Contract 9036 - Change Order 35€¦ · for the 20 19 construction season. An Independent Engineers...

6
1! RECEIVED f\ ' ' I '·..;: ...... .. 7 Washington State ...,,,;~ Deparbnent of Transportation . ...... { Change Record t Contract Number 009036 Contract Title ·~ 1V 468th Ave. SE to W Summit Rd. Rehab. Cone / Deck - Federal Aid Number NHPP-0901 ( 490) Change Order Number 35 Change Description '!; --,- ....,-=-- .. : <I\ . ~ ,. t ··- 2019 Traffic Control .,r').~~·...c.· · .: •;' ... -- .. Date Apr 24, 2019 Region I Project Engineer South Central Region Scott Golbek Phone Number 509-577-1810 Prime Contractor I Design-Builder IMCO General Construction 181 Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications or the RFP r D Change proposed by Contractor I Design-Builder Evolution & Description Of Change This project is a concrete pavement and bridge deck rehabilitation project on eastbound 1-90 just to the west of the summit of Snoqualmie Pass. Several issues have transpired which have affected the work on this project. The most dramatic impact has been from the increased work required to rehabilitate the bridge deck on Bridge 90/97.2. Impacts have increased the cost of the work substantially and affected the entire project schedule to the extent that a project originally scheduled to be completed in two construction seasons has now expanded into a third season. Various change orders have dealt with the Contractors entitlement for added cost and time. Change Order 31 found entitlement for an added 92 working days. As a result the work has pushed into a third construction season. · The Contractor has requested an equitable adjustment for traffic control items that are associated with work that will occur in 2019. This change order provides an equitable adjustment in accordance with Section 1-04.4 for increased traffic control costs, (escalation), that have resulted from the extended schedule. The Contractor has agreed to honor unit bid prices for all items, including those which are currently in excess of 125% for work performed through the end of 2018. This change order will also establish new traffic control items for the Contract for the 2019 construction season. DOT Form 422-002 Revised 06/2016

Transcript of Contract 9036 - Change Order 35€¦ · for the 20 19 construction season. An Independent Engineers...

Page 1: Contract 9036 - Change Order 35€¦ · for the 20 19 construction season. An Independent Engineers Estimate, IEE, was prepared to determine traffic control costs and quantities for

1

RECEIVED f I

middot

~ 7 Washington State ~ Deparbnent of Transportation ~ Change Record

t ~ Contract Number 009036

Contract Title middot~ 1V468th Ave SE to W Summit Rd Rehab Cone Deck -

Federal Aid Number NHPP-0901 ( 490)

Change Order Number 35

Change Description bull----=-- bull ltI ~

t middotmiddot-2019 Traffic Control

r)~~middotcmiddotmiddot bull

-- Date Apr 24 2019

Region IProject Engineer South Central Region Scott Golbek

Phone Number 509-577-1810

Prime Contractor I Design-Builder

IMCO General Construction

181 Ordered by Engineer under the terms of Section 1-044 of the Standard Specifications or the RFP r

D Change proposed by Contractor I Design-Builder

Evolution amp Description Of Change

This project is a concrete pavement and bridge deck rehabilitation project on eastbound 1-90 just to the west ofthe summit of Snoqualmie Pass Several issues have transpired which have affected the work on this project The most dramatic impact has been from the increased work required to rehabilitate the bridge deck on Bridge 90972 Impacts have increased the cost of the work substantially and affected the entire project schedule to the extent that a project originally scheduled to be completed in two construction seasons has now expanded into a third season Various change orders have dealt with the Contractors entitlement for added cost and time Change Order 31 found entitlement for an added 92 working days As a result the work has pushed into a third construction season middot

The Contractor has requested an equitable adjustment for traffic control items that are associated with work that will occur in 2019

This change order provides an equitable adjustment in accordance with Section 1-044 for increased traffic control costs (escalation) that have resulted from the extended schedule The Contractor has agreed to honor unit bid prices for all items including those which are currently in excess of 125 for work performed through the end of 2018

This change order will also establish new traffic control items for the Contract for the 2019 construction season

DOT Form 422-002 Revised 062016

bull

Contract Number

009036 Basis of Cost amp Justification

I Contract Title

468th Ave SE to W Summit Rd Rehab Cone Deck IChange Order Number

35

Entitlement has been found for an extension oftime This is documented with Change Order 31 which added 94 working days due to the changed condition created by the added work involved with Bridge 90972 Due to this change an additional construction season was needed to complete the Contract work This change order will provide traffic control items quantities for the 20 19 construction season

An Independent Engineers Estimate IEE was prepared to determine traffic control costs and quantities for the 2019 construction season this estimate is $115726104 Costs were developed using unit bid history blue book rates for equipment and labor and comparisons to similar work Hours for the various items was estimated by examining the remaining work based on the revised and approved schedule Included in the IEE is an estimate for traffic control hours and the Jump sum cost for Traffic Control Supervisor A copy of the IEE is attached as reference An overall cost was not provided by the Contractor however IMCO did submit costs for individual items Costs for the various items of work that were provided by the Contractor were reviewed by the Engineer Unit prices reflect agreement between the Project Engineer and the Contractor Quantities are based on estimated quantities ofthe IEE

Three traffic control items are currently overrun The Contractor has agreed that all previous quantities oftraffic control items will be paid at unit bid costs

The cost of this change order based on agreed upon costs is $85576996

Contract nme

This change order will make no revision to the number ofworking days on the Contract

Prior Approvals

Headquarters Construction Jon Keeth -April 22 2019 Region Construction Brian White Will Smith-April 17 2019 Project Engineer Scott Golbek- April 17 2019

List Attachments

Change Order 35 IEE

Distribution By Project Office Copy of Change Records amp Change Order wBackup - Project Engineer Copy of ONLY Change Order - Prime Contractor I Design-Builder Electronic Copy of Change Records amp Change Order wBackup - Slate Construction Office Original of Change Records amp Change Order wBackup - Region Construction Office

Region Original of Change Records amp Change Order wBackup - Stale Construction Office

DOT Fam 422-002 Revised 062016

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 1 of -

CONTRACT NO 009036 FEDERAL AID NO NHPP-0901 (490) CONTRACT TITLE I-90 468IH AVE SEl IO W SlMgt1IT RD aNCRBTE DECK CHANGE ORDER NO 35 2019 IRAFFIC CIWmOL

PRIME CONTRACTOR -

WA 98248-9801

(X) Ordered by Engineer under the terms of Section 1-044 of the Standard Specifications

( ) Change proposed by Contractor

SURETY CONSENT

ATTORNEY IN FACT

DATE

ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE THIS ORDER ESTIMATED CONTRACT TOTAL AFTER CHANGE

Approval Required ) Region

2779935866 3321793421

85576996 3407370417

) Olympia Service Center ) Local AgenflG 45 4301

PROJECT ENGINEER

oliL9 DATr 7

Y APPROVAL RECOMMENDED

~(REGIONAl ADMIN -- ~ h-( ~ middot 7drr4~~

( )EXECUTED

ONSTRUCTION ENOINEER

DATE ~411

( )EXECUTED OTHER APPROVAL WHEN REQUIRED

SIONATUREmiddot

REPRESENTING

DATE

CG02Y04 (revised Feb 2005)

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 2 of J

CONTRACT NO 009036 CHANGEORDERNO 35

All wirk rreterials and measurements to be in accoroance with the provisions of the Standard Specifications and Special Provisions for the type of construction involved

Ibis cantract is revised as follows

Change Order 31 found entitlenent for an increase in Orking days an the Contract Ibis change onler provides for an equitable adjustrrent for all traffic control bid itens and establishes new itens for the 2019 construction season

The following are the traffic control itens and quantities through Decanber 31 2018 as shown an Estimate 22 Quantities of these itens will be paid at unit bid prices as shown below

Itan Final Quantity 58 Transportable Atterruator 5 EACH 59 qperatian of Transportable Atterruator 23095 HR 71 Sequential ArrcM Sign 377355 HR 72 Portable Changeable Message Sign 141220 HR 73 other Tatpgtrary Traffic Control $47500000 IS 74 other Traffic Control Iabgtr 1193800 HR 75 Traffic Control SUpervisor $26800000 IS

The following new itens are added to the Contract co 35 Transportable Atterruator CO 35 Cperatian of Transportable Atterruator CO 35 Sequential ArrcM Sign co 35 Portable Changeable Message Sign co 35 other Traffic Chntrol Iabgtr CO 35 other Tatpgtrary Traffic Chntrol CO 35 Traffic Chntrol SUpervisor

Chnstructian Requirenents Work shall be in accoroance with Section 1-10

Measurerent Measurerent for new itens established by this Change Order will be in accoroance with section 1-104

Payment Payment for new itens established by this Change Order will be in accon3ance with Section 1-105

Payment for traffic control will be rrede under existing traffic control bid itens through Decanber 31 2018 Payment for traffic control an or after Jarruary 1 2019 will be rrede under the new co 35 itens established by this change order and shown an page 3

Ibis Olange Order resolves and clears all overruns and undernms of I tens 58 59 71 72 73 74 and 75 No additional equitable adj ustrrent will be

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 3 of

CONTRACT NO 009036 CHANGE ORDER NO 35

provided for these items

Working Days Ibis change order will make no revision to the number of working days on the OJntract

It

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 4 of amp

CONTRACT NO 009036 CHANGE ORDER NO 35

ITEM NO

GROUP NO

STD ITEM

ITEM DESCRIPTION

UNIT MEASURE

UNIT PRICE

EST QTY CHANGE

EST AMT CHANGE

1033 01 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 100 2056880

1033 02 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1033 04 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1034 01 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 6700 569500

1034 02 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 23800 2023000

1034 04 co 35 OPERATION OF TRANSPORTABLE AITEN HOUR 8500 44000 3740000

1035 01 co 35 SEQUENTIAL ARROW SIGN HOUR 268 55000 147400

1035 02 co 35 SEQUENTIAL ARROW SIGN HOUR 268 193000 517240

1035 04 co 35 SEQUENTIAL ARROW SIGN HOUR 268 356000 954080

1036 01 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 41000 410000

1036 02 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 145000 1450000

1036 04 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 268000 2680000

1037 01 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 749462

1037 02 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS ooo 000 2664754

1037 04 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 4913140

1038 01 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 47500 3562500

1038 02 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 169000 12675000

1038 04 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 311000 23325000

1039 01 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 1342037

1039 02 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 4771686

1039 04 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 8797797

85576996

Page 2: Contract 9036 - Change Order 35€¦ · for the 20 19 construction season. An Independent Engineers Estimate, IEE, was prepared to determine traffic control costs and quantities for

bull

Contract Number

009036 Basis of Cost amp Justification

I Contract Title

468th Ave SE to W Summit Rd Rehab Cone Deck IChange Order Number

35

Entitlement has been found for an extension oftime This is documented with Change Order 31 which added 94 working days due to the changed condition created by the added work involved with Bridge 90972 Due to this change an additional construction season was needed to complete the Contract work This change order will provide traffic control items quantities for the 20 19 construction season

An Independent Engineers Estimate IEE was prepared to determine traffic control costs and quantities for the 2019 construction season this estimate is $115726104 Costs were developed using unit bid history blue book rates for equipment and labor and comparisons to similar work Hours for the various items was estimated by examining the remaining work based on the revised and approved schedule Included in the IEE is an estimate for traffic control hours and the Jump sum cost for Traffic Control Supervisor A copy of the IEE is attached as reference An overall cost was not provided by the Contractor however IMCO did submit costs for individual items Costs for the various items of work that were provided by the Contractor were reviewed by the Engineer Unit prices reflect agreement between the Project Engineer and the Contractor Quantities are based on estimated quantities ofthe IEE

Three traffic control items are currently overrun The Contractor has agreed that all previous quantities oftraffic control items will be paid at unit bid costs

The cost of this change order based on agreed upon costs is $85576996

Contract nme

This change order will make no revision to the number ofworking days on the Contract

Prior Approvals

Headquarters Construction Jon Keeth -April 22 2019 Region Construction Brian White Will Smith-April 17 2019 Project Engineer Scott Golbek- April 17 2019

List Attachments

Change Order 35 IEE

Distribution By Project Office Copy of Change Records amp Change Order wBackup - Project Engineer Copy of ONLY Change Order - Prime Contractor I Design-Builder Electronic Copy of Change Records amp Change Order wBackup - Slate Construction Office Original of Change Records amp Change Order wBackup - Region Construction Office

Region Original of Change Records amp Change Order wBackup - Stale Construction Office

DOT Fam 422-002 Revised 062016

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 1 of -

CONTRACT NO 009036 FEDERAL AID NO NHPP-0901 (490) CONTRACT TITLE I-90 468IH AVE SEl IO W SlMgt1IT RD aNCRBTE DECK CHANGE ORDER NO 35 2019 IRAFFIC CIWmOL

PRIME CONTRACTOR -

WA 98248-9801

(X) Ordered by Engineer under the terms of Section 1-044 of the Standard Specifications

( ) Change proposed by Contractor

SURETY CONSENT

ATTORNEY IN FACT

DATE

ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE THIS ORDER ESTIMATED CONTRACT TOTAL AFTER CHANGE

Approval Required ) Region

2779935866 3321793421

85576996 3407370417

) Olympia Service Center ) Local AgenflG 45 4301

PROJECT ENGINEER

oliL9 DATr 7

Y APPROVAL RECOMMENDED

~(REGIONAl ADMIN -- ~ h-( ~ middot 7drr4~~

( )EXECUTED

ONSTRUCTION ENOINEER

DATE ~411

( )EXECUTED OTHER APPROVAL WHEN REQUIRED

SIONATUREmiddot

REPRESENTING

DATE

CG02Y04 (revised Feb 2005)

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 2 of J

CONTRACT NO 009036 CHANGEORDERNO 35

All wirk rreterials and measurements to be in accoroance with the provisions of the Standard Specifications and Special Provisions for the type of construction involved

Ibis cantract is revised as follows

Change Order 31 found entitlenent for an increase in Orking days an the Contract Ibis change onler provides for an equitable adjustrrent for all traffic control bid itens and establishes new itens for the 2019 construction season

The following are the traffic control itens and quantities through Decanber 31 2018 as shown an Estimate 22 Quantities of these itens will be paid at unit bid prices as shown below

Itan Final Quantity 58 Transportable Atterruator 5 EACH 59 qperatian of Transportable Atterruator 23095 HR 71 Sequential ArrcM Sign 377355 HR 72 Portable Changeable Message Sign 141220 HR 73 other Tatpgtrary Traffic Control $47500000 IS 74 other Traffic Control Iabgtr 1193800 HR 75 Traffic Control SUpervisor $26800000 IS

The following new itens are added to the Contract co 35 Transportable Atterruator CO 35 Cperatian of Transportable Atterruator CO 35 Sequential ArrcM Sign co 35 Portable Changeable Message Sign co 35 other Traffic Chntrol Iabgtr CO 35 other Tatpgtrary Traffic Chntrol CO 35 Traffic Chntrol SUpervisor

Chnstructian Requirenents Work shall be in accoroance with Section 1-10

Measurerent Measurerent for new itens established by this Change Order will be in accoroance with section 1-104

Payment Payment for new itens established by this Change Order will be in accon3ance with Section 1-105

Payment for traffic control will be rrede under existing traffic control bid itens through Decanber 31 2018 Payment for traffic control an or after Jarruary 1 2019 will be rrede under the new co 35 itens established by this change order and shown an page 3

Ibis Olange Order resolves and clears all overruns and undernms of I tens 58 59 71 72 73 74 and 75 No additional equitable adj ustrrent will be

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 3 of

CONTRACT NO 009036 CHANGE ORDER NO 35

provided for these items

Working Days Ibis change order will make no revision to the number of working days on the OJntract

It

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 4 of amp

CONTRACT NO 009036 CHANGE ORDER NO 35

ITEM NO

GROUP NO

STD ITEM

ITEM DESCRIPTION

UNIT MEASURE

UNIT PRICE

EST QTY CHANGE

EST AMT CHANGE

1033 01 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 100 2056880

1033 02 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1033 04 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1034 01 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 6700 569500

1034 02 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 23800 2023000

1034 04 co 35 OPERATION OF TRANSPORTABLE AITEN HOUR 8500 44000 3740000

1035 01 co 35 SEQUENTIAL ARROW SIGN HOUR 268 55000 147400

1035 02 co 35 SEQUENTIAL ARROW SIGN HOUR 268 193000 517240

1035 04 co 35 SEQUENTIAL ARROW SIGN HOUR 268 356000 954080

1036 01 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 41000 410000

1036 02 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 145000 1450000

1036 04 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 268000 2680000

1037 01 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 749462

1037 02 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS ooo 000 2664754

1037 04 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 4913140

1038 01 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 47500 3562500

1038 02 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 169000 12675000

1038 04 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 311000 23325000

1039 01 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 1342037

1039 02 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 4771686

1039 04 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 8797797

85576996

Page 3: Contract 9036 - Change Order 35€¦ · for the 20 19 construction season. An Independent Engineers Estimate, IEE, was prepared to determine traffic control costs and quantities for

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 1 of -

CONTRACT NO 009036 FEDERAL AID NO NHPP-0901 (490) CONTRACT TITLE I-90 468IH AVE SEl IO W SlMgt1IT RD aNCRBTE DECK CHANGE ORDER NO 35 2019 IRAFFIC CIWmOL

PRIME CONTRACTOR -

WA 98248-9801

(X) Ordered by Engineer under the terms of Section 1-044 of the Standard Specifications

( ) Change proposed by Contractor

SURETY CONSENT

ATTORNEY IN FACT

DATE

ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE THIS ORDER ESTIMATED CONTRACT TOTAL AFTER CHANGE

Approval Required ) Region

2779935866 3321793421

85576996 3407370417

) Olympia Service Center ) Local AgenflG 45 4301

PROJECT ENGINEER

oliL9 DATr 7

Y APPROVAL RECOMMENDED

~(REGIONAl ADMIN -- ~ h-( ~ middot 7drr4~~

( )EXECUTED

ONSTRUCTION ENOINEER

DATE ~411

( )EXECUTED OTHER APPROVAL WHEN REQUIRED

SIONATUREmiddot

REPRESENTING

DATE

CG02Y04 (revised Feb 2005)

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 2 of J

CONTRACT NO 009036 CHANGEORDERNO 35

All wirk rreterials and measurements to be in accoroance with the provisions of the Standard Specifications and Special Provisions for the type of construction involved

Ibis cantract is revised as follows

Change Order 31 found entitlenent for an increase in Orking days an the Contract Ibis change onler provides for an equitable adjustrrent for all traffic control bid itens and establishes new itens for the 2019 construction season

The following are the traffic control itens and quantities through Decanber 31 2018 as shown an Estimate 22 Quantities of these itens will be paid at unit bid prices as shown below

Itan Final Quantity 58 Transportable Atterruator 5 EACH 59 qperatian of Transportable Atterruator 23095 HR 71 Sequential ArrcM Sign 377355 HR 72 Portable Changeable Message Sign 141220 HR 73 other Tatpgtrary Traffic Control $47500000 IS 74 other Traffic Control Iabgtr 1193800 HR 75 Traffic Control SUpervisor $26800000 IS

The following new itens are added to the Contract co 35 Transportable Atterruator CO 35 Cperatian of Transportable Atterruator CO 35 Sequential ArrcM Sign co 35 Portable Changeable Message Sign co 35 other Traffic Chntrol Iabgtr CO 35 other Tatpgtrary Traffic Chntrol CO 35 Traffic Chntrol SUpervisor

Chnstructian Requirenents Work shall be in accoroance with Section 1-10

Measurerent Measurerent for new itens established by this Change Order will be in accoroance with section 1-104

Payment Payment for new itens established by this Change Order will be in accon3ance with Section 1-105

Payment for traffic control will be rrede under existing traffic control bid itens through Decanber 31 2018 Payment for traffic control an or after Jarruary 1 2019 will be rrede under the new co 35 itens established by this change order and shown an page 3

Ibis Olange Order resolves and clears all overruns and undernms of I tens 58 59 71 72 73 74 and 75 No additional equitable adj ustrrent will be

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 3 of

CONTRACT NO 009036 CHANGE ORDER NO 35

provided for these items

Working Days Ibis change order will make no revision to the number of working days on the OJntract

It

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 4 of amp

CONTRACT NO 009036 CHANGE ORDER NO 35

ITEM NO

GROUP NO

STD ITEM

ITEM DESCRIPTION

UNIT MEASURE

UNIT PRICE

EST QTY CHANGE

EST AMT CHANGE

1033 01 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 100 2056880

1033 02 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1033 04 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1034 01 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 6700 569500

1034 02 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 23800 2023000

1034 04 co 35 OPERATION OF TRANSPORTABLE AITEN HOUR 8500 44000 3740000

1035 01 co 35 SEQUENTIAL ARROW SIGN HOUR 268 55000 147400

1035 02 co 35 SEQUENTIAL ARROW SIGN HOUR 268 193000 517240

1035 04 co 35 SEQUENTIAL ARROW SIGN HOUR 268 356000 954080

1036 01 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 41000 410000

1036 02 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 145000 1450000

1036 04 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 268000 2680000

1037 01 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 749462

1037 02 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS ooo 000 2664754

1037 04 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 4913140

1038 01 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 47500 3562500

1038 02 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 169000 12675000

1038 04 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 311000 23325000

1039 01 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 1342037

1039 02 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 4771686

1039 04 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 8797797

85576996

Page 4: Contract 9036 - Change Order 35€¦ · for the 20 19 construction season. An Independent Engineers Estimate, IEE, was prepared to determine traffic control costs and quantities for

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 2 of J

CONTRACT NO 009036 CHANGEORDERNO 35

All wirk rreterials and measurements to be in accoroance with the provisions of the Standard Specifications and Special Provisions for the type of construction involved

Ibis cantract is revised as follows

Change Order 31 found entitlenent for an increase in Orking days an the Contract Ibis change onler provides for an equitable adjustrrent for all traffic control bid itens and establishes new itens for the 2019 construction season

The following are the traffic control itens and quantities through Decanber 31 2018 as shown an Estimate 22 Quantities of these itens will be paid at unit bid prices as shown below

Itan Final Quantity 58 Transportable Atterruator 5 EACH 59 qperatian of Transportable Atterruator 23095 HR 71 Sequential ArrcM Sign 377355 HR 72 Portable Changeable Message Sign 141220 HR 73 other Tatpgtrary Traffic Control $47500000 IS 74 other Traffic Control Iabgtr 1193800 HR 75 Traffic Control SUpervisor $26800000 IS

The following new itens are added to the Contract co 35 Transportable Atterruator CO 35 Cperatian of Transportable Atterruator CO 35 Sequential ArrcM Sign co 35 Portable Changeable Message Sign co 35 other Traffic Chntrol Iabgtr CO 35 other Tatpgtrary Traffic Chntrol CO 35 Traffic Chntrol SUpervisor

Chnstructian Requirenents Work shall be in accoroance with Section 1-10

Measurerent Measurerent for new itens established by this Change Order will be in accoroance with section 1-104

Payment Payment for new itens established by this Change Order will be in accon3ance with Section 1-105

Payment for traffic control will be rrede under existing traffic control bid itens through Decanber 31 2018 Payment for traffic control an or after Jarruary 1 2019 will be rrede under the new co 35 itens established by this change order and shown an page 3

Ibis Olange Order resolves and clears all overruns and undernms of I tens 58 59 71 72 73 74 and 75 No additional equitable adj ustrrent will be

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 3 of

CONTRACT NO 009036 CHANGE ORDER NO 35

provided for these items

Working Days Ibis change order will make no revision to the number of working days on the OJntract

It

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 4 of amp

CONTRACT NO 009036 CHANGE ORDER NO 35

ITEM NO

GROUP NO

STD ITEM

ITEM DESCRIPTION

UNIT MEASURE

UNIT PRICE

EST QTY CHANGE

EST AMT CHANGE

1033 01 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 100 2056880

1033 02 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1033 04 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1034 01 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 6700 569500

1034 02 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 23800 2023000

1034 04 co 35 OPERATION OF TRANSPORTABLE AITEN HOUR 8500 44000 3740000

1035 01 co 35 SEQUENTIAL ARROW SIGN HOUR 268 55000 147400

1035 02 co 35 SEQUENTIAL ARROW SIGN HOUR 268 193000 517240

1035 04 co 35 SEQUENTIAL ARROW SIGN HOUR 268 356000 954080

1036 01 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 41000 410000

1036 02 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 145000 1450000

1036 04 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 268000 2680000

1037 01 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 749462

1037 02 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS ooo 000 2664754

1037 04 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 4913140

1038 01 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 47500 3562500

1038 02 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 169000 12675000

1038 04 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 311000 23325000

1039 01 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 1342037

1039 02 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 4771686

1039 04 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 8797797

85576996

Page 5: Contract 9036 - Change Order 35€¦ · for the 20 19 construction season. An Independent Engineers Estimate, IEE, was prepared to determine traffic control costs and quantities for

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 3 of

CONTRACT NO 009036 CHANGE ORDER NO 35

provided for these items

Working Days Ibis change order will make no revision to the number of working days on the OJntract

It

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 4 of amp

CONTRACT NO 009036 CHANGE ORDER NO 35

ITEM NO

GROUP NO

STD ITEM

ITEM DESCRIPTION

UNIT MEASURE

UNIT PRICE

EST QTY CHANGE

EST AMT CHANGE

1033 01 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 100 2056880

1033 02 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1033 04 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1034 01 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 6700 569500

1034 02 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 23800 2023000

1034 04 co 35 OPERATION OF TRANSPORTABLE AITEN HOUR 8500 44000 3740000

1035 01 co 35 SEQUENTIAL ARROW SIGN HOUR 268 55000 147400

1035 02 co 35 SEQUENTIAL ARROW SIGN HOUR 268 193000 517240

1035 04 co 35 SEQUENTIAL ARROW SIGN HOUR 268 356000 954080

1036 01 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 41000 410000

1036 02 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 145000 1450000

1036 04 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 268000 2680000

1037 01 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 749462

1037 02 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS ooo 000 2664754

1037 04 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 4913140

1038 01 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 47500 3562500

1038 02 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 169000 12675000

1038 04 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 311000 23325000

1039 01 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 1342037

1039 02 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 4771686

1039 04 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 8797797

85576996

Page 6: Contract 9036 - Change Order 35€¦ · for the 20 19 construction season. An Independent Engineers Estimate, IEE, was prepared to determine traffic control costs and quantities for

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

DATE 043019CHANGE ORDER Page 4 of amp

CONTRACT NO 009036 CHANGE ORDER NO 35

ITEM NO

GROUP NO

STD ITEM

ITEM DESCRIPTION

UNIT MEASURE

UNIT PRICE

EST QTY CHANGE

EST AMT CHANGE

1033 01 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 100 2056880

1033 02 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1033 04 co 35 TRANSPORTABLE ATTENUATOR EACH 2056880 200 4113760

1034 01 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 6700 569500

1034 02 co 35 OPERATION OF TRANSPORTABLE ATTEN HOUR 8500 23800 2023000

1034 04 co 35 OPERATION OF TRANSPORTABLE AITEN HOUR 8500 44000 3740000

1035 01 co 35 SEQUENTIAL ARROW SIGN HOUR 268 55000 147400

1035 02 co 35 SEQUENTIAL ARROW SIGN HOUR 268 193000 517240

1035 04 co 35 SEQUENTIAL ARROW SIGN HOUR 268 356000 954080

1036 01 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 41000 410000

1036 02 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 145000 1450000

1036 04 co 35 PORTABLE CHANGEABLE SIGN HOUR 1000 268000 2680000

1037 01 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 749462

1037 02 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS ooo 000 2664754

1037 04 co 35 OTHER TEMPORARY TRAFFIC CONTROL LS 000 000 4913140

1038 01 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 47500 3562500

1038 02 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 169000 12675000

1038 04 co 35 OTHER TRAFFIC CONTROL LABOR HOUR 7500 311000 23325000

1039 01 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 1342037

1039 02 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 4771686

1039 04 co 35 TRAFFIC CONTROL SUPERVISOR LS 000 000 8797797

85576996