitions - Asbestos Abatement. 1.3 DEFINITIONS

A. Definitions used in this Article are not intended to change the meaning of other terms used in the Contract Documents, such as "specialties," "systems," "structure," "finishes," "accessories," and similar terms. Such terms are self-explanatory and have well-recognized meanings in the construction industry.

1. "Products" are items purchased for incorporation in the Work, whether purchased for the

Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

2. "Named Products" are items identified by the manufacturer's product name, including make

or model number or other designation, shown or listed in the manufacturer's published product literature that is current as of the date of the Contract Documents.

3. "Foreign Products" as distinguished from "domestic products," are items substantially

manufactured (50 percent or more of value) outside the United States and its possessions. Products produced or supplied by entities substantially owned (more than 50 percent) by persons who are not citizens of, nor living within, the United States and its possessions are also considered to be foreign products.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\21 - 01601S96 - Materials & Equipment - bkf.doc 01601 - 2

4. "Materials" are products substantially shaped, cut, worked, mixed, finished, refined or otherwise fabricated, processed, or installed to form a part of the Work.

5. "Equipment" is a product with operational parts, whether motorized or manually operated,

that requires service connections, such as wiring or piping. 1.4 SUBMITTALS

Required submittals: A general listing of products requiring submittals is included at the end of Section 01301 "Submittals." This listing may not be complete. Submittal requirements are found in each specification section. Prepare a schedule in tabular form showing each product listed. Include the manufacturer's name and proprietary product names for each item listed. A. Product List: A list of products required is included at the end of this Section. Prepare a

schedule in tabular form showing each product listed. Include the manufacturer's name and proprietary product names for each item listed.

a. Related Specification Section number. b. Generic name used in Contract Documents.

c. Proprietary name, model number, and similar designations.

d. Manufacturer's name and address.

e. Supplier's name and address.

f. Installer's name and address.

g. Projected delivery date or time span of delivery period.

a. At the Contractor's option, the initial submittal may be limited to product selections

and designations that must be established early in the Contract period.

1. Engineer's Action: The Engineer/Owner’s Representative will respond in writing to Contractor within 2 weeks of receipt of the completed product list. No response within this period constitutes no objection to listed manufacturers or products but does not constitute a waiver of the requirement that products comply with Contract Documents. The Owner’s representative's response will include a list of unacceptable product selections, containing a brief explanation of reasons for this action.

1.5 QUALITY ASSURANCE (NOT USED)

A. Source Limitations: To the fullest extent possible, provide products of the same kind from a single source.

B. Compatibility of Options: When the Contractor is given the option of selecting between 2 or

more products for use on the Project, the product selected shall be compatible with products previously selected, even if previously selected products were also options.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\21 - 01601S96 - Materials & Equipment - bkf.doc 01601 - 3

5. The contractor is responsible for providing products and construction methods that are

compatible with products and construction methods to be installed after completion of the work of this contract.

6. If a dispute arises between contractors over concurrently selectable, but incompatible

products, the Engineer/Owner’s Representative will determine which products shall be retained and which are incompatible and must be replaced.

1.6 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products according to the manufacturer's recommendations, using

means and methods that will prevent damage, deterioration, and loss, including theft. 1. Schedule delivery to minimize long-term storage at the site and to prevent overcrowding of

construction spaces.

2. Coordinate delivery with installation time to assure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to the site in an undamaged condition in the manufacturer's original sealed

container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products upon delivery to ensure compliance with the Contract Documents and to

ensure that products are undamaged and properly protected.

5. Store products at the site in a manner that will facilitate inspection and measurement of quantity or counting of units.

PART 2 - PRODUCTS 2.1 PRODUCT SELECTION (NOT USED)

A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and, unless otherwise indicated, new at the time of installation.

1. Provide products complete with accessories, trim, finish, safety guards, and other devices

and details needed for a complete installation and the intended use and effect. 2. Standard Products: Where available, provide standard products of types that have been

produced and used successfully in similar situations on other projects.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\21 - 01601S96 - Materials & Equipment - bkf.doc 01601 - 4

PART 3 - EXECUTION 3.1 INSTALLATION OF PRODUCTS (NOT USED)

A. Comply with manufacturer's instructions and recommendations for installation of products in

the applications indicated. Anchor each product securely in place, accurately located and aligned with other Work.

1. Clean exposed surfaces and protect as necessary to ensure freedom from damage and

deterioration at time of Substantial Completion.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 1

SECTION 01711

PROJECT DECONTAMINATION PART 1 - GENERAL 1.1 SUMMARY:

A. Work of This Section includes the decontamination of air in the Work Area which has been, or may have been, contaminated by the elevated airborne asbestos fiber levels generated during abatement activities, or which may previously have had elevated fiber levels due to friable asbestos-containing materials (ACM) in the space.

B. Work of This Section includes the cleaning, decontamination, and removal of temporary

facilities installed prior to abatement work, including: 1. Primary and Critical Barriers erected by work of Section 01526 2. Decontamination Unit erected by work of Section 01563 3. Pressure Differential System installed by work of Section 01513

C. Work of This Section includes the cleaning, and decontamination of all surfaces (ceiling, walls,

floor) of the Work Area, and all furniture or equipment in the Work Area. 1.2 RELATED DOCUMENTS:

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to work of this section.

1.3 DESCRIPTION OF REQUIREMENTS:

A. General: Decontamination of the Work Area following asbestos abatement. B. If the asbestos abatement work is on damaged or friable materials the work is a four step

procedure with two cleanings of the Primary Barrier plastic prior to its removal and two cleanings of the room surfaces to remove any new or existing contamination. Unless specifically indicated otherwise all materials are considered damaged or friable for purposes of this section.

C. During the work area cleaning operation of the pressure differential system is used to remove

airborne fibers generated by the abatement work. 1.4 RELATED WORK SPECIFIED ELSEWHERE:

A. Removal of Gross Debris is integral with the performance of abatement work and as such is specified in the appropriate work section(s) of these specifications: 1. Section 02081 Removal of Asbestos-Containing Materials

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 2

1.5 PERIMETER AIR SAMPLING BY THE CONTRACTOR: (Third Party Independent Air

Monitor)

A. Prior to perimeter air sampling, the contractor shall retain the services of an independent air monitoring firm to collect the necessary air samples and comply with the requirements of the

Ohio Department of Health – Asbestos Hazard Abatement Rules, Chapter 3701-34, Ohio Administrative Code, Amended February 1, 1993. Effective date: 11/13/2014.

B. To determine if elevated airborne asbestos concentration were release to the ambient air. The

Contractor will secure samples and analyze them according to the following procedures. 1. One sample upwind and two downwind of the abatement work area. 2. PCM samples will be secured as indicated below.

1.6 AGGRESSIVE SAMPLING BY THE CONTRACTOR (NOT USED) A. All Air Samples will be taken using aggressive sampling techniques as follows:

1. Before sampling pumps are started the exhaust from forced-air equipment (leaf blower with

an approximately 1 horsepower (746 watts) electric motor) will be swept against all walls, ceilings, floors, ledges and other surfaces in the room. This procedure will be continued for 5 minutes per 10,000 (283 cubic meters) cubic feet of room volume.

2. One 20 inch (508 mm) diameter fan per 10,000 cubic feet (283 cubic meters) of room volume will be mounted in a central location at approximately 6 feet-6 inches (2 meters) above floor, directed toward ceiling and operated at low speed for the entire period of sample collection.

3. Air samples will be collected in areas subject to normal air circulation away from room corners, obstructed locations, and sites near windows, doors of vents.

4. After air sampling pumps have been shut off, fans will be shut off. 5. In work areas where a dirt floor or exposed fibrous glass insulation is in the space, but

outside the work area, maintain a critical barrier to prevent disturbance of these surfaces during aggressive sampling.

1.7 SCHEDULE OF CLEARANCE AIR SAMPLES BY CONTRACTOR: (NOT USED)

1.7.1. Prior to clearance air sampling, the contractor shall comply with the requirements of the Ohio Department of Health – Asbestos Hazard Abatement Rules, Chapter 3701-34,

Ohio Administrative Code, Amended February 1, 1993. Effective date: 11/13/2014.

A. Sample cassettes: Samples will be collected on 25 mm. cassettes as follows:

1. PCM: 0.8 micrometer mixed cellulose ester.

2. TEM: 0.45 micrometer mixed cellulose ester or 0.40 micrometer polycarbonate, with 5.0 micron mixed cellulose ester backing filter.

B. Number and Volume of Samples: The number and volume of air samples given in the

schedules is approximate. The exact number and volume of samples collected by the Owner may vary depending upon job conditions and the analytical method used.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 3

C. Sampling sensitivity:

1. PCM: Based on a limit of detection (LOD) of 7 fibers/mm2 on the filter (approximately 5

fiber counted in 100 fields) and a 95% confidence limit, a sample volume of sufficient size that a single sample indicates compliance with the limit values given below. A sample must be at or below the LOD to indicate that it is at or below the limit value. Note: This is different from quantifying a concentration which is a stricter requirement and would need a larger sample volume. a. Clearance samples - a limit value of 0.01 f/cc.

D. PHASE CONTRAST MICROSCOPY:

1. In each Work Area after completion of all cleaning work, a minimum of 7 samples will be

taken and analyzed as follows:

Location Number Limit Approx. Rate Sampled of Value Volume Liters /

Samples (Fibers/cc) (Liters) Minute Each Work Area 5 0.01 <1,000> 10 or Each Room of 1 Work Area (5 min.) 0.01 <1,000> 10

Work Area Blank 1 0.01 0 open for 30

Seconds

Laboratory Blank 1 0.01 0 Do Not Open

2. Analysis: Fibers on each filter will be measured using the NIOSH Method 7400 entitled

"Fibers" published in the NIOSH Manual of Analytical Methods, or the OSHA Reference Method (ORM) (29 CFR 1926.1101 Appendix A).

3. Fibers: referred to in this section include fibers regardless of composition as counted by

the phase contrast microscopy method used.

4. Split Sample: One Work Area sample will be split and both halves analyzed separately for duplicate analysis.

5. Release Criteria: Decontamination of the work site is complete when every Work Area

sample is at or below the Detection Limit above. If any sample is above the Detection Limit then the decontamination is incomplete and re-cleaning per section 01711 Project Decontamination is required.

1.8 TRANSMISSION ELECTRON MICROSCOPY: (NOT USED)

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 4

A. In each Work Area after completion of all cleaning work and compliance with the AHERA

regulations, a minimum of 13 samples will be taken and analyzed as follows: Location Number Analytical Approx. Rate Sampled of Sensitivity Volume Liters/

Samples Struct/cc (Liters) Minute Each Work Area 5 0.005 1,300-1,800 1-10 Outside Each 5 0.005 1,300-1,800 1-10 Work Area

Work Area Blank 1 0.005 0 Open for 30

Seconds

Outside Blank 1 0.005 0 Open for 30 Seconds

Laboratory Blank 1 0.005 0 Do Not Open

B. Analysis will be performed using the analysis method set forth in the AHERA Regulation 40 CFR

Part 763 Appendix A.

C. Asbestos Structures referred to in this Section include asbestos fibers, bundles, clusters or matrices, as defined by method of analysis.

D. Release Criteria: Decontamination of the work site is complete once the Engineer/Owner’s

Representative has inspected and released the work area and in addition, if either of the following two sets of conditions are met:

1. Work Area Samples are below filter background levels

a. All Work Area sample volumes are greater than 1,199 liters for a 25 mm. sampling

cassette.

b. The average concentration of asbestos of the five Work Area Samples does not exceed the filter background level of 70 structures per square millimeter of filter area.

2. Work Area Samples are not statistically different from Outside samples

a. All sample volumes except for blanks are greater than 560 liters for a 25 mm. sampling cassette.

b. The average asbestos concentration of the three blanks is below the filter

background level of 70 structures per square millimeter of filter area.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 5

c. Average asbestos concentrations in Work Area Samples are not statistically different from Outside samples, as determined by the Z-test calculation found in 40 CFR Part 763, Subpart E, Appendix A (Z is less that or equal to 1.65)

E. If these conditions are not met then the decontamination is incomplete, repeat the cleaning

procedures of this section. F. Termination of Analysis: if the arithmetic mean (average) asbestos concentration on the blank

filters exceed 70 structures per square millimeter of filter area the analysis will cease and new samples collected.

1.9 LABORATORY TESTING BY THE CONTRACTOR (Third Party Independent Air Monitor):

A. Phase Contrast Microscopy by the (Third Party Independent Air Monitor):

1. The services of a testing laboratory will be employed by the Contractor to perform laboratory analysis of the air samples. A technician will be at the job site, and samples will be sent daily by overnight delivery, so that verbal reports on air samples can be obtained within 24 hours. A complete record, certified by the testing laboratory, of all air monitoring tests and results will be furnished to the Engineer/Owner’s Representative, the Owner and the Contractor.

B. Transmission Electron Microscopy by the Owner: (NOT USED)

1. Samples will be sent by overnight courier for analysis by Transmission Electron

Microscopy. Samples will not be carried on weekends, so that samples shipped on Friday will arrive on the following Monday. Verbal results will normally be available during the 5th working day after receipt of samples by the laboratory. The laboratory is capable of analyzing a maximum of 13 such samples from this project at any one time. All Transmission Electron Microscopy results will be available to the Contractor.

1.10 SUBMITTALS:

A. Before Start of Work submit the following to the Engineer/Owner’s Representative for review. Do not begin work until these submittals are returned with the Designer's action stamp indicating that the submittal has been Received - Not Reviewed.

1. Safety Data Sheet: Submit Material Safety Data Sheets, or equivalent, in accordance with

the OSHA Hazard Communication Standard (29 CFR 1910.1200) for the following:

a. Lock-Back, sealer. PART 2 - PRODUCTS (NOT APPLICABLE)

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 6

PART 3 - EXECUTION 3.1 START OF WORK:

A. Previous Work: During completion of the asbestos abatement work specified in other sections, the Secondary Barrier of polyethylene sheeting will have been removed and disposed of along with any gross debris generated by the asbestos abatement work.

B. Visual inspection: Perform visual inspections of the work area along with the Engineer/Owner’s

Representative at each step of the decontamination process.

1. Follow inspection procedures in EPA Purple Book. C. Start of Work: Work of this section begins with the cleaning of the Primary Barrier. At start of

work the following will be in place: 1. Primary Barrier: Two layers of polyethylene sheeting on floor and one layer on walls. 2. Critical Barrier: An airtight barrier between the Work Area and other portions of the

building or the outside. 3. Critical Barrier Sheeting: Over lighting fixtures and clocks, ventilation openings,

doorways, convectors, speakers and other openings. 4. Decontamination Units: For personnel and equipment in operating condition. 5. Pressure Differential System: In operation.

3.2 FIRST CLEANING:

A. First Cleaning: Carry out a first cleaning of all surfaces of the work area including items of remaining sheeting, tools, scaffolding and/or staging by use of damp-cleaning and mopping, and/or a High Efficiency Particulate Air (HEPA) filtered vacuum. (Note: A HEPA vacuum may fail if used with wet material.) Do not perform dry dusting or dry sweeping. Use each surface of a cleaning cloth one time only and then dispose of as contaminated waste. Continue this cleaning until there is no visible debris from removed materials or residue on plastic sheeting or other surfaces. 1 Remove All Filters in Air Handling System(s) and dispose of as asbestos-containing waste

in accordance with requirements of Section 02084 Disposal of Regulated Asbestos-Containing Material.

2 After the surfaces have passed a visual inspection verifying that all debris and residue has been removed from the sheet plastic, allow a waiting period that is long enough for the HEPA-filtered fan units operating in the work area to provide 96 air changes to clean air of airborne asbestos fibers. Use oscillating fans as necessary to assure circulation of air in all parts of work areas during this period. Maintain Pressure Differential System in operation for the entire 96 air change period.

3.3 SECOND CLEANING:

A. Second Cleaning: Carry out a second cleaning of all surfaces in the work area in the same manner as the first cleaning.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 7

B. Visual inspection: Before the application of any sealer to abated surfaces as a lock-back, perform a visual inspection to determine if all ACM including debris and residue has been removed. Perform visual inspections along with Engineer/Owner’s Representative. When the area is visually clean, and if after sweeping of all surfaces with leaf blower, no debris, residue, dust or other material is found, complete the certification at the end of this section. Visual inspection is not complete until confirmed in writing, on the certification, by Engineer/Owner’s Representative. After this visual inspection is passed, lock-back sealants can be applied and the work area decontamination process can be initiated.

C. Sealing of substrate: Perform sealing of substrate or installation of spray-applied finishes or

fireproofing, where required, at this time. Maintain Pressure Differential System in operation during encapsulation work. Perform work only after meeting the following requirements: 3 Surfaces to be covered with sealer have met the requirements for a visual inspection in this

section. 4 Airborne fiber counts in the Work Area are at or below 0.01 fibers per cubic centimeter as

measured by phase contrast microscopy.

D. Removal of Primary Barriers: 5 Immediately following the second cleaning of the Primary plastic, remove all Primary

Barrier sheeting and Material Decontamination Unit, if there is one, leaving only: a. Critical Barrier: Which forms the sole barrier between the Work Area and other

portions of the building or the outside. b. Critical Barrier Sheeting: Over lighting fixtures and clocks, ventilation openings,

doorways, convectors, speakers, and other openings. c. Decontamination Unit: For personnel, in operating condition. d. Pressure Differential System: Maintain in continuous operation.

3.4 THIRD CLEANING:

A. Third cleaning: Carry out a third cleaning of all surfaces in the work area in the same manner as the first cleaning immediately after removal of Primary plastic. This cleaning is now being applied to existing room surfaces. Take care to avoid water marks or other damage to surfaces.

B. Contractor's Testing: At the completion of the above cleaning visually inspect all surfaces. Re-

clean if any dust, debris, etc. is found. At completion of this inspection sweep entire Work Area including walls, ceilings, ledges, floors and other surfaces in the Work Area with exhaust from forced-air equipment (leaf blower with approximately 1 horsepower (745.7 watts ) electric motor or equivalent). Do not direct forced-air equipment at any seal in any Critical Barrier. If any debris or dust is found repeat the cleaning. Continue this process until no debris dust or other material is found while sweeping of all surfaces with forced-air equipment.

3.5 FINAL CLEANING:

A. Final Cleaning: Carry out a final cleaning of all surfaces in the Work Area in the same manner as the previous cleaning.

B. Contractor's Testing: At the completion of the above cleaning visually inspect all surfaces. Re-

clean if any dust, debris, etc. is found. At completion of this inspection sweep entire Work Area

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 8

including walls, ceilings, ledges, floors and other surfaces in the Work Area with exhaust from forced air equipment (leaf blower with approximately 1 horsepower electric motor or equivalent). Do not direct forced air equipment at any seal in any critical barrier. If any debris or dust is found repeat the final cleaning. Continue this process until no debris dust or other material is found while sweeping of all surfaces with forced air equipment.

C. After a visual inspection, again wait for a period of time long enough for the HEPA-filtered fan

units operating in the work area to provide 96 air changes to allow HEPA filtered fan units to clean air of airborne asbestos fibers. Use oscillating fans as necessary to assure circulation of air in all parts of Work Areas during this period. Maintain Pressure Differential System in operation for the entire 96 air change period.

3.6 VISUAL INSPECTION:

A. After Final Cleaning Perform a Complete Visual Inspection of the entire Work Area including: all surfaces, ceiling, walls, floor, decontamination unit, all plastic sheeting, seals over ventilation openings, doorways, windows, and other openings; look for debris from any source, residue on surfaces, dust or other matter. During visual inspection sweep entire work area including walls, ceilings, ledges, floors, and other surfaces in the room with exhaust from forced air equipment (leaf blower with approximately 1 horsepower electric motor or equivalent). If any debris, residue, dust or other matter is found repeat final cleaning and continue decontamination procedure from that point. When the area is visually clean, and if after sweeping of all surfaces with leaf blower, no debris, residue, dust or other material is found, complete the certification at the end of this section. Visual inspection is not complete until confirmed in writing, on the certification, by the Engineer/Owner’s Representative.

B. Temporary lighting: Provide a minimum of 100 foot candles (1075 Lumens / sq meter) of

lighting on all surfaces in the areas to be subjected to visual inspection. Provide hand held lights providing 150 foot candles (1600 lumens / sq meter) at 4 feet (1.25 meter) capable of reaching all locations in work area.

C. Lifts: Provide ladders, scaffolding, and lifts as required to provide access to all surfaces in the

area to be subjected to visual inspection. Access is to allow touching of all surfaces. 3.7 CLEARANCE AIR SAMPLING BY CONTRACTOR (NOT USED):

A. Phase Contrast Microscopy (PCM): After the Work Area is found to be visually clean, air

samples will be taken and analyzed by a Third Party Independent Air Monitor hired by the Contractor in accordance with the procedure for Phase Contrast Microscopy set forth in Part 1 of this section.

6. If Release Criteria are not met, repeat Final Cleaning and continue decontamination

procedure from that point.

B. Transmission Electron Microscopy (TEM): (NOT USED) After the work area is found to be visually clean and PCM air sampling completed, TEM air samples will be collected and analyzed by the Owner in accordance with the procedure for Transmission Electron Microscopy set forth in Part 1 of this section.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 9

7. If Release Criteria are not met, repeat Final Cleaning and continue Decontamination procedure from that point.

8. If Release Criteria are met, remove work area isolation in accordance with requirements of

this section. 3.8 LOCK-BACK:

A. Encapsulation of substrate: Perform encapsulation of substrate or installation of spray-applied

finishes or fireproofing, where required, before Removal of Work Area Isolation as specified below. Maintain Pressure Differential System in operation during encapsulation work.

3.9 REMOVAL OF WORK AREA ISOLATION:

A. After all requirements of this section have been met: 9. Shut down and remove the Pressure Differential System. Seal HEPA filtered fan units,

HEPA vacuums and similar equipment with 6 mil (0.15 mm) polyethylene sheet and duct tape to form a tight seal at intake end before being moved from Work Area.

10. Remove Personnel Decontamination Unit. 11. Remove the Critical Barriers separating the Work Area from the rest of the building.

Remove any small quantities of residual material found upon removal of the plastic sheeting with wet wiping, HEPA filtered vacuum cleaners and local area protection. If significant quantities, as determined by the Project Monitor, are found then the entire area affected shall be decontaminated as specified in Section 01712 Cleaning & Decontamination Procedures.

12. Remove all equipment, materials, debris from the work site. 7. Dispose of all asbestos-containing waste material as specified in Section 02084 Disposal of

Regulated Asbestos Containing Material. 3.80 SUBSTANTIAL COMPLETION OF ABATEMENT WORK:

A. Asbestos Abatement Work is Substantially Complete upon meeting the requirements of this section including submission of: 84. Certificate of Visual Inspection 15. Receipts Documenting proper disposal as required by Section 02084 Disposal of Regulated

Asbestos-Containing Material. 96. Punch list detailing repairs to be made and incomplete items. 17. Final Clearance Inspection.

3.91 CERTIFICATE OF VISUAL INSPECTION:

A. Following this section is a "Certificate of Visual Inspection". This certification is to be completed by the Contractor and certified by the Project. Submit completed Certificate with Application for Final Payment. Final payment will not be made until this Certification is executed.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 10

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\22 - 01711S96 - Project Decontamination - bkf.doc 01711 - 11

CERTIFICATION OF VISUAL INSPECTION

In accordance with Section 01711 "Project Decontamination" the Contractor hereby certifies that he has visually inspected the Work Area (all surfaces including pipes, beams, ledges, walls, ceiling and floor, Decontamination Unit, sheet plastic, etc.) and has found no dust, debris or residue. by: (Signature______________________________ Date_______________ (Print Name)________________________________ (Print Title)_______________________________

PROJECT MONITOR CERTIFICATION The Project Monitor hereby certifies that he has accompanied the Contractor on the Contractor’s visual inspection and verifies that this inspection has been thorough and to the best of their knowledge and belief, the Contractor's Certification above is a true and honest one. by: (Signature)____________________________ Date________________ (Print Name)_______________________________ (Print Title)______________________________

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\23 - 01712S96 - Cleaning & Decontamination Procedures - bkf.doc01712 - 1

SECTION 01712

CLEANING AND DECONTAMINATION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to work of this section.

1.2 DESCRIPTION OF THE WORK:

A. The extent of cleaning and decontamination work is shown on the drawings. B. The work includes decontamination of the areas indicated in the "Schedule of Decontamination

Work," found at the end of this section. 1.3 RELATED WORK SPECIFIED ELSEWHERE:

A. Work Area Clearance (NOT USED): Specified in Section 01711.

PART 2 PRODUCTS (NOT APPLICABLE) PART 3 EXECUTION 3.1 GENERAL:

A. Complete the following before start of work of this section:

1. Regulated Areas

2. 01562 Respiratory Protection

3.2 WET CLEANING:

A. Accomplish wet cleaning during decontamination with paper towels or disposable rags:

B. Immerse paper towel or rag in container of amended water or dilute removal encapsulant. C. Wring out,

D. Fold into quarters,

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\23 - 01712S96 - Cleaning & Decontamination Procedures - bkf.doc01712 - 2

E. Wipe surface once and refold to a fresh face of cloth. Proceed in this manner until all available faces of paper towel or rag have been used.

F. Dispose of paper towel or rag,

G. Do not place rag back in container to rinse out or for any other purpose. If a used towel or rag

comes in contact with water, empty container and refill.

H. Material adhered to a surface with removal encapsulant may require the application of additional removal encapsulant to facilitate cleaning.

3.3 REMOVAL OF ASBESTOS-CONTAINING DEBRIS

A. Work of this Section is limited to the cleanup of a small quantity of amassed debris which has

fallen from an architectural finish, fire-proofing, or thermal insulation on pipes, boilers and other equipment.

B. Remove asbestos-containing debris and decontaminate the area involved using the following

sequence: 1. Shut down all ventilation into room. 2. Seal entry to work area with 6 mil (0.15 mm) polyethylene. Slit polyethylene for entry.

Install a flap to cover the slit automatically; tape slit closed after entry. 3.4 CLEANING AND DECONTAMINATING OBJECTS

A. Perform all work of decontaminating objects wherever possible on a plastic drop sheet.

B. HEPA vacuum all surfaces of object and immediate area before moving the object.

C. Pick-up object, if possible, and HEPA vacuum all surfaces.

D. Hand to off-sheet worker who will wet-clean object, if possible, and place in storage location.

E. Decontaminate area where object was located by HEPA vacuuming twice, in two perpendicular

directions. Wet clean if necessary to remove any debris.

F. Return object to its original location. 3.5 DECONTAMINATION OF ROOMS:

A. Shut down all ventilation into space, buildings are vacant and the utilities shall be disconnected

from the mains.

B. Seal entry to Work Area with 6 mil (0.15 mm) polyethylene. Slit polyethylene for entry. Install a flap to cover the slit automatically; tape slit closed after entry.

C. Install Differential Pressure System in accordance with Section 01513.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\23 - 01712S96 - Cleaning & Decontamination Procedures - bkf.doc01712 - 3

D. Recirculate HEPA filtered fan units in space by operating them so that discharge from machine

is back into room. Use one HEPA filtered fan unit for each 2,500 cubic feet (70.8 cubic meters) of room volume.

E. HEPA vacuum all surfaces in the room starting at the ceiling, then top of wall and working

downward to the floor.

F. HEPA vacuum the floor using a floor attachment with rubber floor seals and adjustable floor to attachment height. Adjust the height so that the rubber seals just touch the floor if carpeted and are within 1/16 inch (1.6 mm) of hard surface floors. Vacuum the floor in parallel passes with each pass overlapping the previous by one half the width of the floor attachment. At the completion of one cleaning, vacuum the floor a second time at right angles to the first.

G. Operate HEPA filtered fan unit in space for 96 air changes minimum.

H. Secure area from occupancy until air monitoring results indicate area is safe for reoccupancy by

the demolition contractor. Not applicable due to the fact that the buildings are vacant and scheduled for demolition.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-1

SECTION 02050

BUILDING DEMOLITION PART 1 GENERAL 1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Special Conditions and Division 1 Specification Sections, apply to this Section.

1.02 SUMMARY OF WORK.

A. Building Description

The building structures scheduled for demolition are located at 68 Teamsters Drive, Youngstown, Ohio, between Teamsters Drive and Lilac Street. The buildings and appurtenances were formerly utilized for a commercial business. Additional information on the building structures are provided below. See attached plan sheet at the end of this section for building designations and scheduled work. The following is a description of the Rooms/Building structures scheduled for demolition and abatement:

• 68 Teamsters Drive: In general, the building structure (s) is comprised of four structures (two of which have second floors) connected to each other between Teamsters Drive and Lilac Street. During the asbestos surveys (by others) the building structures were noted as rooms # 1-5. (See Plan Sheet). Overall the buildings are in very poor condition, with partially failed/collapsed roofing systems and floors. Access is limited to the portions of the structures which have not failed or unable to be accessed (eg. Room #1 basement). The exterior of the structures range from brick to speed block with steel and/or wooden structural beams, steel and/or wooden floor joists and wooden roof trusses. The roofing systems appear to be built-up roofing, which in most areas have failed and collapsed into the interior portion its associated structure.

A. Asbestos Removal

As stated in the summary of work (Section 01013), the former building structures are to be abated of all hazardous materials (asbestos, abandoned chemicals) and subsequently demolished. OSHA standards require implementation of appropriate engineering controls and work practices where any asbestos-containing materials are present. The contractor shall use a State of Ohio licensed asbestos abatement contractor to remove the Friable and Category II non-friable asbestos containing materials in accordance with federal, state and local regulations present in the former commercial building structures located at 68 Teamsters Drive, between Teamsters Drive and Lilac Street, Youngstown, Ohio. The following is a list of building structures to be abated prior to demolition activities:

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-2

• ROOM #1 and ROOM#5:

As stated in the summary of work (Section 01013), the building located at 68 Teamsters Drive, Youngstown, Ohio. Please refer to section 01013 for the asbestos survey report conducted by HZW and supplemented by ms consultants, inc. (ms) identifying the locations of the (ACBM) asbestos containing building materials within the building. • ROOM#2: As stated in the summary of work (Section 01013), the building located at 68 Teamsters Drive, Youngstown, Ohio. Please refer to section 01013 for the asbestos survey report conducted by HZW and supplemented by ms consultants, inc. (ms) identifying the locations of the (ACBM) asbestos containing building materials within the building. • ROOM#3: As stated in the summary of work (Section 01013), the building located at 68 Teamsters Drive, Youngstown, Ohio. Please refer to section 01013 for the asbestos survey report conducted by HZW and supplemented by ms consultants, inc. (ms) identifying the locations of the (ACBM) asbestos containing building materials within the building. • ROOM#4: As stated in the summary of work (Section 01013), the building located at 68 Teamsters Drive, Youngstown, Ohio. Please refer to section 01013 for the asbestos survey report conducted by HZW and supplemented by ms consultants, inc. (ms) identifying the locations of the (ACBM) asbestos containing building materials within the building.

B. Lead-based Paint

Contractors shall assume that painted and coated surfaces that may be disturbed during demolition contain lead. Contractors shall follow all applicable regulations.

Building Demolition

The Contractor shall demolish the designated building structures located at 68 Teamsters Drive in their entirety in the City of Youngstown, Mahoning County, Ohio in accordance with applicable federal, state and local regulations and the site-specific specifications. The demolition project consists of demolishing and completely removing the identified structure(s), the associated floors, walls, foundations to the native soils, unless directed differently by the Engineer. Prior to demolition activities beginning, the contractor shall remove furniture, construction debris, appliances, and all hazardous waste and or other regulated materials including polychlorinated biphenyls ballast and fluorescent bulbs from within and outside of the following building(s)structures:

• 68 Teamsters Drive

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-3

The Demolition Work shall include the following: 1. The Contractor shall secure all required Federal, State and Local Demolition Permits.

Costs associated with securing a demolition permit are the responsibility of the Contractor. A City of Youngstown Demolition Permit is required. In addition, the Contractor shall file the OEPA Demolition/Renovation notification with the proper authorities, as well.

2. Install temporary fencing and access gates to secure the designated building structures

work area(s) from being entered during non-working hours by trespassers.

3. The contractor shall properly cap and mark (noting depth below grade with U.S.G.S. datum) for reuse, all sanitary, storm, domestic water, steam lines and gas lines to be abandoned before any demolition activities begin. Contractor shall be responsible for coordinating with utility companies and pay all costs associated with utility disconnection.

4. A detailed demolition schedule shall be submitted to the Engineer at the pre-construction

meeting indicating the demolition completion date. This schedule shall be subject to the approval of the Engineer and the Owner.

5. Any road closures shall be established in accordance with the requirements of the Ohio

Department of Transportation Construction and Material Specifications, current edition, latest revision, and subject to Owner approval. The safety of pedestrian traffic shall be considered at all times. It shall be the Demolition Contractor's responsibility to provide plans for approval along with all lights, signs, barricades, ramps, and other devices to warn and physically separate pedestrians from hazards incidental to the demolition projects.

6. A detailed demolition plan and a protection plan for adjacent roadways, all existing manholes and hydrants shall be prepared and sealed by a Professional Engineer registered in the State of Ohio shall be submitted to the Engineer before the start of any demolition activities.

7. All asbestos containing materials removed from the designated building structures shall

be hauled to an approved asbestos landfill as identified by the Contractor. The Contractor will deliver a certified letter to the Engineer identifying the approved landfill that the Contractor will be using during the contract prior to the start of any demolition work on site.

8. The demolition work shall involve furnishing all labor, material, tools and equipment

necessary to complete the demolition of the designated building structures located at 68 Teamsters Drive, Youngstown, Ohio. Work includes removal of walls, foundations, utilities, concrete, etc. and any other frame or masonry structure which is on the surface or extends above the surface, and any rubbish or debris within the work area boundaries to native soils. The contractor shall remove all asphalt pavement around building structures. The Contractor shall not remove any City sidewalk unless designated for removal. If a city sidewalk or curb is damaged during the demolition project, the contractor shall repair/replace at no additional cost to the project.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-4

9. Refer to Section 02272 “Construction Storm Water Pollution Control”, for temporary construction and storm water control.

10. Refer to Section 02270 “Environmental Protection” for environmental protection

measures for building demolition operations.

1.03 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site at an approved landfill.

B. Existing to Remain: Existing items of construction that are not to be removed and that are not

otherwise indicated to be removed.

C. Demolition: as used herein, includes the complete removal of all existing objects including bases and anchorage’s and removal of all structures, footers etc., to native soils.

1.04 SUPPLEMENTAL SUBMITTALS

A. Qualification Data: The demolition firm shall be licensed, insured, and qualified to perform the work.

B. Proposed Environmental Protection, Dust Control and Noise Control Measures: Submit

statement or drawing that indicates the measures proposed for use, proposed locations, and proposed time frame for their operation. Identify options if proposed measures are determined to be inadequate.

C. Prior to any demolition on-site, letters or certificates from all of the utility companies which

serve the site indicating:

1. Their authorization for demolition to proceed, 2. Stipulating the extent to which they have taken responsibility for disconnection and

removal of utilities.

D. Schedule of Building Demolition Activities: Indicate the following: 1. Detailed sequence of demolition and removal work, with starting and ending dates for

each task. 2. Interruption of utility services. 3. Coordination for shutoff, capping, and continuation of utility services.

4. Locations of temporary protection and means of site ingress and egress, including for neighbors affected by building demolition operations.

E. Pre-demolition Photographs or Videotape: Show existing conditions of adjoining construction

and site improvements, including finish surfaces that might be misconstrued as damage caused by building demolition operations. Submit before any work begins.

1.05 QUALITY ASSURANCE

A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this project. The contractor shall submit similar

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-5

demolition project documents and experience.

B. Qualifications of Workmen: Provide at least one person who shall be present at all times during the demolition operations to direct the workmen, read the plans, and coordinate the work with the construction manager.

C. Regulatory Requirements: Comply with governing EPA notification regulations before beginning

site demolition activities. Comply with hauling and disposal regulations of authorities having jurisdiction.

D. Standards: Comply with, but not limited to: ANSI A10.6, NFPA 241, OAC 3701-34, OSHA

1926.1101, OSHA 1910.134, EPA 40 CFR Part 61, Subpart M, and 40 CFR 82. 1.06 PROJECT CONDITIONS

A. Building structures designated to be demolished are vacated and their use discontinued.

B. Storage or sale of removed items or materials on-site is not permitted. As noted in other sections the structural steel may be rinsed and recycled.

C. Dust Control: Use all means necessary to prevent the spread of dust during performance of the

work of this section; thoroughly moisten all surfaces as required to prevent dust from being a nuisance to the public, neighbors, and/or concurrent performance of other work on the site. No visible emissions beyond thirty (30) feet of the building(s).

D. The Contractor shall not cause or permit any fugitive dust source from the building demolition

without taking or installing reasonably available control measures to prevent fugitive dust from becoming airborne. Prevention of fugitive dust emissions is further referenced in section 3.10.

E. Burning: On site burning of general site debris by building a fire will not be permitted.

Scrap burning, cutting by the use of a torch, shall be limited to the inside of the structures. Anytime there is any interior burning onsite, a Fire Watch man shall be present. It is the Contractor's responsibility to contact the Mahoning/Trumbull County Air Pollution Control Agency for permits required for the interior burning of scrap. Fumes that are emitted from the burning process could be hazardous and contain heavy metals.

F. Protection: Use all means necessary to protect existing objects designated to remain, and in the

event of damage immediately make all repairs and replacements necessary to the approval of the Engineer at no additional cost to the Owner.

G. The Contractor shall disconnect power to all existing equipment and remove power control

centers, motor control centers, and electrical equipment and transformers, as necessary.

H. The demolition material shall become the property of the Contractor unless otherwise noted and shall be disposed of properly by the Contractor at an approved landfill.

I. All pipes, basement walls, floors, foundations shall be removed to native soils.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-6

The concrete, brick or other non-asbestos containing debris resulting from demolition of the structures, may not be utilized as engineered fill material on this project.

J. Upon completion of the demolition activities to grade, the Contractor shall rough grade the site to match the existing site elevation, unless otherwise directed by the Engineer.

1.07 DEMOLITION AND REMOVAL PROCEDURES

A. Before starting the demolition work, the Contractor will be responsible for having all utilities including electric, telephone, water and gas service, etc. for the designated building structures located at 68 Teamsters Drive, Youngstown, Ohio. The Contractor shall notify both OUPS (1-800-362-2764) and each utility company of when the demolition is scheduled. The Contractor is responsible for requesting that each utility service be disconnected and properly sealed. All sewer laterals for down spouts, etc. shall be properly sealed at the street, using burlap and concrete, unless otherwise specified by the utility. The Contractor will be obligated to make all necessary arrangements to secure a supply of water to carry out all provisions of the contract without additional expense to the City of Youngstown. Cost for water shall be paid by the contractor.

B. The Contractor shall fully remove the designated building, including all walls, floors, ceilings,

basement floors and foundations supports, etc. to native soils unless otherwise specified for the following address:

• 68 Teamsters Drive

C. Unless otherwise specified, no structure shall be removed from the premises a whole or any

substantially whole condition, but all such building structures shall be demolished on the premises.

D. In cases where basement/steam tunnels/crawl spaces may exist, the Contractor shall break up the

floors and dispose of the concrete as demolition debris. All work in connection with the breaking up and removal of the basement floors, floor slabs, foundations and bulkheadings for water and sewer connections shall be conducted in the presence of the specific utility company.

E. The Contractor shall not remove, damage or destroy the vaults of private or public utilities,

unless specified in this specification. F. The Contractor must protect existing structures not scheduled to be demolished.

G. The Contractor must fully protect all utilities, which are not to be abandoned, as applicable.

H. The Contractor must prevent movement or settlement of adjacent structures. The Demolition

Contractor shall provide bracing and shoring.

I. The Contractor must conduct the demolition with no interference to adjacent structures.

J. Cease operations immediately when adjacent structures appear to be in danger. Notify the Engineer. Do not resume operations until corrective action measures have been implemented.

K. Conduct demolition operations with minimum interference to public or private accesses.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-7

Maintain any and all egress and access from adjacent structures at all times.

L. Obtain written permission from adjacent property owners when demolition equipment will traverse, infringe upon or limit access to their property.

M. Where the removal of sidewalks and/or curbs have been made necessary to perform any of the

work provided for in this contract, the voids or spaces resulting from such removal shall be replaced in kind by the Contractor at no additional expense to the owner, in accordance with the City of Youngstown standards.

N. The Contractor shall protect sidewalks, curbs, pavements and other public or private facilities not

scheduled for demolition, that may be damaged or endangered by the work required under the specifications and shall restore and make good any structure or facility that may be damaged or destroyed.

O. All masonry structures are to be broken and filled with clean structural backfill. In the case of

cisterns or cesspools, the Contractor shall notify the Owners Representative of the existence of same prior to the removal thereof, and upon obtaining its approval, shall break up such cisterns and/or cesspools and cause the voids or cavities to be filled with clean earth (structural backfill).

1.08 DISCONNECTION OF UTILITIES

A. Before starting site operations, arrange for the disconnection of all utility services at the street. All such work shall be performed in accordance with the requirements of the utility company or agency involved.

B. The demolition contractor shall properly cap and mark (noting depth below grade with U.S.G.S.

datum) for reuse all existing sanitary, storm, domestic water and gas lines to be abandoned as a result of the demolition.

C. The Contractor will be responsible for the coordination and any costs for the

disconnection/removal/relocation of any utility line back to the main line or connection point.

D. The Contractor will be responsible for any damage done to any utility lines.

E. The information provided in this section is for the Contractor’s convenience and may not be complete or up-to-date. The Contractor is advised to verify all representations made herein. 1. SBC – Telephone and Cable

50 West Bowery 6th Floor Akron, OH 44308-1102

1-800-660-1000

2. City of Youngstown Water Department Mr. Gene Leson, 330-743-5338

3. Ohio Edison – First Energy 730 South Avenue Youngstown, Ohio 44502

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-8

Mr. Randy Renstrom, 330-740-7505

4. City of Youngstown Wastewater Treatment Plant Mr. Tom Mirante, 330-742-8820

5. Dominion - East Ohio Gas

1165 West Rayen Avenue Youngstown, Ohio 44502 Construction and Engineering Department, 330-746-7611 Engineering Department, 330-742-8137

Mr. Jerry Lawson, 330-742-8121

6. Air Pollution Mahoning/Trumbull Counties 345 Oak Hill Avenue Youngstown, Ohio Ms. Tara Cioffi 330-743-3333, ext. 283

7. City of Youngstown, Deputy Director of Public Works Mr. Chuck Shasho, 330-742-8800

8. Youngstown Thermal

236 North Champion Street Youngstown, Ohio 44512 (330) 743-7712

1.09 PROTECTION OF UTILITIES

A. Preserve in operating condition all active utilities traversing the construction/demolition area designated to remain.

B. Before starting demolition, check to determine that all utilities services, such as water, gas,

electricity and telephone, have been disconnected at the mains (at the street), in accordance with the rules and regulations governing the utility involved. Preserve all active utility mains traversing the project.

PART 2 PRODUCTS 2.01 FILL MATERIAL

A. Fill material shall be clean dry soil obtained from an offsite borrow source and meet ODOT 203

and per Section 02050 - 1.02,B-10. Backfill materials shall meet the stringent compaction requirements as stipulated in Section 203.06 and 203.07 of the State of Ohio, Department of Highway, Construction, and Material Specifications, 2016 edition. Shale, slag, rock and random materials as specified in ODOT 203.03 will not be accepted for backfill material. Suitable materials for backfill shall meet the requirements of ODOT 703.16 and as restricted in 203.03.

2.02 TEMPORARY BARRICADES

A. Unless otherwise specifically approved by the Engineer, use only new and solid lumber of utility

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-9

grade or better to construct temporary barricades around the objects designated to remain or for safety purposes.

B. The Contractor shall furnish and erect all temporary sidewalks, barricades, covers and other

temporary structures for the proper and safe conduct of the work as required by law. And shall remove all such temporary structures upon the completion of the work under this contract, without additional compensation.

C. If and whenever the work under this contract shall require the excavation of, use of or occupancy

of any public way, area, alley or other public place, the Contractor shall furnish, erect and maintain such barriers and lights during the night time and will prevent the occurrence of any damage caused in connection with such digging up, use and occupancy, and shall assume liability for all damages which may result therefrom.

2.03 BACKFILL AND COMPACTION

A. Entire basement/foundation areas shall be 100% cleaned of all debris. Foundation walls, footers, and all floors will be completely removed to native soils, unless otherwise directed.

B. The cleaned out basement/foundation area(s) shall be backfilled to match existing grade and

compacted to conform with Item #203 of the State of Ohio Department of Transportation Construction and Materials Specifications, 2016 edition (or most current) backfill material shall be accepted, in accordance ODOT 703.16 and compacted per 203.06 or 203.07 (more stringent). Shale, rock, slag and random materials as specified in ODOT 203.03 will not be accepted for backfill material. A Testing Laboratory Service shall be on-site during all filling activities. Testing for compaction shall be paid for by the Contractor. This shall include all soil tests, on-site testing and verification.

C. Immediately following demolition of the structure, hauling away of debris will commence. All

sheds, garages, and accessory buildings and other trash, shrubs, fallen trees, etc. are to be removed from the premises along with the principal structure. Include the cost for this removal in the total bid for the demolition.

D. The Contractor will not move to another location until the demolished structure is hauled away as

RACM and the building void(s) backfilled. Only during Holidays, weekends or heavy rains will there be exceptions to this rule.

E. After the building basement/foundation area(s) have been backfilled and graded to match existing grade, the areas will be temporarily seeded and mulched to prevent erosion of the backfill, unless otherwise directed by the Engineer.

2.04 EXPLOSIVES

A. Explosive: Use of explosives is not permitted for this work. 2.05 OTHER MATERIALS

A. All other materials, not specifically described but required for proper completion of the work in this Section shall be as selected by the Contractor subject to approval of the Engineer.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-10

2.06 WATER SUPPLY

A. The City of Youngstown may furnish the Contractor water in the execution of this contract wherever water mains and hydrants are available. The water will be furnished at the rate or cost established by City and this cost shall be charged to the Contractor for payment which is to be made to the City of Youngstown according to the conditions in terms of the procedures outlined by the City.

B. The cost of water usage will be determined by City of Youngstown. The cost of the water used

from the hydrants during the demolition project will be the responsibility of the Contractor. The current cost of water in the City of Youngstown is $28.50/1,000 gallons.

C. The Contractor shall make all necessary water connections and extensions at his own expense

and use the same subject to the rules and regulations of the City of Youngstown. PART 3 EXECUTION 3.01 NOTIFICATION

A. Notify the Engineer at least ten (10) full working days in writing prior to commencing the work of this Section.

3.02 SITE INSPECTION

A. Prior to all work of this Section, carefully inspect the entire site and all objects designated to be removed and/or to be salvaged.

B. Locate all existing utility lines and determine all requirements for connection to them where applicable.

C. Locate all existing active utility lines traversing the site and determine the requirements for their protection.

3.03 SCHEDULING

A. Schedule all work in a careful manner with all necessary consideration for neighbors and the public.

3.04 TRAFFIC CONTROL

A. All traffic controls, sidewalk closures and barricades must be erected and maintained in compliance with the State of Ohio Manual of Uniform Traffic Control Devices for Streets and Highways and in compliance with the City of Youngstown requirements.

3.05 REMOVAL OF DEMOLITION DEBRIS

A. All excess, surplus and waste materials, including existing items obtained from demolition shall be removed from the site and properly disposed of by the Contractor. Materials shall be cleaned up daily and the entire work area kept in a neat, orderly and workmanlike condition. Upon

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-11

completion of all operations, the Contractor shall do all things as may be necessary or required by the Engineer to satisfactorily complete the work and leave same in a neat, orderly and usable condition.

The Contractor shall, within 10 days of the contract submittal provide a detailed cost and method of disposal of the debris (concrete, steel, etc.)

1. Construction Waste - The material resulting from the demolition of the facility. All material

must be disposed of in a landfill licensed to accept the type of material(s), except for the structural steel, structural steel may be rinsed off and recycled.

3.06 SITE RESTORATION

A. Site Grading: Uniformly grade the area of demolished building structures to the existing grade, providing a smooth surface, free from irregular surface changes. Provide a smooth transition between adjacent existing grades and new grades. Graded areas shall have a minimum 2% finished slope to provide positive surface drainage.

B. The contractor shall temporarily seed and mulch all areas disturbed by the demolition activities including but not limited to backfill of driveways, basements, retaining walls, out buildings, and garages, etc.

3.07 DAMAGE

A. The Contractor shall be responsible for all damage to existing materials, structures, and surfaces. Restore any damage to original condition or repair as directed, at no additional charge to the owner.

3.08 PROCEDURES

A. The Contractor shall furnish and erect all barriers, enclosure chutes, catch platforms and necessary shoring and provide and maintain approved Danger, Warning, and "Keep Out" signs at places and locations where the placing of such signs is warranted.

B. Demolish items and perform other demolition work in such a manner as to avoid hazards to

persons and property, interference with the use of adjacent property, and interruption of free passage to and from such property. This work shall be prosecuted in strict accordance with the covenants, terms and conditions in this specification, as well as, with all rules, regulations, codes, and laws, Federal, State and Local as may govern such operation.

3.09 SEQUENCING AND SCHEDULE

A. The work of this Section shall be carried out as specified, any modifications must be approved by the Engineer, in writing. The working hours for the project are weekdays 7:00a.m to 5:00 p.m. and weekends from 7:00 a.m. to 5:00 p.m.

3.10 DUST CONTROL

A. The Contractor shall provide dust suppression during all demolition activities in accordance with 40 CFR, Part 61, Subpart M (NESHAP) and any other State or Local regulations, as applicable.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-12

B. Dust control and all related costs will be the responsibility of the Contractor. Fugitive emissions

must be kept to a minimum while the building is being demolished. At no time shall the visible fugitive emissions travel beyond thirty (30) feet of the building.

C. The Contractor shall not cause or permit any fugitive dust source from the building demolition

without taking or installing reasonably available control measures to prevent fugitive dust from becoming airborne. Such reasonably available control measures shall include, but not limited to, one or more of the following which are appropriate to minimize or eliminate visible particulate emissions of fugitive dust in accordance with the Ohio Administrative Code (OAC) 3745-17-08(B). If the Contractor violates or fails to properly control fugitive dust, in accordance with OAC 3745-17-08(B), the Contractor will be fined $2,500 per day, in accordance with the Ohio Revised Code (ORC) 3704.99.

3.11 INGRESS AND EGRESS

A. The Contractor will be responsible for replacing any broken cement sidewalks, drives or curbs which may occur as a result of his ingress and egress from the site or from the demolition of the former theatre building, as required.

3.12 SAFETY PRECAUTIONS AND CLEANING UP

A. The operation of the Contractor shall be done in such a manner as to avoid fires and other hazards to persons and property and interference with the use of adjacent buildings and without interruption of free passage to and from such buildings.

B. Upon release of a structure for demolition by the owner to the Contractor, the Contractor shall

take all precautions necessary against damages to persons or property before and during the demolition period.

3.13 ADDITIONAL SPECIFICATIONS

A. All sewers must be capped in the presence of an Owner or Owner’s Representative. Before the empty hole of a demolished structure can be backfilled, it must be viewed by the Owner or Owner’s Representative.

B. The Contractor is required to provide the Engineer with daily and weekly reports of labor and

equipment hours expended on the project. Hours should be detailed, by area and by task, and by regular hours and overtime hours.

C. Refer to –Supplemental Specifications, included herein for the Contractor’s use.

3.14 ADDITIONAL COSTS

A. The total bid cost shall include all loading, hauling, transporting, disposal costs, tipping fees and other required fees, taxes and/or surcharges as imposed by any federal, state or local agency or landfill.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\24 - 02050-Building Demolition.doc 02050-13

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\25 - 02050 - Supplemental Specs to this Section. Originally Section 8 from the COY - modified by B. Fischer.doc 02050 SS - 1

SUPPLEMENTAL SPECIFICATIONS

TO SECTION 02050 – BUILDING DEMOLITION

SCOPE OF WORK The work involves the furnishing of all labor, materials, tools, and equipment necessary for the demolition and removal of all buildings, sheds, fence posts, porches, steps, walks, curbs, walls, drives paved with brick, stone, asphalt, concrete, etc., and any other frame or masonry structure which is on the surface or extends above the surface, and any rubbish or debris within the property line boundaries of the parcel on which the building to be demolished is situated, including the devil strips. DEMOLITION AND REMOVAL PROCEDURES When a structure has a basement or vault that extends beyond the property line and into the City Right-of-way, the contractor will remove the sidewalk, concrete, pavement, brick, stone or paving and backfill the basement or vault with clean fill as stipulated in Section 203.12 of the State of Ohio, Department of Transportation Construction and Material Specifications, most recent issue. The contractor shall remove all coalhole covers, trap doors, lights, gratings and similar appurtenances that occur in the public sidewalk adjacent to the buildings to be removed. The contractor shall cause to be disconnected the sewer utilities that serve each building to be demolished. All sanitary sewer laterals shall be exposed within 5 feet outside of the foundation and capped using the appropriate sized cap and flexible coupling. All work must be inspected by the City of Youngstown Engineering Department or the ms consultants, inc., (ms) representative. The contractor shall contact the Engineering Department at 330-742-8800, or ms at (330) 744-5321, twenty-four (24) hours before starting the work set forth in this paragraph. When the removal of sidewalks has been made necessary to perform any of the work provided for in this contract, the voids or spaces resulting from such removal shall be replaced in kind by the contractor at no additional expense to the City of Youngstown. The contractor shall remove the entire structure, including all walls, floors, ceilings and foundation supports of all kinds to native soils. Cellars of demolished structures in which clean up of debris has been completed shall not be backfilled until a final inspection has been made and approval given by the inspector in charge of the work. Final payment shall not be made where inspection of cellars has not been made prior to backfilling.

Contractor must call in and inform the assigned ms inspector of the houses he will be tearing

down. The City or ms inspector must see this structure the same day before the structures is to be razed. The contractor will not move to another location until the demolished structure is hauled away and the hole backfilled. Holidays, weekends, heavy rains, and snow will be the only exceptions to this rule, as approved by the project inspector.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\25 - 02050 - Supplemental Specs to this Section. Originally Section 8 from the COY - modified by B. Fischer.doc 02050 SS - 2

The contractor shall protect all sidewalks, curbs, pavements and other public or private facilities that may be damaged or endangered by the work required under the specifications and shall restore and make good any structure of facility that may be damaged or destroyed. Any damage to city property such as sidewalks, curbs, catch basins, fire hydrants, etc. will be the responsibility of the contractor. Backfilling and final grading shall be such as to present a neat, well drained appearance and to prevent water from draining unnecessarily onto adjacent properties, or collecting on the site. Contractors shall not leave mud or any mess on streets or sidewalks while equipment is being loaded or unloaded. See also Section 339.08 of the Codified Ordinances. All demolition work, once commenced, must be completed within a reasonable time, 72 hours for residential structures and, once started, commercial demolition work must be continued daily until finished (excluding holidays, Sundays and inclement weather days). SCHEDULED TIMES FOR DEMOLITION WORK All demolition activities performed under this contract shall occur between the hours of 7:00 a.m. and 5:00 p.m. daily, excluding legal holidays, Sundays and inclement weather days. The Demolition Director or his designee may approve exceptions to these specified times, upon written request from the contractor. Requests to perform demolition work after dusk will not be approved under any circumstances. BACKFILL Backfill shall consist of soil, rock or granular material approved by the Engineer and shall meet all general requirements of item 202.06 of the Ohio Department of Transportation Construction and Materials Specifications. Masonry material from the demolition site may NOT be mixed with the above backfill. All demolition debris shall be disposed of at an approved landfill. DUMPING AND DISPOSAL OF DEBRIS The contractor shall provide his own site for dumping and disposal of all debris. The dump site must be approved by ms consultants, inc.. All debris from a razed structure must be removed immediately. Contractors must apply for Refuse Haulers permits in accordance with City Ordinance 98-214 and 98-278 and comply with all hauling regulations therein. It shall be illegal to dump debris from any site in basements or to dispose of on any site other than at an approved landfill or at a construction and demolition landfill. LANDFILL MANIFESTS/DEMOLITION PAVEMENT All landfill manifests relating to disposal of demolition debris and asbestos containing building material must be supplied in order to secure payment for demolition. SAFETY PRECAUTIONS The operations of the contractor shall be conducted in such a manner as to avoid fires and other hazards to persons and property and interference with the use of adjacent buildings and without interruption of free passage to and from such buildings.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\25 - 02050 - Supplemental Specs to this Section. Originally Section 8 from the COY - modified by B. Fischer.doc 02050 SS - 3

Upon release of a structure for demolition by the City of Youngstown or ms consultants, inc., to the contractor, the contractor shall take all precautions necessary to avoid damages to persons or property before and during the demolition period. No structure released for demolition shall be burned either while standing or after being demolished. TRAFFIC CONTROL All traffic controls and barricades must be erected and maintained in compliance with the State of Ohio Manual of Uniform Traffic Control Devices for Street and Highways. WATER SUPPLY/DUST CONTROL The City of Youngstown will furnish the Contractor water in the execution of this contract wherever water mains and hydrants are available. The water will be furnished at the rate or cost established by the City of Youngstown Water Department and this cost shall be charged to the Contractor for payment which is to be made to the City of Youngstown Water Department. Permit required from Water Commissioner. Contractor may provide water through an auxiliary source as approved by the Demolition Director. Dust control and all related costs will be the responsibility of the contractor. Dust must be kept to a minimum while the building is being demolished and the debris being hauled away. Contractors must hose down the work site during the operations by connection to city hydrants adjacent to the work site. This is for dust control measures. Contractors will contact the City Water Department for water metering to control dust, unless contractor provides his own water through portable means. UTILITIES The contractor will be responsible for the protection of all above and underground utilities. The contractor will replace at his expense any damage done to the above, caused by the demolition of the building. The Contractor will be required to check with all utility companies and the Ohio Utilities Protection Service to verify location of any and all utilities. UTILITY LINES The Contractor will be responsible for the removal, relocation or damage of any utility lines. TEMPORARY SIDEWALKS AND BARRICADES The Contractor shall furnish and erect all temporary sidewalks, barricades, covers and other temporary structures for the proper and safe conduct of the work as required by law, and shall remove all such temporary structures upon the completion of the work under this contract, without additional compensation. Where basements or excavations are located within five feet (5’) of the street line, a fence shall be erected along the street line and extended five feet (5’) beyond the basement or excavation. The fence shall be constructed of posts measuring 4” x 4” imbedded in the ground at least two feet (2’) and extend not less than three feet (3’) above grade. The posts shall be located not over eight feet (8’) center to center, and provided with a 2” x 4” top rail and a six inch (6”) rail located at the grade line to form a toe

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\25 - 02050 - Supplemental Specs to this Section. Originally Section 8 from the COY - modified by B. Fischer.doc 02050 SS - 4

board, and a six inch (6”) board to serve as an intermediate rail located between the top rail and the toe board. OCCUPANCY OF PUBLIC WAY If and whenever the work under this contract shall require digging up, use or occupancy of any public way, area, alley or other public place, the Contractor shall furnish, erect and maintain such barriers and lights during the night time and will prevent the occurrence of any damage caused in connection with such digging up, use and occupancy, and shall assume liability for all damages which may result therefrom. USE OF EXPLOSIVES The use of explosives in the performance of this contract is hereby expressly prohibited. SPECIAL The Construction and Materials Specifications, Department of Transportation, State of Ohio, most recent issue and the Supplemental Specifications shall govern the workmanship and materials for this improvement. Wherever in the specifications referred to above, the terms “State or Department” is used, it shall be interpreted to mean the City of Youngstown. Wherever in the specifications referred to above the terms “Director”, “Engineer”, or “Inspector” are used, it shall be interpreted to mean the Deputy Director of Public Works, City of Youngstown, or his authorized representative (ms consultants, inc.). PERMITS The Contractor shall obtain any and all permits or licenses that are required by the City of Youngstown or any other authority prior to beginning performance of this contract. The Contractor shall issue any notices that are required by law or municipal ordinance prior to beginning performance of this contract. The Contractor shall bear any and all costs required to obtain any permits or licenses as well as any costs necessary for the issuance of any notices that may be required by law or municipal ordinance. Failure by the Contractor to comply with the provisions of this section shall subject the Contractor to any penalties or costs that may be provided by law or municipal ordinance in addition to withholding contractual payments and invoking the performance bond. Further, the Contractor shall hold the city harmless from any claim arising against the City of Youngstown as a result of the Contractor’s failure to comply with this section. ADJUSTMENT FOR FIRE DAMAGED STRUCTURES Structures that are fire damaged after a contract is let will be renegotiated at a reduced amount to reflect reduction in work required. FINAL GRADING OF LOT All lots listed in the specifications are to be cleared of debris. This debris is to be disposed of at an approved landfill. All lots are then to be filled and graded to an acceptable grade established by the Site Inspector. This grade is to promote proper runoff and to eliminate standing water.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\25 - 02050 - Supplemental Specs to this Section. Originally Section 8 from the COY - modified by B. Fischer.doc 02050 SS - 5

Any additional soil necessary for fill and grading shall be furnished by the contractor and approved for use by the Site Inspector. The contractor shall include the cost of such material in his price bid for demolition. The final grade shall be free of all rocks and debris larger than three (3) inches in diameter.

GENERAL PLAN NOTES FOR DEMOLITION PROJECTS

MAINTENANCE OF TRAFFIC

All traffic control devices used on this project shall be furnished, placed and subsequently removed by the contractor in conformance with the Ohio Manual of Uniform Traffic Control Devices, most current edition, latest revision. The safety and protection of pedestrians and the traveling public shall be of utmost concern and importance throughout the duration of this project. Should the contractor determine that it is necessary to close any traffic lanes during the demolition process, he shall submit for approval an appropriate traffic control plan to the City of Youngstown Traffic Coordinator’s Office at least seven (7) working days prior to the anticipated date of closure. Upon approval of such plan, all lane closures shall be achieved using appropriate signs, cones, barrels, and/or other traffic control devices in accordance with the Ohio Manual of Uniform Traffic Control Devices. All sidewalk area directly adjacent to the demolition activities shall be properly closed and barricaded throughout the demolition project. Sidewalks shall also be properly protected from damage by falling debris through a method determined by the contractor and approved by the City of Youngstown, Deputy Director of Public Works.

DEMOLITION NOTIFICATION OF FEDERAL & OHIO EPA Written notification of the demolition of these structures is required by 40 CFR 61.145(b) and Ohio Administration Code 3745-20-03. The successful bidder must submit a complete, accurate Ohio EPA Notification of Demolition and Renovation for each structure to be demolished at this facility to the Mahoning-Trumbull Air Pollution Control Agency at least 10 working days before the demolition of that structure begins. A copy of the original notification any subsequent revisions will be forwarded by M-TAPCA to U.S. EPA, Region V. To be complete, a notification must contain all the information required by Items I, II, III, IV, V, VI, IX, X, XVI, and XVIII. Compliance with the notification provisions will be determined by the Mahoning-Trumbull Air Pollution Control Agency. Additional forms and instructions are available from the Mahoning-Trumbull Air Pollution Control Agency, Oakhill Renaissance Place, 345 Oak Hill Avenue, Suite 200, Youngstown, Ohio 44502.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\25 - 02050 - Supplemental Specs to this Section. Originally Section 8 from the COY - modified by B. Fischer.doc 02050 SS - 6

Failure of the successful bidder to submit a notification of demolition or to correct notification deficiencies at M-TAPCA’s direction prior to demolition will result in M-TAPCA initiating an enforcement referral against the contractor with the appropriate state and/or federal agency. YOUNGSTOWN CODIFIED ORDINANCE CHAPTER 1309 (ORDINANCE 99-403) The preceding specifications and provisions thereof are further modified by Youngstown City Ordinance Number 99-403, a copy of which is included as follows:

CHAPTER 1309

Demolition of Structures

SECTION 1309.01 Scheduled Times for Demolition Work SECTION 1309.02 Demolition and Removal Procedures SECTION 1309.99 Penalty

CROSS REFERENCES Fire damaged structures – see FIRE PREV. Ch. 1515

1309.01 SCHEDULED TIMES FOR DEMOLITION

Anyone who does demolition work within the City, shall only perform

demolition work between the hours of 7:00 a.m. and 5:00 p.m. daily, excluding legal holidays, Sundays and inclement weather days. The Housing Department Head or their designee may approve exceptions to these specified times, upon written request from the contractor. Requests to perform demolition work after dusk will not be approved under any circumstances.

1309.02 DEMOLITION AND REMOVAL PROCEDURES

In addition to the Section 8 Supplemental Specifications required of each contractor performing demolition work in the City of Youngstown, each contractor shall adhere to the following requirements in performing such demolition work.

(a) The Contractor must obtain and, if requested, display a valid 30-day permit when performing the demolition work. Extensions may be issued by the City of Youngstown Demolition Department. No permits are to be obtained after demolition work is done.

(b) Contractors must apply for Refuse Hauler permits (Ordinance 98-214 and 98-278) and comply

with all hauling regulations therein.

(c) Contractors must hose down the work site during the operations by connecting to the city hydrants adjacent to the work site. This is for dust control measures. Contractors will pay City Water Department a $10.00 (ten dollar) user fee per single residential structure being demolished or $20.00 per commercial structure, if larger than a duplex, unless contractor provides his own water through portable means.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\25 - 02050 - Supplemental Specs to this Section. Originally Section 8 from the COY - modified by B. Fischer.doc 02050 SS - 7

(d) It shall be illegal to dump debris from any site in basements or to dispose of on any site other than

at an approved landfill or a construction and demolition landfill.

(e) Contractors shall remove all garages, sheds and other outbuildings along with shrubs, bushes, walls, fences and foliage from property, along with structures. AND ALL DEPLORABLE MATERIAL MUST BE REMOVED FROM SITE.

(f) When a contractor applies for payment for demolition work performed, all landfill manifests

relating to the disposal of demolition debris and asbestos-containing materials must be supplied in order to secure payment.

(g) Contractors must protect the area around the site during the demolition process to prevent debris

from falling on active sidewalks and streets (not blocked off). Sidewalks, directly adjacent to the site, shall be properly closed and barricaded throughout the demolition project. Street traffic lanes may be closed as needed only in conjunction with the City Traffic Coordinator’s Office.

(h) Contractors shall reasonably grade lots. They shall present a neat, well-drained appearance and to

prevent water from draining unnecessarily onto adjacent properties or collecting on the site.

(i) Contractors shall not leave mud or any mess on streets or sidewalks while equipment is being loaded or unloaded. See Also Section 339.08 of the Codified Ordinances.

(j) All demolition work, once commenced, must be completed within a reasonable time, 72 hours for

residential structures and, once started, commercial demolition work must be continued daily until finished (excluding holidays, Sundays and inclement weather days).

(k) Any damage to city property such as sidewalks, curbs, catch basins, fire hydrants, etc. will be the responsibility of the contractor.

1309.99 PENALTY

(a) Whoever violates any provision of Section 1309.01 of this chapter is guilty of a minor misdemeanor. When any person is found guilty of a subsequent offense, such person is guilty of a misdemeanor of the fourth degree. Such fine is mandatory and shall not be suspended or remitted when found guilty of a third or subsequent offense.

(b) Whoever violates any provision of Section 1309.02 of this chapter shall be guilty of an

unclassified misdemeanor, punishable by up to six (6) months incarceration or a fine of up to five hundred dollars ($500.00) or both.

END OF SUPPLEMENTAL SPECIFICATIONS TO SECTION 02050

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\26 - 02061S96 - Bldg. Component Demo - bkf.doc 02061-1

SECTION 02061

BUILDING COMPONENT DEMOLITION-ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division - 1 Specification Sections, apply to work of this section.

1.2 DESCRIPTION OF THE WORK

A. The work of this Section includes the demolition of components and installations where asbestos containing materials are present.

1.3 RELATED WORK SPECIFIED ELSEWHERE:

A. Work to be completed prior to start of the work of this section are set forth in the following sections: 1. 01560 Worker Protection - Asbestos abatement 2. 01562 Respiratory Protection 3. 01563 Decontamination Units

B. Section 02084 Disposal of Regulated Asbestos-Containing Material describes the handling and

disposal of asbestos-containing waste.

C. Section 02086 Hazardous Waste Management describes the management and disposal of hazardous waste such as PCB Ballasts, fluorescent light tubes, and mercury containing thermostats encountered during the work of this section.

1.4 SUBMITTALS:

A. Before Start of Work: Submit the following to the Engineer/Owner’s Representative for review.

Do not start work until these submittals are returned with Designer's action stamp indicating that the submittal is returned for unrestricted use. 1. Surfactant: Submit product data, use instructions and recommendations from manufacturer

of surfactant intended for use. Include data substantiating that material complies with requirements.

2. Removal Encapsulant: Submit product data, use instructions and recommendations from manufacturer of removal encapsulant intended for use. Include data substantiating that material complies with requirements.

3. NESHAP Certification: Submit certification from manufacturer of surfactant or removal encapsulant that, to the extent required by this specification, the material, if used in accordance with manufacturer's instructions, will wet asbestos-containing materials (ACM) to which it is applied as required by the National Emission Standard for Hazardous Pollutants (NESHAP) Asbestos Regulations (40 CFR 61, Subpart M).

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\26 - 02061S96 - Bldg. Component Demo - bkf.doc 02061-2

B. Before Start of Work submit the following to the Engineer/Owner’s Representative for review.

Do not begin work until these submittals are returned with the Designer's action stamp indicating that the submittal has been Received - Not Reviewed. 1. Safety Data Sheet: Submit Safety Data Sheets, or equivalent, in accordance with the

OSHA GHS Hazard Communication Standard (29 CFR 1910.1200) for the following: a. Surfactants. b. Encapsulants.

PART 2 - PRODUCTS: 2.1 MATERIALS

A. Wetting Materials: For wetting prior to disturbance of ACM use either amended water or a removal encapsulant:

B. Amended Water: Provide water to which a surfactant has been added. Use a mixture of

surfactant and water which results in wetting of the ACM and retardation of fiber release during disturbance of the material equal to or greater than that provided by the use of one ounce of a surfactant consisting of 50 percent polyoxyethylene ester and 50 percent polyoxyethylene ether mixed with five gallons of water.

C. Removal Encapsulant: Provide a penetrating type encapsulant designed specifically for removal

of ACM. Use a material which results in wetting of the ACM and retardation of fiber release during disturbance of the material equal to or greater than that provided by water amended with a surfactant consisting of 50 percent polyoxyethylene ester and 50 percent polyoxyethylene ether mixed with five gallons of water.

D. Polyethylene Sheet: A single polyethylene film in the largest sheet size possible to minimize

seams, 6.0 mil (0.15 mm) thick frosted, or black as indicated.

E. Duct Tape: Provide duct tape in 2 inch or 3 inch (51 mm or 76 mm) widths as indicated, with an adhesive which is formulated to stick aggressively to sheet polyethylene.

F. Spray Cement: Provide spray adhesive in aerosol cans which is specifically formulated to stick

tenaciously to sheet polyethylene. PART 3 - EXECUTION 3.1 WORKER PROTECTION:

A. Before beginning work with any material for which a Safety Data Sheet has been submitted provide workers with the required protective equipment. Require that appropriate protective equipment be used at all times.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\26 - 02061S96 - Bldg. Component Demo - bkf.doc 02061-3

3.2 REMOVAL OF ARCHITECTURAL FINISHES, AND THERMAL SYSTEM INSULATION: A. Isolate Work Area: from the building exterior and other portions of the building. Where

existing walls, doors, windows, or other such closure is missing, seal openings with polyethylene sheet at least 6 mil (0.15 mm) in thickness, mechanically fastened in place and sealed with duct tape or spray glue. Seal broken windows or other openings to the building exterior with nylon-reinforced plastic.

B. Drop Cloth: Install a drop cloth consisting of clear 6 mil (0.15 mm) sheet plastic in any area

where asbestos removal work is to carried out. C. Adequately wet ACM to be removed prior to stripping and/or tooling to reduce fiber dispersal

into the air. Accomplish wetting by a fine spray (mist) of water, amended water or removal encapsulant. Saturate material sufficiently to wet to the substrate without causing excess dripping. Allow time for water, amended water or removal encapsulant to penetrate material thoroughly. If water or amended water is used, spray material repeatedly during the work process to maintain a continuously wet condition. If a removal encapsulant is used, apply in strict accordance with manufacturer's instructions. Perforate outer covering of any installation which has been painted and/or jacketed in order to allow penetration of water, amended water or removal encapsulant, or where necessary, carefully strip away while simultaneously wetting the installation to minimize dispersal of asbestos fibers into the air.

D. Remove Saturated ACM in small sections from all areas. Scrape materials from substrate and

remove residue using nylon bristled hand brush or high pressure washer. Remove materials in manageable quantities and control the descent to staging or floor below. If height is over 20' use drop chute to contain material during descent. If using water or amended water spray mist continuously during work process. Do not allow material to dry out. As it is removed, simultaneously pack material while still wet into disposal bags. Seal bags, clean outside and move to washdown station adjacent to Material Decontamination Unit.

E. At Completion of Removal Work: Clean all surfaces in the removal area by wet wiping, HEPA

vacuuming or washing down with hoses. Clean from top down. At Contractor's option a proportional feed nozzle may be used to add a surfactant to the water. Collect any water runoff and filter through a dual filtration system. Provide first filter that removes fibers 20 microns and larger, and a final filter that removes all fibers 5 microns and larger.

F. Visual Inspection: Visually inspect work area for debris. If any visible debris is noted, clean all

surfaces in the Work Area again. Continue this procedure until no visible debris is found in the Work Area.

G. Final Air Testing: (NOT USED) Clear the Work Area in accordance with requirements of

section 01711 Project Decontamination. 3.3 HAZARDOUS WASTE MANAGEMENT AND DISPOSAL.

A. Manage and dispose of hazardous waste such as PCB ballasts, fluorescent light tubes, and

mercury thermostats in accordance with the requirements of Section 02086 - Hazardous Waste Management.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\26 - 02061S96 - Bldg. Component Demo - bkf.doc 02061-4

B. Do not mix potentially hazardous waste streams. Where feasible, separate each type of hazardous waste from other types of hazardous wastes, from asbestos waste and from construction waste.

C. Segregate, package, label, transport and dispose of Hazardous Waste in accordance with DOT,

EPA, State and Local regulations. 3.4 DISPOSAL OF WASTE:

A. Pack: All asbestos-containing or contaminated waste material in bags marked as required by GHS – HAZCOMM and Section 02084 Disposal of Regulated Asbestos-Containing Material.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\27 - 02081S96 - Removal of Asbestos Containing Materials - bkf.doc02081 - 1

SECTION 02081

REMOVAL OF ASBESTOS-CONTAINING MATERIALS PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division - 1 Specification Sections, apply to work of this section.

1.2 RELATED WORK SPECIFIED ELSEWHERE:

A. Worker Protection requirements are set forth in Section 01560 Worker Protection - Asbestos abatement.

B. Installation of Critical and Primary Barriers, and Work Area Isolation Procedures are set forth

in Section 01526 Temporary Enclosures.

C. Project Decontamination procedures after removal of the Secondary Barrier are specified in Section 01711 Project Decontamination.

D. Disposal of asbestos-containing waste is specified in Section 02084 Disposal of Regulated

Asbestos-Containing Material.

E. Section 02086 Hazardous Waste Management describes the management and disposal of hazardous waste such as PCB Ballasts, fluorescent light tubes, and mercury containing thermostats encountered during the work of this section.

1.3 SUBMITTALS:

A. Before Start of Work submit the following to the Engineer/Owner’s Representative for

review. Do not begin work until these submittals are returned with the Designer's action stamp indicating that the submittal has been Received - Not Reviewed.

1. Safety Data Sheet: Submit Safety Data Sheets, or equivalent, in accordance with the GHS -

OSHA Hazard Communication Standard (29 CFR 1910.1200) for the following:

a. Surfactants.

b. Encapsulants.

c. Solvents. PART 2 - PRODUCTS: 2.1 MATERIALS

A. Wetting Materials: For wetting prior to disturbance of ACM use either amended water or a removal encapsulant:

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\27 - 02081S96 - Removal of Asbestos Containing Materials - bkf.doc02081 - 2

B. Amended Water: Provide water to which a surfactant has been added. Use a mixture of

surfactant and water which results in wetting of the ACM and retardation of fiber release during disturbance of the material equal to or greater than that provided by the use of one ounce of a surfactant consisting of 50 percent polyoxyethylene ester and 50 percent polyoxyethylene ether mixed with five gallons (19 liters) of water.

C. Removal Encapsulant: Provide a penetrating type encapsulant designed specifically for removal

of ACM. Use a material which results in wetting of the ACM and retardation of fiber release during disturbance of the material equal to or greater than that provided by water amended with a surfactant consisting of one ounce of a mixture of 50 percent polyoxyethylene ester and 50 percent polyoxyethylene ether in five gallons (19 liters) of water.

D. Polyethylene Sheet: A single polyethylene film in the largest sheet size practicable to minimize

seams, 6.0 mil (0.15 mm) thick clear, frosted, or black as indicated.

E. Duct Tape: Provide duct tape in 2 inch or 3 inch (50mm or 75 mm) widths as indicated, with an adhesive which is formulated to stick aggressively to sheet polyethylene.

F. Spray Cement: Provide spray adhesive in aerosol cans which is specifically formulated to stick

tenaciously to sheet polyethylene.

G. Disposal Bags: Provide 6 mil (0.15 mm) thick leak-tight polyethylene bags labeled as required by Section 02084 Disposal of Regulated Asbestos Containing Material.

H. Fiberboard Drums: Provide heavy duty leak tight fiberboard drums with tight sealing locking

metal tops.

I. Paper board Boxes: Provide heavy duty corrugated paper board boxes coated with plastic or wax to retard deterioration from moisture. Provide in sizes that will easily fit in disposal bags.

J. Felt: Standard felt approximately 1/16 inch (1.6 mm) thick and 36 inches (900 mm ) to 72 inches

(1800 mm) in width. PART 3 - EXECUTION 3.1 SECONDARY BARRIER:

A. Secondary Barrier: Over the Primary Barrier, install as a drop cloth a clear 6 mil (0.15 mm) sheet plastic in all areas where asbestos removal work is to be carried out. Completely cover floor with sheet plastic, where the floor is to remain. Where the work is within 10 feet (3 m) of a wall extend the Secondary Barrier up wall to ceiling. Support sheet plastic on wall with duct tape, seal top of Secondary plastic to Primary Barrier with duct tape so that debris is unable to get behind it. Provide cross strips of duct tape at wall support as necessary to support sheet plastic and prevent its falling during removal operations.

1. Install Secondary Barrier at the beginning of each work shift. Install only sufficient

plastic for work of that shift.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\27 - 02081S96 - Removal of Asbestos Containing Materials - bkf.doc02081 - 3

2. Remove Secondary Barrier at end of each work shift or as work in an area is completed. Fold plastic toward center of sheet and pack in disposal bags. Keep material on sheet continuously wet until bagged.

3. Install Walkways of black 6 mil (0.15 mm) plastic between active removal areas and

decontamination units to protect Primary Layer from tracked material. Install walkways at the beginning of, and remove at the end of, each work shift.

3.2 WORKER PROTECTION:

A. Before beginning work with any material for which a Safety Data Sheet has been submitted provide workers with the required protective equipment. Require that appropriate protective equipment be used at all times.

3.3 WET REMOVAL:

A. Thoroughly wet the ACM to be removed prior to stripping and/or tooling to reduce fiber

dispersal into the air. Accomplish wetting by a fine spray (mist) of amended water or removal encapsulant. Saturate material sufficiently to wet to the substrate without causing excess dripping. Allow time for amended water or removal encapsulant to penetrate material thoroughly. If amended water is used, spray material repeatedly during the work process to maintain a continuously wet condition. If a removal encapsulant is used, apply in strict accordance with manufacturer's written instructions. Perforate outer covering of any installation which has been painted and/or jacketed in order to allow penetration of amended water or removal encapsulant, or use injection equipment to wet material under the covering. Where necessary, carefully strip away while simultaneously spraying amended water or removal encapsulant on the installation to minimize dispersal of asbestos fibers into the air. 1. Mist work area continuously with amended water whenever necessary to reduce airborne

fiber levels.

2. Remove saturated ACM in small sections from all areas. Do not allow material to dry out. As it is removed, simultaneously pack material while still wet into disposal bags. Twist neck of bags, bend over and seal with minimum three wraps of duct tape. Clean outside and move to Wash Down Station adjacent to Material Decontamination Unit.

B. Architectural Finish on Scratch Coat: Spray asbestos-containing architectural acoustic finish

with a fine mist of amended water or removal encapsulant. Allow time for amended water or removal encapsulant to saturate materials to substrate. Do not over-saturate to cause excess dripping. Scrape materials from substrate. Remove materials in manageable quantities and control the descent to staging or floor below, if over 20 feet (6000 mm) use drop chute to contain material during descent. If using amended water, spray mist surface continuously during work process. If using removal encapsulant follow manufacturer's written instructions. Remove residue remaining on scratch coat after scraping using stiff nylon bristled hand brush.

C. Architectural Finish on Wire Lath: Spray asbestos-containing architectural acoustic finish with

a fine mist of amended water or removal encapsulant. Allow time for amended water or removal encapsulant to saturate material completely. Do not over-saturate to cause excess dripping. If

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\27 - 02081S96 - Removal of Asbestos Containing Materials - bkf.doc02081 - 4

surface of material has been painted or otherwise coated cut small holes as required and apply amended water or removal encapsulant from above. Cut wire lath into manageable sections and cut hanger wires. Roll or fold up complete with ACM and hand place in container. Do not drop on floor. After removal of lath and ACM remove any overspray on decking and structure above using stiff nylon bristled brush. Use one of the following methods for containing waste.

1. Deposit material in corrugated paper board box. When box is full duct tape closed and

place in disposal bag.

2. Wrap material in felt and place in fiberboard drum lined with two disposal bags. Use caution to insure that all edges of wire lath that could cut plastic are covered with felt.

3. Place material directly in a steel drum. Seal drums when full with leak tight seal. Drum

is to be leak tight in any orientation.

D. Pipe Insulation: Spray with a mist of amended water or removal encapsulant. Allow amended water or removal encapsulant to saturate material to substrate. If a removal encapsulant is used, use in strict accordance with manufacturer's instructions. Cut bands holding preformed pipe insulation, slit jackets at seams, remove and hand-place in a disposal bag. Remove job-molded fitting insulation in chunks and hand place in a disposal bag. Do not drop to floor. Remove any residue on pipe or fitting with stiff bristle nylon hand brush. In locations where pipe fitting insulation is removed from pipe with straight runs insulated with fibrous glass or other non-asbestos-containing fibrous material, remove fibrous material 6" (150 mm) from the point where it contacts the asbestos-containing insulation.

3.4 HAZARDOUS WASTE MANAGEMENT AND DISPOSAL.

A. Manage and dispose of hazardous waste such as PCB ballasts, fluorescent light tubes, and

mercury thermostats in accordance with the requirements of Section 02086 - Hazardous Waste Management.

B. Do not mix potentially hazardous waste streams. Where feasible, separate each type of

hazardous waste from other types of hazardous wastes, from asbestos waste and from construction waste.

C. Segregate, package, label, transport and dispose of Hazardous Waste in accordance with DOT,

EPA, State and Local regulations.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\28 - 02084S96 - Disposal of Regulated Asbestos Containing Material - bkf.doc 02084 -1

SECTION 02084

DISPOSAL OF REGULATED ASBESTOS-CONTAINING MATERIAL PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification Sections, apply to work of this section.

1.2 RELATED WORK SPECIFIED ELSEWHERE:

A. Worker protection requirements are set forth in Sections 01560 Worker Protection - Asbestos abatement

B. Section 01098 Codes, Regulations and Standards - Asbestos Abatement describes applicable

federal, state and local regulations.

C. Ohio Department of Health – Asbestos Hazard Abatement Rules, Chapter 3701-34, Ohio Administrative Code, Amended February 1, 1993, Effective 11/3/2012.

1.3 DESCRIPTION OF THE WORK:

A. This section describes the disposal of Regulated Asbestos-Containing Materials (RACM). Disposal includes packaging of Regulated Asbestos-Containing Materials.

1.4 SUBMITTALS:

A. Before Start of Work: Submit the following to the Engineer/Owner’s Representative for review. Do not start work until these submittals are returned with Designer's action stamp indicating that the submittal is returned for unrestricted use.

1. Copy of state or local license for waste hauler. 2. Name and address of landfill where Regulated Asbestos Containing Materials are to be

buried. Include contact person and telephone number. 3. Chain of Custody form and form of waste manifest proposed

4. Sample of disposal bag and any added labels to be used.

B. On a weekly basis submit copies of all manifests and disposal site receipts to Engineer/Owner’s

Representative.

C. Waste Shipment Record: Maintain a waste shipment record as required by the NESHAP regulation which indicates the waste generator, transporter, and disposal site, and which describes the nature, size, type of container, and form of asbestos waste. Submit to Owner within 35 days of departure from building.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\28 - 02084S96 - Disposal of Regulated Asbestos Containing Material - bkf.doc 02084 -2

PART 2 - PRODUCTS: 2.1 MATERIALS

A. Disposal Bags: Provide 6 mil (0.15 mm) thick leak-tight polyethylene bags labeled with three labels with text as follows: 1. First Label: Provide in accordance with 29 CFR 1910.1200(f) of OSHA's GHS - Hazard

Communication standard. As of June 1, 2016 the new label below must be used. DANGER CONTAINS ASBESTOS FIBERS MAY CAUSE DAMAGE TO LUNGS DO NOT BREATHE DUST AVOID CREATING DUST

2. Second Label: Provide in accordance with U. S. Department of Transportation regulation on hazardous waste marking. 49 CFR parts 171 and 172. Hazardous Substances

ASBESTOS CLASS 9 NA2212-PG III, RQ

3. Third Label: Provide the name of the waste generator (Owner's name), the location from which the waste was generated and the names and addresses of the contractor and transporter. This label must be durable, able to repel dirt and moisture (e.g., permanent marker). Label must be placed directly on disposal bag(s) in a legible format. Peel and stick type labels are expressly prohibited.

PART 3 - EXECUTION 3.1 SEQUENCE

A. Comply with the following sections during all phases of this work:

1. Section 01560 Worker Protection - Asbestos Abatement

2. Section 01562 Respiratory Protection 3.2 GENERAL:

A. All waste is to be hauled by a waste hauler with all required licenses from all state and local authority with jurisdiction.

B. Liquid waste: Mix all liquid asbestos-containing waste or asbestos contaminated waste with a

bladeable material so that it forms a bladeable (non-liquid) form, and have the concurrence of the landfill operator prior to disposal.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\28 - 02084S96 - Disposal of Regulated Asbestos Containing Material - bkf.doc 02084 -3

C. Load all adequately wetted Regulated Asbestos-Containing Material in disposal bags or leak-tight containers. All materials are to be contained in one of the following

1. Two 6 mil (0.15 mm) disposal bags or 2. Two 6 mil (0.15 mm) disposal bags and a fiberboard drum or

3. Sealed steel drum with no bag

D. Protect interior of truck or dumpster with Critical and Primary Barriers as described in Section

01526 Temporary Enclosures.

E. Carefully load containerized waste in fully enclosed dumpsters, trucks or other appropriate vehicles for transport. Exercise care before and during transport, to insure that no unauthorized persons have access to the material.

F. Warning Signs: During loading and unloading mark dumpsters, receptacles and vehicles with a

sign complying with requirements of the EPA NESHAP regulation (40 CFR Part 61), in a manner and location that a person can read the following legend : This signage is required after June 1, 2016.

DANGER

ASBESTOS MAY CAUSE CANCER

CAUSES DAMAGE TO LUNGS AUTHORIZED PERSONNEL ONLY

G. Do not store containerized materials outside of the Work Area. Take containers from the

Work Area directly to a sealed truck or dumpster.

H. Do not transport disposal bagged materials on open trucks. Label drums with same warning labels as bags. Uncontaminated drums may be reused. Treat drums that have been contaminated as Regulated Asbestos-Containing Material and dispose of in accordance with this specification.

I. Advise the landfill operator or processor, at least ten days in advance of transport, of the quantity

of material to be delivered.

J. At disposal site unload containerized waste:

1. At a disposal site, sealed plastic bags may be carefully unloaded from the truck. If bags are broken or damaged, return to work site for re-bagging. Clean entire truck and contents using procedures set forth in section 01711 Project Decontamination.

K. Retain receipts from landfill for materials disposed of.

L. At completion of hauling and disposal of each load submit copy of waste manifest, chain of

custody form, and landfill receipt to the Engineer/Owner’s Representative.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\29 - 02086S96 - Hazardous Waste Mgmt - bkf.doc 02086 -1

SECTION 02086

HAZARDOUS WASTE MANAGEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification Sections, apply to work of this section.

1.2 RELATED SECTIONS

A. Section 01092 Codes and Regulations - Asbestos Abatement describes federal, state and local regulations applicable to asbestos.

B. Section 02084 Disposal of Regulated Asbestos-Containing Material describes the handling and

disposal of asbestos-containing waste. 1.3 DESCRIPTION OF THE WORK:

A. This section describes the segregation, packaging, labeling, transport, and disposal of waste materials generated by abatement activities and the subsequent shipment of properly packaged and labeled waste materials to an approved disposal site.

1.4 CODES AND REGULATIONS

A. General Applicability of Codes and Regulations: Except to the extent that more explicit or

more stringent requirements are written directly into the Contract Documents, all applicable codes and regulations have the same force and effect (and are made a part of the contract documents by reference) as if copied directly into the Contract Documents, or as if published copies are bound herewith.

B. Contractor Responsibility: The Contractor shall assume full responsibility and liability for the

compliance with all applicable Federal, State, and local regulations pertaining to hazardous waste management and disposal. Hold the Owner and Designer harmless for failure to comply with any applicable work, hauling, disposal, safety, health or other regulation on the part of the Contractor, the Contractor’s employees, or Subcontractors.

C. Federal Requirements: which govern the management, hauling and disposal of hazardous waste

include but are not limited to the following:

1. DOT: U. S. Department of Transportation, including but not limited to:

a. Hazardous Substances Title 49, Part 171 and 172 of the Code of Federal Regulations

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\29 - 02086S96 - Hazardous Waste Mgmt - bkf.doc 02086 -2

b. Hazardous Material Regulations General Awareness and Training Requirements for Handlers, Loaders and Drivers Title 49, Parts 171-180 of the Code of Federal Regulations

c. Hazardous Material Regulations

Editorial and Technical Revisions Title 49, Parts 171-180 of the Code of Federal Regulations

2. EPA: U. S. Environmental Protection Agency (EPA), including but not limited to:

a. Management of Hazardous Wastes Resource Conservation and Recovery Act

(RCRA) Title 40, Parts 260- 268 of the Code of Federal Regulations

D. State Requirements: Abide by all state requirements which govern the management, hauling

and disposal of hazardous waste.

E. Local Requirements: Abide by all local requirements which govern the management, hauling and disposal of hazardous waste.

1.5 DEFINITIONS:

A. Toxicity Characteristic Leaching Procedure (TCLP): A laboratory test method to determine

the mobility of both organic and inorganic analytes present in liquid, solid, and multiphasic wastes performed in accordance with test methods required under 40 CFR Part 268.

1.6 SUBMITTALS:

A. Before Start of Work: Submit the following to the Engineer/Owner’s Representative for review. Do not start work until these submittals are returned with Engineer's action stamp indicating that the submittal is returned for unrestricted use.

1. Copy of state and local licenses for waste hauler.

2. U.S. EPA Identification Number of waste hauler.

3. Name and address of waste disposal facility where hazardous waste materials are to be

disposed including: a. Contact person and telephone number.

b. Copy of state license and permit

c. Disposal facility permits

4. Specimen copy of Uniform Hazardous Waste Manifest form.

5. Copy of EPA Notice of Hazardous Waste activity form

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\29 - 02086S96 - Hazardous Waste Mgmt - bkf.doc 02086 -3

6. Copy of forms requires by state and local agencies

7. Sample of disposal label to be used.

B. During Work: Submit the following as required by the work.

1. TCLP test results, as required to characterize waste for segregation and packaging purposes.

2. Submit copies of all executed manifests and disposal site receipts to the Designer.

PART 2 - PRODUCTS: 2.1 MATERIALS

A. Disposal Bags: Provide 6 mil (0.15 mm) thick leak-tight polyethylene bags. B. DOT Hazardous Waste Disposal Drums: Provide DOT 17-H Open -Top Drums (55 gallon) in

accordance with DOT regulations title 49 CFR Parts 173, 178, and 179.

C. DOT Hazardous Waste Labels: in accordance with DOT regulations Title 49 CFR parts 173, 178, and 179.

PART 3 - EXECUTION 3.1 GENERAL

A. Do not mix potentially hazardous waste streams. Where feasible, separate each type of hazardous waste from other types of hazardous wastes, from asbestos waste and from construction waste.

B. Segregate, package, label, transport and dispose of Hazardous Waste in accordance with DOT,

EPA, State and Local regulations. 3.2 HAZARDOUS WASTE:

A. The following waste products are designated by the Owner as non-salvageable and as Hazardous Waste Types:

1. Waste Type A: PCB waste.

a. PCB-containing ballasts from fluorescent light fixtures.

2. Waste Type B: Mercury-containing waste. a. Thermostats with mercury switches. Individually bagged mercury-containing

thermostats. b. Fluorescent, and mercury-vapor lamps.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\29 - 02086S96 - Hazardous Waste Mgmt - bkf.doc 02086 -4

3.1 Hazardous Waste Packaging and Labeling: Package each segregated Hazardous Waste Type, A and B, in specified containers as follows. IMPORTANT: Do Not Mix Waste Streams:

A. Waste Type A

1. Package in DOT 17-H Open-Top Drums

2. Fill to capacity only with Waste Type A (Do Not Mix Waste Stream types).

3. Install gasket on lid, apply lock ring, and seal. 4. Apply Hazardous Waste Label to drum side.

5. Enter DOT Shipping Data as follows: RQ Waste Polychlorinated Biphenols, 9, UN-2315,

PG-II, (M001). 6. Adjacent to each label, enter the date indicating when waste was first placed in each drum.

B. Waste Type B

1. Package in DOT 17-H Open-Top Drums with Polyethylene disposal Bag liners

2. Fill liner bags only with Waste Type B (Do Not Mix Waste Stream types); then neck liner bags down into DOT 17-H Open-Top Drum and seal with duct tape.

3. Install gasket on lid, apply lock ring, and seal.

4. Apply Hazardous Waste Label to drum side.

5. Enter DOT Shipping Data as follows: RQ Hazardous Waste Solid, NOS, 9, NA3077, PG-

III, (D009). 6. Adjacent to each label, enter the date indicating when waste was first placed in each drum.

C. Sealed and Labeled Containers: maintain all containers in a continuously sealed condition after they have been sealed.

1. Do not reopen sealed containers.

2. Do not place additional waste in sealed containers.

3.2 Temporary Storage: Partially filled containers of hazardous waste may be stored at the work site for

intermittent packaging provided that:

A. Each container is properly labeled when it is first placed in service;

B. Each container remains closed at all times except when compatible waste types are added; and C. When moved from site to site, each container remains within the geographic boundaries of the

facility without moving nor crossing public access highways.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\29 - 02086S96 - Hazardous Waste Mgmt - bkf.doc 02086 -5

3.3 Removal of Hazardous Wastes: Immediately seal containers of hazardous waste as each the container is filled. Remove containers of hazardous waste from the work site within seventy-two (72) hours of being filled.

A. Transporting filled containers from the work site to an approved disposal site or recycling

center.

B. Continuously maintain custody of all hazardous material generated at the work site including security, short-term storage, transportation and disposition until custody is transferred to an approved disposal site or recycling center. Document continuous chain-of custody.

C. Do not remove, or cause to be removed, hazardous waste from Owner’s property without a

legally executed Uniform Hazardous Waste manifest.

D. At completion of hauling and disposal of each load submit copy of waste manifest, chain of custody form, and landfill receipt to Designer.

3.4 Recycling and Recovery: Turn over waste which contains materials for which recovery and/or

recycling is possible to an approved recycling center. Materials subject to recycling include: 1. Fluorescent light tubes.

2. Thermostats with mercury switches.

3. Lead acid batteries

4. Combustible lead-based painted building components and lead-based paint chips.

3.5 Backcharges:

A. Where contractor fails to fulfill packaging, handling, transport or disposal requirements as outlined herein, Owner will charge back to the Contractor all costs associated with insuring that hazardous wastes are segregated, packaged, transported and disposed of in accordance with all applicable Federal and State regulations.

B. Environmental pollution of Owner’s property or other environments resulting from Contractor’s

hazardous waste management activities will be promptly remediated under Owner’s direction, to the Owner’s sole satisfaction, and at the Contractor’s sole expense.

C. Contractor agrees to either reimburse the Owner, or reduce the Contract amount by change order

to cover all costs associated with waste re-packaging, waste re-segregation, or pollution remediation efforts.

3.6 Removal of Non-Hazardous Waste Materials:

A. Transport and legally dispose of non-hazardous waste products, materials, residues and refuse at a location not on Owner’s property.

B. Non-hazardous waste products, materials, residues and refuse include, but are not necessarily

limited to:

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\29 - 02086S96 - Hazardous Waste Mgmt - bkf.doc 02086 -6

1. Materials which are determined to be non-hazardous wastes through objective sampling in

accordance with EPA Document SW-846 and laboratory analysis in accordance with EPA Method 1311.

2. Emptied hazardous material containers: containers holding a material with constituents

listed on the SDS as hazardous.

a. When a container is emptied of its hazardous contents by pouring or scraping so that less than one inch of material remains in the bottom of the container, the container is considered empty and is not in itself a hazardous waste.

b. Emptied hazardous material containers may be disposed of as construction debris

waste (i.e. non-hazardous). 3. Personnel protective clothing and safety equipment with de minimis or trace

contamination, as determined by visual inspection by Owner’s Representative.

C. Keep premises in a clean and orderly condition during performance of abatement work.

D. Place non-hazardous construction debris wastes on a daily basis in secure containers for local landfill disposal.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\30 - 02270 - Environmental Protection - bkf.doc 02270-1

SECTION 02270

ENVIRONMENTAL PROTECTION PART 1 GENERAL 1.01 SCOPE OF WORK

A. The work covered by this Section consists of furnishing all labor, materials and equipment and performing all work required for the prevention of environmental pollution in conformance with applicable laws and regulations, during and as the result of construction operations under this Contract. For the purpose of this Specification, environmental pollution is defined as the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to man; or degrade the utility of the environment of aesthetic and recreational purposes.

1. The control of environmental pollution requires consideration of air, water and land, and

involves management of noise and solid waste, as well as other pollutants.

2. The Contractor shall schedule and conduct his work in a manner that will minimize the erosion of soils in the area of the work. The Contractor shall provide erosion control measures in accordance with Section 02272, such as diversion channels, sedimentation or filtration systems, berms, staked hay bales, and seeding, mulching of streams, rivers, impoundments, lakes, etc.

3. These Specifications are intended to ensure that construction is achieved with a minimum of

disturbance to the existing ecological balance between a water resource and its surroundings. These are general guidelines and possible methods for providing environmental protection for land and water resources; however, it is left to the Contractor to decide what specific construction techniques he may best utilize to meet these guidelines.

4. All phases of sedimentation and erosion control shall comply with and be subject to the

approval of the Ohio Environmental Protection Agency. 1.02 APPLICABLE REGULATIONS

A. The Contractor and his subcontractors shall comply with all applicable Federal, State and local laws and regulations concerning environmental pollution control and abatement.

1.03 NOTIFICATIONS

A. The Owner will notify the Contractor in writing of any non-compliance with the foregoing provisions or of any environmental objectionable acts and corrective action to be taken. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor or his authorized representative at the site of the work, shall be deemed sufficient for the purpose. If the Contractor fails or refuses to comply promptly, the Owner may issue an order stopping all or part of the work until satisfactory corrective action has

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\30 - 02270 - Environmental Protection - bkf.doc 02270-2

been taken. No part of the time lost due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor unless it was later determined that the Contractor was in compliance.

1.04 IMPLEMENTATION

A. Prior to commencement of the work the Contractor will meet with the Owner to develop mutual understandings relative to compliance with this provision and administration of the environmental pollution control program.

PART 2 PRODUCTS

Not applicable. PART 3 EXECUTION 3.01 EROSION CONTROL – Refer to SECTION 02272 of this specification. 3.02 PROTECTION OF LAND RESOURCES

A. It is intended that the land resources within the project boundaries and outside the limits of permanent work performed under this Contract be preserved in their present condition or be restored to a condition after completion of construction that will appear to be natural and not detract from the appearance of the project. Insofar as possible, the Contractor shall confine his construction activities to areas shown on the Drawings.

1. The Contractor shall not deface, injure, or destroy trees or shrubs, nor remove or cut them

without authorization of the Engineer. No ropes, cables, or guys shall be fastened to or attached to any existing nearby trees for anchorage unless specifically authorized by the Owner. Contractor shall first adequately wrap the trunk with a sufficient thickness of burlap or rags over which softwood cleat shall be tied before any rope, cable, or wire is placed. The Contractor shall in any event be responsible for any damage resulting from such use.

2. Where trees may possibly be defaced, bruised, injured, or otherwise damaged by the

Contractor's equipment or by his blasting, dumping or other operations, the Contractor shall protect adequately such trees by placing boards, planks, or poles around them. Monuments and marker shall be protected similarly before beginning operations near them.

3. Any trees or other landscape feature scarred or damaged by the Contractor's equipment or

operations shall be restored as nearly as possible to its original condition at the Contractor's expense. The Owner will decide what method of restoration shall be used and whether damaged trees shall be treated and healed or removed and disposed of.

4. All scars made on trees by equipment, construction operations, or by the removal of limbs

larger than 1 inch in diameter shall be coated as soon as possible with an approved tree wound dressing. All trimming or pruning shall be performed in an approved manner by

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\30 - 02270 - Environmental Protection - bkf.doc 02270-3

experienced workmen with saws or pruning shears. Tree trimming with axes will not be permitted. Where tree climbing is necessary, the use of climbing spur will not be permitted.

3.03 PROTECTION OF AIR RESOURCES

A. Burning. The use of burning at the project site for the disposal of refuse and debris will not be permitted.

B. Dust Control. The Contractor will be required to maintain all excavations, embankment,

stockpiles, access roads, plant sites, waste areas, borrow areas, and all other work areas within or without the project boundaries free from dust which could cause the standards for air pollution to be exceeded, and which would cause a hazard or nuisance to others.

1. An approved method of stabilization consisting of sprinkling or other similar methods will

be permitted to control dust. The use of petroleum products is prohibited.

2. Sprinkling, to be approved, must be repeated at such intervals as to keep all parts of the disturbed area at least damp at all times, and the Contractor must have sufficient, competent equipment on the job to accomplish this if sprinkling is used. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs.

3.04 NOISE CONTROL

A. The Contractor shall make every effort to minimize noises caused by his operations. Equipment shall be equipped with silencers or mufflers designed to operate with the least possible noise.

3.05 STORMWATER PREVENTION PLAN

A. The Contractor shall install the soil and erosion control management practices for the project site in accordance with Section 02272.

END OF SECTION

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\31 - 02272-1- Construction Storm Water Pollution Control - bkf.doc 02272-1

SECTION 02272

CONSTRUCTION STORM WATER POLLUTION CONTROL PART 1 - GENERAL 1.01 SCOPE OF WORK The Contractor shall perform all applicable work and provide all materials described in this specification and appendices required to comply with Ohio EPA General Permit OHC000004 for discharge of Construction Site Storm Water. A. Prior to any construction activity, the Contractor shall submit to Ohio EPA a Co-

Permittee Notice of Intent (NOI) and obtain Coverage Under Ohio EPA Storm Water Construction General Permit (Appendix D) and prepare a Storm Water Pollution Prevention Plan (SWPPP) satisfying the requirements of the General Permit (Appendix C). Effective February 1, 2017, the Ohio EPA requires an All-Electronic NOI Form Submittal. This information is included at the end of this Section. Two (2) copies of the NOI submittal and SWPPP shall be sent to the Engineer for record only. Additionally, all storm water permit activities shall be coordinated with the Mahoning County Storm Water Control District.

B. The Contractor shall maintain a signed copy of the NOI and the current SWPPP

available for inspection at the project site. C. The Contractor shall inform all contractors and subcontractors not otherwise defined

as “operators” in Part VII of the general permit, who will be involved in the implementation of the SWPPP, of the terms and conditions of the general permit. Documentation shall be recorded in accordance with Part III(E) of the general permit.

D. During construction, the Contractor will be responsible for installing and maintaining

the temporary sediment and erosion control measures as described in this specification. The Contractor shall amend the SWPPP if at any point the SWPPP proves to be ineffective in controlling pollutants in storm water discharges associated with construction activity.

E. Upon completion and acceptance of construction, the Contractor shall submit a

Notice of Termination for Coverage Under Ohio EPA Storm Water Construction General Permit according to Section IV of the permit.

F. This work consists of furnishing and locating TSEC (Temporary Sediment and

Erosion Control) BMP (Best Management Practices) for both project and off project EDA (Earth Disturbing Activity) areas and developing a SWPPP (Storm Water Pollution Prevention Plan) as required. Furnish these TSEC BMP prior to any EDA. Furnish a SWPPP as required prior to any EDA. In the event of conflict between these requirements and pollution control laws, rules, or regulations of other Federal, State, or local agencies, adhere to the more restrictive laws, rules, or regulations.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\31 - 02272-1- Construction Storm Water Pollution Control - bkf.doc 02272-2

1.02 DEFINITIONS BMP: Best Management Practices CMS: Construction and Material Specifications of the Ohio Department of Transportation Dated January 1, 2016 Earth Disturbing Activity (EDA): Means any activity that exposes bare ground or an erodible material to storm water and anywhere vegetation activities (seeding, sodding, etc.) are performed. EPA: Environmental Protection Agency Isolated Wetland Permit: Ohio EPA permit allowing the discharge of fill material into an isolated wetland NOI: Notice of Intent NOT: Notice of Termination NPDES: National Pollutant Discharge Elimination System ODNR: Ohio Department of Natural Resources OEPA: Ohio EPA ODOT: Ohio Department of Transportation OES: Office of Environmental Services-ODOT OWPCA: Ohio Water Pollution Control Act USACE: United States Army Corps of Engineers OHWM: Ordinary High Water Mark; the USACE's jurisdictional limits involving streams; usually equivalent to a 2 year high water elevation. PCN: Pre-Construction Notification for 404 permit

OEPA General Storm Water Permit OHC000004: OEPA NPDES Construction Effluent Guidelines Permit SCD: Standard Construction Drawing - ODOT SWPPP: Storm Water Pollution Prevention Plan TSEC: Temporary Sediment and Erosion Control 404 Permit USACE permit authorizing discharge of fill material into Waters of the US, per Section 404 of the Clean Water Act

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\31 - 02272-1- Construction Storm Water Pollution Control - bkf.doc 02272-3

401 Water Quality Certification (401 WQC): Ohio EPA permit authorizing discharge of fill material, per Section 401 of the Clean Water Act

1.02 STANDARD CONSTRUCTION DRAWING REFERENCES

A. Standard ODOT Reference Drawings

DM – 4.3 - Filter Dike - Dikes - Rock Channel Protection, Type C or D with/without filter - Sediment Basins and Dams - Slope Drains

DM – 4.4

- Filter Fabric Ditch Check - Inlet Protection - Perimeter Filter Fabric Fence

B. The ODNR Rainwater and Land Development Manual (Current Edition) has BMP

details and requirements. The Contractor shall use all available standard drawings and details as necessary to prepare the SWPPP.

1.04 REQUIREMENTS

A. Furnish and locate TSEC BMP to represent and warrant compliance with the Clean Water Act, 33 USC Section 1251 et seq. and the OWPCA, ORC (Ohio Revised Code) 6111.01 et seq., all conditions of 404 permit/401 WQC/Isolated Wetland Permit, and related rules, local government agency requirements, specifications, SCD, and permits. Furnish a SWPPP to represent and warrant compliance with OEPA GENERAL STORM WATER PERMIT OHC000004, related rules, specifications, SCD, and permits.

B. Post-Construction controls as described in OEPA GENERAL STORM WATER

PERMIT OHC000004 are not a part of this specification. 1.05 PROVISIONS

A. These provisions survive the completion and/or termination of the contract. The following provisions must be followed:

1. If a governmental agency or a local governmental authority finds a violation of

the above noted requirements, or that the TSEC BMP are incomplete, or that the SWPPP is incomplete or that the implementation of the SWPPP is not being performed correctly or completely, full responsibility will be borne by the Contractor to make all corrections.

2. If a governmental agency or a local governmental authority furnishes an

assessment, damage judgement or finding, fine, penalty, or expense for a violation of the above noted requirements, or that the TSEC BMP are incomplete, or that the SWPPP is incomplete, or that the implementation of the SWPPP is not

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\31 - 02272-1- Construction Storm Water Pollution Control - bkf.doc 02272-4

being performed correctly or completely, the Contractor will reimburse the Owner within ten (10) Calendar Days of the amount for any of the above. The Owner may withhold the amount of money requested for the above from the Contractor's next pay estimate and deliver that sum to the governmental agency or local governmental authority issuing the assessment, damage judgement or finding, fine, penalty or expense.

3. The Contractor agrees to indemnify and hold harmless the Owner and Engineer,

and will reimburse the Owner for any assessments, damage judgment or finding, fine, penalty, or expense as a result of the failure of performing this portion of the Contract. The Owner may withhold the amount of any assessments, damage judgment or finding, fine, penalty or expense from the Contractor's next pay estimate.

4. If a governmental agency or a local governmental authority furnishes a stop work

order for a violation of the above noted requirements, or that the TSEC BMP are incomplete, or that the SWPPP is incomplete, or that the implementation of the SWPPP is not being performed correctly or completely, the Owner will find the Contractor in default.

5. If the Owner finds a violation of the above noted requirements, or that the TSEC

BMP are incomplete, or that the SWPPP is incomplete or that the implementation of the SWPPP is not being performed correctly or completely, the Contractor will make all corrections. The Owner may withhold and continue to withhold progress payments until such corrections are made.

PART 2 PRODUCTS 2.01 TSEC BMP Materials

A. Furnish commercial fertilizer, seed, and mulch materials conforming to 2016 CMS Item 659.

B. Furnish filter fabric ditch checks, rock checks, inlet protection, perimeter filter fabric

fence, bale filter dikes, sediment basins and dams, dikes, slope drains, and rock channel protection materials as specified on the SCD. Furnish construction ditch and slope protection conforming to the requirements of 2016 CMS Item 670. The seeding and mulching of the mats are not required. The Owner may accept other materials as BMP if approved by the OEPA.

PART 3 EXECUTION 3.01 Furnish and Locate TSEC BMP

A. Furnish and locate the TSEC BMP as required or as outlined in the Ohio Department of Transportation Location Design Manual Volume II -Drainage Design, ODNR Rainwater and Land Development Manual (current edition) or as outlined in the SWPPP. Keep TSEC BMP functional until the areas are fully stabilized.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\31 - 02272-1- Construction Storm Water Pollution Control - bkf.doc 02272-5

Construct items 1, 2 and 4 through 7, below, according to the SCD.

1. Perimeter Controls. Use perimeter filter fabric fence to protect the project from sheet flow runoff from off Right-of-Way and off construction limit locations. Use perimeter filter fabric fence to protect the following project items from sheet flow runoff: water bodies, wetlands, or other significant items shown on the plans.

Use dikes to prevent sediment flow from coming onto the project and to non-vegetated barren areas on the project.

Install perimeter filter fabric fence and dikes before any clearing and grubbing operations. Ensure that the ponding of water behind the perimeter filter fabric fence or dike will not damage property or risk the safety of life.

2. Inlet Protection. Construct the inlet protection for existing inlets at the beginning of construction and for new inlets immediately after completing the sump. Ensure that the ponding of water behind the inlet will not damage property or risk the safety of life.

3. Construction Seeding and Mulching. Apply seed and mulch materials

according to 2016 CMS (or most current version) Item 659 as modified herein. When straw mulch is used, apply at a rate of 2 tons per acre (0.5 metric ton/1000 m2). Seed and mulch during and after construction, and before or during winter shut down to stabilize EDA areas and as required. Fertilize construction seeding areas at one-half the application rate specified in 2016 CMS Item 659. If project conditions prevent fertilizing the soil and preparing the seedbed, then the fertilizing and preparation requirements of 2016 CMS (or most current version) Item 659 may be waived. Do not place construction seed on frozen ground.

4. Slope Protection. Place dikes, install slope drains, and construct ditches to

divert water from bare non-vegetated areas and to protect cut and fill slopes. Protect the side slopes from erosion by placing dikes at the top of fill slopes.

Before furnishing a cut slope, construct a ditch at the top of the cut slope to reduce runoff coming on the slope.

Furnish Construction Slope Protection at the required locations or at the locations shown on the SWPPP as the slopes are constructed. Furnish all permanent slope protection as final grade is complete.

5. Ditch Checks and Ditch Protection. Place filter fabric ditch checks or rock

checks across a ditch and perpendicular to the flow to protect the ditch from erosion and to filter sediment from the flowing water.

Place ditch checks as soon as the ditch is cut. If working on a ditch, replace the ditch checks by the end of the workday.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\31 - 02272-1- Construction Storm Water Pollution Control - bkf.doc 02272-6

Install filter fabric ditch checks for drainage areas less than or equal to 2 acres (0.8 ha) as shown in the SCD. Install rock checks for drainage areas between 2 to 5 acres (0.8 to 2.0 ha) as shown in the SCD.

Install ditch checks in conjunction with sediment basins and dams.

Furnish Construction Ditch Protection at the required locations or at the locations shown on the SWPPP as the ditches are cut. Furnish all permanent ditch protection as final grade is complete.

6. Bale Filter Dike. Install bale filter dike a few feet (meters) from the toe of a

slope to filter and direct sediment to an appropriate control item before the runoff enters a water body on or off the Project limits.

Use the bale filter dike to collect sediment from:

a. Areas less than 1/4 acre (0.1 ha) for each sediment pit. b. Slopes with a length of less than 100 feet (30 m) and having a maximum

2:1 slope.

Use a sediment pit every 100 feet (30 m) for a 2:1 slope for every 1/4 acre (0.1 ha). Use a greater spacing of the sediment basin for flatter slopes. Begin constructing bale filter dikes within 7 days of commencing grubbing operations. Complete the construction of the bale filter dike before starting the grading operations.

7. Sediment Basins and Dams. Construct basins and dams at concentrated and

critical flow locations to settle out sediment before the water leaves the EDA area. Use basins at the bottom of a ravine, at a culvert inlet, or outlet, along or at the end of a ditch and at any concentrated water exit point of the project. Construct the basins to retain 67 cubic yards (125 m3) of water for every acre (1.0 ha) of drainage area. Use a series of smaller basins or dams as a substitute for a larger basin or dam.

Begin constructing sediment basins and dams within 7 days of commencing grubbing operations. Complete the construction of the sediment basins and dams before starting the grading operations.

When needed construct construction fence around the sediment basins or dams.

8. River, Stream, and Water Body Protection. Protect all streams or water bodies

passing through or on the project using Perimeter Filter Fabric Fence or Bale Filter Dike to line the water edge. Divert project water flow using dikes and slope protection. The Contractor may use a combination of items listed in one through seven above and other TSEC BMP.

9. Concrete washout areas TSCE BMP. For the purpose of payment this BMP is part of the concrete work for payment.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\31 - 02272-1- Construction Storm Water Pollution Control - bkf.doc 02272-7

10. Project access TSEC BMP locations. For the purpose of payment this BMP is part of the total project for payment.

11. Project fueling and refueling TSCE BMP locations. For the purpose of payment

this BMP is part of the total project for payment.

12. All other TSEC BMP: All other TSEC BMP that are required but not specifically referenced will not be paid as a separate item but will be included by the Contractor as part of the lump sum cost.

3.02 MAINTENANCE

A. Properly maintain all TSEC BMP. Dispose of silt removed from TSEC legally at offsite locations. Remove all TSEC BMP before the project is accepted.

Maintain the TSEC BMP until the up-slope permanent grass coverage is 70 percent or better. At this stage, remove the TSEC BMP. 1. Perimeter Filter Fabric Fence, Filter Fabric Ditch Checks, Rock Checks, Inlet

Protection, Dikes, and Bale Filter Dikes. Remove trapped sediment when it reaches half the height of the lowest section. Make appropriate corrections when the TSEC BMP becomes nonfunctional.

2. Sediment Basins and Dams. Remove deposited sediment when sediments reduce the initial volume of the sediment basin or dam by one-half. Make appropriate corrections when these TSEC BMP fail. Remove dams and basins after the up slope has been stabilized.

3.03 STORM WATER POLLUTION PREVENTION PLAN A. Prepare the SWPPP as outlined in this specification and Ohio EPA General Permit

OHC000004. Additional guidance can be found in the Ohio Department of Transportation Location and Design Manual Volume II - Drainage Design, the Ohio Department of Transportation Location and Design Manual Volume III- Highway Plans and ODNR Rainwater and Land Development Manual (Current Edition). Examples of some of the design and information requirements that must be shown on the SWPPP are as follows:

1. A Professional Engineer qualified in TSEC BMP must design and sign the SWPPP.

2. Locate the required TSEC BMP for both on and off project EDA areas. 3. Furnish quantity totals for all TSEC BMP.

4. Locate the following a minimum of 100 feet (30 m) from the water's edge of any stream, ephemeral stream, wetland, or body of water: a. Concrete or asphalt plant areas b. Material and equipment staging or storage areas c. Dewatering Areas d. Concrete truck wash out areas e. Construction access locations f. Vehicle fueling and refueling locations

5. Furnish an implementation schedule for each construction sequence. 6. For any additional requirements, See 2016 CMS 107.19.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\31 - 02272-1- Construction Storm Water Pollution Control - bkf.doc 02272-8

7. Furnish the total EDA areas in acres. 8. Locate all slopes that will be inactive for 21 calendar days or longer. 9. Furnish the name of the individual on site who is in charge of the SWPPP and the

TSEC BMP practices. 10. Describe the type of construction activities that will be taking place. 11. Furnish signatures of all contractors and subcontractors involved in TSEC

practices (see App. B). If there are plan sheets which meet any of the OEPA GENERAL STORM WATER PERMIT OHC000004 requirements, use that information. Design files may be furnished to the awarded Contractor in electronic form in the future.

12. Describe post-construction storm water BMP practices. 3.04 SWPPP REVIEW A. Furnish the initial SWPPP to the local regulatory agencies for review and approval

and to the Owner and Engineer for record. No time extensions to the contract will be granted for the above referenced review times. The Owner’s review will only ensure that the following items have been furnished:

B. The type and location of TSEC BMP with totals. C. A schedule of placing TSEC BMP. D. The applicable requirements of those contained in Paragraph 3.03.

E. Revise the accepted SWPPP as needed. These revisions to the accepted SWPPP will be at no additional cost to the Owner.

3.05 INSPECTIONS A. Perform OEPA GENERAL STORM WATER PERMIT OHC000004 required

inspections. The inspection reports are to be prepared for projects that have a SWPPP. Submit a copy of the inspection reports to the Engineer for record.

B. Use the report form furnished in Appendix A.

END OF SECTION

Page 2 of 37 Ohio EPA Permit No.: OHC000004

TABLE OF CONTENTS PART I. COVERAGE UNDER THIS PERMIT A. Permit Area B. Eligibility C. Requiring an individual permit or an alternative general permit D. Permit requirements when portions of a site are sold E. Authorization F. Notice of Intent Requirements PART II. NON-NUMERIC EFFLUENT LIMITATIONS A. Erosion and Sediment Controls B. Soil Stabilization C. Dewatering D. Pollution Prevention Measures E. Prohibited Discharges F. Surface Outlets PART III. STORM WATER POLLUTION PREVENTION PLAN (SWP3) A. Storm Water Pollution Prevention Plans B. Timing C. SWP3 Signature and Review D. Amendments E. Duty to inform contractors and subcontractors F. Total Maximum Daily Load (TMDL) allocations G. SWP3 Requirements PART IV. NOTICE OF TERMINATION REQUIREMENTS A. Failure to notify B. When to submit an NOT C. How to submit an NOT PART V. STANDARD PERMIT CONDITIONS A. Duty to comply B. Continuation of the expired general permit C. Need to halt or reduce activity not a defense D. Duty to mitigate E. Duty to provide information F. Other information G. Signatory requirements H. Certification I. Penalties for falsification of monitoring systems J. Oil and hazardous substance liability K. Property rights L. Severability M. Transfers N. Environmental laws O. Proper operation and maintenance P. Inspection and entry PART VI. REOPENER CLAUSE PART VII. DEFINITIONS

Page 3 of 37 Ohio EPA Permit No.: OHC000004

PART I. COVERAGE UNDER THIS PERMIT A. Permit Area. This permit covers the entire State of Ohio. B. Eligibility. 1. Construction activities covered. Except for storm water discharges identified under Part

I.B.2, this permit may cover all new and existing discharges composed entirely of storm water discharges associated with construction activity that enter surface waters of the state or a storm drain leading to surface waters of the state.

For the purposes of this permit, construction activities include any clearing, grading, excavating, grubbing and/or filling activities that disturb the threshold acreage described in the next paragraph. Discharges from trench dewatering are also covered by this permit as long as the dewatering activity is carried out in accordance with the practices outlined in Part III.G.2.g.iv of this permit.

Construction activities disturbing one or more acres of total land, or will disturb less than one acre of land but are part of a larger common plan of development or sale that will ultimately disturb one or more acres of land will be eligible for coverage under this permit. The threshold acreage includes the entire area disturbed in the larger common plan of development or sale.

This permit also authorizes storm water discharges from support activities (e.g., concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas) provided:

a. The support activity is directly related to a construction site that is required to

have NPDES permit coverage for discharges of storm water associated with construction activity;

b. The support activity is not a commercial operation serving multiple unrelated

construction projects and does not operate beyond the completion of the construction activity at the site it supports;

c. Appropriate controls and measures are identified in a storm water pollution

prevention plan (SWP3) covering the discharges from the support activity; and

d. The support activity is on or contiguous with the property defined in the NOI (offsite borrow pits and soil disposal areas, which serve only one project, do not have to be contiguous with the construction site).

2. Limitations on coverage. The following storm water discharges associated with construction activity are not covered by this permit:

a. Storm water discharges that originate from the site after construction activities have been completed, including any temporary support activity, and the site has achieved

Page 4 of 37 Ohio EPA Permit No.: OHC000004

final stabilization. Industrial post-construction storm water discharges may need to be covered by an NPDES permit;

b. Storm water discharges associated with construction activity that the director has

shown to be or may reasonably expect to be contributing to a violation of a water quality standard; and

c. Storm water discharges authorized by an individual NPDES permit or another

NPDES general permit; 3. Waivers. After March 10, 2003, sites whose larger common plan of development or sale

have at least one, but less than five acres of land disturbance, which would otherwise require permit coverage for storm water discharges associated with construction activities, may request that the director waive their permit requirement. Entities wishing to request such a waiver must certify in writing that the construction activity meets one of the two waiver conditions:

a. Rainfall Erosivity Waiver. For a construction site to qualify for the rainfall erosivity

waiver, the cumulative rainfall erosivity over the project duration must be five or less and the site must be stabilized with a least a 70 percent vegetative cover or other permanent, non-erosive cover. The rainfall erosivity must be calculated according to the method in U.S. EPA Fact Sheet 3.1 Construction Rainfall Erosivity Waiver dated January 2001 and be found at: http://epa.ohio.gov/portals/35/permits/USEPAfact3-1_s.pdf. If it is determined that a construction activity will take place during a time period where the rainfall erosivity factor is less than five, a written waiver certification must be submitted to Ohio EPA at least 21 days before construction activity is scheduled to begin. If the construction activity will extend beyond the dates specified in the waiver certification, the operator must either: (a) recalculate the waiver using the original start date with the new ending date (if the R factor is still less than five, a new waiver certification must be submitted) or (b) submit an NOI application form and fee for coverage under this general permit at least seven days prior to the end of the waiver period; or

b. TMDL (Total Maximum Daily Load) Waiver. Storm water controls are not needed based on a TMDL approved or established by U.S. EPA that addresses the pollutant(s) of concern or, for non-impaired waters that do not require TMDLs, and equivalent analysis that determines allocations for small construction sites for the pollutant(s) of concern or that determines that such allocations are not needed to protect water quality based on consideration of existing in-stream concentrations, expected growth in pollutant contributions from all sources, and a margin of safety. The pollutant(s) of concern include sediment or a parameter that addresses sediment (such as total suspended solids, turbidity or siltation) and any other pollutant that has been identified as a cause of impairment of any water body that will receive a discharge from the construction activity. The operator must certify to the director of Ohio EPA that the construction activity will take place, and storm water discharges will occur, within the drainage area addressed by the TMDL or equivalent analysis. A written waiver certification must be submitted to Ohio EPA at least 21 days before the construction activity is scheduled to begin.

Page 5 of 37 Ohio EPA Permit No.: OHC000004

4. Prohibition on non-storm water discharges. All discharges covered by this permit must be composed entirely of storm water with the exception of the following: discharges from firefighting activities; fire hydrant flushings; potable water sources including waterline flushings; irrigation drainage; lawn watering; routine external building washdown which does not use detergents; pavement washwaters where spills or leaks of toxic or hazardous materials have not occurred (unless all spilled material has been removed) and where detergents are not used; air conditioning condensate; springs; uncontaminated ground water from trench or well point dewatering and foundation or footing drains where flows are not contaminated with process materials such as solvents. Dewatering activities must be done in compliance with Part II.C and Part III.G.2.g.iv of this permit. Discharges of material other than storm water or the authorized non-storm water discharges listed above must comply with an individual NPDES permit or an alternative NPDES general permit issued for the discharge.

Except for flows from firefighting activities, sources of non-storm water listed above that are combined with storm water discharges associated with construction activity must be identified in the SWP3. The SWP3 must identify and ensure the implementation of appropriate pollution prevention measures for the non-storm water component(s) of the discharge.

5. Spills and unintended releases (Releases in excess of Reportable Quantities). This permit does not relieve the permittee of the reporting requirements of Title 40 of the Code of Federal Regulations (“CFR”) Part 117 and 40 CFR Part 302. In the event of a spill or other unintended release, the discharge of hazardous substances in the storm water discharge(s) from a construction site must be minimized in accordance with the applicable storm water pollution prevention plan for the construction activity and in no case, during any 24-hour period, may the discharge(s) contain a hazardous substance equal to or in excess of reportable quantities. 40 CFR Part 117 sets forth a determination of the reportable quantity for each substance designated as hazardous in 40 CFR Part 116. The regulation applies to quantities of designated substances equal to or greater than the reportable quantities, when discharged to surface waters of the state. 40 CFR Part 302 designates under section 102(a) of the Comprehensive Environmental Response, Compensation and Liability Act of 1980, those substances in the statutes referred to in section 101(14), identifies reportable quantities for these substances and sets forth the notification requirements for releases of these substances. This regulation also sets forth reportable quantities for hazardous substances designated under section 311(b)(2)(A) of the Clean Water Act (CWA). C. Requiring an individual NPDES permit or an alternative NPDES general permit. 1. The director may require an alternative permit. The director may require any operator eligible for this permit to apply for and obtain either an individual NPDES permit or coverage under an alternative NPDES general permit in accordance with OAC Rule 3745-38-04. Any interested person may petition the director to take action under this paragraph. The director will send written notification that an alternative NPDES permit is required. This notice shall include a brief statement of the reasons for this decision, an application

Page 6 of 37 Ohio EPA Permit No.: OHC000004

form and a statement setting a deadline for the operator to file the application. If an operator fails to submit an application in a timely manner as required by the director under this paragraph, then coverage, if in effect, under this permit is automatically terminated at the end of the day specified for application submittal.

2. Operators may request an individual NPDES permit. Any owner or operator eligible for this permit may request to be excluded from the coverage of this permit by applying for an individual permit. The owner or operator shall submit an individual application with reasons supporting the request to the director in accordance with the requirements of 40 CFR 122.26. If the reasons adequately support the request, the director shall grant it by issuing an individual NPDES permit. 3. When an individual NPDES permit is issued to an owner or operator otherwise subject to this permit or the owner or operator is approved for coverage under an alternative NPDES general permit, the applicability of this permit to the individual NPDES permittee is automatically terminated on the effective date of the individual permit or the date of approval for coverage under the alternative general permit, whichever the case may be. D. Permit requirements when portions of a site are sold If an operator obtains a permit for a development, and then the operator (permittee) sells off lots or parcels within that development, permit coverage must be continued on those lots until a Notice of Termination (NOT) in accordance with Part IV.B is submitted. For developments which require the use of centralized sediment and erosion controls (i.e., controls that address storm water runoff from one or more lots) for which the current permittee intends to terminate responsibilities under this permit for a lot after sale of the lot to a new owner and such termination will either prevent or impair the implementation of the controls and therefore jeopardize compliance with the terms and conditions of this permit, the permittee will be required to maintain responsibility for the implementation of those controls. For developments where this is not the case, it is the permittee’s responsibility to temporarily stabilize all lots sold to individual lot owners unless an exception is approved in accordance with Part III.G.4. In cases where permit responsibilities for individual lot(s) will be terminated after sale of the lot, the permittee shall inform the individual lot owner of the obligations under this permit and ensure that the Individual Lot NOI application is submitted to Ohio EPA. E. Authorization 1. Obtaining authorization to discharge. Operators that discharge storm water associated

with construction activity must submit an NOI application form in accordance with the requirements of Part I.F of this permit to obtain authorization to discharge under this general permit. As required under OAC Rule 3745-38-06(E), the director, in response to the NOI submission, will notify the applicant in writing that he/she has or has not been granted general permit coverage to discharge storm water associated with construction activity under the terms and conditions of this permit or that the applicant must apply for an individual NPDES permit or coverage under an alternate general NPDES permit as described in Part I.C.1.

2. No release from other requirements. No condition of this permit shall release the permittee from any responsibility or requirements under other environmental statutes or regulations. Other permit requirements commonly associated with construction activities

Page 7 of 37 Ohio EPA Permit No.: OHC000004

include, but are not limited to, section 401 water quality certifications, isolated wetland permits, permits to install sanitary sewers or other devices that discharge or convey polluted water, permits to install drinking water lines, single lot sanitary system permits and disturbance of land which was used to operate a solid or hazardous waste facility (i.e., coverage under this NPDES general permit does not satisfy the requirements of OAC Rule 3745-27-13 or ORC Section 3734.02(H)). The issuance of this permit is subject to resolution of an antidegradation review. This permit does not relieve the permittee of other responsibilities associated with construction activities such as contacting the Ohio Department of Natural Resources, Division of Water, to ensure proper well installation and abandonment of wells. F. Notice of Intent Requirements 1. Deadlines for notification.

a. Initial coverage: Operators who intend to obtain initial coverage for a storm water discharge associated with construction activity under this general permit must submit a complete and accurate NOI application form and appropriate fee at least 21 days prior to the commencement of construction activity. If more than one operator, as defined in Part VII of this general permit, will be engaged at a site, each operator shall seek coverage under this general permit. Coverage under this permit is not effective until an approval letter granting coverage from the director of Ohio EPA is received by the applicant. Where one operator has already submitted an NOI prior to other operator(s) being identified, the additional operator shall request modification of coverage to become a co-permittee. In such instances, the co-permittees shall be covered under the same facility permit number. No additional permit fee is required.

b. Individual lot transfer of coverage: Operators must each submit an individual lot

notice of intent (Individual Lot NOI) application form (no fee required) to Ohio EPA at least seven days prior to the date that they intend to accept responsibility for permit requirements for their portion of the original permitted development from the previous permittee. The original permittee may submit an Individual Lot NOT at the time the Individual Lot NOI is submitted. Transfer of permit coverage is not granted until an approval letter from the director of Ohio EPA is received by the applicant.

2. Failure to notify. Operators who fail to notify the director of their intent to be covered and

who discharge pollutants to surface waters of the state without an NPDES permit are in violation of ORC Chapter 6111. In such instances, Ohio EPA may bring an enforcement action for any discharges of storm water associated with construction activity.

3. Where to submit an NOI. Operators seeking coverage under this permit must submit a

signed NOI form, provided by Ohio EPA, to the address found in the associated instructions.

4. Additional notification. NOIs and SWP3s are considered public documents and shall be

made available to the public in accordance with Part III.C.2. The permittee shall make NOIs and SWP3s available upon request of the director of Ohio EPA, local agencies approving sediment and erosion control plans, grading plans or storm water management plans, local governmental officials, or operators of municipal separate storm sewer systems (MS4s) receiving drainage from the permitted site. Each operator

Page 8 of 37 Ohio EPA Permit No.: OHC000004

that discharges to an NPDES permitted MS4 shall provide a copy of its Ohio EPA NOI submission to the MS4 in accordance with the MS4’s requirements, if applicable.

5. Re-notification. Existing permittees having coverage under the previous generations of

this general permit (OHC000003, OHC000002 and OHR100000) shall have continuing coverage under OHC000004 with the submittal of a timely renewal application. Existing permittees will receive a renewal application and instructions for how to continue coverage under OHC000004. Within 90 days of receiving a renewal application from Ohio EPA, existing permittees shall submit the completed renewal application expressing their intent for continued coverage. In accordance with Ohio Administrative Code (OAC) 3745-38-02(E)(2)(a)(i), a renewal application fee will only apply to existing permittees having general permit coverage for 5 or more years as of the effective date of this general permit. Permit coverage will be terminated if Ohio EPA does not receive the renewal application within this 90 day period.

Part II. NON-NUMERIC EFFLUENT LIMITATIONS You shall comply with the following non-numeric effluent limitations for discharges from your site and/or from construction support activities. Part III of this permit contains the specific design criteria to meet the objectives of the following non-numeric effluent limitations. A. Erosion and Sediment Controls. You shall design, install and maintain effective

erosion controls and sediment controls to minimize the discharge of pollutants. At a minimum, such controls shall be designed, installed and maintained to:

1. Control storm water volume and velocity within the site to minimize soil erosion;

2. Control storm water discharges, including both peak flowrates and total storm water

volume, to minimize erosion at outlets and to minimize downstream channel and streambank erosion;

3. Minimize the amount of soil exposed during construction activity;

4. Minimize the disturbance of steep slopes;

5. Minimize sediment discharges from the site. The design, installation and maintenance of erosion and sediment controls shall address factors such as the amount, frequency, intensity and duration of precipitation, the nature of resulting storm water runoff, and soil characteristics, including the range of soil particle sizes expected to be present on the site;

6. If feasible, provide and maintain a 50-foot undisturbed natural buffer around surface

waters of the state, direct storm water to vegetated areas to increase sediment removal and maximize storm water infiltration. If it is infeasible to provide and maintain an undisturbed 50-foot natural buffer, you shall comply with the stabilization requirements found in Part II.B for areas within 50 feet of a surface water; and

7. Minimize soil compaction and, unless infeasible, preserve topsoil.

Page 9 of 37 Ohio EPA Permit No.: OHC000004

B. Soil Stabilization. Stabilization of disturbed areas shall, at a minimum, be initiated in accordance with the time frames specified in the following tables.

Table 1: Permanent Stabilization

Area requiring permanent stabilization

Time frame to apply erosion controls

Any areas that will lie dormant for one year or more

Within seven days of the most recent disturbance

Any areas within 50 feet of a surface water of the state and at final grade

Within two days of reaching final grade

Any other areas at final grade Within seven days of reaching final grade within that area

Table 2: Temporary Stabilization

Area requiring temporary stabilization

Time frame to apply erosion controls

Any disturbed areas within 50 feet of a surface water of the state and not at final grade

Within two days of the most recent disturbance if the area will remain idle for more than 14 days

For all construction activities, any disturbed areas that will be dormant for more than 14 days but less than one year, and not within 50 feet of a surface water of the state

Within seven days of the most recent disturbance within the area For residential subdivisions, disturbed areas must be stabilized at least seven days prior to transfer of permit coverage for the individual lot(s).

Disturbed areas that will be idle over winter

Prior to the onset of winter weather

Where vegetative stabilization techniques may cause structural instability or are otherwise unobtainable, alternative stabilization techniques must be employed. Permanent and temporary stabilization are defined in Part VII.

C. Dewatering. Discharges from dewatering activities, including discharges from dewatering of trenches and excavations, are prohibited unless managed by appropriate controls.

D. Pollution Prevention Measures. Design, install, implement and maintain effective

pollution prevention measures to minimize the discharge of pollutants. At a minimum, such measures must be designed, installed, implemented and maintained to:

1. Minimize the discharge of pollutants from equipment and vehicle washing, wheel wash

water, and other wash waters. Wash waters shall be treated in a sediment basin or alternative control that provides equivalent or better treatment prior to discharge;

Page 10 of 37 Ohio EPA Permit No.: OHC000004

2. Minimize the exposure of building materials, building products, construction wastes, trash, landscape materials, fertilizers, pesticides, herbicides, detergents, sanitary waste and other materials present on the site to precipitation and to storm water; and

3. Minimize the discharge of pollutants from spills and leaks and implement chemical spill and leak prevention and response procedures.

E. Prohibited Discharges. The following discharges are prohibited:

1. Wastewater from washout of concrete, unless managed by an appropriate control;

2. Wastewater from washout and cleanout of stucco, paint, form release oils, curing

compounds and other construction materials; 3. Fuels, oils, or other pollutants used in vehicle and equipment operation and

maintenance; and 4. Soaps or solvents used in vehicle and equipment washing. F. Surface Outlets. When discharging from sediment basins utilize outlet structures that

withdraw water from the surface, unless infeasible. (Note: Ohio EPA believes that the circumstances in which it is infeasible to design outlet structures in this manner are rare. Exceptions may include time periods with extended cold weather during winter months. If you have determined that it is infeasible to meet this requirement, you shall provide documentation in your SWP3 to support your determination.)

PART III. STORM WATER POLLUTION PREVENTION PLAN (SWP3) A. Storm Water Pollution Prevention Plans. A SWP3 shall be developed for each site covered by this permit. For a multi-phase construction project, a separate NOI shall be submitted when a separate SWP3 will be prepared for subsequent phases. SWP3s shall be prepared in accordance with sound engineering and/or conservation practices by a professional experienced in the design and implementation of standard erosion and sediment controls and storm water management practices addressing all phases of construction. The SWP3 shall identify potential sources of pollution which may reasonably be expected to affect the quality of storm water discharges associated with construction activities. The SWP3 shall be a comprehensive, stand-alone document, which is not complete unless it contains the information required by Part III.G of this permit. In addition, the SWP3 shall describe and ensure the implementation of best management practices (BMPs) that reduce the pollutants in storm water discharges during construction and pollutants associated with post-construction activities to ensure compliance with ORC Section 6111.04, OAC Chapter 3745-1 and the terms and conditions of this permit. B. Timing A SWP3 shall be completed prior to the timely submittal of an NOI and updated in accordance with Part III.D. Upon request and good cause shown, the director may waive the requirement to have a SWP3 completed at the time of NOI submission. If a waiver has been granted, the

Page 11 of 37 Ohio EPA Permit No.: OHC000004

SWP3 must be completed prior to the initiation of construction activities. The SWP3 must be implemented upon initiation of construction activities. If you wish to continue coverage from the previous generations of this permit (OHR100000, OHC000002 and OHC000003) you shall review and update your SWP3 to ensure that this permit’s requirements are addressed within 180 days after the effective date of this permit. If it is infeasible for you to comply with a specific requirement in this permit because (1) the provision was not part of the permit you were previously covered under (OHR100000, OHC000002 and OHC000003), and (2) because you are prevented from compliance due to the nature or location of earth disturbances that commenced prior to the effective date of this permit, you shall include documentation within your SWP3 of the reasons why it is infeasible for you to meet the specific requirement. (Note: Ohio EPA believes examples of OHC000004 permit conditions that would be infeasible for permittees renewing coverage to comply with include: (1) Post-Construction Storm Water Management requirements, if general permit coverage was obtained prior to April 21, 2003, and (2) Sediment settling pond design requirements, if the general permit coverage was obtained prior to the effective date of this permit and the sediment settling pond has been installed.) C. SWP3 Signature and Review. 1. Plan Signature and Retention On-Site. The SWP3 shall include the certification in Part

V.H, be signed in accordance with Part V.G., and be retained on site during working hours.

2. Plan Availability

a. On-site: The plan shall be made available immediately upon request of the director or his authorized representative and MS4 operators or their authorized representative during working hours. A copy of the NOI and letter granting permit coverage under this general permit also shall be made available at the site.

b. By written request: The permittee must provide the most recent copy of the SWP3 within 10 days upon written request by any of the following:

i. The director or the director’s authorized representative;

ii. A local agency approving sediment and erosion plans, grading plans or storm

water management plans; or

iii. In the case of a storm water discharge associated with construction activity which discharges through a municipal separate storm sewer system with an NPDES permit, to the operator of the system.

c. To the public: All NOIs, general permit approval for coverage letters, and SWP3s

are considered reports that shall be available to the public in accordance with the Ohio Public Records law. The permittee shall make documents available to the public upon request or provide a copy at public expense, at cost, in a timely manner. However, the permittee may claim to Ohio EPA any portion of an SWP3 as confidential in accordance with Ohio law.

Page 12 of 37 Ohio EPA Permit No.: OHC000004

3. Plan Revision. The director or authorized representative may notify the permittee at any time that the SWP3 does not meet one or more of the minimum requirements of this part. Within 10 days after such notification from the director or authorized representative (or as otherwise provided in the notification), the permittee shall make the required changes to the SWP3 and, if requested, shall submit to Ohio EPA the revised SWP3 or a written certification that the requested changes have been made.

D. Amendments The permittee shall amend the SWP3 whenever there is a change in design, construction, operation or maintenance, which has a significant effect on the potential for the discharge of pollutants to surface waters of the state or if the SWP3 proves to be ineffective in achieving the general objectives of controlling pollutants in storm water discharges associated with construction activity. Amendments to the SWP3 may be reviewed by Ohio EPA in the same manner as Part III.C. E. Duty to inform contractors and subcontractors The permittee shall inform all contractors and subcontractors not otherwise defined as “operators” in Part VII of this general permit who will be involved in the implementation of the SWP3 of the terms and conditions of this general permit. The permittee shall maintain a written document containing the signatures of all contractors and subcontractors involved in the implementation of the SWP3 as proof acknowledging that they reviewed and understand the conditions and responsibilities of the SWP3. The written document shall be created and signatures shall be obtained prior to commencement of work on the construction site. F. Total Maximum Daily Load (TMDL) allocations If a TMDL is approved for any waterbody into which the permittee’s site discharges and requires specific BMPs for construction sites, the director may require the permittee to revise his/her SWP3. G. SWP3 Requirements Operations that discharge storm water from construction activities are subject to the following requirements and the SWP3 shall include the following items: 1. Site description. Each SWP3 shall provide:

a. A description of the nature and type of the construction activity (e.g., low density residential, shopping mall, highway, etc.);

b. Total area of the site and the area of the site that is expected to be disturbed

(i.e., grubbing, clearing, excavation, filling or grading, including off-site borrow areas);

c. An estimate of the impervious area and percent imperviousness created by the

construction activity;

Page 13 of 37 Ohio EPA Permit No.: OHC000004

d. A calculation of the runoff coefficients for both the pre-construction and post- construction site conditions;

e. Existing data describing the soil and, if available, the quality of any discharge

from the site; f. A description of prior land uses at the site;

g. An implementation schedule which describes the sequence of major

construction operations (i.e., designation of vegetative preservation areas, grubbing, excavating, grading, utilities and infrastructure installation) and the implementation of erosion, sediment and storm water management practices or facilities to be employed during each operation of the sequence;

h. The name and/or location of the immediate receiving stream or surface water(s)

and the first subsequent named receiving water(s) and the areal extent and description of wetlands or other special aquatic sites at or near the site which will be disturbed or which will receive discharges from disturbed areas of the project. For discharges to an MS4, the point of discharge to the MS4 and the location where the MS4 ultimately discharges to a stream or surface water of the state shall be indicated;

i. For subdivided developments where the SWP3 does not call for a centralized

sediment control capable of controlling multiple individual lots, a detail drawing of a typical individual lot showing standard individual lot erosion and sediment control practices.

This does not remove the responsibility to designate specific erosion and sediment control practices in the SWP3 for critical areas such as steep slopes, stream banks, drainage ways and riparian zones;

j. Location and description of any storm water discharges associated with

dedicated asphalt and dedicated concrete plants covered by this permit and the best management practices to address pollutants in these storm water discharges;

k. A copy of the permit requirements (attaching a copy of this permit is acceptable); l. A cover page or title identifying the name and location of the site, the name and

contact information of all construction site operators, the name and contact information for the person responsible for authorizing and amending the SWP3, preparation date, and the estimated dates that construction will start and be complete;

m. A log documenting grading and stabilization activities as well as amendments to

the SWP3, which occur after construction activities commence; and

n. Site map showing:

Page 14 of 37 Ohio EPA Permit No.: OHC000004

i. Limits of earth-disturbing activity of the site including associated off-site borrow or spoil areas that are not addressed by a separate NOI and associated SWP3;

ii. Soils types for all areas of the site, including locations of unstable or

highly erodible soils;

iii. Existing and proposed contours. A delineation of drainage watersheds expected during and after major grading activities as well as the size of each drainage watershed, in acres;

iv. Surface water locations including springs, wetlands, streams, lakes, water

wells, etc., on or within 200 feet of the site, including the boundaries of wetlands or stream channels and first subsequent named receiving water(s) the permittee intends to fill or relocate for which the permittee is seeking approval from the Army Corps of Engineers and/or Ohio EPA;

v. Existing and planned locations of buildings, roads, parking facilities and

utilities;

vi. The location of all erosion and sediment control practices, including the location of areas likely to require temporary stabilization during the course of site development;

vii. Sediment and storm water management basins noting their sediment

settling volume and contributing drainage area. Ohio EPA recommends the use of data sheets (see ODNR’s Rainwater and Land Development manual for examples) to provide data for all sediment traps, sediment basins and storm water management treatment practices noting important inputs to design and resulting parameters such as their contributing drainage area, disturbed area, water quality volume, sedimentation volume, practice surface area, facility discharge and dewatering time, outlet type and dimensions;

viii. The location of permanent storm water management practices to be used

to control pollutants in storm water after construction operations have been completed;

ix. Areas designated for the storage or disposal of solid, sanitary and toxic

wastes, including dumpster areas, areas designated for cement truck washout, and vehicle fueling;

x. The location of designated construction entrances where the vehicles will

access the construction site; and xi. The location of any in-stream activities including stream crossings.

2. Controls. In accordance with Part II.A, the SWP3 shall contain a description of the controls appropriate for each construction operation covered by this permit and the operator(s) shall implement such controls. The SWP3 shall clearly describe for each

Page 15 of 37 Ohio EPA Permit No.: OHC000004

major construction activity identified in Part III.G.1.g: (a) appropriate control measures and the general timing (or sequence) during the construction process that the measures will be implemented; and (b) which contractor is responsible for implementation (e.g., contractor A will clear land and install perimeter controls and contractor B will maintain perimeter controls until final stabilization). The SWP3 shall identify the subcontractors engaged in activities that could impact storm water runoff. The SWP3 shall contain signatures from all of the identified subcontractors indicating that they have been informed and understand their roles and responsibilities in complying with the SWP3. Ohio EPA recommends that the primary site operator review the SWP3 with the primary contractor prior to commencement of construction activities and keep a SWP3 training log to demonstrate that this review has occurred.

Ohio EPA recommends that the erosion, sediment, and storm water management practices used to satisfy the conditions of this permit should meet the standards and specifications in the most current edition of Ohio’s Rainwater and Land Development (see definitions) manual or other standards acceptable to Ohio EPA. The controls shall include the following minimum components: a. Non-Structural Preservation Methods. The SWP3 shall make use of practices

which preserve the existing natural condition as much as feasible. Such practices may include: preserving existing vegetation and vegetative buffer strips, phasing of construction operations in order to minimize the amount of disturbed land at any one time and designation of tree preservation areas or other protective clearing or grubbing practices. For all construction activities immediately adjacent to surface waters of the state, the permittee shall comply with the buffer non-numeric effluent limitation in Part II.A.6, as measured from the ordinary high water mark of the surface water.

b. Erosion Control Practices. The SWP3 shall make use of erosion controls that

are capable of providing cover over disturbed soils unless an exception is approved in accordance with Part III.G.4. A description of control practices designed to restabilize disturbed areas after grading or construction shall be included in the SWP3. The SWP3 shall provide specifications for stabilization of all disturbed areas of the site and provide guidance as to which method of stabilization will be employed for any time of the year. Such practices may include: temporary seeding, permanent seeding, mulching, matting, sod stabilization, vegetative buffer strips, phasing of construction operations, use of construction entrances and the use of alternative ground cover.

i. Stabilization. Disturbed areas shall be stabilized in accordance with

Table 1 (Permanent Stabilization) and Table 2 (Temporary Stabilization) in Part II.B of this permit.

ii. Permanent stabilization of conveyance channels. Operators shall undertake special measures to stabilize channels and outfalls and prevent erosive flows. Measures may include seeding, dormant seeding (as defined in the most current edition of the Rainwater and Land Development manual), mulching, erosion control matting, sodding, riprap, natural channel design with bioengineering techniques or rock check dams.

Page 16 of 37 Ohio EPA Permit No.: OHC000004

c. Runoff Control Practices. The SWP3 shall incorporate measures which control the flow of runoff from disturbed areas so as to prevent erosion from occurring. Such practices may include rock check dams, pipe slope drains, diversions to direct flow away from exposed soils and protective grading practices. These practices shall divert runoff away from disturbed areas and steep slopes where practicable. Velocity dissipation devices shall be placed at discharge locations and along the length of any outfall channel to provide non-erosive flow velocity from the structure to a water course so that the natural physical and biological characteristics and functions are maintained and protected.

d. Sediment Control Practices. The plan shall include a description of structural

practices that shall store runoff allowing sediments to settle and/or divert flows away from exposed soils or otherwise limit runoff from exposed areas. Structural practices shall be used to control erosion and trap sediment from a site remaining disturbed for more than 14 days. Such practices may include, among others: sediment settling ponds, silt fences, earth diversion dikes or channels which direct runoff to a sediment settling pond and storm drain inlet protection. All sediment control practices must be capable of ponding runoff in order to be considered functional. Earth diversion dikes or channels alone are not considered a sediment control practice unless those are used in conjunction with a sediment settling pond.

The SWP3 shall contain detail drawings for all structural practices.

i. Timing. Sediment control structures shall be functional throughout the

course of earth disturbing activity. Sediment basins and perimeter sediment barriers shall be implemented prior to grading and within seven days from the start of grubbing. They shall continue to function until the up slope development area is restabilized. As construction progresses and the topography is altered, appropriate controls shall be constructed or existing controls altered to address the changing drainage patterns.

ii. Sediment settling ponds. A sediment settling pond is required for any

one of the following conditions:

Concentrated storm water runoff (e.g., storm sewer or ditch);

Runoff from drainage areas, which exceed the design capacity of silt fence or other sediment barriers;

Runoff from drainage areas that exceed the design capacity of inlet protection; or

Runoff from common drainage locations with 10 or more acres of disturbed land.

The permittee may request approval from Ohio EPA to use alternative controls if the permittee can demonstrate the alternative controls are equivalent in effectiveness to a sediment settling pond. In accordance with Part II.F, if feasible, sediment settling ponds shall be dewatered at the pond surface using a skimmer or equivalent device. The sediment settling pond volume consists of both a dewatering zone and a sediment storage zone. The volume of the dewatering zone shall

Page 17 of 37 Ohio EPA Permit No.: OHC000004

be a minimum of 1800 cubic feet (ft3) per acre of drainage (67 yd3/acre) with a minimum 48-hour drain time for sediment basins serving a drainage area over 5 acres. The volume of the sediment storage zone shall be calculated by one of the following methods: Method 1: The volume of the sediment storage zone shall be 1000 ft3 per disturbed acre within the watershed of the basin. OR Method 2: The volume of the sediment storage zone shall be the volume necessary to store the sediment as calculated with RUSLE or a similar generally accepted erosion prediction model. The accumulated sediment shall be removed from the sediment storage zone once it’s full. When determining the total contributing drainage area, off-site areas and areas which remain undisturbed by construction activity shall be included unless runoff from these areas is diverted away from the sediment settling pond and is not co-mingled with sediment-laden runoff. The depth of the dewatering zone shall be less than or equal to five feet. The configuration between inlets and the outlet of the basin shall provide at least two units of length for each one unit of width (> 2:1 length:width ratio); however, a length to width ratio of 4:1 is recommended. When designing sediment settling ponds, the permittee shall consider public safety, especially as it relates to children, as a design factor for the sediment basin and alternative sediment controls shall be used where site limitations would preclude a safe design. The use of a combination of sediment and erosion control measures in order to achieve maximum pollutant removal is encouraged.

iii. Silt Fence and Diversions. Sheet flow runoff from denuded areas shall

be intercepted by silt fence or diversions to protect adjacent properties and water resources from sediment transported via sheet flow. Where intended to provide sediment control, silt fence shall be placed on a level contour downslope of the disturbed area. This permit does not preclude the use of other sediment barriers designed to control sheet flow runoff. The relationship between the maximum drainage area to silt fence for a particular slope range is shown in the following table:

Silt Fence Maximum Drainage Area Based on Slope

Maximum drainage area (in acres) to 100 linear feet of silt fence

Range of slope for a particular drainage area (in percent)

0.5 < 2%

0.25 > 2% but < 20%

0.125 > 20% but < 50%

Placing silt fence in a parallel series does not extend the size of the drainage area. Storm water diversion practices shall be used to keep runoff away from disturbed areas and steep slopes where practicable. Such devices, which include swales, dikes or berms, may receive storm water runoff from areas up to 10 acres.

Page 18 of 37 Ohio EPA Permit No.: OHC000004

iv. Inlet Protection. Other erosion and sediment control practices shall minimize sediment laden water entering active storm drain systems, unless the storm drain system drains to a sediment settling pond. All inlets receiving runoff from drainage areas of one or more acres will require a sediment settling pond.

v. Surface Waters of the State Protection. If construction activities disturb

areas adjacent to surface waters of the state, structural practices shall be designed and implemented on site to protect all adjacent surface waters of the state from the impacts of sediment runoff. No structural sediment controls (e.g., the installation of silt fence or a sediment settling pond) shall be used in a surface water of the state. For all construction activities immediately adjacent to surface waters of the state, the permittee shall comply with the buffer non-numeric effluent limitation in Part II.A.6, as measured from the ordinary high water mark of the surface water. Where impacts within this buffer area are unavoidable, due to the nature of the construction (e.g., stream crossings for roads or utilities), the project shall be designed such that the number of stream crossings and the width of the disturbance within the buffer area are minimized.

vi. Modifying Controls. If periodic inspections or other information indicates a control has been used inappropriately or incorrectly, the permittee shall replace or modify the control for site conditions.

e. Post-Construction Storm Water Management Requirements. So that receiving

stream’s physical, chemical and biological characteristics are protected and stream functions are maintained, post-construction storm water practices shall provide perpetual management of runoff quality and quantity. To meet the post-construction requirements of this permit, the SWP3 shall contain a description of the post-construction BMPs that will be installed during construction for the site and the rationale for their selection. The rationale shall address the anticipated impacts on the channel and floodplain morphology, hydrology, and water quality. Post-construction BMPs cannot be installed within a surface water of the state (e.g., wetland or stream) unless it’s authorized by a CWA 401 water quality certification, CWA 404 permit, or Ohio EPA non-jurisdictional wetland/stream program approval. Note: localities may have more stringent post-construction requirements.

Detail drawings and maintenance plans shall be provided for all post-construction BMPs. Maintenance plans shall be provided by the permittee to the post-construction operator of the site (including homeowner associations) upon completion of construction activities (prior to termination of permit coverage). For sites located within a community with a regulated municipal separate storm sewer system (MS4), the permittee, land owner, or other entity with legal control of the property may be required to develop and implement a maintenance plan to comply with the requirements of the MS4. Maintenance plans shall ensure that pollutants collected within structural post-construction practices, be disposed of in accordance with local, state, and federal regulations. To ensure that storm water management systems function as they were designed and constructed, the post-construction operation and maintenance plan shall be a stand-alone

Page 19 of 37 Ohio EPA Permit No.: OHC000004

document, which contains: (1) a designated entity for storm water inspection and maintenance responsibilities; (2) the routine and non-routine maintenance tasks to be undertaken; (3) a schedule for inspection and maintenance; (4) any necessary legally binding maintenance easements and agreements; and (5) a map showing all access and maintenance easements. Permittees are not responsible under this permit for operation and maintenance of post-construction practices once coverage under this permit is terminated.

Post-construction storm water BMPs that discharge pollutants from point sources once construction is completed, may in themselves, need authorization under a separate NPDES permit (one example is storm water discharges from regulated industrial sites). Construction activities that do not include the installation of any impervious surface (e.g., soccer fields), abandoned mine land reclamation activities regulated by the Ohio Department of Natural Resources, stream and wetland restoration activities, and wetland mitigation activities are not required to comply with the conditions of Part III.G.2.e of this permit. Linear construction projects, (e.g., pipeline or utility line installation), which do not result in the installation of additional impervious surface, are not required to comply with the conditions of Part III.G.2.e of this permit. However, linear construction projects shall be designed to minimize the number of stream crossings and the width of disturbance and achieve final stabilization of the disturbed area as defined in Part VII.J.1.

Large Construction Activities. For all large construction activities (involving the disturbance of five or more acres of land or will disturb less than five acres, but is a part of a larger common plan of development or sale which will disturb five or more acres of land), the post construction BMP(s) chosen shall be able to detain storm water runoff for protection of the stream channels, stream erosion control, and improved water quality. The BMP(s) chosen must be compatible with site and soil conditions. Structural post-construction storm water treatment practices shall be incorporated into the permanent drainage system for the site. The BMP(s) chosen must be sized to treat the water quality volume (WQv) and ensure compliance with Ohio’s Water Quality Standards in OAC Chapter 3745-1. The WQv shall be equivalent to the volume of runoff from a 0.75-inch rainfall and shall be determined according to the following equation:

WQv = C * P * A / 12

where:

WQv = water quality volume in acre-feet

C = runoff coefficient appropriate for storms less than 1 inch

(Either use the following formula: C = 0.858i3 - 0.78i2 + 0.774i + 0.04,

where i = fraction of post-construction impervious surface or use Table 1)

P = 0.75 inch precipitation depth

A = area draining into the BMP in acres

Page 20 of 37 Ohio EPA Permit No.: OHC000004

Table 1 Runoff Coefficients Based on the Type of Land Use

Land Use Runoff Coefficient

Industrial & Commercial 0.8

High Density Residential (>8 dwellings/acre) 0.5

Medium Density Residential (4 to 8 dwellings/acre) 0.4

Low Density Residential (<4 dwellings/acre) 0.3

Open Space and Recreational Areas 0.2

Where the land use will be mixed, the runoff coefficient should be calculated using a weighted average. For example, if 60% of the contributing drainage area to the storm water treatment structure is Low Density Residential, 30% is High Density Residential, and 10% is Open Space, the runoff coefficient is calculated as follows (0.6)(0.3) + (0.3)(0.5) + (0.1)(0.2) = 0.35.

An additional volume equal to 20 percent of the WQv shall be incorporated into the BMP for sediment storage. Ohio EPA recommends that BMPs be designed according to the methodology included in the most current edition of the Rainwater and Land Development manual or in another design manual acceptable for use by Ohio EPA. The BMPs listed in Table 2 below shall be considered standard BMPs approved for general use. However communities with a regulated MS4 may limit the use of some of these BMPs. BMPs shall be designed such that the drain time is long enough to provide treatment, but short enough to provide storage for successive rainfall events and avoid the creation of nuisance conditions. The outlet structure for the post-construction BMP shall not discharge more than the first half of the WQv or extended detention volume (EDv) in less than one-third of the drain time. The EDv is the volume of storm water runoff that must be detained by a structural post-construction BMP. The EDv is equal to 75 percent of the WQv for wet extended detention basins, but is equal to the WQv for all other BMPs listed in Table 2.

Page 21 of 37 Ohio EPA Permit No.: OHC000004

Table 2 Structural Post-Construction BMPs & Associated

Drain (Drawdown) Times

Best Management Practice Drain Time of WQv

Infiltration Basin or Trench1 48 hours

Permeable Pavement – Infiltration1 48 hours

Permeable Pavement – Extended Detention 24 hours

Dry Extended Detention Basin2 48 hours

Wet Extended Detention Basin3 24 hours

Constructed Wetland (above permanent pool)4 24 hours

Sand & Other Media Filtration5 24 hours

Bioretention Area/Cell5,6 24 hours

Pocket Wetland7 24 hours

1 Practices that are designed to fully infiltrate the WQv (basin, trench, permeable pavement) shall empty within 48 hours to provide storage for the subsequent storm events.

2 Dry basins must include forebay and micropool each sized at 10% of the WQv.

3 Provide both a permanent pool and an EDv above the permanent pool, each sized at 0.75 WQv.

4 Extended detention shall be provided for the WQv above the permanent water pool.

5 The surface ponding area (WQv) shall completely empty within 24 hours so that there is no standing water. Shorter drawdown times are acceptable as long as design criteria in Ohio’s Rainwater and Land Development manual have been met.

6 This would include Grassed Linear Bioretention which was previously called Enhanced Water Quality Swale.

7 Pocket wetlands must have a wet pool equal to the WQv, with 25% of the WQv in a pool and 75% in marshes. The EDv above the permanent pool must be equal to the WQv.

The permittee may request approval from Ohio EPA to use alternative structural post-construction BMPs if the permittee can demonstrate that the alternative BMPs are equivalent in effectiveness to those listed in Table 2 above. Construction activities shall be exempt from this condition if it can be demonstrated that the WQv is provided within an existing structural post-construction BMP that is part of a larger common plan of development or if structural post-construction BMPs are addressed in a regional or local storm water management plan. A municipally operated regional storm water BMP can be used as a post-construction BMP provided that the BMP can detain the WQv from its entire drainage area and release it over a 24 hour period. Transportation Projects. The construction of new roads and roadway improvement projects by public entities (i.e., the state, counties, townships, cities, or villages) may implement post-construction BMPs in compliance with the current version (as of the effective date of this permit) of the Ohio Department of Transportation’s “Location and Design Manual, Volume Two Drainage Design” that has been accepted by Ohio EPA as an alternative to the conditions of this permit.

Page 22 of 37 Ohio EPA Permit No.: OHC000004

Offsite Mitigation of Post-Construction. Ohio EPA may authorize the offsite mitigation of the post-construction requirements of Part III.G.2.e of this permit on a case by case basis provided the permittee clearly demonstrates the BMPs listed in Table 2 are not feasible and the following criteria is met: (1) a maintenance agreement or policy is established to ensure operations and treatment in perpetuity; (2) the offsite location discharges to the same HUC-14 watershed unit; and (3) the mitigation ratio of the WQv is 1.5 to 1 or the WQv at the point of retrofit, whichever is greater. Requests for offsite mitigation must be received prior to receipt of the NOI applications.

Redevelopment Projects Sites that have been previously developed where no post-construction BMPs were installed shall either ensure a 20 percent net reduction of the site impervious area, provide for treatment of at least 20 percent of the WQv, or a combination of the two. A one-for-one credit towards the 20 percent net reduction of impervious area can be obtained through the use of green roofs. Where projects are a combination of new development and redevelopment, the total WQv that must be treated shall be calculated by a weighted average based on acreage, with the new development at 100 percent WQv and redevelopment at 20 percent WQv. Non-Structural Post-Construction BMPs The size of the structural post-construction can be reduced by incorporating non-structural post-construction BMPs into the design. Practices such as preserving open space will reduce the runoff coefficient and, thus, the WQv. Ohio EPA encourages the implementation of riparian and wetland setbacks. Practices which reduce storm water runoff include green roofs, rain barrels, conservation development, smart growth, low-impact development, and other site design techniques. For examples, see the Ohio Lake Erie Commission’s Balanced Growth Program at http://balancedgrowth.ohio.gov/. In order to promote the implementation of such practices, the Director may consider the use of non-structural practices to demonstrate compliance with Part III.G.2.e of this permit for areas of the site not draining into a common drainage system of the site, i.e., sheet flow from perimeter areas such as the rear yards of residential lots, for low density development scenarios, or where the permittee can demonstrate that the intent of pollutant removal and stream protection, as required in Part III.G.2.e of this permit is being addressed through non-structural post-construction BMPs based upon review and approval by Ohio EPA. Use of Alternative Post-Construction BMPs This permit does not preclude the use of innovative or experimental post-construction storm water management technologies. However, the Director may require these practices to be tested using the protocol outlined in the Technology Acceptance Reciprocity Partnership’s (TARP) Protocol for Stormwater Best Management Practice Demonstrations or other approvable protocol. For guidance, see the following:

http://www.njstormwater.org

http://www.mastep.net/

The Director may require discharges from such structures to be monitored to ensure compliance with Part III.G.2.e of this permit. Permittees shall request

Page 23 of 37 Ohio EPA Permit No.: OHC000004

approval from Ohio EPA to use alternative post-construction BMPs if the permittee can demonstrate that the alternative BMPs are equivalent in effectiveness to those listed in Table 2 above. To demonstrate this equivalency, the permittee shall show that the alternative BMP has a minimum total suspended solids (TSS) removal efficiency of 80 percent under both laboratory and field conditions. Tests shall be conducted by an independent, third party tester. Also, the WQv discharge rate from the practice shall be reduced to prevent stream bed erosion and protect the physical and biological stream integrity unless there will be negligible hydrological impact to the receiving surface water of the state. The discharges will have a negligible impact if the permittee can demonstrate that one of the following four conditions exist: i. The entire WQv is recharged to groundwater; ii. The larger common plan of development or sale will create less than one

acre of impervious surface; iii. The project is a redevelopment project within an ultra-urban setting (i.e., a

downtown area or on a site where 100 percent of the project area is already impervious surface and the storm water discharge is directed into an existing storm sewer system); or

iv. The storm water drainage system of the development discharges directly into a large river (fourth order or greater) or to a lake and where the development area is less than 5 percent of the watershed area upstream of the development site, unless a TMDL identified water quality problems into the receiving surface waters of the state.

The Director shall only consider the use of alternative BMPs on projects where the permittee can demonstrate that the implementation of the BMPs listed in Table 2 is infeasible due to physical site constraints that prevent the ability to provide functional BMP design. Alternative practices may include, but are not limited to, underground detention structures, vegetated swales and vegetated filter strips designed using water quality flow, natural depressions, rain barrels, green roofs, rain gardens, catch basin inserts, and hydrodynamics separators. The Director may also consider non-structural post-construction approaches where no local requirements for such practices exist. Small Construction Activities For all small land disturbance activities (which disturb one or more, but less than five acres of land and is not a part of a larger common plan of development or sale which will disturb five or more acres of land), a description of measures that will be installed during the construction process to control pollutants in storm water discharges that will occur after construction operations have been completed must be included in the SWP3. Structural measures should be placed on upland soils to the degree attainable. Such practices may include, but are not limited to: storm water detention structures (including wet basins); storm water retention structures; flow attenuation by use of open vegetated swales and natural depressions; infiltration of runoff onsite; and sequential systems (which combine several practices). The SWP3 shall include an explanation of the technical basis used to select the practices to control pollution where flows exceed pre-development levels.

Page 24 of 37 Ohio EPA Permit No.: OHC000004

f. Surface Water Protection. If the project site contains any streams, rivers, lakes, wetlands or other surface waters, certain construction activities at the site may be regulated under the CWA and/or state isolated wetland permit requirements. Sections 404 and 401 of the Act regulate the discharge of dredged or fill material into surface waters and the impacts of such activities on water quality, respectively. Construction activities in surface waters which may be subject to CWA regulation and/or state isolated wetland permit requirements include, but are not limited to: sewer line crossings, grading, backfilling or culverting streams, filling wetlands, road and utility line construction, bridge installation and installation of flow control structures. If the project contains streams, rivers, lakes or wetlands or possible wetlands, the permittee shall contact the appropriate U.S. Army Corps of Engineers District Office. (CAUTION: Any area of seasonally wet hydric soil is a potential wetland - please consult the Soil Survey and list of hydric soils for your County, available at your county’s Soil and Water Conservation District. If you have any questions about Section 401 water quality certification, please contact the Ohio Environmental Protection Agency, Section 401 Coordinator.)

U.S. Army Corps of Engineers (Section 404 regulation):

Huntington, WV District (304) 399-5210 (Muskingum River, Hocking River, Scioto River, Little Miami River, and Great Miami River Basins)

Buffalo, NY District (716) 879-4330 (Lake Erie Basin) Pittsburgh, PA District (412) 395-7155 (Mahoning River Basin) Louisville, KY District (502) 315-6686 (Ohio River)

Ohio EPA 401/404 and non-jurisdictional stream/wetland coordinator can be contacted at (614) 644-2001 (all of Ohio) Concentrated storm water runoff from BMPs to natural wetlands shall be converted to diffuse flow before the runoff enters the wetlands. The flow should be released such that no erosion occurs downslope. Level spreaders may need to be placed in series, particularly on steep sloped sites, to ensure non-erosive velocities. Other structural BMPs may be used between storm water features and natural wetlands, in order to protect the natural hydrology, hydroperiod, and wetland flora. If the applicant proposes to discharge to natural wetlands, a hydrologic analysis shall be performed. The applicant shall attempt to match the pre-development hydroperiods and hydrodynamics that support the wetland. The applicant shall assess whether their construction activity will adversely impact the hydrologic flora and fauna of the wetland. Practices such as vegetative buffers, infiltration basins, conservation of forest cover, and the preservation of intermittent streams, depressions, and drainage corridors may be used to maintain wetland hydrology.

g. Other controls.

i. Non-Sediment Pollutant Controls. In accordance with Part II.E, no solid (other than sediment) or liquid waste, including building materials, shall be discharged in storm water runoff. The permittee must implement all necessary BMPs to prevent the discharge of non-sediment pollutants to the drainage system of the site or surface waters of the state. Under

Page 25 of 37 Ohio EPA Permit No.: OHC000004

no circumstance shall wastewater from the washout of concrete trucks, stucco, paint, form release oils, curing compounds, and other construction materials be discharged directly into a drainage channel, storm sewer or surface waters of the state. Also, no pollutants from vehicle fuel, oils, or other vehicle fluids can be discharged to surface waters of the state. No exposure of storm water to waste materials is recommended. The SWP3 must include methods to minimize the exposure of building materials, building products, construction wastes, trash, landscape materials, fertilizers, pesticides, herbicides, detergents, and sanitary waste to precipitation, storm water runoff, and snow melt. In accordance with Part II.D.3, the SWP3 shall include measures to prevent and respond to chemical spills and leaks. You may also reference the existence of other plans (i.e., Spill Prevention Control and Countermeasure (SPCC) plans, spill control programs, Safety Response Plans, etc.) provided that such plan addresses conditions of this permit condition and a copy of such plan is maintained on site.

ii. Off-site traffic. Off-site vehicle tracking of sediments and dust

generation shall be minimized. In accordance with Part II.D.1, the SWP3 shall include methods to minimize the discharge of pollutants from equipment and vehicle washing, wheel wash water, and other wash waters. No detergents may be used to wash vehicles. Wash waters shall be treated in a sediment basin or alternative control that provides equivalent treatment prior to discharge.

iii. Compliance with other requirements. The SWP3 shall be consistent

with applicable State and/or local waste disposal, sanitary sewer or septic system regulations, including provisions prohibiting waste disposal by open burning and shall provide for the proper disposal of contaminated soils to the extent these are located within the permitted area.

iv. Trench and ground water control. In accordance with Part II.C, there

shall be no turbid discharges to surface waters of the state resulting from dewatering activities. If trench or ground water contains sediment, it shall pass through a sediment settling pond or other equally effective sediment control device, prior to being discharged from the construction site. Alternatively, sediment may be removed by settling in place or by dewatering into a sump pit, filter bag or comparable practice. Ground water which does not contain sediment or other pollutants is not required to be treated prior to discharge. However, care must be taken when discharging ground water to ensure that it does not become pollutant-laden by traversing over disturbed soils or other pollutant sources.

v. Contaminated Sediment. Where construction activities are to occur on

sites with contamination from previous activities, operators shall be aware that concentrations of materials that meet other criteria (is not considered a Hazardous Waste, meeting VAP standards, etc.) may still result in storm water discharges in excess of Ohio Water Quality Standards. Such discharges are not authorized by this permit. Appropriate BMPs include, but are not limited to:

Page 26 of 37 Ohio EPA Permit No.: OHC000004

The use of berms, trenches, and pits to collect contaminated runoff and prevent discharges;

Pumping runoff into a sanitary sewer (with prior approval of the sanitary sewer operator) or into a container for transport to an appropriate treatment/disposal facility; and

Covering areas of contamination with tarps or other methods that prevent storm water from coming into contact with the material.

Operators should consult with Ohio EPA Division of Surface Water prior to seeking permit coverage.

h. Maintenance. All temporary and permanent control practices shall be maintained and repaired as needed to ensure continued performance of their intended function. All sediment control practices must be maintained in a functional condition until all up slope areas they control are permanently stabilized. The SWP3 shall be designed to minimize maintenance requirements. The applicant shall provide a description of maintenance procedures needed to ensure the continued performance of control practices.

i. Inspections. At a minimum, procedures in an SWP3 shall provide that all

controls on the site are inspected at least once every seven calendar days and within 24 hours after any storm event greater than one-half inch of rain per 24 hour period. The inspection frequency may be reduced to at least once every month if the entire site is temporarily stabilized or runoff is unlikely due to weather conditions (e.g., site is covered with snow, ice, or the ground is frozen). A waiver of inspection requirements is available until one month before thawing conditions are expected to result in a discharge if all of the following conditions are met: the project is located in an area where frozen conditions are anticipated to continue for extended periods of time (i.e., more than one month); land disturbance activities have been suspended; and the beginning and ending dates of the waiver period are documented in the SWP3. Once a definable area is finally stabilized, the area may be marked on the SWP3 and no further inspection requirements apply to that portion of the site. The permittee shall assign “qualified inspection personnel” to conduct these inspections to ensure that the control practices are functional and to evaluate whether the SWP3 is adequate and properly implemented in accordance with the schedule proposed in Part III.G.1.g of this permit or whether additional control measures are required.

Following each inspection, a checklist must be completed and signed by the qualified inspection personnel representative. At a minimum, the inspection report shall include:

i. the inspection date; ii. names, titles, and qualifications of personnel making the inspection; iii. weather information for the period since the last inspection (or since

commencement of construction activity if the first inspection) including a best estimate of the beginning of each storm event, duration of each storm event, approximate amount of rainfall for each storm event (in inches), and whether any discharges occurred;

iv. weather information and a description of any discharges occurring at the time of the inspection;

Page 27 of 37 Ohio EPA Permit No.: OHC000004

v. location(s) of discharges of sediment or other pollutants from the site; vi. location(s) of BMPs that need to be maintained; vii. location(s) of BMPs that failed to operate as designed or proved inadequate

for a particular location; viii. location(s) where additional BMPs are needed that did not exist at the time of

inspection; and ix. corrective action required including any changes to the SWP3 necessary and

implementation dates. Disturbed areas and areas used for storage of materials that are exposed to precipitation shall be inspected for evidence of or the potential for pollutants entering the drainage system. Erosion and sediment control measures identified in the SWP3 shall be observed to ensure that those are operating correctly. Discharge locations shall be inspected to ascertain whether erosion and sediment control measures are effective in preventing significant impacts to the receiving waters. Locations where vehicles enter or exit the site shall be inspected for evidence of off-site vehicle tracking. The permittee shall maintain for three years following the submittal of a notice of termination form, a record summarizing the results of the inspection, names(s) and qualifications of personnel making the inspection, the date(s) of the inspection, major observations relating to the implementation of the SWP3 and a certification as to whether the facility is in compliance with the SWP3 and the permit and identify any incidents of non-compliance. The record and certification shall be signed in accordance with Part V.G. of this permit.

i. When practices require repair or maintenance. If the inspection

reveals that a control practice is in need of repair or maintenance, with the exception of a sediment settling pond, it shall be repaired or maintained within 3 days of the inspection. Sediment settling ponds shall be repaired or maintained within 10 days of the inspection.

ii. When practices fail to provide their intended function. If the

inspection reveals that a control practice fails to perform its intended function and that another, more appropriate control practice is required, the SWP3 shall be amended and the new control practice shall be installed within 10 days of the inspection.

iii. When practices depicted on the SWP3 are not installed. If the

inspection reveals that a control practice has not been implemented in accordance with the schedule contained in Part III.G.1.g of this permit, the control practice shall be implemented within 10 days from the date of the inspection. If the inspection reveals that the planned control practice is not needed, the record shall contain a statement of explanation as to why the control practice is not needed.

3. Approved State or local plans. All dischargers regulated under this general permit must comply, except those exempted under state law, with the lawful requirements of municipalities, counties and other local agencies regarding discharges of storm water from construction activities. All erosion and sediment control plans and storm water

Page 28 of 37 Ohio EPA Permit No.: OHC000004

management plans approved by local officials shall be retained with the SWP3 prepared in accordance with this permit. Applicable requirements for erosion and sediment control and storm water management approved by local officials are, upon submittal of a NOI form, incorporated by reference and enforceable under this permit even if they are not specifically included in an SWP3 required under this permit. When the project is located within the jurisdiction of a regulated municipal separate storm sewer system (MS4), the permittee shall certify that the SWP3 complies with the requirements of the storm water management program of the MS4 operator. 4. Exceptions. If specific site conditions prohibit the implementation of any of the erosion and sediment control practices contained in this permit or site specific conditions are such that implementation of any erosion and sediment control practices contained in this permit will result in no environmental benefit, then the permittee shall provide justification for rejecting each practice based on site conditions. Exceptions from implementing the erosion and sediment control standards contained in this permit will be approved or denied on a case-by-case basis. The permittee may request approval from Ohio EPA to use alternative methods to satisfy conditions in this permit if the permittee can demonstrate that the alternative methods are sufficient to protect the overall integrity of receiving streams and the watershed. Alternative methods will be approved or denied on a case-by-case basis. PART IV. NOTICE OF TERMINATION REQUIREMENTS A. Failure to notify. The terms and conditions of this permit shall remain in effect until a signed Notice of Termination (NOT) form is submitted. Failure to submit an NOT constitutes a violation of this permit and may affect the ability of the permittee to obtain general permit coverage in the future. B. When to submit an NOT. 1. Permittees wishing to terminate coverage under this permit shall submit an NOT form in

accordance with Part V.G. of this permit. Compliance with this permit is required until an NOT form is submitted. The permittee’s authorization to discharge under this permit terminates at midnight of the day the NOT form is submitted. Prior to submitting the NOT form, the permittee shall conduct a site inspection in accordance with Part III.G.2.i of this permit and have a maintenance agreement in place to ensure all post-construction BMPs will be maintained in perpetuity.

2. All permittees shall submit an NOT form within 45 days of completing all permit

requirements. Enforcement actions may be taken if a permittee submits an NOT form without meeting one or more of the following conditions:

a. Final stabilization (see definition in Part VII) has been achieved on all portions of the site for which the permittee is responsible (including, if applicable, returning agricultural land to its pre-construction agricultural use); b. Another operator(s) has assumed control over all areas of the site that have not been finally stabilized;

Page 29 of 37 Ohio EPA Permit No.: OHC000004

c. For residential construction only, temporary stabilization has been completed and the lot, which includes a home, has been transferred to the homeowner. (Note: For individual lots without housing, which are sold by the developer, the individual lot permittee shall implement final stabilization prior to the individual lot permittee terminating permit coverage.); or

d. An exception has been granted under Part III.G.4.

C. How to submit an NOT. Permittees shall use Ohio EPA’s approved NOT form. The form shall be completed and mailed according to the instructions and signed in accordance with Part V.G of this permit. PART V. STANDARD PERMIT CONDITIONS. A. Duty to comply. The permittee shall comply with all conditions of this permit. Any permit noncompliance constitutes a violation of ORC Chapter 6111 and is grounds for enforcement action. Ohio law imposes penalties and fines for persons who knowingly make false statements or knowingly swear or affirm the truth of a false statement previously made. B. Continuation of an expired general permit. An expired general permit continues in force and effect until a new general permit is issued. C. Need to halt or reduce activity not a defense. It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the permitted activity in order to maintain compliance with the conditions of this permit. D. Duty to mitigate. The permittee shall take all reasonable steps to minimize or prevent any discharge in violation of this permit which has a reasonable likelihood of adversely affecting human health or the environment. E. Duty to provide information. The permittee shall furnish to the director, within 10 days of written request, any information which the director may request to determine whether cause exists for modifying, revoking and reissuing, or terminating this permit or to determine compliance with this permit. The permittee shall also furnish to the director upon request copies of records required to be kept by this permit.

Page 30 of 37 Ohio EPA Permit No.: OHC000004

F. Other information. When the permittee becomes aware that he or she failed to submit any relevant facts or submitted incorrect information in the NOI, SWP3, NOT or in any other report to the director, he or she shall promptly submit such facts or information. G. Signatory requirements. All NOIs, NOTs, SWP3s, reports, certifications or information either submitted to the director or that this permit requires to be maintained by the permittee, shall be signed. 1. These items shall be signed as follows: a. For a corporation: By a responsible corporate officer. For the purpose of this section, a responsible corporate officer means: i. A president, secretary, treasurer or vice-president of the corporation in charge of a principal business function or any other person who performs similar policy or decision-making functions for the corporation; or ii. The manager of one or more manufacturing, production or operating facilities, provided, the manager is authorized to make management decisions that govern the operation of the regulated facility including having the explicit or implicit duty of making major capital investment recommendations and initiating and directing other comprehensive measures to assure long-term environmental compliance with environmental laws and regulations; the manager can ensure that the necessary systems are established or actions taken to gather complete and accurate information for permit application requirements; and where authority to sign documents has been assigned or delegated to the manager in accordance with corporate procedures; b. For a partnership or sole proprietorship: By a general partner or the proprietor, respectively; or c. For a municipality, State, Federal or other public agency: By either a principal executive officer or ranking elected official. For purposes of this section, a principal executive officer of a Federal agency includes (1) the chief executive officer of the agency or (2) a senior executive officer having responsibility for the overall operations of a principal geographic unit of the agency (e.g., Regional Administrators of U.S. EPA). 2. All reports required by the permits and other information requested by the director shall be signed by a person described in Part V.G.1 of this permit or by a duly authorized representative of that person. A person is a duly authorized representative only if: a. The authorization is made in writing by a person described in Part V.G.1 of this permit and submitted to the director;

Page 31 of 37 Ohio EPA Permit No.: OHC000004

b. The authorization specifies either an individual or a position having responsibility for the overall operation of the regulated facility or activity, such as the position of manager, operator of a well or well field, superintendent, position of equivalent responsibility or an individual or position having overall responsibility for environmental matters for the company. (A duly authorized representative may thus be either a named individual or any individual occupying a named position); and

c. The written authorization is submitted to the director. 3. Changes to authorization. If an authorization under Part V.G.2 of this permit is no longer accurate because a different individual or position has responsibility for the overall operation of the facility, a new authorization satisfying the requirements of Part V.G.2 of this permit must be submitted to the director prior to or together with any reports, information or applications to be signed by an authorized representative. H. Certification. Any person signing documents under this section shall make the following certification:

"I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."

I. Oil and hazardous substance liability. Nothing in this permit shall be construed to preclude the institution of any legal action or relieve the permittee from any responsibilities, liabilities or penalties to which the permittee is or may be subject under section 311 of the CWA or 40 CFR Part 112. 40 CFR Part 112 establishes procedures, methods and equipment and other requirements for equipment to prevent the discharge of oil from non-transportation-related onshore and offshore facilities into or upon the navigable surface waters of the state or adjoining shorelines. J. Property rights. The issuance of this permit does not convey any property rights of any sort, nor any exclusive privileges, nor does it authorize any injury to private property nor any invasion of personal rights, nor any infringement of Federal, State or local laws or regulations. K. Severability. The provisions of this permit are severable and if any provision of this permit or the application of any provision of this permit to any circumstance is held invalid, the application of such provision to other circumstances and the remainder of this permit shall not be affected thereby.

Page 32 of 37 Ohio EPA Permit No.: OHC000004

L. Transfers. Ohio NPDES general permit coverage is transferable. Ohio EPA must be notified in writing sixty days prior to any proposed transfer of coverage under an Ohio NPDES general permit. The transferee must inform Ohio EPA it will assume the responsibilities of the original permittee transferor. M. Environmental laws. No condition of this permit shall release the permittee from any responsibility or requirements under other environmental statutes or regulations. N. Proper operation and maintenance. The permittee shall at all times properly operate and maintain all facilities and systems of treatment and control (and related appurtenances) which are installed or used by the permittee to achieve compliance with the conditions of this permit and with the requirements of SWP3s. Proper operation and maintenance requires the operation of backup or auxiliary facilities or similar systems, installed by a permittee only when necessary to achieve compliance with the conditions of the permit. O. Inspection and entry. The permittee shall allow the director or an authorized representative of Ohio EPA, upon the presentation of credentials and other documents as may be required by law, to: 1. Enter upon the permittee's premises where a regulated facility or activity is located or conducted or where records must be kept under the conditions of this permit; 2. Have access to and copy at reasonable times, any records that must be kept under the conditions of this permit; 3. Inspect at reasonable times any facilities or equipment (including monitoring and control equipment); and 4. Sample or monitor at reasonable times, for the purposes of assuring permit compliance

or as otherwise authorized by the Clean Water Act, any substances or parameters at any location.

P. Duty to Reapply If the permittee wishes to continue an activity regulated by this permit after the expiration date of this permit, the permittee must apply for and obtain a new permit. Q. Permit Actions This permit may be modified, revoked and reissued, or terminated for cause. The filing of a request by the permittee for a permit modification, revocation and reissuance, or termination, or a notification of planned changes or anticipated noncompliance does not stay any permit condition.

Page 33 of 37 Ohio EPA Permit No.: OHC000004

R. Bypass The provisions of 40 CFR Section 122.41(m), relating to “Bypass,” are specifically incorporated herein by reference in their entirety. For definition of “Bypass,” see Part VII.C. S. Upset The provisions of 40 CFR Section 122.41(n), relating to “Upset,” are specifically incorporated herein by reference in their entirety. For definition of “Upset,” see Part VII.GG. T. Monitoring and Records The provisions of 40 CFR Section 122.41(j), relating to “Monitoring and Records,” are specifically incorporated herein by reference in their entirety. U. Reporting Requirements The provisions of 40 CFR Section 122.41(l), relating to “Reporting Requirements,” are specifically incorporated herein by reference in their entirety. PART VI. REOPENER CLAUSE If there is evidence indicating potential or realized impacts on water quality due to any storm water discharge associated with construction activity covered by this permit, the permittee of such discharge may be required to obtain coverage under an individual permit or an alternative general permit in accordance with Part I.C of this permit or the permit may be modified to include different limitations and/or requirements. Permit modification or revocation will be conducted according to ORC Chapter 6111. PART VII. DEFINITIONS A. “Act” means Clean Water Act (formerly referred to as the Federal Water Pollution Control Act or Federal Water Pollution Control Act Amendments of 1972) Pub. L. 92- 500, as amended Pub. L. 95-217, Pub. L. 95-576, Pub. L. 96-483, Pub. L. 97-117 and Pub. L. 100-4, 33 U.S.C. 1251 et. seq. B. “Best management practices (BMPs)” means schedules of activities, prohibitions of practices, maintenance procedures and other management practices (both structural and non-structural) to prevent or reduce the pollution of surface waters of the state. BMP's also include treatment requirements, operating procedures and practices to control plant and/or construction site runoff, spillage or leaks, sludge or waste disposal or drainage from raw material storage. C. “Bypass” means the intentional diversion of waste streams from any portion of a

treatment facility. D. “Commencement of construction” means the initial disturbance of soils associated with clearing, grubbing, grading, placement of fill, or excavating activities or other construction activities.

Page 34 of 37 Ohio EPA Permit No.: OHC000004

E. “Concentrated storm water runoff” means any storm water runoff which flows through a drainage pipe, ditch, diversion or other discrete conveyance channel. F. “Director” means the director of the Ohio Environmental Protection Agency. G. “Discharge” means the addition of any pollutant to the surface waters of the state from a point source. H. “Disturbance” means any clearing, grading, excavating, filling, or other alteration of land surface where natural or man-made cover is destroyed in a manner that exposes the underlying soils. I. “Drainage watershed” means for purposes of this permit the total contributing drainage area to a BMP, i.e., the “watershed” directed to the practice. This would also include any off-site drainage. J. “Final stabilization” means that either: 1. All soil disturbing activities at the site are complete and a uniform perennial vegetative cover (e.g., evenly distributed, without large bare areas) with a density of at least 70 percent cover for the area has been established on all unpaved areas and areas not covered by permanent structures or equivalent stabilization measures (such as the use of mulches, rip-rap, gabions or geotextiles) have been employed. In addition, all temporary erosion and sediment control practices are removed and disposed of and all trapped sediment is permanently stabilized to prevent further erosion; or 2. For individual lots in residential construction by either: a. The homebuilder completing final stabilization as specified above or b. The homebuilder establishing temporary stabilization including perimeter controls for an individual lot prior to occupation of the home by the homeowner and informing the homeowner of the need for and benefits of, final stabilization. (Homeowners typically have an incentive to put in the landscaping functionally equivalent to final stabilization as quick as possible to keep mud out of their homes and off sidewalks and driveways.); or 3. For construction projects on land used for agricultural purposes (e.g., pipelines across crop or range land), final stabilization may be accomplished by returning the disturbed land to its pre-construction agricultural use. Areas disturbed that were previously used for agricultural activities, such as buffer strips immediately adjacent to surface waters of the state and which are not being returned to their pre-construction agricultural use, must meet the final stabilization criteria in (1) or (2) above. K. “Individual Lot NOI” means a Notice of Intent for an individual lot to be covered by this permit (see Part I of this permit).

Page 35 of 37 Ohio EPA Permit No.: OHC000004

L. “Larger common plan of development or sale”- means a contiguous area where multiple separate and distinct construction activities may be taking place at different times on different schedules under one plan. M. “MS4" means municipal separate storm sewer system which means a conveyance or system of conveyances (including roads with drainage systems, municipal streets, catch basins, curbs, gutters, ditches, man-made channels or storm drains) that are: 1. Owned or operated by the federal government, state, municipality, township, county, district(s) or other public body (created by or pursuant to state or federal law) including special district under state law such as a sewer district, flood control district or drainage districts or similar entity or a designated and approved management agency under section 208 of the act that discharges into surface waters of the state; and 2. Designed or used for collecting or conveying solely storm water, 3. Which is not a combined sewer and 4. Which is not a part of a publicly owned treatment works. N. “National Pollutant Discharge Elimination System (NPDES)” means the national program for issuing, modifying, revoking and reissuing, terminating, monitoring and enforcing permits and enforcing pretreatment requirements, under sections 307, 402, 318 and 405 of the CWA. The term includes an "approved program.” O. “NOI” means notice of intent to be covered by this permit. P. “NOT” means notice of termination. Q. “Operator” means any party associated with a construction project that meets either of the following two criteria: 1. The party has operational control over construction plans and specifications, including the ability to make modifications to those plans and specifications; or 2. The party has day-to-day operational control of those activities at a project which are necessary to ensure compliance with an SWP3 for the site or other permit conditions (e.g., they are authorized to direct workers at a site to carry out activities required by the SWP3 or comply with other permit conditions).

As set forth in Part I.F.1, there can be more than one operator at a site and under these

circumstances, the operators shall be co-permittees.

R. “Ordinary high water mark” means that line on the shore established by the fluctuations of water and indicated by physical characteristics such as clear, natural line impressed on the bank, shelving, changes in the character of soil, destruction of terrestrial vegetation, the presence of litter and debris, or other appropriate means that consider the characteristics of the surrounding areas. S. “Owner or operator” means the owner or operator of any “facility or activity” subject to regulation under the NPDES program.

Page 36 of 37 Ohio EPA Permit No.: OHC000004

T. “Permanent stabilization” means the establishment of permanent vegetation, decorative landscape mulching, matting, sod, rip rap and landscaping techniques to provide permanent erosion control on areas where construction operations are complete or where no further disturbance is expected for at least one year. U. “Percent imperviousness” means the impervious area created divided by the total area of the project site. V. “Point source” means any discernible, confined and discrete conveyance, including but not limited to, any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, rolling stock, concentrated animal feeding operation, landfill leachate collection system, vessel or the floating craft from which pollutants are or may be discharged. This term does not include return flows from irrigated agriculture or agricultural storm water runoff. W. “Qualified inspection personnel” means a person knowledgeable in the principles and practice of erosion and sediment controls, who possesses the skills to assess all conditions at the construction site that could impact storm water quality and to assess the effectiveness of any sediment and erosion control measures selected to control the quality of storm water discharges from the construction activity. X. “Rainwater and Land Development” is a manual describing construction and post- construction best management practices and associated specifications. A copy of the manual may be obtained by contacting the Ohio Department of Natural Resources, Division of Soil & Water Conservation. Y. “Riparian area” means the transition area between flowing water and terrestrial (land) ecosystems composed of trees, shrubs and surrounding vegetation which serve to stabilize erodible soil, improve both surface and ground water quality, increase stream shading and enhance wildlife habitat. Z. “Runoff coefficient” means the fraction of total rainfall that will appear at the conveyance as runoff. AA. “Sediment settling pond” means a sediment trap, sediment basin or permanent basin that has been temporarily modified for sediment control, as described in the latest edition of the Rainwater and Land Development manual. BB. “State isolated wetland permit requirements” means the requirements set forth in Sections 6111.02 through 6111.029 of the ORC. CC. “Storm water” means storm water runoff, snow melt and surface runoff and drainage. DD. “Steep slopes” means slopes that are 15 percent or greater in grade. Where a local

government or industry technical manual has defined what is to be considered a “steep slope,” this permit’s definition automatically adopts that definition.

EE. “Surface waters of the state” or “water bodies” means all streams, lakes, reservoirs, ponds, marshes, wetlands or other waterways which are situated wholly or partially within the boundaries of the state, except those private waters which do not combine or effect a junction with natural surface or underground waters. Waters defined as

Page 37 of 37 Ohio EPA Permit No.: OHC000004

sewerage systems, treatment works or disposal systems in Section 6111.01 of the ORC are not included. FF. “SWP3” means storm water pollution prevention plan. GG. “Upset” means an exceptional incident in which there is unintentional and temporary

noncompliance with technology based permit effluent limitations because of factors beyond the reasonable control of the permittee. An upset does not include noncompliance to the extent caused by operational error, improperly designed treatment facilities, inadequate treatment facilities, lack of preventive maintenance, or careless or improper operation.

HH. “Temporary stabilization” means the establishment of temporary vegetation, mulching, geotextiles, sod, preservation of existing vegetation and other techniques capable of quickly establishing cover over disturbed areas to provide erosion control between construction operations. II. “Water Quality Volume (WQv)” means the volume of storm water runoff which must be captured and treated prior to discharge from the developed site after construction is complete. WQv is based on the expected runoff generated by the mean storm precipitation volume from post-construction site conditions at which rapidly diminishing returns in the number of runoff events captured begins to occur.

14

Appendix A Weekly and Rain Event Erosion Control Checklist

Contractor __________________________________________________________________Project Number __________________ Co.-Rt.-Sec. ______________________ Date ________

R=Replacement W=Working M=Maintenance I=Install D=Delete Rain Amt Inspection_________Date_________

Stat

ion

To

Stat

ion

Side

Off

set

Bal

loon

Ref

.

Peri

met

er c

ontr

ol

Inle

t Pro

tect

ion

Con

str.

Seed

Dik

es F

ill S

lope

s

Ditc

h C

ut S

lope

s

Slop

e D

rain

s

FF D

itch

Che

cks

Roc

k D

itch

Ch

Bal

e Fi

lter D

ike

Sedi

men

t Bas

ins

Stre

am R

eloc

ate

Stre

am C

ross

ing

DateWorkWasComplete

To

To

To

To

To

To

To

To

To

To

Notes:___________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Total Station-to-Station Inspected____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ Inspect By Signature Title Date Given ToODOT

15

Appendix B

Signature list

Signature Printed Name Title Company Date

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\36 - 015500(02801) - Traffic Control.doc 02801-1

SECTION 02801

TRAFFIC CONTROL PART 1 GENERAL 1.01 WORK INCLUDED

A. This work shall consist of furnishing and applying all necessary appurtenances for the

maintenance of traffic in the construction areas as per ODOT 614. B. The Contractor shall pay for and obtain a permit to close one lane on Teamsters Drive

and Lilac Street from the City of Youngstown. 1.02 REFERENCE

A. Construction and Material Specifications Department of Transportation, State of Ohio latest edition.

B. Ohio Manual of Uniform Traffic Control Services for Streets and Highways.

END OF SECTION - 02801

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\37 - 312200(02810) - Grading & Turfing.doc 02810-1

SECTION 02810 GRADING AND TURFING

PART 1 GENERAL 1.01 SCOPE

A. This section covers establishment of a graded area, in accordance with the rough grading plan (attached at the end of this section), unless otherwise directed by the Engineer or specifications.

1.02 MATERIALS

A. Topsoil shall be friable loam, reasonably free of subsoil, clay lumps, brush, roots, weeds, and other objectionable organic material, stones and other inorganic material larger than 2" in any dimension, litter and all materials harmful to plant growth.

B. Lime shall be pulverized agricultural limestone containing a minimum of 85% total

carbonates, ground so that at least 90% passes a No. 20 sieve and at least 50% passes a No. 100 sieve, if applicable.

C. Starter fertilizer shall be standard 8-16-8 or 12-12-12 commercial product in bags showing

weight analysis and manufacturer's name. Availability of the various elements shall conform to the standards of the Association of Official Agricultural Chemists.

D. Utility mix grass seed shall be clean and fresh, packed in sealed bags showing net weight,

composition of mix, date of germination tests and supplier's name.

1. An Utility Mixture, such as, Turfgrass Enterprises, Inc., Utility Mix, consisting of 40% perennial ryegrasses, 30% Annual ryegrasses, 15% creeping red fescue and 15% Kentucky Bluegrass.

E. Mulch shall be clean wheat or oats straw.

PART 2 APPLICATION 2.01 TOPSOIL

A. Topsoil shall be friable loam, reasonably free of subsoil, clay lumps, brush, roots, weeds, and other objectionable organic material, stones and other inorganic material larger than 2" in any dimension, litter and all materials harmful to plant growth.

B. For topsoil to be considered a loamy material, it must not contain more than 40-percent clay

passing the No.10 sieve. 2.02 LIME AND FERTILIZER

A. Apply lime at a rate of fifty pounds per one thousand square feet, if necessary.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\37 - 312200(02810) - Grading & Turfing.doc 02810-2

B. Apply starter fertilizer at the rate recommended by the manufacturer’s recommendation.

C. Work lime and/or fertilizer into soil to a depth of at least 2" by raking, discing or harrowing.

2.03 SEEDING

A. Apply seed uniformly at a rate of 5 pounds per one thousand square feet. Use suitable mechanical spreader. Hydro-seeding will be permitted.

B. Contractor shall have the choice of the time during which he will seed, and shall be

responsible for obtaining a satisfactory catch of grass as hereinafter specified. 2.04 MULCHING

A. Apply mulch immediately after seeding, and at the minimum rate of one hundred thirty pounds per one thousand square feet. Mechanical blower will be allowed to apply mulch provided machine is specifically designed and approved for this purpose. Machines that cut mulch into short pieces will not be permitted.

2.05 WATERING

Apply water to the seeded area(s) 1 time per day, until the seed comes up is recommended. After the seed has come up watering is recommended every other day for a ½ hour to an hour, until the grass is fully established. Once the grass is established the contractor shall perform a minimum of 4 waterings, as required.

2.06 MAINTENANCE

A. All areas and spots not showing a catch of grass shall be re-seeded. This operation shall be repeated until a complete coverage is obtained. Seeded areas shall be kept moist until a satisfactory catch of grass is established. Lastly, the Contractor shall perform three (3) mowings.

END OF SECTION - 02810

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\39 - 31 11 00 - Clearing & Grubbing.doc 31 11 00 - 1

SECTION 31 11 00

CLEARING AND GRUBBING

PART 1 GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions, Supplementary Conditions (if included), and Division 1 Specifications Sections, apply to this Section.

B. Clearing and grubbing activities shall comply with ODOT CMS (2016), Item 201.

1.2 SECTION INCLUDES

A. Removal of surface debris.

B. Removal of trees, shrubs, other plant life, stumps, roots, tree debris.

C. Removal of miscellaneous debris piles, tires, etc.

1.3 REGULATORY REQUIREMENTS

A. Comply with Laws and Regulations for environmental requirements, disposal of debris, burning debris on Site, and use of herbicides.

B. Coordinate clearing work with Utility Companies, locate all existing active utility lines traversing the site and determine the requirements for their protection.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 PREPARATION

A. Verify with the Engineer that existing trees, shrubs, and other objects designated to remain are tagged or identified.

B. Identify a salvage area for placing removed materials.

C. Install all soil erosion control measures per Stormwater Pollution Prevention Plan and any permits from the Ohio EPA prior to starting in site clearing and grubbing.

D. Notify Engineer at least five full working days prior to commencing the work of this section.

N:\61\Environmental Managers\Brian Fischer\68 Teamsters Drive\Specs\39 - 31 11 00 - Clearing & Grubbing.doc 31 11 00 - 2

E. The drawings do not purport to show all objects existing on the site.

3.2 PROTECTION

A. Protect trees, plant growth, and features designated to remain, as final landscaping.

B. Protect benchmarks, utilities, survey control points, and existing structures from damage or displacement.

3.3 CLEARING

A. Clear areas required for access to Site and execution of Work.

B. Remove trees and shrubs indicated, stumps, and root system to a depth of 12 inches.

C. Clear undergrowth and deadwood without disturbing subsoil.

D. Remove surface debris.

3.4 REMOVAL

A. Remove all debris from the site and leave the site in a neat and orderly condition to the approval of the Engineer.

3.5 DISPOSAL

A. Dispose of debris, extracted plant life, and removed materials off Site in accordance with Laws and Regulations.

END OF SECTION