Consultancy Support for Electricity Transmission … Consultancy Support for Electricity...

275
Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION (CER) DSO Final June 2015

Transcript of Consultancy Support for Electricity Transmission … Consultancy Support for Electricity...

Page 1: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

Consultancy Support for Electricity Transmission

and Distribution Revenue Controls (2016-2020)

COMMISSION FOR ENERGY REGULATION (CER)

DSO

Final

June 2015

Page 2: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

i

Consultancy Support for Electricity Transmission and Distribution Revenue

Controls (2016-2020)

Project no: PG021000

Document title: DSO

Document no: Final

Revision: 1

Date: June 2015

Client name: Commission for Energy Regulation (CER)

Client no: Client Reference

Project manager: Gary Flynn

Author: Paul Francis, Keith Paintin

File name: DSO

Sinclair Knight Merz (Europe) Ltd (Jacobs)

7th Floor, Stockbridge House

Trinity Gardens

Newcastle upon Tyne, NE1 2HJ

T +44 191 211 2400

F +44 191 211 2401

www.jacobs.com

COPYRIGHT: The concepts and information contained in this document are the property of Sinclair Knight Merz (Europe) Limited (Jacobs). Use

or copying of this document in whole or in part without the written permission of Jacobs constitutes an infringement of copyright.

Document history and status

Revision Date Description By Review Approved

Draft April 2015 Consolidated Interim Reports G Flynn

P Francis

K Paintin

R Clark R Clark

Draft-Final May 2015 Consolidated Interim Reports – CER comments addressed G Flynn

P Francis

K Paintin

R Clark R Clark

Final June 2015 CER and Company comments addresed G Flynn

P Francis

K Paintin

R Clark R Clark

Page 3: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

ii

Contents

Executive Summary ............................................................................................................................................... 1

1. Introduction .............................................................................................................................................. 20

1.1 This Report ................................................................................................................................................................................... 20

1.2 Data Sources and Assumptions.................................................................................................................................................... 21

2. Review of PR3 Operating Expenditure .................................................................................................. 22

2.1 Overview ....................................................................................................................................................................................... 22

2.2 Controllable Costs......................................................................................................................................................................... 24

2.2.1 Network Operations and Maintenance.......................................................................................................................................... 24

2.2.2 Asset Management ....................................................................................................................................................................... 29

2.2.3 Metering ........................................................................................................................................................................................ 30

2.2.4 Customer Service ......................................................................................................................................................................... 31

2.2.5 Provision of Information ................................................................................................................................................................ 32

2.2.6 Corporate charges ........................................................................................................................................................................ 33

2.2.7 Sustainability and R&D ................................................................................................................................................................. 33

2.2.8 Other ............................................................................................................................................................................................. 34

2.3 Non Controllable Costs ................................................................................................................................................................. 34

2.4 Conclusions and Findings ............................................................................................................................................................. 35

3. Review of PR4 Operating Expenditure .................................................................................................. 36

3.1 General / Overview ....................................................................................................................................................................... 36

3.2 Controllable Costs......................................................................................................................................................................... 38

3.2.1 Overall Manpower ......................................................................................................................................................................... 38

3.2.2 Network Operations and Maintenance.......................................................................................................................................... 39

3.2.3 Asset Management ....................................................................................................................................................................... 41

3.2.4 Metering ........................................................................................................................................................................................ 42

3.2.5 Customer Service ......................................................................................................................................................................... 43

3.2.6 Provision of Information ................................................................................................................................................................ 44

3.2.7 Telecoms ...................................................................................................................................................................................... 45

3.2.8 Sustainability and R&D ................................................................................................................................................................. 45

3.2.9 Corporate charges ........................................................................................................................................................................ 46

3.2.10 Insurance ...................................................................................................................................................................................... 47

3.2.11 Legal ............................................................................................................................................................................................. 47

3.2.12 Pensions ....................................................................................................................................................................................... 48

3.2.13 Environmental ............................................................................................................................................................................... 48

3.2.14 Health and Safety ......................................................................................................................................................................... 49

3.2.15 Non controllable costs................................................................................................................................................................... 49

3.3 Report Findings............................................................................................................................................................................. 50

4. Review of PR3 Capital Expenditure ....................................................................................................... 51

4.1 General ......................................................................................................................................................................................... 51

4.2 Network Related Expenditure ....................................................................................................................................................... 55

4.2.1 New Demand Connections ........................................................................................................................................................... 55

Page 4: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

iii

4.2.2 Generator Connections ................................................................................................................................................................. 61

4.2.3 Load Related Reinforcement ........................................................................................................................................................ 63

4.2.4 Dismantling Costs ......................................................................................................................................................................... 73

4.2.5 Non-Repayable Line Diversion Costs ........................................................................................................................................... 75

4.3 Non Load Related Capex.............................................................................................................................................................. 76

4.3.1 Renewal Programme .................................................................................................................................................................... 78

4.3.2 Response Capex .......................................................................................................................................................................... 90

4.3.3 Continuity Capex........................................................................................................................................................................... 91

4.3.4 System Control Network Capex .................................................................................................................................................... 92

4.4 Non Network Related Expenditure................................................................................................................................................ 92

4.4.1 Accommodation Fixtures and Fittings and Office Equipment ....................................................................................................... 93

4.4.2 Vehicles ........................................................................................................................................................................................ 94

4.4.3 IT Systems .................................................................................................................................................................................... 94

4.4.4 Environment .................................................................................................................................................................................. 94

4.4.5 System Control and Telecoms ...................................................................................................................................................... 94

4.4.6 Smart Metering Expenditure ......................................................................................................................................................... 95

4.5 Summary & Conclusions............................................................................................................................................................... 95

4.5.1 Capex Overview............................................................................................................................................................................ 95

4.5.2 Demand Connections ................................................................................................................................................................... 96

4.5.3 Generator Connections ................................................................................................................................................................. 96

4.5.4 Load Related Reinforcement ........................................................................................................................................................ 97

4.5.5 Retirements (Dismantling) Capex ................................................................................................................................................. 98

4.5.6 Diversions ..................................................................................................................................................................................... 98

4.5.7 Non-Load Related Capex ............................................................................................................................................................. 98

4.5.8 Non-Network Capex.................................................................................................................................................................... 100

5. Review of PR4 Capital Expenditure ..................................................................................................... 101

5.1 Load Related Expenditure .......................................................................................................................................................... 103

5.1.1 PR4 New Demand Connections ................................................................................................................................................. 104

5.1.2 Generator Connections ............................................................................................................................................................... 108

5.1.3 Load Related Reinforcement ...................................................................................................................................................... 110

5.1.4 Dismantling Costs ....................................................................................................................................................................... 123

5.1.5 Non-Repayable Line Diversion Costs ......................................................................................................................................... 124

5.2 Non Load Related Capex............................................................................................................................................................ 125

5.2.1 Non Load Related Capex – Overview ........................................................................................................................................ 125

5.2.2 Renewal Programmes ................................................................................................................................................................ 129

5.2.3 Continuity Capex......................................................................................................................................................................... 158

5.2.4 Response Capex ........................................................................................................................................................................ 159

5.2.5 System Control Network Capex .................................................................................................................................................. 160

5.2.6 Integrated Vision for an Active Distribution Network (IVADN) .................................................................................................... 161

5.2.7 North Atlantic Green Zone (NAGZ) ............................................................................................................................................. 162

5.2.8 Non Load Related Expenditure – Summary of Allowances ........................................................................................................ 163

Page 5: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

iv

5.3 Non Network Related Expenditure.............................................................................................................................................. 164

5.3.1 Accommodation Fixtures and Fittings and Office equipment...................................................................................................... 165

5.3.2 Vehicles ...................................................................................................................................................................................... 166

5.3.3 Tools ........................................................................................................................................................................................... 167

5.3.4 IT associated with Asset Management, Control/Operations, IT Infrastructure and Enterprise Applications ............................... 167

5.3.5 Environment ................................................................................................................................................................................ 169

5.3.6 System Control and Telecoms .................................................................................................................................................... 170

5.3.7 Non-Network Capex – Recommendations and Conclusions on Proposed Allowances ............................................................. 172

5.3.8 Smart Metering Expenditure ....................................................................................................................................................... 173

5.4 Summary & Conclusions............................................................................................................................................................. 173

5.4.1 Capex Overview.......................................................................................................................................................................... 173

5.4.2 Demand Connections ................................................................................................................................................................. 175

5.4.3 Generator Connections ............................................................................................................................................................... 176

5.4.4 Load Related Reinforcement ...................................................................................................................................................... 176

5.4.5 Retirements (Dismantling) Capex ............................................................................................................................................... 177

5.4.6 Diversions ................................................................................................................................................................................... 177

5.4.7 Non-Load Related Capex ........................................................................................................................................................... 177

5.4.8 Non-Network Capex.................................................................................................................................................................... 180

6. Conclusions ........................................................................................................................................... 182

Appendix A. Benchmarking .............................................................................................................................. 185

Appendix B. Incentives ..................................................................................................................................... 206

Appendix C. Smart Meter Procurement ........................................................................................................... 241

Appendix D. Asset Lives & Depreciation ........................................................................................................ 258

Page 6: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 1

Executive Summary

ESB Networks carry out the function of Distribution System Operator (DSO) in Ireland. This report sets out the

DSO’s capital expenditure (capex) and operating expenditure (opex) over the PR3 (2011 to 2015) and PR4

(2016 to 2020) periods. The review considers the costs, systems processes, and initiatives of the DSO over

PR3 and identifies key issues to be considered in PR4. The report then reviews the DSOs proposals for

expenditure in PR4 and makes recommendations on the level of expenditure, outputs and incentives to be

allowed by CER.

Data Submissions over the PR4 process

ESBN provided data for the PR4 review according to the following timetable:

Historic Questionnaire Submission: 31 October 2014

Forecast Questionnaire Submission: 21 November 2014

ESBN was provided with the questionnaires in July 2014.

The data requested is in essentially the identical format that was used in PR3 and preceding Price Reviews.

ESBN was advised early in 2014 that the data requested would be the same and in the same format as

previous Price Reviews.

During the review process there has been a number of changes made to the data provided by ESBN through to

May 2015. Although there are invariably corrections and modifications through a review process, in some areas

data which would have been expected to be available was not available causing some delays in the process

and the completion of the reports. ESBN are reviewing internal processes to ensure future reviews and data

requests are more efficiently managed.

PR3 Opex

The CER decision paper (CER/10/198) set out the DSO’s original allowed opex for the PR3 price control period.

This allowance equated to €896.9m in controllable opex, €190.0m in non-controllable opex and €1086.9m in

total1. The price control mechanism allows for a number of adjustments to be applied to the initial opex

allowances set out by the CER. The opex allowances of some of the opex sub-categories were adjusted during

the PR3 period. This resulted in an adjusted PR3 allowance of €1138.8m (excluding commercial costs and

depreciation), comprising of an allowance of €945.5m on controllable opex and €193.3m on non-controllable

opex.

Prior to any adjustments for high level efficiencies; the DSO is broadly operating at the adjusted PR3

allowances with an expected expenditure on controllable and non-controllable items of €1140.4m against an

adjusted allowance of €1138.8m. The most significant overspend is on Network Operations and Maintenance

(€24.1m), with the main underspend being on the Provision of Information (€21.5m). Owing to the pass through

nature of non-controllable opex, PR3 allowance is expected to equal actual expenditure. Taking into account

the CER’s efficiency driver (€-31.3 million) which the DSO acknowledge was not achieved, the DSO Total opex

is overspent by €32.9m (or 3% of total allowed expenditure). A comparison of the adjusted PR3 allowance and

the DSO’s expected outturn is shown below in Table ES.1.

Table ES.1 : Final Allowances v Expected Outturn (PR3)

DSO Operating Costs

(€m 2009 Prices)

PR3 Total

Allowed Forecast Variance %

Network O&M Total 469.3 493.4 24.1 5%

1 2009 prices and excluding Commercial costs and depreciation.

Page 7: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 2

DSO Operating Costs

(€m 2009 Prices)

PR3 Total

Allowed Forecast Variance %

Asset Management 60.2 64.7 4.5 8%

Metering 127.2 130.8 3.6 3%

Customer Service 81.2 74.0 -7.2 -9%

Provision of Information 74.1 52.6 -21.5 -29%

Corporate Costs 64.3 54.0 -10.3 -16%

Telecoms 0.0 0.0 0.0 -

Sustainability and R&D 18.2 8.0 -10.2 -56%

Other 51.0 69.7 18.7 37%

Controllable Total 945.5 947.1 1.6 0%

Network Rates 183.4 183.4 0.0 0%

Car Levy 9.9 9.9 0.0 0%

Non Controllable 193.3 193.3 0.0 0%

Total (Excl Commercial and

Depn)

1138.8 1140.4 1.6 0%

Less High Level Efficiencies -31.3 0.0 31.3 -

Total (Excl. Commercial and

Depreciation)

1107.5 1140.4 32.9 3%

The overspend on Network Operations and Maintenance is predominantly driven by planned maintenance

which is expected to incur a 20% overspend during PR3 (€39.1m) due to significant expenditure on Tree cutting

over and above the allowance. This is partially negated by an underspend of €20.5m on fault maintenance.

There was an underspend of €21.5m on Provision of Information expenditure a significant element of which is

charged from the Business Support Centre. A change of pricing mechanism for IT Services was agreed in 2011

moving to a cost recovery mechanism rather than market price cost. This contributed to lower costs for the

DSO. The most significant element to this reduction is the efficiencies associated with Market Opening

activities. A number of strategies were employed to provide cost reductions, such as headcount reductions,

offshoring work where practicable, development of longer term contracts to drive cost reductions,

implementation of new technologies such as cloud hosting.

Overall expenditure on other opex items is forecast to exceed the PR3 allowance by €18.7m (37%). There are

several factors which impact on the variance in ‘Other’ expenditure:

The DSO have indicated in a number of discussions that costs for Network Assets and Employers/ Public

Liability Insurance is passed from Corporate centre and relates to increases in the Network Asset base.

This does not sufficiently account for the increases and subsequent decreases in the charges during the

PR3 period.

The legal costs would be expected to rise given the increased revenue protection work that the DSO is

experiencing as customers find themselves under economic pressure.

The increase in Health and Safety costs is due to the recent severe safety incidents that have occurred

within the DSO activities. There has been a full review of the Health and Safety processes and procedures

necessitating a significant increase in the level of expenditure (which is over and above the PR3 allowance)

in order to put the requisite changes in place to ensure that the processes and procedures and staff

training / education are in place are fit for purpose from a Health and Safety perspective. This increase is

expected to continue into PR4.

Page 8: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 3

The DSO has not provided a view of their Asset condition at a company-wide level. This is a concern and

should be addressed during PR4. The high level view will allow the DSO to understand the long term effect of

maintenance levels on their asset condition and allow it to take a more informed long term approach to

maintenance and Capex replacement programmes.

The DSO has achieved the cost targets set out in the CER decision paper however we are of the opinion that it

has not achieved the additional cost efficiencies required by the CER. It is our view that the company has

underspent by €10.2m on Sustainability and R&D activities and this may be treated as a windfall gain.

PR4 Opex

The DSO has proposed a total opex allowance for PR4 of €1506.0m, excluding Commercial Costs and

Depreciation. The total proposed opex allowance is broken down as follows:

Proposed controllable opex of €1219.9 (an increase of €245.0m - 25% - from PR3 outturn)

Proposed non-controllable opex of €286.1m (an increase of €87.2m - 44% - from PR3 outturn)

The DSO has proposed a total opex allowance for PR4 of €1506.0m, which represents an increase of €332.3m

(28%) from PR3 forecast outturn.

The DSO has provided a significant amount of narrative on the proposed PR4 forecast operating costs. We

have reviewed the submissions provided and in some cases requested additional information, to clarify

justifications or provide additional supporting information. As a result of our reviews, we have recommended a

reduction of €106.9m to the level of operating expenditure proposed by the DSO. All of our recommended

€106.9m reduction to the DSO’s opex allowance is identified in controllable costs only.

A table summarising the DSO proposed opex for PR4 and our recommended allowances for the same period is

provided below in Table ES.2.

Table ES.2 : DSO Proposed Opex v Jacobs Recommended Allowances (PR4)

DSO Proposed Operating Costs Jacobs Proposed Operating Costs

Proposed Operating Costs

(€m 2014 Prices) PR3 PR4

Variance

PR3 – PR4

Variance

%

PR4

Changes

PR4

Allowed

Variance

to PR3

Network O&M Allowance 507.8 581.1 73.3 14% -43.4 537.7 6%

Asset Management

Allowance 66.6 72.3 5.7 9% 0.0 72.3 9%

Metering Allowance 134.6 180.1 45.5 34% -21.3 158.8 18%

Customer Service Allowance 76.2 90.2 14.1 18% -3.2 87.0 14%

Provision of Information

Allowance 54.2 63.3 9.1 17% -2.9 60.4 11%

Corporate Costs Allowance 55.6 51.4 -4.2 -7% -3.0 48.4 -13%

Telecoms Allowance 0.0 67.7 67.7 - -48.4 19.3 -

Sustainability & R&D

Allowance 8.2 15.6 7.4 91% -4.5 11.1 36%

Other Allowance 71.7 98.2 26.5 37% -12.2 86.0 20%

Controllable Allowance 974.8 1,219.9 245.0 25% -143.9 1076.0 10%

Page 9: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 4

DSO Proposed Operating Costs Jacobs Proposed Operating Costs

Proposed Operating Costs

(€m 2014 Prices) PR3 PR4

Variance

PR3 – PR4

Variance

%

PR4

Changes

PR4

Allowed

Variance

to PR3

Network Rates 188.7 275.1 86.4 46% 0.0 275.1 46%

CER Levy 10.2 11.0 0.8 8% 0.0 11.0 8%

Non Controllable

Allowance 198.9 286.1 87.2 44% 0.0 286.1 44%

Total Allowance (excl.

Commercial and

Depreciation)

1,173.7 1,506.0 332.3 28% -143.9 1362.1 16%

The DSO has proposed a total allowance of €581.1m over the PR4 period for Network Operations and

Maintenance opex. This is €73.3m in excess of the spend in PR3. This increase is predominantly driven by

increased Planned Maintenance expenditure on HV stations. We have proposed reductions of €41.5m in this

activity and a reduction of €1.9m in system control, reducing the total allowance to €537.7m.

The DSO are requesting an increase in metering costs of €45.5m (34%) over the costs forecast for PR3, raising

the PR4 allowance to €180.1m. The main driver for the increase in Metering expenditure (compared to PR3) is

due to Customer Meter Operation (an increase of €13.5m) and Keypad/Token meters (an increase of €26.4m).

The Customer Meter Operation includes Revenue Protection activities. There has been increased activity in

this area in PR3 (see Table 2.16) and we consider that this is likely to continue in PR4. We have accepted the

DSO’s proposed opex allowance for Customer Meter Operation on this basis.

The DSO has proposed an expenditure of €55.3m on keypad/token meters during PR3. Our PR4 proposed

allowance has been based on a unit cost of €400 per keypad/token meter installation and results in a total

expenditure of €34.0m, a reduction of €21.3m.

The DSO has proposed a total PR4 allowance of €47.0m (an increase of €6.2m or 15% on PR3) for Market

Opening activities. The company has identified the cost increases going forward for Retail Market Design

Services in PR4. This increase over PR3 expenditure has been identified to relate to the release of scheme

updates that were not required during PR3 , we have proposed reducing the PR4 allowed expenditure by a total

of €2.9m over the PR4 period.

It is unclear, what level of cost was incurred by the DSO for Telecoms activities in the PR3 period.

Supplementary questions have been issued to the DSO and details have been provided, however this has not

sufficiently clarified the information. On this basis it is not possible to determine how these costs have changed

from PR3 to PR4. The DSO has indicated that there will be external revenue generated from this business

activity, which will be passed on to the customer.It is our view that this income should be netted off the

operating costs and the allowance should be the net costs of operating the service. We have therefore reduced

the proposed expenditure allowance on Telecoms by the expected level of revenue from Telecoms activities

(€48.4m).

The DSO have proposed an allowance of €18.6m for environmental activities over the PR4 period. This

represents a €12.1m (183%) increase over expenditure in PR3. The DSO has not identified any new legislation

that is not currently in force and therefore there should be no additional compliance requirements in PR4. As

the company are presumed to be meeting the current environmental compliance levels, we have reduced the

PR4 allowance by €11.0m to match the levels of expenditure expected at the end of PR3.

The DSO have proposed a PR4 allowance on Health and Safety of €38.8m which equates to an increase of

€18.9m (95%) on PR3 expenditure. It should be noted that the circumstances currently facing the DSO are not

the same as those at the start of PR3 as a result of recent severe safety incidents that have occurred within the

Company Operations. The company has carried out a full review of its Health and Safety processes and

Page 10: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 5

procedures. The resultant corrective actions have resulted in the above expenditure profile. We are supportive

of these actions and the accelerated profile of expenditure. We do believe however that the approach to the

improvement in health and safety should be able to deliver the benefits more speedily and have shown a

reduction in the increase in the later years of PR4. We recommend a reduction of €5.0m giving an allowance of

€33.8m which is 70% higher than in PR3.

We have suggested that the DSO develops an appropriate method to understand the asset heath of its asset

portfolio, in order to understand the overall level of maintenance required and to inform future Asset

Maintenance and Replacement Programmes.

PR3 Capex

Capex Overview:

During the PR3 period, there are a number of significant factors that need to be considered when

assessing DSO outturn capex v CER allowed costs.

In consultation with the CER, ESBN Networks reduced the PR3 Gross Capex delivery programme in two

stages from the original CER allowed value of €4,200m to €2,400m (including Transmission Projects).

Given the reduction in peak demand during the PR3 period, together with pressure to reduce potential

increases on DuoS charges, the DSO considered it appropriate to critically review the network

requirements and the related project portfolio, allowing for deferment of reinforcement projects where the

resultant risks were considered acceptable to do so.

In headline terms, during PR3 the DSO is forecasting to invest net €1,075.3m on network and non-network

assets, which is €91.3m (9.3%) higher than its 2012 revised capex total of €984m (excluding Smart

Metering and R&D costs associated with studying impact of Electric Vehicles). Its latest forecast is €637m

(37%) lower than the initial CER allowed capital expenditure for PR3 of €1,712m.

Due to the unique circumstances that were faced by the DSO in the period leading up and resulting in its

revised capex plans in 2012, it is considered appropriate to use the rebased 2012 capex forecast for

comparison throughout this report wherever possible, although, for completeness, reference is also made

to CER allowed values.

The DSO has been asked for more detailed breakdown of costs associated with the 2012 revised capex

plan broken down into an annual expenditure profile for each of the work programmes for which CER had

made allowances for the PR3 period. However, it is our understanding that this information is not available

due to the progressive and incremental nature of Capex assessment and reprioritisation over the 2012-

2015 period.

Consequently we have not been able to carry out a comparable analysis of DSO forecast v rebased 2012

capex at a work programme level and such analysis has therefore been carried out relative to CER allowed

capex for each defined category of capex.

Table ES.3 summarises the PR3 capex allowances and the DSO forecast.

Table ES.3 : PR3 Capex Summary

Capex Investment Category

CER Allowed

Capex

(GROSS)

Revised

DSO

Proposal

(2012)

DSO

Forecast

(GROSS) -

2014

Variance – DSO

Forecast to CER

Allowed Capex

Variance – DSO

Forecast (2014) to DSO

Revised Proposal (2012)

€m % €m %

New Business 452.7 252.0 235.5 -217.2 -48.0% -16.5 -6.6%

Generation Connections 162.5 70.0 86.7 -75.8 -46.6% 17.7 25.7%

Line Diversions 51.8 52.0 47.1 -4.7 -9.0% -4.9 -9.4%

Distribution Reinforcement 632.6 277.0 316.9 -315.7 -49.9% 39.9 14.4%

Asset Replacement 622.1 433.0 462.4 -159.7 -25.7% 29.4 6.8%

Page 11: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 6

Capex Investment Category

CER Allowed

Capex

(GROSS)

Revised

DSO

Proposal

(2012)

DSO

Forecast

(GROSS) -

2014

Variance – DSO

Forecast to CER

Allowed Capex

Variance – DSO

Forecast (2014) to DSO

Revised Proposal (2012)

€m % €m %

Non Network 179.1 96.0 135.6 -43.5 -24.3% 39.6 41.2%

Total – DSO Excluding Smart

Metering 2,100.8 1,179.0 1284.3 -816.5 -38.9% 105.3 8.9%

Note – “Asset Replacement” Costs include costs associated with the retirement of assets (costs for period from 2011-2013 obtained from

Opex Table 5.1 and costs for period 2014/15 are from Capex Table 6.3, both in the DSO’s PR4 submissions to CER)

Demand Connections (new business):

For Demand Connections, the total DSO Actual Capex (Gross) over the PR3 period is forecast to outturn at

€235.5m, this is €217.2m (48%) less than the CER Allowed capex. It is also €16.5m (6.6%) less than the

DSO Revised Capex Proposal of 2012.

The total DSO Actual Capex (Net) over the PR3 period is forecast to outturn at €123.2m, this is €103.1m

(45.6%) less than the CER Allowed capex.

Customer contributions of €112.3m for a gross expenditure on demand connections of €235.5m (gross)

resulted in a contribution ratio of 48% in PR3 compared with the agreed rate of 50%. The DSO may need

to revise the Basis for Customer Connection Charges for future recovery of the agreed rate of 50% of total

connection charges, although we would expect any revision to be presented to the CER for review and

approval.

The main driver for this significantly lower capex, compared to the original CER allowances, is the reduced

number of customer connections that have been requested to be provided by the DSO over the PR3

period. Based on the DSO latest forecast for 2014 and 2015, it is anticipated by the DSO that the 5-year

total will outturn at 70,417. This is more than 86,000 (i.e. 55%) lower than the PR3 forecast connection

volumes for the full 5-year period.

CER should review the outturn costs for 2014 before finalising its allowances for PR3 period.

It is observed that the DSO total meter costs for PR3 period are 17.9% higher than the CER allowed costs.

This is despite a forecast reduction in connection volumes of 55% over the PR3 period. The DSO has

provided a detailed explanation to explain this apparent adverse variance. The closing of cost accounts

relating to dormant connection projects, to prevent misallocation of costs, has resulted in final connection

cost and the metering cost both being allocated to the metering cost code.

The analysis provided by the DSO supports the higher metering capex costs incurred during PR3. It is

important however that the assessment of PR4 allowed revenues for connections and metering takes due

account of the fact that a proportion of G1-G3 connections costs have been allocated to metering capex

during PR3.

Generator Connections:

The DSO is forecasting to incur gross generation connections costs of €86.7m during PR3, representing an

underspend of €75.8m compared with the CER allowed gross capex of €162.5m. This DSO forecast is

€17.7m (25.7%) higher than the DSO Revised Capex Proposal of 2012.

Customer contributions for generation connections are forecast to be €96.7m, equivalent to a contribution

ratio (or recovery rate) of 112% compared with the allowed recovery rate of 100%.

This over-recovery of connection costs in PR3 will undoubtedly result in DSO net cash outflows during the

early years of PR4 period and this will need further consideration when reviewing the proposed DSO

forecast capex for PR4.

Load Related Reinforcement:

Page 12: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 7

For load related reinforcement, the DSO forecasts a total capex of €316.9m by end of PR3 – this is

€315.7m lower than the original CER allowed load-related reinforcement capex of €632.6m – representing

a variance of 50%.

This DSO forecast is approximately €39.9m higher than the revised proposal of ESBN (€277m) submitted

to CER in 2012.

The main drivers on load-related reinforcement expenditure are the growth in peak demand and energy

delivered (GWh). It is noticeable that from a total of circa 24,000 units in 2008, the DSO has experienced a

reduction to 23,000 GWh units in 2010, followed by a further reduction in actual units to circa 22,100 GWh

by 2013.

Similarly, the system peak demand has not increased in line with the DSO forecast for PR3. The peak in

2007/08 was 4,914 MW and the peak in 2013/14 has reduced to 4,523 MW.

As part of its response to the Business Plan Questionnaire, the DSO was requested to provide a

breakdown of planned v actual cost details of the major projects (38kV and above) that have been

progressed during PR3. This would have allowed us to carry out a more detailed analysis of a sample

number of projects completed during PR3. The purpose of carrying out a detailed analysis of a

representative sample of individual projects is to assess the reasonableness of costs incurred compared to

planned/allowed costs, the reasonableness of the DSO project delivery process and hence to determine

the efficiency of the DSO project delivery and resulting capex.

We have experienced significant delay in receiving the requested information for a sample of 11 major

projects expected to be completed during PR3. Both the delays in providing the required information and

the fact that information was only provided for a small sample of projects rather than all major projects is

disappointing. We would have expected the project information requested to be generally available within

the DSO and find the prolonged delay in providing this information to be a concern. – it is standard

information that we would expect the project managers to be using on a routine basis to manage and

control project delivery and associated costs.

Given the time the DSO has had to provide such information, we consider that their inability to provide such

information to the CER in a timely manner to be an area of weakness that requires improvement during

PR4.

For 10 of the 11 projects, we have observed that the DSO is forecasting total costs (PR2 and PR3) that are

lower than the Capital Approval Amount – with variances in the range of €0.1m to €0.8m. For the remaining

major project (N-D-1027), we observe that the DSO is forecasting a total cost (PR2 and PR3) which is

higher than the Capital Approval amount by €1.0m.However as the lack of cost granularity has limited our

assessment on a constant 2009 price base, conclusions made from any comparison of projects costs need

to recognise this cost base inconsistency. We have not investigated the reasons behind any variance in

total costs v CA costs nor has the DSO provided any details or explanation of the variance.

It was also our intention to request a sample number of post investment appraisal documents for a

selection of completed major projects. The DSO has advised us that they do not presently carry out a

formal post investment review of individual projects and hence no documentation was available for us to

review.

We consider this gap to be an area for improvement within the DSO project delivery process – this has

been recognised by the DSO, who has stated their plans to introduce this improvement over the coming

months.

However, the DSO has provided a supporting narrative document (DH02 – PR3 Load Driven Programme)

that provides detailed commentary of investment during PR3 – this has allowed us to make a quantitative

assessment of non-financial project outputs.

Our analysis suggests that the reduction in DSO forecast capex for 110kV reinforcement projects is higher

than the equivalent volume reductions in transformer capacity or circuit km commissioned. It is expected

that this disparity will be partly due to a number of projects being completed in PR3 that commenced in

PR2 period; with the costs incurred on these projects during PR2 being added to the DSO RAB during

PR2.

Page 13: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 8

Further analysis of 38kV reinforcement projects suggests that the reduction in DSO forecast capex is

higher than the equivalent volume reductions in transformer capacity or circuit km commissioned. Similar to

110kV projects, it is expected that this disparity will be partly due to a number of projects being completed

in PR3 that commenced in PR2 period; the costs incurred on these projects during PR2 being added to the

DSO RAB during PR2.

Using the Planning policy (which permits 180% loading of single transformer nameplate rating under N-1

conditions for dual transformer stations), the DSO has forecast that a total of 48 of their population of 38kV

stations will be outside Planning Standards by the end of PR3 (rather than 32 loaded above nameplate

rating).

These stations will require further attention during PR4 and will be a consideration within the review of DSO

forecast capex.

The DSO has continued its programme to convert its 10kV network to 20kV operation, albeit at lower

volumes. The PR3 forecast volume for this activity was 15,000km. The DSO has reported that by the end

of PR3 a total of 10,000km will be converted to 20kV. The reduction in capex associated with the 20kV

conversion programme is consistent with the reduced circuit lengths converted during PR3 and it appears

to be efficiently incurred.

The DSO is forecasting that capex associated with other MV/LV System improvements during PR3 will

outturn at €33.6m. This is approximately 51% less than the CER allowed capex of €69.1m. The scale of

reduction in DSO capex during PR3 for MV/LV system improvements is consistent with the overall

reduction in PR3 load related reinforcement expenditure (being 50% of CER allowed capex).

Retirements (Dismantling) Capex:

The DSO has continued its practice of charging dismantling costs to its Income Statement for years 2011

to 2013 and proposes a change in Accounting Practice for the remaining two years of PR3 such that the

costs are allocated to capital. Our analysis of DSO dismantling costs has been carried out on a total cost

basis. Total dismantling cost over the PR3 period is forecast at €47.1m, 17.9% less than the CER allowed

capex of €57.4m.

The DSO has introduced revised project costing procedures (Integrated Work Management Module) within

their SAP application from 2009 onwards. This has allowed the DSO to allocate dismantling costs more

directly to the work activity that has driven the need for the dismantling to be carried out.

We would generally agree with the DSO that the proportion of dismantling costs is likely to vary across

each of the work activities. The change in the DSO cost allocation procedures has provided improved

visibility of the drivers on the dismantling activity and associated costs

We would expect the DSO dismantling costs over the PR3 period to be charged to capex for the full five

years, this being consistent with CER allowances. This will result in a transfer of €28.4m of costs from opex

(2009 prices) to capex covering the years 2011 to 2013.

Diversions:

Line diversion costs have historically been proportional to capital expenditure in the category of “gross new

demand connections”. For the PR3 period, this allowance was set at a value equivalent to 11.4% of the

PR3 forecast capex for new connections. The actual diversion costs over 2011 to 2013 are in the range of

19.2% to 21% of the gross connections capex over the same period. The DSO has provided an

explanation for this % increase in percentage costs experienced during PR3 and we consider this to be

reasonable.

In its response (DSO report DR01) to our Interim Report, the DSO provided aThe DSO revised forecast of

line diversions capex for the remaining two years of the PR3 period suggesting line diversionsuggests

costs in the range of 20% for the remainder of PR3- these values are broadly consistent with the first three

years of PR3 and are considered to be reasonable.

Non-Load Related Capex

For non-load related capex, the DSO has forecast a total capex of €415.3m by end of PR3 – this is

€149.4m lower than the CER allowed load-related reinforcement capex of €564.7m – representing a

Page 14: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 9

variance of -26%. This DSO forecast is €29.4m higher than the revised proposal of ESBN (€387m )

submitted to CER in 2012

It should be noted that this forecast includes for a one-off capex of €26.8m in 2014 associated with Storm

Darwin and it also includes a significant increase in capex for year 2015 (relative to 2012 and 2013).

Certain asset replacement projects were deferred in whole or were scaled down based on the DSO’s

prioritisation process.

For PR3, the allowed capex for HV Overhead Line Replacements was €16.3m and the DSO latest forecast

is €15.1m, representing 93% of allowed capex.

The DSO states that the 38kV OCR programme will be substantially completed, although this is dependent

on the delivery of 1,000km during Q4, 2014 and end of 2015. There is a significant risk that this volume of

work associated with the 38kV OCR programme is not delivered in 2015 – it represents a significant

increase in volumes previously delivered and is heavily dependent on contractor resources being in place

and fully operational. Whilst the DSO also acknowledges the 2015 volumes represent a significant increase

in the rate of delivery, it considers its 2015 forecast to be reasonable, citing contractor resource availability

to deliver the majority of the work programmes.

The reduction in capex by deferring 110kV line works has been largely offset by the additional capex

associated with 38kV copper overhead line replacements. Generally, the reduced costs in PR3 are broadly

consistent with the reduced PR3 volumes delivered

The DSO has deferred significant capex during PR3 associated with 110kV and 38kV cable replacement

projects. The reductions in work volumes stated by the DSO are broadly consistent with the reduced

capex.

The DSO has deferred a number of the higher cost HV station replacement projects / programmes

completely, whilst at the same time focussing on the substantial completion of various safety driven and

security driven programmes of work, typically of a much lower cost. These two factors contribute to an

overall underspend of PR3 capex of 36% relating to the HV Station renewal programme.

For the MV OCR programme, the DSO is forecasting the completion of 33,000 km by end of PR3 (i.e. 73%

of the original target (45,000km) upon which allowances were made, although it forecasts a spend of 86%

of the PR3 allowance. This increase in unit costs is being driven by higher labour costs being forecast in

2014 and 2015 - associated with more stringent pole testing procedures that the DSO has introduced to

addressed potential risks associated with accelerated pole rot.

The forecast includes a target of 14,500km being delivered in 2015 alone, predominantly by using contract

resources, this being subject to completion of the tendering and contract procedures. Achieving the 2015

target volumes is therefore considered to be a significant challenge to the DSO.

The DSO is forecasting that approximately 10km of MV cable to be replaced by 2015 – representing an

under-delivery of about 33%, broadly in line with the forecast underspend.

In relation to the MV Station Renewal Programme, the DSO is forecasting an overspend in this category of

27%. Any expected reductions in capex due to the reduction in volumes for many of the categories have

been largely offset by increased costs associated with the higher volume of work associated with the

Magnefix Cast Resin Switchgear programme.

The plan for PR3 period was to refurbish 35,000 spans of LV urban networks. The DSO is forecasting that

less than 50% (~17,000km) of the programme will be completed during PR3 period. The percentage

reduction in capex for the Urban LV Renewal programme is broadly consistent with the equivalent

reduction in work volumes.

For the Rural LV Network Renewal Programme, the reduction in the volume of works compared to PR3

programme (approximately 20%) is higher than the reduction in the Capex (6%) suggesting increase in unit

costs. Of the 20,000+ Groups refurbished during PR3, the DSO has selected more than 1,800 Groups that

were prioritised and selected for refurbishment in conjunction with other works to improve network

performance and power quality, with significantly higher unit costs than the basic fabric only refurbishment

works.

Page 15: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 10

For the LV Cable Renewal Programme - the DSO current forecast for this programme is €6.1m against the

CER PR3 allowed capex of €16.8m. During PR3, the LV cable programmes have been subject to a

significant reduction in order to reduce impact on DUoS charges.

For the Renewal Programme associated with cutouts, the PR3 programme consisted of the planned

replacement of 40,000 pre 1976 indoor cut-outs. This is a continuation of works from PR2 cut-out

replacement programme. The DSO is forecasting to replace up to 30,000 cut-outs by the end of 2015.

(75% of the original target)

For Response Capex, CER PR3 allowed capex of €98.7m, although the DSO revisedforecast for this

programme is €3.055.1m (representing an underspend of 44%). The area of largest underspend relates to

voltage complaints where the DSO is forecasting a -€16.4m variance to CER allowances. The reduced

investment in this category over PR3 period is likely due to a number of factors, such as reduced demand,

impact of MV and LV network renewal, 20kV conversion programmes and replacement of small capacity

transformers in rural areas. A total of 2,748 voltage complaints were resolved during PR3 period up to the

end of 2014. This is noticeably less than the 9,570 voltage complaints resolved during PR2.

In its response to our PR4 capex IR, the DSO explained the need for urgent works that are scheduled for

2015 to address risks associated with the theft of 50mm2 Copper conductor from 4 x 38kV overhead line

circuits. The works involved replacement of the copper conductor with aluminium conductor (of equivalent

rating) and the estimated capex for this new work programme is €2.0m in 2015.

The DSO is forecasting capex relating to the Continuity programme of €13.7m, which is approximately 39%

less than the CER allowed costs of €22.3m. This programme primarily consists of the installation of

automatic and remote control switches and other measures to improve the performance of the network,

The DSO determined that the continuity improvement projects intended for delivery in PR3 would be

largely deferred and priority given to core capex activities that addressed higher priority safety issues.

Non-Network Capex:

For non-network capex, the DSO has forecast a total non-network capex of €135.6m by end of PR3 – this

is €43.5m lower than the CER allowed Non-Network capex of €179.1m, representing a variance of 24.3%.

In general the DSO has deferred expenditures in all areas, and has reprioritised expenditure in areas

necessary to maintain customer service, operations and legislative requirements.

In most cases this can be viewed as efficiency and indeed represents a lower than allowed expenditure

while maintaining network performance. It is likely that there will some elements of catching up with the

DSO capex submission for PR4.

Total PR3 smart meter capex of €12.2m is significantly below the original €500m provisioned by CER

(which included a significant proportion of the proposed full roll-out costs) and also substantially less than

the €50m that the DSO had forecast in 2012 as part of the overall capex re-profiling exercise carried out in

consultation with CER. PR3 capex relates to the design and procurement activity carried out by the DSO in

preparation for approval of the Smart Metering programme. These activities would generally fall into the

classification of enabling works associated with the roll-out of the Smart Metering capex programme if the

programme is approved.

PR4 Capex

Capex Overview:

In headline terms, the DSO is forecasting a total gross expenditure of €1.72bn. This is €433m (25%) lower

than PR3 allowed capex of €2.15bn and €391m higher than PR3 actual/forecast capex of €1.33bn.

Net of customer contributions, the DSO is forecasting total PR4 capex of €1.48bn. This is €273m lower

than PR3 allowed capex and €351m higher than PR3 actual/forecast capex of €1.13bn.

The DSO PR4 forecast can be described in headline terms by the following characteristics:

- Demand Connections – DSO is forecasting a total number of connections in PR4 of 108,000 – this

represents an increase of 53% compared to the total of 70,417 during PR3, but is still only 33% of the

total number of connections made during PR2;

Page 16: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 11

- The DSO is forecasting 0% cumulative growth in peak demand during PR4 – reinforcement

expenditure during PR4 is focused on addressing parts of the system which do not presently comply

with the Planning Standards;

- Capex (gross) associated with generator connections is forecast to increase by 23% from €88.9m in

PR3 to €109.5m to connect a total of 1,250 MW of renewable generation over PR4 period (compared

to 1,200 MW expected by the end of PR3);

- Capex associated with non-load related projects and programmes is the category where the DSO is

forecasting the largest increase in capex in PR4 compared to PR3 – with a variance of €245.6m

(around 58%). The renewal programmes for which the DSO has forecast the largest increases in

capex in PR4 relate to HV Station works and HV and MV overhead line works. The DSO’s plans are

focused on the replacement of aging and defective assets.

- In addition, the DSO has included €87.6m of PR4 capex relating to the North Atlantic Green Zone

(NAGZ) smart grid initiative;

- The forecast increase in PR4 non-network capex (of 24%) is driven by increased expenditure on

vehicles, Distribution Asset Management (including IT infrastructure), Telecoms and System Control;

- In relation to the Smart Metering project, the DSO submission for PR4 includes further development

and project costs necessary to take the project to the next major milestone in 2017. It does not include

capex associated with a country-wide roll out programme as the final investment decision has not yet

been taken.

We have carried out an assessment of the DSO’s proposed capex plan and we have identified a number of

recommended adjustments to the allowed capex for PR4 – these are explained in more detail within the

following sections of the report.

Following our assessment, we recommend PR4 net capex allowance of €1336.72m – representing a

reduction of €144.38m. The PR4 capex proposed by DSO, together with our recommended allowances

are itemised below in Table ES.4.

Table ES.4 : DSO PR4 Capex Summary (€m – 2014 Prices)

SUMMARY OF ALLOWANCES PR3

Allowed

PR3

Actual

PR4

Requested

(Table 6.3)

Revised PR4

Requested

(Table 6.3)

PR4

Recommended

Variance

(Recommended

to Revised

Request)

(G1) New housing Schemes 74.6 16.7 46.5 44.2 45.1 0.9

(G2) Non-scheme Houses 164.4 89.0 106.1 107.7 102.6 -5.1

(G3) Commercial/Industrial Supplies 212.5 120.8 128.5 129.8 125.3 -4.5

Whole Current Metering 12.5 14.7 24.1 19.5 17.8 -1.8

New Business 464.0 241.2 305.2 301.2 290.8 -10.4

Transmission Connection Costs 26.3 0.0 15.2 15.2 15.2 0.0

110kV 236.1 144.4 150.4 150.4 150.4 0.0

38kV 215.2 86.5 85.9 85.9 85.9 0.0

MVLV System Improvements 70.8 34.5 40.9 40.9 36.3 -4.6

IFTs associated with 20kV

Conversion

16.6 22.9

0.0 11.1 11.1 0.0

20kV Conversion 83.0 36.5 25.4 14.3 13.9 -0.4

Reinforcements 648.1 324.7 317.8 317.8 312.8 -5.0

Generation Connections 166.5 88.9 109.5 109.5 109.5 0.0

Dismantling 58.8 48.3 70.2 64.4 55.1 -9.3

Non-Repayable Line Diversions 53.1 48.3 92.1 60.2 50.6 -9.6

Page 17: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 12

SUMMARY OF ALLOWANCES PR3

Allowed

PR3

Actual

PR4

Requested

(Table 6.3)

Revised PR4

Requested

(Table 6.3)

PR4

Recommended

Variance

(Recommended

to Revised

Request)

Total Load Related CAPEX 1390.4 751.3 894.8 853.1 818.7 -34.4

Renew Prog - 110kV & 38kV Lines 16.7 15.5 46.5 38.4 27.5 -10.9

Renew Prog - 110 & 38kV Cables 21.0 6.2 24.5 28.6 25.8 -2.2

Renew Prog - HV Substation 120.4 77.1 126.4 126.5 116.9 -9.6

Renew Prog - MV Overhead Lines 70.7 61.0 131.9 82.2 78.2 -4.1

Renew Prog - MV Cables 2.6 2.0 0.0 0.0 0.0 0.0

Renew Prog - MV Substations 24.7 31.2 23.3 33.2 31.1 -2.1

Renew Prog - Urban LV Renewal 64.3 36.2 46.5 46.4 38.2 -8.3

Renew Prog - Rural LV Network 95.8 84.1 74.8 84.5 78.5 -6.0

Storm Rectification Project 0.0 27.4 0.0 0.0 0.0 0.0

Renew Prog - LV cables and

associated items

17.2 6.2

16.2 16.4 15.7 -0.8

Meters and Time Switches 0.0 0.0 14.0 14.1 10.8 -3.3

Renew Prog - Cut-outs 5.8 4.0 14.3 14.3 5.6 -8.7

Continuity Improvement 22.8 14.0 13.5 13.5 13.5 0.0

Response capex 101.1 56.5 51.3 61.4 54.7 -6.6

System Control 15.4 3.9 16.5 16.5 9.7 -6.8

IVADN 0.0 0.0 7.1 7.1 4.5 -2.6

NAGZ 0.0 0.0 87.6 87.6 70.0 -17.6

Other (specify)2 0.0 0.0 0.0 0.0 0.0 0.0

NRP/ Bulk Supply 0.0 0.0 0.0 0.0 0.0 0.0

Total Non-Load Related CAPEX 578.5 425.4 694.4 671.0 580.65 -90.46

Capex - Non Network 183.5 138.9 172.2 172.2 154.3154.25 -18.017.95

Other (Smart Metering) 0.0 12.9 22.9 22.9 12.9 -10.0

Contributions -398.3 -198.5 -200.1 -238.2 -229.6 8.6

TOTAL NET CAPEX 1754.1 1130.1 1544.3 1481.0 1336.91340 -144.2

Demand Connections:

The DSO PR4 forecast capex (gross) is €301.2m, this is €60.0m (25%) higher than the expected PR3

outturn total capex of €241.2m. Net of customer contributions, the DSO PR4 forecast capex is €150.6m,

some €14.0m higher than expected PR3 outturn.

The increase in gross capex as forecast by the DSO for PR4 period is based on an increased number of

connections for each of G1/G2/G3 categories. Steady growth during PR4 is forecast by the DSO and a

total of 108,000 connections are expected to be made over this period, representing a 53% increase to

PR3 volumes.

We consider that the DSO PR4 forecast of new connections of 108,000 is a reasonable assumption for

tariff purposes, recognising that CER will make adjustments for higher or lower connections based on

allowed unit costs.

2 Included within the Continuity Work Programme

Page 18: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 13

The DSO has proposed standard unit costs for each of the G1/G2/G3 connections. We have concluded

that the proposed DSO unit costs for 2016 and 2017 are reasonable. However we recommend that the

additional costs that the DSO has factored in to its unit cost calculation from 2018 onwards should be

removed, this being consistent with the DSO a priori assumption that its forecast does not include for the

introduction of smart metering.

A reduction in allowed PR4 gross capex of €8.7m is recommended for PR4 demand connections, based on

the difference in unit costs proposed above for G1/G2/G3 connections.

For PR4, the DSO is forecasting total metering capex of €19.5m – this is €4.8m (32.6%) higher than PR3

expected outturn costs and €7.0m (56.3%) higher than PR3 allowed costs.

We recommend allowances for PR4 period based on 6.5% of our recommended PR4 gross capex for

G1/G2/G3 connections of €273m. This results in a recommended allowance for metering of €17.8m

representing a reduction of €1.8m compared to the DSO revised PR4 proposed capex of €19.5m.

Generator Connections:

For generator connections, the DSO is forecasting gross capex in PR4 of €109.5m. This represents an

increase of 24.4% compared to expected PR3 outturn.

Capex during PR4 will be focused on Gate 3 projects that have contracted since mid-2013. The DSO is

estimating that a total of 1,250 MW is to be connected to the distribution system during PR4.

As expected in our review of DSO historic capex, the over-recovery of connection costs in later years of

PR3 results in net cash outflows throughout the PR4 period, with a total net capex over the PR4 period of

€47.4m.

We recommend acceptance of the DSO proposed gross capex of €109.5m.

Load Related Reinforcement:

The DSO load-related reinforcement capex for the PR4 period is €317.8m. Although this is significantly

below the PR3 allowed capex of €648.1m, it is only €6.9m (2.1%) lower than DSO expected outturn

(€324m) for the PR3 period.

The DSO’s proposed PR4 reinforcement capex forecast has been prepared on a zero cumulative load

growth forecast for peak demand from 2013 - 2020. The DSO has made significant investment to reinforce

the network during previous price controls. However, there are still many parts of the network that do not

comply with the Planning Standard.

Unit sales (GWh) during PR4 are forecast to grow at approximately 2.2% per year. The DSO has assumed

that that the unit sales growth does not result in peak demand growth.

Zero load growth and peak demand reduction due to smart metering impact act to suppress the capex

forecast requirements for PR4 relative to previous price controls. There is a risk that the smart metering roll

out is either deferred beyond PR4 or does not have any impact on DSO peak demand. The DSO will need

to res-assess its reinforcement investment plans for later years of PR4 to account for the impact of such a

scenario.

We are satisfied that the DSO has established good practice relating to its preparation of investment plans

for its 110kV and 38kV network development and undertaking project investment appraisals before seeking

technical and financial approval and subsequent commitment of capex to a project.

Notwithstanding some errors and/or inconsistencies with the consolidated list of HV reinforcement projects

compared to individual projects and which are not considered to be material, we conclude that the DSO

proposed PR4 reinforcement capex for 110kV and 38kV is reasonable.

The DSO has proposed a total of €40.9m of reinforcement capex relating to the MV and LV network. The

proposed PR4 capex (€40.9m) represents a 18.8% increase compared to expected costs for PR3

(€34.5m), although considerably less than PR3 allowed costs of €70.8m.

We generally agree with this work being necessary although we would recommend allowances for PR4

such that PR3 actual and PR4 forecast capex is consistent with the PR3 allowed capex of €70.8m – this

was allowed to address known network deficiencies and is considered adequate for the DSO’s zero growth

Page 19: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 14

scenario. In addition we would expect the ongoing 20kV conversion programme to improve the network

and reduce reinforcement requirements.

This will reduce PR4 allowances for MV/LV System reinforcements by €4.6m to €36.3m (a reduction of

11%).

With regard to the 20kV conversion programme, the DSO expected PR3 volumes (10,500km) and capex

(€36.5m) result in a unit cost per km converted of approximately €3,475/km. The DSO proposed PR4

programme is based on converting 4,000km at the same unit cost, giving a total cost of €13.9m. Further

IFT works at cost comparable with PR3 are also proposed. We consider these to be reasonable costs and

consequently we recommend PR4 allowance of €25.0m.

Retirements (Dismantling) Capex:

We recommend PR4 allowances for dismantling which are derived as a proportion of our recommended

PR4 gross network capex – with allowances set at 4.1% of this gross value - this results in a recommended

PR4 capex for dismantling of €55.1m, representing a reduction of €9.3m compared to the DSO forecast of

€64.4m.

Diversions:

It is observed that there is a strong historic relationship between new business gross costs and diversion

gross costs. However, the DSO forecast is not consistent with this historic relationship. We therefore

recommend PR4 allowances for diversion works that are consistent with the historic relationship between

new business and diversion gross costs. We have applied this to our recommended allowances for New

Business gross capex.

This results in a PR4 forecast capex for diversions of €50.6m, representing 17.4% of PR4 gross new

business capex. This is €9.6m (16%) lower than the DSO revised forecast of €60.2m and €42.5m (45%)

lower than the DSO original forecast of €92.1m.

Non-Load Related Capex:

The DSO’s revised non load-related (NLR) capex for the PR4 period is €669.1m. This is significantly above

the expected PR3 outturn capex of €425.4m, although only €92.5m higher than the CER allowed capex for

non-load related capex during PR3.

The main drivers for the proposed PR4 works are to address safety risks, ensure compliance with health &

safety and environmental obligations and to maintain continuity of supply. Replacement works are driven

by the condition and performance of particular asset categories. The DSO NLR PR4 programme consists

of the following projects/programmes:

- Completion of major 110kV and 38kV HV Station replacement projects originally planned for

completion in PR3 but subsequently deferred due to prevailing financial situation at the time;

- Continuation of existing HV & MV asset renewal and security programmes to mitigate safety risk to the

public and the DSO workforce;

- Continuation of cyclical refurbishment of the 38kV & MV overhead lines, together with a project to

rebuild a number of 110kV double circuit tower lines in the Dublin area;

- Commencement of a small number of targeted asset renewal/ refurbishment programmes

- NAGZ is a major smart grid investment initiative aimed at addressing the impact caused by increasing

levels of renewable generation. The project will look to combine intelligent smart grid networks, high

speed communications and IT, linked with increased cross-border connectivity

- The proposed plans also include for a small number of relatively low cost pilot projects to allow for

assessment of emerging/ different technologies before any decision is made regarding roll out of such

technologies on a wider scale. The costs of these are presently incorporated within the DSO’s main

asset renewal programme categories but these could be ring-fenced within the DSO PR4 R&D

forecast expenditure category

Page 20: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 15

In general, we consider the justification for the various PR4 works proposed by the DSO is proven and in

many cases, we agree with the proposed volumes of work. However, our review has identified a number of

significant increases in the DSO PR4 planned costs, compared to PR3 planned costs (for deferred works)

or PR3 expected outturn costs (for works progressed during PR3).

We have therefore made proposed adjustments to the proposed DSO PR4 non-load related capex to

account for such differences where the DSO has been unable to provide further justification supporting

such increases in planned costs for its major projects and its planned unit costs for its asset renewal work

programmes.

In relation to the 38kV Overhead Cyclical Refurbishment Programme, the DSO revised forecast for PR4 is

based on a unit cost which is consistent with outturn cost in PR3. We recommend allowances for PR4 that

are consistent with the PR3 outturn unit costs.

In relation to the re-conductoring of 110kV double circuit tower lines in the Dublin area, it is our

understanding that there has not yet been any detailed line survey and analysis to inform the assessment

of the potential costs and that the DSO has not yet fully developed its proposed investment case. The DSO

PR4 forecast is therefore based on a middle-ground cost scenario. However, taking a low cost based on a

line refurbishment using existing towers, and a high cost based on fully undergrounding and stating that a

half way position is part underground, part tower replacement and part fittings replacement does not

constitute a planned investment.. We would however agree that the requirement to carry out the lowest

cost practical solution at this time seems reasonable and therefore would recommend this cost of €6.8m.

We do recognise the risk associated with this cost uncertainty and therefore once the DSO has developed

its planned investment for these circuits, this should be reviewed to assess the efficiency of their proposed

investment during PR4

The proposed changes result in PR4 recommended capex of €27.5m for 110kV and 38kV lines (with capex

reduced by €10.9m).

Our recommended PR4 capex allowances for 110kV and 38kV cable asset renewal works is €25.8m

broadly in line with DSO original capex submission of €24.5m within Table 6.3 of Forecast Business Plan

Questionnaire, but some €2.2m less than the DSO’s revised capex submission of €28.0m.

For a number of the sub-programmes associated with HV Station Asset Renewals, we have applied a

reduction to the proposed unit costs that the DSO has used in its PR4 forecast. These result in a

recommended PR4 capex of €116.9m, a reduction of €9.0m compared to the DSO forecast of €125.9m.

The DSO is proposing to inspect and refurbish where required, 34,500km of MV OHL as part of a 12 year

cyclical refurbishment programme at a unit cost of more than €2,200 per km. During PR3 period 2011 to

2014, the DSO has completed the refurbishment of approximately 18,400km at an expected unit cost of

€2,100. For PR4, the DSO is forecasting the unit cost will increase to €2,217 per km, representing an

increase of more than 5%.We recommend allowances for PR4 based on unit costs achieved during PR3

(2011 to 2014).

This reduction results in a recommended PR4 capex of €78.1m, a reduction of €4.1m compared to the

DSO revised forecast of €82.2m.

The DSO proposes a zero capex associated with the renewal of MV cables as no planned capital activities

are proposed for MV cable assets. PR3 allowed capex was €2.6m, with PR3 expected outturn of €1.8m.

For a number of the sub-programmes associated with MV Station Asset Renewals, we have applied

reduction to the proposed unit costs that the DSO has used in its PR4 forecast. These result in a

recommended PR4 capex of €38.2m, a reduction of €8.2m compared to the DSO revised forecast of

€33.2m.

The DSO is proposing to refurbish 17,500 spans (typically 25 spans/km) of Urban LV overhead network

(dating pre-1950) at a unit cost of more than €60,000 per km. During PR3, the DSO is forecasting to

complete the refurbishment of approximately 15,700 spans of network at an expected unit cost of more

than €51,500 per km. In support of its higher cost (>€60,000), the DSO has explained that the works are

planned to be delivered mainly by contractor resources and the contractor costs are driving up the unit

costs. The DSO has stated that the proposed networks that will be refurbished in PR4 are the same

vintage as networks refurbished in PR3 and the PR4 programme will mainly consist of networks not

completed in PR3. We remain of the view that there is insufficient justification to support a 20% increase in

Page 21: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 16

unit costs for this work and we recommend PR4 allowances based on the expected outturn unit costs for

PR3. This reduction results in a recommended PR4 capex of €38.2m, a reduction of €8.2m compared to

the DSO’s revised forecast of €46.4m.

The DSO is proposing to refurbish 11,350 bare LV rural groups and commence an additional programme to

inspect and complete remedial works on LV rural networks that have not been addressed since the mid-

late-1990s (a further 5,900 groups). We recommend allowances for these works based on the DSO

expected outturn unit costs during PR3. This reduction will result in a recommended PR4 capex of €78.5m,

a reduction of €6.0m compared to the DSO forecast of €84.5m.

In relation to the renewal programme associated with LV cables and associated items, the DSO proposed

works for PR4 are mainly a continuation of PR3 programmes. We recommend allowances for these works

based on the DSO expected outturn unit costs during PR3. This reduction will result in a recommended

PR4 capex of €15.7m, a reduction of €0.5m compared to the DSO’s revised forecast of €16.2m.

We have proposed adjustments to the DSO PR4 forecast capex of €14.1m associated with meter

replacement. We have adjusted for the CT metering to be replaced during PR4 (80%) and PR5 (20%)

rather than funding the replacement of the full population during PR4. We have also recommended a

reduction in capex associated with the funding for pilot communication project only (GPRS) for quarter

hourly data collection. We have proposed an allowance of €1m rather than the €2m proposed by the DSO

relating to a broad scale upgrade of the communications system. We have not been provided with detailed

cost information to support the €2m project and we would also expect the DSO to prepare a business case

to support the wider scale investment. These adjustments reduce the PR4 forecast capex from €14.1m to

€10.8m, a reduction of €3.3m.

The DSO is expecting to complete replacement of 30,000 cut-outs during PR3 at a total cost of €4.1m,

representing a unit cost of €140 in PR3. The PR4 programme proposed by the DSO is to increase the

replacement volumes to 40,000 although its proposed unit cost of €357 is considerably higher than

expected PR3 outturn. We recommend PR4 allowances based on the proposed DSO volumes and the

PR3 expected outturn unit costs in the absence of evidence from the DSO to support the higher proposed

unit cost. This results in a recommended PR4 capex of €5.6m, a reduction of €8.7m compared to the DSO

forecast of €14.3m.

For each of the proposed continuity improvement programmes, the DSO has carried out cost-benefit

analysis, which has been used to prioritise its investment plans. We recommend that the proposed DSO

PR4 capex of €13.5m relating to its Continuity Improvement programme is allowed. This allowance

includes €1.4m associated with a continuity programme to improve supplies to the DSO’s worst served

customers. In its response to the proposed Incentives for PR4 (Document DR07) the DSO has presented

two separate scenarios to address worst served customers, based on available information from UK DNOs

(the UK RIIO ED1 decision documents). Once CER has finalised the DSO PR4 incentive framework

(including allowances, targets, penalties etc – there may be a requirement to make an adjustment to theses

recommended allowances for DSO continuity capex.

We agree with the DSO proposed Response Capex for PR4 for all categories, other than for costs relating

to failed transformers. In addition, whilst we accept that there will be a need for the DSO to take action to

address the theft of copper conductor from its overhead line network, we note that this is a new category of

reactive work for which the DSO has based PR4 forecast on a nominal €2m per year, this being the

forecast costs for 2015 to address 4 specific circuits that have been subject to repeated thefts. The DSO

PR4 forecast is based on an assumption that similar quantities and works will be required on an annual

basis for the PR4 period. However, in the absence of any detailed risk analysis, we cannot conclude if

these figures are reasonable. We therefore recommend a PR4 allowance of €5m in total. This reduces

PR4 continuity capex by €6.6m to €54.6m.

We recommend PR4 funding relating to SCADA and Control Centre Infrastructure – at a total capex of

€9.7m. This represents a reduction of €3.0m compared to the aggregate total expenditure of €12.7m for

PR4.

In relation to the IVADN project, the DSO has forecast €7.1m in PR4. However it is unclear what capex is

proposed by the DSO during PR4 and what the project deliverables and benefits will be. There appears to

be significant uncertainty regarding how this R&D project will proceed and what it will cost (both capex and

opex).

Page 22: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 17

We therefore recommend that the DSO is allowed the capex costs associated with the reactive power work

stream (of €3.5m) as these are well advanced.

In the absence of detailed plans for the other work streams, we recommend additional total allowance of

€1m. We also suggest that the DSO continues to engage with the CER during PR4 once details of the

particular projects, including timing, cost, expected benefits etc. are known in more detail. Our recommend

allowance is therefore €4.5m, which is €2.6m lower than the DSO proposed PR4 forecast of €7.1m.

The NAGZ has a total project cost of €106m – with the costs split between the DSO (€70m) and NIE

(€36m). The DSO PR4 capex forecast includes for €87.6m associated with the NAGZ project, which has

also recently received grant funding of €31.75m from the EC. These facts suggest that the proposed DSO

PR4 capex forecast relating to the NAGZ is higher than necessary.

We also note that the NAGZ main capex cost components include works for which allowances have been

separately assessed (e.g. PR4 20kV conversion programme and upgraded protection schemes within the

DSO PR4 Continuity Improvement) and for which capex allowances will be made for PR4. There is a

potential risk of duplicating capex allowances as it is not clear that the overall network assessment has

explicitly excluded network assets within the NAGZ. The DSO has advised that all of the 20kV conversion

work undertaken during PR4 will be outside the NAGZ.

We recommend that the CER provides gross capex allowances for the NAGZ during PR4 of €70m – the

DSO proportion of the NAGZ total cost, with a further reduction if the NAGZ project receives funding under

the Connecting Europe Fund.

Non-Network Capex:

The DSO has forecast a total Non-network capex of €172.2m by end of PR4 – this is €33.4m higher than

the actual expenditure of €138.9m in PR3.

There are a number of areas where there is justification for maintaining and increasing expenditure,

however there are other areas where there are proposed significant increases where there has not been

sufficient justification and a demonstrated business case showing need, options and risk associated with

the proposed increases.

Total PR4 forecast expenditure on Refurbishment and Fixtures and Fittings reflects an increase over PR3

of €4.2m, but is €2.8m less than the PR3 allowance. Given the capex constraints in PR3, it seems

reasonable that there would be an increase over the PR3 outturn to ensure the buildings are maintained

and secure. We therefore recommend allowances of €15.5m in line with the forecast.

Total PR4 forecast expenditure on Vehicles at €30m was based on a forecast outturn in PR3 of €17.2m.

Since December 2014 the forecast outturn for PR3 has increased to €35.1m. We have therefore adjusted

the PR4 allowance based on the increased expenditure in 2014 and 2015. Wewe do not believe the

forecast fully exploits improved utilisation and vehicle reduction based on savings driven by the Mobile

Workforce Management system, recommended allowance is therefore €22.75m75m.

The forecast PR4 capex for tools is €10m; this has been reduced from the PR3 total of €14.8m and

represents good progress in developing efficiencies. The proposal is to allow the €10m.

Total PR4 forecast expenditure on Mobile Workforce Management reflects an increase over PR3 of

€14.2m. Given the potential benefits of this, it would be expected that a detailed business case driven by

the efficiency and cost benefit would be apparent. Some information has been provided which suggests

significant opex and capex savings within the business. However this saving is not reflected in the

submission in those areas. It is therefore proposed that the programme in PR4 should be €15m, a

reduction of €5m from the DSO forecast. We would comment that we fully support the full implementation

of this initiative which should not be constrained by the allowance. The allowance reflects that savings

elsewhere not provided at this time will make the initiative self-financing.

Total PR4 forecast expenditure on the Document Management System reflects an increase from €0.94m in

PR3 (all forecast in 2014 and 2015) to €8.1m in PR4. Given the potential benefits of this, it would be

expected that a detailed business case driven by the efficiency and cost benefit would be apparent. As this

is not the case, then it is proposed to reduce the value proposed by €1.2m to €6.9m.

Page 23: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 18

Total PR4 forecast expenditure on Environment is €4m compared to €1.9m in PR3. There has been some

information provide identifying where the additional expenditure is needed therefore it is recommended that

this is allowed at €4m.

Total PR4 forecast expenditure on Control and Telecoms is €53.9m compared to €32.6m in PR3. The

business case for the expenditure has not been clearly demonstrated and it is believed that there should be

opportunities for driving efficiencies from this budget. It is therefore recommended that the proposed

allowance should be reduced by €5.4m giving the PR4 allowance as €48.5m. It is also recommended that

the expenditure allowance is dependent on delivery of the Core & Aggregation IP Network and National

Radio Access Communication Network.

The DSO PR4 forecast for capex associated with smart metering is €22.9m with these costs expected to

be incurred in 2016 (€12.5m) and in 2017 up to end June 2017 (€10.3m). Capex during PR3 is €12.9m.

The DSO has only provided details of the €22.9m split by year, with no indication of planned capex relating

to each of the work streams and the capex deliverables necessary to facilitate the roll-out of the smart

metering program. Without a clear understanding of how the proposed capex is to be invested, what

physical assets are being delivered, we are not able to recommend full allowances.

In the absence of supporting justification, we recommend PR4 allowances set at PR3 outturn levels -

€12.9m representing a reduction of €10.0m compared to the DSO PR4 submission.

Page 24: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 19

Important note about your report

The sole purpose of this report and the associated services performed by Jacobs is to support the Client

(Commission for Energy Regulation - CER) in setting the allowed revenues for the Distribution System Operator

(DSO), the Transmission System Operator (TSO) and the Transmission Asset Owner (TAO) (the ‘Companies’)

as part of the 4th Price Control Review Process in accordance with the scope of services set out in the contract

between Jacobs and the Client. That scope of services, as described in this report, was developed with the

Client.

In preparing this report, Jacobs has relied upon, and presumed accurate, any information (or confirmation of the

absence thereof) provided by the Client, the Companies and/or from other sources. Except as otherwise stated

in the report, Jacobs has not attempted to verify the accuracy or completeness of any such information. If the

information is subsequently determined to be false, inaccurate or incomplete then it is possible that our

observations and conclusions as expressed in this report may change.

Jacobs derived the data in this report from information sourced from the Client (if any), the Companies and/or

available in the public domain at the time or times outlined in this report. The passage of time, manifestation of

latent conditions or impacts of future events may require further examination of the project and subsequent data

analysis, and re-evaluation of the data, findings, observations and conclusions expressed in this report.

Jacobs has prepared this report in accordance with the usual care and thoroughness of the consulting

profession, for the sole purpose described above and by reference to applicable standards, guidelines,

procedures and practices at the date of issue of this report. For the reasons outlined above, however, no other

warranty or guarantee, whether expressed or implied, is made as to the data, observations and findings

expressed in this report, to the extent permitted by law.

This report should be read in full and no excerpts are to be taken as representative of the findings. No

responsibility is accepted by Jacobs for use of any part of this report in any other context.

The findings of this Interim Report are based on the data made available to Jacobs by the Client and the

Companies prior to the agreed submission deadline.

This report has been prepared on behalf of, and for the exclusive use of, Jacobs’s Client, and is subject to, and

issued in accordance with, the provisions of the contract between Jacobs and the Client. Jacobs accepts no

liability or responsibility whatsoever for, or in respect of, any use of, or reliance upon, this report by any third

party.

Page 25: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 20

1. Introduction

The Commission for Energy Regulation (CER) is Ireland’s independent energy regulator, responsible for

overseeing the liberalisation of Irelands Energy Sector. The CER was established and granted powers over the

electricity market in 1999 (under the Electricity Regulation Act, 1999). Regulatory responsibilities in the Gas,

Petroleum Exploration and Extraction and Water sectors followed in 2002, 2010 and 2013 respectively.

Consequently, CER has a wide range of economic, customer protection and safety responsibilities in the energy

sector of Ireland. CER’s mission is to act in the interests of consumers to ensure that:

the lights stay on,

the gas continues to flow,

the prices charged are fair and reasonable,

the environment is protected, and,

energy is supplied safely.

CER regulates to the highest international standards

The CER’s primary economic responsibilities in the electricity sector are to regulate electricity generation, the

electricity networks and electricity supply activities. The overall aim of the CER is to protect the interests of

electrical customers, maintain security of supply, and to promote competition in the generation and supply of

electricity.

Under section 36 of the Electricity Regulation Act, 1999, and Statutory Instrument 445 of 2000 (as amended),

CER approves charges for the use of the electricity distribution and transmission systems. CER is also required

to examine the costs and revenues underlying such charges. As such, CER approves revenues for:

ESB Networks as Distribution System Operator (DSO)

ESB Networks as Transmission Asset Owner (TAO); and

EirGrid as Transmission System Operator (TSO).

These revenues are determined every five years for the following five year period. CER has previously

determined transmission and distribution revenue controls for the periods 2001 to 2005, 2006 to 2010 and 2011

to 2015 inclusive. CER issued an Invitation to Tender (ITT) requesting consultancy support to provide technical

and financial advice in regard to the fourth set of transmission and distribution revenue controls to cover the

next 5 year period from 2016 to 2020 (PC4).

Jacobs were appointed as technical consultants to support CER in setting the allowed revenues for the DSO,

TSO and TAO businesses in PC4.

1.1 This Report

This report sets out Jacobs’ opinion on the DSOs capital expenditure (capex) and operating expenditure (opex)

over the PR3 period (2011 to 2015) and PR4 (2016 to 2020). The report considers the costs, systems

processes, and initiatives of the DSO over PR3 and identifies key issues to be considered in PR4. The report

then reviews the DSO’s proposals for expenditure in PR4 and makes recommendations on the level of

expenditure, outputs and incentives to be allowed by CER.

This report also presents Jacobs’ benchmarking and incentives analysis relative to the DSO in addition to smart

metering and asset lives and depreciation.

This report is divided into 6 sections and 4 appendices. The report sections are structured as follows:

Section 1 contains this introduction

Section 2 contains our review of the DSO’s actual and expected PR3 operating expenditure (opex) and

compares this to the DSO allowances as outlined by the CER for the same period.

Page 26: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 21

In Section 3 presents the DSO’s proposed opex allowances for PR4. These proposed allowances are

reviewed and subsequently we present the Jacobs’ proposed allowed opex for the PR4 period.

Section 4 contains our review of the DSO’s actual and expected PR3 capital expenditure (capex) and

compares this to the DSO allowances as outlined by the CER for the same period.

In Section 5 presents the DSO’s proposed capex allowances for PR4. These proposed allowances are

reviewed and subsequently we present the Jacobs’ proposed allowed capex for the PR4 period.

Section 6 provides a summary of the allowed opex and capex as discussed and presented in Sections 3

and 5.

The report appendices are structured as follows:

Appendix A provides a benchmarking assessment of the DSO and TAO.

Appendix B contains a review of the effectiveness of the incentives placed on the DSO in PR3 and the

DSO performance against these incentives. This section also discusses the ongoing suitability of the DSO

PR3 incentives for application during PR4.

Appendix C discusses the impact of smart meters and smart grids on the DSO.

Appendix D reviews the assumed asset lives and depreciation assumptions with a view for application in

PR4.

1.2 Data Sources and Assumptions

The review has been informed by the companies’ response to the questionnaire on historic operating and

capital costs and associated information papers and network plans, together with further data provided by the

companies at meetings and from supplementary questions raised by CER and consultants.

The review takes into account provisional outturn costs and performance for 2014 and 2015.

CER has also provided a significant amount of background information on previous price reviews and updated

information.

Unless stated otherwise, our review of PR3 expenditure, detailed within Section 2 and Section 4 of this report,

has prices expressed as real prices at 2009 price levels. This allows comparison with the original CER PR3

allowances. Our review of planned PR4 expenditure (Section 3 and Section 5) has prices stated in real prices at

2014 price levels. The conversion to these price levels was based on the inflation factors presented in Table 1.1

below.

Table 1.1 : HICP Adjustment Factors

2009 2010 2011 2012 2013 2014

HICP Adjustment

Factor 1.000 0.984 0.996 1.015 1.020 1.024

CER allowed costs are as set out in the CER PR3 decision paper with annual adjustments made during the

price control period by CER for pass through items along with volume related items included as part of the PR3

settlement.

Page 27: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 22

2. Review of PR3 Operating Expenditure

In this section of the report we review the PR3 (‘historic’) opex of the DSO (covering the years 2011 to 2015)

against the PR3 DSO allowances, as determined by CER for an efficient company operating in Ireland.

The objective of CER in setting allowed operating costs is to ensure that expenditures funded by electricity

consumers through the DUoS tariff are as efficient as possible and that efficiency improvements within the DSO

continue to be made, to the benefit of customers. This should result in setting the companies challenging but

realistic and achievable targets and incentives, all the while moving closer to international best practice. The

objective of this review is to assess the DSO’s performance in achieving the outputs required by CER during

PR3 within the CER allowed costs. The review identifies any changes in circumstances put forward by the DSO

and CER to explain variances in outputs and costs.

Our review of PR3 opex assesses:

Historic trends in opex

Comparison of actual opex against allowed opex

The data presented, analysed and commented on in this report has been provided by the DSO to the CER and

Jacobs via:

Regular workshops hosted by the CER between April 2014 and October 2014,

The return of Questionnaires issued by the CER in July 2014,

Ongoing communications with Jacobs and the CER following the submission of the historical PR3 data at

the end of October 2014.

It should be noted that 2011 to 2013 performance and cost data is based on actual recorded values. 2014

performance and cost data is based on unaudited actuals whilst 2015 performance and cost data is based on

the latest forecast data available.

2.1 Overview

The CER decision paper (CER/10/198) set out the DSO’s original annual allowed opex for the PR3 price control

period. The opex costs outlined in the decision paper were split into controllable and non-controllable costs.

Controllable costs are categorised as:

Network O&M – The day to day System Control covering the Distribution Control Centres in Cork And

Dublin, along with planned and fault maintenance of the Network Assets.

Asset Management – The development of Policies and Asset strategies, along with payments for

wayleaves, forestry and mast interference payments.

Metering – The DSO provides a range of services related to metering to all stakeholders including,

electricity supply companies and customers. These services include the management of these assets,

collection and aggregation of metering data and revenue protection services.

Customer Service – Included within this category are the costs of the Customer Care Centre, Scheduling

Support Centre, customer relations and area operations.

Provision of Information – These costs are associated with DUoS billing and accounts receivable, Meter

Registration System Operator, Market System support costs.

Corporate costs – Costs from corporate centre, for services such as CEO, Group Finance, Corporate

affairs.

Sustainability and R&D – This category relates to initiatives to carry out sustainability and R&D activities.

Other – This category includes items such as Insurance, Legal, Environmental, and Health and Safety.

Non controllable costs are categorised as:

Page 28: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 23

Network Rates

CER levy

Table 2.1 below presents the initial allowed opex for the full PR3 period and also presents the most recent

projection (expectation) of opex by the DSO over the same period3. This data indicates that the DSO expects to

spend around €50m (or 6%) more on controllable opex than originally allowed and approximately €3m (or 2%)

more on non-controllable opex than originally allowed.

Table 2.1 : DSO PR3 Original Cost Allowance v DSO Forecast Outturn

The price control mechanism allows for a number of adjustments to be applied to the initial opex allowances set

out by the CER and presented in Table 2.1 above4. The opex allowances of some of the opex sub-categories

above have been adjusted during the PR3 period. The adjustments allowed are presented below in Table 2.2

and have been substantiated and verified following additional information from the DSO. The individual

adjustments outlined in Table 2.2 are discussed and explained in the sub-sections below5.

Table 2.2 : Adjustments to PR3 Operating Cost Allowances

Operating Cost Adjustments

CER Determination 1086.9

Allowed Adjustments

Metering 26.7

Storm Darwin 23.7

Non Controllable Costs Pass Through 3.3

3 The DSO expenditure for the years 2011 to 2013 data is based on actual values, 2014 based on unaudited actuals and 2015 data reflects the most

recent forecast available 4 For example, the allowance can be altered depending on customer numbers etc. 5 The fault maintenance adjustment (“Storm Darwin”) is discussed in Section 2.2.4 the Metering adjustment is discussed in Section 2.2.6, the

Customer Service adjustment is discussed in Section 2.2.7, the Provision of Information adjustment is discussed in Section 2.2.8 and the Non Controllable Costs adjustment is discussed in Section 2.3.

DSO Operating Costs

(€m 2009 Prices) allowed forecast variance %

Network O & M Total 445.6 493.4 47.7 11%

Asset Management 60.2 64.7 4.5 8%

Metering 100.5 130.8 30.3 30%

Customer Service 82.3 74.0 -8.3 -10%

Provision Of Information 74.8 52.6 -22.2 -30%

Corporate Costs 64.3 54.0 -10.3 -16%

Telecoms 0.0 0.0 0.0 -

Sustainability & R & D 18.2 8.0 -10.2 -56%

Other 51.0 69.7 18.7 37%

Controllable total 896.9 947.1 50.2 6%

Network Rates 180.5 183.4 2.9 2%

Cer Levy 9.5 9.9 0.4 4%

Non Controllable 190.0 193.3 3.3 2%

Total (Excl Commercial and Depn) 1086.9 1140.4 53.5 5%

PR3 Total

Page 29: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 24

Operating Cost Adjustments

Provision of Information -0.7

Customer Service -1.1

Revised PR3 Allowance 1138.8

Table 2.3 provides a revised summary of the DSOs performance against the adjusted PR3 allowances, along

with the high level efficiencies requested by CER as part of the PR3 settlement process.

Table 2.3 : Final Allowance Table for the DSO for PR3

This data indicates that, prior to any adjustments for high level efficiencies; the DSO is broadly operating within

the PR3 allowances with an expected expenditure on controllable and non-controllable items of €1140.4m

against an adjusted allowance of €1138.8m. The most significant overspend is on Network Operations and

Maintenance (€24.0m), with the main underspend being on the Provision of Information (€21.5m). Owing to the

pass through nature of non-controllable opex, PR3 allowance is expected to equal actual expenditure.

Taking into account the efficiency driver (€-31.3 million) which the DSO acknowledge was not achieved

(DH01 – Section 8), the DSO Total Costs are overspent by €32.9m (or 3% of total allowed expenditure).

The sub-sections below provide further details of the over/under spend on a category by category basis.

2.2 Controllable Costs

2.2.1 Network Operations and Maintenance

(Allowed € 469.3m Outturn € 493.4m)

DSO Operating Costs

(€m 2009 Prices) allowed forecast variance %

Network O & M Total 469.3 493.4 24.0 5%

Asset Management 60.2 64.7 4.5 8%

Metering 127.2 130.8 3.6 3%

Customer Service 81.2 74.0 -7.2 -9%

Provision Of Information 74.1 52.6 -21.5 -29%

Corporate Costs 64.3 54.0 -10.3 -16%

Telecoms 0.0 0.0 0.0 -

Sustainability & R & D 18.2 8.0 -10.2 -56%

Other 51.0 69.7 18.7 37%

Controllable total 945.5 947.1 1.6 0%

Network Rates 183.4 183.4 0.0 0%

Cer Levy 9.9 9.9 0.0 0%

Non Controllable 193.3 193.3 0.0 0%

Total (excl Depreciation) 1138.8 1140.4 1.6 0%

Less High Level Efficiencies -31.3 0.0 31.3

Total (excl Depreciation) 1107.5 1140.4 32.9 3%

PR3 Total

Page 30: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 25

Table 2.4 presents a year on year comparison between allowed and actual/forecast expenditure on Network

Operations and Maintenance opex during PR3. This category includes planned maintenance, system control

and fault maintenance activities.

Table 2.4 : Network Operations spend in PR3

Overall, the Network Operations and Maintenance activity is forecast to be overspent over the PR3 period by

€24.0m (5%). This overspend is predominantly driven by planned maintenance which is expected to incur a

20% overspend during PR3 (€39.1m) due to significant expenditure on Tree cutting over and above the

allowance. This is partially negated by an underspend of €20.5m on fault maintenance.

System Control

(Allowed € 70.1m Outturn € 75.5m)

Table 2.5 presents a year on year comparison between allowed and actual/forecast expenditure on System

Control opex during PR3.

Table 2.5 : System Control spend in PR3

The System Control activity covers the control centres in Cork and Dublin. The costs to date are running ahead

of target due to long term illnesses and resultant increases in overtime (around 40% higher than expected

during the Price setting process to cover the resource shortage). The DSO has indicated in its questionnaire

responses6 that structural changes are in the process of being implemented and the full year impact of these

structural changes to reduce the rate of spend going forward will be seen in 2015. The forecast expenditure for

2015 does not appear to reflect this change in approach as forecast expenditure in 2015 is higher than the

actual expenditure in 2014 and a further €2.1m over and above the allowed expenditure for the same year.

Planned maintenance

(Allowed € 198.0m Outturn € 237.1m)

Table 2.6 presents a year on year comparison between allowed and actual/forecast expenditure on Planned

Maintenance opex during PR3. The Planned Maintenance activity is forecast to be overspent over the PR3

period by €39.1m (20%).

Table 2.6 : Planned Maintenance spend in PR3

One of the most significant activities within this category is Tree Cutting, which accounts for around 48% of the

DSO expenditure on Planned Maintenance.

In the DSO submission for Timber Cutting they are forecasting for PR3 an expenditure of €111.8m against an

allowance of €84.7m, which will result in an overspend of €27.1m over the PR3 period.

6 DH01 PR3 Overview p27

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

System control 14.7 16.1 14.4 13.6 14.0 15.2 13.7 15.2 13.3 15.4 70.1 75.5 5.5 8%

Planned maintenance 41.0 46.0 40.3 53.3 39.6 42.7 38.9 50.4 38.2 44.7 198.0 237.1 39.1 20%

Fault maintenance 37.3 31.6 36.4 28.6 35.5 34.1 58.3 57.4 33.7 29.0 201.2 180.7 -20.5 -10%

Network O & M Total 93.1 93.8 91.1 95.5 89.1 92.0 110.8 123.0 85.2 89.2 469.3 493.4 24.0 6%

PR3 Total2014 20152011 2012 2013

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

System control 14.7 16.1 14.4 13.6 14.0 15.2 13.7 15.2 13.3 15.4 70.1 75.5 5.5 8%

2011 2012 2013 2014 2015 PR3 Total

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Planned maintenance 41.0 46.0 40.3 53.3 39.6 42.7 38.9 50.4 38.2 44.7 198.0 237.1 39.1 20%

2011 2012 2013 2014 2015 PR3 Total

Page 31: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 26

The DSO are of the opinion that the allowance set for PR3 was too low to provide an effective level of tree

cutting activity, and have deliberately overspent this allowance as it is their opinion that this is one of the most

cost effective ways to provide an acceptable level of service to customers. In the early part of the PR3 period

the LV tree cutting was curtailed by 25% against planned levels but the DSO management took the decision to

revert back to the original schedule in order to improve service levels.

Table 2.7 sourced from document ‘PR03 Timber Cutting Costs’ indicates annually derived unit costs for the

years 2011 to 2014. Due to the methods that the DSO use to allocate the work (in groups rather than by length)

and collect the data there is a level of uncertainty over the actual lengths of line where tree cutting has been

undertaken, hence the unit rates should be considered as indicative only.

Table 2.7 : Timber Cutting Unit Costs

The 110kV line cut frequency was reduced in 2011 from every 3 years to every 4 years. There is a balance

between the frequency of cut and the depth of the cut to meet required reliability standards (e.g. ESBN would

need to cut more wood to maintain a 4 year frequency than a 3 year frequency). We would expect the balance

on depth and frequency of cut to be mainly driven by cost to provide a given level of reliability and would expect

ESBN to provide justification on that basis. No cost benefit of the changed policy has been provided. Due to the

year on year natural variations it is not possible to determine if the curtailing of tree cutting was beneficial or not.

Where there is no high level assessment by the DSO of the Asset Health of the portfolio of assets under DSO

control, the approach taken by the DSO would restrict a determination of whether the planned maintenance is

sufficient to maintain an appropriate level of serviceability and if the asset class is deteriorating or if excessive

maintenance is being carried out and the customer is paying more than is needed. The DSO has not provided

evidence of the business processes in place to determine this information. It is reasonable to expect that, for a

company that has been PAS55 certified7 for its Asset Management System and approach for seven years, this

information would be utilised by the business to inform its maintenance regime and methodologies. This does

not need be a complex system, for example, a 5 point condition scale could be utilised, as illustrated below in

Table 2.8.

7 PAS55 – A Specification for the Management of Physical Assets, this has been superseded by ISO55000.

2011 2012 2013 2014

Cost €m

110kV/38kV 0.8 1 0.8 1.3

MV & LV Rural 16.3 16.7 17.5 18.5

LV Urban 2.6 1.6 5 2.8

Total 19.7 19.4 23.3 22.6

Volumes (Exact Recorded)

110kV/38kV (km) 2740 2046 1215 2378

Rural MV & LV (Groups) 38676 22730 21214 23081

Rural MV Only 12887 17623 16723 9196

LV Urban (Blocks) 118 110 145 64

Volumes (Approximate km)

110kV/38kV 2740 2046 1215 2378

MV & LV Rural 34707 30447 28691 22221

LV Urban 1686 1830 2421 1331

Total 36393 32277 31112 23552

Unit Rate €/km

110kV/38KV 289 510 651 542

MV & LV Rural 468 549 611 833

LV Urban 1571 873 2067 2087

Average 541 600 750 959

Page 32: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 27

Table 2.8 : Sample Table of Asset Condition Categories

Grade Condition Remaining Life

1 Excellent – as installed 95%

2 Good 75%

3 Fair 50%

4 Poor 30%

5 Bad – must be replaced immediately 5%

By assessing the condition of the assets at a company level it may be possible to identify potential areas of

significant changes in maintenance/ asset replacement requirements going forward, and thus the impact on

associated funding requirements. This can then be used to rate asset health by asset class over a period and

inform the priorities in an asset replacement programme, or change to maintenance frequency and activity. It

should also be possible to articulate the changes that could be seen in asset condition as a result of the

proposed investment and maintenance plans.

During the current PR3 period there have been two significant Health and Safety incidents. The findings from

the resultant investigations have entailed a full review and revision of working practices when dealing with

operational plant and machinery. The DSO has indicated that there is a significant change in the practices and

processes required to address the additional safety regimes. These have increased costs at the end of PR3 and

into PR4

There has been a significant increase in timber cutting costs over the PR3 period over and above the

allowance. The DSO believe that the increased activity level which has been procured by competitive

tendering is more appropriate in providing a satisfactory level of service to the customer and the

continued safety of the overhead network.

Fault Maintenance

(Allowed € 201.2m Outturn € 180.7m)

Table 2.9 presents a year on year comparison between allowed and actual/forecast expenditure on Fault

Maintenance opex during PR3. Overall fault maintenance expenditure is below the allowance for PR3

(€180.7m actual/forecast against €201.2m allowance).

Table 2.9 : Fault Maintenance spend in PR3

During 2013 and 2014 the DSO have stated there has been a significant increase in the level of storm and near

storm classification events, with the resultant knock on post storm costs ranging from relatively benign levels of

€2.0m in 2011 and 2012 to a level in excess of €17.0m in 2014 with associated performance impacts (e.g.

increasing customer contacts). The expenditure peak in 2014 of €57.4m is mainly due to ‘Storm Darwin’. An

adjustment has been made to allow €23.7m of expenditure for Storm Darwin to be added to allowed

expenditure.

Table 2.10 presents fault numbers for 2009 to 2013 taken from the PR03 Historic Questionnaire table 4.9.1.

The data that has been submitted for the period from 2009 indicates that the number of faults in 2013 was

higher than the previous three years. From information provided in workshops held between Jacobs, the CER

and the DSO, the latest predictions of the DSO expect the number of faults in 2014 to be even higher than 2013

levels, although 2014 activity numbers have not been supplied at the time of writing this report.

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Fault maintenance 37.3 31.6 36.4 28.6 35.5 34.1 58.3 57.4 33.7 29.0 201.2 180.7 -20.6 -10%

PR3 Total2011 2012 2013 2014 2015

Page 33: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 28

Table 2.10 : Fault Numbers 2009 to 2013

Fault nos. 2009 2010 2011 2012 2013

110kV Cables 2 3 0 1 0

110 kV Lines 3 1 4 1 16

110 kV Stations 15 11 14 13 1

38kV Cables 16 8 13 8 2

38kV Lines 73 41 57 40 81

38kV Stations 37 34 19 37 35

Total 146 98 107 100 135

The average cost per fault is analysed in Table 2.11 below, and indicates some significant volatility. This

volatility was raised with the DSO who advised us that the costs included not only direct fault costs but also

costs associated with plant failures which had been detected before interruptions had occurred and required

immediate remedial activity. This approach by the DSO and their responses indicate that they are unable to

provide meaningful unit cost analysis as costs are included under the fault headings which may not be directly

associated with post fault rectification but activities that are required to be carried out urgently in order to avoid

faults occurring. The table below has been provided for completeness. It is highly recommended that for PR4

there should be detailed unit costs for all faults, and differentiates the costs associated with attending alarms,

from actual faulted equipment. There should also be clear recording of costs to remedy a fault irrespective if the

costs are subsequently classed as capex. This inability to provide this analysis reference DSO.056.HOP, would

indicate there is little internal analysis carried out post fault to determine opportunities for more efficient fault

management.

Table 2.11 : Average Cost per Fault (2009 to 2013)

€ per fault

(2009 prices)

2009 2010 2011 2012 2013

110kV Cables 64,758 41,200 0 163,538 0

110 kV Lines 22,378 5,286 8,210 3,473 202

110 kV Stations 32,516 46,216 49,863 50,695 780,341

38kV Cables 19,576 46,246 31,792 56,421 179,442

38kV Lines 4,157 6,545 3,373 4,096 6,057

38kV Stations 82,307 67,450 255,765 86,527 47,369

For voltages below 38kV it is not possible to provide voltage specific unit fault costs, these can only be provided

at a summary level, as shown in Table 2.12 below for the years 2011 to 2013. This provides inadequate

granularity to manage fault costs in a meaningful way and identify efficient/ inefficient fault management, and

should be rectified going forward. 2014 data is not yet available from the DSO.

Page 34: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 29

Table 2.12 : MV/LV Fault Cost and Volumes (2011 to 2013 only)

The lack of clear cost monitoring and control of fault maintenance at a detailed level would indicate

there is little internal analysis carried out post fault to assess the efficiency of current fault

management or to determine opportunities for more efficient fault management. This results in an

inability to provide year on year comparisons as with the 110 kV and 38kV data and the inability to

generate unit costs for the lower voltages.

2.2.2 Asset Management

(Allowed € 60.2m Outturn € 64.7m)

Table 2.13 presents a year on year comparison between allowed and actual/forecast expenditure on Asset

Management opex during PR3. This activity comprises of Asset Management (asset managers and their teams

with responsibility for the development of policies and management of the various asset classes) and Forestry

and Wayleaves payments to landholders for compensation due to restrictions on land use due to overhead

lines. Overall expenditure on Asset Management in PR3 is forecast to exceed allowance by €4.5m (8%).

Table 2.13 : Asset Management spend in PR3

Expenditure on Asset Management strategy and policy development activities is forecast to exceed allowance

by €9.1m (a variance of 24%).

Although the DSO expects to spend less than the allowance on Forestry and Wayleaves (by around €4.6m),

there appears to be an increasing trend in the level of payments to landowners. The DSO has indicated that

farming and other environmental groups have become more vocal affecting these payments. This trend is

Fault Costs Table 5.2 €k 2011 2012 2013

MV / LV Fault Recovery 10362 9123 8589

MV / LV Unplanned Maintenance 93 98 197

MV / LV Fault Recovery - UG 6777 7641 6819

MV / LV Meter Installation Fault 564 583 472

OH MV Fault Recovery 5021 4648 4912

Underground Fault Repair 357 228 358

Total MV / LV Fault Costs 23175 22321 21347

Fault Numbers Table 4.9

OH Lines

20 KV 4304 4444 6249

10 kV 3381 3048 4139

LV Ex Services 15433 13132 15715

LV Services 1958 1446 1582

Total 25076 22070 27685

Underground Cables

20kV 18 21 26

10kV 208 243 154

LV Services 1334 1088 1095

Total 3133 2705 2734

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Asset Management 7.8 8.3 7.5 9.6 7.3 9.4 7.2 9.5 7.1 9.3 37.0 46.1 9.1 25%

Forestry & Wayleaves 4.6 3.0 4.7 3.0 4.7 4.2 4.6 3.9 4.6 4.4 23.1 18.5 -4.6 -20%

Asset Management 12.4 11.3 12.2 12.6 12.0 13.7 11.8 13.4 11.7 13.7 60.2 64.7 4.5 8%

2011 2012 2013 2014 2015 PR3 Total

Page 35: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 30

similar across both Transmission and Distribution elements of the Network. Consideration should be given to

renaming this classification of cost items as the term Asset Management could be misleading. Overall we would

consider these landowner payments as reasonable costs to the DSO.

2.2.3 Metering

(Allowed € 127.2m Outturn € 130.8m)

Table 2.14 presents a year on year comparison between allowed and actual/forecast expenditure on Metering

opex during PR3. Overall expenditure on metering in PR3 is forecast to exceed allowance by €3.7m (3%).

Table 2.14 : Metering spend in PR3

There has been an overall reduction in the Metering allowance of €1.6m to cater for the difference in actual

Connections from those assumed within the Final Determination, reducing the allowance from €128.8m to a

revised value of €127.2m. This reduction has been applied via the PCust mechanism. Table 2.15 below shows

the differences in Connections between the PR3 assumptions and actual performance. This data is taken from

the DSO document ‘DR05 Attachment B Allowance.xls’.

Table 2.15 : Connections PR3 Allowance v Actual Performance

2011 2012 2013 2014 2015 Total

PR3 assumption 28,027 29,682 31,330 32,976 34,622 156,637

PR3 actual (2014 and 2015 estimates) 15,121 12,800 15,285 16,191 15,285 74,682

Difference -12,906 -16,882 16,045 -16,785 -19,337 -81,955

Conversely, there has been an additional allowance for the installation of keypad/token meters of €28.2m. This

allowance will be adjusted to fully fund this activity. The keypad/token meter allowance was introduced to

facilitate the introduction of prepayment metering as a result of the economic issues that faced customers, this

resulted in approximately 63,000 keypad/token meters being installed.

Meter reading expenditure is 5% below allowance (€-3.0m), .

The benefits of the implementation of the contract meter readers has been reduced by the additional resources

required to process a significant increase in the number of meter readings being provided directly to the

company by customers. In some cases, manual intervention is required to validate incorrect / missing

information provided through Interactive Voice recognition (IVR) or other automated processes to supplement

the meter readings that are being collected by the meter reading contractors. There are still a significant

number of meter readings that require validation (some 156,000 in 2013 as per DSO document DH12 section

2.4).

It is expected that as the processes mature then there will be a reduced requirement for these resources

especially once the Smart metering programme is implemented.

Going forward, SMART metering has the potential to significantly reduce manual intervention in terms of the

handling of the meter reads as well as the validation of erroneous reads. This will obviously depend upon the

capability of the SMART meters and their connectivity to the respective data collection systems.

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Meter Reading 12.4 12.4 12.2 11.0 11.9 11.1 11.6 10.7 11.4 11.4 59.6 56.6 -3.0 -5%

QH Data 1.5 1.3 1.5 1.3 1.5 1.4 1.4 1.3 1.4 1.4 7.4 6.6 -0.7 -10%

Data Aggregation 4.4 4.9 4.3 4.7 4.2 5.0 4.1 4.9 3.9 5.1 20.9 24.6 3.7 17%

Customer Meter Operation 2.3 2.9 2.3 3.4 2.2 2.5 2.2 3.0 2.1 3.0 11.1 14.8 3.7 34%

Keypad / Token Meter 0.1 0.1 4.6 4.6 8.3 8.3 6.9 6.9 8.3 8.3 28.2 28.2 0.0 0%

Metering 20.8 21.5 24.8 25.0 28.1 28.2 26.2 26.8 27.2 29.2 127.2 130.8 3.7 3%

PR3 Total2011 2012 2013 2014 2015

Page 36: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 31

The DSO has expressed concern in their document DH12 Metering, that there was insufficient allowance

provided at the setting of PR3 to cover for the increase in Revenue Protection work that was not foreseen at the

time. The Data Aggregation cost increase of €3.7m is also caused by the increased level of revenue protection

work being undertaken.

The following table (Table 2.16 - taken from the DSO document DF05 Response Report) shows the levels of

activity for Calls and Interference cases detected.

Table 2.16 : Revenue Protection activity8

2009 2011 2012 2013 2014 (ytd May)

Revenue Protection Calls 9,705 11,936* 8,885 8,247

Interference Cases Detected 609 1,226 1,574* 1,457 1,459

*2012 includes revenue protection pilot calls

The number of cases being dealt with has increased during the period but not along a linear relationship. 2009

data is provided by the DSO to give some context to the level of activity at the setting of PR3 allowances. This

has resulted in consequential increases in operating costs. The effectiveness of Revenue Protection extends

beyond just the cases that are discovered and recovery actions taken. A high profile Revenue Protection activity

can deter people from going down that route, if they know that there is a high likelihood that severe action will

be taken as opposed to knowing that nothing will happen if they try to tamper with their meter. We would expect

that the implementation of SMART meters, which requires a visit to each property and installation of meters with

anti-tamper facilities, should significantly reduce this, once these meters have a critical mass.

Given the economic conditions that have been prevalent over the last 5-6 years, the costs that the DSO are

incurring for its Metering revenue protection and Long Term No Access (LTNA ) related activities do not appear

excessive. The economic climate has resulted in increased financial pressure on customers which has in turn

increased perceived benefits of tampering with meters and thus an increased level of activity in pursuance of

the offenders.

2.2.4 Customer Service

(Allowed € 81.2m Outturn € 74.0m)

Table 2.17 presents a year on year comparison between allowed and actual/forecast expenditure on Customer

Service opex during PR3. This category includes Call Centre operations, Area Operations and Customer

Relations activities. Overall expenditure on Customer Service activities is forecast to be below the PR3

allowance by €7.2m (9%).

Table 2.17 : Customer Service spend in PR3

There has been an overall reduction in the Customer Service allowance of €1.1m from €83.3 to €81.2m to cater

for the difference in actual Connections from those assumed within the Final Determination (as previously

discussed in Section 2.2.3). This reduction has been applied through the PCust mechanism.

During the PR3 period there have been a number of significant changes impacting on the level of Customer

Services provided by the DSO. There has been a significant downturn in the level of new connections and

construction activity in general due to the economic downturn. There has been a significant increase in the

8 2010 data not available

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Call Centre 6.9 7.2 6.6 5.2 6.4 5.0 6.2 5.6 6.0 5.6 32.2 28.6 -3.6 -11%

Area Operations 9.5 9.6 9.3 8.0 9.0 8.3 8.7 8.6 8.5 8.6 45.0 43.1 -1.9 -4%

Customer Relations 0.8 0.3 0.8 0.4 0.8 0.6 0.8 0.6 0.7 0.4 4.0 2.3 -1.7 -43%

Customer Service 17.2 17.2 16.7 13.6 16.2 13.9 15.7 14.7 15.3 14.6 81.2 74.0 -7.2 -9%

2011 2012 2013 2014 2015 PR3 Total

Page 37: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 32

number of customer contacts due to weather related incidents, including an unusually high level of storm and

near storm category events at the end of 2013 and beginning of 2014. During the PR3 period there is a target

of speed of call answering of 83% and to date ESBN have achieved the target.

For the Area Operations element of this category, an underspending of €1.9m (4%) was primarily due to the

reduced connections activity.

For the customer relations activity there is also underspending against the PR3 allowance of €1.7m (43%).

During this time the company have continued to meet their customer service targets, summarised in Table 2.18

and Table 2.19 (as taken from the DSO document ‘DH19 Customer Service’).

Table 2.18 : DSO Customer Service Targets

Customer Service Area Service Target Measurement Process

Speed of telephone response 80% % of calls answered in 20secs inc IVR

Calls Abandoned <5% % of calls abandoned

Mystery shopper 80% External Survey Agency

Customer callback 80% External Survey Agency

Table 2.19 : DSO Customer Service Performance

Performance against Regulatory targets – NCCC Incentive mechanism

Year 2011 2012 2013 2014 2015

Targets

Speed of tel

response

83% 83% 83% 83% 83%

Abandonment Rate 5% 5% 5% 5% 5%

Mystery Caller 80% 80% 80% 80% 80%

Callback Survey 80% 80% 80% 80% 80%

Outcome Forecast

Speed of tel

response

90% 89% 89% 85% 80%

Abandonment Rate 5% 3% 4% 5% 5%

Mystery Caller 85% 83% 82% 80% 80%

Callback Survey 86% 86% 91% 91% 80%

There has been an underspending on the Customer Service activity, it is not possible to quantify with any

certainty if the reduced cost is due to efficiencies or reduced activity due to the economic slow down and

reduced connections activity.

2.2.5 Provision of Information

(Allowed € 74.1m Outturn € 52.6m)

Table 2.20 presents a year on year comparison between allowed and actual/forecast expenditure on Provision

of Information opex during PR3. This category consists of DUoS Billing and Accounts, Market Retail Sector

Operation (MRSO) and Market Opening activities. Overall expenditure on Provision of Information activities is

forecast to be below the PR3 allowance by €21.5m (29%).

Page 38: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 33

Table 2.20 : Provision of Information spend in PR3

There has been a reduction in the Provision of Information allowance to cater for the difference in actual

Connections (as previously discussed in Section 2.2.3) from those assumed within the Final Determination.

This has been applied through the PCust facility and amounts to around €0.7m.

A significant portion of Provision of Information expenditure is charged from the Business Support Centre. A

change of pricing mechanism for IT Services was agreed in 2011 moving to a cost recovery mechanism rather

than market price cost. This contributed to lower costs for the DSO. The most significant element to this

reduction is the efficiencies associated with Market Opening activities. A number of strategies were employed

to provide cost reductions, such as headcount reductions, offshoring work where practicable, development of

longer term contracts to drive cost reductions, implementation of new technologies, such as cloud hosting, as

identified in the DSO document ‘DR05- TAO-DSO Historic Opex Interim Report’9.

2.2.6 Corporate charges

(Allowed € 64.3m Outturn € 54.0m)

Table 2.21 presents a year on year comparison between allowed and actual/forecast expenditure on Corporate

Charges opex during PR3. This category includes Company Wide Costs and Corporate Charges and Affairs.

Table 2.21 : Corporate Charges spend in PR3

Overall expenditure on Corporate Charges is forecast to be below the PR3 allowance by €10.3m (16%).

There are a number of central activities (corporate charges and affairs) that are carried out on behalf of the

DSO and recharged to the company. These costs are charged to the TAO and DSO on the basis of a 17:83

ratio. Initiatives to reduce these costs have resulted in an underspend of €10.3m (16%). It is not possible to

reliably compare these costs with other companies due to the different corporate structures/governance and

charging regimes that exist.

2.2.7 Sustainability and R&D

(Allowed € 18.2m Outturn € 8.0m)

Table 2.22 presents a year on year comparison between allowed and actual/forecast expenditure on

Sustainability and R&D opex during PR3.

Table 2.22 : Sustainability and R&D spend in PR3

9 Page 32

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Duos Billing & Accounts 1.3 1.3 1.3 1.3 1.2 1.1 1.2 1.2 1.2 1.3 6.2 6.1 -0.1 -2%

MRSO 1.9 1.4 1.9 1.2 1.9 1.4 1.8 1.2 1.8 1.7 9.3 7.0 -2.4 -26%

Market Opening 12.2 8.8 11.9 7.6 11.7 7.4 11.5 7.8 11.3 7.9 58.6 39.6 -19.0 -32%

Provision Of Information 15.4 11.5 15.1 10.1 14.8 10.0 14.6 10.2 14.3 10.9 74.1 52.6 -21.5 -29%

PR3 Total2011 2012 2013 2014 2015

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Company Wide Costs 1.9 2.4 1.9 2.4 1.8 2.2 1.8 1.7 1.7 2.0 9.2 10.6 1.4 15%

Corporate Charges & Affairs 11.6 9.2 11.3 8.6 11.0 8.0 10.7 8.5 10.5 9.0 55.2 43.4 -11.7 -21%

Corporate Costs 13.5 11.6 13.2 11.0 12.9 10.2 12.5 10.2 12.2 11.0 64.3 54.0 -10.3 -16%

2011 2012 2013 2014 2015 PR3 Total

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Sustainability 3.0 0.9 3.0 2.0 3.0 1.1 3.0 1.5 3.0 2.5 14.8 8.0 -6.8 -46%

R & D 0.7 0.0 0.7 0.0 0.7 0.0 0.7 0.0 0.7 0.0 3.4 0.0 -3.4 -100%

Sustainability & R & D 3.6 0.9 3.6 2.0 3.6 1.1 3.6 1.5 3.6 2.5 18.2 8.0 -10.2 -56%

PR3 Total2011 2012 2013 2014 2015

Page 39: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 34

Overall expenditure on sustainability and R&D is forecast to be below the PR3 allowance by €10.2m (56%

below allowance). The DSO have indicated that the CER in their document (CER 14/057) have allocated €6.0m

of the total allowance of €18.2m towards an Electric vehicles pilot project. We understand that internally ESBN

have allocated this to ESBN Innovation.. We have not been provided with any information of the level of

expenditure on this project. As the decision paper from the CER was on 5th March 2014 we conclude that the

expenditure on this project is minimal. We consider that these underspends could therefore be classed as a

windfall gain as the intended activities have not been carried out.

2.2.8 Other

(Allowed € 51.0m Outturn € 69.7m)

Table 2.23 presents a year on year comparison between allowed and actual/forecast expenditure on Other opex

during PR3.

Table 2.23 : Other spend in PR3

Overall expenditure on Other opex items is forecast to exceed the PR3 allowance by €18.7m (37%).

There are several factors which impact on the variance in ‘Other’ expenditure. The DSO have indicated in a

number of discussions that costs for Network Assets and Employers/ Public Liability Insurance is passed from

Corporate centre and relates to increases in the Network Asset base. This does not sufficiently account for the

increases and subsequent decreases in the charges during the PR3 period.

The legal costs have risen over the period with an 11% overall increase over allowed revenue, which may be

expected to rise given the increased legal workload associated with the increased revenue protection work that

the DSO is experiencing as customers find themselves under economic pressure.

The increase in Health and Safety costs is due to the recent severe safety incidents that have occurred within

the DSO activities. Following a full review of the Health and Safety processes and procedures a significant

increase in the level of expenditure (which is over and above the PR3 allowance) was required to ensure that

the processes and procedures and staff training / education are fit for purpose. This increase is expected to

continue into PR4.

2.3 Non Controllable Costs

Table 2.24 presents a year on year comparison between allowed and actual/forecast expenditure on Non-

Controllable opex during PR3.

Table 2.24 : Non Controllable spend in PR3

This category includes pass-through costs such as network rates and the CER Levy. The DSO has little/no

control over these costs. The actual values for these two items are factored into the DUoS calculations, hence

the allowance is adjusted in line with the actual/expected spend.

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Insurance 2.5 1.8 2.5 5.0 2.5 3.4 2.5 4.2 2.5 3.4 12.5 17.8 5.3 42%

Legal 2.3 2.1 2.3 2.2 2.3 2.6 2.3 2.9 2.3 2.9 11.3 12.6 1.3 11%

Pension 1.7 2.7 1.6 1.7 1.6 2.0 1.5 2.0 1.5 1.4 7.9 9.7 1.8 23%

Environmental 1.1 1.6 1.1 1.2 1.1 1.3 1.1 1.2 1.1 1.2 5.5 6.4 0.9 16%

Health & Safety 2.9 1.7 2.8 1.8 2.7 2.4 2.7 5.2 2.6 8.3 13.7 19.4 5.7 41%

Misc 0.0 0.9 0.0 1.6 0.0 0.1 0.0 1.0 0.0 0.3 0.0 3.8 3.8

Other 10.5 10.7 10.3 13.4 10.2 11.8 10.1 16.4 10.0 17.4 51.0 69.7 18.7 37%

2011 2012 2013 2014 2015 PR3 Total

DSO Operating Costs

(€m 2009 Prices) allowed actual allowed actual allowed actual allowed actual allowed actual allowed forecast variance %

Network Rates 35.3 35.3 34.2 34.2 34.1 34.1 37.6 37.6 42.1 42.1 183.4 183.4 0.0 0%

Cer Levy 1.6 1.6 1.9 1.9 2.2 2.2 2.0 2.0 2.1 2.1 9.9 9.9 0.0 0%

Non Controllable 36.9 36.9 36.1 36.1 36.4 36.4 39.6 39.6 44.2 44.2 193.3 193.3 0.0 0%

PR3 Total2011 2012 2013 2014 2015

Page 40: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 35

2.4 Conclusions and Findings

The overspend on Network Operations and Maintenance is predominantly driven by planned maintenance

which is expected to incur a 20% overspend during PR3 (€39.1m) due to significant expenditure on Tree cutting

over and above the allowance. This is partially negated by an underspend of €20.5m on fault maintenance.

A significant portion of Provision of Information expenditure is charged from the Business Support Centre. A

change of pricing mechanism for IT Services was agreed in 2011 moving to a cost recovery mechanism rather

than market price cost. This contributed to lower costs for the DSO. The most significant element to this

reduction is the efficiencies associated with Market Opening activities. A number of strategies were employed

to provide cost reductions, such as headcount reductions, offshoring work where practicable, development of

longer term contracts to drive cost reductions, implementation of new technologies such as cloud hosting.

Overall expenditure on other opex items is forecast to exceed the PR3 allowance by €18.7m (37%). There are

several factors which impact on the variance in ‘Other’ expenditure:

The DSO have indicated in a number of discussions that costs for Network Assets and Employers/ Public

Liability Insurance are passed from Corporate centre and relate to increases in the Network Asset base.

This does not sufficiently account for the increases and subsequent decreases in the charges during the

PR3 period.

The legal costs would be expected to rise given the increased revenue protection work that the DSO is

experiencing as customers find themselves under economic pressure.

The increase in Health and Safety costs is due to the recent severe safety incidents that have occurred

within the DSO activities. There has been a full review of the Health and Safety processes and procedures

necessitating a significant increase in the level of expenditure (which is over and above the PR3 allowance)

in order to put the requisite changes in place to ensure that the processes and procedures and staff

training / education are in place are fit for purpose from a Health and Safety perspective. This increase is

expected to continue into PR4.

The DSO has faced some major challenges during PR3, particularly the economic downturn and the significant

increase in severe weather events, neither of which could be foreseen at the setting of the PR3 determination.

The DSO has not provided a view of their Asset condition at a company-wide level. This is a concern and

should be addressed during PR4. The high level view will allow the DSO to understand the long term effect of

maintenance levels on their asset condition and allow it to take a more informed long term approach to

maintenance and Capex replacement programmes.

The DSO has achieved the cost targets set out in the CER decision paper however we are of the opinion that it

has not achieved the additional cost efficiencies required by the CER. It is our view that the company has

received windfall gains of €10.2m on Sustainability and R&D activities.

Page 41: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 36

3. Review of PR4 Operating Expenditure

The objective of the CER in setting allowed opex is to ensure that expenditure is efficient and that efficiency

improvements within the DSO continue to be made, to the benefit of customers. This should result in setting the

companies challenging but realistic and achievable targets and incentives, all the while moving closer to

international best practice. In this section of the report we review the DSO’s proposed opex for the PR4 period

and advise on any adjustments that we believe are necessary in order to allow the CER to determine the

appropriate opex allowances for the PR4 period covering the years 2016 to 2020 for an efficient company

operating in Ireland.

The data presented, analysed and commented on in this report is based on data provided by the DSO to the

CER and Jacobs via:

The return of Questionnaires issued by the CER in July 2014 and associated information papers and

network plans

Ongoing communications with Jacobs and the CER following the submission of the forecast PR4 data in

November 2014.

Background information from CER on previous price reviews

It should be noted that 2011 to 2013 performance and cost data is based on actual recorded values. Unless

stated otherwise, the 2014 and 2015 performance and cost data is based on the original forecast data

submitted at the time of the initial forecast submission. Where updated 2014 and 2015 information has been

made available by the DSO and this information differs significantly from the initial forecast submission this

information been taken into consideration when outlining our proposed allowances.

3.1 General / Overview

Excluding Commercial Costs, the DSO has proposed a total opex allowance for PR4 of €1506.0m, which

represents an increase of €332.3m (28%) from PR3 forecast outturn.

The total proposed opex allowance is broken down as follows:

Proposed controllable opex of €1219.9 (an increase of €245.0m - 25% - from PR3 outturn)

Proposed non-controllable opex of €286.1m (an increase of €87.2m - 44% - from PR3 outturn)

A breakdown of the DSO’s proposed expenditure is provided below in Table 3.1. Commercial Costs are

included in this table for completeness but are not discussed further in this report due to their non-controllable

nature.

Table 3.1 : DSO Proposed Opex Allowances for PR4

Page 42: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 37

* The PR3 outturn presented above is different from that reported in Section 2 of this report due to a change in

price base from 2009 to 2014 utilising HICP rates.

The DSO has provided a significant amount of narrative on the proposed PR4 forecast operating costs. We

have reviewed the submissions provided and in some cases requested additional information, to clarify

justifications or provide additional supporting information. As a result of our reviews, we have recommended a

reduction of €143.9m to the level of operating expenditure proposed by the DSO. All of our recommended

€143.9m reduction to the DSO’s opex allowance is identified in controllable costs only.

Table 3.2 below provides an annual view of our proposed allowances.

Table 3.2 : High level comparison of DSO Opex Allowances for PR4

Table 3.3 provides a summary of our proposed DSO opex allowance for PR4 compared to the DSO’s original

proposition.

Proposed Operating Costs

(€ 2014 Prices)

Network O&M Allowance 507.8 94.3 114.4 117.9 116.0 116.7 116.1 581.1 73.3 14%

Asset Management Allowance 66.6 13.7 14.0 14.2 14.4 14.7 15.0 72.3 5.7 9%

Metering Allowance 134.6 29.0 40.4 38.0 34.2 33.9 33.6 180.1 45.5 34%

Customer Service Allowance 76.2 14.2 18.4 17.8 17.8 18.1 18.2 90.2 14.1 18%

Provision of Information Allowance 54.2 10.2 12.4 12.4 12.9 12.8 12.8 63.3 9.1 17%

Corporate Costs Allowance 55.6 10.5 10.3 10.3 10.3 10.3 10.3 51.4 -4.2 -7%

Telecoms Allowance 0.0 0.0 13.2 13.5 13.6 13.7 13.8 67.7 67.7 -

Sustainability & R&D Allowance 8.2 1.1 2.3 2.6 3.4 3.7 3.6 15.6 7.4 91%

Other Allowance 71.7 12.1 22.7 21.7 18.9 17.8 17.1 98.2 26.5 37%

Controllable Allowance 974.8 185.1 248.1 248.2 241.4 241.5 240.5 1,219.9 245.0 25%

Network Rates 188.7 35.0 46.9 51.0 55.0 59.1 63.1 275.1 86.4 46%

CER Levy 10.2 2.3 2.2 2.2 2.2 2.2 2.2 11.0 0.8 8%

Non Controllable Allowance 198.9 37.3 49.1 53.2 57.2 61.3 65.3 286.1 87.2 44%

Total Allowance (excl. Depreciation) 1,173.7 222.4 297.3 301.4 298.7 302.8 305.8 1,506.0 332.3 28%

DSO Proposed Operating Costs

PR3 2013 2016 2017 2018Variance

%2019 2020 PR4

Variance

PR4-PR3

Propsed Operating Costs

(€ 2014 Prices)

Network O&M Allowance 507.8 94.3 114.4 117.9 116.0 116.7 116.1 581.1 73.3 14% -43.4 537.7 -7%

Asset Management Allowance 66.6 13.7 14.0 14.2 14.4 14.7 15.0 72.3 5.7 9% 0.0 72.3 0%

Metering Allowance 134.6 29.0 40.4 38.0 34.2 33.9 33.6 180.1 45.5 34% -21.3 158.8 -12%

Customer Service Allowance 76.2 14.2 18.4 17.8 17.8 18.1 18.2 90.2 14.1 18% -3.2 87.0 -4%

Provision of Information Allowance 54.2 10.2 12.4 12.4 12.9 12.8 12.8 63.3 9.1 17% -2.9 60.4 -5%

Corporate Costs Allowance 55.6 10.5 10.3 10.3 10.3 10.3 10.3 51.4 -4.2 -7% -3.0 48.4 -6%

Telecoms Allowance 0.0 0.0 13.2 13.5 13.6 13.7 13.8 67.7 67.7 - -48.4 19.3 -71%

Sustainability & R&D Allowance 8.2 1.1 2.3 2.6 3.4 3.7 3.6 15.6 7.4 91% -4.5 11.1 -29%

Other Allowance 71.7 12.1 22.7 21.7 18.9 17.8 17.1 98.2 26.5 37% -17.2 81.0 -18%

Controllable Allowance 974.8 185.1 248.1 248.2 241.4 241.5 240.5 1,219.9 245.0 25% -143.9 1,076.0 -12%

Network Rates 188.7 35.0 46.9 51.0 55.0 59.1 63.1 275.1 86.4 46% 0.0 275.1 0%

CER Levy 10.2 2.3 2.2 2.2 2.2 2.2 2.2 11.0 0.8 8% 0.0 11.0 0%

Non Controllable Allowance 198.9 37.3 49.1 53.2 57.2 61.3 65.3 286.1 87.2 44% 0.0 286.1 0%

Total Allowance (excl. Depreciation) 1,173.7 222.4 297.3 301.4 298.7 302.8 305.8 1,506.0 332.3 28% -143.9 1,362.1 -10%

DSO Proposed Operating Costs

2019 2020 PR4Variance

PR4-PR3PR3 2013 2016 2017 2018

Variance

%

Jacobs Proposed Operating

Costs

Variance

to PR3

PR4

Allowed

PR4

Changes

Page 43: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 38

Table 3.3 : Jacobs Proposed DSO Opex Adjustments for PR4

The rationale behind the DSO’s proposed allowances and our adjustments to those proposals is provided within

each sub-section below.

3.2 Controllable Costs

Controllable costs are categorised as follows:

Network O&M – The day to day System Control covering the Distribution Control Centres in Cork and

Dublin, along with planned and fault maintenance of the Network Assets.

Asset Management – The development of Policies and Asset strategies, along with payments for

wayleaves, forestry and mast interference payments.

Metering – The DSO provides a range of services related to metering to all stakeholders including

electricity supply companies and customers. These services include the management of these assets,

collection and aggregation of metering data and revenue protection services.

Customer Service – Included within this category are the costs of the Customer Care Centre, Scheduling

Support Centre, Customer Relations and Area Operations.

Provision of Information – The costs in this category are associated with DUoS billing and accounts

receivable, Meter Registration System Operator, Market System Support Costs.

Corporate costs – The costs within this category are from Corporate Centre for services such as CEO,

Group Finance, Corporate affairs.

Telecomm – The provision of telecomms equipment to monitor and operate the DSO Network remotely.

Sustainability and R&D – The costs in this category relate to initiatives to carry out sustainability and R&D

activities.

Other – This includes items such as Insurance, Legal, Environmental, and Health and Safety.

We address each of these categories in the sub-sections below after a brief section on Manpower.

3.2.1 Overall Manpower

The company has identified the following manpower related costs in its submissions.

Table 3.4 provides a comparison between the headcounts for PR3 and PR4. The DSO is forecasting a total of

108 additional staff over the PR4 period compared to the position at the end of PR3. We can see from this table

that the DSO are forecasting for PR4 to keep the cost rate per full time employee (FTE) in line with the levels of

Proposed Operating Costs

(€ 2014 Prices)

Network O&M Allowance 507.8 94.3 105.8 109.2 107.3 108.0 107.4 537.7 29.9 6%

Asset Management Allowance 66.6 13.7 14.0 14.2 14.4 14.7 15.0 72.3 5.7 9%

Metering Allowance 134.6 29.0 32.7 33.0 30.9 31.0 31.2 158.8 24.2 18%

Customer Service Allowance 76.2 14.2 17.3 17.5 17.4 17.4 17.5 87.0 10.9 14%

Provision of Information Allowance 54.2 10.2 12.3 12.4 12.0 11.9 11.8 60.4 6.2 11%

Corporate Costs Allowance 55.6 10.5 9.7 9.7 9.7 9.7 9.7 48.4 -7.2 -13%

Telecoms Allowance 0.0 0.0 3.5 3.8 3.9 4.0 4.1 19.3 19.3 -

Sustainability & R&D Allowance 8.2 1.1 2.3 2.6 1.9 2.2 2.1 11.1 2.9 36%

Other Allowance 71.7 12.1 20.2 18.7 15.5 13.9 12.7 81.0 9.3 13%

Controllable Allowance 974.8 185.1 217.9 221.0 213.0 212.6 211.6 1,076.0 101.2 10%

Network Rates 188.7 35.0 46.9 51.0 55.0 59.1 63.1 275.1 86.4 46%

CER Levy 10.2 2.3 2.2 2.2 2.2 2.2 2.2 11.0 0.8 8%

Non Controllable Allowance 198.9 37.3 49.1 53.2 57.2 61.3 65.3 286.1 87.2 44%

Total Allowance (excl. Depreciation) 1,173.7 222.4 267.0 274.2 270.2 273.9 276.9 1,362.1 188.4 16%

2016PR3 2013

Jacobs Proposed Operating Costs

Variance

PR4-PR3

Variance

%PR42020201920182017

Page 44: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 39

PR3. This table would lead us to conclude that the DSO is managing the costs of its staff. These numbers also

include 105 FTE saving10 that will be achieved due to the implementation of IT driven solutions in front line and

back office staff.

Table 3.4 : Comparison of Headcount Costs (PR3 v PR4) (TAO and DSO combined)

PR3 PR4

2011 2012 2013 2014 2015 Average 2016 2017 2018 2019 2020 Average

Payroll €m (Table 3.4.1)

281 341 248 256 251 275 274 275 271 269 264 271

Headcount (Table 4.8.1)

3391 3273 3049 3062 3145 3184 3299 3329 3300 3276 3257 3292

Costs per FTE €k 83 104 81 83 80 86 83 83 82 82 81 82

n.b. This table includes DSO and TAO Staff and Costs – on the understanding that there is no significant

difference between the staff on DSO and TAO duties (this was verbally confirmed with DSO/TAO during

workshops).

In discussions and workshops with the DSO and the regulator, the DSO have indicated that there will be

additional resources used from Contractors, where appropriate, to carry out activities to support the in- house

staff.

3.2.2 Network Operations and Maintenance

DSO requested €581.1m, Recommended reduction €-43.4m, Allowance recommended €537.7m

Table 3.5 presents a year on year comparison between the DSO’s proposed Network Operations and

Maintenance opex allowance for PR4 and Jacobs proposed opex allowance for PR4.

The DSO has proposed a total allowance of €581.1m over the PR4 period for Network Operations and

Maintenance opex. This is €73.3m in excess of the spend in PR3, partly due to changes in practices and partly

due to intentional deferrals from PR3 as a cost saving measure. This increase is predominantly driven by

increased Planned Maintenance expenditure on HV stations. We have made reductions of €41.5m in this

activity and a reduction of €1.9m in system control, as shown in table 3.5 below, reducing the total allowance to

€537.7m.

Table 3.5 : Summary of Jacobs Proposed Network O&M Opex Allowance for PR4

The DSO has proposed a total allowance of €83.0m over the PR4 period for System Control opex. This is

€5.3m in excess of the spend in PR3. Within System Control, the DSO have identified a number of capex

10 DF06 DSO forecast Capex response Table11

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed System Control 77.7 15.6 16.4 16.6 16.7 16.7 16.7 83.0 5.3 7%

Jacobs Proposed Changes -0.3 -0.4 -0.4 -0.4 -0.4 -1.9 -1.9

Jacobs Proposed System Control Allowance 77.7 15.6 16.1 16.2 16.3 16.3 16.3 81.1 3.4 4%

DSO Proposed Planned Maintenance 244.2 43.8 64.9 67.7 66.0 66.7 66.0 331.4 87.2 36%

Jacobs Proposed Changes -8.3 -8.3 -8.3 -8.3 -8.3 -41.5 -41.5

Jacobs Proposed Planned Maintenance Allowance 244.2 43.8 56.6 59.4 57.7 58.4 57.7 289.9 45.7 19%

DSO Proposed Fault Maintenance 185.8 35.0 33.1 33.5 33.3 33.3 33.5 166.7 -19.1 -10%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Fault Maintenance Allowance 185.8 35.0 33.1 33.5 33.3 33.3 33.5 166.7 -19.1 -10%

DSO Proposed Network O&M Total 507.8 94.3 114.4 117.9 116.0 116.7 116.1 581.1 73.3 14%

Jacobs Proposed Changes -8.6 -8.7 -8.7 -8.7 -8.7 -43.4 -43.4

Jacobs Proposed Network O&M Allowance 507.8 94.3 105.8 109.2 107.3 108.0 107.4 537.7 29.9 6%

PR4

Variance

PR4-PR3

Variance

%PR3 2013 2016 2017 2018 2019 2020

Page 45: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 40

investments that will be required to infrastructure systems based upon 3 components; SCADA, OMS and

Control Centre. The DSO has also identified a need for LV system mapping that is currently not available. We

have considered the request and have proposed an increase of €3.4m in excess of the PR3 expenditure as we

would expect that the company will have reductions in some of the redundant systems and be incentivised to

seek efficiencies.

The DSO has proposed a total allowance of €331.4m over the PR4 period for Planned Maintenance. The DSO

are seeking €87.2m greater allowance for Planned Maintenance in PR4 compared to PR3. The key contributor

to this increase is Station Maintenance, accounting for €72m of the increase and comprising of €43m for HV

station maintenance and €29.0m for MV/LV substation/minipillar inspections and follow ups. This increase is

justified by the DSO on the basis that:

Additional work in the form of condition monitoring and recording, to support the introduction of condition

based strategies, will result in more optimum maintenance in the longer term.

Additional overhauls that were not carried out in PR3 due to insufficient funding will be required in PR4

In papers DF03 and presentations made by the company, information was provided on the approach and costs

of major changes to the planned maintenance with changes to the frequency of inspections and testing and

major overhauls of some equipment like the Magnefix units which have had a number of failures. Following the

failures there has been discharge testing carried out to identify possible future failures. The report indicates that

93% were in good condition, with 55 units needing overhaul and 40 units in poor condition and needing to be

replaced (this is following a period where the units were monitored from 2006). Based on this there appears to

be a condition based approach recently introduced which manages the population reasonably well identifying

the condition and where there is a need for replacement or overhaul. However the company have stated11 that

they are moving away from Condition Based Maintenance for their Magnefix MV switchgear and back to

cyclical, which is a reversion from their policy in 2006. The cost of the Magnefix overhauls in the submission is

€16.5m. They have 2200 units on the system and plan to replace 400 in PR4 reducing the population to 1800.

With a 4 year overhaul that equates to around €7500 per unit in PR4. The switchgear is encased epoxy resin

and the failures appear to be due to tracking due to surface dirt and moisture building up over time, and also

contact resistance causing burning to insulation, again over a long period of time. Both of these can and have

been targeted in the discharge testing and could also be monitored using thermal imaging equipment.

The costs implied in this programme seem excessive and the monitoring approach would ensure only targeted

actions would be required. In addition the €7,500 per unit seems extremely high as some units will only require

cleaning of surface contamination and checking contacts for corrosion and cleaning.

Within DF03 there is reference to benchmarking to GB DNO’s which was also stated in the PR3 submission in

2009, and as stated in the 2009 SKM report this would be expected to reduce overall costs not increase them.

The requested allowance for PR3 €247m, and the allowance was recommended as €198m, partially due to an

underspend on allowances in PR2 on substation maintenance by €18m. The outturn planned maintenance in

PR3 is €244m, broadly in line with the PR3 requested allowance and well in excess of the allowed revenue.

The DSO are proposing the development of Condition Based Maintenance (CBM), whilst we recognise the need

and benefits of CBM strategies (which in themselves are usually justified as a cost reduction mechanism). The

DSO are only proposing a pilot study at Distribution Level citing that there is ‘not yet a firm business case or

technological maturity’12. Given that Condition Based Maintenance methodology has been in existence for some

time, it is surprising to find that the DSO consider this new technology. The submission indicates that in moving

to condition based maintenance there will be considerably higher costs on top of the existing cyclic

maintenance. The cost increases being driven by the increased data management and identifying appropriate

systems that the new methodology will require. The normal approach is to analyse the condition failure

mechanisms and target the monitoring of those areas where the information is gathered more efficiently. In

addition, some aspects of condition monitoring remove the need to remove plant from service and carry out

detailed intrusive overhaul. Overall the approach taken does not appear to justify the major increases in costs

11 DR05 – TAO-DSO Forecast interim report p33 12 DR05 – TAO-DSO Forecast interim report p37

Page 46: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 41

for this activity. This inconsistency of strategy and approach has led us to believe that there is an inconsistent

and uncoordinated overall approach to this activity.

We would expect that there would be savings from reduced maintenance during the pilot and expected rollout.

There has been little evidence in the PR4 proposed allowances of the potential savings that would be expected

to arise from this activity. We would also expect to see significant changes to the levels of maintenance carried

out in PR5 through condition based maintenance and a better understanding of the overall condition of the

assets.

As a result of this we have recommended a reduction in Planned Maintenance Allowance by €41.5m, giving an

allowance of €289.9m.

The Tree cutting activity is also a significant contribution to the Planned Maintenance activity, with a PR4

forecast of €112.8m against a spend of €110.8 (2014 prices) in PR3. The PR3 spend is in excess of the PR3

allowance and is discussed in the Historic Opex report. We have proposed no change to the level of tree

cutting allowance in PR4 from the submission provided by the DSO, however we would recommend that

additional reporting metrics are developed in PR4 to determine what the unit rates are for the work carried out

(in €/km, rather than per “block”), in order to gain a better understanding of the efficiency or the service being

provided.

The DSO has proposed a total allowance of €166.7m over the PR4 period for Fault Maintenance. This equates

to €19.1m less than the PR3 expected outturn. The fault costs proposed are broadly in line with the expected

spend in PR3 after adjusting for Storm Darwin costs of €23.7m.

3.2.3 Asset Management

DSO requested €72.3m, Recommended reduction €0.0m, Allowance recommended €72.3m

Table 3.6 presents a year on year comparison between the DSO’s proposed Asset Management opex

allowance for PR4 and Jacobs proposed opex allowance for PR4.

The DSO has proposed a total allowance of €72.3m over the PR4 period for Asset Management opex. This is

€5.7m in excess of the spend in PR3.

Table 3.6 : Jacobs Proposed Asset Management Opex Allowance for PR4

The costs incurred in this category are for the costs of the Asset managers and their teams, who have the

responsibility for the determination of policies and management of the various assets under DSO control. The

PR4 costs for the Asset Management Teams seem reasonable and are in line with the annual costs for the

latter part of PR3. We therefore do not propose any changes to the DSO proposed values. The Forestry and

Wayleave costs have been allowed in full as we recognise that there is pressure from environmental lobby

groups and we consider the level of allowance going forward is appropriate.

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Asset Management 47.5 9.7 9.4 9.6 9.6 9.6 9.7 47.9 0.4 1%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Asset Management Allowance 47.5 9.7 9.4 9.6 9.6 9.6 9.7 47.9 0.4 1%

DSO Proposed Forestry & Wayleaves 19.1 4.0 4.5 4.7 4.8 5.0 5.3 24.4 5.3 28%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Forestry and Wayleaves Allowance 19.1 4.0 4.5 4.7 4.8 5.0 5.3 24.4 5.3 28%

DSO Proposed Asset Management 66.6 13.7 14.0 14.2 14.4 14.7 15.0 72.3 5.7 9%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

66.6 13.7 14.0 14.2 14.4 14.7 15.0 72.3 5.7 9%Jacobs Proposed Asset Management and Forestry

Allowance

PR4

Variance

PR4-PR3

Variance

%PR3 2013 2016 2017 2018 2019 2020

Page 47: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 42

3.2.4 Metering

DSO requested €180.1m, Recommended reduction €21.3m, Allowance recommended €158.8m

Table 3.7 presents a year on year comparison between the DSO’s proposed Metering opex allowance for PR4

and Jacobs’ proposed opex allowance for PR4. Overall, the DSO are requesting an increase in metering costs

of €45.5m (34%) over the costs forecast for PR3, raising the PR4 allowance to €180.1m.

Table 3.7 : Jacobs Proposed Metering Opex Allowance for PR4

For Meter Reading, Quarter Hourly (QH) data and Data Aggregation, the recommendation is to carry forward

the allowance in line with the DSO proposals. The DSO is forecasting a consistent growth in the number of QH

Meters being installed in PR4 as shown in Table 3.8 below. Currently within PR3 there is a mechanism to

correct for actual meter installation and customer numbers. The expectation is that this will continue and any

such changes in the forecast connections and meter numbers within PR4 will be corrected and the above

allowances adjusted.

Table 3.8 : QH meters installed forecast13

2014 2015 2016 2017 2018 2019 2020

Total QH meters installed 13,750 14,600 14,968 15,328 15,688 16,048 16,048

The main driver for the increase in Metering expenditure (compared to PR3) is due to Customer Meter

Operation (an increase of €13.5m) and Keypad/Token meters (an increase of €26.4m).

The Customer Meter Operation includes Revenue Protection activities. There has been increased activity in

this area in PR3 (see Table 2.16) and we consider that this is likely to continue in PR4. The DSO have also

identified that there will be a significant increase in the Major Meter Testing (MMT) activity in PR4 compared to

the 33% of the targeted activity in PR3 as there is now a requirement to manage and install Power Quality

Meters on all Distribution connected generator sites. We have accepted the DSO’s proposed opex allowance

for Customer Meter Operation on this basis.

For the additional metering costs, the DSO has indicated that the latest meters with their anti-tampering

capabilities are significantly more expensive than the current meters. However when reviewing the current unit

costs as illustrated in Table 3.9 below, it can be seen that there are significant increases in unit costs in PR4

without the increased costs of the new keypad/token meters. The DSO has proposed an expenditure of €55.3m

on keypad/token meters during PR3. Our PR4 proposed allowance has been based on revised volumes and a

13 DH12 – Metering.pdf p10 and DF12 Metering.pdf p7

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Meter Reading 58.3 11.3 11.6 11.7 11.6 11.6 11.7 58.2 -0.1 0%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Meter Reading Allowance 58.3 11.3 11.6 11.7 11.6 11.6 11.7 58.2 -0.1 0%

DSO Proposed QH Data 6.8 1.4 1.8 1.8 1.8 1.8 1.9 9.2 2.3 34%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed QH Data Allowance 6.8 1.4 1.8 1.8 1.8 1.8 1.9 9.2 2.3 34%

DSO Proposed Data Aggregation 25.3 5.1 5.5 5.7 5.8 5.8 5.9 28.6 3.3 13%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Data Aggregation Allowance 25.3 5.1 5.5 5.7 5.8 5.8 5.9 28.6 3.3 13%

DSO Proposed Customer Meter Operation 15.3 2.5 5.8 5.8 5.6 5.7 5.8 28.8 13.5 88%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Customer Meter Operation Allowance 15.3 2.5 5.8 5.8 5.6 5.7 5.8 28.8 13.5 88%

DSO Proposed Keypad/Token Allowance 28.9 8.5 15.7 13.0 9.3 8.9 8.4 55.3 26.4 91%

Jacobs Proposed Changes -7.7 -5.0 -3.3 -2.9 -2.4 -21.3 -21.3

Jacobs Proposed Keypad/Token Allowance 28.9 8.5 8.0 8.0 6.0 6.0 6.0 34.0 5.1 18%

DSO Proposed Metering 134.6 29.0 40.4 38.0 34.2 33.9 33.6 180.1 45.5 34%

Jacobs Proposed Changes -7.7 -5.0 -3.3 -2.9 -2.4 -21.3 -21.3

Jacobs Proposed Metering Allowance 134.6 29.0 32.7 33.0 30.9 31.0 31.2 158.8 24.2 18%

PR3 2013 2016 2017 2018 2019 2020 PR4

Variance

PR4-PR3

Variance

%

Page 48: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 43

unit cost of €400 per keypad/token meter installation, during workshop discussions with the DSO. This results

in a total expenditure of €34.0m, a reduction of €21.3m.

Table 3.9 : Keypad / Token Meter Unit Costs (PR3 v PR4) all in 2014 prices.

DSO view

PR3 PR4

2011 2012 2013 2014 2015 Total 2016 2017 2018 2019 2020 Total

Meters (000) 0.7 14.7 26.6 20.8 17.5 80.3 25 22 15 15 15 92.5

DSO Cost €m 0.1 4.7 8.5 7.1 8.6 29.0 15.7 13 9.3 ‘8.9 8.4 55.3

€ per meter 137.8 318.7 317.9 341.3 493.0 360.7 615.7 590.9 620 593.3 560 597.8

Jacobs view

Revised volumes of meters (000s)

20.0 20.0 15.0 15.0 15.0 85

Allowance at €400 per meter

8.0 8.0 6.0 6.0 6.0 34

3.2.5 Customer Service

DSO requested €90.2m, Recommended reduction €-3.2m, Allowance recommended €87.0m.

Table 3.10 presents a year on year comparison between the DSO’s proposed Customer Service opex

allowance for PR4 and Jacobs’ proposed opex allowance for PR4.

Table 3.10 : Jacobs Proposed Customer Service Opex Allowance for PR4

The DSO has proposed a total allowance of €90.2m over the PR4 period, an increase of €14.1m (18%) on the

expected outturn spend in PR3.

The DSO has indicated14 that there will be additional expenditure within the Call Centre activity in order to

facilitate additional online services for customers, such as improved websites and development of social media

communications. This shows excellent awareness of customer trends and preferences, however the increase in

costs does not seem proportionate to the increase in services15. We are proposing an increase in allowance

over PR3 actual expenditure levels of 4% (i.e €1.2m) for this increase in services. This resultant allowance is in

excess of the current rate of expenditure for 2013/14 and forecast for 2015.

14 DF19 Customer Service 15 The increase in services is likely to be marginal as the website is already developed and it is understood to require only minor tweaks.

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Call Centre 29.4 5.1 6.3 6.4 6.4 6.5 6.5 32.1 2.7 9%

Jacobs Proposed Changes -0.3 -0.3 -0.3 -0.3 -0.3 -1.5 -1.5

Jacobs Proposed Call Centre Allowance 29.4 5.1 6.0 6.1 6.1 6.2 6.2 30.6 1.2 4%

DSO Proposed Area Operations 44.4 8.5 8.8 8.9 8.9 8.9 8.9 44.4 0.0 0%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Area Operations Allowance 44.4 8.5 8.8 8.9 8.9 8.9 8.9 44.4 0.0 0%

DSO Proposed Customer Relations 2.3 0.6 3.2 2.4 2.5 2.8 2.8 13.7 11.4 487%

Jacobs Proposed Changes -0.8 0.0 -0.1 -0.4 -0.4 -1.7 -1.7

Jacobs Proposed Customer Relations Allowance 2.3 0.6 2.4 2.4 2.4 2.4 2.4 12.0 9.7 414%

DSO Proposed Customer Service 76.2 14.2 18.4 17.8 17.8 18.1 18.2 90.2 14.1 18%

Jacobs Proposed Changes -1.1 -0.3 -0.4 -0.7 -0.7 -3.2 -3.2

Jacobs Proposed Customer Service Allowance 76.2 14.2 17.3 17.5 17.4 17.4 17.5 87.0 10.9 14%

2020 PR4

Variance

PR4-PR3

Variance

%PR3 2013 2016 2017 2018 2019

Page 49: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 44

The DSO has proposed an allowance of €44.4m for the Area Operations activity. This proposed allowance is

based upon current projections and is in line with PR3 levels of expenditure. We have accepted this proposal

with no changes.

The DSO has proposed an allowance of €13.7m for the Customer Relations activity, which is €11.4m (487%)

higher than PR3. The rationale for the increase is to cover for increased awareness and media campaigns for

public safety, power outages, vulnerable customers etc. The DSO have not identified what the benefits to the

company are for this level of expenditure (i.e. less customer calls, third party damage, thefts etc.). We propose

that the allowance is reduced to €2.4m per annum. This is still a significant increase over the expenditure in

PR3 and includes additional costs for an increased activity level for A18 transaction charges for repeat visits,

typically due to:-

no adults being present,

no access

and continued process with agreed appointments.

The DSO are also developing social media communications within the Call centre activity and we believe there

is an opportunity for synergies between the two activities to develop joint initiatives.

3.2.6 Provision of Information

DSO requested €63.3m, Recommended reduction €-2.9m, Allowance recommended €60.4m.

Table 3.11 presents a year on year comparison between the DSOs proposed Provision of Information opex

allowance for PR4 and Jacobs proposed opex allowance for PR4.

Table 3.11 : Jacobs Proposed Provision of Information Opex Allowance for PR4

The DSO has proposed a total PR4 allowance of €7.2m for DUoS billing (an increase of €0.9m or 15% on PR3)

and €9.2m for MRSO (an increase of €2.0m or 28% on PR3). These increases have been justified by the DSO

on the basis of the interactions between themselves and the suppliers in terms of Trading and Settlement

activities and seem reasonable given the historical performance and the supporting narrative provided by the

company.

The DSO has proposed a total PR4 allowance of €47.0m (an increase of €6.2m or 15% on PR3) for Market

Opening activities. The company have identified the cost increases going forward for retail Market Design

Services in PR4 but not in sufficient detail to warrant an additional allowance over and above the current level of

expenditure. The increase over PR3 expenditure has not been clearly justified whilst there may be increased

activity in this area, we are not minded to accept that this will lead to an increase in the costs that the DSO has

identified and as we have reduced the PR4 allowed expenditure by a total of €2.9m over the PR4 period.( This

includes additional costs that will be incurred in PR4 in relation to schema releases that have not been part of

the PR3 activity.

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Duos Billing 6.3 1.1 1.4 1.4 1.4 1.4 1.5 7.2 0.9 15%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Duos Billing Allowance 6.3 1.1 1.4 1.4 1.4 1.4 1.5 7.2 0.9 15%

DSO Proposed MRSO 7.2 1.5 1.8 1.8 1.9 1.8 1.8 9.2 2.0 28%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed MRSO Allowance 7.2 1.5 1.8 1.8 1.9 1.8 1.8 9.2 2.0 28%

DSO Proposed Market Opening 40.8 7.6 9.2 9.1 9.5 9.5 9.6 47.0 6.2 15%

Jacobs Proposed Changes -0.1 0.0 -0.9 -0.9 -1.0 -2.9 -2.9

Jacobs Proposed Market Opening Allowance 40.8 7.6 9.1 9.1 8.6 8.6 8.6 44.1 3.3 8%

DSO Proposed Provision of Information 54.2 10.2 12.4 12.4 12.9 12.8 12.8 63.3 9.1 17%

Jacobs Proposed Changes -0.1 0.0 -0.9 -0.9 -1.0 -2.9 -2.9

Jacobs Proposed Provision of Information Allowance 54.2 10.2 12.3 12.4 12.0 11.9 11.8 60.4 6.2 11%

Variance

%PR3 2013 2016 2017 2018 2019 2020 PR4

Variance

PR4-PR3

Page 50: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 45

It should also be noted that within this category, the DSO have made no provision for the effect of Smart

metering. Once that is initiated it will have an impact on the costs of this activity, however we expect that this will

have a more significant impact on PR5 rather than PR4 as it is unlikely a critical mass will be delivered during

PR4.

3.2.7 Telecoms

DSO requested €67.7m, Recommended reduction €-48.4m, Allowance recommended €19.3m.

Table 3.12 presents a year on year comparison between the DSOs proposed Telecoms opex allowance for PR4

and Jacobs proposed opex allowance for PR4.

Table 3.12 : Jacobs Proposed Telecoms Opex Allowance for PR4

The costs incurred by the DSO for Telecoms activities in the PR3 period are not sufficiently transparent.

Supplementary questions have been issued to the DSO and details have been provided by the, however this

has not sufficiently clarified the information to our satisfaction. On this basis it is not possible to determine how

these costs have changed from PR3 to PR4.

The DSO has indicated16 that there will be external revenue generated from this business activity, which will be

passed on to the customer. The DSO’s projection of revenue from Telecoms activities is detailed in Table 3.13

below.

Table 3.13 : DSO Forecast External Revenue from Telecoms Activities17

2016 2017 2018 2019 2020 Total

External Revenue (€m) 9.67 9.67 9.67 9.67 9.67 48.4

It is our view that this income should be netted off the operating costs and the allowance should be the net costs

of operating the service. We have therefore reduced the proposed expenditure allowance on Telecoms by the

expected level of revenue from Telecoms activities (€48.4m). In discussions with the DSO they have indicated

that they wish to class the external income as ‘Miscellaneous Telecoms Income’. Whilst we accept that for

accounting purposes this may be more convenient, we consider that for Regulatory purposes there should be

clarity on the operating costs that the customer is expected to pay in the provision of this activity for operation of

the regulated business. Any variations in the level of external income should be taken into account in assessing

the performance of this activity during PR4. In assessing PR4 efficiency at the end of the period, the level of

expenditure and income should be reviewed. Any under recovery should be borne by the business and any

over-recovery should be passed to the customer.

3.2.8 Sustainability and R&D

DSO requested €15.6m, Recommended reduction €4.5m, Allowance recommended €11.1m.

Table 3.14 presents a year on year comparison between the DSOs proposed Sustainability and R&D opex

allowance for PR4 and Jacobs proposed opex allowance for PR4.

16Telecoms PR4 comparison of charges’ 17 Telecoms PR4 comparison of charges

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Telecoms 0.0 0.0 13.2 13.5 13.6 13.7 13.8 67.7 67.7 -

Jacobs Proposed Changes -9.7 -9.7 -9.7 -9.7 -9.7 -48.4 -48.4

Jacobs Proposed Telecoms Allowance 0.0 0.0 3.5 3.8 3.9 4.0 4.1 19.3 19.3 -

2020 PR4

Variance

PR4-PR3

Variance

%PR3 2013 2016 2017 2018 2019

Page 51: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 46

Table 3.14 : Jacobs Proposed Sustainability and R&D Opex Allowance for PR4

The DSO has not proposed an allowance under the sustainability heading. We have accepted this proposal.

The DSO has proposed a total PR4 allowance of €15.6m (an increase of €7.4m – 91% - on PR3) for R&D

activities. The DSO has provided details of the areas that they wish to research, including18:

Distributed storage €400k

Demand response €400k

Distribution Large scale storage €1000k

evolvDSO €240k

MV/LV substation monitoring €2300k

MV/LV control and automation €1750k

North Atlantic Green Zone €2050k

Servo €450k

Solar Photovoltaic Trial €170k

Variable access trial €1075k

International Collaboration fees €875k

Future Technologies €4500k

The ‘Future Technologies’ research area has no supporting evidence as to the intentions or benefits of this

allowance. On this basis, the R&D allowance has been reduced by €4.5m over the PR4 period, which is

equivalent to the ‘Future Technologies ‘ line.

We suggest that the CER may wish to consider annual reporting of the R&D expenditure in order to review the

previous year and to be informed of the following periods activity and expectations. If there is need for

significantly greater investment than this allowance, we recommend that the DSO engage with the Regulator to

ensure funding is available for these activities by way of a suitably justified business case. This allowance is

provided on the basis of ‘use it or lose it’. Any underspending on this activity should not be considered an

efficiency but returned to the customers.

3.2.9 Corporate charges

DSO requested €51.4m, Recommended reduction €-3.0m, Allowance recommended €48.4m.

Table 3.15 presents a year on year comparison between the DSOs proposed Corporate Charges opex

allowance for PR4 and Jacobs proposed opex allowance for PR4. 18 DF09 Smart Netwoks RandD(final) p38

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Sustainability 8.2 1.1 0.0 0.0 0.0 0.0 0.0 0.0 -8.2

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Sustainability Allowance 8.2 1.1 0.0 0.0 0.0 0.0 0.0 0.0 -8.2

DSO Proposed R&D 0.0 0.0 2.3 2.6 3.4 3.7 3.6 15.6 15.6

Jacobs Proposed Changes 0.0 0.0 -1.5 -1.5 -1.5 -4.5 -4.5

Jacobs Proposed R&D Allowance 0.0 0.0 2.3 2.6 1.9 2.2 2.1 11.1 11.1

DSO Proposed Sustainability and R&D 8.2 1.1 2.3 2.6 3.4 3.7 3.6 15.6 7.4 91%

Jacobs Proposed Changes 0.0 0.0 -1.5 -1.5 -1.5 -4.5 -4.5

Jacobs Proposed Sustainability and R&D Allowance8.2 1.1 2.3 2.6 1.9 2.2 2.1 11.1 2.9 36%

2020 PR4

Variance

PR4-PR3

Variance

%PR3 2013 2016 2017 2018 2019

Page 52: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 47

Table 3.15 : Jacobs Proposed Corporate Opex Allowance for PR4

There are a number of charges that the DSO incurs for the likes of the CEO, Finance etc that are passed down

from Corporate Centre. The DSO have advised that the costs are split between Transmission and Distribution

activities in the ratio of 17:83 in PR3 but this is being revised in PR4 to a 23:77 split. We have based our

allowance on this split across the business based upon the cost currently being incurred in 2013-14. The

corporate charges have been allowed in line with the proposed percentage allocation. The Company wide costs

have been reduced to ensure continued focus on corporate costs. Overall the Costs allowed for Corporate and

Company costs across the TAO and DSO are broadly in line with current levels of expenditure. .

3.2.10 Insurance

DSO requested €18.7m, Recommended reduction €-1.2m, Allowance recommended €17.5m

Table 3.16 presents a year on year comparison between the DSOs proposed Insurance opex allowance for

PR4 and Jacobs proposed opex allowance.

Table 3.16 : Jacobs Proposed Insurance Opex Allowance for PR4

The DSO has proposed an increase in expenditure on Insurance from PR3 to PR4 of €0.4m. The increase has

been explained by the DSO that the insurance costs are linked to the value of their assets, this does not appear

to be the case historically in PR3 and as a result the Insurance costs have been pegged at the average for

2011-2013 inclusive rolled forward for 5 years. This approach provides a total allowance of €17.5m over the

PR4 period.

3.2.11 Legal

DSO requested €14.9m, Recommended reduction €0m, Allowance recommended €14.9m

Table 3.17 presents a year on year comparison between the DSOs proposed Legal opex allowance for PR4

and Jacobs proposed opex allowance.

Table 3.17 : Jacobs Proposed Legal Opex Allowance for PR4

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Corporate Charges & Affairs 44.7 8.2 8.4 8.4 8.4 8.4 8.4 42.1 -2.6 -6%

Jacobs Proposed Changes -0.3 -0.3 -0.3 -0.3 -0.3 -1.5 -1.5

Jacobs Proposed Corporate and Affairs 44.7 8.2 8.1 8.1 8.1 8.1 8.1 40.6 -4.1 -9%

DSO Proposed Company Wide Costs 10.9 2.2 1.9 1.9 1.9 1.9 1.9 9.3 -1.6 -15%

Jacobs Proposed Changes -0.3 -0.3 -0.3 -0.3 -0.3 -1.5 -1.5

Jacobs Proposed Company Wide Cost Allowance 10.9 2.2 1.6 1.6 1.6 1.6 1.6 7.8 -3.1 -29%

DSO Proposed Corporate Costs 55.6 10.5 10.3 10.3 10.3 10.3 10.3 51.4 -4.2 -7%

Jacobs Proposed Changes -0.6 -0.6 -0.6 -0.6 -0.6 -3.0 -3.0

Jacobs Proposed Corporate Costs Allowance 55.6 10.5 9.7 9.7 9.7 9.7 9.7 48.4 -7.2 -13%

PR3 2013 2016 2017 2018 2019 2020 PR4

Variance

PR3 - PR4

Variance

%

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Insurance 18.3 3.5 3.8 3.8 3.7 3.7 3.7 18.7 0.4 2%

Jacobs Proposed Changes -0.3 -0.3 -0.2 -0.2 -0.2 -1.2 -1.2

Jacobs Proposed Insurance Allowance 18.3 3.5 3.5 3.5 3.5 3.5 3.5 17.5 -0.8 -5%

Variance

%PR3 2013 2016 2017 2018 2019 2020 PR4

Variance

PR4-PR3

Page 53: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 48

The company have proposed an allowance for Legal expenditure of €14.9m over the PR4 period, with annual

expenditure of around €3.0m per annum. This represents an increase of €1.9m over and above the expenditure

in PR3. Given the expected increased Revenue Protection activities and the associated legal implications we

consider that this increase is reasonable.

3.2.12 Pensions

DSO requested €7.2m, Recommended reduction €0.0m, Allowance recommended €7.2m

Table 3.18 presents a year on year comparison between the DSOs proposed Pension allowance for PR4 and

Jacobs proposed opex allowance.

Table 3.18 : Jacobs Proposed Pension Opex Allowance for PR4

The DSO have proposed an allowance of €7.2m, representing a reduction on the outturn for PR3 of €2.8m

(28%). We have accepted this reduced cost for the administration of the pension fund when considering the

additional staff that are forecast to be recruited over the period.

3.2.13 Environmental

DSO requested €18.6m, Recommended reduction €-11.0m, Allowance recommended €7.6m

Table 3.19 presents a year on year comparison between the DSOs proposed Environmental allowance for PR4

and Jacobs proposed opex allowance.

Table 3.19 : Jacobs Proposed Environmental Opex Allowance for PR4

The DSO have proposed an allowance of €18.6m for environmental activities over the PR4 period. This

represents a €12.1m (183%) increase over expenditure in PR3. The DSO has not identified any new legislation

that is not currently in force and therefore there should be no additional compliance requirements in PR4. We

consider that the company should have no additional allowances when there is no increase in legislative

requirements and the company is complying with the current requirements. As the DSO has not provided clear

explanations of the individual cost increases requested we have proposed that the PR4 allowance be reduced

by €11.0m to match the levels of expenditure expected at the end of PR3, this is still an increase over total PR3

levels of 16%.

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Legal 12.9 2.6 3.0 3.0 3.0 3.0 2.9 14.9 1.9 15%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Legal Allowance 12.9 2.6 3.0 3.0 3.0 3.0 2.9 14.9 1.9 15%

PR3 2013 2016 2017 2018 2019 2020 PR4

Variance

PR4-PR3

Variance

%

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Pension 10.0 2.0 1.3 1.4 1.4 1.5 1.5 7.2 -2.8 -28%

Jacobs Proposed Changes 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Jacobs Proposed Pension Allowance 10.0 2.0 1.3 1.4 1.4 1.5 1.5 7.2 -2.8 -28%

PR3 2013 2016 2017 2018 2019 2020 PR4

Variance

PR4-PR3

Variance

%

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Environmental 6.6 1.3 3.7 3.7 3.7 3.7 3.7 18.6 12.1 183%

Jacobs Proposed Changes -2.2 -2.2 -2.2 -2.2 -2.2 -11.0 -11.0

Jacobs Proposed Environmental Allowance 6.6 1.3 1.5 1.5 1.5 1.5 1.5 7.6 1.1 16%

PR3 2013 2016 2017 2018 2019 2020 PR4

Variance

PR3 - PR4

Variance

%

Page 54: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 49

3.2.14 Health and Safety

DSO requested €38.8m, Recommended reduction €5.0m, Allowance recommended €33.8m

Table 3.20 presents a year on year comparison between the DSO’s proposed Health & Safety allowance for

PR4 and Jacobs proposed opex allowance.

Table 3.20 : Jacobs Proposed Health and Safety Opex Allowance for PR4

The DSO have proposed a PR4 allowance on Health and Safety of €38.8m which equates to an increase of

€18.9m (95%) on PR3 expenditure. It should be noted that the circumstances currently facing the DSO are not

the same as those at the start of PR3 as a result of recent severe safety incidents that have occurred within the

Company Operations. The company has carried out a full review of its Health and Safety processes and

procedures. The resultant corrective actions have resulted in the above expenditure profile. The company have

provided a number of initiatives in order to correct the deficiencies in their systems:

Technical development €5.9m

Workplace Safety €7.6m

Legal €1.5m

Engagement €1.5m

Public Safety €2.1m

Enterprise Content Management €0.8m

Shield €0.8m

Behaviours €6.1m

Assurance €10.9m

Approvals €1.5m

We are supportive of these actions and the accelerated profile of expenditure. We do believe however that the

approach to the improvement in health and safety should be able to deliver the benefits more speedily and have

shown a reduction in the increase in the later years of PR4. Since the submission of the PR3 forecast position

for Health and Safety expenditure the DSO has provided and updated expenditure profile for PR4 as shown in

table 3.20. With the acceleration of spend in PR3 brining the activities forward, we consider that there is a

reduced requirement in PR4, as a result we recommend a reduction of €5.0m giving an allowance of €33.8m

which is 70% higher than in PR3.

3.2.15 Non controllable costs

Table 3.21 presents a year on year comparison between the DSOs proposed non-controllable opex allowance

for PR4 and Jacobs proposed opex allowance for PR4.

Table 3.21 : Non-Controllable Opex Allowance for PR4

Proposed Operating Costs

(€m 2014 Prices)

DSO Proposed Health & Safety 19.9 2.5 10.9 9.8 7.0 5.9 5.2 38.8 18.9 95%

Jacobs Proposed Changes 0.0 -0.5 -1.0 -1.5 -2.0 -5.0 0.0

Jacobs Proposed Health and Safety Allowance 19.9 2.5 10.9 9.3 6.0 4.4 3.2 33.8 13.9 70%

2017 2018 2019 2020 PR4

Variance

PR4-PR3

Variance

%PR3 2013 2016

Page 55: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 50

The DSO is forecasting significant increases in the Network Rates going forward. These are largely outside of

the control of the DSO and this is recognised by the Regulator. The Network Rates and CER levy costs are

accepted on a pass through basis for the annual DUoS charges. The proposed costs seem reasonable given

the evidence provided by the DSO19.

3.3 Report Findings

The DSO has proposed a total opex allowance for PR4 of €1652.7m, including Commercial Costs but excluding

Depreciation20. The total proposed opex allowance is broken down as follows:

Proposed controllable opex of €1219.9 (an increase of €245.0m - 25% - from PR3 outturn)

Proposed non-controllable opex of €286.1m (an increase of €87.2m - 44% - from PR3 outturn)

Excluding Commercial Costs, the DSO has proposed a total opex allowance for PR4 of €1506.0m, which

represents an increase of €332.3m (28%) from PR3 forecast outturn21.

The DSO has proposed a total PR4 opex allowance (excluding commercial costs and Depreciation) of

€1506.0m. We have reviewed the submission and consider that a reduced allowance of €1362.1m would be an

appropriate allowance for PR4.

Key changes to the DSO proposed costs are;

A reduction in O&M allowance from €581.1m proposed to €537.7m a reduction of €43.4m, mainly in the

planned maintenance activity, where the DSO was seeking a 36% increase over PR3.

A reduction in Metering allowance from €180.1m proposed to €158.8mm, a reduction of €21.3m in

token/keypad meters based on a reduction in unit costs which appear high.

A reduction in Telecoms allowance from €67.7m proposed to €19.3m, a reduction of €48.4m. This

recognises the change in the Telecoms business moving in-house in PR3, but there has not been

sufficient explanation to justify such a high level of cost, and we have proposed netting off the

anticipated revenue to ensure focus is maintained on managing the net cost

Other reductions have been made in customer service €5.2m, provision of information €9.4m, Corporate costs

€3.0m, R&D €4.5m, €11m on environmental and €1.2m on insurance, and €5m on Health and Safety.

We have suggested that the DSO develop an appropriate method to understand the asset heath of its asset

portfolio, in order to understand the overall level of maintenance required and to inform future Asset

Maintenance and Replacement Programmes. We have also allowed, a significant increase in, the Health and

Safety Allowance in order to provide the DSO staff and the public with a safe operating environment.

19 DF61 Rates 20 Document ‘D05 Attachment A’, 21 The PR3 outturn is different from that reported in Section 2 of this report due to a change in price base from 2009 to 2014.

Proposed Operating Costs

(€m 2014 Prices)

Network Rates 188.7 35.0 46.9 51.0 55.0 59.1 63.1 275.1 86.4 46%

Car Levy 10.2 2.3 2.2 2.2 2.2 2.2 2.2 11.0 0.8 8%

Non Controllable 198.9 37.3 49.1 53.2 57.2 61.3 65.3 286.1 87.2 44%

Variance

%PR3 2013 2016 2017 2018 2019 2020 PR4

Variance

PR4-PR3

Page 56: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 51

4. Review of PR3 Capital Expenditure

This section reviews the DSO’s projected capital expenditure over the PR3 period 2011 to 2015 compared with

the expenditure allowed by CER in the PR3 decision paper

The purpose of our review is to assess and compare the levels and appropriateness of the DSO capital

expenditure against network operational and investment needs and to analyse, comment on and make

recommendations on efficient expenditure, and project and asset delivery in line with industry best practice. It is

not associated with confirming the accuracy with respect to monies spent and received as would be undertaken

by Independent Auditors in line with normal Company Law and also regulatory requirements as appropriate.

Our role involves a review of and advising on the processes employed by DSO in its delivery of capex i.e. where

delivery is inefficient, the reason behind this inefficiency and changes which could be made to management and

delivery processes to improve efficiency.

A further important element of the review of PR3 actual/forecast outturns is a comparison agaichemenst the

original forecast and allowed expenditures and the determination of the reasons behind any significant

deviations as this will inform views with respect to the ability of the businesses to forecast expenditure

requirements and also to manage the delivery of such expenditure and associated operational efficiencies.

From the DSO, we have been provided with, through the questionnaire, a line by line and year by year Capex

expenditure submission in the same format as the final allowances from the previous price control. We note

2011-14 to be actual costs and 2015 to be latest best estimates (LBE). We have reviewed data and the

narrative responses provided by the DSO and requested additional clarifications from the DSO to assist in our

review and to further explain specific variances.

We would normally expect Capex variances to fall mainly into the categorisation of:

Volume

Asset Replacement (deferment or acceleration of programme/asset replacement)

Load Related (deferment or acceleration due to demand variance, project churn)

Unit Costs (delivery efficiency, procurement initiatives, commodity price impacts)

We would normally expect capitalised faults to be an aspect of the historic capex and policy changes relating to

capitalisation and the impacts of major incidents may impact on the outturn. Again we have reviewed these

issues and comment whether they are likely to affect the 2016-2020 forecast period.

We consider whether the 2015 LBE forecast expenditure is realistic based on the actual Capex and we have

sought further explanation from the DSO to justify this forecast both in terms of comparison with previous

delivery rates and the staffing forecasts. We have also sought to make sure that the LBEs include the delivery

of commissioned assets and not advance procurement of major assets that will form part of the 2016-2020

programmes. We will use this information to determine if any variance on the 2011-2015 controls impact on the

forecast Capex for the 2016-2020 price control.

As part of this historic Capex review we expected to see an explanation of the DSO investment appraisal and

approval process and selected example documentation that was used to justify any significant projects that

were not included in the current submission.

4.1 General

This section reviews the DSO’s projected capital expenditure over the PR3 period (2011 to 2015) compared

with the expenditure allowed by CER in the PR3 decision paper22.

22 CER/10/198 - Decision on 2011 to 2015 distribution revenue for ESB Networks Ltd

Page 57: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 52

During the PR3 period, there are a number of significant factors that need to be considered when assessing

DSO outturn capex v CER allowed costs. In consultation with the CER, ESBN Networks reduced the PR3

Capex delivery programme for distribution and transmission in two stages from the original CER allowed value

of €4,200m23 (see column “CER Allowed Capex for ESBN” in Table 4.1). The first stage resulted in a

reduction to €2,956m (See Table 4.1 column “Adjusted PR3”). This reduction was driven by the following

items:

• Capex associated with both demand and generator connections was significantly below expected levels

• Capex associated with Smart Metering (€500m) was not expected to be incurred until the PR4 period;

• Expenditure relating to the new ESBN HQ in Carrickmines was to be deferred.

The second stage of reduction was driven by the prioritisation and deferral of capex relating to load

reinforcement, asset replacement and non-network investment categories. This was considered necessary to

manage the freeze in the corporate debt markets as part of the global financial crisis and also to reduce the

impact of DUoS prices on ESBN customers and reduced the expenditure further from €2,956m to €2,400m, as

detailed in column “ESBN Proposal24

”.

Focussing only on distribution expenditure, and excluding the capital expenditure relating to Smart Metering, the

programme was reduced from €2101m to €1,708m and then to €1,179m.

Table 4.1 : DSO: Re-alignment of Distribution Capital Programme (€m – Gross 2009 prices)

Capex Investment Category CER Allowed Capex

for ESBN Adjusted PR3 ESBN Proposal

New Business – Demand Connections to DSO network 452.7 252 252

New Business - Generation Connections to DSO network 162.5 70 69

Line Diversions – relocation of DSO network assets necessary

to allow new development 51.8 52 52

Smart Metering – installation of latest technology “smart”

meters for domestic customers 500.0 51 50

Transmission Network Related Expenditure (not DSO)

1,599.2 *

1,197 1,171

Carrickmines Building Relating Expenditure for new ESBN

Head Office - -

Load Related Reinforcement expenditure of DSO distribution

network 632.6 533 277

Asset Replacement 622.1 622 433

Non Network 179.1 179 96

Total - ESBN 4,200 2,956 2,400

Total – ESBN – DSO Only (Excluding Transmission Capex

and Smart Metering Capex) 2100.8 1,708 1,179

* Number assumed based on gross total for ESBN of €4.2b

Note 1- Source – ESBN – PR4 Submission: Document Reference DH01 PR3 Distribution Overview

Note 2 – “Asset Replacement” Costs include costs associated with the retirement of assets

This compares with CER PR3 DSO allowed gross capex of €2,101m and latest DSO forecast (gross) of

€1,199m (as presented in Figure 4.1 and itemised in Table 4.2).

23 ESBN Transmission and Distribution Total Capital Expenditure 24

ESBN Proposal was submitted to CER in December 2012 – and these revised capex values are considered as the agreed rebased values against which we also provide an assessment of outturn v rebased forecast

Page 58: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 53

In headline terms, during PR3 the DSO has invested gross €1,284.3m on network and non-network

assets, which is €816.5m (39%) lower than the CER allowed capital expenditure of €2,101m (excluding

Smart Metering and Electric Vehicles). It is €105.3m higher (8.9%) than the DSO Revised Capex

Proposal of December 2012.

Due to the unique circumstances that were faced by the DSO in the period and resulting in its revised capex plans in 2012, it is considered appropriate to use the rebased 2012 capex forecast for comparison throughout this report wherever possible, although, for completeness, reference is also made to CER allowed values.

However, the DSO has been asked for more detailed breakdown of costs associated with the 2012 revised capex plan broken down into an annual expenditure profile for each of the work programmes for which CER had made allowances for the PR3 period - it is our understanding that this information is not available.

We received the following statement from the DSO…“It is important to appreciate that whilst a lower level of CAPEX was agreed with CER at this time, there was no single point of decision where detailed work programmes commensurate with the revised budget amount was decided on - Instead the process was that annual work programmes were decided on for 2012 and 2013 and as the borrowing positon eased, 2 year work programmes were agreed for 2014 – 15. As is evident from the description, these decisions are informed by an understanding of the benefit to cost analysis that ESBN had done in advance of PR3 and indeed for earlier price controls”.

Consequently we have not been able to carry out a comparable analysis of DSO forecast v rebased

2012 capex at a work programme level and such analysis has therefore been carried out relative to

CER allowed capex for each defined category of capex.

Whilst a PR3 allowance of €500m for expenditure associated with smart metering was provided by CER, the

DSO has only incurred €14.6m of costs. It should be noted that the allowed capex for smart metering was

removed on an annual basis throughout PR3 such that the DSO customers were not charged for these costs.

Figure 4.1 : DSO PR3 Capex Summary (excluding costs associated with smart metering) – Gross Costs (€m 2009 prices)

2,101

1,1791,284

0

500

1000

1500

2000

2500

5 Year Total

€m

CER Allowed Capex ESBN Proposal (2012) DSO Actual / Forecast

Page 59: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 54

Table 4.2 : DSO PR3 Capex Summary by Investment Category (£m – 2009 prices) 25

Capex Investment Category

CER Allowed

Capex

(GROSS)

Revised

DSO

Proposal

(2012)

DSO

Forecast

(GROSS) -

2014

Variance – DSO Forecast

to CER Allowed Capex

Variance – DSO Forecast

(2014) to DSO Revised

Proposal (2012)

€m % €m %

New Business 452.7 252.0 235.5 -217.2 -48.0% -16.5 -6.6%

Generation Connections 162.5 70.0 86.7 -75.8 -46.6% 17.7 25.7%

Line Diversions 51.8 52.0 47.1 -4.7 -9.0% -4.9 -9.4%

Distribution Reinforcement 632.6 277.0 316.9 -315.7 -49.9% 39.9 14.4%

Asset Replacement 622.1 433.0 462.4 -159.7 -25.7% 29.4 6.8%

Non Network 179.1 96.0 135.6 -43.5 -24.3% 39.6 41.2%

Total – DSO Excluding Smart

Metering 2,100.8 1,179.0 1284.3 -816.5 -38.9% 105.3 8.9%

Note – “Asset Replacement” Costs include costs associated with the retirement of assets (costs for period from 2011-2013 obtained from

Opex Table 5.1 and costs for period 2014/15 are from Capex Table 6.3)

The DSO actual net capex26 for the period 2011 to 2013, together with its forecast for the 2014 and 2015 period

is presented in Table 4.3 and is illustrated in graphical format in Figure 4.2 below, compared to CER allowances

for PR3 period. Annual comparison of DSO actual/forecast for PR3 with its rebased 2012 plan is not possible as

the annual capex totals are not available.

Table 4.3 : PR3 Net Capital Expenditure – DSO Actual/Forecast v PR3 Allowances (€m - 2009 Prices)27

2011

(Actual)

2012

(Actual)

2013

(Actual)

2014

(Forecast)

2015

(Forecast)

5 Year Total

(2011 – 2015)

CER Allowed Net Capex (€m) 344.6 343.1 340.8 342.4 341.3 1712.2

Actual Capex (Net) - €m 283.8 177.3 166.1 201.6 246.5 1075.3

Variance to CER Allowances €m -60.8 -165.8 -174.7 -140.8 -94.8 -636.9

% Variance -18% -48% -51% -41% -28% -37%

25 DSO Forecast for PR3 is based on data provided by the DSO within its Business Plan Questionnaire Table 6.3 (revised – dated March 2015). 26 Net of customer contributions and Interest during Construction (IDC) Charges 27 Excludes costs associated with Smart Metering

Page 60: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 55

Figure 4.2 : PR3 Net Capital Expenditure – DSO Actual/Forecast v PR3 Allowances (€m – 2009 prices)

In headline terms, during PR3 the DSO is forecasting to invest net €1,075.3m on network and non-network

assets, which is €91.3m (9.3%) higher than its 2012 revised capex total of €984m 28(excluding Smart Metering

and R&D costs associated with studying impact of Electric Vehicles).

Its latest forecast is €637m (37%) lower than the CER allowed capital expenditure of €1,712m.

Each of the capex categories presented in Table 4.2 are considered in further detail within the sections below.

Capex relating to New Business, Generation Connections, Line Diversions and Distribution Reinforcement are

discussed in Section 4.2 whilst capex relating to Asset Replacement is discussed in Section 4.3. Non network

related capex is discussed in Section 4.4.

4.2 Network Related Expenditure

4.2.1 New Demand Connections

The DSO capex between 2011 and 2015 relating to new (demand) connections is summarised in Table 4.4

below. Expenditure is presented both in gross terms and also net of customer contributions.

Table 4.4 : New Connections Capex (Demand Connections) - Comparison of PR3 Costs v CER Allowances (€m – 2009 prices)

Capex Category 2011

(Actual)

2012

(Actual)

2013

(Actual)

2014

(Actual)

2015

(Forecast) 5 Year Total

Gross

CER Allowed Capex 85.4 88.1 90.6 93.1 95.5 452.7

DSO Actual Capex 52.5 46.4 41.0 48.45 47.24 235.5

DSO Revised Capex (2012) 252.0

Variance (DSO Actual to CER Allowed

Capex) -32.9 -41.7 -49.6 -44.7 -48.3 -217.2

% Difference -38.6% -47.4% -54.8% -48.0% -50.5% -48.0%

Variance (DSO Actual to DSO Revised

Capex – 2012) -16.5

28

Calculated based on assuming 50% contribution target for demand connections and 100% for generator connections

0

50

100

150

200

250

300

350

400

2011 2012 2013 2014 2015

€m

CER Allowed Net Capex (€m) Actual Capex (Net) - €m

Page 61: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 56

Capex Category 2011

(Actual)

2012

(Actual)

2013

(Actual)

2014

(Actual)

2015

(Forecast) 5 Year Total

% Difference -6.6%

Net

CER Allowed Capex 42.7 44.1 45.3 46.6 47.8 226.4

DSO Actual Capex 28.4 24.5 17.6 24.3 28.5 123.2

DSO Revised Capex (2012) 126.0

Variance (DSO Actual to CER Allowed

Capex) -14.3 -19.6 -27.7 -22.3 -19.3 -103.1

% Difference -33.6% -44.5% -61.1% -47.8% -40.4% -45.6%

Variance (DSO Actual to DSO Revised

Capex – 2012) -2.8

% Difference 2.2%

Contributions

CER Allowed Contributions -42.7 -44.1 -45.3 -46.6 -47.8 -226.4

DSO Contributions – Demand Connections -24.1 -21.9 -23.3 -24.2 -18.8 -112.3

Note 1- CER Contributions – these values are based on a contribution ratio of 50% as per CER Decision Paper CER/1/198

Note 2 – DSO Contributions (Actual) – values have been calculated based on total contributions (DSO Questionnaire Table 6.3) less

contributions relating to generator connections (Table 6.4)

The total DSO Actual Capex (Gross) over the PR3 period is forecast to outturn at €235.5m, this is €217.2m

(48%) less than the CER Allowed capex. It is also €16.5m (6.6%) less than the DSO Revised Capex Proposal of

2012 (€252.0m).

The total DSO Actual Capex (Net) over the PR3 period is forecast to outturn at €123.2m, this is €103.1m

(45.6%) less than the CER Allowed capex, although it is only €2.8m (2.2%) less than the DSO Revised Capex

Proposal of 2012 (€126.0m).

Customer contributions are based on standard costs for each type of connection and metering, the customer

being charged 50% of the standard costs. Customer contributions of €112.3m for a gross expenditure on

demand connections of €235.5m (gross) resulted in a contribution ratio of 48% compared with the agreed rate

of 50%.

The main driver for this significantly lower capex, compared to the CER allowances, is the reduced

number of customer connections that have been requested to be provided by the DSO over the PR3

period. For the first three years of PR3 the total actual number of connections provided is 41,749. This

is some 53.1% lower than the PR3 forecast connection volumes for the same 3-year period (89,039).

The DSO may need to revise the Basis for Customer Connection Charges for future recovery of the

agreed rate of 50% of total connection charges, although we would expect any revision to be

presented to the CER for review and approval.

The lower volume of connection volumes during PR3 is detailed more fully in Table 4.5 below.

Table 4.5 : PR3 Connection Volumes (Actual) v Forecast

Capex Category

PR3 Forecast

Connection Volumes

PR3 Actual Connection

Volumes

Variance –

Actual 2011 -

2013

Variance –

Actual 2011 -

2015

2011-

2013

Actual

2014-

2015

Forecast

5

Year

Total

2011-

2013

Actual

2014-

2015

Forecast

5

Year

Total

No’s % No’s %

Page 62: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 57

Capex Category

PR3 Forecast

Connection Volumes

PR3 Actual Connection

Volumes

Variance –

Actual 2011 -

2013

Variance –

Actual 2011 -

2015

2011-

2013

Actual

2014-

2015

Forecast

5

Year

Total

2011-

2013

Actual

2014-

2015

Forecast

5

Year

Total

No’s % No’s %

G1 Scheme Housing 34,081 28,622 62,703 10,735 11,028 21,763 -23,346 -68.5% -40,940 -65.3%

G2 Non Scheme

Housing 31,055 21,916 52,971 16,379 9,754 26,133 -14,676 -47.3% -26,838 -50.7%

G3 Non Domestic 23,903 17,060 40,963 14,635 7,886 22,521 -9,268 -38.8% -18,442 -45.0%

Total 89,039 67,598 156,637 41,749 28,668 70,417 -47,290 -53.1% -86,220 -55.0%

Note 1 – PR3 Forecast connection volumes from SKM Report “SKM DSO Capex costs 2006 to 2015”

Note 2 – Actual Numbers for 2011 to 2013 from DSO PR4 Submission Document Reference DH05

The following observations can be made from the above table:

For the first three years of PR3 the total actual number of connections provided is 41,749. This is some

53.1% lower than the PR3 forecast connection volumes for the same 3-year period (89,039).

Based on the DSO latest forecast for 2014 and 2015, it is anticipated by the DSO that the 5-year total will

outturn at 70,417. This is more than 86,000 (i.e. 55%) lower than the PR3 forecast connection volumes for

the full 5-year period.

The most significant variance in connection volumes relates to G1 Scheme Housing connections (actual

variance of 68.5% lower than PR3 predicted levels for the 2011-2013 period)..

The number of connection volumes for both Non-Scheme Housing (G2) and Non-Domestic Connections

(G3) are also significantly lower than the PR3 forecast connection volumes (actual variance of 50.7% and

45% lower than PR3 predicted level respectively over the 5 year period).

The DSO forecast for 2014 and 2015 is based on a continuation of the lower rate of connection volumes

experienced during the first three years of PR3, with some recovery evident in the forecast for G1 housing

schemes.

The original forecast for PR3 was based on the expectation that there would be a gradual recovery from the

economic recession, manifested by a slight increase in construction activities year by year as shown by the red

line in Figure 4.3.This has clearly not been the case and the downward trend in connection volumes

experienced in the period 2007 to 2010 (blue line in Figure 4.3) has continued, with an expectation that there

will be a minor increase in annual volumes by 2015 (green line in Figure 4.3).

Page 63: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 58

Figure 4.3 : New Connections made to DSO Network over period 2006 to 2015

4.2.1.1 New Demand Connections Unit Costs

Another potential driver on the lower forecast outturn capex during PR3 period relates to the unit costs 29for

each of the different connections. The unit costs allowed by CER for PR3 together with the DSO actual unit

costs for each type of connection are detailed in Table 4.6 and Figure 4.4.

Table 4.6 : Connections: Comparison of DSO Actual Unit Costs v CER Allowances (€ - 2009 prices)

Note 1– CER Allowed Unit Costs from SKM Report "SKM DSO Capex Costs 2006 to 2015"

Note 2 – DSO Actual Unit Costs from ESBN PR4 Submission document Reference DH05 – New Connections

29 We agree with the DSO that the unit costs presented in the table (and in DSO narrative document DH05) are derived from the total expenditure

incurred in each category for any given year divided by the volume of connections completed in the year 30 In its response (DSO Report DR01) to our PR3 Capex IR, the DSO provided updated 2014 actual costs but not updated 2014 volumes.

Consequently 2014 actual unit costs are based on DSO submission of 5th December 2014. 31 DSO response DR01 provided revised 2015 forecast costs and forecast volumes for each of the G1/G2/G3 connections. Based on data provided,

the unit costs were €856 (G1) €3,214 (G2) and €4,951 (G3).

0

20,000

40,000

60,000

80,000

100,000

120,000

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

Nu

mb

er

of

Co

nn

ec

tio

ns

Actual (to 2010) PR3 Forecast (2009) PR3 Actual Connections

Category of

Connection

CER Allowed Unit Costs DSO Actual Unit Costs

2011 2012 2013 2014 2015 2011 2012 2013 201430 201531

G1 Scheme Housing 1,185 1,174 1,162 1,150 1,139 700 646 618 1,150 856

G2 Non Scheme

Housing 3,093 3,062 3,031 3,001 2,971 3,195 3,343 3,155 3,002 3,214

G3 Non Domestic 5,165 5,113 5,062 5,012 4,961 5,392 5,461 3,851 5,013 4,951

Page 64: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 59

Figure 4.4 : Connections: Comparison of DSO Actual Unit Costs v CER Allowances (€ - 2009 prices)

The unit costs for G1 New Scheme Housing have reduced during PR3 such that by 2013 the outturn unit cost of

€618 was 47% lower than the unit cost allowed by CER. The DSO has explained this variance is due to sunk

costs in scheme housing projects being experienced in the early time periods of developments, together with

the completion or partial completion of Ghost Estates. The DSO has explained that many housing

developments were placed on hold during PR2 with the main connection infrastructure (MV substations, MV

and LV circuits) having been established during the PR2 period. Consequently small numbers of incremental

connections have been provided during PR3 period without necessarily having to establish additional

infrastructure.

We have validated this explanation from the DSO by analysing the average quantity of assets installed

per customer over the 5-year PR2 period against the average quantities installed per customer during

the first three years of PR3. For the main asset categories (MV substations, MV and LV circuits) we have

observed a noticeable reduction in the average number of assets installed per customer during PR3 (to

end of 2013). For LV cables, the average length installed per customer is 41% lower in the first three

years of PR3 compared to the average length per customer in PR2. For MV cables, the average length is

88% lower.

The average number of MV/LV 3-phase pole-mounted transformers and ground mounted transformers

per customer are also noticeably lower, 20% and 10% lower respectively, than the PR2 average values.

Our review of the DSO forecast PR4 capex for the different categories of demand connections assesses

appropriate unit costs, taking account of outturn costs during PR2 and PR3, together with any other relevant

factors.

DSO actual unit costs for G2 Non-Scheme houses are broadly in line with the allowed PR3 unit costs, albeit

marginally higher. The DSO cites a number of contributory factors, resulting in upwards pressure on unit costs,

including:

reduced opportunity to achieve economies of scale because of lower connection volumes,

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

2011 2012 2013 2014 2015

G1 Scheme Housing G2 Non Scheme Housing G3 Non Domestic

Note: Solid line = Actual/forecast; Dashed line = CER allowed

Page 65: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 60

increased use of live-line techniques in providing connections;

an increase in the number of special connections associated with farm automation requiring capacity

increases from 20 kVA to 29 KVA. (These are driven by legislation requiring on site storage chilling of milk)

and geothermal heating connections. The average number of these special connections over PR3 period is

over 230 – this is 46% higher than 2010 volumes.

DSO actual unit costs for G3 Commercial / Industrial Connections are noticeably lower in 2013 compared to the

allowances set by CER, with an outturn unit cost of €3,851 being 24% lower. The DSO cites the recent

Telecommunications roll-out of the “E-Fibre” to the cabinet with significant volumes in 2012 and more so in 2013

impacting on unit costs. These cabinets are being installed primarily in urban locations with civil works being

completed by the customer. These connections are unmetered and are currently undergoing an intensive

“peak” of installations in urban areas. The unit costs for these types of connection are much lower than the

average G3 connection. Table 4.7 shows the annual number of these connections provided during PR3. It is

clear that the significant number of connections provided to the E-Fibre cabinets in 2013 (42% of the total

number of G3 connections) has contributed to the significant reduction in the unit cost for G3 connections.

Table 4.7 : Analysis of the number of E-Fibre connections

2011 2012 2013

Number of E-Fibre Cabinet Connections 0 825 2,325

Number of G3 Connections 4,714 4,378 5,543

Number of E-Fibre Connections as percentage of G3 total 0 18.8% 41.9%

4.2.1.2 Analysis of PR3 Meter Costs

CER allowances for PR3 period were based on a unit cost of €85 for whole current metering. This cost was

based on an assumption of 33% of connections being non-metered and 6% of non-domestic connections being

three phase supplies. A PR3 allowance of €12.2m was subsequently approved by the CER. The DSO actual

metering costs for PR3 compared to this allowance are presented in Table 4.8 below.

Table 4.8 : Meters: Comparison of DSO Actual Costs v CER Allowances (€m - 2009 prices)

2011 2012 2013 2014 2015 5 Year Total

CER Allowed Capex 2.2 2.3 2.4 2.6 2.7 12.2

DSO Actual / Forecast 3.5 3.1 2.5 2.5 2.7 14.4

Variance 1.3 0.8 0.1 -0.1 -0.0 2.2

% Difference 61.1% 36.0% 4.4% -4.8% -12.0% 17.9%

Note the 2012 Revised Capex for DSO did not provide detailed assessment of revised meter costs

It is observed that the DSO total meter costs for PR3 period are 17.9% higher than the CER allowed costs. This

is despite a forecast reduction in connection volumes of 55% over the PR3 period.

The average meter unit cost (over the 2011 to 2013 period) has a 3-year actual average unit cost of €165 per

meter32. This is significantly higher than the unit cost of €85 used in determining PR3 allowances and the DSO

original unit cost of €150 that the DSO proposed in its forecast CAPEX for PR3. The DSO has provided a

detailed explanation to explain this apparent adverse variance.

Specifically the closing of cost accounts relating to dormant connection projects, to prevent misallocation of

costs, has resulted in final connection cost and the metering cost both being allocated to the metering cost

code. This has obviously resulted in the identified increase in metering costs. The DSO explanation has been

32 Excluding meter volumes and costs associated with the replacement of faulty meters- as this is provisioned within the DSO Response capex

category.

Page 66: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 61

supported by analysis33 of the time and material cost movement for G1 metering cost components over the

period 2006 to 2013, showing a significant increase in both over this period (relative to 2006) whilst there has

been a corresponding reduction in the time and material costs (relative to 2006) for the G1 connection cost

component.

Similar analysis carried out by the DSO for G2 and G3 connections also shows an increase in material costs

due to the allocation of service cable connection costs to the metering cost allocation code.

The analysis provided by the DSO supports the higher metering capex costs incurred during PR3. It is

important that the assessment of PR4 allowed revenues for connections and metering takes due

account of the fact that a proportion of G1-G3 connections costs have been allocated to metering

capex during PR3.

4.2.2 Generator Connections

The DSO capex related generator connections is summarised in Table 4.9 below. Expenditure is presented

both in gross terms and also net of customer contributions.

Table 4.9 : New Connections Capex (Generator Connections) - Comparison of PR3 Costs v CER Allowances (€m – 2009 prices)

2011 2012 2013 2014 2015 5 Year Total

Gross

CER Allowed Capex 7.2 40.2 31.8 16.5 66.8 162.5

DSO Actual Capex 17.5 10.4 16.9 8.0 34.0 86.7

DSO Revised Capex (2012) 69.0

Variance (DSO Actual to CER Allowed

Capex) 10.3 -29.8 -14.9 -8.5 -32.8 -75.8

% Difference 143% -74% -47% -52% -49% -47%

Variance (DSO Actual to DSO Revised

Capex – 2012) 17.7

% Difference 25.7%

Net

CER Allowed Capex - Net -0.1 0.0 0.0 0.0 0.0 0.0

DSO Capex - Net -2.8 2.6 -9.6 -9.0 8.8 -10.0

Contributions

CER Allowance Contributions 7.3 40.2 31.8 16.5 66.8 162.5

DSO Actual Contributions 20.3 7.8 26.5 17.0 25.2 96.7

A comparison of gross expenditure is shown in Figure 4.5 below.

33 Supporting analysis provided in Document Reference DR01 DSO Capex Final.pdf

Page 67: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 62

Figure 4.5 : Generator Connections – Comparison of PR3 Costs v CER Allowances

The DSO is forecasting to incur gross generation connections costs of €86.7m during PR3, representing an

underspend of €75.8m compared with the CER allowed gross capex of €162.5m. This DSO forecast is €17.7m

(25.7%) higher than the DSO Revised Capex Proposal of 2012

The lower level of generation connections is due to the timing of new generation projects which are linked to the

Gate2 - Gate 3 grouped process for coordinating generation connections. The DSO has explained that most of

the Gate 3 projects have accepted their connection offers in the summer of 2013, although their original offers

had been provided in the 2009-2011 period. The CER approved a suspension of the expiry dates on the issued

Gate 3 connection offers until issues regarding constraints and curtailment of wind were fully resolved. This

resolution came in the form of a SEM decision in March 2013, and all applicants were provided with constraint

and curtailment levels applicable to their projects.

The DSO expects to make significant progression during 2014 and 2015 in the design and scoping of Gate 3

wind connections and the commencement of substantial construction activity. This is reflected in the profile of

customer contributions for generation connections. These are forecast to be €96.7m, equivalent to a

contribution ratio (or recovery rate) of 112% compared with the allowed recovery rate of 100%. This over-

recovery is partly due to the timing of contributions expected for 2015 with the resulting impact of higher levels

of related expenditure to be incurred during PR4. The DSO has cited a further large tranche of Gate 3 wind

projects, totalling approximately 2,000 MW that have been offered and accepted their connection offers. The

0

10

20

30

40

50

60

70

80

2011 2012 2013 2014 2015

€m

CER Allowed Capex - Gross DSO Actual Capex - Gross

162.5

6987

0

20

40

60

80

100

120

140

160

180

5 Year Total

€m

CER Allowed Capex - Gross ESBN Proposal (2012) DSO Actual Capex - Gross

Page 68: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 63

over recovery forecast in PR3 relates to the generator connections that are expected to move through the

design stage and into construction stage in final years of PR3 and early years of PR4 resulting in higher cash

outflows during PR4.

This over-recovery of connection costs in PR3 will undoubtedly result in DSO net cash outflows during

the early years of PR4 period and this will need further consideration when reviewing the proposed

DSO forecast capex for PR4.

4.2.3 Load Related Reinforcement

The DSO load-related capex for the PR3 period is shown in Table 4.10 below.

Table 4.10 : Comparison of PR3 Costs v CER Allowances – Load Related Reinforcement (€m 2009 prices)

Category 2011 2012 2013 2014 2015 5 Year Total

CER Allowed Capex 130.8 127.7 125.8 124.8 123.5 632.6

DSO Actual / Forecast 92.8 55.0 57.1 49.7 62.3 316.9

Variance -38.0 -72.7 -68.7 -75.1 -61.2 -315.7

% Difference -29.0% -56.9% -54.6% -60.2% -49.5% -49.9%

The DSO forecast a total capex of €316.9m by end of PR3 – this is €315.7m lower than the CER allowed load-

related reinforcement capex of €632.6m – representing a variance of 50%. This DSO forecast is approximately

€39.9m higher than the revised proposal of ESBN (€277m) submitted to CER in 2012 – see Figure 4.6 below.

Figure 4.6 : Comparison of DSO PR3 Costs – Load Related Reinforcement

Table 4.11 below provides an itemised breakdown of the DSO load related capex over PR3 period, compared to

the CER allowed capex for each of the categories.

It should be noted that the ESBN Proposed revisions to the capex were provided at an aggregated level

(totalling €277m) and were not broken down into the individual categories shown below.

633

277 317

0

100

200

300

400

500

600

700

5 Year Total

€m

CER Allowed Capex ESBN Proposal (2012) DSO Actual / Forecast

Page 69: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 64

Table 4.11 : Load Related Reinforcement – Comparison of Capex by Category (€m – 2009 prices)

Category CER Allowed

Capex

DSO Actual /

Forecast Variance €m Variance %

Transmission Connection Costs 25.7 0.0 -25.7 -100%

110kV 230.5 140.9 -89.6 -39%

38kV 210.1 84.4 -125.7 -60%

MVLV System Improvements 69.1 33.6 -35.5 -51%

IFTs associated with 20kV Conversion 16.2 22.4 6.2 38%

20kV Conversion 81.0 35.6 -45.4 -56%

Total 632.6 316.9 -315.7 -50%

The main drivers on load-related reinforcement expenditure are the growth in peak demand and energy

delivered (GWh). The graph below (Figure 4.7) shows the actual total GWh units distributed by the DSO

(including 110kV) since 2005, together with its forecast for the remainder of the PR3 period. The original PR3

forecast (derived in 2009) is also plotted. It is noticeable that from a total of circa 24,000 GWh in 2008, the DSO

has experienced a reduction to 23,000 GWh units in 2010, followed by a further reduction in actual GWh units to

circa 22,100 by 2013. This represents a total reduction in units distributed of approximately 6.4% over the

course of five years. A modest increase in units distributed is forecast by 2015. The actual annual units

distributed between 2011 and 2015 are significantly different to the expected annual units required for

distribution at the time of PR3.

Figure 4.7 : Total Units Distributed (GWh) from 2005 to 2015)

Similarly, the system peak demand has not increased in line with the DSO forecast for PR3. This is illustrated in

Figure 4.8 below. The left-side figure shows the system demand (historic together with the forecast for PR3

period) whilst the right-side figure shows the system demand (actual to 2013). The peak in 2007/08 was 4,914

MW and the peak in 2013/14 has reduced to 4,523 MW.

Given the reduction in peak demand during the PR3 period, together with the borrowing constraints faced by

ESBN and the pressure to reduce potential increases on DUoS charges, the DSO considered it appropriate to

critically review the network requirements and the related project portfolio, allowing for deferment of

reinforcement projects where the resultant risks were considered acceptable to do so.

19000

20000

21000

22000

23000

24000

25000

26000

27000

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

Un

its

Dis

trib

ute

d (

GW

h)

Actual (to 2010) PR3 Forecast (2009) PR3 Actual Units

Page 70: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 65

Figure 4.8 : System Demand – PR3 Forecast v PR3 Actual

Most global distribution companies use either a deterministic or probabilistic approach to assess network

security when planning the network. A deterministic approach is based on the absolute requirement that for a

given event (e.g. a network outage) the network supplying the group demand has to be secure (i.e. meet the

security standards). Using this absolute approach, there is no consideration of the risk/probability of such an

event, whereas a probabilistic approach to network planning will make an assessment of the likelihood/impact of

events occurring as a driver for network reinforcement.

GB DNOs all use a deterministic approach to network planning although we understand that they are

considering a future update to the Network Planning Standard and this may address probabilistic techniques in

addition to the deterministic criteria set out in the current standard. The DSO continues to use a deterministic

approach to network planning, with the security standards detailed in Table 4.12 below being used as a driver

for reinforcement.

We consider that the current methodology continues to be appropriate for the DSO – it is in line with

international practice and provides a good baseline against which investment needs can be assessed.

Table 4.12 : DSO Security of Supply Standards

Due to the reduction in units distributed and reduction in peak demand from 2011 onwards, the original PR3

Distribution Reinforcement programme was scaled back by the DSO in 2012 from €633m to €277m, although

the DSO latest forecast for PR3 period is €316.9m.

34

GD is restored when either fault is repaired or the plant being maintained is switched back in.

Group Demand (GD) Standby Provision Restore at least within

60 secs 15 mins 3 hours Repair Time

0 – 1 MVA None GD

>1 – 10 MVA N-1 GD – 1 MVA GD

>10 – 30 MVA N-1 GD – 10 MVA GD

>30 – 100 MVA N-1 GD – 30 MVA GD

>100 MVA

N-1 GD

N-1-1 2/3 GD GD restored as soon as possible34

Page 71: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 66

HV load related expenditure has been limited by the DSO during PR3 to the following categories of expenditure:

Projects carried over from PR2;

New projects required to address significant overload and / or major breeches in security standards;

New HV and MV connections to major industrial and commercial customers; and

Ongoing programme to replace obsolete Siemens 38kV substations.

The PR3 programme for network reinforcement was based on the Dublin and Country network plans, which set

out a programme of work to maintain system loading and security within network capacity and planning

standards.

ESBN's Network security standards are similar to international practice with n-1 security provided at primary

transformer stations taking into account transfer capacity. The DSO typically uses ONAN35

ONAF transformers;

typically rated at 15 MVA when naturally cooled (ONAN) and 20 MVA when cooling is supplemented by fans

(ONAF36

). Such units are operated at a short time overload rating of 180% of installed capacity for up to 30

minutes in which time the demand is reduced to within ONAF rating by demand transfer where available. This

compares with current GB practice where transformers are equipped with oil pumps as well as fans (OFAF37

)

and operate with a higher normal demand but have a lower short time overload rating of 130%. Overall there is

little difference between security standards in GB and Ireland. However the sparse network in parts of Ireland

means that for many rural substations there is limited post fault transfer capacity available to adjacent

substations.

Review of 110kV and 38kV (Major Projects)

As part of its response to the Business Plan Questionnaire, the DSO was requested to provide a breakdown of

planned v actual cost details of the major projects (38kV and above) that have been progressed during PR3.

This would have allowed us to carry out a more detailed analysis of a sample number of projects completed

during PR3. The purpose of carrying out a detailed analysis of a representative sample of individual projects is

to assess the reasonableness of costs incurred compared to planned/allowed costs, the reasonableness of the

DSO project delivery process and hence to determine the efficiency of the DSO project delivery and resulting

capex.

However, in its original submission submitted on 31st October 2014, this cost information relating to individual

major projects was not provided. In its revised submission of 5th December 2014 this cost information relating to

individual major projects was not provided.

On 18th December 2014, we received a list of individual 38kV and 110kV major projects. The list provided the

total capex incurred on 81 reinforcement projects over the period of 2011 to 2013. It did not provide any

information relating to the forecast capex during PR3 (and beyond) to complete each of these individual

projects. It did not provide any information of actual costs incurred on these projects during PR2 nor did it

provide any information on the total planned/approved capex for each of the projects. This lack of information

restricted our ability to carry out any detailed analysis.

On 16th February 2015, we received further detailed cost information in relation to a sample of 11 major 38kV

and 110kV reinforcement projects that are expected to be completed in PR3 period (hence no forecast costs

beyond 2015) and we have analysed the information provided. Both the delays in providing the required

information and the fact that information was only provided for a small sample of projects rather than all major

projects is disappointing. We would have expected the project information requested to be generally available

within the DSO and find the prolonged delay in providing this information to be a concern. This is standard

information that we would expect the project managers to be using on a routine basis to manage and control

project delivery and associated costs. Given the time the DSO has had to provide such information, we consider

that their inability to provide such information to the CER in a timely manner to be an area of weakness that

requires improvement during PR4.

35

ONAN – Oil Natural-Air Natural cooling system for transformer 36 ONAF – Oil Natural – Air Forced cooling system for transformer

37 OFAF - Oil Forced-Air Forced cooling system for the transformer

Page 72: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 67

Table 4.13 below summarises the major project information provided.

Table 4.13 : Summary of DSO Major Reinforcement Projects

DSO Reinforcement Major Projects – Summary Data

Total Number of 38kV and 110kV Reinforcement Projects 81

Total Capex (2011-2013) on these projects (2009 Prices) €137.4m

Total Forecast Capex (PR3) on these projects (2009 prices) €219.4m

Sample Projects – Summary Data % of PR3 total

projects

Total Number of Sample Projects (selected by ESBN) 11 13.6%

Total Capex (2011-2013) on these projects (2009 prices) €45.3m 32.9%

Total Forecast Capex (PR3) on these projects (2009 prices) €58.1m 26.5%

Proportion of capex to be incurred in 2014 & 2015 22.0%

Proportion of capex to be incurred in 2015 only 6.7%

The DSO has provided details for a representative sample of projects in terms of the number of projects (13.6%

of total number) and their proportionate contribution to PR3 capex (32.9% of actual capex over period 2011 to

2013, 26.5% over the full PR3 period). It should be noted that the sample projects for which information has

been provided, were selected by the DSO.

The DSO is forecasting to complete all 11 projects within PR3 with 93% of costs fully incurred by end 2014 -

2015 forecast capex is relatively low, suggesting that the majority of costs have already been incurred. Details

of the 11 projects are presented in Table 4.14 below.

Table 4.14 : DSO Sample Reinforcement Projects- Analysis of Capex

Project Project Name

Actual Total

Spend PR2

PR3 Total

Spend

Grand Total

IA Cost

Forecast for Price Review

Cost

Capital Approval Amount ex IDC

Variance: Grand Total to Capital

Approval Amount excluding IDC

€M €M €M €M €M €M €M %

N-D-0952 Longford 38kV Stn Uprate 4.8 0.4 5.2 2.6 0.0 5.3 -0.1 -1.6%

H-I-0630 Caherdavin 38kv Stn uprate 2.7 0.4 3.1 1.2 4.6 3.2 -0.1 -3.9%

N-D-1401 Purcells Inch 38kV Station Uprate 1.9 0.6 2.5 1.5 0.0 3.0 -0.5 -17.6%

N-D-1461 Uprate Oakfield 38kV stn 2.3 0.6 3.0 2.3 0.0 3.2 -0.3 -8.3%

N-D-1118 Uprate Bushfield 38kV Station 2.2 0.9 3.1 2.4 0.0 3.2 -0.1 -2.5%

H-I-0707 Cong to Ballinrobe 38kV line 0.0 1.1 1.1 0.6 1.9 1.2 -0.1 -9.1%

N-D-1405 Uprate Blessington 38kV Station 1.9 1.3 3.2 1.6 0.0 3.2 0.0 -0.8%

N-D-1150 Inchicore 220kV Stn T2106 7.4 4.7 12.0 7.4 0.0 12.4 -0.4 -3.2%

N-D-0754/ H-I-0577

Connemara 110kV Reinforcement Project/Screeb

4.1 46.3 50.4 33.2 36.7 51.3 -0.8 -1.6%

H-I-1083 Doon 110kV station 0.7 0.7 1.4 1.1 0.0 1.6 -0.2 -11.1%

N-D-1027 College Park 3rd 110/MV trafo 1.1 1.1 2.2 0.9 0.0 1.3 1.0 78.6%

Page 73: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 68

TOTAL 29.1 58.1 87.2 54.7 43.2 88.8 -1.6 -1.8%

It should be noted that we have not been able to present the capex figures in the above table in 2009 prices as

the costs provided by the DSO did not readily allow for the application of appropriate inflation adjustments. For

example:

The PR2 total capex is the sum of PR2 capex in nominal terms – we do not have yearly breakdown to

which we could apply inflation adjustments to convert to 2009 prices.

The Investment Appraisal (IA) Costs are Prime Costs and are stated in whichever year the IA was

prepared. The DSO states it is likely that for most of the projects the year will be 2007/08 although we have

not been provided with details of which year is appropriate for each project and hence we have not

adjusted to 2009 prices.

The Capital Approval (CA) costs are Gross Costs and these are stated in the year in which the CA was

prepared. The DSO indicates this would vary between 2006 and 2011 although we have not been provided

with details of which year for which project and hence we have not adjusted to 2009 prices.

The DSO has provided annual capex for each project during PR3 and so we have converted to 2009 prices

For 10 of the 11 projects, we have observed that the DSO is forecasting total costs (PR2 and PR3) that are

lower than the Capital Approval Amount – with variances in the range of €0.1m to €0.8m.

For the remaining major project (N-D-1027), we observe that the DSO is forecasting a total cost (PR2 and PR3)

which is higher than the Capital Approval amount by €1.0m.

However as the lack of cost granularity has limited our assessment on a constant 2009 price base, conclusions

made from any comparison of projects costs need to recognise this cost base inconsistency. We have not

investigated the reasons behind any variance in total costs v CA costs nor has the DSO provided any variance.

It was also our intention to request a sample number of post investment appraisal document for a

selection of completed major projects. The DSO has advised us that they do not presently carry out a

formal post investment review of individual projects and hence no documentation was available for us

to review.

We consider this gap to be an area for improvement within the DSO project delivery process – this has

been recognised by the DSO, who has stated their plans to introduce this improvement over the

coming months.

However, the DSO has provided a supporting narrative document (DH02 – PR3 Load Driven Programme) that

provides detailed commentary of investment during PR3 – this has allowed us to make a quantitative

assessment of non-financial project outputs.

Many of the projects identified for delivery during PR3 have been deferred due to the negative load growth.

Some of the projects completed by the DSO during PR3 are those projects that were carried over from PR2.

There were also four additional 110kV projects that had not been identified by the DSO at the time of their PR3

submission, each relating to a separate major commercial data centre in the Dublin area.

The total transformer capacity (MVA) and HV circuit lengths (km) added during PR3 period, compared to the

CER allowed values (PR3 forecast) is shown in Table 4.15 below.

Table 4.15 : DSO Reinforcement: Summary of PR3 Additional Capacity / Assets added to Distribution System

Asset Type Unit PR3 Forecast

Volumes

PR3 Actual

Volumes Variance %

220/110kV Transformers MVA 500 500 0.0%

110/38kV Transformers MVA 378 346.5 -8.3%

Page 74: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 69

Asset Type Unit PR3 Forecast

Volumes

PR3 Actual

Volumes Variance %

110/MV Transformers MVA 451.5 323 -28.5%

110kV lines km 107 96 -10.3%

110kV cables km 47 25.9 -44.9%

38kV/MV transformers MVA 427 417.8 -2.2%

38kV lines km 272 128.2 -52.9%

38kV cables km 26 22.7 -12.7%

Convert 10kV network to 20kV

operation km 15000 10000 -33.3%

Analysis of the above volumes, together with the variance in capex for 110kV reinforcement projects / assets is

presented in Figure 4.9 below.

Figure 4.9 : 110kV Reinforcement Work Volumes – Variance Analysis – DSO Actual for PR3 compared to CER Allowances

The DSO forecast capex for 110KV reinforcement projects is 39% lower than CER allowed costs. The variance

in transformer capacity commissioned during PR3 period is in the range of 0% to 28.5% lower whilst the

variance in 110kV lines and cable kilometres is 10.3% and 44.9% lower respectively.

This analysis suggests that the reduction in DSO forecast capex for 110kV reinforcement projects is

higher than the equivalent volume reductions in transformer capacity or circuit km commissioned

(other than 110kV cable).

This disparity will be partly due to a number of projects being completed in PR3 that commenced in

PR2 period; with the costs incurred on these projects during PR2 being added to the DSO RAB during

PR2.

0.0%

-8.3%

-28.5%

-10.3%

-44.9%

-39%

-50.0%

-45.0%

-40.0%

-35.0%

-30.0%

-25.0%

-20.0%

-15.0%

-10.0%

-5.0%

0.0%

220/110kVTransformers

110/38kVTransformers

110/MVTransformers 110kV lines 110kV cables 110kV Capex

Page 75: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 70

We have carried out a similar analysis of variance in DSO volumes/capex for 38kV projects. This is illustrated in

Figure 4.10 below.

Figure 4.10 : 38kV Reinforcement Works – Variance Analysis – DSO Actual for PR3 compared to CER Allowances

The DSO forecast capex for 38kV reinforcement projects is 60% lower than CER allowed costs. The variance in

38kV transformer capacity commissioned during PR3 period is only 2.2% lower whilst the variance in 38kV lines

and 38kV cables is 52.9% and 12.7% lower respectively.

The analysis suggests that the reduction in DSO forecast capex for 38kV reinforcement projects is

higher than the equivalent volume reductions in transformer capacity or circuit km commissioned.

Again, this disparity will be partly due to a number of projects being completed in PR3 that

commenced in PR2 period; with the costs incurred on these projects during PR2 being added to the

DSO RAB during PR2.

Since 2010, the GB DNO’s have been reporting on substation loading by using a set of Load Indices, allowing

the companies to demonstrate the network risks and the effectiveness of their investments to manage peak

loading at its major substations. We consider the use of Load Indices to be good practice. Although the DSO

does not presently use Load Indices to track movement in peak demand on its major substations resulting from

its capex investment, during our meeting with the DSO in early December 2014, they have explained they are

considering adopting the use of load indices – we would support such an improvement.

However, the DSO has provided details that summarise the historic trend regarding the overloading of its

population of 38kV substations. This is provided in Table 4.16 below.

Table 4.16 : Historic Trend of 38kV Overloaded Substations

Indicator 2000 2005 2010 2015 (Forecast)

38kV Substations normally overloaded 68 65 72 32

38kV Substations normally loaded above 75% 213 190 150 75

It is noted that the reported numbers are derived based on the nameplate rating of the substation transformers.

Using the Planning policy (which permits 180% loading of single transformer nameplate rating under

N-1 conditions for dual transformer stations), the DSO has forecast that a total of 48 of their population

of 38kV stations will be outside Planning Standards by the end of PR3 (rather than 32 loaded above

-2.2%

-52.9%

-12.7%

-60%

-70.0%

-60.0%

-50.0%

-40.0%

-30.0%

-20.0%

-10.0%

0.0%38kV/MV transformers 38kV lines 38kV cables 38kV Capex

Page 76: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 71

nameplate rating).

These stations will require further attention during PR4 and will be a consideration within the review of

DSO forecast capex.

The DSO network planning standard relating to security of supply is not aligned with the GB DNO Security

Standards (Engineering Recommendation P2/6) with respect to load bands and the amount of load that could

be disconnected for a period following an (n-1) fault although the format and principles applied are the same.

The application of a short duration emergency rating of 180% by the DSO is more onerous than typical ratings

applied in UK (~130%) and consequently reduces the DSO reinforcement need and resulting capex.

The capacity margin of a substation is defined as the excess of capacity over demand taking the capacity of a

substation to be 180% of the installed name plate transformer rating. Capacity margin is a measure of the spare

capacity that is available at individual substations and on the network overall. Analysis of transformer utilisation

and capacity margin over PR3 period is detailed in Table 4.17 below.

Table 4.17 : PR3 Movement in Capacity Margin at DSO Substations

110/38kV Stations 2010-11 2011-12 2012-13 2013-14 2014-15 5-year Change

MVA %

Aggregated Demand (MVA) 4326 3867 3801 3669 3698 -628 -15%

Aggregated transformer capacity (MVA) 6806 6900 6932 6932 7058 252 4%

Utilisation 63.6% 56.0% 54.8% 52.9% 52.4%

Capacity Margin 57% 78% 82% 89% 91%

110/MV Stations

Aggregated Demand (MVA) 782 738 759 738 738 -44 -6%

Aggregated transformer capacity (MVA) 1681 1761 1761 1841 1921 240 14%

Utilisation 46.5% 41.9% 43.1% 40.1% 38.4%

Capacity Margin 115% 139% 132% 149% 160%

38/MV Stations

Aggregated Demand (MVA) 3841 4237 3662 3405 3430 -411 -11%

Aggregated transformer capacity (MVA) 5496 5601 5618 5658 5822 326 6%

Utilisation 69.9% 75.6% 65.2% 60.2% 58.9%

Capacity Margin 43% 32% 53% 66% 70%

Note 1: The capacity figures exclude transformer installed and exclusively used for renewable generation.

Note 2: The aggregate capacity shown is the actual capacity installed. The change from year to year is inclusive of new capacity installed net of capacity retired.

Note 3: There are now a number of transformers on the system that are shared between load and generation and that have been changed to larger unit sizes to accommodate generation. This has the effect of showing a reduced load utilisation. The quantity of such transformers is relatively small at present but is growing with the increased level of renewable penetration.

It is observed that the DSO investment made over PR3 period to reinforce those parts of the network which

were already non-compliant with the Planning Standards, coupled with reduction in system peak demands has

resulted in a reduction in utilisation across all voltage levels.

Page 77: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 72

For 110/38kV Stations, there has been a 15% reduction in aggregate demand over PR3 with a 4% net

increase in aggregated transformer capacity, thus resulting in an overall reduction in transformer utilisation

and increased capacity margin.

For 110/MV stations, there has been a smaller reduction in aggregate demand over PR3 of 6% with a 14%

net increase in aggregate transformer capacity.

For 38kV/MV stations, the reduction in aggregate demand is 11% with a 6% increase in aggregate

transformer capacity.

The 5-year net change in aggregated demand on the stations, together with net change in aggregate

transformer capacity is illustrated below in Figure 4.11.

Figure 4.11 : PR3 Net Change in Aggregate Station Demand v Capacity

Review of DSO 20kV Conversion Programme

The DSO has continued its programme to convert its 10kV network to 20kV operation, albeit at lower volumes.

Conversion of the networks to 20kV has benefits, specifically the capacity of an uprated line is increased by a

factor of 4 and for the same capacity the losses are reduced to one quarter.

In PR1, a total of 18,000 km had been converted to 20kV operation. By the end of PR2, a further 19,000 km

was converted to 20kV. As detailed in Table 4.15, the PR3 forecast volume for this activity was 15,000km. The

DSO has reported that by the end of PR3 a total of 10,000km will be converted to 20kV, resulting in a

cumulative total of 47,000 km of network converted.

We have satisfied ourselves that the DSO has in place an appropriate cost-benefit and prioritisation process,

with the CBA considering the impact of losses on the network, together with improved network voltage. 90% of

the network conversions have been required due to voltage deficiencies of the network.

Analysis of the PR3 volumes, together with the variance in capex for the 20kV conversion programme is

presented in Figure 4.12 below.

-628

252

-44

240

-411

326

-800

-600

-400

-200

0

200

400

Total MVA Demand (MVA)Total transformer capacity

(MVA)

110/38kV Stations 110/MV Stations 38/MV Stations

-15%

4%

-6%

14%

-11%

6%

-20%

-15%

-10%

-5%

0%

5%

10%

15%

20%

Total MVA Demand (MVA)Total transformer capacity

(MVA)

110/38kV Stations 110/MV Stations 38/MV Stations

Page 78: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 73

Figure 4.12 : 20kV Conversion Works – Variance Analysis – DSO Actual for PR3 compared to CER Allowances

The reduction in capex associated with the 20kV conversion programme is consistent with the reduced

circuit lengths converted during PR3 and it appears to be efficiently incurred.

MV/LV System Reinforcements

The DSO is forecasting that capex associated with other MV/LV System improvements during PR3 will outturn

at €35.5m. This is approximately 51% less than the CER allowed capex of €69.1m for this programme of work.

The DSO cites the reduction in demand since 2008 combined with the major investments made in previous

price control periods in the MV and LV renewal programmes as both contributing to the continued reduction in

the scale of investment observed during PR2 and PR3.

The scale of reduction in DSO capex during PR3 for MV/LV system improvements is consistent with

the overall reduction in PR3 load related reinforcement expenditure (being 50% of CER allowed capex)

4.2.4 Dismantling Costs

In relation to dismantling (retirement) costs, CER allowance for PR3 period was €57.4m. This value was derived

based on an a priori assumption that dismantling costs were directly proportional to the gross cost of load driven

reinforcement and non-load related network capex. The PR3 allowed costs were based on 4.8% of this gross

value.

ESBN’s accounting practice for dismantling costs historically has been to treat these as opex, with costs

included within the Income Statement. However, the CER has previously proposed a change to the regulatory

treatment of dismantling costs to treat these costs as Capex rather than opex – this change was made at PR2

determination and capital expenditure in PR3 was allowed on this basis.

The DSO has continued its practice of charging dismantling costs to its Income Statement for years 2011 to

2013 and proposes a change in Accounting Practice for the remaining two years of PR3 such that the costs are

allocated to capital. Our analysis of DSO dismantling costs has been carried out on a total cost basis, as shown

in Table 4.18.

-33.3%

-39%

-40.0%

-39.0%

-38.0%

-37.0%

-36.0%

-35.0%

-34.0%

-33.0%

-32.0%

-31.0%

-30.0%

Convert 10kV network to 20kV operation -Volume Variance (Circuit km)

20kV Conversion (including IFTs) - CAPEXVARIANCE (%)

Page 79: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 74

Table 4.18 : Comparison of DSO Dismantling Costs (€m 2009 prices)

2011 2012 2013 2014 2015

5 Year

Total

CER Allowed Capex 11.8 11.6 11.5 11.3 11.2 57.4

DSO Actual / Forecast (See Note 1) 9.1 9.7 18.7

DSO Actual / Forecast (See Note 2) 11.6 8.8 7.9 28.4

Total DSO Actual (Dismantling) 11.6 8.8 7.9 9.1 9.7 47.1

Variance % -1.3% -23.8% -31.3% -19.9% -13.7% -17.9%

DSO Actual / Forecast of Load Related Reinforcement and Non-

Load Related Capex 213.5 113.4 119.9

135.6 149.8 732.2

Dismantling as % of Load Related Reinforcement and Non-load

related capex 5.5% 7.8% 6.6%

6.7% 6.5% 6.4%

Note 1 – Source data from Table 6.3 (ESBN Distribution – Planned & Forecast Capex)

Note 2 – Source data from Table 5.1 (ESBN Distribution- Breakdown of Actual & Forecast OPEX)

Based on the above, the following observations can be made:

Total dismantling cost over the PR3 period is forecast at €47.1mm, 17.9% less than the CER allowed

capex of €57.4m

This reduction is much less than the corresponding DSO reduction in capex relating to reinforcement and

non-load related capex.

The actual dismantling costs as a proportion of the reinforcement plus non-load related capex for years

2011 to 2013 are higher than the percentage allocation basis of 4.8% used in the setting of allowances for

PR3, with annual values in the range 5.5% to 7.8% and a three year average of 6.4%. The DSO has

provided further details to support this increase and these are itemised below.

The DSO has introduced revised project costing procedures (Integrated Work Management Module) within their

SAP application from 2009 onwards. This has allowed the DSO to allocate dismantling costs more directly to

the work activity that has driven the need for the dismantling to be carried out. A summary of this cost allocation

provided by the DSO is presented in Table 4.19 below.

Table 4.19 : Allocation of DSO Dismantling Costs over period 2011 to 2013(€m – Nominal)

Note – Source ESBN PR4 Submission – document DH29 PR3 Dismantling/Retirements (Table 4.2)

Page 80: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 75

The DSO made the following points relating to the above analysis38:

It is reasonable to expect the level of dismantling driven spend to vary across different program types

depending on the nature of the asset and the work involved. This is borne out by the various ratios where non-

load capex and line diversions drive significantly more dismantling spend than reinforcement, and new

business.

New Business and reinforcement which account for 2.5% of dismantling costs are down from a combined 65%

of total CAPEX spend in PR2, to 53% in PR3.

On the other hand, non-load capex which drives a further 6.1% of dismantling costs is up from 28% to 36%.

Within that average one would expect that overhead line replacement activities would drive higher dismantling

spend that station refurbishment activities.

In 3 years to date 30% (8.8m) of dismantling cost arose from activities that are not part of the current formula,

particularly New Business and Line Diversions.

We would generally agree with the DSO that the proportion of dismantling costs is likely to vary across each of

the work activities. The change in the DSO cost allocation procedures has provided improved visibility of the

drivers on the dismantling activity and associated costs.

We would expect the DSO dismantling costs over the PR3 period to be charged to capex for the full

five years, this being consistent with CER allowances. This will result in a transfer of €28.4m of costs

from opex (2009 prices) to capex covering the years 2011 to 2013.

4.2.5 Non-Repayable Line Diversion Costs

During PR3, the DSO has allocated the costs of line diversions to capital allocation codes39 in line with agreed

outcome at the PR3 settlement where the CER allowed costs relating to non-rechargeable line diversions for a

total of €51.8m.

Line diversion costs have historically been proportional to capital expenditure in the category of “gross new

demand connections”. For the PR3 period, this allowance was set at a value equivalent to 11.4% of the PR3

forecast capex for new connections. The DSO actual costs for 2011 to 2013, together with forecast to 2015 are

shown below in Table 4.20.

Table 4.20 : Comparison of DSO Line Diversion Costs (€m 2009 prices)

2011 2012 2013 2014 2015

5 Year

Total

CER Allowed Capex 9.8 10.1 10.4 10.6 10.9 51.8

DSO Actual / Forecast 10.6 8.9 8.6 9.6 9.5 47.1

Variance to CER allowed capex (€m) 0.8 -1.2 -1.8 -0.5 1.7 -1.0

Variance to CER allowed capex (%) 8.1% -11.9% -17.1% -9.9% -13.1% -9.0%

Capex as a proportion of New Connections

Capex (Gross) 20.2% 19.2% 21.0% 19.7% 20.0% 20.0%

As described in Section 4.2.1 there has been a significant reduction in new connections capex during PR3

period, although it is evident that the rate of expenditure associated with asset diversions has not reduced to the

38 Document DH29 – PR3 Dismantling / Retirements 39 During previous PC periods, the costs associated with line diversions had been treated by the DSO as an operating cost.

Page 81: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 76

same levels. The actual diversion costs over 2011 to 2013 are in the range of 19.2% to 21% of the gross

connections capex over the same period.

The DSO cites this higher rate being driven by an underlying “bank” of diversion works that is required, which

has become more clearly evident with the connections expenditure reducing to the current outturn levels. The

DSO has carried out regression analysis over the PR2 and PR3 period to identify more accurately the

relationship between connections capex and diversions capex.

In its response (DSO report DR01) to our Interim Report, provided the DSO revised forecast of line

diversions capex for the remaining two years of the PR3 period suggests costs in the range of 20% for

the remainder of PR3- these values are broadly consistent with the first three years of PR3 and are

considered reasonable.

4.3 Non Load Related Capex

The DSO non-load-related capex for the PR3 period is shown in Table 4.21 below.

Table 4.21 : Comparison of PR3 Costs v CER Allowances Non- Load Related Capex (€m 2009 prices)

Category 2011 2012 2013 2014 2015 5 Year Total

CER Allowed Non-load

related Capex 115.8 114.3 112.9 111.5 110.2 564.7

DSO Actual / Forecast 120.7 58.4 62.8 85.9 87.5 415.3

Variance 4.9 -55.9 -50.1 -25.6 -22.7 -149.4

% Difference 4% -49% -44% -23% -21% -26%

The DSO expects a total non-load related capex of €415.3m by end of PR3 – this is €149.4mm lower than the

CER allowed non- load-related capex of €564.7m – representing a variance of 26%. This DSO forecast is

€29.4m higher than the revised proposal of ESBN (€387m40) submitted to CER in 2012 (see Figure 4.13 below)

but it should be noted that this forecast includes for a one-off capex of €26.8m in 2014 associated with Storm

Darwin and it also includes a significant increase in capex for year 2015 (relative to 2012 and 2013).

40 €433m less forecast retirement costs (considered separately) of €46m

Page 82: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 77

Figure 4.13 : Summary of PR3 Non Load Related Capex

Table 4.22 below provides an itemised breakdown of the DSO non-load related capex over PR3 period,

compared to the CER allowed capex for each of the categories. It should be noted that the ESBN Proposed

revisions to the capex in 2012 were provided at an aggregated level (totalling €387m) and were not

broken down into the individual categories shown below.

Table 4.22 : Comparison of PR3 Non-Load Related Investment (€m 2009 prices) by Category

Investment Category CER Allowed DSO Actual Variance

PR3 TOTAL PR3 TOTAL €m %

Renewal Programme - 110kV & 38kV Lines 16.3 15.1 -1.2 -7%

Renewal Programme – 110kV & 38kV Cables 20.5 6.0 -14.5 -71%

Renewal Programme - HV Substation 117.5 75.3 -42.2 -36%

Renewal Programme - MV Overhead Lines 69.0 59.5 -9.5 -14%

Renewal Programme - MV Cables 2.5 1.9 -0.6 -23%

Renewal Programme - MV Substations 24.1 30.5 6.4 27%

Renewal Programme - Urban LV Renewal 62.8 35.3 -27.5 -44%

Renewal Programme - Rural LV Network 93.5 82.1 -11.4 -12%

Renewal Programme - LV cables and associated items 16.8 6.1 -10.7 -64%

Renewal Programme - Cutouts 5.7 5.7 3.9 -1.8

Continuity Improvement 22.3 22.3 13.7 -8.6

Response capex 98.7 98.7 55.1 -43.6

System Control 15.0 15.0 3.8 -11.2

Storm Darwin Rectification Project 0.0 26.8 26.8

Total 564.7 415.3 -149.4 -26%

It is noted from Table 4.21 above that the DSO non-load related expenditure in 2011 was broadly consistent

with CER allowed costs for the year, albeit slightly higher.

However from 2012 onwards it is evident that there is a significant negative variance with CER allowed capex

for the PR3 period. This reduction in expenditure was proposed by the DSO to CER in 2012 as part of its overall

plan to reduce its capital expenditure given the difficulty in bond funding at the time, and the impact of DUoS

564.7

386 415

0

100

200

300

400

500

600

5 Year Total

€m

CER Allowed Capex ESBN Proposal (2012) DSO Actual / Forecast

Page 83: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 78

charges that would otherwise be experienced by its customers resulting from the reduction in consumption over

the PR3 period.

The reduced expenditure was only achievable by deferring large proportions of planned asset renewal works

with the reduced forecast being derived by the DSO following a detailed and prioritised assessment of key

criteria, including safety, environmental impact, probability of plant failure, asset criticality and practicability of

deferring works.

The DSO’s revised PR3 forecast of 2012 for non-load related expenditure was €385.9m. Its latest PR3

forecast of €415.3m is broadly consistent with its revised 2012 forecast of €385.9m if the 2014 costs

associated with Storm Darwin, at €26.8m, are netted off. It should be noted that the PR3 forecast

proposes for a significant increase in capex for year 2015, relative to previous years 2012 to 2014.

Certain asset replacement projects were deferred in whole or were scaled down based on the DSO’s

prioritisation process. Additional commentary relating to each of the main categories itemised within the above

Table 4.22 is provided in the sub-sections below:

4.3.1 Renewal Programme

4.3.1.1 110kV & 38kV Lines

CER PR3 allowed capex of €16.3m, although the DSO current forecast for this programme is €15.1m

representing a reduction of 7%.

38kV line refurbishment: In PR3 a nine-year 38 kV overhead line refurbishment cycle was approved. The work

involves inspection and refurbishment of the 38 kV network, with the cycle aligned to the hazard patrols, tree

cutting cycles and the MV overhead cyclical refurbishment programme.

The 5-year PR3 target for this programme was 2,321km, however by Q3-2014 the DSO has completed

approximately 52% of this target (~1,220km). By the end of PR3, the DSO is targeting completion of a further

1,000km using a mix of internal resources (300km) and contractor resources (700km), increasing the total km

during PR3 period to 2,221km (representing 96% of the original PR3 target).

There is a significant risk that this volume of work associated with the 38kV OCR programme is not

delivered in 2015 – it represents a significant increase in volumes previously delivered and is heavily

dependent on contractor resources being in place and fully operational. Whilst the DSO also

acknowledges the 2015 volumes represent a significant increase in the rate of delivery, it considers its

2015 forecast to be reasonable, citing contractor resource availability to deliver the majority of the

work programmes.

110kV line refurbishment: The original PR3 programme also included for the re-conductoring of four 110kV

circuits (23.7 km) within the greater Dublin area. The DSO deferred this programme in full during PR3 period

due to an engineering issue and initiated annual helicopter flying patrols of the four lines and periodic IR

imaging.

The PR3 programme associated with the 110kV lines outside of the Dublin area catered for minor refurbishment

of four 110kV circuits (total length 33km). The DSO deferred this programme in full during PR3 period and

initiated ongoing hazard patrols of these circuits.

38kV line – Covered Conductor: The PR3 programme for the use of covered conductor on 38kV line was

targeted to replace 20km of bare conductor. The DSO has modified this from a proactive programme of

replacements, to a fully developed standard technical solution to address problem 38kV feeders on a reactive

basis. Consequently only a small number of pilot projects have been completed during PR3.

Page 84: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 79

38kV Copper Overhead Line Replacements: The DSO is reporting a further €1.9m of capex associated with

the replacement of 38kV copper overhead lines that was largely completed during PR2 period.

For PR3, the allowed capex for HV Overhead Line Replacements was €16.3m and the DSO latest

forecast is €15.1m, representing 93% of allowed capex.

The DSO states that the 38kV OCP programme will be substantially completed, although this is

dependent on the delivery of 1,000km during Q4, 2014 and end of 2015.

The reduction in capex by deferring 110kV line works has been largely offset by the additional capex

associated with 38kV copper overhead line replacements.

Generally, the PR3 costs are broadly consistent with the PR3 volumes delivered.

4.3.1.2 110kV & 38kV Cables

CER PR3 allowed capex of €20.5m, although the DSO current forecast for this programme is €6.0m,

representing a reduction of 71%.

During PR3, the 110kV fluid-filled cable replacement programme was originally focused on the replacement of

the Inchicore – Francis St circuit (total circuit length of 5.6km, of which 3,8km runs alongside the Grand Canal).

The DSO has deferred replacement works for this circuit until PR4. Replacement of this cable has been

previously justified partly to address the number of oil leaks from the cable.

Deferment of the programme therefore has introduced environmental and network reliability risks that the DSO

has addressed by the introduction of the use of perfluorocarbon tracing (PFT) gas technology to find leaks in a

much quicker and more efficient manner.

The programme associated with the replacement of 9 km of gas compression 110 kV cables supplying Milltown

in Dublin has been deferred. The works were previously deemed necessary to address deterioration and

leakage of the cable pipeline. The DSO has made further use of the PFT technology to manage cable leaks and

reduce outage periods.

The programme for the replacement of 38kV Fluid-Filled Replacement during PR3 period has been significantly

deferred by the DSO. The original programme was to replace a total of 10% of the total 38kV fluid-filled cable

population of 80km. However, works completed during the PR3 period has been restricted to the completion of

projects that commenced in PR2 period.

The programme relating to the replacement of 15 sets of defective oil filled 110KV and 38kV cable terminations

has been deferred with no works completed during PR3.

The PR3 programme for the replacement of 38kV cable consisted of four circuits with total length of 17km.

These circuits supply critical Dublin City substations. Works were completed during PR3 on the two Kimmage

circuits (total length of 8.9km).

For the other two 38kV circuits, limited progress has been made during PR3 with remaining works proposed for

completion during PR4. For the Leeson St – Milltown circuit, the ducting and cabling has been completed, but

no jointing has been progressed. For the Merrion Sq – Milltown circuit, the cable route has been partially ducted

and cabled, although no jointing completed.

A project to replace a section of 110kV XLPE cable that is routed through private property and close to the

foundations of houses along the Taney – Central Park 110kV feeder route involved the installation of 600m of

cable rerouted in a safer location has been progressed by the DSO and it is forecasting completion by the end

of 2015.

Page 85: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 80

The DSO has deferred significant capex during PR3 associated with 110kV and 38kV cable

replacement projects. The reductions in work volumes stated by the DSO are broadly consistent with

the reduced capex.

4.3.1.3 HV Substation

CER PR3 allowed capex of €117.5m, although the DSO current forecast for this programme is €75.3m,

representing a reduction of 36%.

Siemens 38kV station replacements: the planned replacement of five Siemens 38kV substations during PR3

has been significantly deferred, with only two of the five now forecast to be fully completed by end of 2015.

Works are in progress at all five stations, summarised below:

Cloonbanin – originally deferred, although subsequently reinstated into the renewal programme; civil works

commenced in early 2014 and scheduled for completion by end 2015;

Newtown St Alban – originally deferred, although subsequently reinstated into the renewal programme;

work is in progress but will not be completed until PR4 period (2016)

Garryowen – originally deferred, although subsequently reinstated into the renewal programme; scheduled

for completion by end 2015;

Mount Misery - originally deferred, although subsequently reinstated into the renewal programme; some

work completed in 2013 although subsequently de-prioritised – now scheduled for completion in PR4

period (2016);

Lake – this station is being retired with load transferred to Dunmanway 110kV station. Project is in

progress, with scheduled completion date of mid 2016

The DSO continues to have operational restrictions in place for these types of station such that the 38kV

line disconnectors within the station must not be operated live.

Replacement of Convoy ‘Wood Pole’ 38kV Station: Originally scheduled for PR3, the DSO has deferred this

project completely and work is not scheduled to start by the end of PR3 period. The DSO has provided

explanation on additional mitigation actions carried out to assess the degree of rot appertaining to the wood

pole supports within the station. Based on the specialist pole testing carried out in 2013, the DSO has been able

to make an informed decision to defer works.

Pembroke 38kV Station – MV Switchgear Replacement: The replacement of the compressed air operated

switchgear was originally scheduled for PR3, the DSO has deferred this project completely and work is not

scheduled to start by the end of PR3 period. Asset Risk Management Plans are in place for this substation to

address the ongoing risks until the equipment is replaced.

Bedford Row Station – 38kV and MV Switchgear Replacement: The station is now over 80 years old and the

switchgear is based on long outdated technology. The replacement of the switchgear was originally scheduled

for PR3, the DSO has deferred this project completely and work is not scheduled to start by the end of PR3

period. Asset Risk Management Plans are in place for this substation to address the ongoing risks until the

equipment is replaced.

Kilbarry – 38kV Switchgear Replacement: During PR3, it was proposed to replace the existing 38kV

switchgear and associated control and protection with a GIS module with integrated protection and modern

substation control system. The DSO has deferred this project completely and in late 2014 has reinstated this

project into the replacement programme, although it is unlikely that detailed works will be progressed on site.

Asset Risk Management Plans are in place for this substation to address the ongoing risks until the equipment

is replaced.

Ardnacrusha Station – 38kV Switchgear Replacement: During PR3, it was proposed to replace the existing

38kV switchgear and associated control and protection with a GIS module with integrated protection and

modern substation control system. The DSO deferred works at this station for a short period as it was decided

that the risks associated with this station could be managed for a short period of deferral. Work is not scheduled

Page 86: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 81

to start by the end of PR3 period. Asset Risk Management Plans are in place for this substation to address the

ongoing risks until the equipment is replaced.

38kV & 10kV CB Replacements: The majority of the DSO sub-transmission and distribution substations

comprise of outdoor air insulated switchgear. A programme of replacement was allowed for during the PR3

period. However, the total volume of CB replacements during PR3 has been reduced significantly, with the

exception of like-for-like 38kV CB replacements (with no protection relays included in replacement scope). This

can be seen in Table 4.23 below.

Table 4.23 : HV Substation Allowed and Forecast Replacement works

Activity PR3 allowed PR3 Forecast

38kV Outdoor / Indoor CBs only -like for like 10 41

38kV Outdoor / Indoor CBs & EM Relays 70 18

10kV Outdoor / Indoor CBs & EM Relays 100 13

A prioritised programme of replacement has been progressed by the DSO, with an integrated scope being

established for each station, taking due account of asset replacement, protection upgrades, fabric works and

other related station works being deemed necessary.

Replacement of Reyrolle Type ‘C’ 10kV Switchgear: Four switchboards were scheduled for replacement

during PR3. A decision was taken early in PR3 to defer works at these four stations. Although no on-site works

have been progressed at any of the four stations, the DSO has identified that there is a considerable risk with

two of the stations if the replacement works do not get completed in the near future.

The DSO is progressing replacement works at Marrowbone Lane and Glasnevin. It is expected that

Marrowbone Lane will be completed between mid-2015 and the end of 2016. Glasnevin is likely to follow a

similar timescale.

Protection Upgrades: Work was originally prioritised into two specific categories:

Priority 1, inadequate primary earth fault protection

Priority 2, slow or unreliable fault protection

The DSO has reported that the volume of protection relay replacements completed in PR3 is significantly lower

than the programme put forward for PR3. Compared to PR3 planned volumes, approximately12% of the priority

1 protection upgrades and 8% of the priority 2 upgrades have been completed in PR3. The replacement

programme completed during PR3 has been based on a prioritised programme of work. The shortfall in volumes

delivered during PR3 will need to be addressed during PR4.

Battery Replacement at HV Stations: During PR3 it was planned to replace battery equipment at 15 of their

major substations. The DSO reports that during PR3, four 220V batteries and five 110V have been replaced

and forecast that all batteries will be replaced by the end of PR3 period.

In addition a large scale programme of replacement of 24V batteries, housed in outdoor cubicles was scheduled

for PR3 period. The DSO is forecasting to complete this programme in full by the end of PR3.

Replacement of HV Transformers: The original PR3 programme catered for the replacement of three 110kV

transformers and 69 x 38kV/MV transformers (of capacity less than 3.2 MVA).

In relation to the 110kV transformers replacement, the DSO adopted a reactive based programme during PR3.

This initially deferred planned works and subsequently resulted in a change in the specific sites that

replacement works were carried out. The DSO decided to replace transformers at both Francis St T-142 and

Blake T-142, thus deferring Dungarvan T-141 and Thornsberry T-142. The replacement of Drumline T-142 is

still included within the DSO programme.

Page 87: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 82

The justification for the revised programme would appear to be reasonable and the DSO has made use of a

31.5MVA transformer at Blake that has been recovered from the system (ex Carlow station), demonstrating

efficient use of retired assets. Further, the DSO plans to make use of a recovered transformer for redeployment

at Drumline T-142 although plans are not yet firmed up regarding specific site form which the unit will be

recovered. This uncertainty adds some doubt to this planned scenario materialising during PR3.

Replacement works at Blake were completed in 2012/13; works at Francis St T-142 is scheduled for completion

in 2014/15.

The programme to replace the 69 No. 38kV/MV low capacity transformers has been significantly deferred during

PR3. A total of 15 units are forecast to be replaced by the end of PR3. The DSO has implemented a risk based

prioritisation tool to allow the candidate transformer replacement projects under this program to be ranked and

tracked.

Transformer Bunding retrofit to contain oil leakage: At the beginning of PR3 there was still a large quantity

of legacy transformers that remained unbunded.

The PR3 target was to install 250 retrofit bunds to transformers in 38kV stations and the DSO is forecasting that

197 will be completed by the end of PR3.

For 110kV stations, the PR3 target was to install 30 retrofit bunds to transformers stations and the DSO is

forecasting that 10 will be delivered.

In conjunction with an external supplier, the DSO has developed an alternative bunding solution, using a plastic

bund wall (manufactured using High Density Polyethylene HDPE)

Ground Potential Rise (GPR) Mitigation: The DSO reports that the programme to mitigate risks associated

with GPR has been only partially delivered during PR3.For efficiency reasons, the remedial measures are

generally undertaken in conjunction with other station works (e.g. station upgrades or security fence

replacements).Consequently, the deferral of other station renewal works has impacted on the GPR mitigation

programme, with a reduced volume of works being completed within PR3.

Replacement of 38kV and 10kV ‘Doulton’ Insulator Busbar Supports: The DSO is expecting to complete a

total of 16 units during PR3 out of an allowed total of 30. These works are usually replaced in conjunction with

other station works. The general deferral of station projects has contributed to the reduced volume of

replacement works associated with this activity.

Improved Station Security Programmes: the PR3 programme consisted of works at 70 stations to replace

existing chain-link fencing with palisade fencing. This consisted of 41 distribution sites with the balance at

transmission sites. The DSO has reported that 47 stations have been completed by end 2013, and is

forecasting completion of the full programme (of 70 stations) by the end of PR3.

A programme to install security monitoring systems during PR3 at stations was also planned by the DSO. The

design of security system to be installed has been dependent on the level of risk determined for each location.

The DSO reports that there are now over 50 stations (distribution and transmission) equipped with externally

monitored CCTV systems installed, although it is not clear if the full PR3 programme has been delivered. These

systems have been rented third party systems (opex cost) rather than a DSO owned CCTV systems (capex).

This arrangement was adopted by the DSO as it represented the lower short term cost. However, this short term

approach will need to be re-assessed when considering appropriate allowances for PR4.

The DSO programme to replace station locks during PR3 has been completed.

The programme to replace 110kV and 38kV station wood doors with high security, multi-point locking steel

doors has only been partially completed, with only 20 doors replaced out of PR3 target of 150.

Page 88: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 83

Installation of Emergency Lighting in HV Stations: The programme of works during PR3 has not been

progressed, the DSO having modified its approach to emergency lighting by concentrating in the current period

on the repairs to existing lighting systems.

Renovation of existing HV Substation Control Rooms: The PR3 target was to replace 10 control rooms and

the DSO is forecasting that 7 will be completed. To reduce installation risks and associated costs, the DSO has

developed a prefabricated, floorless, standard control room.

Flood protection in HV Stations: The flood defence programme, originally planned for PR3 period, has not

been progressed by the DSO who reports that work has been progressed during PR3 in developing its strategy

for flood management.

Analysis of the variances detailed above relating to the various components of the HV station renewal

programme, together with the variance in capex for HV station renewal is presented in Figure 4.14.

It is clear that in response to the borrowing constraints during PR3, the DSO has deferred a number of

the higher cost HV station replacement projects / programmes completely, whilst at the same time

focussing on the substantial completion of various safety driven and security driven programmes of

work, typically of a much lower cost.

These two factors contribute to an overall underspend of PR3 capex of 36% relating to the HV Station

renewal programme.

Page 89: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 84

Figure 4.14 : HV Station Renewal Works – Variance Analysis – DSO Actual for PR3 compared to CER Allowances

4.3.1.4 MV Overhead Lines

CER PR3 allowed capex of €69.0m, although the DSO current forecast for this programme is €59.5m

(representing an underspend of 14%).

MV Overhead Cyclic Refurbishment (OCR) Programme: For the PR3 period, the DSO proposed to

commence in 2011 a 9 year cycle of overhead line refurbishment, completing 9,000 km per year (PR3 total of

45,000km) and anticipating a pole replacement rate of 4.8%. This 9 year cycle is the same as for 38 kV and 110

kV lines. The refurbishment programme has been based on a nine year cycle and with the delivery of blocks

coordinated with other maintenance programmes - the 3 year rural MV public safety (hazard) programme and

the MV timber cutting programme.

The DSO reports that the original 9-year cycle is being amended to a 12 year cycle with this change in policy

being risk-assessed. The benefits of previous refurbishment works are resulting in lower volumes of defects

being identified on networks previously refurbished. The change to a 12 year cycle would reduce target volumes

for PR3 period to about 34,500km.

-60%

-100%

-60%

-100%

0% 0%

-78%

-26%

0%

-47%

0%

-100%

-30%

-100%

-36%

-120%

-100%

-80%

-60%

-40%

-20%

0%

Page 90: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 85

The DSO reports that delivery has been below target in PR3 to date, largely due to the challenges associated

with pushing out a new initiative with new standards, documentation and procedures on a national basis. (This

is evidenced by the circuit km refurnished in 2011 of only 5-6% of the five-year programme target).

The DSO also reports its concern about accelerated deterioration of wood poles that were installed on networks

from the late 1990’s. This issue of premature pole rot appears to be specific to Scantrepo poles creosoted

between 1998 and 2003. The DSO has communicated with Swedish utility companies who report similar cases

of premature decay in wood poles sourced from Scandinavia.

The DSO has revised its standard for MV OCR Standard in September 2014 to allow for a more detailed

inspection of certain poles that requires an extra switch-out. This is likely to increase costs for pole inspections

for 2015 and into PR4.

The DSO is reporting that the pole replacement rate is approximately 30 poles per 100km

For the MV OCR programme, the DSO is forecasting the completion of 33,000 km by end of PR3 (i.e.

73% of the original target (45,000km) upon which allowances were made, although it forecasts a spend

of 86% of the PR3 allowance. This increase in unit costs is being driven by higher labour costs being

forecast in 2014 and 2015 - associated with more stringent pole testing procedures.

The forecast includes a target of 14,500km being delivered in 2015 alone, predominantly by using

contract resources, this being subject to completion of the tendering and contract procedures.

Achieving the 2015 target volumes is therefore considered to be a significant challenge to the DSO.

4.3.1.5 MV Cables

CER PR3 allowed capex of €2.5m, although the DSO current forecast for this programme is €1.9m

(representing an underspend of 23%).

The original PR3 programme was based on the replacement of 15km of fault prone XLPE cable. This

programme is inherently reactive with strict criteria being applied by the DSO before an individual cable section

is progressed for replacement.

The DSO is forecasting that approximately 10km of MV cable to be replaced by 2015 – representing an

under-delivery of about 33%, broadly in line with the forecast underspend.

4.3.1.6 MV Substations

CER PR3 allowed capex of €24.1m, although the DSO current forecast for this programme is €30.5m

(representing an overspend of 27%).

Replacement of Indoor Oil-Filled MV RMUs: The PR3 approved replacement programme was to remove all

remaining 305 indoor oil-filled ring main units in indoor substations. The DSO is forecasting that more than 180

units will be replaced by the end of 2015 representing approximately 60% of the programme 5-year target.

The DSO has observed difficulties arising with the replacement works at locations where access to the

substations is difficult and has provided examples of some of the practical challenges they have faced. It is not

uncommon with a large scale station replacement programme in urban areas that some of the more challenging

locations are deferred towards the end of the programme period.

The reduced volume of works has necessitated a prioritised programme of replacements to be established by

the DSO, together with additional hazard patrols being carried out.

Replacement of Open-Cubicle Switchgear in Indoor MV Substations: The PR3 approved replacement

programme was to remove all remaining 369 open-cubicle switchgear in indoor substations for safety and

Page 91: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 86

operational reasons. The DSO is forecasting to complete approximately 300 by the end of PR3, representing

approximately 82% of the PR3 target with a forecast capex of €6.6m, 18% higher than PR3 allowed capex.

Whilst the DSO has reported that a number of the open-cubicle indoor substations with complex configurations

and multiple feeders have been deferred beyond PR3, it also identifies that a large proportion of the stations

have been progressed during PR3 period but at a higher unit cost.

Some of these practical considerations cited include:

Use of mobile generation;

Road Opening Licenses (for cable access and jointing);

Traffic Management;

Relocation of cable joint bays

Temporary Jointing

Site management;

Extensive plant rearrangement

Generator Hire

Crane Hire

Replacement of MV/LV Transformers in Association with Switchgear Replacement: This programme was

approved for PR3 focusing on the replacement of the older population of high loss transformers in stations

where it is proposed to replace MV switchgear (for instance indoor oil RMU or open cubicle switchgear).

A total of 113 station transformers were planned for replacement – in conjunction with the MV switchgear

replacement.

This programme is fully-linked with the replacement programmes for indoor oil-filled and open-cubicle

switchgear. Consequently, a reduced programme of delivery for these switchgear replacement programmes has

also resulted in reduced number of transformers replaced during PR3.

The DSO forecasts approximately 74 units will be replaced by the end of PR3, representing 65% of the PR3

target.

Replacement of Magnefix Cast-Resin type Switchgear: The PR3 approved programme volume was for the

replacement of 100 units. The DSO is forecasting that more than 220 units will be replaced during PR3 period,

representing 223% of the PR3 target.

This additional volume will be carried out during PR3 following reprioritisation by the DSO to address safety

concerns with the Magnefix switchgear and displaced a number of RGB cast resin units originally scheduled for

replacement in PR3.

Replacement of RGB Cast-Resin type Switchgear: The PR3 approved programme volume was for the

replacement of the remaining population of 180 ring main units (RMUs). The DSO is forecasting that

approximately 130 units will be replaced during PR3, representing 73% of the planned programme.

Replacement of Timber Substation Doors: At commencement of PR3, there were approximately 2,500

stations with timber doors in service, in varying states of repair. The current MV substation specification requires

ESB standard galvanised steel doors be fitted to all new stations. The DSO is forecasting full delivery of the

planned volume of substation door replacements by the end of 2015.

Oil bunding of permanent 20 kV interface transformer sites: The transformers located at 20kV/10kV

interface sites are presently unbunded. In order to address environmental risks, the DSO proposed and the

CER allowed expenditure during PR3 to install appropriate bunding to mitigate risk of oil leaking.

Page 92: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 87

However, the DSO has not yet been able to establish a solution that is feasible or acceptable for the exposed

rural station locations, all situated outdoors. These tend to be on land that is privately owned, and controlled

with livestock and vegetation in close proximity to the sites. In addition, the bunding solution will require a

drainages system to allow for water entering the bunded area to be released.

The DSO continues to explore permanent solutions and until such time, the DSO carries out regular inspection

of the interface transformer sites, to identify and rectify impact of any leaks or potential leaks.

Shrouding of LV Panels: The DSO has a number of older distribution substations that have LV panels

consisting of unshrouded LV busbars that present a safety risk to staff working within the stations. The planned

programme for PR3 consisted of shrouding being added to a total of 200 LV substation panels.

Due to the high priority nature of these works to mitigate these safety risks, the DSO has continued with the

programme during PR3 and expects the programme to be substantially delivered.

Substation upgrades with evidence of trespass and illegal dumping: Under this programme, the DSO is

undertaking pro-active works at distribution substation sites to minimise or eliminate the potential for illegal

dumping. The DSO selects sites for inclusion in this programme on a reactive basis, based on defects, condition

or reported hazards during the substation Hazard Patrol programme. The DSO is forecasting that approximately

250 sites will have been subject to various upgrade works during PR3 period, although this is below the

originally planned volume of 500.

Replacement of Underground Residential Distribution (URD) Transformers: The DSO programme to

replace the low kVA capacity single phase distribution transformers has continued in PR3. A total of 102 URD

transformers existed on the system at the start of PR3 period.

The DSO reports that the scope of replacements during PR3 period has been extended such that the

replacement works also include for replacement of the associated LV service vaults because of an inherent

safety risk. This added requirement has increased the complexity and cost of the replacement works. The DSO

has also faced the challenge of having to address the more complex locations as many of the URD

transformers replaced in the previous PR2 period were more straightforward to replace.

The DSO is forecasting that by the end of 2015, approximately 67 URD transformers will be replaced (~66%).

Analysis of the variances detailed above relating to the various components of the MV station renewal

programme, together with the variance in capex for MV station renewal is presented in Figure 4.15.

Page 93: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 88

Figure 4.15 : MV Station Renewal Works – Variance Analysis – DSO Actual for PR3 compared to CER Allowances41

Whilst the majority of programmes have been subject to reduced volumes in PR3, the exception to this has

been in the works associated with:

The replacement of timber station doors and the shrouding of bare LV panels, both of which will be

substantially completed

The replacement of Magnefix cast resin switchgear – where the DSO is forecasting the completion of 223%

of the original PR3 target.

In relation to the MV Station Renewal Programme, the DSO is forecasting an overspend in this

category of 19%.

Any expected reductions in capex due to the reduction in volumes for many of the categories have

been largely offset by increased costs associated with the higher volume of work associated with the

Magnefix Cast Resin Switchgear programme.

4.3.1.7 Urban LV Renewal

CER PR3 allowed capex of €62.8m, although the DSO current forecast for this programme is €35.3m

(representing an underspend of 44%).

The plan for PR3 period was to refurbish 35,000 spans of LV urban networks. This programme was a

continuation of works commenced previously during PR2. The DSO has prioritised PR3 works, focussing on

networks pre-dating the 1950s.

41 Excludes Station upgrades due to trespass and illegal dumping

-40% -18%

-35%

123%

-27%

6%

-100%

-19% -22%

27%

-150%

-100%

-50%

0%

50%

100%

150%

Indoor Oil-Filled MVRMUs

Open-CubicleSwitchgear

Replace MV/LVTransformers inAssociation with

SWGR

Magnefix Cast-Resin typeSwitchgear

RGB Cast-Resintype Switchgear

Timber SubstationDoors

Oil bunding ofpermanent 20 kV

IFTsitesShrouding of LV

PanelsReplace URDTransformers Capex Variance %

Page 94: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 89

The DSO is forecasting that less than 50% (~17,000km) of the programme will be completed during PR3 period.

The percentage reduction in capex for the Urban LV Renewal programme is broadly consistent with

the equivalent reduction in work volumes.

4.3.1.8 Rural LV Network

CER PR3 allowed capex of €93.5m, although the DSO current forecast for this programme is €82.1m

(representing an underspend of 12%).

The DSO has approximately 50,000 km of single phase rural low voltage overhead lines. 16% of these lines

were refurbished in the period 1996 – 2002 as part of the rural network renewal programme. A programme to

refurbish the outstanding 84% of the rural low voltage lines commenced in 2006. 42% were completed in PR2

and it was planned to complete the remaining lines in PR3 (21,000km).

The DSO is forecasting approximately 80% of the original programme will be delivered by the end of PR3. This

forecast is based on a challenging target for 2015, representing approximately 35% of the original 5-year

programme being delivered in one year. These works are being delivered by DSO internal resource with a

significant number of external contractor resources having been stood down in 2012 when it became necessary

to reduce work volumes.

For the Rural LV Network Renewal Programme, the reduction in the volume of works compared to PR3

programme (approximately 20%) is higher than the reduction in the Capex (6%) suggesting an increase

in unit costs.

Of the 20,000+ Groups refurbished during PR3, the DSO has selected more than 1,800 Groups that

were prioritised and selected for refurbishment in conjunction with other works to improve network

performance and power quality, with significantly higher unit costs than the basic fabric only

refurbishment works.

4.3.1.9 LV Cables and Associated Items

CER PR3 allowed capex of €16.8m, although the DSO current forecast for this programme is €6.1m

(representing an underspend of 64%).

During PR3, the LV cable programmes have been subject to a significant reduction in order to reduce impact on

DUoS charges. To achieve this, the DSO has applied strict prioritisation, and action to ensure that a careful

strategy is adhered to, ensure that the safety of these LV assets is not compromised. The sub-sections below

provide further commentary on PR3 programme

Replacement of Painted Steel Mini-pillars: The PR3 programme to address the condition of minipillars was a

continuation of the mini-pillar replacement programme undertaken previously, with the replacement of 600 cast-

iron mini-pillars and 1,000 painted steel mini-pillars.

The current DSO forecast is for the completion of 200-250 painted steel minipillar replacements by the end of

PR3. Prioritisation of replacement works has been based on the mini-pillar hazard patrol programme. This is

significantly lower than planned volumes of 1,000 and the DSO has addressed the resulting risks associated

with dangerously degrading pillar doors in the short term. Consequently the DSO has increased the number of

minipillar doors replaced during PR3 – approximately 1,500 (based on DSO reporting of 1,100 actual by August

2014). (Note that in 2010, the DSO replaced only 56).

Replacement of Cast Iron Mini-pillars: The DSO is forecasting that between 400 and 500 of these pillars will

be replaced by end of PR3 period (target of 600). Prioritisation of replacement works has been based on the

mini-pillar hazard patrol programme.

Page 95: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 90

Concentric Cable Replacement: This programme is delivered in response to recurrent faults and customer

complaints. To date only one project has been undertaken.

Aging Link box Replacement Programme: The DSO forecasts that approximately 50 link boxes will be

replaced by end of PR3.

Replacement of Sub-standard Copper Services: The PR3 programme is based on the replacement of

approximately 1,000 of the small 6mm2 copper services in the Dublin area (estimated total population of 2,500).

Due to reduced capex spending, the programme has been reactively driven with only 80 replacement services

being forecast by the DSO during PR3.

4.3.1.10 Cutouts

CER PR3 allowed capex of €5.7m, although the DSO current forecast for this programme is €3.9m

(representing an underspend of 32%).

The PR3 programme consisted of the planned replacement of 40,000 pre 1976 indoor cut-outs. This is a

continuation of works from PR2 cut-out replacement programme. The DSO is forecasting to replace up to

30,000 cut-outs by the end of 2015. (75% of the original target)

4.3.2 Response Capex

CER PR3 allowed capex of €98.7m, although the DSO current forecast for this programme is €55.1m

(representing an underspend of 44%).

The DSO has provided a narrative commentary and detailed breakdown of actual costs against each of the nine

categories of investment within the Response work programme. The breakdown of PR3 costs compared to the

CER allowed capex in each of these categories is shown in Table 4.24 below. The table also shows the DSO

revised PR3 forecast, provided in its response42 (report DR01-dated Feb 2015) to our interim PR3 capex report

(showing a minor variance of €0.3m compared to the DSO original PR3 forecast of €52.7m provided in Dec

2014.

Table 4.24 : PR3 Response Capex – Comparison of DSO Actual v CER Allowances for PR3 (€m – 2009 Prices)

Category PR3 Allowed

Capex

DSO PR3

Actual

Variance to

CER

allowances

Variance

to CER

allowances

%

Voltage Complaints 29.6 13.2 -16.4 -55%

25mm SCA OH Conductor

Replacement 9.3 3.0 -6.3 -68%

MV/LV UG Cable Replacement. 8.6 2.8 -5.8 -67%

Metering Replacement 7.7 6.6 -1.1 -14%

Time-switch Replacement. 5.0 4.9 -0.1 -2%

Failed Transformer Replacement 11.9 14.2 2.3 19%

38kV Cable Replacement 5.6 0.9 -4.7 -84%

Undergrounding MV & LV OH lines 16.1 6.8 -9.3 -58%

Advance Ducting 5.0 0.6 -4.4 -88%

Totals 98.7 53.0 -45.8 -46%

38kV Copper Line - Theft

Response 0.0 2.0 2.0

42 Document title DR01 ESBN Response to DSO Historic Capex – dated 06-02-2015

Page 96: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 91

Category PR3 Allowed

Capex

DSO PR3

Actual

Variance to

CER

allowances

Variance

to CER

allowances

%

Revised Total 98.7 55.1 -43.8 -44%

Note – Source data for DSO PR3 Actual – Document Reference DH07 – PR3 Response Capex (Table 1) – converted to 2009 prices

Significant underspend is observed in all but one of these categories (Failed Transformer Replacement). The

area of largest underspend relates to voltage complaints4. The reduced investment in this category over PR3

period is likely due to a number of factors, such as:

reduced demand,

impact of MV and LV network renewal,

20kV conversion programmes and

replacement of small capacity transformers in rural areas.

A total of 2,748 validated43 voltage complaints were resolved during PR3 period up to the end of 2014. This is

noticeably less than the 9,570 voltage complaints resolved during PR2.

Reactive activities that are primarily related to construction activities have been subject to notable reductions

(undergrounding of existing lines, advance installation of ducts). The DSO has observed an increasing number

of thefts of overhead line conductor during PR3.

The number of 38kV cable faults has reduced during PR3 period in overall terms, contributing to the major 61%

reduction in capex associated with the replacement of faulty 38kV cables.

An increase in capex (material cost only) relating to the replacement of faulted station equipment (transformers) is observed over the PR3 period.We would not expect the short term deferral of asset replacement works to result in an increase in reported fault rates and hence higher replacement costs for PR3. We have checked the reported DSO fault rates for faulted station equipment although we have not observed any noticeable increase in fault rates for PR3 period when compared to average for PR2 (2009 and 2010 only). The DSO reports (DH03) a programme to monitor the causes of increased transformer faulting and increased application of condition monitoring activities to identify the leading indicators of faults in these transformers.

In its response44 to our PR4 capex IR, the DSO explained the need for urgent works that are scheduled for 2015 to address risks associated with the theft of 50mm

2 Copper conductor from 4 x 38kV overhead line circuits. The

works involved replacement of the copper conductor with aluminium conductor (of equivalent rating) and the estimated capex for this new work programme is €2.0m in 2015. (Note this value is not included within the PR3 forecast capex detailed within Table 4.24).

4.3.3 Continuity Capex

The DSO is forecasting capex relating to the Continuity programme of €13.7m, which is approximately 39% less

than the CER allowed costs of €22.3m. The actual costs for each year of PR3 are shown in Table 4.25 below.

Table 4.25 : PR3 Continuity Capex – Comparison of DSO Actual v CER Allowances for PR3 (€m – 2009 Prices)

2011 2012 2013 2014 2015 5 Year Total

CER Allowed Capex 4.5 4.5 4.5 4.4 4.4 22.3

DSO Actual / Forecast 2.8 3.5 2.5 2.0 2.9 13.7

Variance €m -1.7 -1.0 -2.0 -2.4 -1.5 -8.6

43 The actual number of voltage complaints each year is much higher than the validated complaints. Validation is carried out by ESBN connecting a

voltage recording device to assess the actual voltage at the premises. 44 Document DR06 – DSO Forecast Capex – Interim Report; ESB Networks Response – dated 09-03-2015

Page 97: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 92

Variance % -38.2% -22.8% -44.5% -55.6% -34.1% -38.7%

This programme primarily consists of the installation of automatic and remote control switches and other

measures to improve the performance of the network. The DSO determined that the continuity improvement

projects intended for delivery in PR3 would be largely deferred and priority given to core capex activities that

addressed higher priority safety issues.

Distribution Automation: The original programme for the PR3 period consisted of the installation of 500

devices on the MV system as part of a widespread distribution remote control initiative. These devices were

planned to be installed by the DSO within a number of network schemes, located and set up to minimise the

length of network without supply in a fault situation.

The DSO reports that by late 2014 a total of 64 devices have been installed within the scope of 13 fully

operation integrated network schemes. In addition a further 184 devices have been installed in non-scheme

locations on the network. Although these do not provide automated sectionalising and back-feed within 3

minutes (in the event of a fault), they do provide the functionality that was planned at PR3 – in terms of more

network sectionalisation and remote control, thus reducing CI and CML respectively. Further schemes are in

progress and the DSO expects 50 more devices to be in operation by end of 2015. Prioritisation of network

schemes has been carried out by the DSO in order to derive maximum benefit from the significantly reduced

scale of this improvement programme. The DSO has observed an increased scope of works being necessary to

accommodate the automation devices. Additional switches have to be installed on either side of the vacuum

interrupters in order to provide points of isolation, increasing the unit cost of each device. The DSO also reports

additional time required to install and fully commission each of these devices.

The DSO has also installed a total of 27 remote controlled switches on the 38kV network.

Single Phase Reclosers: The DSO has reported that a very small quantity of single phase reclosers has been

installed on the MV network during PR3 approximately 130 forecast against a planned volume of 1,000. They

have also replaced approximately 65 obsolete reclosers (Type F4C).

Changes to 20kV neutral earthing system: The DSO programme to install arc suppression coils, whereby the

20kv transformer neutral point is earthed through a self-tuning arc suppression coil has continued during PR3.

The DSO reports that there are three 20kV arc suppression systems that are fully operational with a further two

constructed but not yet fully operational.

Worst Served Customers: Typically these customers are supplied on rural single phase overhead networks

and experience >=5 interruptions in the previous 12 month period and >=15 interruptions in the previous 3

years. In PR3 the DSO has introduced an initiative to address the “worst served customers”. The initiative

consists of necessary remediation works following line patrols and identification of root causes. Targeted

investments have been made to improve network continuity for 380 customers during PR3.

4.3.4 System Control Network Capex

The DSO has forecast a capex spend of €4.0m over PR3 period compared to CER allowances of €15.0m. This

represents a variance of 73%.The majority of expenditure relating to System Control is included within Non-

Network Capex – see Section 4.4.5

Network related expenditure for System control has been significantly deferred with the DSO indicating that the

deferred work will need to be progressed during PR4. This will be reviewed as part of the assessment of DSO

forecast capex.

4.4 Non Network Related Expenditure

The DSO non-network capex for the PR3 period is shown in Table 4.26 below.

Page 98: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 93

Table 4.26 : Comparison of PR3 Costs v CER Allowances –Non- Network Capex (€m 2009 prices)

Category 2011 2012 2013 2014 2015 5 Year Total

CER Allowed Capex 33.6 35.3 34.9 37.6 37.7 179.1

DSO Actual / Forecast 22.4 19.1 21.7 32.1 40.3 135.6

Variance -11.2 -16.2 -13.2 -5.5 2.6 -43.5

% Difference -33% -46% -38% -14.7% 6.9% -24.3%

The DSO has forecast a total capex of €135.6m by end of PR3 – this is €43.5mm lower than the CER allowed

Non-Network capex of €179.1m, representing a reduction of 24.3%.

The detailed breakdown of the Non Network Capex is shown below in Table 4.27.

In general the DSO has deferred expenditures in all areas, and has reprioritised expenditure in areas

necessary to maintain customer service, operations and legislative requirements. In most cases this

can be viewed as efficiency and indeed represents a lower than allowed expenditure while maintaining

network performance.

It is likely that there will some elements of catching up with the DSO capex submission for PR4.

Table 4.27 : Detailed Breakdown of PR3 Non-Network Capex (€m 2009 prices) by Category

Actual Spending Actual Allowed

2009 Prices PR3 PR3

2011 2012 2013 2014 2015 Total (5 year) Total (5 year)

€m €m €m €m €m €m €m

New Accommodation -

Accommodation Refurbishment 1.8 0.7 4.2 2.3 1.9 10.9 18.3

Fixture & Fittings 0.03 0.01 0.03 0.0 0.0 0.1 1.5

Office Equipment 0.01 0.00 0.00 0.0 0.0 0.0 0.5

Vehicles 2.3 0.7 0.3 11.5 19.5 34.2 35.0

Tools 3.0 2.6 4.1 3.6 1.9 15.2 15.6

Distribution Assets Management

7.6 8.9 8.4 8.3 8.1 41.3 69.6 Distribution Control / Operation

IT Infrastructure

Enterprise Applications

Environment 0.6 0.3 0.4 0.1 0.5 1.9 7.0

Telecoms & System Control 3.2 2.9 1.9 3.0 5.6 16.6 31.6

Non Rab Telecoms 3.8 3.2 2.5 3.1 2.7 15.3 -

Total 22.4 19.1 21.7 32.1 40.3 135.6 179.1

4.4.1 Accommodation Fixtures and Fittings and Office Equipment

The major emphasis during PR3 was to build on the work carried out during PR2 and focus on reducing costs

by the rationalisation of the number of depots and at the same time manage the ongoing maintenance of

existing depots in the Estate. A big emphasis was also placed on a consolidation process to reduce and

streamline the number of contractors who carry out maintenance work in the depots. Following the consolidation

process which is nearing completion the newly appointed contractors are carrying out safety risk assessments

Page 99: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 94

which will require significant capital expenditure to bring standards up to the required regulatory safety

standards. The allowed PR3 capex was €18.3 million and this is expected to outturn at €10.6 million.

4.4.2 Vehicles

As part of the allowances in PR3, the DSO proposed to reduce the fleet from 2,300 to 2,000 vehicles and

extend vehicle life to between 10 and 15 years, depending on vehicle model. This was expected to reduce the

number of vehicles replaced from 200 per year at €35m to 165 per year at a capital cost of €16.8m. Based on

historic costs this reduction appears to be reasonable. The extremely low expenditure in the first 3 years of the

review was due to funding constraints. Initial forecasts for PR3 within the DSO November 2014 submission

showed a forecast €16.8m for the PR3 period. This has subsequently been increased to €34.2m after

publication of the interim reports showing PR4 allowances. This major increase in spend forecast in 2014 and

2015 could be viewed as accelerated PR4 spend.

4.4.3 IT Systems

The IT programme was reprioritised to deliver the projects that provided the strongest customer and business

benefit. The main impact of this was the deferral of certain aspects of the Mobile Working programme

(€10.5m). This programme has been partially delivered in PR3 with further developments planned for the PR4

period.

The other main area of reduced expenditure related to planned upgrades to SAP and other Enterprise

applications with a forecast reduction of around € 11.3m. A decision was taken to defer the SAP ISU Upgrade

until the Smart Metering project requirements are finalised. The Customer Charter system upgrade has also

been deferred to PR4.

4.4.4 Environment

The total PR3 allowed expenditure was €7.0m. The total PR3 actual expenditure is forecast to be €1.9m giving

an associated under expenditure of €5.1m. This is primarily due to either zero or much lower expenditure in the

following areas:

1) Wood pole storage facilities - Nationally

2) Wood pole storage facility - Kilteel

3) Depot drainage infrastructural improvements

4) Oil filled equipment storage requirements at HV Stations

Capital rationing also had a significant effect on the PR3 outturn expenditure, as the Non Network related

expenditure was cut back during the period. The DSO believes that the impact of these reduced expenditures

will not have an adverse effect.

4.4.5 System Control and Telecoms

The significant approved expenditure areas in PR3 for System Control were OMS and DMS upgrades at

approximately €5m and RTU replacement at approximately €6m. It is likely that the majority of the OMS

upgrade project will be completed in PR3 with some Smart Networks enabling functionality deferred to PR4.

The PR3 RTU replacement programme will remain unspent in PR3 and will be submitted to CER for

consideration as a PR4 programme as part of the future submission.

Although the Allowed Expenditure in PR3 was €31.6 million, and the actual reported was €16.6 million, there

was also a reported €14.6 million expenditure on Non RAB Telecomm Expenditure. This was not defined as a

separate allowance in the initial review, but it is recognised that the Telecoms function provides a service across

all licensed businesses and the corporate functions of the group business.

Page 100: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 95

4.4.6 Smart Metering Expenditure

In the process of setting its allowances for the PR3 period, the CER requested the DSO to estimate the costs

that would be incurred during PR3 if the smart metering project was proved to be worthwhile. The DSO

estimated that a sum of €500m would be prudent. The CER subsequently included €500m as a provisional

amount for profiling purposes to ensure that if the smart metering project were progressed that there would be

no step change in the DuoS tariff.

DSO discussions with CER at the end of 2012 confirmed that the bulk of expenditure on the smart metering

project was likely to occur during PR4 period (and beyond). Consequently, the DSO is forecasting expenditure

during PR3 period that is significantly below the €500m provisional sum allowed for by CER.

The actual capex on Smart Metering for PR3 period is summarised in Table 4.28 below.

Table 4.28 : Smart Metering – DSO Capex during PR3 (€m – 2009 prices)

2011 2012 2013 2014 2015 PR3 Total

1.2 1.1 2.7 2.4 4.8 12.2

For PR3 the DSO Smart Metering project focus has been on defining the business, process, technical and

performance requirements, as well as strategies for sourcing delivery of its part of the overall National Smart

Metering Program.

The DSO has reported the following key activities progressed during PR3 period:

Development of strategy and approach to deliver and operate smart metering

Development of business and functional requirements for smart metering

Development of technical and security requirements for smart metering

Technology Trials and Studies

Conduct Networks Workshops and agree changes to Market Design

Prepare, Design and Conduct Major Procurements for Smart Metering – this activity will be the primary

focus for 2015.

Total PR3 smart meter capex of €12.2m is significantly below the original €500m provisioned by CER

and also substantially less than the €50m that the DSO had forecast in 2012 as part of the overall

capex re-profiling exercise carried out in consultation with CER. PR3 capex relates to the design and

procurement activity carried out by the DSO. These activities would generally fall into the

classification of enabling works associated with the roll-out of the Smart Metering capex programme.

4.5 Summary & Conclusions

4.5.1 Capex Overview

During the PR3 period, there are a number of significant factors that need to be considered when

assessing DSO outturn capex v CER allowed costs.

In consultation with the CER, ESBN Networks reduced the PR3 Gross Capex delivery programme in two

stages from the original CER allowed value of €4,200m to €2,400m (including Transmission Projects).

Given the reduction in peak demand during the PR3 period, together with pressure to reduce potential

increases on DUoS charges, the DSO considered it appropriate to critically review the network

requirements and the related project portfolio, allowing for deferment of reinforcement projects where the

resultant risks were considered acceptable to do so.

In headline terms, during PR3 the DSO is forecasting to invest net €1,075.3m on network and non-network

assets, which is €91.3m (9.3%)higher than its 2012 revised capex total of €984m (excluding Smart

Page 101: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 96

Metering and R&D costs associated with studying the impact of Electric Vehicles). Its latest forecast is

€637m (37%) lower than the CER allowed capital expenditure of €1,712m.

Due to the unique circumstances that were faced by the DSO in the period leading up and resulting in its

revised capex plans in 2012, it is considered appropriate to use the rebased 2012 capex forecast for

comparison throughout this report wherever possible, although, for completeness, reference is also made

to CER allowed values.

The DSO has been asked for more detailed breakdown of costs associated with the 2012 revised capex

plan broken down into an annual expenditure profile for each of the work programmes for which CER had

made allowances for the PR3 period. However, it is our understanding that this information is not available

due to the progressive and incremental nature of Capex assessment and reprioritisation over the 2012-

2015 period.

Consequently we have not been able to carry out a comparable analysis of DSO forecast v rebased 2012

capex at a work programme level and such analysis has therefore been carried out relative to CER allowed

capex for each defined category of capex.

4.5.2 Demand Connections

For Demand Connections, the total DSO Actual Capex (Gross) over the PR3 period is forecast to outturn at

€235.5m, this is €217.2m (48%) less than the CER Allowed capex. It is also €16.5m (6.6%) less than the

DSO Revised Capex Proposal of 2012.

The total DSO Actual Capex (Net) over the PR3 period is forecast to outturn at €123.2m, this is €103.1m

(45.6%) less than the CER Allowed capex.

Customer contributions of €112.3m for a gross expenditure on demand connections of €235.5m (gross)

resulted in a contribution ratio of 48% compared with the agreed rate of 50%. The DSO may need to revise

the Basis for Customer Connection Charges for future recovery of the agreed rate of 50% of total

connection charges, although we would expect any revision to be presented to the CER for review and

approval.

The main driver for this significantly lower capex, compared to the CER allowances, is the reduced number

of customer connections that have requested to be provided by the DSO over the PR3 period. Based on

the DSO latest forecast for 2014 and 2015, it is anticipated by the DSO that the 5-year total will outturn at

70,417. This is more than 86,000 (i.e. 55%) lower than the PR3 forecast connection volumes for the full 5-

year period.

CER should review the outturn costs for 2014 before finalising its allowances for PR3 period.

It is observed that the DSO total meter costs for PR3 period are 17.9% higher than the CER allowed costs.

This is despite a forecast reduction in connection volumes of 55% over the PR3 period. The DSO has

provided a detailed explanation to explain this apparent adverse variance. The closing of cost accounts

relating to dormant connection projects, to prevent misallocation of costs, has resulted in final connection

cost and the metering cost both being allocated to the metering cost code.

The analysis provided by the DSO supports the higher metering capex costs incurred during PR3. It is

important however that the assessment of PR4 allowed revenues for connections and metering takes due

account of the fact that a proportion of G1-G3 connections costs have been allocated to metering capex

during PR3.

4.5.3 Generator Connections

The DSO is forecasting to incur gross generation connections costs of €86.7m during PR3, representing an

underspend of €75.8m compared with the CER allowed gross capex of €162.5m. This DSO forecast is

€17.7m (25.7%) higher than the DSO Revised Capex Proposal of 2012.

Customer contributions for generation connections are forecast to be €96.7m, equivalent to a contribution

ratio (or recovery rate) of 112% compared with the allowed recovery rate of 100%.

This over-recovery of connection costs in PR3 will undoubtedly result in DSO net cash outflows during the

early years of PR4 period and this will need further consideration when reviewing the proposed DSO

forecast capex for PR4.

Page 102: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 97

4.5.4 Load Related Reinforcement

For load related reinforcement, the DSO forecasts a total capex of €316.9m by end of PR3 – this is

€315.7m lower than the CER allowed load-related reinforcement capex of €632.6m – representing a

variance of 50%.

This DSO forecast is approximately €39.9m higher than the revised proposal of ESBN (€277m) submitted

to CER in 2012.

The main drivers on load-related reinforcement expenditure are the growth in peak demand and energy

delivered (GWh). It is noticeable that from a total of circa 24,000 units in 2008, the DSO has experienced a

reduction to 23,000 GWh units in 2010, followed by a further reduction in actual units to circa 22,100 GWh

by 2013.

Similarly, the system peak demand has not increased in line with the DSO forecast for PR3. The peak in

2007/08 was 4,914 MW and the peak in 2013/14 has reduced to 4,523 MW.

As part of its response to the Business Plan Questionnaire, the DSO was requested to provide a

breakdown of planned v actual cost details of the major projects (38kV and above) that have been

progressed during PR3. This would have allowed us to carry out a more detailed analysis of a sample

number of projects completed during PR3. The purpose of carrying out a detailed analysis of a

representative sample of individual projects is to assess the reasonableness of costs incurred compared to

planned/allowed costs, the reasonableness of the DSO project delivery process and hence to determine

the efficiency of the DSO project delivery and resulting capex.

We have experienced significant delay in receiving the requested information for a sample of 11 major

projects expected to be completed during PR3. Both the delays in providing the required information and

the fact that information was only provided for a small sample of projects rather than all major projects is

disappointing. We would have expected the project information requested to be generally available within

the DSO and find the prolonged delay in providing this information to be a concern. – it is standard

information that we would expect the project managers and the DSO senior management team to be using

on a routine basis to manage and control project delivery and associated costs.

Given the time the DSO has had to provide such information, we consider that their inability to provide such

information to the CER in a timely manner to be an area of weakness that requires improvement during

PR4.

For 10 of the 11 projects, we have observed that the DSO is forecasting total costs (PR2 and PR3) that are

lower than the Capital Approval Amount – with variances in the range of €0.1m to €0.8m. For the remaining

major project (N-D-1027), we observe that the DSO is forecasting a total cost (PR2 and PR3) which is

higher than the Capital Approval amount by €1.0m.However as the lack of cost granularity has limited our

assessment on a constant 2009 price base, conclusions made from any comparison of projects costs need

to recognise this cost base inconsistency. We have not investigated the reasons behind any variance in

total costs v CA costs nor has the DSO provided any variance

It was also our intention to request a sample number of post investment appraisal document for a selection

of completed major projects. The DSO has advised us that they do not presently carry out a formal post

investment review of individual projects and hence no documentation was available for us to review.

We consider this gap to be an area for improvement within the DSO project delivery process – this has

been recognised by the DSO, who has stated their plans to introduce this improvement over the coming

months.

However, the DSO has provided a supporting narrative document (DH02 – PR3 Load Driven Programme)

that provides detailed commentary of investment during PR3 – this has allowed us to make a quantitative

assessment of non-financial project outputs.

Our analysis suggests that the reduction in DSO forecast capex for 110kV reinforcement projects is higher

than the equivalent volume reductions in transformer capacity or circuit km commissioned. It is expected

that this disparity will be partly due to a number of projects being completed in PR3 that commenced in

PR2 period; with the costs incurred on these projects during PR2 being added to the DSO RAB during

PR2.

Page 103: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 98

Further analysis of 38kV reinforcement projects suggests that the reduction in DSO forecast capex is

higher than the equivalent volume reductions in transformer capacity or circuit km commissioned. Similar to

110kV projects, it is expected that this disparity will be partly due to a number of projects being completed

in PR3 that commenced in PR2 period; the costs incurred on these projects during PR2 being added to the

DSO RAB during PR2.

Using the Planning policy (which permits 180% loading of single transformer nameplate rating under N-1

conditions for dual transformer stations), the DSO has forecast that a total of 48 of their population of 38kV

stations will be outside Planning Standards by the end of PR3 (rather than 32 loaded above nameplate

rating).

These stations will require further attention during PR4 and will be a consideration within the review of DSO

forecast capex.

The DSO has continued its programme to convert its 10kV network to 20kV operation, albeit at lower

volumes. The PR3 forecast volume for this activity was 15,000km. The DSO has reported that by the end

of PR3 a total of 10,000km will be converted to 20kV. The reduction in capex associated with the 20kV

conversion programme is consistent with the reduced circuit lengths converted during PR3 and it appears

to be efficiently incurred.

The DSO is forecasting that capex associated with other MV/LV System improvements during PR3 will

outturn at €33.6m. This is approximately 51% less than the CER allowed capex of €69.1m. The scale of

reduction in DSO capex during PR3 for MV/LV system improvements is consistent with the overall

reduction in PR3 load related reinforcement expenditure (being 50% of CER allowed capex).

4.5.5 Retirements (Dismantling) Capex

The DSO has continued its practice of charging dismantling costs to its Income Statement for years 2011

to 2013 and proposes a change in Accounting Practice for the remaining two years of PR3 such that the

costs are allocated to capital. Our analysis of DSO dismantling costs has been carried out on a total cost

basis. Total dismantling cost over the PR3 period is forecast at €47.1m, 17.9% less than the CER allowed

capex of €57.4m.

The DSO has introduced revised project costing procedures (Integrated Work Management Module) within

their SAP application from 2009 onwards. This has allowed the DSO to allocate dismantling costs more

directly to the work activity that has driven the need for the dismantling to be carried out.

We would generally agree with the DSO that the proportion of dismantling costs is likely to vary across

each of the work activities. The change in the DSO cost allocation procedures has provided improved

visibility of the drivers on the dismantling activity and associated costs

We would expect the DSO dismantling costs over the PR3 period to be charged to capex for the full five

years, this being consistent with CER allowances. This will result in a transfer of €28.4m of costs from opex

(2009 prices) to capex covering the years 2011 to 2013.

4.5.6 Diversions

Line diversion costs have historically been proportional to capital expenditure in the category of “gross new

demand connections”. For the PR3 period, this allowance was set at a value equivalent to 11.4% of the

PR3 forecast capex for new connections. The actual diversion costs over 2011 to 2013 are in the range of

19.2% to 21% of the gross connections capex over the same period. The DSO has provided an

explanation for this % increase in percentage costs experienced during PR3 and we consider this to be

reasonable.

In its response (DSO report DR01) to our Interim Report, the DSO provided the DSO revised forecast of

line diversions capex for the remaining two years of the PR3 period suggesting line diversion suggests

costs in the range of 20% for the remainder of PR3- these values are broadly consistent with the first three

years of PR3 and are considered reasonable.

4.5.7 Non-Load Related Capex

For non-load related capex, the DSO has forecast a total capex of €415.3m by end of PR3 – this is

€149.4m lower than the CER allowed load-related reinforcement capex of €564.7m – representing a

Page 104: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 99

variance of 26%. This DSO forecast is €29.4m higher than the revised proposal of ESBN (€387m45)

submitted to CER in 2012

It should be noted that this forecast includes for a one-off capex of €26.8m in 2014 associated with Storm

Darwin and it also includes a significant increase in capex for year 2015 (relative to 2012 and 2013).

Certain asset replacement projects were deferred in whole or were scaled down based on the DSO’s

prioritisation process.

For PR3, the allowed capex for HV Overhead Line Replacements was €16.3m and the DSO latest forecast

is €15.1m, representing 93% of allowed capex.

The DSO states that the 38kV OCR programme will be substantially completed, although this is dependent

on the delivery of 1,000km during Q4, 2014 and end of 2015. There is a significant risk that this volume of

work associated with the 38kV OCR programme is not delivered in 2015 – it represents a significant

increase in volumes previously delivered and is heavily dependent on contractor resources being in place

and fully operational. Whilst the DSO also acknowledges the 2015 volumes represent a significant increase

in the rate of delivery, it considers its 2015 forecast to be reasonable, citing contractor resource availability

to deliver the majority of the work programmes.

The reduction in capex by deferring 110kV line works has been largely offset by the additional capex

associated with 38kV copper overhead line replacements. Generally, the reduced costs in PR3 are broadly

consistent with the reduced PR3 volumes delivered

The DSO has deferred significant capex during PR3 associated with 110kV and 38kV cable replacement

projects. The reductions in work volumes stated by the DSO are broadly consistent with the reduced

capex.

The DSO has deferred a number of the higher cost HV station replacement projects / programmes

completely, whilst at the same time focussing on the substantial completion of various safety driven and

security driven programmes of work, typically of a much lower cost. These two factors contribute to an

overall underspend of PR3 capex of 36% relating to the HV Station renewal programme.

For the MV OCR programme, the DSO is forecasting the completion of 33,000 km by end of PR3 (i.e. 73%

of the original target (45,000km) upon which allowances were made, .although it forecasts a spend of 86%

of the PR3 allowance. This increase in unit costs is being driven by higher labour costs being forecast in

2014 and 2015 - associated with more stringent pole testing procedures.

The forecast includes a target of 14,500km being delivered in 2015 alone, predominantly by using contract

resources, this being subject to completion of the tendering and contract procedures. Achieving the 2015

target volumes is therefore considered to be a significant challenge to the DSO.

The DSO is forecasting that approximately 10km of MV cable to be replaced by 2015 – representing an

under-delivery of about 33%, broadly in line with the forecast underspend.

In relation to the MV Station Renewal Programme, the DSO is forecasting an overspend in this category of

27%. Any expected reductions in capex due to the reduction in volumes for many of the categories have

been largely offset by increased costs associated with the higher volume of work associated with the

Magnefix Cast Resin Switchgear programme.

The plan for PR3 period was to refurbish 35,000 spans of LV urban networks. The DSO is forecasting that

less than 50% (~17,000km) of the programme will be completed during PR3 period. The percentage

reduction in capex for the Urban LV Renewal programme is broadly consistent with the equivalent

reduction in work volumes.

For the Rural LV Network Renewal Programme, the reduction in the volume of works compared to PR3

programme (approximately 20%) is higher than the reduction in the Capex (6%) suggesting increase in unit

costs. Of the 20,000+ Groups refurbished during PR3, the DSO has selected more than 1,800 Groups that

were prioritised and selected for refurbishment in conjunction with other works to improve network

performance and power quality, with significantly higher unit costs than the basic fabric only refurbishment

works.

45 €433m less forecast retirement costs (considered separately) of €46m

Page 105: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 100

For the LV Cable Renewal Programme - the DSO current forecast for this programme is €6.1m against the

CER PR3 allowed capex of €16.8m. During PR3, the LV cable programmes have been subject to a

significant reduction in order to reduce impact on DUoS charges.

For the Renewal Programme associated with cutouts, the PR3 programme consisted of the planned

replacement of 40,000 pre 1976 indoor cut-outs. This is a continuation of works from PR2 cut-out

replacement programme. The DSO is forecasting to replace up to 30,000 cut-outs by the end of 2015.

(75% of the original target)

For Response Capex, CER PR3 allowed capex of €98.7m, although the DSO forecast for this programme

is €53.055.1m (representing an underspend of 44%). The area of largest underspend relates to voltage

complaints where the DSO is forecasting a €16.4m variance to CER allowances. The reduced investment

in this category over PR3 period is likely due to a number of factors, such as reduced demand, impact of

MV and LV network renewal, 20kV conversion programmes and replacement of small capacity

transformers in rural areas. A total of 2,748 voltage complaints were resolved during PR3 period up to the

end of 2014. This is noticeably less than the 9,570 voltage complaints resolved during PR2.

In its response to our PR4 capex IR, the DSO explained the need for urgent works that are scheduled for

2015 to address risks associated with the theft of 50mm2 Copper conductor from 4 x 38kV overhead line

circuits. The works involved replacement of the copper conductor with aluminium conductor (of equivalent

rating) and the estimated capex for this new work programme is €2.0m in 2015.

The DSO is forecasting capex relating to the Continuity programme of €13.7m, which is approximately 39%

less than the CER allowed costs of €22.3m. This programme primarily consists of the installation of

automatic and remote control switches and other measures to improve the performance of the network,

The DSO determined that the continuity improvement projects intended for delivery in PR3 would be

largely deferred and priority given to core capex activities that addressed higher priority safety issues.

4.5.8 Non-Network Capex

For non-network capex, the DSO has forecast a total non-network capex of €135.6m by end of PR3 – this

is €43.5m lower than the CER allowed Non-Network capex of €179.1m, representing a variance of 24.3%.

In general the DSO has deferred expenditures in all areas, and has reprioritised expenditure in areas

necessary to maintain customer service, operations and legislative requirements.

In most cases this can be viewed as efficiency and indeed represents a lower than allowed expenditure

while maintaining network performance. It is likely that there will some elements of catching up with the

DSO capex submission for PR4.

Total PR3 smart meter capex of €12.2m is significantly below the original €500m provisioned by CER and

also substantially less than the €50m that the DSO had forecast in 2012 as part of the overall capex re-

profiling exercise carried out in consultation with CER. PR3 capex relates to the design and procurement

activity carried out by the DSO. These activities would generally fall into the classification of enabling

works associated with the roll-out of the Smart Metering capex programme.

Page 106: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 101

5. Review of PR4 Capital Expenditure

This section reviews the DSO’s proposed capital expenditure for the PR4 period (2016 to 2020) compared

with the PR3 (2011 to 2015) expenditure allowed by CER in the PR3 decision paper46, the rebased PR3 plan

from 2012 and the DSO forecast expenditure for the PR3 period47.

Table 5.1 below details the DSO’s proposed capex for each of the defined capex categories whilst Figure 5.1

presents the PR4 totals in graphical format. For completeness, the table shows the DSO original forecast for

PR4 capex submitted in November 2014, together with its updated PR4 forecast capex – issued in March

2015. This updated forecast was issued in response to our DSO Forecast Capex Interim Report.

Table 5.1 : DSO PR4 Capex Summary by Expenditure Category (€m – 2014 prices)

Capex

Investment

Category

PR3

Allowed48

PR3

Revised

Proposal

(2012)

PR3

Actual49

PR4

Proposed50

Revised

PR4

Proposed51

Variance: Revised

PR4 Proposed v

PR3 Allowed

Variance: Revised

PR4 Proposed v

PR3

Actual/Forecast

€m % €m %

Load Related

Capex 1390.4 665.9 751.3 894.8 853.1 -537.3 -38.6% 101.8 13.6%

Non-Load Related

Capex 578.5 443.6 425.4 694.4 671.0 92.5 16.0% 245.6 57.7%

Non-Network

Capex 183.5 98.4 138.9 172.4 172.2 -11.2 -6.1% 33.4 24.0%

Other Capex –

Smart Metering - 51.2 12.9 22.9 22.9 22.9 - 10.0 77.5%

Customer

Contributions -398.3 -199.8 -198.5 -240.1 -238.2 160.1 -40.2% -39.7 20.0%

TOTAL NET

CAPEX 1754.1 1059.3 1130.1 1544.3 1481.0 -273.1 -15.6% 351.0 31.1%

46 CER/10/198 - Decision on 2011 to 2015 distribution revenue for ESB Networks Ltd 47 Actual Expenditure in 2011 to 2014 and forecast expenditure in 2015. 48 Excluding Smart Metering Capex of €500m (2009 prices) 49 Includes €29.1m Dismantling Costs for period 2011 to 2013 allocated by DSO as Capital Driven Opex ; Excludes Interest During Construction

(IDC) Charges 50 DSO Proposal for PR4 Capex received by Jacobs on 21st November 2014 - Excludes IDC Charges 51 DSO Revised Proposal for PR4 Capex received by Jacobs on 25th March 2015 – Excludes IDC Charges

Page 107: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 102

Figure 5.1 : DSO PR4 Capex Summary – Net Costs (€m 2014 prices)

The DSO’s revised PR4 forecast can be described in headline terms by the following characteristics:

With regard to Demand Connections, the DSO is forecasting a total number of connections in PR4 of

108,000. This represents an increase of 53% compared to the total of 70,417 during PR3, but is still

only 33% of the total number of connections made during PR2.

The DSO is forecasting 0% cumulative growth in peak demand during PR4. Reinforcement expenditure

during PR4 is focused on addressing parts of the system which do not presently comply with the

Planning Standards.

Capex (gross) associated with generator connections is forecast to increase by 23% from €88.9m in

PR3 to €109.5m in order to connect a total of 1,250 MW of renewable generation over the PR4 period

(compared to 1,200 MW expected by the end of PR3).

Capex associated with non-load related projects and programmes is the category where the DSO is

forecasting the largest increase in capex in PR4 compared to PR3 with a variance of €245.6m (around

57.7%). The renewal programmes for which the DSO has forecast the largest increases in capex in PR4

relate to HV Station works and HV and MV overhead line works. The DSO’s plans are focused on the

replacement of aging and defective assets. The DSO advises that much of this work has been carried

over as financially deferred work from PR3.

In addition, the DSO has included €87.6m of PR4 capex relating to the North Atlantic Green Zone

(NAGZ) smart grid initiative.

The forecast increase in PR4 non-network capex (of 24%) is driven by increased expenditure on

vehicles, Distribution Asset Management (including IT infrastructure), Telecoms and System Control.

In relation to the Smart Metering project, the DSO submission for PR4 includes for further development

and project costs necessary to take the project to the next major milestone in 2017. It does not include

capex associated with a country-wide roll out programme as the final investment decision has not yet

been taken.

In headline terms, the DSO is forecasting a total gross expenditure of €1.72bn. This is €433m (20%)

lower than PR3 allowed capex and €391m (29%) higher than PR3 actual/forecast capex.

Net of customer contributions, the DSO is forecasting total PR4 capex of €1.48bn – this is €273m lower

than PR3 allowed capex and €351m higher than PR3 actual/forecast capex.

1,754

1,059

1,130

1,481

0

500

1000

1500

2000

5 Year Total

€m

PR3 Allowed 2012 Rebased Plan PR3 Actual PR4 Revised Forecast (April 2015)

Page 108: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 103

Figure 5.2 below presents the DSO net capex for PR4 on an annual basis (excluding IDC). It is noted that

the financial situation in PR3 reduced capex in the 2012-2014 period, with the DSO forecasting an increase

in net capex in the final year of PR3 due to somewhat more relaxed financial markets. Capex in 2016 is

forecast to increase to above €300m, some 5% higher than 2011 levels. Capex during PR4 is forecast to be

fairly consistent, although falling slightly over the period.

Figure 5.2 : DSO Annual Capex Profile (Net - €m – 2014 prices)

Each of the capex categories itemised above is considered in further detail within the following sections of

the report. Capex relating to New Business, Generation Connections, Line Diversions and Distribution

Reinforcement is discussed in Section 5.1 whilst capex relating to Non-load related and Asset Replacement

is discussed in Section 5.2. Non network related capex is discussed in Section 5.3.

5.1 Load Related Expenditure

A breakdown of the DSO’s total Load Related Capex for the PR4 period is presented below in Table 5.2.

Table 5.2 : DSO PR4 Load Related Capex - Gross (€m – 2014 prices)

Category

PR3 Allowed

PR3 Actual

PR4 Requested

Revised PR4

Requested

Variance Revised PR4

Requested v PR3 allowed

Variance Revised PR4

Requested v PR3 actual/forecast

€m €m €m €m €m % €m %

(G1) New housing Schemes 74.6 16.7 46.5 44.2 -30.4 -40.8% 27.5 164.5%

(G2) Non-scheme Houses 164.4 89.0 106.1 107.7 -56.7 -34.5% 18.7 21.0%

(G3) Commercial/Industrial Supplies

212.5 120.8 128.5 129.8 -82.7 -38.9% 9.0 7.4%

Whole Current Metering 12.5 14.7 24.1 19.5 7.0 56.3% 4.8 32.6%

New Business – Demand Connections

464.0 241.2 305.2 301.2 -162.8 -35.1% 60.0 24.9%

Transmission Connection Costs

26.3 0.0 15.2 15.2 -11.1 -42.3% 15.2 -

110kV reinforcements 236.1 144.4 150.4 150.4 -85.7 -36.3% 6.0 4.2%

38kV reinforcements 215.2 86.5 85.9 85.9 -129.4 -60.1% -0.6 -0.7%

292

183173

217

265

305 303297

283293

0

100

200

300

400

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

€m

PR3 Actual PR4 Revised Forecast (April 2015)

Page 109: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 104

Category

PR3 Allowed

PR3 Actual

PR4 Requested

Revised PR4

Requested

Variance Revised PR4

Requested v PR3 allowed

Variance Revised PR4

Requested v PR3 actual/forecast

€m €m €m €m €m % €m %

MVLV System Improvements 70.8 34.5 40.9 40.9 -29.8 -42.2% 6.5 18.8%

IFTs associated with 20kV Conversion

16.6 22.9 0.0 11.1 -5.5 -33.1% -11.8 -51.6%

20kV Conversion 83.0 36.5 25.4 14.3 -68.7 -82.8% -22.2 -60.8%

Reinforcements 648.1 324.7 317.8 317.8 -330.3 -51.0% -6.9 -2.1%

Generation Connections 166.5 88.9 109.5 109.5 -57.0 -34.2% 20.6 23.2%

Dismantling 58.8 48.3 70.2 64.4 5.6 9.6% 16.2 35.5%

Non-Repayable Line Diversions

53.1 48.3 92.1 60.2 7.1 13.4% 11.9 24.6%

Total Load Related CAPEX - GROSS

1390.4 751.3 894.8 853.1 -537.3 -35.6% 101.8 19.1%

Each of the categories presented in the table above is reviewed in detail below.

5.1.1 PR4 New Demand Connections

The DSO PR4 forecast capex relating to new demand connections is presented below in Table 5.3.

Table 5.3 : DSO Capex – Demand Connections: comparison of PR4 Capex with PR3 (€m – 2014 prices)

PR3 Allowed

PR3 Actual

PR4 Requested

Revised PR4

Requested

Variance Revised PR4

Requested v PR3 allowed

Variance Revised PR4

Requested v PR3 actual/forecast

€m €m €m €m €m % €m %

(G1) New housing Schemes 74.6 16.7 46.5 44.2 -30.4 -40.8% 27.5 164.5%

(G2) Non-scheme Houses 164.4 89.0 106.1 107.7 -56.7 -34.5% 18.7 21.0%

(G3) Commercial/Industrial Supplies

212.5 120.8 128.5 129.8 -82.7 -38.9% 9.0 7.4%

Whole Current Metering 12.5 14.7 24.1 19.5 7.0 56.3% 4.8 32.6%

New Business – Demand Connections

464.0 241.2 305.2 301.2 -162.8 -34.2% 60.0 24.9%

Customer Contributions - Demand Connections

-232.0 -104.6 -152.6 -150.652 81.4 -35.1% -46.0 44.0%

Demand Connections Capex - NET

232.0 136.7 152.6 150.6 -81.4 -35.1% 14.0 10.2%

The DSO PR4 forecast capex (gross) is €301.2m. This is €60.0m (25%) higher than the expected PR3

outturn total capex of €241.2m. Net of customer contributions, the DSO PR4 forecast capex is €150.6m,

some €14.0m (10%) higher than expected PR3 outturn. Customer contributions are based on standard

costs for each type of connection and metering, with the customer being charged 50% of the standard costs.

Recovery of contributions during PR3 period was 45%.

The increase in gross capex as forecast by the DSO for the PR4 period is based on an increased number of

connections for each of G1/G2/G3 categories.

Details of the DSO forecast connection volumes are presented below in Table 5.4 and Figure 5.3. The DSO

forecast is based on a slow recovery within the Irish Economy, and growth projections based on increases in

population, declining emigration and Government support in financing programmes for the construction of

52 DSO has submitted a supplementary report “titled DR06 Addendum Contributions” – this identifies €150.6m of contributions relating to demand

connections for PR4, based on 50% of new demand connection costs of €301.2m. It further identifies €62.0m of contributions relating to generator connections and €22.2m of Grants relating to the NAGZ. This results in total contributions during PR4 of €234.9m. However, we note Table 6.3 (April 2015 version) states total PR4 contributions of €238.2m.

Page 110: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 105

affordable housing, in line with recent announcements53. Steady connection growth during PR4 is forecast by

the DSO and a total of 108,000 connections are expected to be made over this period, representing a 53%

increase on the total number of connections throughout PR3.

Table 5.4 : Connections made to DSO Network over period 2006 to 2020

Figure 5.3 : Connections to DSO Network over period 2006 to 2020

In order to evaluate the reasonableness of the DSO forecast of connection volumes for PR4, we have

carried out an econometric assessment of the data by connection category (G1, G2 and G3) against various

combinations of GDP and Population data (taken from the World Bank and IMF databases) covering the

historic period 2006 to 2015, with forecasts covering 2016 to 2020.

This analysis indicates that under all reasonably identifiable relationships, the forecast number of new

connections by the DSO appears to be on the lower side when compared to outputs from our analysis,

maybe representative of being conservative but not unreasonable.

The GDP and population growth forecasts for the period 2016 to 2020 that we have used in our assessment

are presented below in Table 5.5.

Table 5.5 : IMF / World Bank Econometric Growth Indicators54

Category 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Population (Millions) 4.58 4.59 4.78 4.81 4.83 4.88 4.92 4.97 5.01 5.05

Population % Growth 0.4% 0.2% 4.2% 0.6% 0.6% 0.9% 0.9% 0.9% 0.9% 0.8%

GDP (€b – 2014 Prices) 173.3 172.8 173.1 179.3 184.8 189.5 194.5 199.4 204.5 210.3

GDP % growth 2.8% -0.3% 0.2% 3.6% 3.0% 2.5% 2.6% 2.5% 2.5% 2.8%

The number of new connections (residential in particular - G1 and G2) can be linked to other factors such as

Government policy and house prices (as indicated in the ESBN document ‘DH05 New Connections’, page 6)

and these factors have not been considered in our econometric analysis. Nevertheless, the IMF and World

53 Government Announcement of 14 Oct 2014 that €2.2bn of funding is to be made available for major social housing development. 54 International Monetary Fund, World Economic Outlook Database, October 2014

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

G1 69,406 59,297 33,800 14,224 9,000 3,913 3,267 3,555 5,091 5,937 7,000 8,500 9,500 11,500 13,500

G2 21,959 19,802 17,596 12,257 9,867 6,494 5,155 4,730 4,877 4,877 5,500 6,000 6,500 7,000 7,500

G3 13,762 15,301 13,654 8,370 7,473 4,714 4,378 5,543 3,894 3,992 4,500 4,500 5,000 5,500 6,000

Total Connections 105,127 94,400 65,050 34,851 26,340 15,121 12,800 13,828 13,862 14,806 17,000 19,000 21,000 24,000 27,000

5 Year PR Total 108,000325,768 70,417

Connection

Category

Actual * Forecast

PR2 PR3 PR4

0

20,000

40,000

60,000

80,000

100,000

120,000

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Nu

mb

er

of

Co

nn

ec

tio

ns

PR2 Actual PR3 Actual PR4 Forecast

325,768

70,417108,000

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000N

um

be

r o

f C

on

ne

cti

on

s

5-year PR2 total 5-year PR3 total 5-year PR4 forecast

Page 111: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 106

Bank are expecting an upturn in fortunes for the Irish economy (and population growth) and the DSO

forecast connections volumes do not seem to fully reflect this expected up-turn in recovery/growth.

The connection numbers in each category do however, increase year on year through PR4 (G1 increasing

from 7,000 connections in 2016 to 13,500 in 2020; G2 increasing from 5,500 connections in 2016 to 7,500 in

2020; G3 increasing from 4,500 connections in 2016 to 6,000 in 2020), reflecting the increased confidence

associated with a sustained economic recovery.

Based on the above analysis, we consider that the DSO PR4 forecast of new connections of 108,000

is a reasonable assumption for tariff purposes, recognising that CER will make adjustments for

higher or lower connections based on allowed unit costs.

5.1.1.1 New Demand Connections - Unit Costs

In its original PR4 forecast submission, the DSO has proposed standard unit costs for each of the G1/G2/G3

connections. These unit costs proposed for PR4 period are presented below in Table 5.6.

Table 5.6 : Connections: Originally Proposed DSO PR4 Units Costs (€ - 2014 prices)

Connection Category 2016 2017 2018 2019 2020

G1 - Scheme Housing 905 904 926 947 947

G2 - Non Scheme Housing 3,174 3,166 3,256 3,340 3,339

G3 - Non Domestic 4,935 4,925 5,027 5,125 5,127

The following assumptions have been applied by the DSO in establishing these unit costs:

To address lower PR3 outliers and higher PR2 outliers in the range of historic unit costs, the DSO has

taken the long term average as the basis for deriving unit costs in the submission, using average prime

costs over the period 2006 to 2013.

The application of company overheads to establish gross unit costs

Smart meter penetration in PR4 connections has been assumed to be 0% in years 2016 and 2017, 50%

in 2018 and 100% in 2019 and 2020.

Average additional unit cost (prime) per G1/G2 smart meter is €80.50 plus 10% on-cost and €38.00 per

G3 smart meter (these are estimated values in advance of tender/procurement process).

Within the DSO response to a subsequent query (DSO.016.FCA), the DSO provided a revised set of unit

costs (excluding smart metering) and these are itemised in Table 5.7 below.

Table 5.7 : Connections: Revised Proposed DSO PR4 Units Costs (€ - 2014 prices)

Connection Category Cost (€)

G1 Scheme Housing 883

G2 Non Scheme Housing 3,315

G3 Non Domestic 5,090

The DSO stated that the unit costs would not vary over the PR4 period year on year but did not provide

explanation of the changes in unit costs from its original submission (as per Table 5.6) and its revised unit

costs (as per Table 5.7). In such absence, we have carried out our analysis relative to the unit costs

presented in Table 5.6.

We have reviewed unit costs for each of the G1-G3 connections over the PR2/PR3 period and analysed the

movement in costs over the period. We considered a number of different approaches including the use of

median values, rather than simple average values in order to assess impact of outliers over the assessment

period. However, this approach did not result in any reductions to unit costs.

Page 112: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 107

We have concluded that the proposed DSO unit costs for 2016 and 2017 are reasonable. However

we recommend that the additional costs that the DSO has factored in to its original unit cost

calculation from 2018 onwards should be removed, this being consistent with the DSO a priori

assumption that its forecast does not include for the introduction of smart metering. In its response

to our Interim Report, the DSO agreed with this approach

We therefore propose to adjust the DSO unit costs presented in Table 5.6 from 2017 onwards to:

Remove the additional unit costs associated with smart metering

Apply incremental reduction to the gross costs from 2018 to 2020 on the same basis as applied by the

DSO in its adjustment to gross unit costs between 2016 and 2017.

These adjustments result in proposed unit costs set out in Table 5.8 below.

Table 5.8 : Recommended Unit Costs for PR4 compared to DSO Unit Costs (€ - 2014 prices)

Category DSO Unit Costs Recommended Unit Costs

2016 2017 2018 2019 2020 2016 2017 2018 2019 2020

G1 Scheme Housing 905 904 926 947 947 905 904 903 902 901

G2 Non Scheme

Housing 3,174 3,166 3,256 3,340 3,339 3,174 3,166 3,158 3,150 3,142

G3 Non Domestic 4,935 4,925 5,027 5,125 5,127 4,935 4,925 4,915 4,905 4,895

Applying the unit costs provided in table 5.7 to the DSO forecast connection volumes will result in the revised

capex shown in Table 5.9 below.

Table 5.9 : Demand Connections – Recommended Capex (€m – 2014 prices))

2016 2017 2018 2019 2020

TOTAL - PR4

Recommended

PR4 - DSO

Forecast

PR4 – Revised

DSO Forecast

G1 Scheme Housing 6.3 7.7 8.6 10.4 12.2 45.1 46.5 44.2

G2 Non Scheme

Housing 17.5 19.0 20.5 22.1 23.6 102.6 106.1 107.7

G3 Non Domestic 22.2 22.2 24.6 27.0 29.4 125.3 128.5 129.8

Total Expenditure 46.0 48.8 53.7 59.4 65.1 273.0 281.1 281.7

A reduction in allowed PR4 gross capex of €8.7m (relative to the DSO’s revised forecast) is

recommended for PR4 demand connections, based on the exclusion of the DSO’s provision for roll

out of smart meters within the connections activity.

5.1.1.2 Analysis of PR4 meter costs

For PR4 the DSO is forecasting total metering capex of €19.5m. This is €4.8m (32.6%) higher than PR3

expected outturn costs and €7m (56.3%) higher than PR3 allowed costs. A comparison of DSO metering

costs is provided below in Table 5.10. The proposed increase in capex for PR4 is the result of the DSO’s

forecast increase in connection volumes.

Table 5.10 : DSO PR4 Forecast Metering Costs (€m – 2014 prices)

Category PR3 Allowed PR3 Actual

DSO Original

PR4 Proposed

DSO Revised PR4

Proposed

Metering – G1 Domestic - Scheme 5.2 Not itemised

Page 113: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 108

Category PR3 Allowed PR3 Actual

DSO Original

PR4 Proposed

DSO Revised PR4

Proposed

Metering – G2 Domestic Non-Scheme 15.3

Metering – G3 Non-Domestic 3.5

Total Metering 12.5 14.7 24.1 19.5

The CER allowed metering costs in PR3 were based on an average unit cost of €87 (2014 prices) for whole

current metering.

Our review of PR3 capex identified that actual metering costs over the period 2011 to 2013 resulted in

average costs that were significantly higher than the CER allowed costs, with average metering costs in the

range of €178 to €218. The DSO provided a detailed explanation to explain this apparent adverse variance

and this was reviewed during our assessment of DSO historic capex. Specifically, the closing of cost

accounts relating to dormant connection projects, to prevent misallocation of costs, has resulted in final

connection cost and the metering cost both being allocated to the metering cost code, resulting in an

increase in metering costs.

We concluded that the analysis provided by the DSO supports the higher metering capex costs incurred

during PR3. We also stated the importance that the assessment of PR4 allowed revenues for connections

and metering takes due account of the fact that a proportion of G1-G3 connections costs have been

allocated to metering capex during PR3. The lack of transparency in metering costs during PR3 has resulted

in PR4 forecast metering capex including an element of connection costs within the totals.

In its response to our Interim Report relating to PR4 forecast expenditure, the DSO has stated:

“While ESBN is undertaking a project at present to better identify the specific costs associated with metering

as opposed to other works, it is important that any reduction in the PR4 allowed metering cost (on the

premise of metering only being allowed in the proposed unit cost) would be accompanied by corresponding

increases in the allowed cost of new connections such that the total allowed expenditure is based on the

complete costs of previous years. Alternatively, an allowed unit cost based on the historical information used

and provided by ESBN is appropriate, on the premise that under certain circumstances final connection

works are completed as part of an integrated project cost”.

The DSO PR3 metering costs of €14.7m equates to 6.5% of the PR3 gross capex of €226.5m relating to

G1/G2/G3 connections. For PR4 period, the DSO proposed metering costs of €19.5m equates to 6.9% of

the PR4 gross capex of €281.7m relating to G1/G2/G3 connections.

We recommend allowances for PR4 period based on 6.5% of our recommended PR4 gross capex

for G1/G2/G3 connections of €273m.

This results in a recommended allowance for metering of €17.8m representing a reduction of €1.8m

compared to DSO revised PR4 proposed capex of €19.5m.

We would encourage the DSO to complete the project relating to the more accurate allocation of

costs associated with metering. This should be completed as a matter of priority early in the PR4

period.

5.1.2 Generator Connections55

For generator connections the DSO is forecasting gross capex in PR4 of, in headline terms, €109.5m (as

shown below in Table 5.11). This represents an increase of 24.4% compared to expected PR3 outturn.

Table 5.11 : New Connections Capex (Generator Connections) – Comparison of PR3 v PR4 Forecast (€m – 2014 prices)

Category PR3 PR3 DSO PR4 Variance PR4

Requested v PR3

Variance PR4

Requested v PR3

55 Note for Capex associated with Generator Connections, The DSO revised capex (issued March 2015)for the PR4 period is the same as its

original capex (issued in November 2014)

Page 114: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 109

Allowed Actual Proposed allowed actual/forecast

€m % €m %

Generation Connections – Gross Capex 166.5 88.9 109.5 -57.0 -34.2% 20.6 23.2%

During PR3, approximately 1,200 MW of renewable generation was connected to the DSO distribution

system. During the PR3 period, the CER approved a suspension of the expiry dates on the issued Gate 3

connection offers until issues regarding constraints and curtailment of wind were fully resolved. This

resolution came in the form of a SEM decision in March 2013, and all applicants were provided with

constraint and curtailment levels applicable to their projects.

Consequently most of the Gate 3 offers were accepted during the summer of 2013 and the DSO expects

significant activity in the latter part of PR3 and into PR4. Gate 3 projects entered design and scoping phase

during 2014-2015 and this is forecast to continue into 2015 and the DSO expects construction works to

commence from 2016 on large numbers of these projects. Capex during PR4 will therefore be focused on

these Gate 3 projects that have contracted since mid-2013. The DSO is estimating that a total of 1,250 MW

is to be connected to the distribution system during PR4, a similar magnitude to the capacity connected

during PR3 (1,200 MW). The estimated PR4 aggregate capacity is less than the current level of contracted

generation as the DSO is not expecting all contracted Gate 2 / Gate 3 connections will progress to

completion and there is some uncertainty about which projects will proceed to completion by 2020.

The developer for a proposed wind farm also has the option to follow a contestable path relating to the

connection to the DSO network (excluding non-contestable works). This choice is available to the developer

until the latter stages of the overall connection process (but always pre-construction commencement) and

such late decisions can impact on project scope, cost and timescales. This situation makes a simplified

comparison of the PR3 Actual and PR4 proposed costs/MW somewhat inappropriate at the present time.

The DSO forecast has taken into account the projects which are contestable and also those where

contestability is anticipated (e.g. where a modification to the connection application is in progress). Of the

Gate 3 projects in progress, the DSO has advised that approximately 60% are being contested (i.e. shallow

works) and for each project, some element of work, classed as non-contestable will be necessary.

The high volume of accepted connection offers in the summer of 2013, coupled with the requirement to meet

the REFIT56 deadline for completed connections by end of 2017, results in the forecast capex/ contributions

presented below in Table 5.12 and Figure 5.4.

Table 5.12 : New Business (Generator connections) – PR4 forecast cash flow (€m – 2014 prices)

Generator Connections 2016 2017 2018 2019 2020 PR4 Total

Gross Capex 49.4 32.9 8.8 8.8 9.6 109.5

Customer Contributions57 -27.9 -18.6 -5.0 -5.0 -5.6 -62.0

Net Capex 21.5 14.3 3.8 3.8 4.0 47.4

56 REFIT II – Renewable Energy Feed In Tariff – Incentive to promote development of renewable energy projects which provides price

guarantees for 15 years. Criteria includes requirement for connection by end of 2017. 57 DSO Supplementary Report titled “DR06 Addendum Contributions” confirms €62.0m of contributions relating to generator connections – this

figure being consistent with Table 6.4 of the DSO FBPQ

Page 115: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 110

Figure 5.4 : New Business (Generator connections) – PR4 forecast cash flow (€m – 2014 prices)

The DSO forecast has been compiled based on the likely progression of accepted offers, and is consistent

with the high level of expenditure forecast for 2015. Due to the profiling of customer contributions versus

capital expenditure it should be noted that there was a level of over-recovery in PR3 which is reflected in a

degree of under-recovery being forecast for PR4.

As expected in our review of DSO historic capex, the over-recovery of connection costs in later years

of PR3 is resulting in net positive cash flows throughout the PR4 period, with a total net capex over

PR4 period of €47.4m.

We recommend acceptance of the DSO proposal for gross capex of €109.5m

5.1.3 Load Related Reinforcement

The DSO load-related reinforcement capex for the PR4 period is shown in Figure 5.5 below showing a total

PR4 reinforcement capex of €317.8m. Although this is significantly below the PR3 allowed capex of

€648.1m, it is only €6.9m (2.1%) lower than DSO expected outturn (€324.7m) for the PR3 period.

Table 5.13 details capex for each of the defined reinforcement categories.

49.4

32.9

8.8 8.8 9.6

-27.9

-18.6

-5.0 -5.0 -5.6

-40.0

-30.0

-20.0

-10.0

0.0

10.0

20.0

30.0

40.0

50.0

60.0

2016 2017 2018 2019 2020

Gross Capex Customer Contributions Net Capex

Page 116: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 111

Figure 5.5 : PR4 DSO Reinforcement Capex compared to PR3 (€m – 2014 prices)

Table 5.13 : Comparison of PR4 Forecast v PR3 Capex – Load Related Reinforcement (€m 2014 prices)

PR3

Allowed

PR3

Actual

DSO

Original

PR4

Proposed

DSO

Revised

PR4

Proposed

Variance Revised

PR4 Proposed v

PR3 allowed

Variance Revised

PR4 Proposed v

PR3

actual/forecast

€m % €m %

Transmission Connection

Costs 26.3 0.0 15.2 15.2 -11.1 -42.3% 15.2 -

110kV Reinforcements 236.1 144.4 150.4 150.4 -85.7 -36.3% 6.0 4.2%

38kV Reinforcements 215.2 86.5 85.9 85.9 -129.4 -60.1% -0.6 -0.7%

MVLV System Improvements 70.8 34.5 40.9 40.9 -29.8 -42.2% 6.5 18.8%

IFTs associated with 20kV

Conversion 16.6 22.9 0.0 11.1 -5.5 -33.1% -11.8 -51.6%

20kV Conversion 83.0 36.5 25.4 14.3 -68.7 -82.8% -22.2 -60.8%

Total Reinforcements 648.1 324.7 317.8 317.8 -330.3 -51.0% -6.9 -2.1%

The main drivers for reinforcement expenditure relate to growth in peak demand and the requirement of the

DSO to comply with the Planning Standards for Security and Voltage. The DSO’s proposed PR4

reinforcement capex forecast has been prepared on a zero cumulative load growth forecast for peak demand

from 2013 to 2020. Factors cited by the DSO which will contribute to this zero growth scenario include:

648

325 318

0

200

400

600

800

5 Year Total

€m

PR3 Allowed PR3 Actual PR4 Revised Forecast (April 2015)

Page 117: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 112

Smart Metering rollout should divert load from peak time to less expensive lower demand periods with

an associated reduction in the longer term drivers for network reinforcement58.

Increasing trend in the production of energy efficient appliances will also contribute to the containment

of peak growth.

20kV conversion plan will reduce losses on the network, most significantly at time of peak but will not

impact on end user consumption.

The recorded system peak demand over the period to 2013 is shown below in Figure 5.6. The peak demand

in 2007/08 was 4,914 MW whilst the peak in 2013/14 had reduced to 4,523 MW.

Figure 5.6 : System Peak Demand (MVA) to 2013

The DSO has made significant investments to reinforce the network during previous price controls. However,

there are still many parts of the network that do not comply with the Planning Standard. This is evidenced in

Table 5.14 below. This table identifies the number of substations (110kV and 38kV) that were loaded outside

the requirements of the DSO Planning Standard. For 38kV substations, the number of stations that do not

comply with the Planning Standards has reduced from 105 to 32 during PR3, whilst for 110kV stations, a

reduction from 16 to 5 has been achieved.

Despite investment throughout PR2 and PR3 (albeit reduced in PR3), it is clearly evident that further

reinforcement is required, even with an assumed zero percentage growth in peak demand. However, there

is little evidence of the DSO considering ‘smart solutions’.

Table 5.14 : HV Station Loading -Summary

Year

38kV Substations

loaded above

Planning Criteria

38kV Substations

normally loaded

above 75%

110kV Substations

loaded above

Planning Criteria

110kV Substations

normally loaded

above 75%

2000 68 213 5 16

2005 65 190 16 35

2010 105 187 16 38

2015 32 75 5 19

58 Although it should be noted that Smart Metering rollout is not expected to be complete until 2019 or 2020 and significant reduction in peak

demand is not expected until Time of Use tariffs are introduced which may take a further 1 – 2 years, i.e. outside the PR4 period.

Page 118: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 113

Although growth in peak demand on the network has been assumed to be zero, the DSO does forecast an

increase in energy consumption during PR4. This is illustrated in Figure 5.7 below. Unit sales (GWh) during

PR4 are forecast to grow at approximately 2.2% per year. We undertook regression analysis to determine a

reasonable relationship between unit sales and various combinations of both GDP and population. The

strongest relationship identified was a positive one with related unit sales to GDP. The DSO’s proposed

growth in unit sales is considered to be reasonable when compared to the sound relationships identified

through regression analysis. The DSO has assumed that that the unit sales growth does not result in peak

demand growth.

Figure 5.7 : Total Units Distributed (GWh) – 2005 to 2020

The DSO’s forecast of zero load growth coupled with related growth of other econometric indicators (such as

GDP and population) suggests a conservative approach has been taken by the DSO in developing its PR4

reinforcement forecast (i.e. there is an increased likelihood of a cost overrun in PR4 outturn). We have also

observed that the DSO’s assessment of peak loadings in order to identify, prioritise and schedule

reinforcement projects also takes account of potential impact on peak demand following the roll-out of smart

meters. The DSO has assumed that introduction of Smart Meters will reduce the contribution of domestic

load to system peak by 8%59.

On the basis that domestic load comprises approximately 50% of the total load, the DSO has assumed that

the total peak is expected to be reduced by 4%. Consequently only the stations that remain overloaded after

their current loading have been adjusted for the introduction of Smart Meters in the PR4 Submission.

Both of these assumptions (zero load growth and peak demand reduction due to smart metering impact) act

to suppress the capex forecast requirements for PR4 relative to previous price controls.

We sought assurance from the DSO that it had carried out sensitivity analysis to determine the capex

requirements for reinforcement assuming zero smart meter impact, compared to their proposed PR4

programme. The DSO has confirmed that sensitivity analysis has been carried out which confirmed that if no

allowance was made for Smart Meters an additional five HV reinforcement projects would need to be

included in the PR4 programme, comprising three additional substation uprating projects and two load

transfer projects.

59 This information came from a report that was published by the CER entitled " Electricity Smart Metering Customer Behaviour Trials (CBT) Final

Report, CER11080(a), 16th May 2011". The report states that the outcome of the Residential Trial was that Smart Meters would reduce the overall electricity usage by 2.5% and peak usage by 8.8%.

19,000

20,000

21,000

22,000

23,000

24,000

25,000

26,000

27,000

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Un

its

Dis

trib

ute

d (

GW

h)

Actual (to 2013) PR3 Forecast (2009) PR3 Actual Units PR4 Forecast

Page 119: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 114

The DSO PR4 programme is therefore based on addressing network deficiencies that will remain after

accounting for the impact of Smart Meters. Such deficiencies will encompass existing major breaches of

planning and safety standards have been identified. These breaches include:-

Plant Overloading

Non-Compliance with Voltage Standards

Safety standards (Short Circuit Deficiencies)

To address these deficiencies, the DSO proposes investment on an annual basis as shown below in Figure

5.8, and Table 5.15.

Figure 5.8 : PR4 DSO Proposed Reinforcement Capex Plan (€m – 2014 prices)

Table 5.15 : PR4 DSO Reinforcement Capex by Category

2016 2017 2018 2019 2020 PR4 Total

110kV (including Transmission Connection

Costs) 25.3 28.1 33 38 41.3 165.7

38kV 13.1 14.5 17.1 19.7 21.4 85.8

MV LV System Improvements 6.3 6.9 8.2 9.4 10.2 41.0

IFTs associated with 20kV Conversion

including 20kV network conversion 3.8 4.3 5.1 5.8 6.3 25.3

Total 48.5 53.8 63.4 72.9 79.2 317.8

Within the scope of the reinforcement plan for PR4, the DSO proposes to install the following infrastructure

projects and volumes (Table 5.16 and Table 5.17).

Table 5.16 : PR4 Summary of Reinforcement Projects

Project Driver Network Item Quantity

Infrastructure Installed to address plant

overloads

New 110kV/MV Substations 5

Uprated 110/38kV Substations 5

110kV/MV installations in existing 110kV Substations 5

New 38kV/MV Substation 1

48.553.8

63.472.9

79.2

0

10

20

30

40

50

60

70

80

90

2016 2017 2018 2019 2020

€m

Page 120: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 115

Project Driver Network Item Quantity

Uprated 38kV/MV Substations or additional 38kV/MV

capacity in 110kV Substations

22

Load transfers at MV to defer new/uprated Substations 3

New 110kV Circuits 1

New 38kV Circuits 8

Infrastructure installed to address

Voltage Compliance Issues

New 110/38kV Substations 1

New 38kV/MV Substations 2

Infrastructure installed to address Short

Circuit Level Deficiencies

Replacement of inadequately rated 110kV busbars 2

Table 5.17 : PR4 Reinforcement Infrastructure Volumes

Plant Unit of

Measure

Projected Capacity to be

installed in PR4

110/38kV Transformers MVA 220.5

110kV/MV Transformers MVA 311.5

38kV/MV Transformers MVA 163

110kV Lines km 35

New and Reconstructed 38kV Lines km 150.2

110kV Cables km 19

38kV Cables km 1

In relation to the proposed 38kV lines, the DSO has also included a provision for €5.6m during PR4 relating

to land access payments. This provision relates to ongoing negotiations with the Irish Farmers Association

(IFA) that are nearing completion and relate to set access payment arrangements for the construction of

single pole 38kV 150mm2 AAAC circuits, using average payments per km of line as opposed to payments

based on number/type of structures positioned within landowner’s property. This “Flexibility of Access

Payment” is estimated to be €45k/km at 38kV.

5.1.3.1 Assessment of the DSO Reinforcement HV (110kV and 38kV) Investment Plans for PR4

The load related network investment requirements for the DSO network are set out in two plans:

a) HV Network Investment Plan 2014-2024, November 2014 - Covers the entire 38kV network,

excluding Greater Dublin, divided into 26 Zones.

b) HV Network Investment Plan-Dublin 2014-2024, October 2014 - Covers the 38kV and 110kV

network in Greater Dublin divided into 5 Zones.

The methodology employed by the DSO in undertaking these load related investment plans is set out below:

Load Growth

The load growth for both investment plans is based on winter 2013 demands taken from substation

recorders complemented by SCADA load profiles where available. A blanket 2% per annum growth rate is

applied to the demands throughout the network including Greater Dublin. Substation demands are adjusted

by the demand of known committed large developments. It is noted that only a single 2% growth scenario

was studied within these investment plans, with the DSO citing that such a scenario would allow for optimum

reinforcement solutions to be identified and developed when the need arises rather than taking a more

narrow view which could lead to sub-optimal development.

Page 121: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 116

The PR4 HV/LV Reinforcement Programme both Nationally and for Dublin, has been formulated on zero

growth scenarios (i.e. no reinforcements are driven by the 2% growth scenario detailed above).

Network Performance Review

For each year of the plans the performance of the network is analysed and reviewed against the Planning

and Security of Supply Criteria60, under intact (N) and contingency (N-1) network conditions. The review

identifies:

a) Non-firm overhead line, cable and substation transformer capacity.

b) Network voltage levels below the standard.

c) Short circuit levels approaching switchgear ratings.

A project is identified to overcome any non-compliance with the Planning Standard and an Investment

Appraisal (IA) document is prepared to determine the outline design and Prime Cost61 of the project.

Schedule of Investment Requirements

Each investment plan includes a schedule of projects for each zone that states Gross Costs62 and the year in

which the project is required to be in service.

Adequacy of Investment Plans

The process employed by the DSO in developing load related investment plans reflects Good Industry

Practice as undertaken by Distribution Companies in many regulated jurisdictions.

Investment Appraisals (IA)

An IA document is prepared for each project identified in the Network Investment Plans. Because of the

recent economic downturn most of the projects identified in the previous investment plans have not

materialised therefore the IAs prepared in 2011 are still valid. Accordingly the IAs submitted for PR4

comprise the 2011 IA with a 2014 Addendum.

5.1.3.2 Investment Appraisal Methodology for HV Reinforcement Projects

The methodology employed by the DSO in undertaking IAs is set out below.

Project Divers

The IA identifies the non-compliance with the relevant Planning Standard(s) that is the driver for the project.

Options

Options to overcome the non-compliance are identified and generally can include the following:

a) Do nothing

b) Transfer demand to adjacent substations

c) Uprate or refurbish substations with larger transformer capacity

d) Build/Develop a new substation

e) Reinforce or replace overhead lines and cables circuits

60 Dated 7 June 2007 61 Time + Material + Other +ESBI Costs. 62 Sometimes itemised but not defined in IAs.

Page 122: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 117

The options should take into account the condition of plant and equipment and other development projects

that have an interacting impact on network performance.

Technical and Financial Appraisal of options

Outline designs of each viable option are developed which subsequently identify the principle items of plant

and equipment required for the project. Prime Cost estimates are then prepared using Base Planning Object

Costs (2nd Generation edition, November 2014).

A technical and financial appraisal of each option is undertaken, including the capitalisation (NPV) of losses

where these are significant, and the Least Cost Technically Acceptable (LCTA) option is selected.

Adequacy of Investment Plans

The process employed by the DSO in developing investment appraisals for planned capex investment

projects reflects historic Good Industry Practice as undertaken by Distribution Companies in many regulated

jurisdictions albeit that investigation of ‘smart’ alternatives are now being investigated in a number of

jurisdictions.

Gross Costs

The 2014 addendums to the IAs include a cost (stated as an NPV) that is not defined as prime or gross but

generally corresponds to the project Gross Costs set out in the Network Investment Plans. The uplift factor

applied to Prime Costs to give Gross Costs varies from project to project.

5.1.3.3 Sample Review of IAs

IAs for eight projects selected by the DSO have been reviewed and a summary of the outcome is set out in

Table 5.18.

Page 123: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 118

Table 5.18 : IA Review Summary

ID Project Project Driver All

Options

Preferred Option LCTA 2011

Prime

Cost (€M)

63

2014

Prime

Cost (€M)

2014

Gross

Cost (€M) 64

2014 NPV

(€)

Apparent

Overhead

Factor65

Comment

SD301 Abbeyliex

Substation

Abbeyliex MV voltage

below Standard during

normal and standby

feeder arrangements

Yes New 1x5MVA 38kV/MV

substation at Abbeyliex

Yes 2.746 Not Stated 4.661 8.6466

1.697

KP0109 Bagenalstown

Substation

Existing 2x5MVA

38/10kV TXs non-firm

throughout year under

N-1 conditions &

overloaded during winter

peaks under N

conditions

Yes Refurbish Bagenalstown

to 2x10MVA 38/20kV

with 2x20/10kV TXs to

feed retained 10kV

network

Yes 2.557 Not Stated 2.740 1.96 ? Addendum to the 2011 IA states that a

cost reduction is applicable to 2011

costs as no 38kV work required to

uprate to 2x10MVA but this does not

appear to have been reflected in the

Gross Cost in the Investment Plan

PB042 Ballygar

Substation

Existing 1x5MVA

38/10kV TXs overloaded

during winter peaks

Yes Install additional 5MVA

38/10kV TX

Yes 1.024 Not Stated 2.161 0.8166

2.110 Addendum to 2011 IA states NPV of

0.81 which does not appear consistent

with Prime or Gross costs?

TM0055 Baroda

Substation

Existing 2x10MVA &

2x5MVA 38kV/MV

substations feeding

Newbridge Town non-

firm under N-1 winter

peaks

Yes New 2x20MVA

110kv/MV substation at

Baroda

Yes 5.407 Not Stated 7.166 10.766 1.325

63 2011 Investment Appraisal (IA) 64

Appendix A HV Network Investment Plan 2014-2024, November 2014 65 Based on 2011 Prime Cost 66 Includes capitalised losses

Page 124: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 119

BF0003 Kinsale

Substation

Existing 2x5MVA

38kV/MV substation

non-firm under N-1

winter peaks

Yes Uprate Kinsale to

2x10VA 38kV/MV TXs

Yes 2.459 Not Stated 1.998 1.99 ? Addendum to 2011 IA states NPV of

1.99 as costs have been reduced – not

clear whether NPV is Prime or Gross?

CY021A Oranmore

Substation

Existing 2x5MVA

38kV/10kV substation

non-firm under N-1

winter peaks

yes Uprate Oranmore to

2x10VA 38kV/10kV TXs

Yes 1.138 Not Stated 1.998 1.99 1.756

CC0012 Trabeg

Substation

Existing 2x31.5MVA

110/38kV TXs non-firm

throughout year under

N-1 conditions &

overloaded during winter

peaks under N

conditions

Yes Uprate Trabeg to

2x63MVA 110/38kV TXs

Yes 2.899 Not Stated 3.466 4.5866

1.196

DH094 Drynam

Substation

Three 2x10MVA

38kV/MV substations

serving Swords non-firm

under winter peak N-1

conditions

Yes New 2x20MVA

100kv/MV substation at

Drynam

Yes 11.807 Not Stated 18.60067 13.70 1.575

67 HV Network Investment Plan-Dublin 2014-2024, October 2014

Page 125: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 120

The general issues arising from the review are:

1) Uplift on Prime Costs to give Gross Costs as uplift varies from project to project.

2) The 2014 Addendums do not indicate whether costs are Prime or Gross. Also some 2011 IAs cost

comparisons are based on Prime Costs whereas others are based on Gross Costs.

3) There are some minor numerical differences between comparable 2011 and 2014 costs.

4) Appendix A to the HV Investment Plan indicates that the majority of projects are required by 2016

whereas logistically it is questioned whether the implementation by this date is realistic. It is also not

consistent with the annual PR4 capex plan illustrated in Figure 5.8 above.

Some project specific issues arising from the review are:

1) Project ID KP0109 - the reduced 2014 NPV cost does not appear to have been carried forward to

Appendix A of the HV Network Investment Plan.

2) Project PB042 – the 2014 NPV cost does not appear to be consistent with the Prime or Gross costs.

3) Project BF0003 - the reduced 2014 NPV cost and Gross Cost to account for a different control room

construction is significantly less than the 2011 Prime Cost which seems inconsistent with the cost

saving due to control room construction.

5.1.3.4 Unit Costs for System Reinforcement Projects

The DSO has provided a report detailing an independent study carried out to benchmark its unit costs for

new build works for both connections and system reinforcements. The comparison has been carried out

relative to GB DNO’s. The biggest challenge with carrying out such benchmarking studies is to ensure that

the comparisons are made on a like for like basis. Items such as design costs, engineering management,

transport and associated civil work costs are not always included in such comparisons.

Because of such difficulties, Ofgem has previously separated out direct and indirect costs (DPCR5) and

benchmarked DNO direct costs only. More recently, RIIO-ED1 comparison of unit costs excluded civil costs.

The independent study commissioned by the DSO has been carried out on direct costs excluding civil works.

As part of its Questionnaire submission, the DSO provided a set of asset unit costs (Table 4.3 of PR4

Distribution Future Questionnaire) which were then subject to adjustments prior to being used in the

benchmarking study. The following adjustments were made to the DSO unit costs provided in its

Questionnaire response:

Labour Costs in Table 4.3 were subject to an additional surcharge in the range of 1.38 – 1.60 to account

for certain labour related costs included in DNO labour costs but not in the DSO unit costs (Annual

Leave, travel time, sick leave, personal protective equipment).

Design Fees were subtracted from the unit costs (as they were not included in the comparison data

costs).

Civil works costs for major HV station works were removed.

For underground cables a proportion of civil works costs were applied.

We are familiar with the benchmarking approach that has been carried out. The results of the benchmarking

study generally indicate that the DSO unit costs compare favourably with the UK DNO unit costs. However

there are a number of uncertainties with the exercise that need to be borne in mind when analysing the study

results:

The DSO unit costs relate to new build/system reinforcement whilst the DNO unit costs relate to asset

replacement works, which tend to be higher than the corresponding unit cost for new build.

DSO unit costs relate to the in-house delivery of projects, whilst DNO costs may include costs from

external service providers – the extent of this is unknown.

Page 126: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 121

The DSO has applied Purchasing Power Parity (PPI) Index to convert its in-house labour costs to £

sterling at a value of 0.84.

For some assets (such as transformers) with different sizes/specifications, only a single DNO unit cost

has been published – this is likely to be an average cost across the range of costs within such an asset

category. This means that comparison of this average published DNO unit cost has to be made across

the range of the DSO unit costs.

Given the uncertainty with the above and although the results of the independent study show that the DSO

costs compare favourably with DNO unit costs and are not unreasonable, they should be considered with

appropriate caution. Where possible we have also made assessment of DSO outturn unit costs for PR3 and

compared with the planned unit costs for PR4 work programmes. This is considered more fully within our

assessment of the DSO’s forecast for non-load related capex.

We are satisfied that the DSO has established good practice relating to its preparation of

investment plans for its 110kV and 38kV network development and undertaking project investment

appraisals before seeking technical and financial approval and subsequent commitment of capex to

a project.

Notwithstanding some errors and/or inconsistencies with the consolidated list of HV reinforcement

projects compared to individual project IAs, these are not considered to be material and we

conclude that the DSO proposed PR4 reinforcement capex for 110kV and 38kV projects to be

reasonable.

5.1.3.5 MV/LV Reinforcements

The DSO has proposed a total of €40.9m of reinforcement capex relating to the MV and LV network. This

investment is proposed to target known network deficiencies and projects will involve one or more of the

following:

Increased Three phase Medium Voltage Capacity additional or uprated MV/LV station capacity.

Reinforcement of MV Circuits by installation of additional MV Circuits.

Reconductoring MV and LV overhead Network to increase MV/LV capacity and reduce volt drop.

Installation of MV boosters to improve voltage on normal and standby operation.

Installation of reclosers to bring protection of the network within standard.

Installation of new sections of MV cables or overhead lines to loop network where the load has

increased above 1MVA.

Conversion of single phase network to 3 phase network to address voltage problems or address

unbalance problems on the network.

Rebalancing network.

We have not observed any investigation/planned use of smart grid technologies or “Smart” solutions by the

DSO within its PR4 capex plans to address network reinforcement requirements. The proposed PR4 capex

(€40.9m) represents a 18.8% increase compared to expected costs for PR3 (€34.5m), although considerably

less than PR3 allowed costs of €70.8m.

Page 127: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 122

We generally agree with this work being necessary although we would recommend allowances for

PR4 such that PR3 actual and PR4 forecast capex is consistent with the PR3 allowed capex of

€70.8m – this was allowed to address known network deficiencies and is considered adequate for

the DSO’s zero growth scenario.

In addition we would expect the ongoing 20kV conversion programme to continue to improve the

network and reduce reinforcement requirements.

This will reduce PR4 allowances for MV/LV System reinforcements by €4.6m to €36.3m.

5.1.3.6 20kV Conversion Programme

DSO PR4 forecast capex relating to its ongoing 20kV conversion programme is €14.3m with a further

€11.1m of capex relating to the installation of Interface Transformers (IFTs) – giving a total of €25.4m. This

total expenditure will be targeted towards converting approximately 4,000km of existing 10kV network to

20kV operation. The DSO estimates that more than 90% of the 20kV conversion required in PR4 is required

due to current network being outside voltage standards based on 2012 loads.

In the 1990’s, the DSO embarked on a programme to convert most of its 10 kV MV network to 20 kV. The

DSO is able to convert parts of its network to 20 kV by changing pole transformers and maintaining the

existing line insulation which was designed for an unearthed 10 kV system, but converting to an earthed

20 kV system.

The capacity of an uprated line is increased by a factor of 4 and for the same capacity the losses are

reduced to one quarter.

Uprating has some disadvantages in that the fault rate can increase in the early years after uprating as the

line operates at higher stresses and incipient defaults are discovered.

In addition to the network capacity gains achieved through conversion to 20kV, the financial justification for

this programme is augmented by the losses savings achieved.

At the end of PR1 18,500km of the MV network was operating at 20kV and a further 30,000km of overhead

network had been refurbished to 20kV standard.

During 2006-2010 an additional 19,000km of network was converted to 20kV operation.

The DSO’s latest forecast for PR3 includes the uprating of a further 15,000 km of overhead line at a cost of

€102m.

The proposal for the conversion programme in PR3 was based on an MV network study that was carried out

in 2009. This resulted in a plan to convert 15,000km of network that were outside standard. The PR3 plan to

convert 15,000km was adjusted and the latest DSO forecast is that 10,500km will be converted to 20kV

operation by the end of PR3. The resulting balance of network deferred from PR3 is the planned target for

PR4.

We agree there are strong benefits in continuing with the conversion programme. We have satisfied

ourselves that the DSO has in place an appropriate cost-benefit and prioritisation process, with the CBA

considering the impact of losses on the network, together with improved network voltage.

The DSO expected PR3 volumes (10,500km) and capex (€36.5m) result in a unit cost per km

converted of approximately €3,475/km. The DSO proposed PR4 programme is based on converting

4,000km at the same unit cost, giving a total cost of €13.9m.

Further IFT works at costs comparable with PR3 are also proposed.

We consider these to be reasonable costs and consequently we recommend PR4 allowance of

€25.0m.

Page 128: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 123

5.1.4 Dismantling Costs

DSO forecast capex associated with dismantling (or “retirements”) for the PR4 period is shown in Table 5.19

below.

Table 5.19 : Comparison of PR4 Dismantling Costs (€m – 2014 prices)

PR3 Allowed PR3 Actual68 DSO Original PR4

Proposed

DSO Revised PR4

Proposed

Variance of PR4

revised forecast

to PR3 Allowed

Variance of PR4

revised forecast

to PR3 Actual

58.8 48.3 70.2 64.4 5.6 16.2

PR3 allowed capex was based on an ‘a priori’ assumption that dismantling costs were directly proportional to

the gross cost of load related and non-load related network capex. The PR3 allowed costs were based on

4.8% of this gross value, although the actual dismantling costs incurred during PR3 are expected to be 4.1%

of the PR3 gross value.

The DSO introduced revised project costing procedures (Integrated Work Management Module) within their

SAP application from 2009 onwards. This allowed the DSO to allocate dismantling costs more directly to the

work activity that has driven the need for the dismantling to be carried out. Allocation of dismantling costs

over the period 2011 to 2013 identified that 30% of dismantling cost arose from activities that are not part of

the formula used to determine PR3 allowances, in particular New Business and Line Diversions.

We concluded in our review of DSO PR3 capex that the change in the DSO cost allocation procedures has

provided improved visibility of the drivers on the dismantling activity and associated costs

The DSO forecast for PR4 dismantling cost allocation has been derived based on the application of the

outturn percentage allocations during 2011-2013 to each relevant category of its PR4 forecast, as itemised in

Table 5.20 below.

Table 5.20 : PR4 Dismantling Cost Allocation

Capex Category % Allocation applied to

Gross Cost

New Business 2.5%

Generator Connections 0.8%

Diversions 11.8%

Reinforcement 2.5%

Non-Load Related 6.1%

Application of this approach resulted in the DSO PR4 original forecast for Dismantling of €70.2m, equivalent

to 4.4% of the DSO’s gross PR4 network-related capex. Its PR4 revised forecast of €64.4m is equivalent to

4.2% of its revised PR4 forecast gross capex of €1.52bn.

We tested this approach against PR2 gross capital expenditure and our analysis calculated a hypothetical

PR2 dismantling cost of €97m although the PR2 outturn was significantly less at €67.7m. This differential

demonstrates the sensitivity of the results to the overall capex disaggregated into the different capex

categories.

The PR2 outturn dismantling costs were 2.7% of gross costs whilst the PR3 outturn dismantling costs are

expected to be 4.1% of gross network capex costs.

We therefore recommend PR4 allowances for dismantling which are derived as a proportion of our

68 Includes €29.1m (2014 prices) of dismantling costs over the period 2011 to 2013 that were allocated by ESBN to their Income Statement

Page 129: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 124

recommended PR4 gross network capex – with allowances set at 4.1% of this gross value - this

results in a recommended PR4 capex for dismantling of €55.1m, representing a reduction of €9.3m

compared to the DSO revised forecast of €64.4m.

The DSO has also provided commentary in its submission relating to the future treatment of dismantling

costs. They present two options for consideration by, and agreement with, the CER. The two options are:

1) Maintain the dismantling (retirement) cost line as a separate heading within its capex reporting

framework; or

2) Record the dismantling costs against the activity that is the main driver to the dismantling requirement.

The DSO’s stated preference is to implement option 2 in order to simplify the current basis for determining

capital and dismantling allowances to the mutual benefit of CER and the DSO. The preferred approach is

normal practice within many utilities in other jurisdictions. Whilst we agree with the DSO that it provides more

accurate allocation of costs and better understanding of costs for the main work driver, this benefit is

countered by a resulting loss of transparency of costs at this detailed level. On balance, Jacobs would

support adopting option 2.

5.1.5 Non-Repayable Line Diversion Costs

DSO forecast capex associated with line diversions for the PR4 period is shown in Table 5.21.

Table 5.21 : Comparison of PR4 Line Diversion Costs (€m – 2014 prices)

PR3 Allowed PR3 Actual DSO Original

PR4 Proposed

DSO Revised PR4

Proposed

Variance of PR4

revised forecast to

PR3 Allowed

Variance of PR4

revised forecast

to PR3 Actual

53.1 48.3 92.1 60.2 7.1 11.9

Line diversion costs have historically been proportional to capital expenditure in the category of “gross new

demand connections”. For the PR3 period, this allowance was set at a value equivalent to 11.4% of the PR3

forecast capex for new connections.

Despite significant reduction in new connections capex during PR3 period, the rate of expenditure

associated with asset diversions has not reduced to the same levels. The actual diversion costs over 2011 to

2013 are in the range of 19.2% to 21% of the gross connections capex over the same period.

The DSO derived its original PR4 forecast (of €92.1) based on linear regression of actual costs (prime) over

the 2006 to 2013 period. The defined relationship was then applied by the DSO to PR4 new business

forecast gross capex and this resulted in a PR4 capex requirement for diversions equating to 30.2% of gross

new business forecast capex. In its response to our Interim Report, the DSO has confirmed that its original

submission included an erroneous miscalculation and confirmed its agreement that the historical relationship

(or correlation) between new business and line diversion costs is an appropriate basis upon which PR4

forecast and hence allowances should be made.

We have analysed the historical relationship (of gross costs) from 2006 to 2013 and also analysed the DSO

PR4 revised forecast of €60.2m. The results are presented in Figure 5.9 below. This figure presents new

business costs (x axis) against the cost of diversions (y axis) for the years 2006 to 2013 (as shown by the

Historic Data points in blue) and the years 2014 to 2020 (as shown by the forecast data points in red -

representative of the DSO’s revised PR4 forecast).

Page 130: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 125

Figure 5.9 : PR4 Forecast Diversion Costs – Comparison with Historic Performance (€m – 2014 prices)

It is observed that there is a strong historic relationship (R2 of 0.9581) between new business gross costs

and diversion gross costs. However, the DSO PR4 revised forecast is not consistent with this historic

relationship.

We therefore recommend PR4 allowances for diversion works that are consistent with the historic

relationship between new business and diversion gross costs. We have applied this to our

recommended allowances for New Business gross capex.

This results in a PR4 forecast capex for diversions of €50.6m, representing 17.4% of PR4 gross new

business capex. This is €9.6m (16%) lower than the DSO revised forecast of €60.2m and €42.5m

lower than the DSO original forecast of €92.1m.

5.2 Non Load Related Capex

5.2.1 Non Load Related Capex – Overview

The DSO non load-related (NLR) capex for the PR4 period is summarised in Figure 5.10 below and shows a

total PR4 NLR capex of €671m. This is significantly above the expected PR3 outturn capex of €425.4m

(57.7% higher) although only €92.5m (16%) higher than the CER allowed NLR capex during PR3.

y = 0.111x + 3.6446R² = 0.9581

0

5

10

15

20

25

30

35

40

0 50 100 150 200 250 300

Div

ers

ion

s

New Business

Historic Data DSO Revised Forecast Linear (Historic Data)

Page 131: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 126

Figure 5.10 : PR4 DSO Non Load Related Capex compared to PR3 (€m – 2014 prices)

The main drivers for the proposed PR4 works are to:

address safety risks,

ensure compliance with health & safety and environmental obligations, and

to maintain continuity of supply.

Replacement works are driven by the condition and performance of particular asset categories.

The DSO NLR PR4 programme consists of the following projects/programmes:

Completion of major 110kV and 38kV HV Station replacement projects originally planned for completion

in PR3 but subsequently deferred due to the prevailing financial situation at the time;

Continuation of existing HV & MV asset renewal and security programmes to mitigate safety risk to the

public and the DSO workforce;

Continuation of cyclical refurbishment of the 38kV & MV overhead lines, together with a project to

rebuild a number of 110kV double circuit tower lines in the Dublin area;

Commencement of a small number of targeted asset renewal/refurbishment programmes;

NAGZ is a major smart grid investment initiative aimed at addressing impact caused by increasing

levels of renewable generation. The project will look to combine intelligent smart grid networks, high

speed communications and IT, linked with increased cross-border connectivity;

The proposed plans also include for a small number of relatively low cost pilot projects to allow for

assessment of emerging/different technologies before any decision is made regarding roll out of such

technologies on a wider scale. The costs of these are presently incorporated within the DSO’s main

asset renewal programme categories but these could be ring-fenced within the DSO PR4 R&D forecast

expenditure category.

Table 5.22 below details capex for each of the defined asset renewal or refurbishment categories.

579

425

671

0

200

400

600

800

5 Year Total

€m

PR3 Allowed PR3 Actual PR4 Revised Forecast (April 2015)

Page 132: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 127

Table 5.22 : Comparison of PR4 Forecast v PR3: Non Load Related Capex (€m 2014 prices)

PR3

Allowed

PR3

Actual

DSO

Original

PR4

Proposed

DSO

Revised

PR4

Proposed

Variance of PR4

revised forecast to

PR3 Allowed

Variance of PR4

revised forecast to

PR3 Actual

€m % €m %

Renewal Programme -

110kV & 38kV Lines 16.7 15.5 46.5 38.4 21.7 129.7% 22.9 147.6%

Renewal Programme -

110 & 38kV Cables 21.0 6.2 24.5 28.6 7.6 36.2% 22.4 362.4%

Renewal Programme -

HV Substation 120.4 77.1 126.4 126.5 6.2 5.1% 49.4 64.0%

Renewal Programme -

MV Overhead Lines 70.7 61.0 131.9 82.2 11.5 16.3% 21.2 34.8%

Renewal Programme -

MV Cables 2.6 2.0 0.0 0.2 -2.4 -91.9% -1.8 -89.5%

Renewal Programme -

MV Substations 24.7 31.2 23.3 33.2 8.5 34.6% 2.0 6.4%

Renewal Programme -

Urban LV Renewal 64.3 36.2 46.5 46.4 -17.9 -27.8% 10.2 28.3%

Renewal Programme -

Rural LV Network 95.8 84.1 74.8 84.5 -11.3 -11.8% 0.4 0.5%

Storm Rectification

Project 0.0 27.4 27.4 - -27.4 -

Renewal Programme -

LV cables and

associated items

17.2 6.2 16.2 16.4 -0.8 -4.5% 10.2 163.4%

Renewal Programme -

Meters and Time

Switches

0.0 0.0 14.0 14.1 14.1 - 14.1 -

Renewal Programme -

Cut-outs 5.8 4.0 14.3 14.3 8.4 144.7% 10.3 257.6%

Continuity Improvement 22.8 14.0 4.2 4.2 -18.6 -81.4% -9.8 -69.7%

Response capex 101.1 56.5 51.3 61.4 -39.8 -39.3% 4.9 8.7%

System Control 15.4 3.9 16.5 16.5 1.1 7.5% 12.6 319.1%

IVADN (Integrated

Vision for an Active

Distribution Network)

Project

0.0 0.0 7.1 7.2 7.2 7.2 -

NAGZ 0.0 0.0 87.6 87.6 87.6 87.6 -

Other (specify) – relates

to Continuity

Improvement

0.0 0.0 9.3 9.3 9.3 9.3 -

NRP/ Bulk Supply 0.0 0.0 0.0 0.0 0.0 0.0 -

Total Non-Load

Related CAPEX 578.5 425.4 694.4 671.0 92.5 20.0% 245.6 57.7%

The PR4 capex includes a total of €87.6m relating to the NAGZ project, which is subject to European funding

of €31.75m and is described further in Section 5.2.7. Capex relating to the NAGZ is expected to occur

Page 133: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 128

during the early years of PR4 and the annual NLR capex over PR4 is also shown in Figure 5.11. For

comparison purposes, if the €87.6m of capex relating to the NAGZ is excluded from the DSO PR4 total, the

NLR capex reduces to €606.8m for PR4, which is comparable (~5% higher) with CER allowances of €579m

for PR3.

Figure 5.11 : PR4 Non-Load Related Capex – Annual Investment including NAGZ (€m – 2014 prices)

As part of our assessment of the DSO NLR capex, we have undertaken a modelling exercise as a top-down

assessment of asset replacement requirements. This assessment methodology based on the Survivor model

– which uses a Poisson distribution for replacement of asset types, based on a mean asset life.

Replacement profiles are essentially distribution profiles that allow for assets to be replaced around the

assumed technical life (using standard deviations) and not on the exact assumed technical life. Standard

deviations define the percentage of assets that will be replaced within an age range, based around the

assumed asset life. For example, 68% of all assets will be replaced within 1 standard deviation of the

assumed asset life, whilst 95% of all assets will be replaced within 2 standard deviations of the assumed

asset life.

Historically it has been typical to assign normal distribution profiles to asset types. This process requires

assumptions relating to both a technical life of an asset and an assessment of its standard deviation (in

years). In recent years, some regulators (including Ofgem in the UK) have moved towards using Poisson

distributions in their price control assessments. The benefit of utilising Poisson distribution profiles is that the

standard deviation is inherently assumed within the distribution profile and therefore an estimate of an assets

standard deviation is not required.

Using the DSO age profile data for the main asset categories, the model output results in a replacement

profile (and hence volumes of replacement during PR4) for each asset class that is derived based on age

profile, assumed asset life and a Poisson distribution of replacement. In the modelling exercise we have

used the technical asset lives as proposed in Appendix D together with DSO age profile data.

Our modelling indicated that in general the PR4 renewal volumes proposed by DSO were less than

modelling indicated, suggesting longer asset lives being used by the DSO with an implied higher risk being

adopted. We concluded that the proposed DSO asset replacement volumes in PR4 are therefore not

unreasonable.

The model is not appropriate for a wide range of activities – such as security driven programmes, flood

mitigation, cyclical overhead refurbishment programme – this latter point was recognised by Ofgem in the

previous DPCR5 for certain DNO’s and the asset category was removed from Ofgem’s modelling

assessment.

We also carried out a bottom-up analysis of each of the sub-programmes of work that are included within

each of the main asset renewal programmes. This allowed us to assess DSO forecasts at a much greater

118.0 116.5 115.5 116.7 116.7

29.6 28.9 29.10.0 0.0

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

160.0

2016 2017 2018 2019 2020

Total Non-Load Related CAPEX - Excluding NAGZ NAGZ

Page 134: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 129

level of detail than the top-down modelling methodology briefly described above. The results of the bottom-

up assessment are presented in the following sub-sections.

5.2.2 Renewal Programmes

The DSO has structured its asset renewal programmes into a series of defined categories of work to address

assets at a specific location or to address a particular set of assets across the DSO network as part of a

broader work programme. Many of the proposed works during PR4 fall into one of the following categories:

Progressing works that were originally planned for PR3 but deferred in full until PR4 due to financial

constraints prevailing at the time.

Continuation of work programmes previously established and progressed during PR3.

Commencement of new programmes of work to address identified risks with a specific type of asset.

The DSO has provided a detailed narrative document69 that provides significant detail of the proposed asset

renewal plans for PR4. The document is divided into 10 separate chapters, with each chapter focusing on a

specific asset class. Within each chapter, the document describes the various network risks for sub-

components within the broad asset class that need to be addressed during PR4. Details are provided of the

proposed PR4 volumes of work and the proposed PR4 capex at this sub-programme level. The document

gives good visibility of the DSO asset management plans during PR4.

In general, we consider the justification for the various PR4 works proposed by the DSO is proven and in

many cases, we agree with the proposed volumes of work. However, our review has identified a number of

significant increases in the DSO PR4 planned costs, compared to PR3 planned costs (for deferred works) or

PR3 expected outturn costs (for works progressed during PR3). We have therefore proposed adjustments to

the proposed DSO PR4 capex to account for such differences where the DSO has been unable to provide

further justification supporting such increases in planned costs for its major projects and its planned unit

costs for its asset renewal work programmes.

The following sub-sections provide a summary of our review for each of the DSO asset renewal

programmes.

69 Document DF03 – Asset Replacement and Maintenance Final.pdf

Page 135: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 130

5.2.2.1 110kV & 38kV Lines

DSO proposed PR4 capex is €38.4m70, CER PR3 allowed capex of €16.7m, DSO current forecast for PR3 is €15.5m.

The proposed PR4 works associated with 110kV and 38kV lines are summarised in Table 5.23 below.

Table 5.23 : Summary of PR4 capex relating to 110kV and 38kV Lines (€m – 2014 prices, unless stated otherwise)

HV Overhead

Lines – Sub

Category

Background

DSO PR4 Forecast PR4 Recommended Variance to

DSO PR4

Capex (€m)

PR4

Revised

Capex (€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit

Cost (€)

PR4 Capex

(€m)

38kV Overhead

Cyclical

Refurbishment

Continuation of approved PR3 programme to inspect 5/9ths of the 38kV

overhead network excluding parts of the network under 15 yrs old and

refurbish those assets which fall outside ESBN’s condition standard for that

asset. Expected to extend life of assets and maintain fault rate while reducing

risk to public and staff safety.

9 year OCR programme started in PR3.

20.0 3,169 6,313 PR3 Outturn 6,300 20.0 -0.0

Refurbishment

of 110kV double

circuits in Dublin

Major refurbishment/rebuild is proposed for four 110kV circuits within the

greater Dublin area. Originally planned for refurbishment due to age (50yrs +)

and location of these lines (dense residential, industrial areas and near major

roads) and results of conductor sampling showing significant signs of

deterioration.

Programme deferred from PR3.

17.7 15 Scheme

Cost

Lowest Cost

Technically

Acceptable

Scheme

6.8 --10.9

Refurbishment

of 110kV circuits

outside of Dublin

Painting and sheer block repairs are to take place for up to 33km in addition to

reinforcement work to uprate the capacity of the line in order to return these

circuits to a minimum standard considered necessary to prevent hazards from

the public and environmental issues such as corrosion.

Programme deferred from PR3.

0.7 33 21,212 DSO PR4

proposed 21,212 0.7 -

TOTAL 38.4 27.5 -10.9

70 Revised March 2015

Page 136: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 131

In relation to the 38kV Overhead Cyclical Refurbishment Programme, the DSO revised forecast for PR4 is based on a unit cost which is consistent with

outturn cost in PR3. We recommend allowances for PR4 that are consistent with the PR3 outturn unit costs.

In relation to the re-conductoring of 110kV double circuit tower lines in the Dublin area, it is our understanding that there has not yet been any detailed

line survey and analysis to inform the assessment of the potential costs and that the DSO has not yet fully developed its proposed investment case. The

DSO PR4 forecast is therefore based on a middle-ground cost scenario. However, taking a low cost based on a line refurbishment using existing towers,

and a high cost based on fully undergrounding and stating that a half way position is part underground, part tower replacement and part fittings

replacement does not constitute a planned investment. We would however agree that the requirement to carry out the lowest cost practical solution at

this time seems reasonable and therefore would recommend this cost of €6.8m. We do recognise the risk associated with this cost uncertainty and

therefore once the DSO has developed its planned investment for these circuits, this should be reviewed to assess the efficiency of their proposed

investment during PR4..

The proposed changes result in PR4 recommended capex of €27.5m for 110kV and 38kV lines (with capex reduced by €10.9m).

Page 137: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 132

5.2.2.2 110kV & 38kV Cables

DSO revised proposed PR4 capex is €28.6m71, CER PR3 allowed capex of €21.0m, DSO current forecast for PR3 is €6.2m.

The proposed PR4 works associated with 110kV and 38kV cables are summarised in Table 5.24 below.

Table 5.24 : Summary of PR4 capex relating to 110kV and 38kV Cables (€m – 2014 prices, unless stated otherwise)

HV Cables –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Revised

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit

Cost (€)

PR4

Capex

(€m)

Replacement of

Pfisterer 110kV

Terminations

Three failures in PR3 to date which have come prematurely on terminations installed pre 2009.

Based on survey results, it is required to replace all pre-2009 manufactured terminations on the

system.

0.8 22 36,364 DSO PR4

proposed 36,364 0.8 -

Replace 110kV

and 38kV Indoor

Fluid-filled

Terminations

Replacement of 4 sets of 38kV and 1 set of 110kV due to potential fatality risk arising from

explosions, potential leakage and in prior cases of explosions.

Programme deferred from PR3.

Work involves installing short length of XLPE cable, transition joint between XLPE cable and oil

filled cable and new dry terminations for XLPE cable.

0.8 5 160,000 DSO PR4

proposed 160,000 2.0

0.0

Replacement of

Pre 1940s 38kV

Paper Cables

16.7km of paper cables will be 77 yrs of age by 2015. Due to high fault rates on paper cables (30-

49 times higher) than modern XLPE cables and the high number of customers that depend upon

them. Capacity of new cable will increase from 20MVA to 40MVA and improve operational

flexibility.

Significant works already completed prior to PR4 - 65% of route already trenched, 12km of cable

already procured.

Programme deferred from PR3.

7.6 16.7 455,090 DSO PR4

proposed 455,090 7.6 -

Replacement of

110kV Pipe

Type Gas

Expected rapid deterioration in the upcoming years on two cables. Costly pumping exercises will

also be reduced and the risk of supply interruptions also. Also believed that losses will reduce with

new XPLE cables.

4.1 8.9 460,674 DSO PR4

proposed 460,674 4.1 -

71 Table 6.3 (April 2015 version) states €28.6m – however it is noted that the DSO response to our Interim Report stated total capex of €28.0m

Page 138: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 133

HV Cables –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Revised

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit

Cost (€)

PR4

Capex

(€m)

Compression

Cables –

It is proposed to retrofit the Milltown circuits only with City Cable – a 3 core XLPE type cable used

to replace cables in piped installations, particularly in urban areas. This means effectively removing

the old cable from within the pipe, and reinserting a new compact XLPE insulated 110kV cable. As

the new cables are pulled through the existing pipework, excavation will be restricted to the

existing joint positions. This results in less costly and disruptive works.

Programme deferred from PR3.

Replacement of

Inchicore to

Francis St.

110kV Fluid-

Filled Cable.

along Grand

Canal route

Replacement of a leaky circuit with high leak rates in an area close to the city canal and nearby

congested areas.

Programme deferred from PR3.

5.5 5.7 964,912 DSO PR4

proposed 964,912 5.5 -

Replacement of

further 5% of

population of

38kV fluid-filled

cables.

Replacement of leakiest circuits to reduce the leakage rate with the same as above justifications

and the inclusion of cable faults reducing with replacement. 3 6 500,000

DSO PR4

proposed 500,000 3.0 -

Tag 110kV/38kV

fluid-filled cables

with PFT tracer

Gas Pump PFT

gas impregnated

oil into 50

circuits

Condition assessment based work will be carried out to replace existing insulating cable fluid with

PFT tagged cable fluid. This is due to ESB networks comparing unfavourably to other utilities with

regards to cable leakage and to the environment agency standards. The PFT gear will also reduce

repair and planned outage times as well as reducing costs.

6.2

65km of

3c cable;

15km of

single core

cable

38.2k (3-

core)

95.7k (3 x

single core)

Applied

Reduction to

PR4 unit costs

4.0 -2.2

TOTAL 28.0 25.8 - 2.2

Page 139: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 134

DSO Revised Table 6.3 Forecast of €28.6m relating to HV Cable Replacements, although summation of the capex associated with the individual sub-programmes

is €28.0m (which is also stated by DSO in its narrative response to the Jacobs Forecast Capex Interim Report).

With the adjustments proposed above, our recommended PR4 capex allowances for 110kV and 38kV cable asset renewal works is €25.8m – a reduction of €2.2m.

In its response to our Interim Report, the DSO were seeking to increase the cost for the PFT tagging programme from €2.2m to €6.2m. This technique will provide improved

monitoring of the cables, however the estimated costs seem high with the relative difference between 3 core and single core containing the same oil volume per metre, which

is the major determining factor for the time taken to tag the cables. We would therefore expect costs to be around €4m, which is greater than the DSO initial forecast (of

November 2014) but below its revised forecast (March 2015).

Page 140: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 135

5.2.2.3 HV Substation

DSO revised proposed PR4 capex is €126.5m72, CER PR3 allowed capex of €120.4m, DSO current forecast for PR3 is €77.1m.

The proposed PR4 works associated with HV Stations (110kV and 38kV) are summarised in Table 5.25 below.

Table 5.25 : Summary of PR4 capex relating to HV Stations (€m – 2014 prices, unless stated otherwise)

HV Stations –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Reyrolle Class

'C'

Replacements

There are four switchboards remaining in Dublin city centre stations, namely East Wall Road,

Glasnevin, Granby Row and Marrowbone Lane totalling 39 cubicles.

Short circuit rating of this type of switchgear is well below IEC standard levels and as a result

increased rate of risk with severe consequences. As a result of risk assessments, replacement of

the 4 remaining class c assets are to be replaced for MV GIS and protection.

Work deferred from PR3 - previously allowed by CER - now planned for completion in PR4 by the

DSO.

8.5 4 2,100,000

Adjustment to

DSO PR4

submitted

costs

1,610,000 6.4 -2.1

ASEA NRB 38kV

Disconnect

Replacements

These switches are triple pole, pedestal mounted, outdoor disconnects and were installed from the

1960s. They are rated for 52kV and are used on the 38kV system in 110kV substations. They are

manually operated at ground level by rotating a lever through 180 degrees.

The total population of 67 disconnects are installed in 11 110kV stations and have been in service

for 51 years. Of this population, individual testing completed in 2013 / 2014 revealed 16 units to

require immediate remedial work due to indication of immediate mechanical failure.

0.5 30 16,667 DSO PR4

proposed 16,667 0.5 -

10kV FPE LBFM

Switch

Replacements

(Kyle Cooper)

Load break fault make (LBFM) switches manufactured by Kyle Cooper are used in the DSO

faulted phase earthing (FPE) cubicles to earth faulted phases.

There are approximately 1000 units in total on the system at present, in FPE cubicles, on 20 kV

transformer neutrals and in interface sites close to feeding stations. The FPE system is the earth

fault treatment for 10kV isolated neutral networks across the country; therefore its reliability is

extremely important for staff and public safety. The Kyle Cooper LBFM switches mechanism

1 100 10,000 DSO PR4

proposed 10,000 1.0 -

72 As per updated Table 6.3

Page 141: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 136

HV Stations –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

boxes are prone to water ingress which leads to failure of the unit. Approximately 681 of these

switches are installed in outdoor FPE cubicles. These failures are attributed to a design flaw which

applies to all units and is not limited to a particular batch or age range. The sealing of the

mechanism box is sub standard leading to water ingress.

DSO proposes to replace 100 switches with a modern circuit breaker.

110kV Sprecher

and Schuh circuit

breaker

replacement (oil

filled CBs with

spring close

mechanism)

These circuit breakers were installed in the 1970’s. Transmission System experienced similar

problems and have replacement programme in place over previous 15 years.5 failures on

transmission system and 1 failure on Distribution system where broken drive insulators were

identified. There are also issues with the cement joints on most units. DSO also cites international

experience is similar, justifying replacement programme. Elsewhere, porcelain insulators of the

Sprecher & Schuh switchgear were found to fail at 30+ years in service.

For PR4, the DSO proposes to replace all 25 units, due to failure rate at 30+ yrs age of asset and

the risk of failure. The proposed approach is consistent with transmission system practices.

1.6 25 64,000 DSO PR4

proposed 64,000 1.6 -

Balteau CT

Replacement

Oil filled Balteau current transformers (CTs) are installed at 38 kV and 110 kV - 20 units at 110kV

and further units at 38kV. These CTs were installed at 110kV between 1953 and 1980, and at

38kV between 1970 and 1981. Recently they have been found to contain high levels of moisture.

This is attributed to a design flaw – the rubber bellows degrade and lose their seal, allowing

moisture into the oil, eventually leading to internal flashover.

In late 2009, such moisture ingress leads to a catastrophic failure in Hollyhill 38 kV station. Testing

of units on the transmission system have confirmed that a high occurrence of this issue. Similar

testing on the distribution system is ongoing.

DS proposes replacement of 20 110kV units and 175 38kV units within PR4.

3.6 195 18,462 DSO PR4

proposed 18,462 3.6 -

Earth fault

protection

PR3 programme established to upgrade existing protection systems. Priority 1 works focusing on

primary earth fault protection was progressed during PR3. The priority 2 works originally planned

for PR3 related to slow or unreliable fault protection although these works were largely deferred.

For PR4, the DSO has proposed a reduction in scope of work from PR3 as it only focuses on

areas where there is an absence of earth fault protection. 739 units have been identified from

implementation to address absence of adequate earth fault protection. This will increase safety to

public/staff, reduce operational costs and allow accurate fault location data to be provided quicker.

15.9 739 + 7

ASC 21,516

PR3 expected

outturn costs

17,811

(Relays) 15.9 0.0

Page 142: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 137

HV Stations –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

In addition the DSO proposes the installation of 7 x MV Arc Suppression Coils (ASC) at various

locations in order to improve the earth fault protection on its rural 10kV network

38kV & 10kV

Switchgear

replacement

Continuation of programme allowed for during PR3 to replace outdoor 38kV and 10kv CBs. ESB

have identified a population of ‘at-risk’ 10kV and 38kV Circuit breakers require replacement due to

performance issues, including that of insufficient short circuit rating.

PR 3 allowed 180 units to be replaced although only 72 are forecast for replacement by 2015. The

DSO is targeting a further 100 units for replacement during PR4.

8.6 100 86,000 PR3 expected

outturn costs 51,921 5.2 - 3.4

Replacement of

Doulton Insulator

Busbar Supports

During PR3 a programme of replacements was allowed, which is completed based on the

discovery of these supports in HV stations when other activities are being carried out. Works were

largely deferred in PR3.

DSO proposes that this programme be completed in PR4 so that the risks associated with these

supports are removed completely.

0.6 30 20,000

DSO proposed

PR4 unit costs

-

20,000 0.6 -

Siemens

Stations

Replacements

Replacement works at 3 - 85 year old stations, which present fire, continuity and safety risks.

Work deferred from PR3 - previously allowed by CER - now planned for completion in PR4 - works

at Newtown St Alban and Mount Misery. Lake Station being retired completely with load

transferred to Dunmanway 110kV station.

These are the last remaining Siemens stations on the DSO network. .

9.9 3 3,300,000 DSO PR4

proposed 3,300,000 9.9 -

Convoy Wood

Pole station

replacement

Replacement originally scheduled for replacement during PR3 and Capex allowed by CER - now

planned for PR4. 5 1 5,000,000

DSO PR4

proposed 5,000,000 5.0 -

Pembroke 10kV

Sw'gear

replacement

The replacement of the compressed air operated switchgear was originally scheduled for PR3 and

Capex allowed by CER - now planned for PR4. 3.9 1 3,900,000

Increased PR3

costs 3,600,000 3.6 - 0.3

Bedford Row -

38kV and 10kV

Sw'gear

replacement

The station is now over 80 years old and the switchgear is based on long outdated technology.

The replacement of the switchgear was originally scheduled for PR3 and Capex allowed by CER -

now planned for PR4.

7.0 1 7,000,000 DSO PR4

proposed 7,000,000 7.0 -

Page 143: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 138

HV Stations –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Kilbarry - 38kV

Sw'gear

replacement

During PR3, it was proposed to replace the existing 38kV switchgear and associated control and

protection with a GIS module with integrated protection and modern substation control system.

Originally scheduled for replacement during PR3 and Capex allowed by CER - now planned for

PR4.

4.4 1 4,400,000 Increase to

PR3 costs 3,500,000 3.5 -0.9

Ardnacrusha -

38kV Sw'gear

replacement

During PR3, it was proposed to replace the existing 38kV switchgear and associated control and

protection with a GIS module with integrated protection and modern substation control system.

Replacement originally scheduled for replacement during PR3 and Capex allowed by CER - now

planned for PR4.

6.1 1 6,100,000 Increase to

PR3 costs 5,500,000 5.5 -0.6

Remedial

measures to

mitigate GPR

The earth grids of many older 38kV stations have deteriorated over their lifetime.

During PR3 a programme of remedial works was initiated, under which one or more of a range of

measures identified are put in place to mitigate risks associated with a rise in ground potential.

The DSO propose to continue this programme in PR4, to ensure the safety of staff, and to prevent

damage to plant in the station compound or neighbouring third party premises.

2.8 205 13,700

DSO proposed

PR4 unit costs

-

13,700 2.8 -

Flood Defence in

vulnerable

locations

This programme is proposed by DSO to mitigate risk of flooding to its HV stations. The proposed

works will involve the introduction of possible station relocations, low walls and sealing cables to

prevent water damage. This is due to previous history of flooding and the environmental, safety

and continuity risks presented by flooding.

0.6 1 600,000

DSO proposed

PR4 unit costs

-

600,000 0.6 -

Air quality

monitoring

Partial discharge was found in 55% of 40 stations tested and 5% had unacceptable ozone levels.

It is proposed that air quality and partial discharge survey of all 150 indoor type stations be

completed to establish the quality of the air.

The DSO PR4 capex plan is for ozone detectors to be installed in 100 HV station locations to

assist in the future detection of ozone gas in stations or within cable boxes.

1.1 100 11,000

Applied

Reduction to

DSO PR4 unit

costs

7,700 0.8 -0.3

Storage facility

for used and oil

filled HV

equipment

Storage of usable spares and second hand equipment needs to be stored in a secure and

independent location which ensures no further damage of deterioration which may harm the

possible return to service of the equipment.

DSO has not yet finalised plans of either new site or extension to existing property is most

effective option - process still ongoing to assess options.

0.5 1 500,000

DSO proposed

PR4 unit costs

-

500,000 0.5 -

Page 144: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 139

HV Stations –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Bunding of

Transformers

near waterways

A large quantity of legacy transformers remain unbunded, this was addressed partly in PR3 when

a programme of installing bunding retrospectively was undertake in order to reduce the risk of

damaging the Environment.

It is proposed to continue with this programme in PR4 with a combination of either new retrofit

bunding of 38kV transformers (86) or upgrading of existing binding (150 locations).

4.2 236 17,797

DSO proposed

PR4 unit costs

-

17,797 4.2 -

Upgrade of

existing battery

systems

Programme of battery replacements at DSO stations was progressed in PR3. It is proposed to

continue this programme in PR4 with work focused on 24V systems at 250 locations where the Ni

Cad batteries and associated systems installed in period 1990 - 1993 have significantly

deteriorated to 45% of their design capacity and require replacement due to the dependency of

SCADA and protection on these assets.

Battery upgrades are also proposed for 50 major 110kV and 220kV stations.

4.8 300 16,000

DSO proposed

PR4 unit costs

-

16,000 4.8 -

Replacement of

110/38kV

Transformers

Replacement of 3 transformers that were installed between 1950 and 1960. Transformers of same

installation period have been associated with tap-changer and transformer faults.

Dungarvan T141, Manufacturer ACEC, 1953

Drumline T142, Manufacturer - METRO VICKERS, 1950

Thornsberry T142, Manufacturer – ACEC, 1965

5.5 3 1,833,333

DSO proposed

PR4 unit costs

-

1,833,333 5.5 -

Transformer Oil

Regeneration

Oil regeneration of 30 transformers during PR4, to extend the life of transformers that have acidity

approaching 0.1mg KOH/g to defer replacement work costs and fault/repair costs. 3.6 40 90,000

DSO proposed

PR4 unit costs 90,000 3.6 -

Roof repairs Replacement/refurbishment of 30 substation roofs based on station specific needs. Driven by poor

condition leading to increased moisture levels that can cause discharge of components. 1.4 30 46,667

Applied

reduction to

DSO proposed

PR4 unit costs

35,897 1.1 -0.3

Condition

Monitoring

Transformer condition monitoring plant has been used on DSO and TSO transformers since early

1990s, There are currently 3 units installed in -Mc Dermot, Crane and Dunmanway stations. DSO

proposes installation of 15 units on transformers that are at most risk of failure to allow constant

monitoring and early detection, which will allow corrective measures to be implemented.

0.7 15 33,333

Applied

reduction to

DSO proposed

PR4 unit costs

46,667 0.7 -

Page 145: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 140

HV Stations –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Station fence

upgrades

Increase in metal prices has been linked to a steady increase in the theft and break ins to HV

stations. DSO has progressed a programme during PR3 to replace chain-link fences with Palisade

fencing.

During PR4, the DSO proposes to upgrade 70 station fences to palisade (20 x 110kv; 50 x 38kV)

and 10 power fence installations based on prior history of break ins and existing condition of

fences.

10.3 70 147,143 Expected PR3

outturn costs

190,000

Power

Fence

115,000

Upgrade

10.0 - 0.4

Station

monitoring

The DSO proposes to improve station security at a number of its HV stations due to the cost

effective advantage over on-site guards to deter theft and allow possible action to be taken swiftly.

An installation comprising of a combination of either intruder alarms or CCTV system is proposed

by the DSO

9.2

High risk –

200 Fixed

CCTV

Medium

risk – 20

270

Intruder

alarms

198,000

(H)

121,000

(M)

13,000 (L)

DSO proposed

PR4 unit costs 9.2 -

Station

emergency

lighting

Programme deferred from PR3.

Installation in 544 HV stations (394 at 38kV; and 150 at 110kV) due to the need to compile with

regulations and many stations have out of date lighting.

2.9 544 5,331

Applied

reduction to

DSO proposed

PR4 unit costs

4,101 2.2 - 0.7

Door and lock

replacements

Continuation of programme associated with the replacement of wooden doors with high security,

multi point locking steel doors is proposed with the replacement of 200 deteriorating doors that

are proving a security risk to stations.

DSO also proposes a pilot scheme of locks with programmable keys - the introduction of 150 locks

that are programmable to personnel/time to deter future theft.

1.7 350 4,857 DSO proposed

PR4 unit costs 4,857 1.7 -

TOTAL 125.973 116.9 -9.0

73 Table 6.3 states €126.5m PR4 capex relating to HV Station Asset Renewal Programme

Page 146: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 141

In its response to our Interim Report, the DSO provided further details relating to a number of the sub work programmes, these details have been considered when

determining recommended allowances and resulted in increased capex compared to our Interim Report.

For a number of the sub-programmes associated with HV Station Asset Renewals, we have applied a reduction to the proposed unit costs that the DSO has

used in its PR4 forecast.

We have allowed the DSO’s proposed capex for flood mitigation, however the DSO has not provided a robust case that this is sufficient to provide

appropriate continuity.

These result in a recommended PR4 capex of €116.9m, a reduction of €9.0m compared to the detailed DSO forecast of €125.9m.

Page 147: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 142

5.2.2.4 MV Overhead Lines

DSO (revised) proposed PR4 capex is €82.2m, CER PR3 allowed capex of €70.7m, DSO current forecast for PR3 is €61.0m.

The proposed PR4 works associated with MV Overhead Lines are summarised in Table 5.26 below.

Table 5.26 : Summary of PR4 capex relating to MV Overhead Lines (€m – 2014 prices, unless stated otherwise)

MV Overhead

Lines – Sub

Category

Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

Revised

PR4

Capex

(€m)

PR4

Revised

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

MV Overhead

Cyclical

Refurbishment

(OCR)

For PR4, DSO proposes to extend the 9 year MV overhead refurbishment programme (established

in PR3) to a12 year cycle. This decision is based on DSO risk assessment and decision informed

by relatively low volume of major defects encountered per km of line and the scope and standards

of OCR programme remain unchanged.

76.5 34,500 2,217 PR3 outturn

costs 2,100 72.5 -4.1

S and C spring

assisted fuse

tubes to

increase

reliability

An overhead fuse consists of a fuse base, a fuse tube and a replaceable fuse element. There are

100,000 fuse locations on the overhead networks There have been a number of mal-operations

encountered by the DSO with fuse tubes not dropping out, when the fuse blows Manufacturers

have developed fuse tubes, which incorporate an additional spring, to assist the fuse tube to open

when the fuse blows. It is proposed that this solution be applied for 1,000 fuses. This will reduce

safety risk and also help reduce the risk of fault hunting (extended outages).

0.3 1000 300 DSO proposed

PR4 unit costs 300 0.3 0.0

Triple pole

Switch TPS

replacement

The population of approx. 3,500 triple pole switches have been installed on the 20kV system since

the early 1990s. They are a means of ensuring triple pole switching at 20kV, as the previous

practice of single pole switching on overhead networks via single fuse cut-outs results in mal-

tripping of 20kV protective devices under a sensitive earth fault condition. DSO has experienced a

number of instances of deterioration of these switches, especially in coastal areas. The nature of

the problem is significant. Deterioration of the metal fixings and cement at the base of the 9 post

insulators on the assembly may result in metal/rust expansion that cracks the ceramic insulator.

When the device is being operated the cracked insulator fails and shatters. Operator is exposed to

the risk of falling ceramic shards and the electrical risk of a failed switch.

On inspection of the failed switches, investigations confirmed that the cement used to secure the

pins into the insulators was absorbing salts from the atmosphere and holding the salt in contact

with the pin, which was attacking the galvanised coating and subsequently the cast iron of the pin

0.6 100 6,000 DSO proposed

PR4 unit costs 6,000 0.6 0.0

Page 148: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 143

MV Overhead

Lines – Sub

Category

Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

Revised

PR4

Capex

(€m)

PR4

Revised

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

itself.

Ongoing condition surveys are in place (2014) to determine scale of replacements required and

pending full survey results, the DSO has proposed replacement of 100 units during PR4.

MV Conductor

assessment and

replacement

Replacement of 100km of ACSR conductor on circuits that were constructed pre 1960 based on

condition assessments. Results of torsion tests from where line drops occur on aluminium strands

showed failure significantly below minimum acceptable level

3.1 100 31,000 DSO proposed

PR4 unit costs 31,000 3.1 0.0

Storm

Resilience

programme

Introduction of a pilot programme through targeted cutting of trees, use of covered conductor, line

diversions and potential undergrounding of network is proposed. 0.7 100 7,000

DSO proposed

PR4 unit costs 7,000 0.7 0.0

Creosote poles

alternative pilot

Pilot study of using alternative pole technologies such as: concrete, wood, galvanised steel, glass

reinforced fibre and alternative products to the wooden stay block. This will comply with the law of

phasing out creosote poles

1 1 1,000,000 DSO proposed

PR4 unit costs 1,000,000 1.0 0.0

TOTAL 82.2 78.1 -4.1

The DSO is proposing to inspect and refurbish where required, 34,500km of MV OHL as part of a 12 year cyclical refurbishment programme at a unit cost of more

than €2,200 per km. During PR3 period 2011 to 2014, the DSO has completed the refurbishment of approximately 18,400km at an expected unit cost of €2,100.

For PR4, the DSO is forecasting the unit cost will increase to €2,217 per km, representing an increase of more than 5%.We recommend allowances for PR4 based

on unit costs achieved during PR3 (2011 to 2014).

This reduction results in a recommended PR4 capex of €78.1m, a reduction of €4.1m compared to the DSO revised forecast of €82.2m.

In the DSO response to our Interim Report, the DSO also asserts the existence of a “principle” that PR3 outturn costs be recommended for PR4 unit costs.

Jacobs has not simply accepted the DSO’s PR3 outturn costs as being efficient and therefore acceptable for PR4. The PR3 capex has been subject to detailed

assessment and review to inform our opinion on appropriate allowances for PR4 – covering all of the DSO capex activities.

Page 149: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 144

5.2.2.5 MV Cables

The DSO proposes a zero capex associated with the renewal of MV cables as no planned capital activities are proposed for MV cable assets. PR3 allowed capex

was €2.6m, with PR3 expected outturn of €2.0m.

Page 150: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 145

5.2.2.6 MV Substations

DSO revised proposed PR4 capex is €33.2m, CER PR3 allowed capex of €24.7m, DSO current forecast for PR3 is €31.2m.

The proposed PR4 works associated with MV Stations are summarised in Table 5.27 below.

Table 5.27 : Summary of PR4 capex relating to MV Stations (€m – 2014 prices, unless stated otherwise)

MV Stations –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

Revised

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Replacement of

Indoor Oil-Filled

MV RMUs

No installation of these assets has been carried out in over 30 years and is now proving difficult to

source spare parts. After a number of explosive failures of RMUs at outdoor installations, the

necessity of replacements has been highlighted. It is proposed to remove all 130 units during PR4

Programme commenced in PR3 and proposed for completion in PR4

5.2

130

22,128

PR3 outturn

costs 21,840 2.8

0.0 Replacement of

Open-Cubicle

Switchgear in

Indoor MV

Substations

Proposed to remove the remaining 105 units during PR4. These units exhibit explosive failures and

other potentially dangerous failures. This will also reduce maintenance cost in future due to the

nature of the new equipment. Through the replacement this also allows the future conversion of the

10kV network to 20kV.

PR3 programme was to replace remaining units – although this was not completed. It is now

proposed to be completed during PR4

105 PR3 outturn

costs 24,200 2.5

Replacement of

MV/LV

Transformers in

Association with

Switchgear

Replacement

Planned to replace 43 units during PR4, through a continuation of the PR3 programme that was

approved. These units are no longer deemed safe or functional. In addition to this it is also

expected that the new low losses type transformers that will be put in their place will help reduce

losses overall

The PR4 replacement programme is a continuation of the PR3 programme

0.6 40 15,000

DSO

proposed PR4

unit costs

15,000 0.6 0.0

Replacement of

Magnefix Cast-

Resin Type

Switchgear

There are approximately 2200 Magnefix switches on the ESB system in 2014

In less than 18 months, there have been 16 Magnefix failures which resulted in fires leading to

units being burnt severely in many cases. After undertaking a survey of 200+ units it was found

that 55 units required urgent overhauls, while 40 units required immediate replacement.

20.5 400 51,250

Applied

Reduction to

DSO PR4 unit

costs

47,040 18.8 -1.7

Page 151: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 146

MV Stations –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

Revised

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

It is proposed to remove 400 units in PR4 which is an increase compared to the PR3 planned

volumes

PR4 replacement is part of 15-20 year programme to completely remove the asset population from

ESB network expectation

Replace RGB

Cast-Resin type

Switchgear

RGB switchgear has been subject to a programme of removal throughout PR3 such that only a

very small residual population is expected to remain at the beginning of 2016 – in the region of 60

units in total.

It is propose that the programme of removal from PR3 will be continued until they have been

completely removed from the system by the end of PR4.

1.1 60 18,333

DSO

proposed PR4

unit costs

18,333 1.1 0.0

Replace URD

Transformers

Over PR2 and PR3, many URD transformers have been removed and replaced with modern

ground mounted installations.

By the beginning of 2016 it is expected that only 34 units will remain. The PR4 replacement

programme plans to complete the removal of these URD transformers. This will reduce the risk of

failure as well as reducing the cost of maintenance as the need for annual inspections is removed.

1.9 34 55,882

Applied

reduction to

DSO

proposed PR4

unit costs

50,802 1.7 -0.2

Replace URD

LV Vaults

A survey of 40 units in the Tallaght area has shown that 25-30% of units required immediate

replacements for safety purposes.

DSO plans to replace 250 of these vaults and overhaul of a further 4,000 within PR4

1.3 250 5,200

DSO

proposed PR4

unit costs

5,200 1.3 0.0

Replace

Substation

Doors

Entirely based on the condition of the existing door, it is estimated that 200 wooden doors will

require replacement during PR4. These new steel doors will increase the safety to public as holes

in doors and unauthorised access will be eliminated and reduce the regular maintenance costs that

wooden doors require

Continuation of programme commenced during PR3

1.4 200 7,000

Applied

reduction to

DSO

proposed PR4

unit costs

5,385 1.1 -0.3

Shrouding of LV

Panels

Proposed addition of shrouding to 200 LV indoor and unit substation panels. Condition and

performance of unshrouded LV panels is acceptable and electrical faults are uncommon, however

a serious safety risk in relation to exposed live conductors present where unshrouded panels are

common

0.3 100 3,000

DSO

proposed PR4

unit costs

3,000 0.3 0.0

Page 152: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 147

MV Stations –

Sub Category Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

Revised

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Continuation of programme commenced during PR3

Station Civil

Upgrade works

Areas where substations are installed can become subject to illegal dumping which affects the

ventilation. Proposed steel caging or landscaping of a substation proves effective and is to be used

to upgrade 200 substations, however this will be site specific. This will reduce the risk of substation

failure and the clean-up cost of dumping is reduced which is a legal necessity for ESBN

1.0 200 5,000

Applied

reduction to

DSO

proposed PR4

unit costs

3,846 0.8 -0.2

TOTAL 33.2 31.1 -2.1

In its response to our Interim Report, the DSO has identified additional capex relating to the replacement of Magenfix Substations rather than Magnefix kiosks. We

have made an appropriate allowance for this.

For a number of the sub-programmes associated with MV Station Asset Renewals, we have applied a reduction to the proposed unit costs that the DSO has used in

its PR4 forecast.

These result in a recommended PR4 capex of €31.1m, a reduction of €2.1m compared to the DSO revised forecast of €33.2m.

Page 153: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 148

5.2.2.7 Urban LV Renewal

DSO revised proposed PR4 capex is €46.4m, CER PR3 allowed capex of €64.3m, DSO current forecast for PR3 is €36.2m.

The proposed PR4 works associated with Urban LV Overhead Line Renewal is summarised in Table 5.28 below.

Table 5.28 : Summary of PR4 capex relating to Urban LV Overhead Line Renewal (€m – 2014 prices, unless stated otherwise)

LV Urban

Renewal

Category

Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Revised

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

LV Network

Renewal

The LV Urban overhead line programme addresses the refurbishment of bare LV network in urban

centres.

This programme is a continuation of a PR3 programme.

It is proposed that 14,000 spans of pre-1950 LV urban network be addressed in PR4. This

refurbishment work is essential to maintaining the safety and operability of these networks.

42.1 17,500 60,14374 PR3 outturn

costs 51,652 36.2 -5.9

Public lighting

Interface

Separation

Works

The DSO identified requirement for this work in its March 2015 response to our Interim Report. The

DSO states this sub programme is an immediate requirement to ensure the safety of the public

interface. No other details have been provided

4.3 €400,000 per

year 2.0 -2.3

TOTAL 46.4 38.2 -8.2

In its response to our Interim Report, the DSO clarified it is proposing to refurbish 17,500 spans of Urban LV overhead network (dating pre-1950) at a unit cost of

more than €60,000 per km.

During PR3, the DSO has completed the refurbishment of approximately 15,700 spans of network at an expected unit cost of more than €51,500 per km.

In support of its higher unit cost (>€60,000), the DSO has explained that the works are planned to be delivered mainly by contractor resources and the contractor

costs are driving up unit costs. The DSO has stated that the proposed networks that will be refurbished in PR4 are the same vintage as networks refurbished in

74 Unit Cost per km based on refurbishment of 17,500 spans and 25 spans per km of network

Page 154: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 149

PR3 and the PR4 programme will mainly consist of networks not completed in PR3

We remain of the view that there is insufficient justification to support a 20% increase in unit costs for this work and we recommend PR4 allowances based on the

expected outturn unit costs for PR3.

This reduction results in a recommended PR4 capex of €38.2m, a reduction of €8.2m compared to the DSO’s revised forecast of €46.4m.

In its response to our Interim Report, the DSO has also identified a new sub programme, not previously proposed. This sub programme relates to the separation of public

lighting from the DSO LV network. The DSO has not provided any further details about this newly described sub programme and consequently we cannot recommend full

allowances. We have suggested an allowance of €400,000 per year over PR4 period to commence this programme. We would expect the DSO to fully assess the network

risks and associated mitigations required during PR4.

Page 155: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 150

5.2.2.8 Rural LV Network

DSO revised proposed PR4 capex is €84.5m, CER PR3 allowed capex of €95.8m, DSO current forecast for PR3 is €84.1m.

The proposed PR4 works associated with Rural LV Overhead Line Renewal is summarised in Table 5.29 below.

Table 5.29 : Summary of PR4 capex relating to Rural LV Overhead Line Renewal (€m – 2014 prices, unless stated otherwise)

LV Rural Overhead

Lines Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Low Voltage Rural

Refurbishment (LVR)

DSO proposes continuation of LVR programme that commenced in PR2 focusing work on

the bare LV rural groups with intention to bring these rural networks back to a minimum

acceptable standard.

55.6 11,350 4,900 PR3 outturn

costs 4,550 51.6 -4.0

Programme to inspect

and complete remedial

works on networks not

included in PR2/PR3

programme

In addition to LVR programme, the DSO proposes a programme in PR4 to inspect and

complete remedial works on a risk basis on networks which were not included in the

PR2/PR3 programme. This will include bare networks which were last inspected during the

period 1996 – 2002, thus 20 years since last patrolled and remedial works completed. As

such, the condition of assets – particularly wood poles – which two decades ago had not

deteriorated to the point which warranted replacement may no longer be in fit condition for

continued service.

28.9 5,900 4,900 PR3 outturn

costs 4,550 26.8 -2.1

TOTAL 84.5 78.5 -6.0

The DSO is proposing to refurbish 11,350 bare LV rural groups and commence an additional programme to inspect and complete remedial works on LV rural

networks that have not been addressed since the mid-late-1990s (a further 5,900 groups).

In its response to our Interim report, the DSO has provided further information relating to PR3 outturn costs. The original submission implied a unit cost of €4,100

per LV group, although the DSO latest PR3 forecast suggests €4,550 per LV group.

The DSO has assumed an increase in PR4 unit costs driven by increased defect rates and contract costs. Having observed a 10% increase in PR3 unit costs from its

original submission to its revised submission we do not agree that a further 10% increase in PR4 is justified.

We recommend allowances for these works based on the DSO expected outturn unit costs during PR3. This reduction will result in a recommended PR4 capex of

Page 156: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 151

€78.5m, a reduction of €6.0m compared to the DSO revised forecast of €84.5m.

Page 157: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 152

5.2.2.9 LV Cables and associated items

DSO revised proposed PR4 capex is €16.4m75, CER PR3 allowed capex of €17.2m, DSO current forecast for PR3 is €6.2m.

The proposed PR4 works associated with LV cables and associated items is summarised in Table 5.30 below.

Table 5.30 : Summary of PR4 capex relating to LV cables and associated items (€m – 2014 prices, unless stated otherwise)

LV Cables and

Associated Items –

Work Categories

Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Replace Painted Steel

Mini Pillars

DSO proposes a continuation of PR3 programme (affected by reduced volumes) relating to

the replacement of various types of mini pillar, dating from the 1970’s. Prioritisation of

replacement works will be based on the mini-pillar hazard patrol programme.

DSO also proposes to address the risks associated with dangerously degrading pillar

doors during PR4.

13 2000 6,500

Applied

reduction to

DSO proposed

PR4 unit costs

6,273 12.5 -0.5

Replace Cast Iron Mini

Pillars 1.3 200 6,500

Applied

reduction to

DSO proposed

PR4 unit costs

6,273 1.3 0.0

Replace Mini Pillar

Doors 0.4 1000 400

Applied

reduction to

DSO proposed

PR4 unit costs

386 0.4 0.0

Replace LV Link Boxes

DSO proposes further replacement of LV link boxes into PR4 – continuing the programme

from PR3. The main driver for this work is the age/condition of these items, (some >80

years old) with some models no longer having spare parts available.

0.3 100 3,000

Applied

reduction to

DSO proposed

PR4 unit costs

2,895 0.3 0.0

Replace 6mm2 Copper

Services

These are small cross-section service cables having a reduced rating. They are routed

within the interior of houses and pose a significant fire risk to the house and its occupants. 1.0 100 10,000

DSO proposed

PR4 unit costs 10,000 1.00 0.0

75 Updated Table 6.3 states PR4 capex of €16.4m. Previous PR4 capex was €16.4m. Within its response to our Interim Report, the DSO has identified a €0.2m reduction to its previous total of €16.4m and hence there is an obvious

inconsistency between Table 6.3 and the DSO response.

Page 158: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 153

LV Cables and

Associated Items –

Work Categories

Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Ongoing replacement programme will reduce the risk to the public and also improve

continuity through the introduction of a single customer underground service cable rather

than the current looped service.

Replace LV 4-core

XLPE pole top

terminations

DSO proposes a programme in PR4 to replace 200 faulty pole-top terminations. These 200

cases are where there is no UV resistant material over the exposed cores where water can

flow into and react with the aluminium causing severe corrosion at ground level.

This is estimated to be less than 0.5% of the total population of LV terminations.

0.2 200 1,000 DSO proposed

PR4 unit costs 1,000 0.2 0.0

TOTAL 16.2 15.7 - 0.5

In relation to the renewal programme associated with LV cables and associated items, the DSO proposed works for PR4 are mainly a continuation of PR3

programmes.

We recommend allowances for these works based on the DSO expected outturn unit costs during PR3. This reduction will result in a recommended PR4 capex of

€15.7m, a reduction of €0.5m compared to the DSO forecast of €16.2m76.

In relation to Minipillars, minipillar doors and LV link box replacement programmes, the DSO response suggests that our minor unit cost reductions will be difficult to achieve during PR4. As the PR4 unit costs proposed in our Interim Report were based on our assessment of reasonable costs incurred by the DSO during PR3, we believe these costs are appropriate to set allowances for PR4 capex.

76 €16.4m in updated Table 6.3

Page 159: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 154

5.2.2.10 Meters and Time Switches

DSO proposed PR4 capex is €14.1m, CER PR3 allowed capex of €0.0m, DSO current forecast for PR3 is €0.0m.

In PR3, the DSO did not carry out any planned meter replacements – this was to avoid any potential duplication of work or inefficient investment related to a potential roll-out

of smart metering programme. The DSO has identified a large group of meters in need of replacement, which are unlikely to be part of any smart metering rollout and which

are suggested to be in need of replacement by the end of PR4. The smart metering programme, when implemented, will cater for replacement of meters for domestic

customers and smaller commercial customers. The population of profile meters, using CTs, will not be covered by the smart meter programme – the total population of meters

exceeds 36,000.

The proposed PR4 works associated with Metering and Time Switch Renewal is summarised in Table 5.31 below.

Table 5.31 : Summary of PR4 capex relating to Metering and Time Switch Renewal (€m – 2014 prices, unless stated otherwise)

Metering and Time Switch replacements

Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4 Capex

(€m)

PR4 Volumes

PR4 Unit costs (€)

Unit Cost Assumptions

Unit Cost (€)

PR4 Capex

(€m)

CT Planned Meter

Replacement

DSO proposes to replace the external time switch meters with digital meters and these

replacements will ensure that the meter population will continue to operate to an

acceptable level.

The DSO PR4 programme caters for the replacement of 4,710 external time switch meters

and 12,507 digital meters (~55%).

11.3 17,217 654

DSO

Proposed PR4

costs

654 9.0 -2.3

Load Research Work

Program

CER has previously approved the installation of 1,800 load research recorders, allowing

representative sample data to be collected on customer behaviour across different

customer profiles.

Since then a number of the customers have been de-energised and changes in

consumption behaviour have depleted the quantity of sample meters.

The DSO proposes that 50 meters a year will be required in the PR4 period to ensure that

previous meters will not degrade and become unusable.

0.1 250 520

DSO

Proposed PR4

costs

520 0.1 -

Page 160: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 155

Metering and Time Switch replacements

Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4 Capex

(€m)

PR4 Volumes

PR4 Unit costs (€)

Unit Cost Assumptions

Unit Cost (€)

PR4 Capex

(€m)

Non Quarter Hourly to

Quarter Hourly meter

replacements

CER determined that sites which consume over 300,000 kWh p.a must become quarter-

hourly sites.

The DSO estimates that 200 sites will become eligible for quarter-hourly metering during

each year of PR4 and as a result ESB is obliged to comply with the meter replacements.

0.5 1,000 500

DSO

Proposed PR4

costs

500 0.5 -

Replacement of Power

Quality Meters

Due to the 20 year service life of these meters and their importance, the DSO proposes to

replace 150 PQ meters during PR4. 0.1 150 933

DSO

Proposed PR4

costs

933 0.1 -

Communications Project

The quarter hourly data collection unit (Profile Data Services) is responsible for the

collection, validation and distribution of quarter hourly data for the market that covers

approximately 40% of DUoS billing.

Due to service level agreements with the market to provide quarter hourly information, this

is currently being done via SIM card using GSM.

Movement towards a more cost effective and technologically current solution (GPRS) is

being looked at with the introduction of a pilot study to see the benefits over the GSM

which has been in place for the last 10-15 years and will become increasingly difficult to

source materials and communications support for the older communications.

30% of sites polled by MV90 comms system will require replacement of both meter and

modem and 70% modem only.

Completion of these works will be informed by a pilot which is scheduled for 2015, after the

MV90 upgrade has been completed.

DSO will only undertake the broader scale upgrade works if the 2015 pilot project proves

successful*.

2.0 1 2,020,000

DSO

Proposed PR4

costs

1.0 -1.0

Page 161: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 156

Metering and Time Switch replacements

Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4 Capex

(€m)

PR4 Volumes

PR4 Unit costs (€)

Unit Cost Assumptions

Unit Cost (€)

PR4 Capex

(€m)

TOTAL 14.1 10.8 -3.3

We have made adjustments to the DSO PR4 forecast capex of €14.1m associated with meter replacement. We have adjusted for the CT metering to be replaced

during PR4 (80%) and PR5 (20%) rather than funding the replacement of the full population during PR4.

We have also recommended a reduction in capex associated with the funding for a pilot communication project only (GPRS) for quarter hourly data collection.

We have proposed an allowance of €1m rather than the €2m proposed by the DSO relating to a broad scale upgrade of the communications system, .We have

not been provided with detailed cost information to support the €2m project and we would also expect the DSO to prepare a business case to support the wider

scale investment.

These adjustments reduce the DSO PR4 forecast capex from €14.1m to €10.8m, a reduction of €3.3m

Page 162: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 157

5.2.2.11 Cut-outs

DSO proposed PR4 capex is €14.3m, CER PR3 allowed capex of €5.8m, DSO current forecast for PR3 is €4.0m.

The proposed PR4 works associated with cut-out replacements is summarised in Table 5.32 below.

Table 5.32 : Summary of PR4 capex relating to Cut-out replacements (€m – 2014 prices, unless stated otherwise)

Cut-out replacements Background

DSO PR4 Forecast PR4 Recommended Variance

to DSO

PR4

Capex

(€m)

PR4

Capex

(€m)

PR4

Volumes

PR4 Unit

costs (€)

Unit Cost

Assumptions

Unit Cost

(€)

PR4

Capex

(€m)

Replacement of pre

1976 Cut outs

The DSO is proposing to continue with cut-out replacement programme during PR4

focusing on pre 1976 Cut outs. These are generally located in hallways etc., compared to

modern cut outs that are installed outside of premises in metal containers. Their location

represents a fire risk to the premises.

DSO estimates there are as many as165,000 pre 1976 cut outs, of which 97,000 have

been investigated and replaced where necessary during PR2 and PR3.

14.3 40,000 357.5 PR3 outturn

costs 140 5.6 -8.7

The DSO is expecting to complete replacement of 30,000 cut-outs during PR3 at a total cost of €4.1m (unit cost of €140). The PR4 programme is to increase the

replacement volume to 40,000 although its proposed unit cost (€357) is considerably higher than expected PR3 outturn. We recommend PR4 allowances based

on the proposed DSO volumes and the PR3 expected outturn unit costs in the absence of ESBN evidence to support the higher proposed unit cost.

This results in a recommended PR4 capex of €5.6m, a reduction of €8.7m compared to the DSO forecast of €14.3m.

Page 163: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 158

5.2.3 Continuity Capex

DSO proposed PR4 capex is €13.5m77, CER PR3 allowed capex of €22.8m, DSO current forecast for PR3

is €14.0m.

This programme primarily consists of the installation of automatic and remote control switches and other

measures to improve the performance of the network. The various programmes are summarised in Table 5.33

below.

Table 5.33 : Summary of PR4 capex relating to Continuity Improvement (€m – 2014 prices, unless stated otherwise)

Improvement Programme Unit Volume Total

Cost €m Unit Cost € DSO BCR

Loop Automation Schemes 50 8.5 170,000 7.3

Single Phase Reclosers Spurs 150 0.6 4,000 2.1

Fault Passage Indicators Units 1,150 1.1 957 7.8

Worst Served Customers Customer 6,000 1.4 233 0.9

Remote Control of RMU's (PILOT Project) Unit 30 0.3 10,000

38kV Switch Automation Unit 30 1.3 43,333

Wildlife diverters in HV Stations Unit 300 0.3 1,000

MV Arc Suppression (Reinforcement Expenditure) Station 17 0 -

Total Capex

13.5

For PR4, the DSO proposes to further progress a number of continuity improvement programmes that

commenced in PR3 but were curtailed due to financing constraints and requirement to focus on safety driven

investments. Such programmes include further installation of:

Loop automation schemes – these comprise two interconnected MV networks with sufficient capacity to

provide backup supply to each other in the event of a fault on one of the interconnecting feeders. Typically,

five reclosers per two interconnecting feeders will be required.

Single Phase Reclosers – installation of reclosers on single phase spurs to address customer interruptions

due to transient faults, installed only on spurs where the calculated benefit is greatest.

Fault passage indicators – higher accuracy units (based on actual current measurements provided by

CT’s), indicating passage of fault current remotely. These units also communicate via GPRS and can be

integrated with the DSO SCADA system.

Improvements to worst served customers.

Smaller scale continuity improvements are also proposed by the DSO, including:

the fitting of ultrasonic bird diverters in HV stations.

installation of 30 remotely operable line switches on the 38kV network.

pilot project for urban RMU automation (deferred from PR3).

For each of the proposed continuity improvement programmes, the DSO has carried out cost-benefit analysis,

which has been used to prioritise its investment plans.

We recommend that the proposed DSO PR4 capex of €13.5m relating to its Continuity Improvement

programme is allowed.

This allowance includes €1.4m associated with a continuity programme to improve supplies to the

77 This incorporates €4.2m as per Table 6.3 Continuity Improvement Capex item plus a further €9.3m that the DSO categorised as ‘Other (specify)’

which the DSO has confirmed also relates to the Continuity Improvement capex work programme.

Page 164: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 159

DSO’s worst served customers. In its response to the proposed Incentives for PR4 (Document DR07)

the DSO has presented two separate scenarios to address worst served customers, based on available

information from UK DNOs (the UK RIIO ED1 decision documents). Once CER has finalised the DSO

PR4 incentive framework (including allowances, targets, penalties etc – there may be a requirement to

make an adjustment to theses recommended allowances for DSO continuity capex.

The CML/CI benefits associated with its Continuity Programme that have been identified by the DSO will be fully

assessed when determining appropriate network performance incentive targets for the DSO during PR4.

5.2.4 Response Capex

DSO PR4 revised proposed capex is €61.2m78; CER PR3 allowed capex of €101.1m, DSO PR3 forecast is

€56.5m.

This is a reactive work programme, generally driven by third parties or unplanned events. There are 9 existing

categories of reactive work against which the DSO allocates and monitors expenditure. Within its response to

our Interim Report, the DSO has identified a further category of reactive work associated with the theft of 38kV

Copper overhead lines The DSO proposed capex for each of these categories is summarised in Table 5.34

below and compared the equivalent expenditure and allowance in PR3.

Table 5.34 : PR4 Response Capex – Comparison of DSO Forecast v PR3 (€m – 2014 Prices)

Category CER PR3

Allowed

DSO PR3

Outturn

DSO Original

PR4 Proposed

DSO Revised

PR4 Proposed

Recommended

DSO PR4

Voltage Complaints 30.3 13.9 14.2 14.2 14.2

25mm SCA OH Conductor Replacement 9.5 4.0 4.2 4.2 4.2

MV/LV UG Cable Replacement. 8.8 2.3 2.0 2.0 2.0

Metering Replacement 7.9 4.8 2.6 2.6 2.6

Time-switch Replacement. 5.1 3.0 1.6 1.6 1.6

Failed Transformer Replacement 12.2 16.9 18.4 18.4 16.8

38kV Cable Replacement 5.7 2.2 0.9 0.9 0.9

Undergrounding MV & LV OH lines 16.5 6.5 6.6 6.6 6.6

Advance Ducting 5.1 0.8 0.7 0.7 0.7

38kV Copper Line - Theft Response 0.0 2.0 0.0 10.0 5.0

Totals 101.1 56.3 51.2 61.2 54.6

Note – Source data for DSO PR3 Outturn – Document Reference DH07 – PR3 Response Capex (Table 1) – converted to 2014 prices

In its response to our PR4 capex IR, the DSO explained the need for urgent works that are scheduled for 2015

to address risks associated with the theft of 50mm2 Copper conductor from 4 x 38kV overhead line circuits. The

works involved replacement of the copper conductor with aluminium conductor (of equivalent rating) and the

estimated capex for this new work programme is €2.0m in 2015.

We agree with the DSO proposed Response Capex for PR4 for the majority of the existing categories, other than for costs relating to failed transformers.

For this category, the DSO proposed a 10% increase on PR3 capex. We have not observed an increase in transformer failure rates during PR3 to justify this cost increase and therefore we have recommended a reduction for this category to the PR3 run-rate.

In addition, whilst we accept that there will be a need for the DSO to take action to address the theft of copper conductor from its overhead line network, we note this is a new category of reactive work for

78 Note – DSO Table 6.3 (April 2015) states €61.4m, whilst the DSO response to our Interim Report states €61.2m

Page 165: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 160

which the DSO has based PR4 forecast on a nominal €2m per year, this being the forecast costs for 2015 to address 4 specific circuits that have been subject to repeated thefts.

The DSO PR4 forecast is based on an assumption that similar quantities and works will be required on an annual basis for the PR4 period. However, in the absence of any detailed risk analysis, we cannot conclude if these figures are reasonable. We therefore recommend a PR4 allowance of €5.05m in total

This reduces PR4 continuity capex by €6.6m to €54.6m.

5.2.5 System Control Network Capex

DSO PR4 proposed capex is €16.5m; CER PR3 allowed capex of €15.4m, DSO PR3 forecast is €3.9m.

The DSO has identified a number of proposed system control projects79 that may be undertaken during PR4.

These fall into three main categories and are summarised below in Table 5.35, together with the DSO forecast

PR4 capex of each project.

Table 5.35 : PR4 System Control Expenditure for PR4 (€m – 2014 prices)

Expenditure Item Capex

(m)

OMS Related

OMS Upgrade 3.5

Mobile Interface 1.2

AMS Interface 1

Sub-Total 5.7

SCADA related

RTU Replacements 4.3

SCADA NM7 upgrade 0.8

Server Replacements 0.7

Sub-Total 5.8

Control Centre Infrastructure

Emergency Control Room 0.7

Back up Cello Station alarm (GSA) 0.5

Sub-Total 1.2

GRAND TOTAL 12.7

We have observed from the above table that the grand total of PR4 capex relating to the identified projects is

€12.7m, although the DSO has submitted a PR4 capex forecast of €16.5m. The DSO has acknowledged that

the correct amount sought was €12.7m. Generally, the DSO has not provided sufficient justification to support

the planned investment.

OMS has been upgraded in PR3; the DSO is proposing further upgrade in PR4 at a cost of €3.5m – with no

business case to support this investment. It is unlikely that within the 5 years there would be such a change in

the hardware and software for an operational system such as this, there may however be a need to carry out

some upgrading which is as yet not specified and provision of €1.5m would allow maintaining the system rather

than provisioning for an unknown requirement.

79 Identified within Narrative Document DF11 -

Page 166: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 161

There is also no business case for the proposed mobile interface with OMS, the DSO has however identified the

operational advantages and initiatives to provide facilities such as switching instructions direct to the mobile

transport and real time network updates and would therefore allow the mobile interface of €1.2m.

Regarding AMR interface, we recommend this should be considered separately within the context of the smart

meter roll out programme, this being consistent with DSO PR4 submission excluding smart metering.

We recommend PR4 funding relating to SCADA and Control Centre Infrastructure at a total capex of

€9.7m. This represents a reduction of €3.0m compared to aggregate total of €12.7m80.

5.2.6 Integrated Vision for an Active Distribution Network (IVADN)

The DSO has proposed PR4 capex of €7.1m in relation to its R&D project titled “Integrated Vision for an Active

Distribution Network” (IVADN). The DSO narrative document ‘DF09a IVADN’ provides background information

relating to this project.

Key focus areas for the project will be:

Setting out the revised vision for the planning and operation of the Distribution System in an optimised

manner which is fit for purpose to 2025.

Reviewing European Codes to ensure impacts on system planning and operations are fully understood.

The transposition of Network Code non-exhaustive requirements into the Distribution Code.

Engagement with the TSO within DS381 to ensure that the Distribution System operates in a manner which

can facilitate achieving 75% System Non-Synchronous Penetration (SNSP) target, whilst maintaining

Distribution standards and DSO license obligations

The project involves a number of study work streams to analyse network subjects such as MV Regulator issues,

38kV Regulator issues, Reactive Power studies and Distribution System Management.

The DSO has identified a number of workstreams within the scope of the IVADN project and provided estimated

costs for each workstream. The capital costs can be summarised as follows:

Reactive Power Workstreams - €3.5m

Rate of Change of Frequency (ROCOF) Protection Alternative - €2.0m

Remote Control of MV Boosters €0.4m

Power Quality (PQ) Recorder Replacement €1.2m

Sub Total €7.1m82

Although the DSO has forecast €7.1m in PR4, it is unclear what the specific project deliverables and

benefits will be. There appears to be significant uncertainty regarding how this R&D project will

proceed and what it will cost (both capex and opex).

We therefore recommend that the DSO is allowed the capex costs associated with the reactive power

work stream (of €3.5m) as these are well advanced.

In the absence of detailed plans for the other work streams we recommend additional total allowance

of €1m. We also suggest that the DSO continues to engage with the CER during PR4 once details of

the particular projects, including timing, cost, expected benefits, etc. are known in more detail.

Our total recommended allowance is therefore €4.5m which is €2.6m lower than the DSO proposed

PR4 forecast of €7.1m.

80 A reduction of €6.8m compared to the DSO forecast of €16.5m for PR4 (within Table 6.3) 81

DS3 - Delivering a Secure Sustainable Electricity System (DS3) – Eirgrid /Soni Programme (http://www.eirgrid.com/operations/ds3/) 82 In addition, there is a further €3.6m identified relating to OMS upgrades (considered separately within System Control Capex)

Page 167: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 162

5.2.7 North Atlantic Green Zone (NAGZ)

The DSO PR4 capex forecast includes €87.6m associated with the NAGZ project. The DSO is the project co-

ordinator of this project which will, subject to acquisition of the necessary grant funding, implement a Smart Grid

on an infrastructural scale in the North-West of Ireland. The project partners in this consortium are:

1) ESBN

2) Northern Ireland Electricity

3) EirGrid

4) SONI

The NAGZ project aims to address the challenges faced by network system operators across Europe as the

penetration of renewable generation increases to unprecedented levels. This project is intended to marry

intelligent electricity networks, high-speed communications and IT, coupled with increased cross-border

connectivity, with the objective of achieving operational excellence and ensure the involvement of all users. It

will be the blueprint for future network deployment on the island of Ireland and across Europe.

Project elements include:

20kV conversion from medium voltage networks – 12,000km

Dynamic Active Distribution System Management

Network automation and upgraded protection systems (part of PR3 and will form part of work programmes

for PR4 & PR5). This consists of a combination of the following:

- Three Phase Reclosers (102)

- Switches (167)

- Fault Passage Indicators (279)

- Single Phase Reclosers (186)

- Widespread Arc Suppression protection systems will be deployed - to all the 20kV networks in the

North Atlantic Green Zone – 23 station installations.

Cross Border Interconnection - Interconnection is a crucial part of the NAGZ project. As this is a first for

both DSOs at MV level, it will require significant discussions and development from both a planning and

operational perspective, as well as involving EirGrid and SONI. Route corridors have been identified from

the initial European Commission submission stage but now detailed surveys are required.

Advanced Communications (Optical fibre network) - optical fibre network deployed on the 38kV system

connect all of the 38kV stations to the backbone communications network. This will entail the fibre

wrapping and sub-ducting of approximately 377km of 38kV network. In addition to the deployment of fibre,

NAGZ also involves the deployment of an advanced WiMax wireless mobile field area network to connect

all medium voltage down-line sensors and devices.

The total benefits stated in the NAGZ CBA report are €246.2m with the net benefits standing at €130.7m over

20 years. The NAGZ has a total project cost of €106m – with the costs split between ESB Networks (€70m) and

NIE (€36m).

The main capex cost components include:

Deployment of ASC Systems: €16.2m

20kV Conversion: €14.9m

Fibre & WiMax communications: €16.6m

Network Automation and DMS: €16.3m

Interconnection with NI: €4.1m

Page 168: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 163

The NAGZ project received an award of €31.75m in grant funding from the European Commission in November

2014.The funding provided to the DSO is expected to be €22.2m83 and this will need to be netted off the gross

capex requirements for PR4.

The NAGZ has a total project cost of €106m – with the costs split - DSO: €70m, NIE: €36m. The DSO

PR4 capex forecast includes for €87.6m associated with the NAGZ project, which has also recently

received grant funding of €31.75m from the EC, with the expectation that the DSO will receive €22.2m

of this grant.

These facts suggest that the proposed DSO PR4 capex forecast of €87.6m relating to the NAGZ is

higher than necessary.

We also note that the NAGZ main capex cost components include works for which allowances have

been separately assessed (e.g. PR4 20kV conversion programme and upgraded protection schemes

within the DSO PR4 Continuity Improvement) and for which capex allowances will be made for PR4.

There is a potential risk of duplicating capex allowances as it is not clear that the overall network

assessment has explicitly excluded network assets within the NAGZ.

In its response to our Interim Report, the DSO has advised that all of the 20kV conversion work

undertaken during PR4 will be outside the NAGZ.

We recommend that the CER provides gross capex allowances for the NAGZ during PR4 of €70m – the

DSO proportion of the NAGZ total cost, netted off by the amount of CEF funding of €47.8M.

5.2.8 Non Load Related Expenditure – Summary of Allowances

The previous sub-sections have detailed the DSO’s proposed PR4 capex relating to its asset renewal

programmes and its other non-load related capex plans. For each category, we have made recommendations

on proposed capex allowances for PR4 period and these recommendations are summarised below in Table

5.36. Based on the information available from the DSO at the time of writing this report, we recommend that the

PR4 NLR Capex is reduced from €694.3m to €564.0m, a reduction of €105.1.

Table 5.36 : PR4 – Non Load Related Capex – Summary (€m – 2014 prices)

Category of work DSO Original PR4

Proposed

DSO Revised PR4

Proposed

Revised

Recommended PR4

PR4 Variance PR4

Recommended v

DSO Revised

Forecast

Renewal Programme - 110kV &

38kV Lines 46.5 38.4 27.5 -10.9

Renewal Programme - 110 &

38kV Cables 24.5 28.0 25.8 -2.2

Renewal Programme - HV

Substation 126.4 125.9 116.9 -9.6

Renewal Programme - MV

Overhead Lines 131.9 82.2 78.2 -4.1

Renewal Programme - MV

Cables 0.0 0.0 0.0 0.0

Renewal Programme - MV

Substations 23.3 33.2 31.1 -2.1

Renewal Programme - Urban LV 46.5 46.4 38.2 -8.3

83 DR06 Addendum contributions

Page 169: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 164

Category of work DSO Original PR4

Proposed

DSO Revised PR4

Proposed

Revised

Recommended PR4

PR4 Variance PR4

Recommended v

DSO Revised

Forecast

Renewal

Renewal Programme - Rural LV

Network 74.8 84.5 78.5 -6.0

Storm Rectification Project 0.0 0.0 0.0 0.0

Renewal Programme - LV cables

and associated items 16.2 16.2 15.7 -0.5

Renewal Programme - Meters

and Time Switches 14.0 14.1 10.8 -3.3

Renewal Programme - Cut-outs 14.3 14.3 5.6 -8.7

Continuity Improvement 13.5 13.5 13.5 0.0

Response capex 51.2 61.2 54.6 -6.8

System Control 16.5 16.584 9.7 -6.8

IVADN (Integrated Vision for an

Active Distribution Network)

Project

7.1 7.1 4.5 -2.6

NAGZ 87.6 87.6 70.0 -17.6

Other (specify) - Included in

CONTINUITY Programme above 0.0

TOTAL 694.4 669.1 580.5 -90.6

5.3 Non Network Related Expenditure

The DSO has forecast a total non-network related capex of €172.2m in PR4. This is €33.4m higher than the

actual Non-Network capex of €138.9m in PR3, representing an increase of 24%.

The detailed breakdown of the Non Network Capex is shown below in Table 5.37 (as submitted in the initial

forecast questionnaire).

Table 5.37 : Detailed Breakdown of PR4 Forecast Non-Network Capex (€m 2014 prices) by Category

Category PR4 Forecast PR3 Actual

2016 2017 2018 2019 2020 Total Total

New Accommodation - - - - - - -

Accommodation Refurbishment 2.96 2.96 2.96 2.96 2.96 14.8 11.2

Fixture & Fittings 0.14 0.14 0.14 0.14 0.14 0.7 0.1

Office Equipment - - - - - - 0.0

Vehicles 6.0 6.0 6.0 6.0 6.0 30.0 35.1

Tools 2.0 2.0 2.0 2.0 2.0 10.0 15.6

Distribution Assets Management

Distribution Control / Operation 17.7 12.5 9.5 11.5 7.7 58.9 42.3

IT Infrastructure

84 As per DSO FBPQ Table 6.3 dated 5th Dec 2014

Page 170: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 165

Enterprise Applications

Environment 0.8 0.8 0.8 0.8 0.8 4.0 1.9

Telecoms & System Control 11.3 12.6 11.6 9.3 9.2 53.9 17.0

Non Rab Telecoms - - - - - - 15.7

Total 40.9 36.9 33 32.6 28.8 172.2 138.9

In general the DSO has increased expenditures in all areas excluding Tools, and has prioritised significant

increases in areas of Vehicles, Accommodation, Enterprise Applications and Telecoms. Although there are

significant increases in some areas there was an underspend against the PR3 allowances due to financial

constraints within the business. It is likely that there will be some element of catching up with the DSO capex

expenditure in PR3.

We discuss the proposed PR4 expenditures in the sub-sections below.

5.3.1 Accommodation Fixtures and Fittings and Office equipment

The DSO has forecast that the capital expenditure for PR4 on refurbishment will be €2.96m per year and an

additional €0.14m per year on fixtures and fitting giving a total forecast of €15.5m over PR4. This is in

comparison with an average of €2.0m per year in PR2 and €2.3m per year in PR3.

This increase has been put down to the fact that during PR3 capital restrictions were in place and only

necessary refurbishment took place. The plan for PR4 is that general coordinated refurbishment will continue

due to the expectation that gaining capital will be less of an issue. 60% of the DSO buildings are currently over

20 years of age and as a result were not designed to meet current accommodation standards. This therefore

appears to be a reasonable justification for an increase in expenditure due to the age and condition of buildings.

In supporting documentation submitted by the DSO the requested €15.5m was split as shown in Table 5.38, the

only difference being to segregate out the budget to include Safety and Security as part of the overall

refurbishment and fixtures and fittings budget.

Table 5.38 : Forecast Building Expenditure PR4 (€m – 2014 prices)

Years 2016 2017 2018 2019 2020 Totals

Refurbishment €2.3m €2.3m €2.3m €2.3m €2.3m €11.3m

Safety €0.5m €0.5m €0.5m €0.5m €0.5m €2.5m

Security €0.5m €0.2m €0.2m €0.2m €0.2m €1.0m

Furniture & Fittings €0.1m €0.1m €0.1m €0.1m €0.1m €0.7m

Office Equipment €0.1m €0.0m €0.0m €0.0m €0.0m €0.0m

Totals €3.1m €3.1m €3.1m €3.1m €3.1m €15.5m

The expenditure in safety and security equates to €3.5m in PR4, of which €1m of this is forecast for upgrading

security systems due to the number of successful break-in attempts during PR3 at a cost of €0.2m per year.

ESBN have stated that €0.5m per annum is to be spent on the safety aspect of refurbishment and is expected

to be an output from a number of initiatives. These initiatives are:

Documentation including risk assessment updates appropriate to the location, updates to documented safe

methods of work, safety audits and local emergency plans.

Survey/Inspection/Audit particularly updates to premises survey and audits (including asbestos) particularly

those locations where there are high staff concentrations, building inspections with findings classified and

implemented according to whether they are emergency, urgent or best practice and radon testing (which is

a requirement for all premises).

Page 171: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 166

Implementation of Group-wide standards and Best Practices - Electrical (e.g. RCD and Portable Appliance

Testing), Mechanical (e.g. Lifts, Air Handling and Plumbing) and Structural.

The decommissioning of HVAC units that contain R22 Gas has to be completed within the next five years

per a recent clarification from the EPA on the subject.

Water quality standards also require annual testing for legionella and appropriate risk mitigation actions will

be required to ensure compliance with safety standards.

Total PR4 forecast expenditure on Refurbishment and Fixtures and Fittings reflects an increase over

PR3 of €4.2m, but is €2.8m less than the PR3 allowance.

Given the capex constraints in PR3 it seems reasonable that there would be an increase over the PR3

outturn to ensure the buildings are maintained and secure. We therefore recommend allowances of

the full €15.5m.

5.3.2 Vehicles

The total expenditure forecast for PR4 is €30.0m, with expenditure incurred at a rate of €6.0m per annum. The

profile of vehicular expenditure is shown below in Figure 5.12.

Figure 5.12 : DSO Vehicles – Annual Expenditure Profile (€m)

The DSO reports that they are re-commencing capex expenditure on the fleet vehicles beginning in 2014 and

2015 and continuing throughout PR4 at a rate of €6m per year. In the submission in November 2014 (Ref DF32)

the forecast for Vehicles was for an outturn of €17.2m for PR3 and a proposed expenditure of €30m in PR4 to

satisfy the business requirements.

An updated forecast issued by the DSO in March 2015 shows a significant change in the outturn for PR3

increasing from the €17.2m to €35.1m (effectively doubling the expenditure expected in PR3 from the forecast

in November 2014. This change was reportedly due to incorrect forecasting of the later years of PR3. The

0

5

10

15

20

25

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

An

nu

al

Exp

en

dit

ure

(ém

)

DSO Forecast Mar 2015 DSO Forecast Dec 2014

Page 172: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 167

previous submission stated that the increase in expenditure in 2014 and 2015 was the start of the increase

planned through to 2020, with a total expenditure over the seven years of €44.0m.

The latest forecast shows an expenditure of €31.8m in 2014 and 2015 whilst still maintaining an expenditure of

€30m for the 5 years of PR4 to 2020, increasing the total expenditure between 2014 and 2020 to €61.8m

compared to the €44.0m expected in the earlier forecast.

In addition, we recognise that the initial forecast in PR3 was well below expenditure in PR2 and was due to

unavailability of funds. We understand the need to ensure vehicles are properly managed and accept that the

expenditure increase in 2014 and 2015 will recover the underspend in 2011 2012 1nd 2013. It is evident that the

forecast for PR4 does not fully reflect the efficiencies being driven by the introduction of the Mobile Workforce

Management system. In addition the issues raised in the PA Consulting Transport review( ref ESBN document

DF 32) identified many issues relating to under-usage of vehicles and there should be further opportunities to

reduce the fleet rather than replace based on utilisation, avoiding dedicated vehicles and increase use of shared

vehicles. The costs identified in the company response of increasing maintenance costs for HGV vehicles would

suggest that the priority be given to advancing the HGV replacement while deferring the vans and cars, where

with relatively lower mileages, the maintenance costs would be considerably lower. The case put in DR06 would

have been significantly higher than the proposed requirements in DF32, and some of the points raised are

indeed identifying potential opex savings..

Due to the significant increase in expenditure in 2014 and 2015, we would anticipate that there should

be an opportunity to defer some expenditure pending a thorough review of the utilisation and volume

requirements following efficiencies driven by Mobile Workforce Management systems.

We have therefore proposed an allowance of €23.75m compared to the €30m DSO forecast over PR4,

a reduction of €6.25m.

5.3.3 Tools

The forecast PR4 capex for tools is €10m; this has been reduced from the PR3 total of €14.8m and

represents good progress in developing efficiencies. The proposal is to allow the €10m.

5.3.4 IT associated with Asset Management, Control/Operations, IT Infrastructure and Enterprise

Applications

The forecast IT expenditure on Non Network Capex is shown below in Table 5.39 and equates to €58.9m over

the PR4 period. This indicates an increase of 39% over the PR3 outturn of €42.3m.

Table 5.39 : DSO PR4 Forecast Non Network IT Expenditure

IT Capex 2016 2017 2018 2019 2020 Totals

Mobile Workforce Management €4.1m €4.1m €4.1m €4.5m €3.8m €20.6m

Document Management System €5.5m €2.4m €0.0m €0.2m €0.0m €8.1m

Web & SW Development €3.9m €4.0m €2.3m €2.9m €2.4m €15.9m

PC Hardware & Accessories €1.3m €0.8m €0.2m €0.7m €0.4m €3.4m

Upgrades €2.9m €1.3m €2.8m €3.2m €0.7m €10.8m

Total €17.7m €12.5m €9.4m €11.5m €7.7m €58.9m

The table above comes from the ESBN pdf ‘DF 15 IT Projects’. The assessment of these programmes is

provided below.

Page 173: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 168

Mobile Workforce Management

The DSO has identified a €20.6m programme covering mobile applications for inspections, reacting to faults,

timesheet reporting and forms for completing in the field. The documentation states there are substantial

quantifiable benefits of implementing this programme. The DSO states that “these benefits will be refined during

the scope and design stage of each project as it is initiated”. This is a substantial investment and could

potentially drive benefits, however to approve such funds in advance of submission of associated business

cases will likely result either in an underspend or in potentially wasteful costs.

We would expect to see an operational initiative defining a forecast efficiency in delivery of operations resulting

in opex and capex efficiency with a net benefit for this investment. Some additional information has been

provided identifying potential savings of 105 FTE’s both back office and field staff. The forecast headcount

within ESBN over the period of the introduction of this system is shown below in Figure 5.13. Although there

are numerous areas where there may be a requirement to increase headcount, the potential reduction of 105

FTE’s would be expected to show a larger impact on the overall headcount and flow through as reduced opex in

the maintenance and restoration activities, and reduced unit costs in the capex activities. Neither of these are

evident in the submission.

Figure 5.13 : DSO Headcount

There are obvious benefits to utilising Mobile Workforce Solutions and we would expect this to be progressively

developed with break points reflecting on the delivered benefits, the additional information provided has

indicated a sound business case and would be supported, however the forecast opex and capex costs do not

appear to reflect the benefits, we are therefore not inclined to change our view that €12.5m, averaging €2.5m a

year to be justifiable unless there is a demonstrated saving identified in costs in line with the business case

figures provided. The DSO have presented the case for this expenditure and we fully support the potential

benefits , however we maintain that the increase in cost in this area should have been offset by at least an

equivalent amount within PR4 and going forward in PR5.

Total PR4 forecast expenditure on Mobile Workforce Management reflects an increase over PR3 of

€14.2m. Given the potential benefits of this, it would be expected that a detailed business case driven

by the efficiency and cost benefit would be apparent. There has been information suggesting that the

business case justifies this, however this does not seem to be reflected in the submission for capex

and opex in the areas suggested within the business case.

It is therefore proposed that the programme in PR4 should be €15.0m, a reduction of €5.0m from the

DSO forecast. We would however emphasise that we are not constraining this initiative which we fully

support and would encourage the DSO to progress this rapidly to ensure the benefits are delivered

early. The additional costs will be offset by the benefits and make this self-financing.

Page 174: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 169

Document Management System

In Document DF15 there is a list of benefits associated with the Document Management System, but these do

not have any tangible quantified benefit listed. We would expect the DSO to identify benefits leading to future

efficiencies. The document management system is proposed at a cost of €8.1m in PR4 years 2016 and 2017

after an initial €0.94m of expenditure in PR3 with the majority being forecast for 2015 (Tab 6.2 Historic

Questionnaire). We would not expect the expenditure to be incurred mainly in 2016 when a clear business case

with tangible benefits are not presented with options for reducing expenditure where delivered benefits are not

being achieved. ESBN has provided further information listing deliverables and restating the €8.1m, however

the document also states;

“This project is required to deliver a fit for purpose document management system to contribute to an overall fit

for purpose Safety Management System. The existing document management systems have been found to be

not appropriate and this project must proceed. This project does not have a traditional business case supporting

the expenditure for these reasons.”

The driver may be clear cut and the need stated relates to safety and viewed in that light. We would fully

support efforts to improve safety and deliver systems which would achieve this, however the need does not

detract from the necessity to carry out a detailed business case, which is essential in clearly defining the need,

identifying a number of potential solutions with each approach and option delivering a range of benefits at a

range of costs. This would then be challenged to ensure the need is satisfied at the optimum cost. The danger

in not taking this approach would be to incur costs inefficiently and we would recommend carrying out the

business case urgently to determine opportunities to scope the project more efficiently. We would therefore

suggest reducing the amount to €6.9 m.

Total PR4 forecast expenditure on the Document Management System reflects an increase from

€0.94m in PR3 (all forecast in 2014 and 2015) to €8.1m in PR4. Given the potential benefits of this, it

would be expected that a detailed business case driven by the efficiency and cost-benefit would be

apparent. As this is not the case, then it is proposed to reduce the value proposed by €1.2m to €6.9m

5.3.5 Environment

The forecast DSO PR4 Environmental capex figures show a relatively significant increase when compared with

both PR2 and PR3. The average annual expenditure that the DSO has forecast for the PR4 period is €0.8million

as shown in Figure 5.14 below.

Figure 5.14 : DSO Non Network Capex Environment Expenditure PR2 to PR4 (€m – 2014 prices)

Page 175: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 170

Within the PR2 period, the average expenditure on this category was €0.1million with very low and in some

cases, zero expenditure. Within PR3, the average expenditure of €0.4million was half the DSO forecast for PR4.

The DSO justification for this increase in expenditure in PR4 has been based on a number of services. The

largest component of the expenditure is related to wood pole storage, which is forecast for an increase and a

total expenditure of €1.4million. The rationale for this is that many of the DSO’s storage facilities are currently

not up to best practice standard and require upgrading to prevent any further contamination to wood poles.

The DSO has also stated that there will be a forecast increase in oil management, depot drainage infrastructure

improvements, waste management and energy efficiency with regards to buildings nationwide in PR4.

The DSO has identified a number of specific projects where there is a requirement for remedial action to

improve the storage areas for poles and reduce potential contamination. We recommend that the allowance is

in line with their proposal of €4m.

Total PR4 forecast expenditure on Environment is €4m compared to €1.9m in PR3, there are a number

of projects specified which require remedial action particularly associated with pole storage. It is

recommended that the proposal of €4m is allowed. .

5.3.6 System Control and Telecoms

The forecast expenditure on System Control and Telecoms is €53.9m. In PR3 the expenditure was €17.0m on

System Control and Telecoms plus €15.7m on Non RAB Telecoms. These are now amalgamated with the

assets being added to the RAB. The projects which account for the forecast expenditure are as shown in Table

5.40 below.

Table 5.40 : Forecast PR4 Capex - System Control and Telecoms (€m – 2014 prices)

Project Title Project Costs

3.2.1 Provision of Telecommunications Connectivity for HV Locations

3.2.1.1 WAN Expansion of Operational Fibre Network into HV Stations €4.0 m

3.2.1.2 Expansion of Services of Existing Operational WAN €1.7 m

3.2.1.3 Microwave Radio Expansion & Network Enhancement €2.7 m

3.2.1.4 Reinforcement & Growth of Satellite Network €1.5 m

3.2.1.5 New Protection Schemes – Network Distribution €1.2 m

3.2.1.6 Provision of Connectivity for Migration of Teleprotection Services off 3rd Party Circuits €0.2 m

3.2.2 Telecommunications Network Infrastructure Replacement

3.2.2.1 Polling Radio Replacement €2.9 m

3.2.2.2 Replacement of Microwave Radio Network €2.1 m

3.2.2.3 Replacement of Obsolete Add/Drop Equipment €0.4 m

3.2.2.4 Pilot Cable Termination Replacement €0.3 m

3.2.3 Substation SCADA Infrastructure

3.2.3.1 Transducer/HV Telemetering €0.9 m

3.2.3.2 RTU Flash Upgrade €0.6 m

3.2.4 Operational Voice and Telephony Services

3.2.4.1 NCCC Upgrade €4.7 m

3.2.4.2 OpTel Replacement €1.1 m

3.2.4.3 IPT Network Access Infrastructure €1.4 m

3.2.4.4 Voice & Video €0.6 m

3.2.5 Critical Supporting Infrastructure and Systems

Page 176: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 171

3.2.5.1 Power Systems €3.2 m

3.2.5.2 Air Conditioning €1.0 m

3.2.5.3 Network, Service & Work Management Systems €0.7 m

3.2.5.4 Network Management Infrastructure €0.4 m

3.2.5.5 ConnectMaster €1.1 m

3.2.6 Telecommunications Network Expansion & Technology Developments

3.2.6.1 Core & Aggregation IP Network €11.9 m

3.2.6.2 National Radio Access Communications Network €5.3 m

3.2.6.3 New Telecom Projects & Trials €4.0 m

Total €53.9 m

The supporting documentation lists the various systems and provides some explanation of the capabilities of the

equipment and the potential functionality, however there is no clear quantitative assessment of the business

case with explanation of need and options to justify the cost and selected option and scale.

There is limited explanation of the impact of not progressing these activities, or the options to reduce the scale

and timing of the delivery programme to ensure the need is clearly defined and the projects scaled to meet the

defined need. If the investment in all of these areas does not proceed there needs to be a clear understanding

of the impact and the mitigation to minimise the impact.

Figure 5.15 shows the DSO historic expenditure and the forecast for PR4.

Figure 5.15 : PR3 and PR4 Forecast Telecoms and Control Expenditure (2014 prices)

The major expenditures of Core & Aggregation IP Network, National Radio Access Communication Network and

New Telecoms projects and Trials (unspecified) represents €21m of the Total Forecast. These are all geared to

an unspecified growth in sensors on the network and described as:

-

2

4

6

8

10

12

14

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

An

nu

al e

xpe

nd

itu

re (

€m

)

Page 177: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 172

“an enabler in efficiently meeting the evolving energy needs of electricity customers…This single

consolidated new generation network will be a fundamental building block in fulfilling the existing and future

communications requirements of the electricity network. This core network will also provide a platform for

replacing legacy technologies and systems that are approaching end of life. In addition it will act as a key

enabler of smart network operations.”

This seems to be geared to building new infrastructure against a need that is not quantitatively defined and

without defining the constraints within the existing infrastructure. There has been additional information provided

but not a standard business case with explanation of drivers, relating to quantitative measures which would

allow an assessment of the appropriate timing and appropriateness of this investment and an impact evaluation

of mitigating approaches to the investment. The key amounts from Table 5.39 relating to core and aggregation

IP Network and National Radio Access Network are major changes in infrastructure which were viewed as ‘Non

RAB’ expenditure and provide services for the networks business but also provide services to third parties,

which generates an income. It seems inappropriate to fund capex entirely from the regulated business with the

capital allowed revenues, and then have services provided to 3rd

parties, which are not linked to the investment.

It is recognised that income is offset in the regulated business but if fully funded and guaranteed, there appears

to be no major driver to maximise the potential revenue from third parties to ensure the regulated electricity

customer is benefiting from the investment. Mixing regulated and unregulated expenditures can also be seen as

a potential issue for the competition in these unregulated areas. It is proposed to accept the need for the

expenditure on the Core & Aggregation IP Network and National Radio Access Communication Network, but

there should be the opportunity to recover this investment if these projects don’t proceed preventing the

expenditure being used in other areas which will not generate additional income.

As there has been a significant increase in the proposed budget and insufficient detail provided to show

optimum cost effective solutions have been provided then it is proposed to apply a 10% efficiency target

equating to €5.4m.

Total PR4 forecast expenditure on Control and Telecoms is €53.9m compared to €32.6m in PR3. The

business case for the expenditure has not been clearly demonstrated and it is believed that there

should be opportunities for driving efficiencies from this budget. It is therefore recommended that the

proposed allowance should be reduced by €5.4m giving the PR4 allowance as €48.5m. It is also

recommended that the expenditure allowance is dependent on delivery of the Core & Aggregation IP

Network and National Radio Access Communication Network.

5.3.7 Non-Network Capex – Recommendations and Conclusions on Proposed Allowances

In conclusion there are a number of areas where there is justification for maintaining and increasing

expenditure, however there are other areas where there are proposed significant increases where there has not

been sufficient justification and a demonstrated business case showing need, options and risk associated with

the proposed increases. Table 5.41 shows the aggregate allowance for Non Network Capex for the PR4

period.

Table 5.41 : Summary of DSO Proposed Non Network Capex PR4 (€m – 2014 prices)

Non Network Capex - Category Actual PR3 DSO Forecast PR4 Recommended PR4

New Accommodation - - -

Accommodation Refurbishment 11.2 14.8 14.8

Fixture & Fittings 0.1 0.7 0.7

Office Equipment 0.0 - -

Vehicles 35.1 30.0 23.75

Tools 15.6 10.0 10.0

Distribution Assets Management 42.3 58.9 52.5

Distribution Control / Operation

Page 178: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 173

IT Infrastructure

Enterprise Applications

Environment 1.9 4.0 4.0

Telecoms & System Control 17.0 53.9 48.5

Non RAB Telecoms 15.7 - -

Total 138.9 172.3 154.3

5.3.8 Smart Metering Expenditure

The DSO PR4 forecast for capex associated with smart metering is €22.9m with these costs expected to

be incurred in 2016 (€12.5m) and in 2017 up to end June 2017 (€10.3m). Outturn Capex during PR3 is

€12.9m.

The PR4 forecast costs are proposed by the DSO to deliver its responsibilities in the National Smart Metering

Program (NSMP) until mid-2017, recognising the gated approach that the CER has adopted.

The final decision to award contracts arising from the procurement project rests with the NSMP following

reassessment of an updated CBA. At this point in Q2 2017 it is expected that CER will be in a position with

sufficient cost information to enable a final decision on how to proceed.

The staged nature of the overall NSMP is reflected in the DSO PR4 submission which states total costs that are

likely to be incurred up to that CER decision point and these costs are sought as a CAPEX allowance.

The DSO has identified a number of work streams necessary up to this gate position:

Project Management and stakeholder engagement - The ongoing management and control of the program

including networks work-stream and engagement with stakeholders including program at CER.

Deliver key smart metering procurements - This activity will be focused on the procurement of

communications services, meters and the meter Data Management System products and services.

Design and Delivery of Critical Backend IT upgrades.

Full rollout phase planning and preparation.

The DSO has only provided details of the €22.9m split by year, with no indication of planned capex

relating to each of the work streams and the capex deliverables necessary to facilitate the roll-out of

the smart metering program. Without a clear understanding of how the proposed capex is to be

invested, what physical assets are being delivered, we are not able to recommend full allowances.

In the absence of detailed supporting justification, we recommend PR4 allowances set at PR3 outturn

levels - €12.9m representing a reduction of €10.0m compared to the DSO PR4 submission.

5.4 Summary & Conclusions

5.4.1 Capex Overview

In headline terms, the DSO is forecasting a total gross expenditure of €1.7bn for PR4. This is €433m (25%)

lower than PR3 allowed capex of €2.15bn and €391m higher than PR3 actual/forecast capex of €1.33bn.

Net of customer contributions, the DSO is forecasting total PR4 capex of €1.48bn. This is €273m lower

than PR3 allowed capex and €351m higher than PR3 actual/forecast capex of €1.13bn.

The DSO PR4 forecast can be described in headline terms by the following characteristics:

- Demand Connections – DSO is forecasting a total number of connections in PR4 of 108,000 – this

represents an increase of 53% compared to the total of 70,417 during PR3, but is still only 33% of the

total number of connections made during PR2;

Page 179: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 174

- The DSO is forecasting 0% cumulative growth in peak demand during PR4 – reinforcement

expenditure during PR4 is focused on addressing parts of the system which do not presently comply

with the Planning Standards;

- Capex (gross) associated with generator connections is forecast to increase by 23% from €88.9m in

PR3 to €109.5m to connect a total of 1,250 MW of renewable generation over PR4 period (compared

to 1,200 MW expected by the end of PR3);

- Capex associated with non-load related projects and programmes is the category where the DSO is

forecasting the largest increase in capex in PR4 compared to PR3 – with a variance of €245.6m

(around 58%). The renewal programmes for which the DSO has forecast the largest increases in

capex in PR4 relate to HV Station works and HV and MV overhead line works. The DSO’s plans are

focused on the replacement of aging and defective assets. Non-load related Capex was the area

most affected during PR3 by capital funding constraints, so a larger catch-up allowance is to be

expected.

- In addition, the DSO has included €87.6m of PR4 capex relating to the North Atlantic Green Zone

(NAGZ) smart grid initiative;

- The forecast increase in PR4 non-network capex (of 24%) is driven by increased expenditure on

vehicles, Distribution Asset Management (including IT infrastructure), Telecomms and System Control;

- In relation to the Smart Metering project, the DSO submission for PR4 includes for further

development and project costs necessary to take the project to the next major milestone in 2017. It

does not include capex associated with a country-wide roll out programme as the final investment

decision has not yet been taken.

We have carried out an assessment of the DSO’s proposed capex plan and we have identified a number of

recommended adjustments to the allowed capex for PR4 – these are explained in more detail within the

preceding sections of the report.

Following our assessment, we recommend PR4 net capex allowance of €1336.78m – representing a

reduction of €144.381m. The PR4 capex proposed by DSO, together with our recommended allowances

are itemised below.

Table 5.42 : DSO PR4 Capex Summary (€m – 2014 Prices)

SUMMARY OF ALLOWANCES PR3

Allowed

PR3

Actual

PR4

Requested

(Table 6.3)

Revised PR4

Requested

(Table 6.3)

PR4

Recommended

Variance

(Recommended

to Revised

Request)

(G1) New housing Schemes 74.6 16.7 46.5 44.2 45.1 0.9

(G2) Non-scheme Houses 164.4 89.0 106.1 107.7 102.6 -5.1

(G3) Commercial/Industrial Supplies 212.5 120.8 128.5 129.8 125.3 -4.5

Whole Current Metering 12.5 14.7 24.1 19.5 17.8 -1.8

New Business 464.0 241.2 305.2 301.2 290.8 -10.4

Transmission Connection Costs 26.3 0.0 15.2 15.2 15.2 0.0

110kV 236.1 144.4 150.4 150.4 150.4 0.0

38kV 215.2 86.5 85.9 85.9 85.9 0.0

MVLV System Improvements 70.8 34.5 40.9 40.9 36.3 -4.6

IFTs associated with 20kV

Conversion 16.6 22.9 0.0 11.1 11.1 0.0

20kV Conversion 83.0 36.5 25.4 14.3 13.9 -0.4

Reinforcements 648.1 324.7 317.8 317.8 312.8 -5.0

Generation Connections 166.5 88.9 109.5 109.5 109.5 0.0

Dismantling 58.8 48.3 70.2 64.4 55.1 3

Page 180: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 175

SUMMARY OF ALLOWANCES PR3

Allowed

PR3

Actual

PR4

Requested

(Table 6.3)

Revised PR4

Requested

(Table 6.3)

PR4

Recommended

Variance

(Recommended

to Revised

Request)

Non-Repayable Line Diversions 53.1 48.3 92.1 60.2 50.6 -9.6

Total Load Related CAPEX 1390.4 751.3 894.8 853.1 818.7 -34.4

Renew Prog - 110kV & 38kV Lines 16.7 15.5 46.5 38.4 27.5 -10.9

Renew Prog - 110 & 38kV Cables 21.0 6.2 24.5 28.6 25.8 -2.8

Renew Prog - HV Substation 120.4 77.1 126.4 126.5 116.9 -9.6

Renew Prog - MV Overhead Lines 70.7 61.0 131.9 82.2 78.2 -4.1

Renew Prog - MV Cables 2.6 2.0 0.0 0.0 0.0 0.0

Renew Prog - MV Substations 24.7 31.2 23.3 33.2 31.1 -2.1

Renew Prog - Urban LV Renewal 64.3 36.2 46.5 46.4 38.2 -8.3

Renew Prog - Rural LV Network 95.8 84.1 74.8 84.5 78.5 -6.0

Storm Rectification Project 0.0 27.4 0.0 0.0 0.0 0.0

Renew Prog - LV cables and

associated items 17.2 6.2 16.2 16.4 15.7 -0.8

Meters and Time Switches 0.0 0.0 14.0 14.1 10.8 -3.3

Renew Prog - Cut-outs 5.8 4.0 14.3 14.3 5.6 -8.7

Continuity Improvement 22.8 14.0 13.5 13.5 13.5 0.0

Response capex 101.1 56.5 51.3 61.4 54.6 -6.8

System Control 15.4 3.9 16.5 16.5 9.7 -6.8

IVADN 0.0 0.0 7.1 7.2 4.5 -2.6

NAGZ 0.0 0.0 87.6 87.6 70.0 -17.6

Other (specify)85 0.0 0.0 0.0 0.0 0.0 0.0

NRP/ Bulk Supply 0.0 0.0 0.0 0.0 0.0 0.0

Total Non-Load Related CAPEX 578.5 425.4 694.4 671.0 580.5 -90.6

Capex - Non Network 183.5 138.9 172.2 172.2 154.3 -18.0

Other (Smart Metering) 0.0 12.9 22.9 22.9 12.9 -10.0

Contributions -398.3 -198.5 -200.1 -238.2 -229.8 8.4

TOTAL NET CAPEX 1754.1 1130.1 1544.3 1481.0 1336.9 144.2

5.4.2 Demand Connections

The DSO PR4 forecast capex (gross) is €301.2m, this is €60.0m (25%) higher than the expected PR3

outturn total capex of €241.2m. Net of customer contributions, the DSO PR4 forecast capex is €150.6m,

some €14.0m higher than expected PR3 outturn.

The increase in gross capex as forecast by the DSO for PR4 period is based on an increased number of

connections for each of G1/G2/G3 categories. Steady growth during PR4 is forecast by the DSO and a

total of 108,000 connections are expected to be made over this period, representing a 53% increase to

PR3 volumes.

85 Included within the Continuity Work Programme

Page 181: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 176

We consider that the DSO PR4 forecast of new connections of 108,000 is a reasonable assumption for

tariff purposes, recognising that CER will make adjustments for higher or lower connections based on

allowed unit costs.

The DSO has proposed standard unit costs for each of the G1/G2/G3 connections. We have concluded

that the proposed DSO unit costs for 2016 and 2017 are reasonable. However we recommend that the

additional costs that the DSO has factored in to its unit cost calculation from 2018 onwards should be

removed, this being consistent with the DSO a priori assumption that its forecast does not include for the

introduction of smart metering.

A reduction in allowed PR4 gross capex of €8.7m is recommended for PR4 demand connections, based on

difference in unit costs for G1/G2/G3 connections.

For PR4, the DSO is forecasting total metering capex of €19.5m – this is €4.8m (32.6%) higher than PR3

expected outturn costs and €7.0m (56.3%) higher than PR3 allowed costs.

We recommend allowances for PR4 period based on 6.5% of our recommended PR4 gross capex for

G1/G2/G3 connections of €273m. This results in a recommended allowance for metering of €17.8m

representing a reduction of €1.8m compared to the DSO revised PR4 proposed capex of €19.5m.

5.4.3 Generator Connections

For generator connections, the DSO is forecasting gross capex in PR4 of €109.5m. This represents an

increase of 24.4% compared to expected PR3 outturn.

Capex during PR4 will therefore be focused on these Gate 3 projects that have contracted since mid-2013.

The DSO is estimating that a total of 1,250 MW is to be connected to the distribution system during PR4.

As expected in our review of DSO historic capex, the over-recovery of connection costs in later years of

PR3 is resulting in net positive cash flows throughout the PR4 period, with a total net capex over the PR4

period of €47.4m.

We recommend acceptance of the DSO proposed gross capex of €109.5m.

5.4.4 Load Related Reinforcement

The DSO load-related reinforcement capex for the PR4 period is €317.8m. Although this is significantly

below the PR3 allowed capex of €648.1m, it is only €6.9m (2.1%) lower than DSO expected outturn

(€324.7m) for the PR3 period.

The DSO’s proposed PR4 reinforcement capex forecast has been prepared on a zero cumulative load

growth forecast for peak demand from 2013 - 2020. The DSO has made significant investment to reinforce

the network during previous price controls. However, there are still many parts of the network that do not

comply with the Planning Standard.

Unit sales (GWh) during PR4 are forecast to grow at approximately 2.2% per year. The DSO has assumed

that that the unit sales growth does not result in peak demand growth.

Zero load growth and peak demand reduction due to smart metering impact act to suppress the capex

forecast requirements for PR4 relative to previous price controls.

We are satisfied that the DSO has established good practice relating to its preparation of investment plans

for its 110kV and 38kV network development and undertaking project investment appraisals before seeking

technical and financial approval and subsequent commitment of capex to a project.

Notwithstanding some errors and/or inconsistencies with the consolidated list of HV reinforcement projects

compared to individual projects and which are not considered to be material, we conclude that the DSO

proposed PR4 reinforcement capex for 110kV and 38kV is reasonable.

The DSO has proposed a total of €40.9m of reinforcement capex relating to the MV and LV network. The

proposed PR4 capex (€40.9m) represents a 18.8% increase compared to expected costs for PR3

(€34.5m), although considerably less than PR3 allowed costs of €70.8m.

We generally agree with this work being necessary although we would recommend allowances for PR4

such that PR3 actual and PR4 forecast capex is consistent with the PR3 allowed capex of €70.8m – this

Page 182: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 177

was allowed to address known network deficiencies and is considered adequate for the DSO’s zero growth

scenario. In addition we would expect the ongoing 20kV conversion programme to improve the network

and reduce reinforcement requirements.

This will reduce PR4 allowances for MV/LV System reinforcements by €4.6m to €36.3m (a reduction of

11%).

With regard to the 20kV conversion programme, the DSO expected PR3 volumes (10,500km) and capex

(€36.5m) result in a unit cost per km converted of approximately €3,475/km. The DSO proposed PR4

programme is based on converting 4,000km at the same unit cost, giving a total cost of €13.9m. Further

IFT works at cost comparable with PR3 are also proposed. We consider these to be reasonable costs and

consequently we recommend PR4 allowance of €25.0m.

5.4.5 Retirements (Dismantling) Capex

We recommend PR4 allowances for dismantling which are derived as a proportion of our recommended

PR4 gross network capex – with allowances set at 4.1% of this gross value - this results in a recommended

PR4 capex for dismantling of €55.17m, representing a reduction of €9.39m compared to the DSO forecast

of €64.4m.

5.4.6 Diversions

It is observed that there is a strong historic relationship between new business gross costs and diversion

gross costs. However, the DSO forecast is not consistent with this historic relationship. We therefore

recommend PR4 allowances for diversion works that are consistent with the historic relationship between

new business and diversion gross costs. We have applied this to our recommended allowances for New

Business gross capex.

This results in a PR4 forecast capex for diversions of €50.6m, representing 17.4% of PR4 gross new

business capex. This is €9.6m (16%) lower than the DSO revised forecast of €60.2m and €42.5m (45%)

lower than the DSO original forecast of €92.1m.

5.4.7 Non-Load Related Capex

The DSO’s revised non load-related (NLR) capex for the PR4 period is €669.1m. This is significantly above

the expected PR3 outturn capex of €425.4m, although only €92.5m higher than the CER allowed capex for

non-load related capex during PR3.

The main drivers for the proposed PR4 works are to address safety risks, ensure compliance with health &

safety and environmental obligations and to maintain continuity of supply. Replacement works are driven

by the condition and performance of particular asset categories. The DSO NLR PR4 programme consists

of the following projects/programmes:

- Completion of major 110kV and 38kV HV Station replacement projects originally planned for

completion in PR3 but subsequently deferred due to prevailing financial situation at the time;

- Continuation of existing HV & MV asset renewal and security programmes to mitigate safety risk to the

public and the DSO workforce;

- Continuation of cyclical refurbishment of the 38kV & MV overhead lines, together with a project to

rebuild a number of 110kV double circuit tower lines in the Dublin area;

- Commencement of a small number of targeted asset renewal/ refurbishment programmes

- NAGZ is a major smart grid investment initiative aimed at addressing the impact caused by increasing

levels of renewable generation. The project will look to combine intelligent smart grid networks, high

speed communications and IT, linked with increased cross-border connectivity

- The proposed plans also include for a small number of relatively low cost pilot projects to allow for

assessment of emerging/ different technologies before any decision is made regarding roll out of such

technologies on a wider scale. The costs of these are presently incorporated within the DSO’s main

asset renewal programme categories but these could be ring-fenced within the DSO PR4 R&D

forecast expenditure category

Page 183: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 178

In general, we consider the justification for the various PR4 works proposed by the DSO is proven and in

many cases, we agree with the proposed volumes of work. However, our review has identified a number of

significant increases in the DSO PR4 planned costs, compared to PR3 planned costs (for deferred works)

or PR3 expected outturn costs (for works progressed during PR3).

We have therefore made proposed adjustments to the proposed DSO PR4 non-load related capex to

account for such differences where the DSO has been unable to provide further justification supporting

such increases in planned costs for its major projects and its planned unit costs for its asset renewal work

programmes.

In relation to the 38kV Overhead Cyclical Refurbishment Programme, the DSO revised forecast for PR4 is

based on a unit cost which is consistent with outturn cost in PR3. We recommend allowances for PR4 that

are consistent with the PR3 outturn unit costs.

In relation to the re-conductoring of 110kV double circuit tower lines in the Dublin area, it is our

understanding that there has not yet been any detailed line survey and analysis to inform the assessment

of the potential costs and that the DSO has not yet fully developed its proposed investment case. The DSO

PR4 forecast is therefore based on a middle-ground cost scenario. However, taking a low cost based on a

line refurbishment using existing towers, and a high cost based on fully undergrounding and stating that a

half way position is part underground, part tower replacement and part fittings replacement does not

constitute a planned investment.. We would however agree that the requirement to carry out the lowest

cost practical solution at this time seems reasonable and therefore would recommend this cost of €6.8m.

We do recognise the risk associated with this cost uncertainty and therefore once the DSO has developed

its planned investment for these circuits, this should be reviewed to assess the efficiency of their proposed

investment during PR4.

The proposed changes result in PR4 recommended capex of €27.5m for 110kV and 38kV lines (with capex

reduced by €10.9m).

Our recommended PR4 capex allowances for 110kV and 38kV cable asset renewal works is €25.8m

broadly in line with DSO original capex submission of €24.5m within Table 6.3 of Forecast Business Plan

Questionnaire, but some €2.2m less than the DSO’s revised capex submission of €28.0m.

For a number of the sub-programmes associated with HV Station Asset Renewals, we have applied a

reduction to the proposed unit costs that the DSO has used in its PR4 forecast. These result in a

recommended PR4 capex of €116.9m, a reduction of €9.0m compared to the DSO forecast of €125.9m.

The DSO is proposing to inspect and refurbish where required, 34,500km of MV OHL as part of a 12 year

cyclical refurbishment programme at a unit cost of more than €2,200 per km. During PR3 period 2011 to

2014, the DSO has completed the refurbishment of approximately 18,400km at an expected unit cost of

€2,100. For PR4, the DSO is forecasting the unit cost will increase to €2,217 per km, representing an

increase of more than 5%.We recommend allowances for PR4 based on unit costs achieved during PR3

(2011 to 2014).

This reduction results in a recommended PR4 capex of €78.1m, a reduction of €4.1m compared to the

DSO revised forecast of €82.2m.

The DSO proposes a zero capex associated with the renewal of MV cables as no planned capital activities

are proposed for MV cable assets. PR3 allowed capex was €2.6m, with PR3 expected outturn of €1.8m.

For a number of the sub-programmes associated with MV Station Asset Renewals, we have applied

reduction to the proposed unit costs that the DSO has used in its PR4 forecast. These result in a

recommended PR4 capex of €31.1m, a reduction of €2.1m compared to the DSO revised forecast of

€33.2m.

The DSO is proposing to refurbish 17,500 spans of Urban LV overhead network (dating pre-1950) at a unit

cost of more than €60,000 per km. During PR3, the DSO is forecasting to complete the refurbishment of

approximately 15,700 spans of network at an expected unit cost of more than €51,500. In support of its

higher cost (>€60,000), the DSO has explained that the works are planned to be delivered mainly by

contractor resources and the contractor costs are driving up the unit costs. The DSO has stated that the

proposed networks that will be refurbished in PR4 are the same vintage as networks refurbished in PR3

and the PR4 programme will mainly consist of networks not completed in PR3. We remain of the view that

there is insufficient justification to support a 20% increase in unit costs for this work and we recommend

Page 184: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 179

PR4 allowances based on the expected outturn unit costs for PR3. This reduction results in a

recommended PR4 capex of €38.2m, a reduction of €8.2m compared to the DSO’s revised forecast of

€46.4m.

The DSO is proposing to refurbish 11,350 bare LV rural groups and commence an additional programme to

inspect and complete remedial works on LV rural networks that have not been addressed since the mid-

late-1990s (a further 5,900 groups). We recommend allowances for these works based on the DSO

expected outturn unit costs during PR3. This reduction will result in a recommended PR4 capex of €78.5m,

a reduction of €6.0m compared to the DSO forecast of €84.5m.

In relation to the renewal programme associated with LV cables and associated items, the DSO proposed

works for PR4 are mainly a continuation of PR3 programmes. We recommend allowances for these works

based on the DSO expected outturn unit costs during PR3. This reduction will result in a recommended

PR4 capex of €15.7m, a reduction of €0.5m compared to the DSO’s revised forecast of €16.2m.

We have made adjustments to the DSO PR4 forecast capex of €14.1m associated with meter replacement.

We have adjusted for the CT metering to be replaced during PR4 (80%) and PR5 (20%) rather than

funding the replacement of the full population during PR4. We have also recommended a reduction in

capex associated with the funding for pilot communication project only (GPRS) for quarter hourly data

collection. We have proposed an allowance of €1m rather than the €2m proposed by the DSO relating to a

broad scale upgrade of the communications system. We have not been provided with detailed cost

information to support the €2m project and we would also expect the DSO to prepare a business case to

support the wider scale investment. These adjustments reduce the PR4 forecast capex from €14.1m to

€10.8m, a reduction of €3.3m.

The DSO is expecting to complete replacement of 30,000 cut-outs during PR3 at a total cost of €4.1m (unit

cost of €140) in PR3. The PR4 programme is to increase the replacement volume to 40,000 although its

proposed unit cost (€357) is considerably higher than expected PR3 outturn. We recommend PR4

allowances based on the proposed DSO volumes and the PR3 expected outturn unit costs in the absence

of evidence from the DSO to support the higher proposed unit cost. This results in a recommended PR4

capex of €5.6m, a reduction of €8.7m compared to the DSO forecast of €14.3m.

For each of the proposed continuity improvement programmes, the DSO has carried out cost-benefit

analysis, which has been used to prioritise its investment plans. We recommend that the proposed DSO

PR4 capex of €13.5m relating to its Continuity Improvement programme is allowed. This allowance

includes €1.4m associated with a continuity programme to improve supplies to the DSO’s worst served

customers. In its response to the proposed Incentives for PR4 (Document DR07) the DSO has presented

two separate scenarios to address worst served customers, based on available information from UK DNOs

(the UK RIIO ED1 decision documents). Once CER has finalised the DSO PR4 incentive framework

(including allowances, targets, penalties etc – there may be a requirement to make an adjustment to theses

recommended allowances for DSO continuity capex.

We agree with the DSO proposed Response Capex for PR4 for all categories, other than for costs relating

to failed transformers. In addition, whilst we accept that there will be a need for the DSO to take action to

address the theft of copper conductor from its overhead line network, we note that this is a new category of

reactive work for which the DSO has based PR4 forecast on a nominal €2m per year, this being the

forecast costs for 2015 to address 4 specific circuits that have been subject to repeated thefts. The DSO

PR4 forecast is based on an assumption that similar quantities and works will be required on an annual

basis for the PR4 period. However, in the absence of any detailed risk analysis, we cannot conclude if

these figures are reasonable. We therefore recommend a PR4 allowance of €5m in total. This reduces

PR4 continuity capex by €6.6m to €54.6m.

We recommend PR4 funding relating to SCADA and Control Centre Infrastructure – at a total capex of

€9.7m. This represents a reduction of €3.0m compared to the aggregate total expenditure of €12.7m80 for

PR4.

In relation to the IVADN project, the DSO has forecast €7.1m in PR4. However it is unclear what capex is

proposed by the DSO during PR4 and what the project deliverables and benefits will be. There appears to

be significant uncertainty regarding how this R&D project will proceed and what it will cost (both capex and

opex).

Page 185: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 180

We therefore recommend that the DSO is allowed the capex costs associated with the reactive power work

stream (of €3.5m) as these are well advanced.

In the absence of detailed plans for the other work streams, we recommend additional total allowance of

€1m. We also suggest that the DSO continues to engage with the CER during PR4 once details of the

particular projects, including timing, cost, expected benefits etc. are known in more detail. Our recommend

allowance is therefore €4.5m, which is €2.6m lower than the DSO proposed PR4 forecast of €7.1m.

The NAGZ has a total project cost of €106m – with the costs split between the DSO (€70m) and NIE

(€36m). The DSO PR4 capex forecast includes for €87.6m associated with the NAGZ project, which has

also recently received grant funding of €31.75m from the EC. These facts suggest that the proposed DSO

PR4 capex forecast relating to the NAGZ is higher than necessary.

We also note that the NAGZ main capex cost components include works for which allowances have been

separately assessed (e.g. PR4 20kV conversion programme and upgraded protection schemes within the

DSO PR4 Continuity Improvement) and for which capex allowances will be made for PR4. There is a

potential risk of duplicating capex allowances as it is not clear that the overall network assessment has

explicitly excluded network assets within the NAGZ. The DSO has advised that all of the 20kV conversion

work undertaken during PR4 will be outside the NAGZ.

We recommend that the CER provides gross capex allowances for the NAGZ during PR4 of €70m – the

DSO proportion of the NAGZ total cost.

5.4.8 Non-Network Capex

The DSO has forecast a total capex of €172.2m by end of PR4 – this is €33.4m higher than the actual Non-

Network capex of €138.9m in PR3.

There are a number of areas where there is justification for maintaining and increasing expenditure,

however there are other areas where there are proposed significant increases where there has not been

sufficient justification and a demonstrated business case showing need, options and risk associated with

the proposed increases.

Total PR4 forecast expenditure on Refurbishment and Fixtures and Fittings reflects an increase over PR3

of €4.2m, but is €2.8m less than the PR3 allowance. Given the capex constraints in PR3, it seems

reasonable that there would be an increase over the PR3 outturn to ensure the buildings are maintained

and secure. We therefore recommend allowances of €15.5m in line with the forecast.

Total PR4 forecast expenditure on Vehicles at €30m was based on a forecast outturn in PR3 of €17.2m.

Since December 2014 the forecast outturn for PR3 has increased to €35.1m. We have therefore adjusted

the PR4 allowance based on the increased expenditure in 2014 and 2015. We do not believe the forecast

fully exploits improved utilisation and vehicle reduction based on savings driven by the Mobile Workforce

Management system, recommended allowance is therefore €22.75m.

The forecast PR4 capex for tools is €10m; this has been reduced from the PR3 total of €14.8m and

represents good progress in developing efficiencies. The proposal is to allow the €10m.

Total PR4 forecast expenditure on Mobile Workforce Management reflects an increase over PR3 of

€14.2m. Given the potential benefits of this, it would be expected that a detailed business case driven by

the efficiency and cost benefit would be apparent. Some information has been provided which suggests

significant opex and capex savings within the business. However this saving is not reflected in the

submission in those areas. It is therefore proposed that the programme in PR4 should be €15m, a

reduction of €5m from the DSO forecast. We would comment that we fully support the full implementation

of this initiative which should not be constrained by the allowance. The allowance reflects that savings

elsewhere not provided at this time will make the initiative self-financing.

Total PR4 forecast expenditure on the Document Management System reflects an increase from €0.94m in

PR3 (all forecast in 2014 and 2015) to €8. 1m in PR4. Given the potential benefits of this, it would be

expected that a detailed business case driven by the efficiency and cost benefit would be apparent. As this

is not the case, then it is proposed to reduce the value proposed by €1.2m to €6.9m.

Page 186: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 181

Total PR4 forecast expenditure on Environment is €4m compared to €1.9m in PR3. There has been some

information provided identifying where the additional expenditure is needed therefore it is recommended

that this is allowed at €4m.

Total PR4 forecast expenditure on Control and Telecoms is €53.9m compared to €32.6m in PR3. The

business case for the expenditure has not been clearly demonstrated and it is believed that there should be

opportunities for driving efficiencies from this budget. It is therefore recommended that the proposed

allowance should be reduced by €5.4m giving the PR4 allowance as €48.5m. It is also recommended that

the expenditure allowance is dependent on delivery of the Core & Aggregation IP Network and National

Radio Access Communication Network.

The DSO PR4 forecast for capex associated with smart metering is €22.9m with these costs expected to

be incurred in 2016 (€12.5m) and in 2017 up to end June 2017 (€10.3m). Capex during PR3 is €12.9m.

The DSO has only provided details of the €22.9m split by year, with no indication of planned capex relating

to each of the work streams and the capex deliverables necessary to facilitate the roll-out of the smart

metering program. Without a clear understanding of how the proposed capex is to be invested, what

physical assets are being delivered, we are not able to recommend full allowances.

In the absence of supporting justification, we recommend PR4 allowances set at PR3 outturn levels - €12.9m

representing a reduction of €10.0m compared to the DSO PR4 submission.

Page 187: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 182

6. Conclusions

The DSO has proposed a total PR4 opex allowance (excluding commercial costs and Depreciation) of

€1506.0m. We have reviewed each line item and consider that a reduced allowance of €1399.1m is sufficient

for an efficient DSO to operate.

We have suggested that the DSO develops an appropriate method to understand the asset heath of its asset

portfolio, in order to understand the overall level of maintenance required and to inform future Asset

Maintenance and Replacement Programmes. We have also allowed, in full, the Health and Safety Allowance in

order to provide the DSO staff and the public with a safe operating environment.

With regard to capex, in headline terms, the DSO is forecasting a total gross expenditure of €1.72bn. This is

€433m (25%) lower than PR3 allowed capex of €2.15bn and €391m higher than PR3 actual/forecast capex of

€1.33bn. Net of customer contributions, the DSO is forecasting total PR4 capex of €1.48bn. This is €273m lower

than PR3 allowed capex and €351m higher than PR3 actual/forecast capex.

We have carried out an assessment of the DSO’s proposed capex plan and we have identified a number of

recommended adjustments to the allowed capex for PR4. Following our assessment, we recommend PR4 net

capex allowance of €1336.9m – representing a reduction of €144.2m..

Page 188: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 183

Table 6.1 : DSO Allowed Opex Revenue for PR4

DSO Proposed PR4 Jacobs Proposed PR4

Variance % 2016 2017 2018 2019 2020 Total 2016 2017 2018 2019 2020 Total

OPEX

Capital Driven Opex

Network O&M Total 114.4 117.9 116 116.7 116.1 581.1 105.8 109.2 107.3 108.0 107.4 537.7 -43.4 -7%

Asset Management 14.0 14.2 14.4 14.7 15.0 72.3 14.0 14.2 14.4 14.7 15.0 72.3 0.0 0%

Metering 40.4 38.0 34.2 33.9 33.6 180.1 34.7 35.0 32.4 32.5 32.7 167.2 -12.9 -7%

Customer Service 18.4 17.8 17.8 18.1 18.2 90.2 16.9 17.1 17.0 17.0 17.1 85.0 -5.2 -6%

Provision of Information 12.4 12.4 12.9 12.8 12.8 63.3 10.7 10.8 10.9 10.8 10.7 53.9 -9.4 -15%

Corporate Costs 10.3 10.3 10.3 10.3 10.3 51.4 9.7 9.7 9.7 9.7 9.7 48.4 -3.0 -6%

Telecoms 13.2 13.5 13.6 13.7 13.8 67.7 3.5 3.8 3.9 4.0 4.1 19.3 -48.4 -71%

Sustainability R & D 2.3 2.6 3.4 3.7 3.6 15.6 2.3 2.6 1.9 2.2 2.1 11.1 -4.5 -29%

Other 19.5 19.6 19.6 19.6 19.7 98.2 20.2 18.7 15.5 13.9 12.7 80.9 -17.3 -18%

Controllable Total 244.9 246.2 242.2 243.4 243.2 1219.8 217.8 221.0 213.0 212.6 211.6 1076.0 -143.9 -12%

Network Rates 46.9 51.0 55.0 59.1 63.1 275.1 46.9 51.0 55.0 59.1 63.1 275.1 0.0 0%

Car Levy 2.2 2.2 2.2 2.2 2.2 11.0 2.2 2.2 2.2 2.2 2.2 11.0 0.0 0%

Non Controllable 49.1 53.2 57.2 61.3 65.3 286.1 49.1 53.2 57.2 61.3 65.3 286.1 0.0 0%

TOTAL 294.1 299.4 299.4 304.6 308.5 1506 266.9 274.2 270.2 273.9 276.9 1362.0 -143.9 -10%

Page 189: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 184

Table 6.2 : DSO Allowed Capex Revenue for PR4

DSO Proposed PR4 Jacobs Proposed PR4

Variance % 2016 2017 2018 2019 2020 Total 2016 2017 2018 2019 2020 Total

CAPEX

New Business 48.9 52.1 59.1 67.2 74.0 301.2 290.8 -10.4 -3.5%

Reinforcements 48.5 53.9 63.3 73.0 79.2 317.8 312.8 -5.0 -1.6%

Generation Connections 49.4 32.9 8.8 8.8 9.6 109.5 109.5 0.0 0.0%

Dismantling 12.8 13.1 13.3 12.3 12.9 64.4 55.1 -9.3 -14.5%

Non-Repayable Line

Diversions 8.4 11.1 11.1 13.5 16.1 60.2 50.6 -9.6 -16.0%

Load Related Capex 168.0 163.1 155.6 174.7 191.8 853.1 818.7 -34.4 -4.0%

Non-Load Related

Capex 147.6 145.4 144.6 116.7 116.7 671.086 580.6 -90.6 -13.5%

Non-Network Capex 40.9 36.9 33.0 32.6 28.8 172.2 154.3 -18.0 -10.4%

Other (Smart Metering) 12.5 10.3 0.0 0.0 0.0 22.9 12.9 -10.0 -43.7%

Contributions -63.9 -52.4 -36.6 -40.6 -44.7 -238.2 -229.8 8.6 3.6%

Total Net Capex 305.1 303.3 296.6 283.4 292.6 1481.0 1336.9 -144.2 -9.7%

86 It should be noted that assessment of the DSO’s detailed non-load related capex suggests a total proposed capex of €669.1m, as shown in the summary tables of Section 5.

Page 190: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 185

Appendix A. Benchmarking

This appendix sets out the methodology and results of benchmarking ESBN’s distribution and 110kV

transmission costs in PR2, PR3 and PR4 by using Great Britain Distribution Network Operators (GB DNOs) as a

reference set.

Benchmarking exercises are often undertaken by businesses, regulators and academics in a variety of fields to

identify practices which lead to efficiency gains. Efficiency gains are most often analysed with respect to cost

reductions whilst maintaining the same level of output but can also include improvements in innovation, service

quality or other areas a business deems important to their goals.

This benchmarking study focusses on identifying relative changes within ESBN in their operating costs and non

network capital costs in delivering the same volume of services during the PR3 period and whether the

forecasts proposed in PR4 represent appropriate increases or decreases in expenditure. Within the context of

this study, volume of services and quality of services are two distinct concepts with different meaning and

interpretation. This study does not aim to analyse the efficiency of the quality of service delivered by ESBN; for

example we will use the volume and cost of faults in the study but we do not adjust for whether the faults are

being restored in a shorter or longer time.

A top down approach to opex and opex plus non-network capex (NN capex) has been undertaken to make the

comparison. The top down figures have been adjusted and normalised to generate data sets that are

comparable to published GB DNO data. More detailed assessment of unit costs has been undertaken in the

body of this report and is based on a bottom-up approach.

The data for the benchmarking assessment has been gathered from the TAO and DSO up to 24 November

2014. The review has been informed by the companies’ responses to the questionnaires on historic and

forecast costs, and associated information papers and network plans. Data provided by the companies at

meetings and supplementary questions raised by CER and their consultants has also been used to inform the

analysis. For this reason, the results presented for ESBN in 2007 may differ from those presented in the 2009

report as the 2009 study was completed using the data submitted at the time.

Jacobs has reduced the 2014 fault maintenance costs by €23.4m to account for the increased cost caused by

the Darwin storm. It is Jacobs’ opinion that this is reasonable due to the atypical nature of the event as stated in

our report87.

As advised by the companies, this study assumes that data presented in the PR4 Submission Questionnaires

uses the following price bases:

2007 to 2014: Nominal

2015: 2014 prices

2015 to 2020: 2014 prices

Based on this assumption, data has been adjusted to 2007 prices using the adjustment factors shown in Table

A.1 below. All cost data presented in this study is shown in 2007 prices to allow for a like-for-like comparison

between PR2, PR3 and PR4.

Table A.1 : Inflation Adjustment Factors

Inflation Adjustments 2007 2008 2009 2010 2011 2012 2013 2014

Page 191: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 186

Inflation Adjustments 2007 2008 2009 2010 2011 2012 2013 2014

HICP Average

Annual Inflation Rate 2.87% 3.11% -1.69% -1.57% 1.17% 1.93% 0.53% 0.40%

2007 Adjustment

Factor 1.000 0.972 0.943 0.959 0.974 0.963 0.945 0.940

No further information has been used in the production of this study.

Operating and non-network capital costs for GB DNOs are reported in financial years and in Great British Pound

(GBP). To compare these costs to ESBN’s, an exchange rate has been applied to the original data. The

exchange rate used is the average exchange rate between 1 April 2007 and 31 March 2008 (i.e. the rate

prevailing in the period from which the GB DNO data is taken) according to data collected from Oanda

(http://www.oanda.com/). Table A.2 outlines the exchange rate used in this study.

Table A.2 : Exchange Rates

Exchange Rate FY2007/08

EUR/GBP 1.42

Data for the GB DNOs is from Ofgem’s ‘Electricity Distribution Cost Review 2007-2008 – Activity Costs’88 report,

and is the same data used in SKM’s 2009 PR3 benchmarking review. The Scottish DNOs (Scottish Hydro

Electric Power and SP Distribution) have been excluded from the GB DNO group as they do not manage the

132kV network in the region, and as such, do not have an equivalent EHV network to ESBN’s 110kV network.

This group of GB DNOs is consistent with the group used in SKM’s 2009 PR3 benchmarking review.

A.1 Methodology

The Office of Gas and Electricity Markets (Ofgem) has developed a number of benchmarking techniques over

the last four price control reviews for GB. Ofgem’s methodology normalises operating expenditure by using a

Composite Scale Variable (CSV). Further details for each CSV calculation developed by Ofgem can be seen in

Section A.1.4 below. For the purposes of this study, benchmarking has been undertaken using linear

regression analysis adopted by Ofgem for the GB Distribution Price Control Review 4 (DPCR4) period 2005/06

– 2009/10. The benchmarking technique used in DPCR4 was chosen as the methodology used in this study

due to two factors:

1) Availability of high quality data; and,

2) Relative benefit of sophisticated econometric techniques.

In DPCR5 (2010/11 – 2014/15) Ofgem’s approach to benchmarking became increasingly complex, using

advanced econometric methods and onerous data requirements to complete the study. To overcome these

burdens, amongst other reasons, Ofgem has restructured its approach to benchmarking for the incoming RIIO-

ED1 price control review period 2015/16 – 2022/23. The focus in RIIO-ED1 has been on total expenditure

(“totex”) using modern equivalent asset value (MEAV) and customer numbers as the normalising factors (i.e.

cost drivers). Standardised and accurate MEAV information on GB DNOs is not readily available in the public

domain and therefore was excluded as an option in this study.

A.1.1 Totex or Opex

The choice between totex (opex plus capex) and opex as the level at which a benchmark is conducted is an

issue which requires consideration of the advantages and disadvantages of each option in the circumstances it

will be applied to. A discussion between Jacobs, CER and the companies at the beginning of this consultation

period covered this issue, which led to the use of opex and opex plus NN capex as the measure to be used for

88 https://www.ofgem.gov.uk/publications-and-updates/electricity-distribution-cost-review-2007-2008

Page 192: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 187

this benchmarking study rather than totex. However for clarity, the following section presents Jacobs’ views on

its use in this study.

Network investment (i.e. capex) is largely driven by the economic climate in which the network operator

operates in (i.e. load driven) and the investment cycle of the network (asset management). Therefore capex

delivery is more sensitive to peaks and troughs of an economy as the availability of credit changes and load-

growth on the network responds to reduced demand. As a result of the global financial crisis in 2007, Europe

experienced a significant economic recession and low availability of credit to fund investments. The impact on

Ireland due to this crisis was far more severe than that seen in the UK, as shown by Figure A.1 below, which led

to the downgrading of ESBN’s capex programme during PR3. The impact this issue had on ESBN’s capex

during PR3 is evidenced by ESBN’s revised 2012 capex plan and covered in more detail in section 4 of this

report. This has led to a disparity being created between GB DNOs and ESBN investment horizons as GB DNO

capex was less affected, and the path to network upgrade has largely continued as planned.

Figure A.1 : Annual GDP Growth for Ireland and United Kingdom (2005 – 2013)89

On the other hand, opex is less correlated with changes in macroeconomic influences. The key output of opex

is to maintain and operate a safe and reliable network, which needs a minimum level of expenditure to achieve

on an on-going basis, exclusive of any external factors such as economic growth. Figure A.2 below

demonstrates this relationship between opex and capex using the DSO’s reported90 figures. As expected, opex

is relatively stable over the nine year period however capex is much more volatile, due to the reasons

mentioned above. The standard deviation for opex in this sample was €67.4m whereas the standard deviation

for capex was €122.5m. The sample period is largest possible based on the historical data provided by ESBN.

Jacobs notes that ESBN’s consultants propose using average capex over a number of years to even out the

peaks and troughs. Jacobs agrees that this technique may lead to a more useful measure of capex over the

period, however due to the long-term impact of such a large economic and financial crisis, capex would need to

be examined across multiple review periods and therefore render the analysis inadequate for the purposes of

this study.

Therefore to mitigate the issue of macroeconomic impacts, including credit availability, Jacobs has continued

with the approach of benchmarking at an opex and non-network capex level.

89 Source: World Bank 90 PR4 Forecast Questionnaire Submission; Gross capex is line 74 of Table 6.3, Opex is line 72 of Table 5.1, NN capex is line 160 of Table 6.1

Page 193: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 188

Figure A.2 : DSO Capex, opex and NN Capex (2006 – 2015, nominal prices)

A.1.2 Data Choice

The data used to derive the relationship between network size and expenditure is based on GB DNO data from

2007/08. Although there are more recent examples of high-level opex data91 available in the public domain, this

is the most recent set of publicly available data with the level of granularity required for normalising to produce a

like for like comparison to ESBN expenditure.

Public data for RIIO-ED1 determinations in GB has only been provided as totex and therefore is not suitable for

comparison opex. ESBN’s consultants have suggested using RIIO-ED1 totex data and adjusting this data using

a straight line factor of 52% derived from historic actuals. As stated above, capex is much more volatile than

opex and therefore it is Jacobs’ opinion that applying a single adjustment factor across all years would be

negligent and unreasonable.

This point is emphasised by Figure A.3 below which shows DSO opex and capex as a percentage of totex

between 2006 and 2015, as reported in the forecast questionnaire submission. The yellow line represents totex

across the period. The figure demonstrates that opex has varied between 50.2% in 2006, to a peak of 74.6% in

2012 before dropping to 64.7% in the forecasted 2015 period. Observing the totex line shows how the

relationship between opex as a percentage of totex and totex is, as expected, inversely proportional. The

implications of this are that when a percentage factor is applied to a volatile totex figure, opex will be perceived

as relatively more volatile than it actually is.

91 Ofgem (2012), Electricity Distribution Annual Report for 2010-11, <https://www.ofgem.gov.uk/ofgem-

Page 194: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 189

Figure A.3 : Opex and Capex as a Percentage of Totex (excludes non-network capex)

A.1.3 Benchmarking Technique

The benchmarking technique used in this study is Corrected Ordinary Least Squares (COLS). COLS is an

extension of the regular ordinary least squares (OLS) technique. Regular OLS estimates the average

performance of the group of firms by fitting a line of minimum deviation from the average in graph of Opex

versus the CSV (as described in Section A.1.4), whereas COLS shifts the OLS benchmarking line from the

average towards the best performing, or more efficient, firms. The slope of the benchmarking line remains the

same, or in other words, the relationship between the scalar dependent variable, in this case costs, and the

explanatory variable, in this case the CSV, is held constant.

For the purpose of this study, two COLS benchmarks, in addition to the original OLS (i.e. GB Average), have

been developed based on the ‘upper quartile’ and ‘most efficient’ of the GB DNOs. As the benchmarks are only

to derive the relationship between expenditure and network size in this study, the relative position of ESBN to all

three lines in irrelevant. Only a single line has been used to measure the relative change of ESBN against itself.

In this case the line used is the upper quartile since this line demonstrates ESBN’s performance with the most

clarity. The other benchmarks have been kept in the graphs to aid the visual interpretation of the changes

between price review periods.

A.1.4 Cost Drivers Used by Ofgem in DPCR3, DPCR4, DPCR5 and RIIO-ED1

As discussed above Ofgem have used a number of different cost drivers to benchmark GB DNOs in the past 15

years. The calculation of each of these costs is presented below, including the CSV for DPCR 4 which was

used in this study.

Computation of the CSV for DPCR 3:

𝐶𝑆𝑉𝐷𝑃𝐶𝑅3 = (1 +𝑑𝑈

𝑈+

𝑑𝐿

𝐿) × 𝐶

Where;

dU

U = Proportional deviation in units distributed from the overall average

dL

L = Proportional deviation in network length from the overall average

Page 195: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 190

C = Customer Numbers (millions)

Computation of the CSV for DPCR 4:

𝐶𝑆𝑉𝐷𝑃𝐶𝑅4 = 𝐴0.5 × 𝐵0.25 × 𝐶0.25

Where;

A = Length of Network (‘000 km)

B = Units Distributed before losses (GWh)

C = Customer Numbers (millions)

Computation of the CSV for DPCR 5:

Ofgem adopted more direct modelling of individual direct and indirect costs against specific drivers such as

number of faults and network length. This is described in ‘Ofgem DPCR5 Initial Proposals 3 Allowed

Revenue and Cost Assessment’ and the associated appendix ‘Ofgem DPCR5 Initial Proposals 3 Allowed

Revenue and Cost Assessment Appendix’.

Computation of the CSV for RIIO-ED1:

𝐶𝑆𝑉𝑅𝐼𝐼𝑂−𝐸𝐷1 = 𝑀𝐸𝐴𝑉0.87 × 𝐶0.13

Where;

MEAV = Modern Equivalent Asset Value

C = Customer Numbers (millions)

A.1.5 Normalisation of ESBN and GB DNO Data

GB DNO and ESBN’s costs must be normalised to ensure that only comparable activities and costs are

benchmarked and to take account of differences in capitalisation policies. Table A.3 presents ESBN’s

Comparable Controllable Operating Expenditure and Non-Network Capital Expenditure for the PR4 period.

Table A.3 : ESBN Comparable Controllable Operating Expenditure and Non-Network Capital Expenditure (€m, 2014 prices)

Activity 2016 2017 2018 2019 2020

DSO TAO DSO TAO DSO TAO DSO TAO DSO TAO

DSO:

System control 16.4 16.6 16.7 16.7 16.7

Planned maintenance 64.9 67.7 66 66.7 66

Fault maintenance 33.1 33.5 33.3 33.3 33.5

Other 0 0 0 0 0

Asset Management 14 14.2 14.4 14.7 15

Area Operations 8.8 8.9 8.9 8.9 8.9

Customer relations 3.2 2.4 2.5 2.8 2.8

DUoS Billing 1.4 1.4 1.4 1.4 1.5

MRSO 1.8 1.8 1.9 1.8 1.8

Market Opening 9.2 9.1 9.5 9.5 9.6

Page 196: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 191

Activity 2016 2017 2018 2019 2020

DSO TAO DSO TAO DSO TAO DSO TAO DSO TAO

Insurance 3.8 3.8 3.7 3.7 3.7

Pension 1.3 1.4 1.4 1.5 1.5

Corporate Charges 8.4 8.4 8.4 8.4 8.4

Safety 7.7 7.7 7.8 7.8 7.8

Environmental 3.7 3.7 3.7 3.7 3.7

Telecoms 13.2 13.5 13.6 13.7 13.8

TAO/TSO:

Transmission

Operations 1.3 1.3 1.3 1.3 1.3

Transmission Repairs

And Maintenance 9.5 9.5 9.5 9.5 9.5

Transmission

Retirements 0 0 0 0 0

Asset Management 0.5 0.5 0.5 0.6 0.6

Corporate Charges 1.2 1.2 1.2 1.2 1.2

Insurance 0.3 0.3 0.3 0.3 0.3

Pension 0.2 0.2 0.2 0.2 0.2

Health & Safety 0 0 0 0 0

Telecom Fees 0.7 0.7 0.7 0.7 0.8

Total Controllable

Comparable Opex 191 13.8 194.3 13.9 193.3 13.9 194.6 13.9 194.6 14

DSO + 110 kV TAO

Controllable Opex 204.8 208.2 207.2 208.5 208.6

DSO:

Total Head Office 11.9 11.9 11.9 11.9 11.9

Total Distribution Asset

Management 3.9 4.1 4.7 4.1 3.9

Total Control/Operations

(EMS) 0 0 0 0.6 0

Total IT Infrastructure 0 0 0 0 0

Total Enterprise

Applications 13.8 8.3 4.8 6.7 3.8

Total Telecoms 11.3 12.6 11.6 9.3 9.1

Total Non-network Capex 40.9 36.9 33 32.6 28.8 -

Total Controllable Opex +

NN Capex 231.9 13.8 231.2 13.9 226.3 13.9 227.2 13.9 223.4 14

DSO + 110 kV TAO

Controllable Opex + NN

Capex

245.7 245.1 240.2 241.1 237.4

ESBN distribution and transmission costs for 2007 to 2014 are shown in Table A.4. These costs are shown in

outturn prices, except for 2015 which is reported in 2014 prices. Table A.5 presents the GB (excluding Scottish

DNOs) Distribution Company Activity Costs in 2007/08 nominal prices. DNOs report activity costs as direct

costs only and these costs have been adjusted to include appropriate indirect costs based on information from

Ofgem’s rules for cost reporting. GB DNOs capitalise more costs than ESBN, particularly fault costs and a

Page 197: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 192

proportion of support activities. ESBN has retained a more traditional capitalisation policy and we have

confirmed these practices through a questionnaire.

ESBN report operating costs on an activity basis, and these costs include indirect costs fully absorbed into the

main activity headings. GB DNO’s costs are normalised to the DSO’s costs taking account of the following.

DNO capitalise 23.5% of operating costs but these normally capitalised costs are retained in operating

costs in this analysis as these costs are not capitalised by ESBN.

DNOs would capitalise part of System Control costs and Health and safety costs and these are all included

in operating costs, since such costs do not appear to be capitalised by ESBN.

ESBN costs exclude line diversions as these are capitalised in GB.

All ESBN and DNO metering costs are excluded from the benchmarking. ESBN has full meter operator

obligations, whereas the DNO remaining meter operations are separately regulated.

DNO call centres take mainly no supply calls whereas ESBN call centres handle meter reading calls and

no supply calls. Customer Call Centre costs are therefore excluded from benchmarking. Other ESBN and

DNO customer service costs are included.

ESBN and DNOs both have responsibility for DUoS billing and meter point registration so DUoS and

MRSO costs are included.

ESBN market systems IT costs are included at 25% of total costs, which is an estimate of those IT costs

supporting the MRSO meter registration activity, which is the proportion adopted by DSO in its

benchmarking.

Corporate costs, Safety, Environment, Insurance costs and Pension administration costs are included.

ESI/licence fees, network rates and commercial excluded services costs are excluded from benchmarking.

ESBN 110 kV costs (transmission and distribution) are equivalent to DNO 132 kV costs. TAO 110 kV fault

and planned maintenance costs are included. Other transmission operating costs relate to 400 kV 220 kV

and 110 kV costs and are included in proportion to the 110 kV maintenance costs.

Table A.6 and Table A.7 present ESBNs historic and forecast network characteristics respectively. These

characteristics are required to calculate the DPCR4 CSV for each year.

Page 198: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 193

Table A.4 : ESBN Comparable Controllable Operating Expenditure and Non-network Capital Expenditure (€m outturn prices, except 2015 as 2014 prices)

Activity 2007 2008 2009 2010 2011 2012 2013 2014 2015

DSO TAO DSO TAO DSO TAO DSO TAO DSO TAO DSO TAO DSO TAO DSO TAO DSO TAO

DSO:

System control 18.6 19.7 16.4 16.1 16.1 13.8 15.5 16.0 15.8

Planned maintenance 44.6 48.6 47.8 39.1 45.8 54.1 43.6 49.9 45.8

Fault maintenance 44.5 37.6 39.4 38.8 31.5 29.0 34.8 38.7* 29.7

Other 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Asset Management 12.5 10.8 12.6 11.2 11.3 12.8 13.9 14.1 14.0

Area Operations 10.4 11.1 8.7 9.8 9.6 8.1 8.5 8.3 8.0

Customer relations 2.4 2.1 1.5 0.6 0.3 0.4 0.6 0.4 0.5

DUoS Billing 1.3 1.7 1.3 1.2 1.3 1.3 1.1 1.3 1.3

MRSO 1.3 1.5 1.1 1.4 1.4 1.2 1.5 1.8 1.8

Market Opening 13.2 14.3 12.0 10.3 8.8 6.9 6.8 7.3 7.6

Insurance 4.2 3.6 1.9 3.2 1.8 5.1 3.5 3.5 3.5

Pension 1.1 2.5 2.5 3.2 2.7 1.7 2.0 1.8 1.4

Corporate Charges 12.0 13.1 11.9 10.9 9.2 8.8 8.2 8.7 9.2

Safety 3.8 3.3 3.0 2.0 1.7 1.8 2.5 4.0 3.9

Environmental 0.4 0.2 0.7 1.7 1.5 1.2 1.3 0.7 0.7

Telecoms 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

TAO/TSO:

Transmission Operations 0.5 0.9 1.4 0.7 1.5 1.6 1.5 1.3 1.3

Transmission Repairs And Maintenance 4.0 6.1 7.2 6.1 8.9 9.0 8.0 7.8 8.0

Transmission Retirements 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Asset Management 0.2 0.3 0.5 0.3 0.4 0.4 0.5 0.5 0.5

Corporate Charges 0.8 1.4 1.6 1.6 1.1 1.0 0.9 0.9 0.9

Insurance 0.1 0.1 0.4 0.3 0.1 0.2 0.1 0.2 0.2

Pension 0.1 0.0 0.0 0.0 0.3 0.2 0.2 0.2 0.1

Health & Safety 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Telecom Fees 0.3 0.6 1.0 2.9 0.7 0.7 0.8 0.8 0.8

Total Controllable Comparable Opex 170.3 6.0 170.1 9.4 160.7 12.1 149.5 12.0 142.8 13.0 146.3 13.1 143.7 12.1 156.8 11.8 143.3 11.9

DSO + 110 kV TAO Controllable Opex 176.2 179.6 172.9 161.4 155.8 159.4 155.8 168.6 155.2

DSO:

Total Head Office 15.2 19.2 17.6 15.4 7.8 4.3 9.1 11.5 12.4

Total Distribution Asset Management 9.4 14.4 6.7 0.8 - 0.7 0.6 1.9 3.3

Total Control/Operations (EMS) 2.4 4.2 9.0 3.7 0.2 3.0 4.6 3.1 1.2

Total IT Infrastructure - - - - 0.2 0.2 0.3 0.5 0.2

Total Enterprise Applications 6.0 2.2 1.1 4.7 7.1 5.1 3.1 2.3 3.6

Total Telecoms 1.9 0.9 1.0 0.2 7.0 6.1 4.4 5.3 8.5

Total Non-network Capex 34.9 - 40.9 - 35.3 - 24.9 - 22.3 - 19.4 - 22.1 - 24.6 - 29.2 -

Total Controllable Opex + NN Capex 205.2 6.0 211.0 9.4 196.0 12.1 174.3 12.0 165.1 13.0 165.7 13.1 165.8 12.1 181.4 11.8 172.4 11.9

DSO + 110 kV TAO Controllable Opex + NN Capex

211.1 220.5 208.2 186.3 178.1 178.8 177.9 193.2 184.3

*€23.4m removed for Darwin Storm repairs

Page 199: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 194

Table A.5 : GB (excluding Scottish DNOs) Distribution Company Activity Costs (£m 2007/08 nominal prices)

DNO A DNO B DNO C DNO D DNO E DNO F DNO G DNO H DNO I DNO J DNO K DNO L

Direct Activities 142 154 102 88 105 53 88 110 113 194 140 104

Load Related New Connections Net 11 46 10 12 2 -1 1 18 8 35 36 5

Non load related non fault and replacement 87 63 64 43 55 32 45 51 63 80 52 68

Non operational capex 2 2 4 4 4 3 15 8 7 19 8 3

Faults 24 27 16 17 29 8 14 23 22 40 23 13

Inspection and Maintenance 12 12 5 5 7 6 7 10 8 12 14 6

Tree Cutting 5 3 2 6 7 4 5 0 5 8 7 8

Network Policy and R & D 1 1 1 1 1 1 1 0 0 0 0 1

Indirect Activities 76 67 71 43 50 41 49 67 60 101 79 56

Network Design and Engineering 6 5 9 4 4 4 5 7 4 7 3 6

Project Management 4 2 4 2 4 3 5 6 4 8 7 5

Engineering Management and Clerical Support 23 17 15 9 11 7 10 15 14 27 20 11

Control Centre 4 4 3 2 3 2 2 3 3 5 3 2

System mapping and cartography 2 2 1 1 2 1 1 2 1 2 1 1

Customer Call Centre inc compensation claims 1 1 1 1 2 1 1 1 2 3 3 1

Stores and procurement 1 2 1 1 1 1 1 2 2 3 2 1

Vehicles and transport 5 6 2 3 3 3 4 3 4 7 12 5

IT and telecoms 11 10 13 7 7 7 7 9 8 12 8 8

Property management 6 5 7 2 3 2 3 6 6 8 4 4

HR and non op training 1 1 3 2 2 1 1 3 3 4 3 2

Health and Safety and Op training 2 2 1 1 1 1 1 1 1 2 2 2

Finance and Regulation 8 8 9 6 6 6 6 8 7 11 9 6

CEO Group Legal secretary and community 2 2 2 2 1 2 2 1 1 2 2 2

Total Activity Costs 80 92 103 88 102 69 106 84 72 118 207 103

Atypical cash costs 2 1 15 0 5 4 7 2 3 3 3 1

Pension deficit payments 8 10 0 22 6 13 21 15 16 4 27 0

Metering (separate price control) 1 1 1 3 5 2 6 2 3 6 13 12

Excluded services and de minimus activities 12 10 15 13 11 9 25 45 10 31 27 9

Distributed Generation less contributions 0 0 0 0 0 0 0 0 0 0 0 1

IFIs (Innovation Incentives) 1 1 1 0 1 0 0 2 1 2 1 0

Disallowed related party margins -5 4 12 3 2 0 1 0 0 1 4 10

Statutory depreciation 39 42 59 32 47 25 34 42 40 56 68 36

Network Rates 20 27 17 14 18 15 18 23 10 26 38 16

Transmission Exit Charges 8 4 9 5 10 4 5 12 8 9 10 12

Pension deficit payments - related parties -8 -10 0 0 0 0 0 0 0 0 -27 0

Non activity costs and reconciliation 2 2 -26 -4 -3 -3 -11 -59 -19 -20 43 6

Total annual opex and capex per Reg Accounts 298 313 276 219 257 163 243 261 245 413 426 263

Page 200: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 195

Table A.6 : Historic Network Characteristics for ESBN

Characteristic ESBN 2007 ESBN 2009 ESBN 2010 ESBN 2011 ESBN 2012 ESBN 2013 ESBN 2014 ESBN 2015

Number of Customers 2,151,285 2,227,521 2,237,232 2,239,507 2,237,138 2,233,276 2,237,097 2,245,755

Length of Circuit (km) 162,203 167,498 168,970 170,063 171,128 171,858 171,997 172,376

Length of Circuit (m/customer) 75.4 75.2 75.5 75.9 76.5 77.0 76.9 76.8

Units Distributed (GWh) 23,456.6 22,953.4 22,927.7 22,578.4 22,323.6 22,113.4 22,503.5 22,746.3

Units/Customer 10.9 10.3 10.2 10.1 10.0 9.9 10.1 10.1

CSV Ofgem DPCR4 33.9 34.6 34.8 34.8 34.8 34.8 34.9 35.1

Table A.7 : Future Network Characteristics for ESBN

Characteristic ESBN 2016 ESBN 2017 ESBN 2018 ESBN 2019 ESBN 2020

Number of Customers 2,258,679 2,275,282 2,296,538 2,322,684 2,354,321

Length of Circuit (km) 179,250.7 180,484.2 181,810.6 183,268.8 184,861.2

Length of Circuit (km/customer) 0.0794 0.0793 0.0792 0.0789 0.0785

Units Distributed (GWh) 22,669.2 23,051.6 23,523.1 23,826.3 24,241.0

Units/Customer 10.037 10.131 10.243 10.258 10.296

CSV Ofgem DPCR4 35.81 36.15 36.56 36.92 37.37

Page 201: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 196

A.1.6 Treatment of TAO and TSO Costs

The TAO has provided standalone planned and fault maintenance costs for the 110 kV network which (as

described above) is considered equivalent to the GB DNO’s 132 kV network. These costs have been included in

the operating costs benchmarking study and then used to proportion other TAO and TSO costs. Other

transmission operating costs are proportioned based on the ratio between the 110 kV maintenance costs and

the total maintenance costs for the 110 kV, 220 kV and 400 kV networks collectively. The Opex Ratio of costs

attributable to the 110 kV portion of the network is calculated as:

𝑂𝑟𝑎𝑡𝑖𝑜 = 𝑀110𝑘𝑉

𝑀𝑇𝐴𝑂

Where;

Oratio = Ratio of 110 kV operating costs to entire transmission network operating costs

M110kV = Sum of Planned Maintenance and Fault Maintenance on the 110kV Network

MTAO = Sum of Planned Maintenance and Fault Maintenance for the whole transmission

network (i.e. 110 kV, 220 kV and 400 kV)

To proportion a TAO operating cost, the Opex Ratio is then applied as follows;

𝑂𝑝𝑒𝑥 𝐶𝑜𝑠𝑡 𝐶𝑎𝑡 ′𝑋′110𝑘𝑉 = 𝑂𝑝𝑒𝑥 𝐶𝑜𝑠𝑡 𝐶𝑎𝑡 ′𝑋′𝑇𝐴𝑂 × 𝑂𝑟𝑎𝑡𝑖𝑜

Where;

Opex Cost Cat ‘ X’110kV = The portion of the TAO/TSO cost category ‘X’ attributed to the

110kV network

Opex Cost Cat ‘X’TAO = The total cost for transmission network operating cost category ‘X’

A detailed summary of how each cost category presented in the distribution and transmission questionnaires

has been treated is provide below in Table A.8.

Table A.8 : Treatment of ESBN Distribution and Transmission Cost Categories

Company Cost Category Cost Treatment

DSO Capital Driven Opex Non Repayable Line Diversions Omitted

Dismantling Omitted

Network Operations &

Maintenance

System control Controllable and included

Planned maintenance Controllable and included

Fault maintenance Controllable and included

Asset Management Asset Management Controllable and included

Forestry & Wayleaves Controllable and included

Metering Meter Reading Omitted

QH Data Omitted

Data Aggregation Omitted

Customer Meter Operation Omitted

Keypad / Token Meter Omitted

Smart Metering Opex Smart Metering Opex No costs provided

Customer Service Call Centre Controllable and included

Page 202: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 197

Area Operations Controllable and included

Customer Relations Controllable and included

Provision Of Information Duos Billing & Accounts

Receivable

Controllable and included

MRSO Controllable and included

Market Opening Omitted

Commercial External repayable: Omitted

Transaction charges Omitted

3rd party damages Omitted

Supply repayable Omitted

Other inter ESB Omitted

Other external repayable Omitted

Other commercial Omitted

Sustainability & R & D Sustainability Controllable and included

R & D Controllable and included

Other Network Rates Non-controllable

Cer Levy Non-controllable

Company Wide Costs Omitted

Corporate Charges & Corporate

Affairs

Controllable and included

Insurance Controllable and included

Legal Omitted

Pension Controllable and included

Environmental Controllable and included

Misc Omitted

Health & Safety Controllable and included

Telecoms Controllable and proportioned at 25%

Depreciation Omitted

PSO Omitted

Restructuring costs Omitted

Market Support Costs Omitted

Manufacturing Omitted

Settlement Difference Omitted

Prior Year Adj Omitted

Pension Deficit Charge Omitted

Unabsorbed Overhead Omitted

Capitalise Pension Adjustment Omitted

Misc Omitted

TAO Transmission Operations Transmission Operations Proportioned with respect to 110kV

PM and FM

Transmission Repairs And

Maintenance

Planned Maintenance (PM) 110kV proportion included

Fault Maintenance (FM) 110kV proportion included

Page 203: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 198

Transmission Retirements Transmission Retirements Omitted

Asset Management Asset Management Proportioned with respect to 110kV

PM and FM

Other Rates Omitted

Cer Levy Omitted

Company Wide Costs Omitted

Corporate Charges Proportioned with respect to 110kV

PM and FM

Insurance Proportioned with respect to 110kV

PM and FM

Legal Omitted

Pension Proportioned with respect to 110kV

PM and FM

Health & Safety Proportioned with respect to 110kV

PM and FM

Misc Omitted

Depreciation Omitted

Professional Fees Omitted

Telecom Fees Proportioned with respect to 110kV

PM and FM

A.2 Interim Results

A top-down benchmarking study has been undertaken to examine ESBN’s performance against GB DNOs in

2007/08 with respect to operating expenditure and non-network capital expenditure. By using the same data

from SKM’s 2009 benchmarking exercise, ESBN’s improvement since the previous review can be examined

and measured. The purpose was to validate the benchmarking at a known point and effectively examine the

movement of opex costs by ESBN against that benchmarked position.

Results of the interim benchmarking study can be seen in Section A.2.1 of this report. An initial evaluation of

these results is presented in Section A.2.2.

A.2.1 Results

Two COLS models have been run to examine ESBN’s performance during PR3 and analyse their forecast

spend in PR4 relative to their position at the last price review period. To do this a benchmark has been derived

in each model from GB DNO data which explains the relationship between network size and expenditure. The

first model uses ESBN’s controllable and comparable opex, as described above, whereas the second model

also includes non-network capex. Table A.9 shows the correlation coefficient, or R2, for each of the linear

regression models. As can be seen, both models display a high correlation coefficient, indicating that the

DPCR4 CSV is a good descriptor of each of the cost sets.

It is reasonable to include non-network capex because these costs cover business support costs and are often

depreciated over short timeframes. Different companies have different approaches to managing these types of

costs, for example one company may purchase a fleet of vehicles, whereas another might lease the vehicles.

Therefore excluding these costs from the analysis entirely would mean incorrectly evaluating the total operating

costs required to deliver ESBN’s services to its customers.

Page 204: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 199

Table A.9 : Linear Regression Specification

Dependent Variable Independent Variable Correlation (R2)

Comparable & Controllable Opex DPCR 4 CSV 0.92

Comparable & Controllable Opex + NN

Capex DPCR 4 CSV 0.88

Figure A.4 and Figure A.5 demonstrate the results of the controllable opex benchmarking study. In each figure

the GB Average, GB Upper Quartile and GB Most Efficient benchmarks can be seen, along with where ESBN is

placed compared to these lines. Figure A.4 shows the overall placement of ESBN with respect to the GB DNOs

whereas Figure A.5 is a close up of the ESBN data points.

As can be seen from the overall chart, ESBN’s data points are located to the far right and clustered close

together. This is to be expected due to ESBN’s large network compared to GB DNOs, and relatively small

changes in opex compared to the range of the sample.

Figure A.6 and Figure A.7 demonstrate the results of the controllable opex and non-network capex

benchmarking study. Again, the GB Average, GB Upper Quartile and GB Most Efficient benchmarks can be

seen in each figure, with Figure A.7 providing a close up view of EBSN’s movements during PR3. Non-network

capex is often less consistent than opex and hence ESBN’s results vary more in this study.

Figure A.4 : Regression of DSO & 110kV TAO Controllable Opex versus GB DNOs – Overview (€m, 2007 prices)

Page 205: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 200

Figure A.5 : Regression of DSO & 110kV TAO Controllable Opex versus GB DNOs – ESBN Detail (€m, 2007 prices)

Figure A.6 : regression of DSO & 110kV TAO Controllable opex + Non-Network Capex versus GB DNOs – Overview (€m, 2007

prices)

Page 206: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 201

Figure A.7 : Regression of DSO & 110kV TAO Controllable Opex + Non-Network Capex versus GB DNOs – ESBN Details (€m,

2007 prices)

A.2.2 Consideration of the results

Benchmarking studies are dependent on the assumptions and data sources used and therefore should be

considered in association with other detailed qualitative analysis. This study was intended to inform and support

the analysis performed in other aspects of the price control review being undertaken. As previously stated, this

exercise aimed to examine the relative efficiency of ESBN against itself, using GB DNO 2007/08 data as a

reference point.

The reference data used in this study is from 2007/08 and as such is seven years old. Any conclusions drawn

from this study should note that the reference set has been used to derive an expenditure versus cost-drivers

relationship to account for the organic increases in costs due to a network expanding. The reference set should

not be used as a direct comparison between ESBN and GB DNOs of today.

Results from this study only examine the reported costs of the companies and do not take into account how well

ESBN delivered their services. Consideration of how efficiently ESBN provided the services required, such as

customer care, reliability and safety, is outside the scope of this benchmarking analysis. Hence a reduction in

expenditure should be examined in conjunction with broader outputs to determine a final position on the overall

efficiency of the companies during PR3.

A detailed assessment of ESBN’s performance in each of the models is discussed below. The GB upper

quartile benchmark has been used to represent ESBN’s change throughout the examined period.

A.2.2.1 Controllable Operating Expenditure

In 2007 ESBN’s annual opex was €1.2 million above the GB DNO average and €9.3 million from the upper

quartile frontier. This suggests that ESBN was performing just below average of the GB DNOs at this time.

Page 207: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 202

During PR2, ESBN has shown significant efficiency improvements in relation to operating expenditure

compared to its 2007 position. By 2010 ESBN’s annual opex was €16.1 million below upper quartile frontier. By

this time ESBN had also surpassed the most efficient GB DNO in 2007/08.

In 2014 ESBN moderately regressed, positioning itself only €8.8 million below the upper quartile frontier. This is

despite the Darwin storm costs being excluded from the analysis.

Between 2007 and 2015, ESBN has shown an overall efficiency gain, with respect to its own opex costs of,

16.5%. However under the proposed opex costs for PR4, this efficiency gain would be completely offset and by

2020 and a 1.1% efficiency loss will be observed.

A summary of the ESBNs historic controllable opex performance with respect to the GB DNO’s is summarised

in Table A.10 below.

Table A.10 : Historical ESBN Controllable Opex Summary

Opex Performance 2007 2010 2011 2012 2013 2014 2015

Distance from GB Upper Quartile (€m

2007) 9.3 -16.1 -19.1 -17.3 -24.0 -14.9 -20.6

Table A.11 presents ESBN’s proposed opex for PR4 compared to each benchmark. It is evident from these

results that the proposed PR4 opex is much greater than allowances in previous years or periods.

Table A.11 : ESBN PR4 Proposal Summary

Opex Performance 2016 2017 2018 2019 2020

Distance from GB Upper Quartile (€m

2007) 16.7 18.2 15.4 14.9 12.8

Figure A.8 : Controllable Opex Summary

Page 208: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 203

Table A.12 shows the relative performance of ESBN during each review period. Each period is calculated as the arithmetic

average of the years in that period. PR3/4 is the average of 2011 – 2020 period. As shown, the average normalised spend was

significantly lower in PR3 compared to other periods. However the average outlay across the combined PR3 and proposed

PR4 period is only €1.79m below upper quartile frontier. Table A.12 : ESBN Opex Performance Summary by Period

Opex Performance PR2 PR3 PR4 PR3/4

Distance from GB Upper Quartile

(€m 2007) -3.23 -19.18 15.59 -1.79

A.2.2.2 Controllable Operating Expenditure and Non-network Capital Expenditure

In 2007 ESBN’s annual opex and non network capex was €19.3 million above the GB DNO average and €22.9

million from the upper quartile frontier. This suggests that in efficiency terms ESBN was performing well below

average against GB DNOs at that time.

Similarly to the controllable opex study, ESBN has shown significant improvement during PR2, such that by

2010 ESBN’s annual opex was €14.1 million below the upper quartile frontier. In 2011 ESBN had reached the

same level of efficiency as the most efficient GB DNO in 2007/08.

ESBN continued to improve efficiency during the first three years of PR3, however has regressed from this

position in the last two years of the period.

Between 2007 and 2015, ESBN has shown an overall efficiency gain, with respect to its own opex and non-

network capex costs, of 18.0%. However under the proposed opex and non-network capex costs, this efficiency

gain would be reduced to 4.0% by 2020.

A summary of the ESBNs historic controllable opex performance with respect to the GB DNO’s is summarised

in Table A.13 below.

Table A.13 : Historical ESBN Controllable Opex and Non-Network Capex Summary

Opex + NN Capex Performance 2007 2010 2011 2012 2013 2014 2015

Distance from GB Upper Quartile

(€m 2007) 22.9 -14.1 -19.2 -20.5 -25.0 -13.9 -15.5

Table A.14 presents ESBN’s proposed opex and non-network capex for PR4 compared to each benchmark. It is

evident from these results that the proposed PR4 opex and non-network capex is far greater than allowances in

previous years.

Table A.14 : ESBN PR4 Proposal Summary

Opex + NN Capex Performance 2016 2017 2018 2019 2020

Distance from GB Upper Quartile

(€m 2007) 32.7 30.4 23.6 22.5 16.7

Page 209: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 204

Figure A.9 : Controllable Opex plus Non-Network Capex Summary

Table A.15 shows the relative performance of ESBN during each review period. Each period is calculated as the

arithmetic average of the years in that period. PR3/4 is the average of 2011 – 2020 period. Similarly to opex,

the average normalised spend was significantly lower in PR3 compared to other periods.

Table A.15 : ESBN Opex and Non-Network Capex Performance Summary by Period

Opex + NN Capex Performance PR2 PR3 PR4 PR3/4

Distance from GB Upper Quartile

(€m 2007) 8.06 -18.81 25.19 3.19

A.2.3 Conclusions

It should be noted that at the initial kick off meetings between ESBN, CER and the consultants in discussions on

the approach to benchmarking it was agreed that the approach would be the one taken within this report using

opex and non network capex and that the Totex approach used by Ofgem in RIIO would be inappropriate. In

response to this report ESBN has submitted reports proposing the Totex approach would demonstrate a more

positive view of efficiency for ESBN. We would accept that there are flaws to both the approach taken and the

use of Totex in this instance. The economic climate throughout PR3 impacted on the availability of investment

funds, and in both capex and opex there were severe restrictions resulting in expenditure being significantly

reduced. There has then been a change during the end of 2014 through 2015, flowing through into PR4 where

expenditure has increased significantly.

This study aimed to investigate the relative efficiency change of ESBN during PR3 with respect to operational

and non-network capital expenditure against their position in PR2. Following this analysis, the study has used

these results to examine ESBN’s proposed PR4 costs at a high-level, which can be used to supplement more

detailed findings in other Jacobs reports.

It should be kept in mind that this report only examines the cost effectiveness of ESBN and does not attempt to

determine the overall efficiency of ESBN with respect to other factors such as network reliability, customer

service quality, safety and sustainability. In other reports prepared for the CER, Jacobs demonstrates how a

number of these factors have been affected by a lack of expenditure.

Due to the difficulties in obtaining up to date data of GB expenditure with the appropriate level of detail, the

implications of choosing between opex and totex as the level of benchmark and the unprecedented economic

Page 210: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 205

climate observed in PR3 leading to disparity between GB and Ireland, Jacobs is unable to convincingly

conclude that ESBN’s performance during PR3 was either efficient or inefficient. The results of the study show

that ESBN was able to reduce their opex and non-network capex during PR3 relative to their network size;

however Jacobs is unable to distinguish between improvements in efficiency, lack of expenditure due to

external factors such as credit availability or deferred spending due to downward pressure on profits margins as

a result of poor economic factors in Ireland.

The proposed PR4 forecast opex is, on average, €34.77m p.a. higher than PR3 for a network of equivalent size.

Similarly, opex plus NN capex is, on average, €44.0m p.a. higher than PR3 for a network of equivalent size.

Jacobs acknowledges that distribution networks are currently undergoing rapid changes due to advances in

smart technology, uptake of electric cars, the wide spread deployment of intermittent renewable generation and

the increase in distributed generation however we believe that the magnitude of these increases are unjustified.

As noted earlier, opex generally remains more consistent than capex and therefore these large changes are out

of the ordinary.

Further to this the proposed PR4 levels would return ESBN to expenditure levels well above those of pre-global

financial crisis levels. While this is understandable for capex related spend, due to improving the network and

ensuring it is ready for the changes that are expected over the coming decade, the change in opex should be

significantly less impacted by these changes.

It is Jacobs’ opinion that, based on the results of this benchmarking study, non-network capex has suffered

large deferred spending cuts rather than efficiency gains. For example, ESBN was able to cut costs to €19.4m

by 2012 however now propose a 2016 non-network capex of €40.9m. In addition, the average non-network

capex during PR3 was €23.5m whereas the proposed PR4 non-network capex is €34.4m, further demonstrating

that spending has been postponed from PR3 to PR4. This conclusion is supported by the analysis described in

sections 3 and 5 of this report.

ESBN have presented a different approach to benchmarking in consultationwith Frontier Economics using a

Totex approach in which they derive the opex value from a fixed percentage of the Totex(52%) and apply this to

conclude that GB DNO’s opex costs have increased by 30% between 2007/8 and 2013/14, and using this

increase to reflect on the ESBN opex over the same period. The driver for Opex is the scale of the network and

costs are predominantly dictated by O&M, Asset Management, Metering, Customer Service and Provision of

Information, at over 85 % of controllable opex in PR3, In evaluating this within ESBN, we have determined that

opex has varied between 50.2% in 2006, to a peak of 74.6% in 2012 before dropping to 64.7% in the forecasted

2015 period. Observing the totex line shows how the relationship between opex as a percentage of totex and

totex is, as expected, inversely proportional. The implications of this are that when a percentage factor is

applied to a volatile totex figure, opex will be perceived as relatively more volatile than it actually is.

Jacobs recommends that further consultation between stakeholders is undertaken with respect to benchmarking

prior to the next price review period. Given the current state of European economies, totex benchmarking could

constitute a more appropriate measure in the future. This would also enable a wider range of data to be

collected and therefore more direct comparisons to be completed, providing more conclusive and useful

analysis. We would however comment that the detailed bottom up approach undertaken in section 2 and 3 of

this report is the basis of the proposed allowances due to the uncertainties and assumptions used throughout

the benchmarking process.

Page 211: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 206

Appendix B. Incentives

B.1 Introduction

As part of PR4, CER required Jacobs to:

“…comment on the incentives that were placed on the TAO, TSO & DSO businesses over the period 2010-

2015 and comment on their suitability for implementation over the period 2016-2020. Recommendations

should also be made on the removal or introduction of any incentive mechanism. This point relates to

incentives regarding quality of supply, Customer Minutes Lost, Customer Interruptions, Loss Adjustment

Factors, et cetera, rather than the broader incentives placed on the utilities by the form of the revenue

control. In addition, provide advice on potential new incentives for infrastructure delivery.”

This appendix sets out our comments in relation to the DSO, with respect to the above requirement.

B.2 Objectives

As part of the PR4 support, CER requires Jacobs to:

Comment on the incentives that were placed on the TSO, TAO & DSO businesses during PR3,

Advise on the extent to which the businesses have delivered against these incentives and are due any

associated payments,

Comment on the continuing suitability of these incentives for implementation over the period 2016-2020

(PR4),

Provide advice on potential new incentives for infrastructure delivery which is seen as a continuing

problematic area, and

Provide recommendations on the removal or introduction of any incentive mechanism for PR492.

In recognition of the differing functions of the three businesses, individual business specific reports have been

prepared. This report focusses on the DSO businesses.

B.3 Data Sources & Assumptions

Data and information used within this report has been provided to Jacobs by ESBN and is assumed to be

correct and accurate. Specifically, information relevant to this report has been sourced from the following

documents:

DSO Historic Questionnaire

DSO Forecast Questionnaire

DH08 Incentives Proposal (FINAL)

DF08 Incentives Proposal (FINAL)

DH30 Continuity Performance

DF30 Continuity Plan (Final)

140730 Final DUoS Revenue and Tariff.xlsx

CER Decision Paper CER/10/198

Only information provided to Jacobs prior to 1 March 2015 has been used in the analysis of DSO Incentives.

92 This point relates to incentives regarding quality of supply, Loss Adjustment Factors and Network Development, et cetera, rather than the broader

incentives placed on the utilities by the form of the revenue control.

Page 212: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 207

B.4 Incentives Applied in PR3

B.4.1 Losses

Table B.1 below shows the target losses that were set out in the PR3 determination.

Table B.1 : PR3 Losses Target

2009 2010 2011 2012 2013 2014 2015

GWh distributed 22,955 22,902 23,269 24,014 24,758 25,526 26,317

Distribution Losses 1,738 1,709 1,715 1,752 1,787 1,824 1,860

Losses as % of total GWh 7.6 7.5 7.4 7.3 7.2 7.1 7.1

CER proposed that the value of these incentives would be €65,000 per GWh, consistent with the previous PR2

determination. The maximum impact of the losses incentive was set at penalty or reward equal to ±1.5% of

annual allowed revenue per annum (€10.5m in 2009 money).

CER indicated that there was uncertainty in relation to the measurement of these losses and therefore no

incentive payment would be made until the methodology used by the DSO for the measurement of losses had

been demonstrated to be accurate. The CER also directed that it would need to be demonstrated that any

reductions in losses beyond that built into the capital programme were a direct result of actions by the DSO and

not related to underlying system conditions.

B.4.2 Continuity

ESBN is incentivised against two measures of continuity:

Customer Minutes Lost (SAIDI - System Average Interruption Duration Index) - the average duration

of interruptions for all customers during the year determined by dividing the sum of all durations of service

interruptions to customers by the total number of customers

Customer Interruptions (SAIFI - System Average Interruption Frequency Index) – the average

number of interruptions per 100 customers during the year determined by dividing the total annual number

of customer interruptions by the total number of customers served during the year and multiplying by 100.

The measures include only outages of duration greater than three minutes and are subject to adjustment on

days for which customer lost minutes (CML) is greater than 61,570. This is known as the “storm threshold”.

CER set incentivised targets for system performance for the period 2010 to 2015 and the DSO received

incentive payments for exceeding targets and was penalised where targets were not met.

The target values set for PR3 in the decision paper CER/10/198 and corresponding work volume adjusted

targets are set out in Table B.2 below.

Table B.2 : PR3 Continuity Targets

2011 2012 2013 2014 2015

Customer Interruptions per 100 Customers (CI)

Unplanned 120.5 116.9 113.3 109.6 106.0

Planned 22.6 22.6 22.6 22.6 22.7

Total 143.1 139.5 135.9 132.2 128.7

Total (adjusted) 138.5 130.9 127.1

Customer Lost Minutes (CML)

Unplanned 85.3 80.6 76.4 72.2 68.0

Page 213: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 208

2011 2012 2013 2014 2015

Planned 55.8 55.8 55.7 55.8 55.8

Total 141.1 136.4 132.1 128.0 123.8

Total (adjusted) 128.8 113.0 108.1

Penalty / incentive rates of €0.26166m/CML and €0.20646m/CI (2009 prices) apply to differences between

actual outturn and targets. Reward and penalty payments are made based on total CI and CML in any given

year.

An overall cap / floor of ±1.5% of allowed revenue applies to the CI incentive. An overall cap / floor of ±1.5% of

allowed revenue also applies to the CML incentive.

The annual continuity target for planned outages is set based on forecast levels of planned work on the

network, and is subject to adjustment each year based on the amount of planned work actually carried out

according to the factors set out in Table B.3 below. Hence if more work than planned is completed, the allowed

continuity target would increase according to these factors to reflect the increased investment in the network

and vice versa. The work programmes in this context have been subject to the capex prioritisation and deferral

processes that are set out in other areas of ESBN’s PR3 historic submission.

Table B.3 : CI and CML per Work Unit

Activity Work unit CI x 100 per work unit CML per work unit

20kV conversion km 0.000442 0.00126

MV overhead line cyclic conversion km 0.000431 0.00116

Cut-out replacement Cut-out 0.000044 0.00003

Minipillar replacement Minipillar 0.000265 0.00095

LV urban overhead line refurbishment Span 0.000177 0.00064

LV rural refurbishment Group 0.000534 0.001514

Non-scheme new connections Connections 0.000508 0.0013

Correction of voltage complaints Jobs 0.00095 0.00242

Jacobs notes that work delivered volumes for 2013 have not been provided however ESBN has made

adjustments to the 2013 planned outage targets. 2014 data has also not been made available.

B.4.3 RedC

This incentive is based on an Annual Survey/Interview with 2,500 independently sampled customers who dealt

with the DSO in the previous six months.

It measures the customers’ perception of the service provided by ESBN in six areas:

Investigation of Voltage Complaints

Unplanned Outages

Planned Outage

New Connections – Domestic Schemes

New Connections – Domestic Non-Scheme

New Connections – Business

The targets, rates of financial payments and cap / floor for this incentive are set out in Table B.4 below.

Page 214: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 209

Table B.4 : RedC Incentive Targets 2011 to 2015

Red C Poll

2011 2012 2013 2014 2015

Target 74.0% 74.0% 74.0% 74.0% 74.0%

Value applied to deviation from target,

(€m per % deviation, 2009 money) 0.7215 0.7215 0.7215 0.7215 0.7215

Cap on this incentive,

+/- €m, 2009 money +1.6 / -6.5 +1.6 / -6.6 +1.6 / -6.7 +1.6 / -6.8 +1.6 / -6.9

B.4.4 Customer Satisfaction

This incentive tracks ESBN’s performance across a number of areas relating to the overall performance of the

ESBN Contact Centre in Wilton Cork. The metrics below apply at all times including during storm events:

B.4.4.1 Speed of Telephone Response

TSF 20 (including Interactive Voice Recognition, IVR) is the percentage of calls to the call centre answered

(by an agent or IVR) within 20 seconds.

TSF 30 (excluding IVR) is the percentage of calls that are in a queue waiting to speak to an agent (after

being placed in the queue either via the IVR or by an agent) that are answered by an agent within 30

seconds

The speed of telephone response measure applies under all conditions, including storms to ensure ESBN

is continually focussed on customer interaction during outage events.

B.4.4.2 Call Abandonment Rate

This measure will record the number of calls that are abandoned while a caller is waiting in a queue to speak to

an agent.

The call abandonment rate measure applies under all conditions, including storms, to ensure ESBN is

continually focussed on customer interaction during outage events.

B.4.4.3 Customer Call-Back survey results

ESBN’s customers will be contacted within two days of calling the ESBN Contact Centre. The call-backs will be

carried out by an independent research company engaged by ESBN and reporting to both the Commission and

ESBN. The calls will be selected randomly, subject to the (reasonable) inclusion of calls by:

Time of day when call was made (morning, afternoon, evening, night).

Purpose of call (for example, supply problem, meter reading).

Handling of call (on-call resolution, requiring call-back or referral).

Customers will be asked to score their call centre experience on a scale of 1 (very dissatisfied) to 5 (very

satisfied) based on:

The politeness of the member of staff.

Their willingness to help.

The accuracy of the information given (if information was given).

The usefulness of the information given (if information was given).

Page 215: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 210

B.4.4.4 Mystery Caller survey results

This measure involves a third party, in the guise of a genuine caller, making calls to gain an assessment of

various aspects of customer service provided. Aspects of the call centre agent’s approach and disposition will

be evaluated, including helpfulness, responsiveness, tone and style of the agent.

The areas of activity that will be tested are:

New connections for a single site.

New connections for a multi-site development.

Service alterations.

Planned outages.

Moving a meter.

No supply.

Meter reading policy.

Tree cutting.

Some of the scenarios above will be selected by CER each quarter to be assessed under the survey.

Priority will be given to those queries that, if responded to effectively, provide the most benefit to customers.

B.4.4.5 First Contact/Call Referral

This is a target through which ESBN Contact Centre agents are required to meet a target of dealing with a % of

calls within one call, that is, without requiring call-backs.

The targets for each of these areas, and the overall (ESATRAT) target are set out in Table B.5 below.

Table B.5 : Customer Satisfaction Target 2011 to 2015

Component of customer satisfaction metrics

2011 2012 2013 2014 2015

KPI Weighting Target Target Target Target Target

Speed of telephone response 25% 83% 83% 83% 83% 83%

Abandonment rate 25% 5% 5% 5% 5% 5%

Mystery caller 20% 80% 80% 80% 80% 80%

Call back survey 15% 80% 80% 80% 80% 80%

Call referral rate 15% 15% 15% 15% 15% 15%

ESATRAT (performance target) 85% 85% 85% 85% 85%

A reward/penalty of €0.7215m per % deviation applies to the weighted overall target. An annual maximum

reward of €1.6m and maximum penalty of €6.5m applies for 2011 rising to €1.7m and €6.9m, respectively, by

2015.

B.4.5 Metering

ESBN is incentivised against a set of Service Level Agreements (SLAs) for the provision of certain services by

the DSO under its licence obligations. These came into force in January 2005 and are reported on by the DSO

to CER in its annual performance report. SLA number 14 is the area against which metering performance is

measured. These targets state that:

100% of premises should have a scheduled read visit 2 times per year.

Page 216: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 211

97% of premises should have a scheduled read visit 4 times per year.

80% of visits should result in an actual meter read.

98% of meters should have 1 reading (DSO or customer) per year.

99% of meters will not have back to back block estimates.

For PR3, CER introduced financial incentives for the latter two items above. These are incentivised to a value of

±€1m per year. The targets and performance for the metering incentive are set out below in Table B.6 and

Table B.7.

Table B.6 : Regulatory Targets (at least one meter reading per year)

2010 2011 2012 2013 2014 2015

Target n/a 98.0% 98.0% 98.0% 98.0% 98.0%

Dead-band within which no payments are made n/a 0.2% 0.2% 0.2% 0.2% 0.2%

Value applied to deviation from target

€m per 0.1% deviation from target, 2009 money n/a 0.1 0.1 0.1 0.1 0.1

Cap on this incentive, +/- €m, 2009 money n/a 0.50 0.50 0.50 0.50 0.50

Table B.7 : Regulatory Targets (avoiding back to back estimates)

2010 2011 2012 2013 2014 2015

Target n/a 97.9% 98.1% 98.4% 98.7% 99.0%

Value applied to deviation from target

€m per 0.1% deviation from target, 2009 money n/a 0.1 0.1 0.1 0.1 0.1

Cap on this incentive, +/- €m, 2009 money n/a 0.50 0.50 0.50 0.50 0.50

B.4.6 Generation Connections

An incentive was proposed by ESBN in their PR3 submission to incentivise connection of renewable generation

to the distribution system. The proposal focussed on:

planning stage between offer acceptance to lodging of planning application;

detailed design stage from receipt of planning approval to issue of second stage payment invoice; and

construction stage from receipt of the second stage payment to energisation of the generator.

There was on-going consultation about generation connection policy in 2010 which resulted in delays to the

progression of most Gate 3 connections. This resulted in the deferral of any incentive regime based on

generator connection due to the continued uncertainty about timelines for connection. As a result this incentive

was not progressed in PR3 by CER or ESBN.

B.4.7 Worst Served Customer

Worst Served Customers (WSC) are those customers who experience a large number of supply interruptions

over a specified period. In order to be included on the worst served customer list, both of the following criteria

must be met:

greater than or equal to five interruptions over the past year; and

greater than or equal to 15 interruptions over the past three years.

Typically the customers impacted are supplied on rural single phase overhead networks.

ESBN proposed that a fund of €10m be put in place to improve service to worst served customers over the PR3

period. The fund of €10m was not included in the DSO revenue.

Page 217: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 212

While this fund was available for approved proposals, no penalties would have applied for non-performance.

B.4.8 CAPEX Delivery

The PR3 capex proposal was agreed at €2.3bn for Distribution.

There was an incentive designed to promote delivery of agreed portions of the overall distribution capex

proposal. The intention was to focus delivery within a large capex programme of key network development work

areas specifically relating to load and non-load capex. This looked at individual unit delivery of nominated work

programmes on a nominal 20% per annum basis for the five years. The incentive metrics were set at:

Programme Delivery <50% = penalty of €7m.

Programme Delivery 50% <70% = penalty payment of between €7m and €0m. -0.35 per % <70%

Programme Delivery 70% <80% = €0 (dead band)

Programme Delivery 80% <100%= payment of between €0m and €7m. 0.35 per % >80%

Table B.8 : Capex Delivery (Actuals against Targets)

2010 2011 2012 2013 2014 2015

Target

180.198 180.198 180.198 180.198 180.198

Cap on this incentive, +/- €m, real 2009

7.00 7.00 7.00 7.00 7.00

Following discussions between CER and ESBN in 2012, where a re-profiled capex programme was agreed for

PR3, the appropriateness of this incentive was considered and the incentive was suspended in 2013.

B.4.9 Summary of PR3 incentives

Table B.9 : Summary of PR3 Incentives

Incentive Value (€m, 2009 prices)

Losses +/- €10.5m

Continuity +/- 1.5% of revenue CI ~€10.5m;

+/- 1.5% of revenue CML ~€10.5m

RedC +/-€1.6m

Customer Satisfaction +€1.6m / - €6.9m

Metering +/- €1m

Generation connections discontinued

Worst served customer €10m fund available

Capex delivery +/ - €7m - discontinued

B.5 Performance in PR3

B.5.1 Losses

The DSO believes that the performance of the business has been improving generally and losses have been

decreasing over the last number of years. The DSO reports that there have been varying levels of success in

trying to produce a consistent and reliable set of losses figures year on year (annual variances in the output

undermine confidence in the specific figures though suggest an overall trend of declining losses). The actual

losses performance of the distribution system is stated to be in the region of 7 – 8%.

Page 218: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 213

Figure B.1 shows the performance achieved by ESBN during PR2 and PR3 (subject to the uncertainties noted

above) – Method A is based on an estimated throughput at the Transmission – Distribution boundary and

Method B. is based on measurement of inputs at the interface between transmission and distribution system

Figure B.1 : Losses Calculation for 2010, 2011 and 2012

To date, ESBN has not submitted any outturn losses figures to CER for consideration under the losses

incentive.

B.5.2 Continuity

In Table B.10 the values provided were in the original data submission. This has subsequently been updated

with changes in the forecasts and the actuals in earlier years. Volumes in 2014 were significantly down on the

forecast values originally provided.

Figure B.2 and Figure B.3 below set out the fault continuity performance of the DSO against the work-adjusted

targets set over the PR3 period to date, with Table B.11 showing the corresponding data in tabular format.

Planned outage targets are adjusted annually ex ante, taking into account actual delivered work volumes in that

year. The adjustments are based on the work volumes provided in’140730 Final DUoS Revenue and Tariff.xlsx’,

which is shown in Table B.10 below. These work volumes are multiplied by the corresponding per work unit

allowances in Table 46 of the CER Decision Paper CER/10/198. Figures for 2014 and 2015 have not been

adjusted as this information was not available at the time.

Table B.10 : PR3 Actual Work Volumes

Activity Work unit 2011 2012 2013 2014* 2015*

20kV conversion km 2,252 1,877 2,579 3,000 3,000

MV overhead line cyclic conversion km 2,877 6,936 5,632 9,000 9,000

Cut-out replacement Cut-out 11,405 4,310 5,371 8,000 8,000

Minipillar replacement Minipillar 122 156 101 320 320

LV urban overhead line

refurbishment Span 7,343 3,460 2,749 7,600 7,600

LV rural refurbishment Group 7,168 528 1,482 5,000 5,000

Page 219: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 214

Activity Work unit 2011 2012 2013 2014* 2015*

Non-scheme new connections Connections 6,494 5,155 4,730 10,836 11,079

Correction of voltage complaints Jobs 922 587 370 1600 1500

* Forecast Values based on the questionnaire submitted. These values were later updated and included variations to earlier years

Figure B.2 : PR3 Customer Interruptions per 100 Customers

Figure B.3 : PR3 Customer Minutes Lost

Page 220: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 215

Table B.11 : System Performance (2011 to 2015)

2011 2012 2013 2014 2015** PR3 Average

Customer Interruptions per 100 Customers (CI)

Planned

PR3 Actual 18.1 18.5 16.6 16.7 22.3 18.4

PR3 Targets (adjusted*) 18.0 14.0 13.8 22.6 22.7 18.2

Variance (negative = good) 0.1 4.5 2.8 -5.9 -0.4 0.2

Unplanned

PR3 Actual 94.6 85.7 114.2 129.6 95.2 103.9

PR3 Targets 120.5 116.9 113.3 109.6 106.0 113.3

Variance (negative = good) -25.9 -31.2 0.9 20.0 -10.8 -9.4

Customer Lost Minutes (CML)

Planned

PR3 Actual 46.6 44.9 42.1 42.3 40.8 43.3

PR3 Targets (adjusted*) 43.5 32.4 31.7 55.8 55.8 21.5

Variance (negative = good) 3.1 12.4 10.4 -13.5 -15.0 -0.5

Unplanned

PR3 Actual 69.6 62.0 86.7 101.1 83.1 80.5

PR3 Targets 85.3 80.6 76.4 72.2 68.0 76.5

Variance (negative = good) -15.7 -18.6 10.3 28.9 15.1 4.0

Total (Planned and Unplanned)

CI

PR3 Actual 112.7 104.3 130.8 146.3 117.5 122.3

PR3 Targets (adjusted*) 138.5 130.9 127.1 132.2 128.7 131.5

Variance (negative = good) -25.8 -26.7 3.6 14.1 -11.2 -9.2

CML

PR3 Actual 116.2 106.9 128.8 143.4 123.9 123.8

PR3 Targets (adjusted*) 128.8 113.0 108.1 128.0 123.8 120.4

Variance (negative = good) -12.6 -6.1 20.7 15.4 0.0 3.5

* Adjusted targets for 2011, 2012 and 2013. Targets for 2014 and 2015 remain as original CER decision targets.

** 2015 actuals are based on current forecasts.

Table B.11 shows that, on average, the DSO has met its PR3 CI target by 9.2 interruptions per 100 customers

and fallen short, on average, of its CML target by 3.5 minutes per customer.

Outturn figures for 2012 appear to differ between the DSO Forecast Questionnaire submission and DH08

Incentives, leading to a difference in reward payments being presented. Table B.12 shows that the rewards

payment for CI and CML in 2012 should have been €5.5m and €1.6m respectively. Note that 2014 and 2015

figures are based on current forecasts.

Page 221: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 216

Table B.12 : Achieved Earnings with respect to Continuity Performance (2009 prices)

Financial Payments 2011 2012 2013 2014* 2015*

Jacobs CI (€m) 5.3 5.5 -0.8 -2.9 2.3

ESBN CI (€m) 5.3 6.1 -0.8

Jacobs CML (€m) 3.3 1.6 -5.4 -4.0 0.0

ESBN CML (€m) 3.3 2.1 -5.4

* 2014 and 2015 values based on current estimates

Targets and performance exclude exceptional storm days, which totalled 22 days from 2010 to 2015, to ensure

that performance is measured on a consistent basis over time and with comparator countries.

Outages on the MV network give rise to the majority of CI and CML. There was a sharp decrease in CI and

CML in 2011 and 2012 which the DSO attributes to benign weather, rising again in 2013 and 2014 due to an

increase in storm activity.

The underlying network performance is best represented by the performance for unplanned interruptions which

has improved between PR2 and PR3 on a yearly average basis by around 20%, as shown in Table B.13.

Table B.13 : Improvement in network Performance Unplanned Outages (2010 to 2015)

Unplanned Outages PR2 Average PR3 Average Change in Average

Customer Interruptions (CI) 131.7 103.9 -21.11%

Customer Minutes Lost (CML) 103.8 80.5 -22.45%

Figure B.4 and Figure B.5 below compare the performance in PR2 to PR3. As can be seen, 2006 and 2007 had

particularly high CI and CML compared to the other years over the last decade. It should be noted that there

was a change in definition on interruptions, with PR2 figures including all interruptions greater than 1 minute,

whereas in PR3 the definition was for interruptions over 3 minutes.

Figure B.4 : Customer Interruptions (CI) in PR2 and PR3

Page 222: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 217

Figure B.5 : Customer Minutes Lost (CML) in PR2 and PR3

B.5.3 RedC

Achieved performance during the PR3 period is set out in Table B.14. The DSO has beaten the target by a

significant margin in every year with the corresponding reward being capped at the maximum level in each year

to date. Note that information for 2015 actuals was not available at the time of writing.

Table B.14 : PR3 Performance against RedC Incentive

RedC Poll

2010 2011 2012 2013 2014 2015

Target n/a 74.0% 74.0% 74.0% 74.0% 74.0%

Actual n/a 81.0% 83.8% 82.4% 80.5%

Value applied to deviation from target, €m, 2009 n/a 0.7215 0.7215 0.7215 0.7215

Cap on this incentive, +/- €m, real 2009 n/a 1.60 1.60 1.60 1.60

Cap on this incentive, +/- €m, nominal n/a 1.59 1.62 1.63 1.64

Payment ignoring cap on this incentive, €m, real 2009 n/a 5.05 7.07 6.08 4.69

Payment ignoring cap on this incentive, €m, nominal n/a 5.02 7.17 6.20 4.80

Payment allowing cap on this incentive, €m, nominal n/a 1.59 1.62 1.63 1.64

B.5.4 Customer Satisfaction

The DSO has exceeded the target in each year of PR3 to date and has earned the maximum (i.e. capped) level

of incentive under this mechanism (Table B.15). Note that information for 2015 actuals was not available at the

time of writing.

Page 223: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 218

Table B.15 : PR3 Performance against Customer Satisfaction Incentive

Customer Satisfaction

2010 2011 2012 2013 2014 2015

Target 85.4% 85.3% 85.3% 85.3% 85.3% 85.3%

Actual 89.8% 90.4% 86.5% 89.4% 90.0%

Value applied to deviation from target, €m, 2009 0.85 0.7215 0.7215 0.7215 0.7215

Cap on this incentive, +/- €m, real 2009 1.7 1.67 1.78 1.80 1.88

Payment ignoring cap on this incentive, €m, real 2009 2.07 3.73 2.35 3.02 3.41

Payment ignoring cap on this incentive, €m, nominal 3.15 3.71 2.39 3.08 3.48

Payment allowing cap on this incentive, €m, nominal 1.7 1.87 1.78 1.80 1.88

B.5.5 Metering

In terms of the obligation to achieve at least one meter reading per annum for customers, the DSO has

exceeded the target in each year of PR3 period to date (though with the performance being within the dead-

band in the last two years and hence no reward earned. Details are provided in Table B.16. Note that

information for 2015 actuals was not available at the time of writing.

Table B.16 : Performance against objective to obtain at least one meter reading per year

At least one meter reading per year

2010 2011 2012 2013 2014 2015

Target n/a 98.0% 98.0% 98.0% 98.0% 98.0%

Actual n/a 98.5% 98.2% 98.1% 98.0%

Dead-band within which no payments are made n/a 0.2% 0.2% 0.2% 0.2%

Value applied to deviation from target, €m, 2009 n/a 0.1 0.1 0.1 0.1

Cap on this incentive, +/- €m, real 2009 n/a 0.50 0.50 0.50 0.50

Cap on this incentive, +/- €m, nominal n/a 0.50 0.51 0.51 0.51

Payment ignoring cap on this incentive, €m, real 2009 n/a 0.30 0.00 0.00 0.00

Payment ignoring cap on this incentive, €m, nominal n/a 0.30 0.00 0.00 0.00

Payment allowing cap on this incentive, €m, nominal n/a 0.30 0.00 0.00 0.00

In terms of the obligation to avoid back-to-back estimated consumption for customers, the DSO has exceeded

the target in each year of PR3 period to date. Details are provided in Table B.17.

Note that information for 2015 was not available at the time of writing.

Page 224: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 219

Table B.17 : Performance against target to avoid back-to-back estimated consumption

Avoiding back to back block estimates

2010 2011 2012 2013 2014 2015

Target n/a 97.9% 98.1% 98.4% 98.7% 99.0%

Actual n/a 99.0% 98.9% 99.2% 99.7%

Value applied to deviation from target, €m, 09 n/a 0.1 0.1 0.1 0.1

Cap on this incentive, +/- €m, real 09 n/a 0.50 0.50 0.50 0.50

Cap on this incentive, +/- €m, nominal n/a 0.50 0.51 0.51 0.51

Payment ignoring cap on this incentive, €m, real 09 n/a 1.13 0.80 0.80 1.00

Payment ignoring cap on this incentive, €m, nominal n/a 1.12 0.81 0.82 1.02

Payment allowing cap on this incentive, €m, nominal n/a 0.50 0.51 0.51 0.51

B.5.6 Generation Connections

An incentive was proposed by DSO in PR3 submission to incentivise connection of renewable generation to the

Distribution System.

There has been on-going consultation and uncertainty about the roll out of Gate 3 connections in PR3 which

has delayed the progression of most Gate 3 connections. This resulted in the deferral of any incentive regime

based on generator connection. As a result this incentive was not progressed in PR3 by CER or ESBN.

B.5.7 Worst Served Customer

In 2014 ESBN has initiated a programme of targeted investigation and remedial works to improve the continuity

of supply seen by a group of customers classified as “Worst Served Customers” (WSC) – those customers who

have seen 15 interruptions in the past three years and at least five interruptions in the past year. There are

47,400 such customers based on 2013 outturn – the last full year of recorded outturn.

To date CER have approved projects proposed by ESBN totalling approximately €25k pa over the PR3 period.

In PR3 an initiative has been undertaken to address the WSC issue. The initiative has been addressed in the

following manner.

A list of single phase spurs on the WSC list were identified

A patrol of the single phase spurs was carried out. The goal of the patrol is to identify issues, with particular

focus on a range of pre-identified root causes and assets to which continuity issues are often attributed:

- Conductors

- Stays

- Crossarms, headgear, Insulators and accessories

- Line jumpers and connectors

- Pole mounted transformers

- Surge arresters

Following patrol and identification of issues, work orders are prepared to address plant defects or to install

items of plant expected to offer targeted remediation.

Remediation works are completed.

Typical Remediation Works

The typical remediation works required can be summarised under two broad categories:

Page 225: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 220

Solutions with lower resource requirement:

- Replacement surge arresters

- Bird caps on transformers

- Insulation of jumpers and bridgings

- Timber cutting

- Boxing in of the stay wires

Resource intensive remediation options:

- Single Phase Reclosers

- Single phase to three phase conversion

The current programme involves patrolling the networks feeding an identified spur where WSC are connected,

and remedial measures being proposed based on their observations of the network. The number of

interruptions seen by WSC may be attributable to a wide range of issues, including sub-standard network

components, timber contact with lines, environmental factors including gusts of wind, lightning, birds landing on

transformers and shorting across the bushings, or livestock interfering with poles or stays. ESBN has provided

no performance measurement metric for this programme.

B.5.8 CAPEX Delivery

In PR3 there was an incentive designed to promote delivery of agreed portions of the overall Distribution capex

proposal. The intention was to focus delivery within a large capex programme of key network development

work areas specifically relating to load and non-load capex. Following discussions with CER in 2012 where

ESBN agreed a re-profiled capex programme for PR3, the appropriateness of this incentive was discussed.

CER and ESBN agreed that the incentive for capex delivery was no longer appropriate. As a result the incentive

was suspended in 2013.

ESBN does not intend to put forward a Capex Delivery Incentive for PR4.

B.6 Suitability of Incentives for PR4

The following section discusses the incentives proposed by ESBN and the suitability of these incentives PR4.

B.6.1 Losses

ESBN does not intend to put forward a losses reduction target for PR4 and intends to discuss at a later date in

PR4 how the installation of Smart Meters may be used to facilitate a reliable measurement methodology. There

may also be scope at that point to consider the value in targeting commercial or technical losses for an

incentivised reduction programme.

Given the ongoing problems in accurate measurement of losses, we would recommend incentivising the DSO

(perhaps in conjunction with suppliers) to develop a measurement methodology including appropriate basis for

calculating accruals for estimated consumption from the date of last reading to year-end. For example, this

could take the form of a requirement to deliver an agreed methodology by end 2015 and to implement

calculation and reporting by end 2016, with penalties becoming payable in the event of non-performance.

B.6.2 Continuity

ESBN state that incentivised focus on improvement of continuity has resulted in steady improvement in the

performance of the network as experienced by their customers. This is an area of incentivisation that ESBN

believes should endure.

Page 226: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 221

B.6.2.1 Review of Proposed Incentives

ESBN’s proposed continuity targets based on the proposed Continuity CAPEX plan are shown in Figure B.6,

Figure B.7 and Table B.18. The targets are based on extrapolation of performance for previous years,

excluding 2011, 2012 and 2014 which are considered by ESBN to be outliers.

ESBN has not proposed financial payment figures for deviating from the proposed targets.

In our opinion the increase in CI and CML experienced following the benign years of 2011 and 2012 is in part a

consequence of the better than expected performance in those years (i.e. events that might otherwise have

occurred in those years under average conditions are simply deferred, and occur later along with other events

that would have occurred in that later year anyway). Hence consideration should be given to deriving a target

from historic performance across all years rather than taking out the high and low years. The principal is based

on knowing that even with storm events removed there will be good and bad years, the incentive is to ensure

the business progressively improves its approach towards prevention and response to supply loss.

Page 227: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 222

Figure B.6 : Forecast Customer Interruptions

Figure B.7 : Forecast Customer Minutes Lost

Table B.18 : DSO Proposed Network Performance Targets

DSO Forecast PR2

Average

PR3

Average

Average

Change

PR2 - PR3

2016 2017 2018 2019 2020 PR4

Averag

e

Average

Change

PR3 - PR4

Unplanned CI 131.7 103.9 -21.16% 113.7 112.4 111.1 109.8 108.5 111.1 6.96%

Unplanned CML 103.8 80.5 -22.48% 84.2 82.5 80.9 79.2 77.5 80.86 0.45%

Planned CI 29.5 18.4 -37.40% 21.8 22.1 22.4 22.8 23.1 22.44 21.69%

Planned CML 106.2 43.3 -59.19% 52.3 53.1 53.9 54.8 55.8 53.98 24.56%

Page 228: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 223

The DSO has made proposals for improvement in network performance for the period 2016 to 2020 including

operational improvements, network renewal and specific continuity improvement projects. Table B.19 below

summarises the balance of improvements and degradation DSO has forecast over PR4.

Table B.19 : DSO Proposals for Network Performance Improvement

Programme Units CI CML Cost (€m)

20kV Conversion 4,000 -0.02 -1.20

Loop Automation (schemes) 50 0.10 4.88 8.5

Single Phase Reclosers (spurs) 150 0.005 0.77 0.6

Fault Passage Indicators 1,150 0.00 6.67 1.1

Worst Served Customers 6,000 0.001 0.11 1.4

38kV Switch Automation 1.3

Wildlife Diverters in HV Stations 300 0.3

Urban RMU Automation Pilot 30 0.20 0.3

MV Arc Suppression (Stations 17 0.02 1.94

The extent of the 20kV conversion programme will be much reduced in PR4 compared to that of PR3 with

4,000km planned for completion. There is expected to be a higher number of outages per km converted than in

PR3 but the total quantity of network converted to 20kV operation will be less. The overall impact of this

programme is to increase CI and CML’s and so the overall CI and CML impact of 20kV conversion will be less in

PR4 than it was in PR3.

There is also expected to be an increased number of planned outages required as part of the MV Overhead

Cyclic Refurbishment (OCR) programme in order to deal with the issue of accelerated pole rot on Scantrepo

poles. Furthermore there is a large volume of MV OCR (approx. 17,000 km) anticipated for 2015 with the

quantity then reducing to approximately 6,900 km per annum for the duration of PR4, resulting in a high CI and

CML impact in 2015.

The LV Rural Refurbishment (LVR) work programme will be ramped up in 2015 and there will be a consequent

increase in the CI and CML numbers for this programme.

In section 1 of DF 30 Continuity Plan ESBN proposes that 6,000 WSC will be benefited for a cost of €1.4m as

shown above, however in section 2 the stated number of WSC to benefit from the same expenditure is 4,000.

Jacobs recommends that the intended units for Worst Served Customers are confirmed at either 4,000

or 6,000 customers for the €1.4m fund ESBN is requesting. The outcome of this confirmation will impact

on the incentive scheme proposed for WSC in section B.5.7.

Table 2 in ESBN’s DF30 Continuity Plan report outlines the cost-benefit of the proposed continuity improvement

programmes for PR4.

The forecasts for planned outages are based on assumed levels of activities in different areas. Table B.20

shows proposed work volumes and Table B.21 shows the corresponding CI and CML adjustments per work unit

in each area.

In relation to the MV OCR programme, an increase in the allowed CI and CML per work unit is proposed. ESBN

report that the data for 2013 outturn indicates that the actual duration of outages for customers was correct,

whereas the number of outages required to complete the total work programme was higher than anticipated. A

number of factors contributed to this result with the work being completed in smaller blocks due to resource

availability and also the increasing impact of accelerated rot on Scantrepo poles. New work practises are being

Page 229: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 224

put in place to address the Scantrepo pole issue with one outage required to assess the full pole length and a

second outage required to replace the pole. An increase in the allowed CI and CML for MV OCR is proposed.

Table B.20 : DSO Proposed Work Programmes

Activity Work unit 2014 2015 2016 2017 2018 2019 2020

20kV conversion km 2,000 2,000 800 800 800 800 800

MV overhead line cyclic

conversion km 5,000 17,000 6,900 6,900 6,900 6,900 6,900

Cut-out replacement Cut-out 4,000 4,000 8,000 8,000 8,000 8,000 8,000

Minipillar replacement Minipillar 102 102 440 440 440 440 440

LV urban overhead line

refurbishment Span 2,000 2,000 3,500 3,500 3,500 3,500 3,500

LV rural refurbishment Group 4,000 9,000 3,450 3,450 3,450 3,450 3,450

Non-scheme new connections Connections 4,987 5,243 5,500 6,000 6,500 7,000 7,500

Correction of voltage

complaints Jobs 850 850 850 800 750 700 650

Table B.21 : Proposed CI and CML per Work Unit

Activity Work unit CI x 100 per work unit CML per work unit

20kV conversion km 0.000784 0.002235

MV overhead line cyclic conversion km 0.000869 0.002347

Cut-out replacement Cut-out 0.000045 0.000027

Mini-pillar replacement Mini-pillar 0.000267 0.000963

LV urban overhead line refurbishment Span 0.000178 0.000642

LV rural refurbishment Group 0.000542 0.001540

Non-scheme new connections Connections 0.000513 0.001307

Correction of voltage complaints Jobs 0.000958 0.002444

B.6.2.2 Assessment and Recommendations for Continuity Incentives in PR4

CI and CML targets are a key measure used internationally for measuring and incentivising distribution

company performance. Hence it is recommended that targets continue to be applied on this basis. We would

expect the level of targets to be set at a level consistent with a trend of continued improvement in performance.

Although ESBN’s forecast levels of CI and CML show a declining trend through the PR4 period, we note that,

because 2011, 2012 and 2014 data have been excluded from the base-line used from the forecast, the

proposed targets appear to be less onerous than those currently in place under PR3.

As well as continuing the general downward trend, the specific level of the targets should also be set taking into

account the benefits expected to arise from capex schemes and opex activities (such as tree-cutting) approved

as part of the PR4 determination.

As stated in section B.5.2 above, ESBN has, on average, outperformed its CI targets throughout PR3 while it

has underperformed, on average, with respect to CML targets based on current data. This would indicate that

CI more challenging targets can be set for PR4 in order to encourage a better service for customers on the

network. Although ESBN has missed its CML targets by 2.9%, on an average basis, this deviation is relatively

minor and therefore we believe PR4 targets should be set at levels which continue to incentivise improvements

in this area.

Page 230: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 225

Furthermore, due to the incentive scheme being centred on the aggregated planned and unplanned total for

each metric, ESBN has only exceeded the targets by relatively small amounts in the more severe weather years

of 2013 and 2014. In using the total level as the target, the DSO is not incentivised to minimise planned outages

over unplanned outages. It is our opinion that unplanned outages have a more adverse impact on customers

due to the inherent uncertainty associated with them, and therefore we would encourage a scheme that

incentivises planned outages compared to unplanned outages.

Hence we would recommend using separate targets for unplanned and planned outages, with a 50%

less weighting on planned outage financial payments.

This would encourage the DSO to be proactive in managing the causes of unplanned outages, such as timber

contact, and provide further incentives to introduce innovative asset management strategies.

We recommend that targets be set at those stated in Table B.22 below. Planned allowances have been

calculated based on the following:

Planned CI – sum-product of work volumes and CI per work unit allowances plus an additional allowance

of 6 CI for unidentified planned outages.

Planned CML – sum-product of work volumes and CML per work unit allowance plus an additional

allowance of 10.6 CML for unidentified planned outages.

Unplanned outages have been calculated based on the following methodology:

3) Calculate the average outturn of unplanned outages for 2010 – 2014, PR3ave (5 years of most recent data).

4) Retrospectively set the 2013 target (i.e. midpoint of PR3) equal to PR3ave.

5) Using the slope from the original PR3 targets, calculate new targets for 2011, 2012, 2014 and 2015 to

create ‘modified PR3 targets’.93

6) Set the recommended target for 2016 to the 2015 target from the ‘modified PR3 targets’.

7) Using the slope from the DSO proposed PR4 targets, calculate recommended targets for 2016 – 2020.

An example calculation is shown in Figure B.8 below.

93 ESBN state that in their Capex reduction programme, continuity capex was reduced to a greater extent than

other capex. We note that in the early meetings when we pointed out the poorer performance in the later years

of the review and we suggested that the lack of investment would be a factor, ESBN stated that that was not the

case. Also given the modest forecast improvements due to capital programmes that were in the original plan,

then the reduced spending will not have had a significant impact on out-turn when the avoidance planned

outages is considered.

Page 231: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 226

Figure B.8 : Unplanned Outages Example

Using the modified PR3 targets described in step 3) above, the DSO would have achieved net deviations of

+0.5 CML and -22.4 CI over the PR3 period for unplanned outages. The average annual deviations would have

been 0.1 CML and -4.5 CI during PR3. This evidence clearly demonstrates that the modified PR3 targets, upon

which the recommended PR4 unplanned targets are based, were achievable in PR3 and reflect current

operating conditions for the DSO.

ESBN has not proposed financial reward and penalty figures; therefore we would recommend that PR3

figures, adjusted to real 2014 prices, are used for PR4.

As in PR3, planned outage metrics should be adjusted ex post with regard to the outturn work volumes

completed in any given year.

Table B.22 : Recommended Network Performance Target for PR4

Target Unit 2016 2017 2018 2019 2020 PR4 change

Planned CI CI × 100 15.4 15.6 15.8 16.0 16.2 5.1%

Planned CML CML 35.6 36.1 36.6 37.1 37.6 5.6%

Unplanned CI CI × 100 101.1 99.8 98.5 97.2 95.9 -5.1%

Unplanned CML CML 71.9 70.2 68.4 66.6 64.9 -9.7%

Total CI CI × 100 116.5 115.4 114.3 113.2 112.1 -3.8%

Total CML CML 107.5 106.3 105.1 103.8 102.5 -4.6%

On average across PR4, the recommended targets for planned outages are between 30% and 33% lower than

those proposed by ESBN and between 11% and 16% lower for unplanned outages. For total customer

interruptions and customer lost minutes, the recommended targets are between 14% and 23% lower than

ESBN’s proposed PR4 targets. A detailed summary of the changes can be seen in Table B.23 below.

Table B.23 : Percent difference between ESBN Proposed and Jacobs Recommended Targets

Change from ESBN Proposal Unit 2016 2017 2018 2019 2020

Planned CI CI × 100 -30% -30% -30% -30% -30%

Planned CML CML -32% -32% -32% -32% -33%

Unplanned CI CI × 100 -11% -11% -11% -11% -12%

Page 232: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 227

Change from ESBN Proposal Unit 2016 2017 2018 2019 2020

Unplanned CML CML -15% -15% -15% -16% -16%

Total CI CI × 100 -14% -14% -14% -15% -15%

Total CML CML -21% -22% -22% -23% -23%

Financial payments have been split on a 1:2 ratio between planned and unplanned outages for both the CI and

CML metric. These payments are outlined in Table B.24 below. The average financial payment for deviating

from the CI and CML targets is shown to be same as the PR3 financial payments in 2014 prices. Capping of

financial payments should continue as implemented in PR3.

Table B.24 : Recommended Financial payments for PR4 (2014 Prices)

Financial Payments 2016 2017 2018 2019 2020

Planned CI € 141,012 € 141,012 € 141,012 € 141,012 € 141,012

Planned CML € 178,713 € 178,713 € 178,713 € 178,713 € 178,713

Unplanned CI € 282,024 € 282,024 € 282,024 € 282,024 € 282,024

Unplanned CML € 357,426 € 357,426 € 357,426 € 357,426 € 357,426

Average CI € 211,518 € 211,518 € 211,518 € 211,518 € 211,518

Average CML € 268,070 € 268,070 € 268,070 € 268,070 € 268,070

Should this weighted payment regime be implemented by CER, it will be especially important that

outage data in PR4 is independently audited when submitted to CER. It has been noted that the DSO

has provided further information relating to the impact of the planned outages which suggests that the

targeted improvements may be difficult to achieve. As we have stated there should be independently

audited performance, this should also cover the planned outage programmes to derive a better baseline

for the review and future targets.

We believe these targets are stretching but achievable while ensuring that customers continue to see an

improvement in the network service they receive from ESBN. For comparison, Figure B.9 to Figure B.14 below

show a breakdown of PR3 performance, PR3 targets, ESBN’s proposed PR4 targets and Jacobs’

recommended PR4 targets for each element of the continuity incentive scheme.

It is also noted however that ESBN have proposed a number of amendments to the calculation of continuity

metrics including:

revised definition of storm threshold;

revised adjustment factors for planned outage activities; and

smart metering.

These proposed amendments are discussed in sections B.6.2.3 to B.6.2.6. The North Atlantic Green Zone

scheme is also discussed in the context of continuity.

Page 233: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 228

Figure B.9 : Planned CI Comparison

Figure B.10 : Planned CLM Comparison

Figure B.11 : Unplanned CI Comparison Figure B.12 : Unplanned CML Comparison

Page 234: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 229

Figure B.13 : Total CI Comparison

Figure B.14 : Total CML Comparison

B.6.2.3 Revised storm threshold

ESBN have proposed that a storm threshold of 2.5 standard deviations from the mean daily level (assuming a

log-normal distribution) as per the IEEE 1366-2003 standard. For comparison, Ofgem approved RIIO-ED1

Incentives with a storm threshold set at eight times the daily average.

If ESBN’s proposal were to be accepted, it would result in a reduction in the storm threshold from 61,570CML to

49,161CML with a corresponding increase in the number of days being captured by the exclusion. This would

result in an apparent improvement in performance relative to historic figures calculated on the original basis.

Figure B.15 illustrates this point.

Page 235: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 230

Figure B.15 : Illustration of Impact of Proposed Change to Storm Threshold

Changing the storm threshold is an area the DSO and CER should consider further in consultation with other

stakeholders. Due to the time constraints at this stage of PR4 the consultation would not allow sufficient time to

retrospectively determine past performance, therefore creating inconsistency between past and future targets.

We consider that the CER support further investigation in monitoring performance and determining appropriate

targets. However there would need to be fully independently audited network performance data made available

which is consistent with most regulated businesses where financial rewards and penalties are involved.

Experience has shown that independent auditing identifies inaccuracies and errors which need to be factored

into reporting values before financial payments are confirmed.

In general the proposed changes suggested by the DSO would remove more abnormal days from consideration

reducing the CI and CML values being considered as incentivised, in which case the impact which could be

achieved during more ‘normal ‘ type fault day events would be reducing and the level of incentive would need to

be adjusted accordingly reducing potential rewards and penalties and hence the impact of the incentive.

Jacobs acknowledges that the DSO is likely to face changing weather conditions in the future but believes that

the network should be designed in such a way to mitigate these risks and provide benefit to customers through

a comprehensive cost-benefit approach.

Hence it is recommended that the storm threshold remain unchanged at present but CER should

undertake a full consultation with the DSO to determine an appropriate measure for future price

controls. There needs to be fully independently audited network performance information available to

the CER to ensure the validity of performance against any propsed changes in targets.

B.6.2.4 Revised adjustment factors

The target levels for CI and CML for planned outages are proposed based on an assumed level of activity with

respect to different work areas (20kV conversion, cyclic refurbishment, cut-out replacement, etc). Where the

volume of work completed in each of these areas differs from the original assumptions, adjustment factors are

applied to re-calculate the target accordingly.

Additional CML excluded with new lower threshold

CML excluded with current storm threshold

Illustration of impact of proposed change to storm threshold

Page 236: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 231

We note that the DSO has stated that they believe the current scheme does not allow enough flexibility in

relation to volumes of work. It is our opinion that the current scheme is suitably flexible for its purpose.

For the PR4 period, ESBN have proposed increases to the per unit CI and CML allowances for two planned

work programmes compared to PR3. The increases proposed are 77% for the 20kV conversion work

programme and 102% for the and MV overhead line cyclic conversion work programme, as shown in Table

B.25 below.

Table B.25 : Comparison of CI and CML Adjustments for Planned Work Units between PR3 and PR4

Activity Work unit

PR3 Allowances PR4 Allowances Change (%)

CI x 100 per work unit

CML per work unit

CI x 100 per work unit

CML per work unit

CI x 100 per work unit

CML per work unit

20kV conversion km 0.000442 0.00126 0.000784 0.002235 77% 77%

MV overhead line cyclic conversion

km 0.000431 0.00116 0.000869 0.002347 102% 102%

Cut-out replacement Cut-out 0.000044 0.00003 0.000045 0.000027 2% -10%

Minipillar replacement Minipillar 0.000265 0.00095 0.000267 0.000963 1% 1%

LV urban overhead line refurbishment

Span 0.000177 0.00064 0.000178 0.000642 1% 0%

LV rural refurbishment Group 0.000534 0.001514 0.000542 0.00154 1% 2%

Non-scheme new connections

Connections 0.000508 0.0013 0.000513 0.001307 1% 1%

Correction of voltage complaints

Jobs 0.00095 0.00242 0.000958 0.002444 1% 1%

This appears counter-intuitive; it would be expected that the early phases of the 20kV conversion would have

been targeted towards sections of the network with the greatest benefit (i.e. the greatest load and number of

customers). This would ensure that the maximum number of customers benefitted earlier in the programme and

the improvement in network performance would give maximum benefit to ESBN in the incentive scheme.

Hence the later phases of this programme would then be expected to be biased towards parts of the network

with lower customer density, and lower values of adjustment factor would be expected on this basis.

The ESBN submission notes that “the volume of outages required per km of 20kV conversion has proven to be

higher than was anticipated for PR3”. Some explanation has been provided in response to questions on this

including the impact of Scantrepo poles and that there has been an increase in the number of outages required.

In most instances there are lower numbers of customers affected per outage. ESBN have commented that the

20kV conversion is targeted at high load growth and poor voltage networks rather than initially high loaded

feeders, seems reasonable. This may seem to indicate that the customers affected may not reduce over time. It

would however be expected that when planning a work programme the priority would be given to the feeders

which impact most customers for voltage problems. We would generally not expect the impact to be increasing.

For comparison and consistency-checking we have normalised historic and forecast figures to identify the

underlying levels of planned outage CML that would be expected if no change was made to the per unit work

allowances (i.e. the PR3 allowances). This analysis identifies apparent anomalies in the underlying levels of

planned outage CI and CML. As shown in Figure B.16 and Figure B.17, the normalised level of planned CI and

CML has decreased from PR3 to PR4 as a result of lower work volumes being forecast, rather than

improvements in the management of outages due to planned work.

Page 237: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 232

Figure B.16 : CI Normalised with respect to PR3 planned work unit adjustment factors

Figure B.17 : CML Normalised with respect to PR3 planned work unit adjustment factors

Page 238: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 233

ESBN has provided further justification for the proposed increases in adjustment factors for 20kV

conversion and MV overhead cyclic conversion work programmes. There does not however appear to

be sufficient account taken of the approach that would target the feeders which would give the biggest

improvement early, leading to a reduced impact as the programme progresses. We do note the

concerns expressed by ESBN, and feel that this may be an area where there are opportunities for

annual reviews against audited actual values in the work programmes which give greatest concern.

In the interim, we would recommend that the proposed PR4 per work unit allowances be set at 0.95 of

the PR3 figures. Table B.26 outlines these recommended allowances.

Table B.26 : Recommended CO and CML per work unit for PR4

Activity Work unit Recommended PR4 allowances

CI x 100 per work unit CML per work unit

20kV conversion km 0.000420 0.001197

MV overhead line cyclic conversion km 0.000409 0.001102

Cut-out replacement Cut-out 0.000042 0.000029

Minipillar replacement Minipillar 0.000252 0.000903

LV urban overhead line refurbishment Span 0.000168 0.000608

LV rural refurbishment Group 0.000507 0.001438

Non-scheme new connections Connections 0.000483 0.001235

Correction of voltage complaints Jobs 0.000903 0.002299

Using the ESBN’s proposed PR4 work volumes and per work unit allowances, the level of outages in PR4

contributable to work programmes proposed have been calculated. The variance between the outages

contributable to work programmes and ESBN’s proposed planned outages varies between 7.2 and 7.9 for CI

and 13.6 and 15.0 for CML. This difference has been termed the ‘unidentified level of planned outages’ and we

recognise the importance of these outages, particularly where an increase in planned outages leads to a

decrease in unplanned outages. A summary of this information is presented in Table B.27 below.

For comparison, the level of unidentified planned outages included in the PR3 targets was constant at 6.0 for CI

and 10.6 for CML.

Table B.27 : Comparison of Calculated Planned CI and CML against Proposed CI and CML

Planned interruptions 2016 2017 2018 2019 2020

Planned CI contributable to work

programmes

14.4 14.6 14.8 15.0 15.2

Planned CML contributable to work

programmes

38.7 39.2 39.7 40.3 40.8

ESBN proposed PR4 planned CI 22.3 21.8 22.1 22.4 22.8

ESBN proposed PR4 planned CML 52.3 53.1 53.9 54.8 55.8

Unidentified planned CI 7.9 7.2 7.3 7.4 7.6

Unidentified planned CML 13.6 13.9 14.2 14.5 15.0

We recommend that the same level of unidentified planned outages in PR3 be added to the calculated

planned outages for PR4. These supplements of 6.0 and 10.6 for planned CIs and CMLs, respectively,

should be added ex post to the CI and CML per work unit allowances being approved.

Page 239: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 234

B.6.2.5 Smart Metering and Fibre to the Building

ESBN have stated that these programmes are likely to result in an increased level of planned outages to

existing customers over the period and that they believe that the continuity performance targets should be set

appropriately, with an appropriate allowance being set per unit of work delivered. We are minded to agree that

the continuity targets need to be consistent with the obligations of the smart meter programme.

We believe the cost incentive associated with the programme is sufficient incentive for ESBN to manage this

project timely and efficiently.

Hence we recommend that interruptions and outages caused directly by the smart meter programme be

reported separately from the overall CI and CML figures, and excluded from the continuity incentive

scheme entirely.

B.6.2.6 North Atlantic Green Zone

The North Atlantic Green Zone is an EU supported programme of investments in the cross-border region

between Ireland and Northern Ireland. One of the stated aims is to reduce customer interruptions by 54%. In

their submission, ESBN discuss a programme of conversion from 10kV to 20kV and automation of a large

number of overhead lines and switches. The extent (if any) to which such work overlaps within the existing

programmes of planned work in this context is unclear. ESBN have stated that there is no overlap, and that they

will not be seeking to increase continuity Capex should NAGZ not proceed.

The NAGZ programme has been deemed as independent of the existing continuity investment plans and

performance.

B.6.3 RedC

The DSO initially proposed an overall target level of 74%, with this target level fixed for each year of the control

period. Previously, the DSO also proposed that this incentive is given equal weight to the NCCC Customer

Satisfaction weighting, and therefore proposed the use of the same value per 100 basis points difference

against the target, e.g. €721,000 per percent deviance, with a maximum penalty/reward of €1.6m annually. It

proposed that equal value is given to over and under-performance against the target level.

ESBN believes that this incentive should endure and they highlight that the connection volumes are forecast to

increase and that this may impact on customer service achievement – however the forecast levels are below

historical highs. However, we would expect that the scalability and resourcing in areas for connections both in

delivery and in customer contact would comfortably manage the volumes and therefore we would not expect

deteriorating satisfaction levels due to connections levels increasing form a very low level. To suggest this

would appear to assume that as the volumes may increase then the existing resource would be used and thus

perform at a lower level.

An average performance of 82.4% has been achieved for PR3 to date. Given the ease with which the target

has been achieved to date, we believe a more challenging target should be applied to drive continued

improvement in performance.

Furthermore we note that this survey is an annual survey but based on customers who contacted the company

in the preceding six months. Hence CER may wish to consider specifying the timing of the survey so that it

would not be artificially restricted to customers contacting ESBN during the summer months, when logic would

suggest there might be fewer interruption-related enquiries.

Hence we would recommend the target be set at 82.5% to incentivise the DSO to at least maintain their

current performance level.

Page 240: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 235

B.6.4 Customer Satisfaction

ESBN believes that this this incentive should endure and has proposed targets for each area and the overall

(ESATRAT) target as set out in Table B.28 below.

Table B.28 : Customer Satisfaction Proposed Annual Targets

KPI Target

Speed of telephone response 83%

Abandonment rate 5%

Mystery caller 80%

Call back survey 80%

Call referral rate 15%

ESATRAT (performance target) 85%

In PR3 the annual reward was capped at 0.25% of revenue, while the annual penalty was collared at 1.0% of

revenue. This equated to annual maximum reward of circa €1.6m and maximum penalty of circa €6.5m. In a

similar way to the continuity incentive, ESBN would like CER to consider the definition of “Exceptional Events”

from a contact centre perspective where it is not reasonable to expect that the normal targets will be met.

These days could be removed from the incentivised reporting criteria and replaced with the average of all of the

other day’s performance. ESBN is happy to work with CER to define a threshold and mechanism that is

reasonable and appropriate.

Although Exceptional Events days would result in high level of calls, this is likely to be the main (or perhaps

even the only) occasion on which some customers contact the distribution company. The DSO should therefore

have a strong incentive to deal adequately with customers and keep them informed in such circumstances.

ESBN have proposed a target of 85%, which is the same as that during PR3. Given the ease with which this

target has been achieved thus far, we believe a more challenging but achievable target should be considered.

Using the average achieved performance for years 2010, 2011 and 2013 would give a target of 89.9%. (2012

showed a marked dip in performance and was excluded as an outlier; if it were included the average would be

89% instead).

To incentivise continuing improvement in this area, we would recommend that the PR4 ESATRAT target

be set at 89%, with the same reward/penalty scheme as that in PR3 continued; adjusted to 2014 prices.

B.6.5 Metering

In PR3 ESBN was incentivised against a set of Service Level Agreements (SLAs) for the provision of metering

services as set out in the DSO licence. These are:

98% of meters should have 1 reading (DSO or customer) per year.

99% of meters will not have back to back block estimates.

These are incentivised to a value of +/- €1m per year. The targets and performance for the metering incentive

are set out below.

ESBN believes that this set of incentives should continue for the duration of PR4. Meter reading in its current

form is likely to change as Smart Metering infrastructure is rolled out over the coming years. It is appropriate to

review the continuation of the metering incentive model as decisions about Smart Metering rollout are made

over the course of PR4. In the meantime this is an important area of service provision and the ongoing

incentivisation of this activity is encouraged.

A simpler approach may be to restrict the proposed incentive to be applicable only to legacy meters (i.e. not on

smart meters).

Page 241: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 236

In the UK, the accepted industry standard is for at least one meter read per year for 97% of customers94. The

proposed standard by ESBN is a higher standard than the UK, which is generally seen as an international

benchmark.

We recommend that this incentive endure and that the mechanism is reviewed throughout the Smart

Meter rollout programme to monitor its appropriateness and design.

B.6.6 Generation Connections

This incentive was not progressed in PR3 by CER or ESBN and as a result ESBN does not propose a

Generation Connection Incentive in PR4.

B.6.7 Worst Served Customer

ESBN proposes a programme to address the continuity performance received by 4,000 Worst Served

Customers (WSC) during PR3. It is anticipated that this will cost a total of €1.4m.

As yet there is very significant uncertainty as to the extent to which it is possible to address WSC issues in full

and trials to date have not proven conclusive. Nonetheless, ESBN considers this programme to warrant delivery

in the interests of taking measures in addressing the needs of those who experience the worst network

performance.

It is noted that ESBN had 47,400 WSC connected to their network in 2013, or 2.1% of all customers. This is a

large percentage of customers, especially when compared to GB DNOs. Further to this, ESBN claimed circa

€25,000 per annum of the €10m fund available during PR3, indicating a significant underspend in this area. As

the programme by the DSO is not expected to have sufficient valid data till 2017/18 then there would be some

difficulties in determining the impact of measures and the net result of the investment. The DSO have

suggested using UK RIIO data to determine the value of improvement for each worst served customer. The

DSO has also suggested that information they have gathered between November 2014 and April 2015 gives an

indication that they would require considerably higher allowances to deliver improvements.

It should be noted that the information provided in this latest submission significantly raises the allowances

proposed. We do not consider there has been sufficient justification for this increase, and equally any

comparison to UK DNO’s neglects the fact that they have undergone extensive investment over many years in

this area, where the cost per customer has been much lower. We would not consider that the cost per customer

to improve the performance at the start of this programme would be comparable to the cost when a programme

has been in operation for many years. The improvements which can be made diminish and the costs increase

over time so the point in the cycle in which the improvement is targeted has a greater influence over the cost.

One option available to the CER would be to impose a reward/penalty based on a glide path 2020 set of targets,

with financial settlement occurring three years after the year in question on a net present value (NPV) neutral

basis. The incentive would be capped and collared either to a percentage of revenue in that year, or a nominal

amount. The WSC definition requires a three year lag in payment in order to confirm the improved performance

objective. For example, the impact of a scheme designed to reduce the number of WSC by 1,500 which is

implemented in 2016 would only be fully realised in 2019 once three years of data had been collected.

Hence we would recommend introducing an additional reward/penalty scheme of ±€500 per WSC to

incentivise ESBN to deliver on their plan to reduce the number of WSC to 43,400 by 2020. The cap and

floor for such a scheme would need to be discussed between CER and ESBN to determine appropriate

levels by which non-WSC customers are subsidising WSC. We would recommend that the floor be

greater than the proposed funding amount thereby strongly disincentivising ESBN to do nothing.

We note that there is a large degree of uncertainty when planning WSC schemes and hence would

encourage the use of an appropriate dead band either side of the target (i.e. de minimis threshold). We

would encourage further consultation with ESBN regarding the introduction of this additional element

94 http://www.elexon.co.uk/reference/market-compliance/peer-comparison-graphs/

Page 242: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 237

to the WSC incentive scheme. To determine the effectiveness of an introduced programme, ESBN

should provide evidence that customer interruptions in the targeted area have reduced by a target level,

for example 25%, which was used in DPCR5 in GB. We would again emphasise that any historic and

improved performance needs to be independently validated through an audited sample of the defined

WSC’s.

B.6.8 CAPEX Delivery

ESBN has stated that it does not intend to put forward a capex delivery incentive for PR4.

B.6.9 Potential new incentives

In addition to those incentive mechanisms already employed, we have considered potential additional

mechanisms for consideration by CER to incentivise continued improvement in ESBN’s performance. Areas to

consider in this respect would include:

Different continuity targets for urban and rural customers – given the different characteristics of rural

customers (typically low density, geographically dispersed and often on single spur connection) compared

with urban customers (higher density, geographically concentrated and with greater degrees of redundancy

in connections), consideration has been given to the possibility of setting different targets for such

customers. Rural customers typically experience a greater frequency of outages and outages of longer

duration. – This would require customers to be classified by type, which in the past stakeholders have had

difficulty agreeing on, and retrospective analysis of historical performance in order to set appropriate

performance base-lines. However classification has been achieved in other jurisdictions such as Australia,

where the Australian Energy Regulator (AER) classifies customers as CBD, urban, short rural and long

rural. If material differences were identified in service levels for rural customers compared to urban, it could

lead to pressure for discounted pricing for disadvantaged rural customers (despite the fact that such

customers are more expensive to serve than urban customers).

Load Connections – specifying a target time to provide a connection offer/quotation and target time to

connect (following acceptance of connection offer). Different targets would need to be specified according

to customer type (e.g. scheme housing, non-scheme housing, small commercial, medium commercial, etc).

Reporting of volume of customer complaints by different categories (e.g. metering, billing, new

connections, interruptions, voltage, etc). Customer satisfaction is currently assessed by call-back surveys,

mystery caller surveys and the RedC survey. Whilst these provide an indication of satisfaction levels for

the customers contacted, it does not provide any insight on the aggregate number of complaints received

by the DSO.

Compiling statistics on the basis of number of complaints received would provide information that could

guide the setting of appropriate areas for incentives in future price control periods (PR). Given the lack of

historical information, it may not be appropriate to set quantitative targets at this stage. However applying

a requirement to compile and report such statistics on an annual basis during PR4 would then provide a

base-line for quantitative targets in subsequent PRs.

Identification of vulnerable customers – an incentive to ensure the DSO maintains accurate information

on vulnerable customers connected to its network and provides assistance to such customers (for example

during planned and unplanned outages). Note: Delivery of this may require additional opex.

B.6.10 Possible new incentives to consider

Table B.29 present possible new incentives to be considered for application in PR4.

Table B.29 : Proposed Incentives for PR4

Incentive Proposed incentive PR4

Connections TBA / ESBN to propose

Reporting of customer complaint

statistics Reporting requirement only – incentive mechanism to develop PR5

Page 243: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 238

Vulnerable customers TBA / ESBN to propose

B.7 Recommendations

At this stage, our key recommendations for further work in the development of the proposed incentives are:

1) Losses – ESBN to be tasked with proposing an outline project plan and timetable for the development of a

methodology for calculation of losses (including calculation of accruals for un-metered consumption)

Planned outages – provide delivered work volumes for 2011 – 2014 in stand alone document

Continuity incentive storm threshold – remain unchanged but reviewed with independently audited data

as the baseline.

Continuity incentive – To operate to the proposed targets but allow ESBN to provide further detail to

support their proposed CI and CML adjustment factors for planned work as part of the independently

audited reporting recommended to ensure accurate data is used in determining rewards and penalties.

Worst Served Customers – reward/penalty scheme to be introduced to encourage implementation of

initiatives

Connections – ESBN to propose new incentive incorporating target times for making connection offers to

different categories of customer connections, target time for completion of connection following offer

acceptance.

Customer complaint reporting – ESBN to be requested to commence reporting of customer complaint

numbers by category of customer and category of complaint.

Recommendations to consider going forward in future price control periods include:

2) Audited continuity metrics – it is not clear whether the figures presented for interruptions and outage

durations have been independently audited. We would recommend that ESBN submit independently

audited information to the CER annually.

B.8 Findings

The interim findings of this report are set out below by incentive scheme, followed by a summary of performance

in PR3, ESBN’s proposed PR4 incentives and possible new incentives to consider.

B.8.1 Losses

ESBN believe that losses are improving however consistent reporting has been challenging. ESBN have not

applied for any rewards in relation to losses during PR3 and have not proposed a PR4 losses scheme.

Jacobs recommends that ESBN propose an outline project plan and timetable for the development of a robust

losses calculation methodology.

B.8.2 Continuity

During PR3 ESBN have, on average, met their SAIFI targets and marginally missed their SAIDI targets. Total

SAIFI has reduced by 19.3% between 2010 and 2015 (current forecast), while total SAIDI has increased by

1.3% in the same time.

ESBN has proposed adjustments to the storm threshold and per work unit allowances for planned outages in

PR4. Jacobs recommends the storm threshold remain unchanged. We believe increases in the per work unit

allowances is counter intuitive and recommend that PR4 allowances are set at 95% of PR3 allowances. There

have been a number of presentations regarding the reasons for the changes proposed by ESBN, however we

believe that the current reporting needs to be independently validated to ensure an accurate baseline, and then

the actual changes going forward due to any change in the storm threshold and unit allowance for work

programmes can be accurately tracked.

Page 244: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 239

Jacobs further recommends that planned outages are incentivised above unplanned outages. As such, we

recommend that rewards and penalties for planned outages are half that of unplanned outages. This will require

rewards and penalties to be calculated on both planned and unplanned in PR4, rather than the total sum as in

PR3.

Higher forecast work volumes in PR4 are due to increase planned outages across the network.

We agree with ESBN that the smart metering programme will lead to a large increase in planned outages.

Therefore we recommend that outages directly associated with this programme be excluded from the continuity

incentive scheme and be reported independently of other outages. This is important to safeguard the interests

and goals of the smart meter programme; most notably the quality of service and safety of installers is essential.

B.8.3 RedC

ESBN have reached the annual reward cap for each year of this incentive. We recommend the PR4 target is set

higher at 82.5%, which is approximately the average score achieved over the past five years.

B.8.4 Customer Satisfaction

ESBN have reached the annual reward cap for each year of this incentive. We recommend the PR4 target is set

higher at 89.0%, which is approximately the average score achieved over the past five years.

B.8.5 Metering

Metering targets are set at above standard levels and ESBN has been successful in achieving these throughout

PR3. We believe this incentive should endure in its current form.

B.8.6 Generation Connections

The generation connections incentive was not progressed in PR3 and ESBN has not proposed an incentive for

PR4.

We recommend that ESBN propose a new connections incentive scheme for PR4.

B.8.7 Worst Served Customers

Of the €10m fund granted to ESBN for approved worst served customer (WSC) programmes, only circa €25,000

p.a. has been spent annually. According to 2013 outturn figures, ESBN had 47,400 WSC on their network or

2.1% of total customers.

In PR4 ESBN initially proposed a €1.4m fund to alleviate 4,000 WSC from the network. We are of the opinion

that there is not enough incentive for ESBN to deliver improved service to these customers and therefore

recommend an enhanced scheme. The enhanced scheme introduces a reward and penalty payment for the

number of WSC alleviated, with payments occurring three years post-programme implementation on a NPV-

neutral basis. The payments could be capped and floored at an appropriate level to provide a disincentive to

ESBN for non-action.

B.8.8 CAPEX Delivery

The capex delivering incentive was suspended in 2013 after discussion between CER and ESBN.

ESBN has not proposed a capex delivery incentive for PR4.

B.8.9 Summary of Performance in PR3

Table B.30 provides a summary of the DSO’s PR3 performance in addition to the DSO’s proposed incentives for

PR4

Page 245: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 240

Table B.30 : Summary of PR3 Performance

Incentive Value

(€m, 2009 prices)

Incentive earned

(€m, min - max)

DSO’s proposed

incentive PR4

Losses +/- €10.5m Not claimed No proposal

Continuity +/- 1.5% of revenue CI ~€10.5m;

+/- 1.5% of revenue CML ~€10.5m €6.2m - €8.6m

+/- 1.5% of revenue CI

+/- 1.5% of revenue CML

RedC +/-€1.6m €1.6m +/- €1.6m

Customer Satisfaction +€1.6m / - €6.9m €1.6m +€1.6m / - €6.9m

Metering +/- €1m €0.5m - €0.8m +/- €1m

Generation connections Discontinued Discontinued No proposal

Worst served customer €10m fund available €25k pa claimed €1.4m fund

Capex delivery +/ - €7m - Discontinued Discontinued No proposal

B.8.10 Possible new incentives to consider

Table B.31 provides a list of possible new incentives to be considered in PR4.

Table B.31 : Possible New Incentives to Consider

Incentive Proposed incentive PR4

Connections TBA / ESBN to propose

Reporting of customer complaint

statistics Reporting requirement only – incentive mechanism to develop PR5

Vulnerable customers TBA / ESBN to propose

Page 246: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 241

Appendix C. Smart Meter Procurement

The DSO will undertake a procurement tender for smart meters in 2014/15 which will be in line with CER’s

decision on the smart metering detailed design. Therefore expected capital costs for smart metering will not be

known until 2015.

CER requires an appropriate and rigorous framework and methodology that will allow CER to assess the

following over the course of the PR4 period and future price controls:

a) capital and operational expenditure on smart metering by the DSO; and

b) the process, timing and methodology of recovery of those expenditures.

c) a review of programme expenditure and reasonable costs

In particular, CER will use the framework, and the PR4 process in general, to ensure that consumers

demonstrably gain the benefits (inter alia through DUoS charges) that the expenditures on Smart Metering will

bring to the wider operation and costs of the DSO business.

Note that expenditure on “Smart Grids” is has been addressed in the relevant business capex forecast. The

main benefit that has been incorporated into the forecasts is an assumption of peak load reduction arising from

customer behaviour changes. This assumption has the effect of reducing the peak load forecast by 4% and

consequently reducing the reinforcement expenditure that would otherwise have been initiated.

This document provides this framework.

C.1 Assumptions

At the time of writing this report the smart meter costs have not been finalised as tenders have not been

submitted. In addition revenue streams can be estimated but cannot be calculated with a high degree of

accuracy as they are inherently variable by their nature; whether it is customer take up or seasonal climatic

variations. Therefore this report will concentrate on the methodology framework of how to monitor capital and

operational costs with respect to the return on investment over the PR4 period.

The recommendations that follow are largely based upon forecast and assumptions information supplied by

CER, ESBN and PWC95 many of which are still the subject of CER decisions. Certain elements of these could

change significantly as policy decisions are formulated. CER is advised to base the templates that are issued to

the companies on the timing and programme that are agreed for use in the approved cost benefit analysis

(CBA.) The recommendations will identify the key cost components and the framework in which they can be

assessed.

C.2 Project Management Framework Methodology

The ESBN smart meter rollout is ambitious in that it has significant costs and high volume, estimated at 1.9M

electricity smart meter changes and 0.5M smart gas meter changes. As has been stated the firm capital and

revenue costs are not available at the time of writing this report. It is therefore recommended that when these

are available that there is a review the real business case and a ‘go no go’ decision by the key stakeholders is

taken. This will also be an opportunity to review the smart meter roll out timetable and revaluate whether this is

achievable bearing in mind that the resource requirement will be needed at the same time that the UK will be

also carrying out an estimated 22 million smart meter changes.

The requirement for a robust and rigorous framework for the rollout of smart metering and associated

technology would be best served by an industry standard project management system, such as Prince2, which

will give a framework that caters for all of the key elements of the ESBN smart project forecast deliverables. The

project management tool should provide a management system to capture, monitor and control the key

95 PWC report NSMP [2] (Electricity &Gas) Cost Benefit Analysis report Oct 2014

Page 247: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 242

elements of the project. The overall aim will be to minimise risk and uncertainty. We would advise that as part of

the assessment process that CER confirms that the appropriate project control structure is in planned.

C.2.1 Smart Project Streams

The ESBN commitments over the PR4 period naturally breakdown into three areas:

1. Smart Meter rollout

2. Smart Grid rollout

3. Added value benefits associated with these technologies when used in conjunction with existing business

practice and other new initiative responses by the business. This will also include the inherent benefits for

Irish energy industry. The overall benefit to the energy generation, distribution and supply industry could

then be calculated from a composite study of the three report streams.

The first area is covered in this report, point 2 is covered in the forecast capex assessment and point 3 needs to

be considered by stakeholders but will not impact DUoS.

C.2.2 Project Initiation Documents

Each of the smart projects should be recognised and broken down into their constituent parts for the evaluation

of scope, size, complexity, resources, timescales and forecast for their ability to deliver against the forecast

benefits. This should include a strong and robust business case for return on capital investment, earned value

against actual cost, cumulative savings and identify a breakeven point in time. For metering this may involve

multiple project initiation documents covering geographic areas or time based projects (e.g. Year 1 rollout)

The table below shows the scale on the proposed implementation programme and an indication of the resource

requirement. Note that the resource requirement indicated is conservative as many of the installations may be

required on evenings and weekends and therefore shift teams may be required. At present we have not been

presented with a resource plan by ESBN.

Table C.1 : Smart Meter Rollout Forecast Volumes and Resources

2017 2018 2019 2020

80% of total 1.9M 1520000 meters 10% 35% 40% 15%

Annual meter installation 152000 532000 608000 228000

Monthly meter installation (22day month) 12667 44333 50667 19000

Number of installers (assuming 4 per day/ single

working) 144 504 576 216

The resource implication should not be underestimated given that the UK is undertaking a programme ten times

the size in the same period and therefore access to appropriate staff will need to be considered in any project

initiation documents. The assumptions on labour requirements above are to indicate the scale of the project

only. The actual productivity of the installation teams should be assessed as part of the tendering process.

C.2.3 Reporting Schedule

CER require ESBN to provide robust information on the physical and financial progress of the metering

programme to justify any allowance for the expenditure. In addition CER require ESBN to identify the benefits

that are accrued to make sure that any efficiencies that cover activities that are already funded under the PR4

settlement are identified to avoid double counting of cost or benefits.

The reporting schedule needs to meet the CER’s needs as they are in a supervisory role and not a

management role and consideration of the reporting burden needs made. Therefore it is recommended that

reporting of installation progress and cost /benefit is captured on a monthly basis and summated by quarter.

Page 248: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 243

Quarterly reporting should be sufficient for the CER and the monthly granularity will enable this frequency of

reporting to be increased if required.

The proposed reporting templates are provided in Annex A-C. These provide the:

CER information requirement

Data structure to be completed

Required Narrative responses

Reporting timeframe

C.2.4 Ownership of Responsibilities

From the outset of the project clearly defined rolls, responsibilities and ownership need to be identified and

agreed between CER, ESBN, suppliers and contractors.

The CER’s role will be to allow the appropriate expenditure to ESBN to undertake the works, monitor the

performance to ensure that the programme is being undertaken efficiently and that the planned the benefits are

achieved and are passed on to customers.

ESBN will be responsible for determining the delivery method, the project management and all associated

activities in line with requirements/obligations/licence conditions as set out by CER.

This framework is intended to allow CER to have the oversight that it requires to monitor the implementation

programme and the delivery of benefits; while making sure that there is no double counting of costs/benefits

against the allowances provided for the core network activities in PR4.

C.3 Smart Meter Project Rollout

In this section we detail the aspects of capital and operating costs that we would expect to be captured to

monitor the delivery of the smart meter programme along with the expected benefits. These are intended to

provide a framework for assessing the impact on DUoS. As the metering systems will facilitate the Gas Smart

metering process then the costs need to be correctly recorded. Costs could either be recorded net of any Gas

Metering element or costs and revenues could be identified separately to allow them to be removed later. CER

indicate that the latter would be preferred as it increases transparency.

C.3.1 Smart Meter Capital and Operational Costs

This section will identify the key areas of capital and operational costs of the electricity smart meter project that

will be expected to be part of the business case and therefore monitored as part of the framework. The aim is to

provide an explanation of what would be expected in the justification documentation.

C.3.1.1 Purchase cost of electricity smart meters

The meter purchase capital cost should be recorded separately from installation as the programme may

require significant advance purchases to ensure stock is available to meet the challenging installation

programme. Alternatively a supply and install contract may be the preferred option. In this case the meter

element should be identified separately.

Any additional capital cost associated with systems to facilitate the Gas Smart metering system also need to be

captured. These are likely to be data transmitters where a single data transmitter is used to send Electricity and

Gas data. These can be separate devices or integral to the Electricity meter. An agreed cost apportionment

could be used to allocate portion of the costs to the Gas Metering system.

Page 249: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 244

C.3.1.2 Smart meter installation

The capital cost of installation is not known at this time. The Price Cooper Waterhouse (PwC) report has

offered an estimated rollout programme for smart meter installation in line with the project delivery time table.

There is a target of 80% of all smart meters to be installed by 2020. The installation schedule is: 2017 10% of

all smart meters, 2018 35%, 2019 40% and 2020 15%. This assumption may be used to forecast the delivery

schedule however ESBN should confirm prior to project commencement and this will provide the baseline for

CER to monitor progress against.

Costs of disposal of existing meters should be captured. It is not agreed if these will be treated as capital or

operating cost at this time. Normally we would expect any replacement to be wholly capital. ESBN should agree

the capitalisation policy with CER.

C.3.1.3 Communication System

The capital cost of the associated communications system should also be identified if it is separate to the Meter.

E.g telecommunications links (including GPRS charges)

C.3.1.4 Data management of smart meters

This should incorporate capital and operational costs of back office IT operations related to: migration from

the existing systems, data storage, data security availability and integrity, web portal, and customer service

integration for enquires and changes.

C.3.1.5 Electricity meter customer service interface

Capital and operational costs of dealing with the telephone and online customer enquiries and complaints (do

not include costs for the IT systems in C.3.1.3 above.

C.3.1.6 Smart meter repairs and maintenance

Repairs and maintenance operational cost associated with identification and rectification of faults on the

metering systems. We would expect replacement of faulty meters to be an operational costs in line with existing

repairs and maintenance practice. However an argument can be made for capital replacement if the whole unit

is replaced. ESBN will need to be clear in the treatment of any capital repairs.

C.3.1.7 Energy consumption by smart meters

Energy associated with the internal power requirement of the metering device. This will not be able to be

individually measured and will in practice present as system loss. However the choice of meter will drive the

energy consumption and so a typical value based on the technical specification should be recorded – this is

effectively an Operational cost. This will be based on the technical specification value and the volumes

installed.

C.3.1.8 Smart meters manual reads

This captures operational cost associated with maintaining a manual read for smart meters that are located

where there is no mobile network coverage and will therefore have to be provisioned for by traditional meter

reading visits. Note that this will be used to gauge the number of sites impacted. It would be expected that

reduction in meter read costs are a benefit arising from the smart meter programme and as we would expect

such benefit to be apportioned based on the roll out of the programme then any cost assorted with meters that

do not give the expected benefit should be captured here. If the benefits are only claimed based on actual

manual reads avoided then no additional cost is required to be monitored here. ESBN will be required to

demonstrate that residual manual reads are undertaken efficiently. It is understood that there are economies of

scale in manual meter reading however, we would expect manual reads to be required in clusters due to lack of

communication coverage which should limit the impact therefore the base efficient level will be the current cost

Page 250: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 245

on manual reads to incentivise ESBN to avoid leaving isolated individual properties. ESBN will be required to

justify any deviation from the current manual meter reads unit cost.

C.3.2 Smart Meter Savings and Benefits

This section will identify the kind of key savings of the electricity smart meter project that will be monitored. All

the values will need to be identified by ESBN as part of the project reporting.

C.3.2.1 Avoided meter readings (pavement reading)

Operational Cost saving based on manual visits no longer being required to read all customer energy meters.

The costs should accurately reflect the reduction in manual read costs. If average costs per meter installed are

used then costs of reading non- networked meters will need to be included in operational costs as in C.3.1.7

above.

C.3.2.2 Meter change deferral for 15 years

Capital Expenditure saving associated with the standard end of life change of old meters this should reflect

historic programme expenditure costs that would have been incurred. This is captured as an avoided future cost

which will be relevant for meters that would have been due for replacement soon after the smart meter roll out

however there is also an NPV cost of replacing the existing meters before the end of life which should be

factored into any business case. This can be minimised by replacing older meters earlier in the programme

subject to compliance with the overall rollout programme requirement.

C.3.2.3 Meter Fault savings

Operational Expenditure saving due to reduced fault costs due to new meters. This should be based on the

average R&M cost per meter. The costs of R&M on new meters is captured as per C.3.1.5 above.

C.3.2.4 Disconnections and reconnections

Operational savings as smart meters have the capability of be remotely switched on or off. These savings will

need to be supported by reference to the actual Disconnection/Re-connection instruction sent and evidenced by

the average cost of historic practice.

C.3.2.5 Voltage complaints

Operational saving as Smart meters monitor system voltage which can be remotely monitored and recorded.

Normally a voltage recorder would have to be installed to verify customer complaints. These savings will need to

be supported by reference to actual voltage complaints managed using smart meter data and the average cost

of traditional voltage recording less the cost of accessing the smart meter data. ESBN will be required to adjust

any direct charges to customers (where applicable) to reflect the reduced costs.

C.3.2.6 Prepayment meters

Operational saving as simplified prepayment debit arrangements will be available for customers without having

to install a separate meters. ESBN should be able to identify the prepayment meter arrangements implemented

through Smart meters and identify the historic cost of providing the same service.

C.3.2.7 Avoided theft

Operational savings as smart meters have more security features than traditional meters and should therefore

reduce theft. Identification of actual savings will difficult as a significant amount of theft is not detected therefore

the only savings that should be documented are the reductions against current monthly averages. It should be

noted that a whole system roll out will, by necessity, include visits to each premises which may identify

additional tampering. Estimates based on any theft identified during the installation process should also be

included.

Page 251: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 246

C.3.2.8 Reduced Network Investment cost

Impact of enhanced information

Smart meters can provide accurate feeder loading data so that networks can be designed so as to avoid or

defer asset reinforcement. ESBN may be able to identify planned projects that can be deferred due to more

detailed load information. e.g. load profiles of standby feeders with different peak times allowing assessment of

n-1 capability on a time of day basis. Capital expenditure savings should only include the net present value

(NPV) of any deferral.

Impact of demand reduction

Demand Side Response and ‘Time of use’ tariffs which are predominantly used to reduce peak loads and

reduce overall generation costs will have an impact on distribution systems. However, this will be very

dependent on the actual network. Savings will only be made if load related investment was imminent on a

particular part of the network and some deferral can be attributed to consumer led demand reduction. Any

capital expenditure savings will need to demonstrate that the demand reduction or peak shift is not due to

other economic factors and only include the NPV or any deferral. We note that in ESBN’s PR4 submission an

assumption of 4% load reduction due to smart metering has been made and this has led to an investment plan

being put forward based on a 0% load growth scenario. This assumption effectively obscures specific project

cost benefits and therefore to fully support a business benefit assessment ESBN would be required to provide a

counterfactual investment requirement based on no load reduction from Smart Metering.

Post implementation the 4% demand reduction assumption should be tested using a sample set of customers to

isolate the smart metering impact from general growth. This should be achievable as through the

implementation programme there will be groups of customers with and with-out smart meters, therefore the non-

smart meter demand effects can be isolated by comparing load to pre-smart meter programme levels.

C.3.2.9 Fault management benefits

Smart meters could allow identification of customers who have lost supply without customers having to make

contact with the company. This should provide benefits in fault identification and understanding of the extent of

overhead system faults; which will mean that the correct staff can be dispatched in the first instance and thus

reduce cost and duration of interruptions. This will have an operating cost reduction and SAIDI reduction.

C.3.3 Benefits to the Irish Energy Industry

In addition to the above benefits there are wider benefits to the Irish energy generators, suppliers and

customers that may be considered but will not directly impact ESBN and so will not impact DUoS.

C.4 Recovery of expenditures

As a capital programme with consequent operational costs and benefits, we would expect the DSO net Capex

and net Opex derived from the agreed Smart Metering business case to be added to the allowed PR4

revenues. This will mean that the required efficient capex/opex expenditure would be allowed but any displaced

costs that are already included in PR4 allowance will be reduced accordingly. This will remove any double

allowance.

As some of the installation and operational costs of the electricity meters will facilitate the Gas Smart Metering

system then we would expect there to be a revenue stream from the gas businesses that will offset the costs

associated with this facilitation.

We would expect expenditure on the metering installation programme and associated communication system to

be recovered as a capital addition to the regulatory asset base. We note that in PR3 smart meters were allowed

to be allocated to a separate depreciation pot with a depreciation period of 10 years while standard meters are

included in the Network Asset base at 45 years depreciation. There are also separate depreciation lives for IT

and communication assets that are appropriate for the systems to support the smart meters.

Page 252: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 247

Clearly the technical asset life of the smart meter equipment is less that the average deprecation life assigned

to distribution assets. However, the new meters replace existing meters with generally similar asset life

expectancy and so it could be argued that they could be included in the network asset base.

We provide recommendations on the appropriate technical life of assets and the impact on the regulated

deprecation period in Interim Report 8/9 – ‘Depreciation of RAB’ however the impact of the smoothing of the

costs is not discussed. With a separate depreciation pot the full impact of the smart meter programme is funded

by customers over a relatively short period. This has not been the case with conventional metering. The 45

year depreciation period (based on a weighted asset base life) smooths the costs to customers and inclusion of

the metering assets does not significantly affect the weighted asset base life; certainly not to the extent that the

weighted life approaches the 45 depreciation period. Thus including smart meters in the general network asset

base may provide a way of smoothing the up-front cost of the programme to customers.

This should therefore be considered as an option in any consultation.

Page 253: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 248

ANNEX A: Smart Metering Reporting Framework

Project management of the Smart Meter rollout should incorporate rigorous monitoring and control of the smart

meter installation and the associated capital and operating costs over the PR4 period and future price controls

including tracking of benefits to allow validation of the business case.

Below we present the recommended reporting framework templates for monitoring the installation programme,

implementation costs and accrued DUoS impacting benefits.

Smart Meter Cost Allowance

The expenditure allowance will require a detailed submission of costs proposed costs and benefits. The

definitions are detailed in Annex B. In addition, the cost submission should be accompanied by a detailed

business case and responses to the relevant narrative questions in Annex C.

Table C.2 : Smart Metering Cost Submission

Cost Reporting Area 2016 €m 2017 €m 2018 €m 2019 €m 2020 €m

Smart meter purchase cost (Capex)

Smart meter installation (Capex)

Communication System (Capex)

Communication System (Opex)

Data management (Capex)

Data management (Opex)

Customer contact centre (Capex)

Customer contact centre (Opex)

Faulty meter (Capex)

Faulty meter (Opex)

Smart meter energy cost (Opex)

Smart meter manual Reads (Opex)

Other (Capex)*

Other (Opex)*

Table C.3 : Gas Metering Facilitation

Cost Reporting Area 2016 €m 2017 €m 2018 €m 2019 €m 2020 €m

Costs for Gas metering facilitation

(Capex)

Costs for Gas metering facilitation

(Opex)

Revenue for Gas metering

facilitation

Page 254: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 249

Table C.4 : Smart Metering Benefits Submission

Cost Reporting Area 2016 €m 2017 €m 2018 €m 2019 €m 2020 €m

Meter reading (Opex)

Meter change deferral (Capex)

Meter R&M (Opex)

Dis/reconnection (Opex)

Voltage Complaint (Opex)

Prepayment Meter (Capex)

Prepayment Meter (Opex)

Theft Reduction (Opex)

Network Investment (Capex)

Fault management (Opex)

Other (Capex)*

Other (Opex)*

The efficient net Capex and Opex arising from this submission will be agreed and added to the RP4 allowances.

The Smart Meter Rollout

From a regulatory perspective quarterly update reports and an annual substantive report on implementation

progress would be recommended. The quarterly reports would give a brief explanation of any deviations for the

years plan and identify recovery actions being undertaken with an annual submission providing detailed review

of programme and unit costs with any unit cost or programme deviations explained along with any effect of the

current year’s performance on future delivery. The annual report should also provide the targets that the follow

year will be monitored against and the revised overall programme for implementation and benefit realisation

with reference back to the original Project Initiation Document business case.

The quarterly and annual report should be captured in the format below to enable CER to assess the

programme and financial progress.

Page 255: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 250

Table C.5 : ESBN Smart Meter 2017 Rollout Project Performance

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Forecast installation No.

for the month 12667 12667 12667 12667 12667 12667 12667 12667 12667 12667 12667 12667

Actual installation No. for

that month

Variance

Cumulative total No.

behind forecast

Planned Cost (Capex)

Actual Cost (Capex)

Planned Cost (Opex)

Actual Cost (Opex)

Planned Benefit (Capex)

Actual Benefit (Capex)

Planned Benefit (Opex)

Actual Benefit (Opex)

Planned Net Capex

Actual Net Opex

Planned Net Opex

Actual Net Opex

When measuring variance a RAG Red Amber Green project indicator system should be used. Green on track,

Amber <10% of forecast and Red <20% of forecast

To allow full reference back to the business case the figures in the summary sheets should be derived from

detail sheets that align to the specific cost and benefit areas as presented in Table C.5 and Table C.6 below.

Smart Meter Capital and Operating Costs

The tables below provide the supporting reporting framework where monthly and cumulative costs can be

tracked. These should be accompanied by a narrative as described in Annex C.

Page 256: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 251

Table C.5 : ESBN Smart Meter Capital and Operational Expenditure Forecast and Actual

Cost Reporting Area Month 1

Actual

Month 2

Actual

Month 3

Actual

Quarterly

Actual

Quarter

Planned

Quarter

Variance

Smart meter purchase cost (Capex)

Smart meter installation (Capex)

Communication System (Capex)

Communication System (Opex)

Data management (Capex)

Data management (Opex)

Customer contact centre (Capex)

Customer contact centre (Opex)

Faulty meter (Capex)

Faulty meter (Opex)

Smart meter energy cost (Opex)

Smart meter manual Reads (Opex)

Other (Capex)*

Other (Opex)*

*any reported costs under ‘Other’ will need a detailed explanation

Any costs and revenues associated with Gas Smart Meter facilitation can be captured in the table below if

required however these will be dependent on the overall programme and could therefore just be determined

based on the proportion of the total system costs in Table C.5 above.

Table C.6 : ESBN Gas Smart Meter facilitation cost and revenue

Cost Reporting Area Month 1

Actual

Month 2

Actual

Month 3

Actual

Quarterly

Actual

Quarter

Planned

Quarter

Variance

Costs for Gas metering facilitation

(Capex)

Costs for Gas metering facilitation

(Opex)

Revenue for Gas metering facilitation

Page 257: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 252

ESBN Smart Meter Savings and Benefits

Table C.7 : ESBN Savings and Benefits Forecast and Actual

Cost Reporting Area Month 1

Actual

Month 2

Actual

Month 3

Actual

Quarterly

Actual

Quarter

Planned

Quarter

Variance

Meter reading (Opex)

Meter change deferral (Capex)

Meter R&M (Opex)

Dis/reconnection (Opex)

Voltage Complaint (Opex)

Prepayment Meter (Capex)

Prepayment Meter (Opex)

Theft Reduction (Opex)

Network Investment (Capex)

Fault management (Opex)

Other (Capex)*

Other (Opex)*

*any reported costs under ‘Other’ will need a detailed explanation

Page 258: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 253

ANNEX B: Smart Metering Framework – Cost Definitions

Cost/Benefit Explanatory Note

Purchase cost of

electricity smart meters

The meter purchase capital cost is recorded separately from installation as the

programme may require significant advance purchases to ensure stock is

available to meet the challenging installation programme. Alternatively a supply

and install contract may be the preferred option. In this case the meter element

should be identified separately.

Smart meter installation The capital cost of installation including the associated communications

systems.

Costs of disposal of existing meters as part of the installation should be captured.

Communication Costs The capital cost and operational costs of the associated communications

system if it is separate to the Meter. E.g telecommunications links (including

GPRS charges)

Data management of

smart meters

This should incorporate capital and operational costs of back office IT

operations related to: migration from the existing systems, data storage, data

security availability and integrity, telecommunications links (including GPRS

charges), web portal, and customer service integration for enquires and changes.

Electricity meter

customer service

interface

Capital and operational costs of dealing with the telephone and online customer

enquiries and complaints (do not include costs for the IT systems in C.3.1.3

above.

Smart meter repairs and

maintenance

Repairs and maintenance operational cost associated with identification and

rectification of faults on the metering systems. We would expect replacement of

faulty meters to be an operational costs in line with existing repairs and

maintenance practice. However an argument can be made for capital

replacement if the whole unit is replaced. ESBN will need to be clear in the

treatment of any capital repairs.

Energy consumption by

smart meters

Energy associated with the internal power requirement of the metering device.

This will not be able to be individually measured and will in practice present as

system loss. However the choice of meter will drive the energy consumption and

so a typical value based on the technical specification should be recorded – this is

effectively an Operational cost. This will be based on the technical specification

value and the volumes installed. An alternative to monthly reporting could just be

notification of the ‘per Meter’ value to the CER.

Smart meters manual

reads

This captures operational cost associated with maintaining a manual read for

smart meters that are located where there is no mobile network coverage and will

therefore have to be provisioned for by traditional meter reading visits. Note that

this will be used to gauge the number of sites impacted. It would be expected that

reduction in meter read costs are a benefit arising from the smart meter

programme and as we would expect such benefit to be apportioned based on the

roll out of the programme then any cost assorted with meters that do not give the

expected benefit should be captured here. If the benefits are only claimed based

Page 259: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 254

Cost/Benefit Explanatory Note

on actual manual reads avoided then no additional cost is required to be

monitored here. ESBN will be required to demonstrate that residual manual reads

are undertaken efficiently. It is understood that there are economies of scale in

manual meter reading however, we would expect manual reads to be required in

clusters due to lack of communication coverage which should limit the impact

therefore the base efficient level will be the current cost on manual reads to

incentivise ESBN to avoid leaving isolated individual properties. ESBN will be

required to justify any deviation from the current manual meter reads cost.

Avoided meter readings

(pavement reading)

Operational Cost saving based on manual visits no longer being required to read

all customer energy meters. The costs should accurately reflect the reduction in

manual read costs. If average costs per meter installed are used then costs of

reading non- networked meters will need to be included in operational costs of

manual reads above.

Meter change deferral

for 15 years

Capital Expenditure saving associated with the standard end of life change of

old meters this should reflect historic programme expenditure costs that would

have been incurred. This is captured as an avoided future cost which will be

relevant for meters that would have been due for replacement soon after the

smart meter roll out (ESBN should state if these costs are included in the PR4

expenditure forecast) however there is also an NPV cost of replacing the existing

meters before the end of life which should be factored into any business case.

This can be minimised by replacing older meters earlier in the programme.

Meter Fault savings Operational Expenditure saving due to removed fault costs of old meters. This

should be based on the average R&M cost per meter. The costs of R&M on new

smart meters are captured separately. ESBN should indicate if these costs are

included in the Operational Cost submission in PR4.

Disconnections and

reconnections

Operational savings as smart meters have the capability of be remotely

switched on or off. These savings will need to be supported by reference to the

actual Disconnection/Re-connection instruction sent and evidenced by the

average cost of historic practice.

Voltage complaints Operational saving as Smart meters monitor system voltage which can be

remotely monitored and recorded. Normally a voltage recorder would have to be

installed to verify customer complaints. These savings will need to be supported

by reference to actual voltage complaints managed using smart meter data and

the average cost of traditional voltage recording less the cost of accessing the

smart meter data. ESBN will be required to adjust any direct charges to

customers (where applicable) to reflect the reduced costs.

Prepayment meters Operational saving as simplified prepayment debit arrangements will be

available for customers without having to install a separate meters. ESBN should

be able to identify the prepayment meter arrangements implemented through

Smart meters and identify the historic cost of providing the same service.

Avoided theft Operational savings as smart meters have more security features than

traditional meters and should therefore reduce theft. Identification of actual

savings will difficult as a significant amount of theft is not detected therefore the

only savings that should be documented are the reductions against current

Page 260: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 255

Cost/Benefit Explanatory Note

monthly averages. It should be noted that a whole system roll out will, by

necessity, include visits to each premises which may identify additional

tampering. Estimates based on any theft identified during the installation process

should also be included.

Impact of enhanced

information

Smart meters can provide accurate feeder loading data so that networks can be

designed so as to avoid or defer asset reinforcement. ESBN may be able to

identify planned projects that can be deferred due to more detailed load

information. e.g. load profiles of standby feeders with different peak times

allowing assessment of n-1 capability on a time of day basis. Capital

expenditure savings should only include the net present value (NPV) of any

deferral.

Impact of demand

reduction

Demand Side Response and ‘Time of use’ tariffs which are predominantly used to

reduce peak loads and reduce overall generation costs will have an impact on

distribution systems. However, this will be very dependent on the actual network.

Savings will only be made if load related investment was imminent on a particular

part of the network and some deferral can be attributed to consumer led demand

reduction. Any capital expenditure savings will need to demonstrate that the

demand reduction or peak shift is not due to other economic factors and only

include the NPV or any deferral.

We note that in ESBN’s PR4 submission and assumption of 4% load reduction

due to smart metering have been made and this has led to an investment plan

being put forward based on a 0% load growth scenario. To fully support a

business benefit assessment ESBN would be required to provide a counterfactual

investment requirement based on no load reduction from Smart Metering.

Fault management

benefits

Smart meters could allow identification of customers who have lost supply without

customers having to make contact with the company. This should provide benefits

in fault identification and understanding of the extent of overhead system faults;

which will mean that the correct staff can be dispatched in the first instance and

thus reduce cost and duration of interruptions. This will have an operating cost

reduction and SAIDI reduction

Costs for Gas metering

facilitation

The capital cost and operational costs of any aspect of the metering system

that is used to facilitate a Gas Smart Metering system. If these are associated

with a system element (E.g. meter or data transmitter) of the metering system that

cannot be physically identified as solely for the facilitation of Gas Smart Metering

then then the costs should be the agreed apportionment of the shared element.

Revenue for Gas

metering facilitation

Any revenues received from Gas distribution or Supply businesses for the

provision of hardware or maintenance and management services that facilitate

the Gas Smart Metering system/

Page 261: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 256

ANNEX C: Smart Metering Framework – Narrative Response

Information Narrative Response Response

Required

Project Initiation

Document

Explain the derivation of the monthly programme (quarterly and

annual totals) for the PR4 period

Method of determining resourcing plan; explain the use of existing

metering staff (Management and Field) in the resourcing of the

smart grid programme and how the costs for these staff were

include in the RP4 submission

Method of determining Target unit cost.

Provide Detailed cost benefit factoring all relevant operating and

capex costs and benefits. Use categories identified in this

framework (and referenced as Project Initiation below) – if they

are not applicable for any reason state the reason. If additional

cost or benefits are identified that are relevant to the DSO these

should be explained and the method of recording them detailed.

Project Initiation

Smart meter

installation

Explain the proposed installation mechanism (Direct

labour/Contract or mix) and the reasons for the choice.

Project initiation

(plus 1/4ly or

annual if delivery

mechanism

changes)

Purchase cost of

electricity smart

meters

Explain how the purchase of smart meters will be managed and

accounted for. E.g. are cost recorded as stock is procured or as

they are installed? Are meters to be procured by the chosen

installer if this is contracted resource?

Project initiation

(plus 1/4ly or

annual if delivery

mechanism

changes)

Communication

costs

Explain which cost elements are included as Communication cost

as distinct from the Smart meter and Data management..

Project initiation

(plus 1/4ly or

annual if delivery

mechanism

changes)

Gas Smart Meter

Facilitation

Explain which cost elements are included as Gas Smart Meter

facilitation and whether the costs in other expenditure lines are net

or gross of these costs. Also explain how the agreed revenue

payments are calculated.

Project initiation

(plus 1/4ly or

annual if delivery

mechanism

changes)

Data management

of smart meters

Explain which cost elements are included in the installed meter

cost and which will be separate costs.

Project initiation

(plus 1/4ly or

annual if delivery

mechanism

changes)

Page 262: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 257

Information Narrative Response Response

Required

Smart meter

repairs and

maintenance

Explain how smart meter R&M is separately identified and whether

such costs are treated as opex or capex (if the meter is replaced)

Project initiation

Energy

consumption by

smart meters

State the designed internal energy usage of the chosen meter type

and the anticipated annual total kwh consumption based on the

target installation plan.

Project initiation

plus annual

summary based

on actual

installed

programme.

Avoided meter

readings

(pavement reading)

Explain how the costs of the retained manual reads are calculated

and what overheads are included. Demonstrate that the overhead

is not included in the costs attributed to the smart meter

installation.

Project initiation

plus annual

summary report

Meter change

deferral for 15

years

Explain how ESB will calculate the benefit of avoiding the

replacement cost of the existing meter asset base and if the

programme will take account of the age of existing meters.

Project initiation

Disconnections

and reconnections

Provide the unit costs for existing Disconnection/Re-connection

activities.

Project initiation

Voltage complaints Provide an explanation of the average unit cost of undertaking the

data recording required to assess a voltage complaints that can be

obviated through interrogation of the smart meter

Project initiation

Prepayment meters Explain if prepayment smart meters will be used and how the any

operational savings will be realised.

Project initiation

Avoided theft Explain the number of meter tampering incidences identified

during the implementation programme and the estimate of theft

avoided.

1/4ly report

Impact on delivery

programme

Explain reasons for deviation from the planned programme and

unit cost

1/4ly report

Impact on delivery

programme

Explain reasons for deviation from the planned programme and

unit cost and impact on future programme. Reference impact on

initial business case.

Annual report

Impact of demand

reduction

Provide a sample group that can be monitored for load reduction

estimates comparing annual consumption through the programme.

The group should include customers that will not be changed until

late in the programme to isolate any non-smart meter effects

Annual report

Page 263: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 258

Appendix D. Asset Lives & Depreciation

As part of the PR4 support CER required Jacobs to:

advise on the efficient level and method of depreciation of assets in the RAB, and

to assess the appropriate depreciation level and methodology and useful asset life for:

- smart grid; and

- smart metering assets; and

to advise whether a different approach should be taken to other RAB assets.

This report provides a review of the current average regulatory 45 and 50 year asset lives of distribution and

transmission assets with regard to the requirements above.

A key building block in determining business revenue is depreciation. In the regulatory context depreciation is

used as a form of revenue profiling that reflects the way future revenue streams are profiled. The aggregate

depreciation charge for an asset is the initial capital cost of the asset, in real terms. So the choice of approach

to depreciation does not affect the total revenue raised to cover the cost of the asset, only the extent to which

the burden of the cost of the asset is borne by today’s consumersversus future consumers. One way of setting

an appropriate depreciation profile is to set charges to customers reflecting the long run incremental cost of their

use of the asset. In this way depreciation measures the reduction in the value of an asset as a result its use.

Therefore an important concept is to determine the ‘useful’ life of an asset given that a depreciation profile could

be set to allocate an asset’s cost over its useful economic life. In regulatory terms the aim is to allocate an

asset’s cost in a way that reflects the pattern its economic benefits are consumed in generating revenues. In

this way, the accruals or ‘matching’ concept is followed, whereby revenues are matched to the expenses

incurred in generating them. The allocation of this asset cost is depreciation and the purpose of calculating

depreciation is to build up funds for the replacement of assets or to recover the original investment.

An amount for depreciation of the regulatory asset base (RAB) is included within the revenue allowance for

network operators, calculated over the average assumed useful lives of the relevant assets. In Ireland the CER

PR2 decision papers increased average transmission asset lives from 40 to 50 years and distribution from 40 to

45 years. Under the existing price control the CER reiterated these asset lives. CER has also reiterated its

view that depreciation of the transmission and distribution RABs should reflect the cost of using the assets

during the period. CER documentation (CER 05/143 and CER 05/138) also stated that the depreciation method

should reflect, as fairly as possible, the pattern in which an asset’s economic benefits are consumed.

D.1 Asset lives

D.1.1 Defining asset lives

There are a number of different ways of defining the life of a network asset, in particular:

Design life

Technical life

Economic life

Each asset has a design life which is the period of time during which it is expected by its designers to work

within its specified parameters; in other words, the life expectancy of the asset. The ‘technical’ life is the

expected life of an asset from commissioning until it falls below minimum technical and/or safety performance

level. The economic life of an asset is the period of time over which it is expected to be actively used on the

network.

Through good maintenance and management, the technical life of an asset may exceed its design life. On the

other hand an asset’s economic life cannot exceed its technical life. However, depending on the pattern of

Page 264: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 259

usage of the asset, its economic life may be shorter than its technical life. Therefore the pattern of usage of an

asset is fundamental to determining its economically useful life and the most appropriate depreciation profile. In

simple terms an asset can be in excellent condition, but if it no longer performs any useful function, it has

reached the end of its economic life.

D.1.2 Experience in Great Britain

In the earlier stages of market deregulation (pioneered in GB) the asset lives assumed for networks were

relatively short (in the order of 20 years) – partly based on the need to ensure privatisation was an attractive

option for investors, also on the then age profile of the network asset base and the perceived ‘financeability’

issues of the industry. Over time the economic life of network assets has been seen to increase as longer term

regulatory perspectives are introduced and the experience of efficient network operators increases. Overall

network operators have found that much equipment, when properly specified, installed and maintained will last

longer than had previously been assumed. Performance of older assets is generally adequate, not least due to

the modest pace of technological advance in electricity networks, and the risks of purely age related failure are

considered to be low. In addition, condition monitoring has replaced age-based techniques in determining

effective asset lifetimes.

Work undertaken for Ofgem96

assessed the existing asset base of the GB electricity network and the technical

life of each asset class within the network. A single weighted technical life was determined using Modern

Equivalent Asset Value (MEAV) as the weighting. The results for electricity transmission and distribution are

shown in Table D.1, with the weighted technical life of a transmission asset 54-60 years and 60-75 years for

distribution.

Table D.1 : Summary of Asset Lives

Accounting life Technical Life

Transmission 10-80 54-60

Distribution 2-100 60-75

The study then considered the economic life of these assets – based on their expected future usefulness.

Given that the energy market is challenged by significant change driven largely by renewable and carbon

targets and aspirations, scenario modelling was undertaken to assess the impact of asset lives of a number of

key drivers. Some of the key events that influenced the scenarios and resulting analysis are shown below in

Table D.2.

Table D.2 : Asset Life Influencing Factors

Event Impact on Average Asset

Life

Rationale

Smart Grids / Information

Technology

Decrease Information Technology tends to have a short asset live.

Unlikely to be material.

New Technology Unclear The impact could go in either direction depending on the cost

benefit analysis associated with the new approach /

technology

Increase in Cost of Raw

Materials

Increase More expensive assets could justify increased maintenance

to extend the technical life or change the cost benefit

analysis underlying health and safety limits on asset lives

Policy Decisions Decrease Government decisions on decarbonisation could lead to a

wholesale change in approach or technology beyond that

suggested by a simple cost benefit analysis. Shifting

96 https://www.ofgem.gov.uk/ofgem-publications/48276/cepa-econ-lives.pdf

Page 265: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 260

Event Impact on Average Asset

Life

Rationale

between gas and electricity based space heating would be

an example that could have a significant impact on asset

lives.

Four scenarios exploring the use of the electricity network to 2050 were developed. The scenarios highlighted

some uncertainties that could either increase or decrease the economic lives of assets. The uncertainties

include the impact from technological changes with the move to a smarter grid, increases in raw material prices

and policy decisions by government affecting the speed of change. The analysis undertaken for Ofgem

concluded that, under all future scenarios evaluated, long term electricity demand grows significantly as the

economy moves to a lower carbon base, but that the pattern of use may change. The study proposed a

conservative approach to economic asset lives, with economic asset lives significantly below average technical

lives and recommended a range of 45-55 years.

Ofgem also noted that network operators currently use an expected useful economic life for their network assets

as part of their depreciation accounting policy disclosed in their statutory and regulatory accounts. Table D.3

shows that the proposed asset lives fit within the envelope used by the DNOs own accounting asset lives97.

Table D.3 : GB DNO Accounting Lives

Electricity Distribution Network Asset Type Accounting

Useful

economic Life

(Years)

CE Northern Electric DL and Yorkshire

Electricity DL

Distribution System Assets

Information Technology

45

Up to 10

Central Networks East and Central

Networks East

Distribution Network Assets 40 - 70

EDFE EPN, EDFE LPN and EDFE SPN Overhead and Underground Lines

Other Network Plant and Buildings

45 – 60

20 – 60

Electricity North West Infrastructure Assets 5 – 80

SP Distribution and SP Manweb Distribution Plant

Towers, Lines and Underground Cables

30 – 40

40 – 60

SSE Hydro Distribution Assets 10 – 40

SSE Southern Distribution Assets 10 – 80

WPD S Wales and WPD S West Overhead Lines and Poles

Underground Cables

Transformers and Switchgear

Towers and Substations

45

60

45

Up to 55

The move to a longer term view of network assets in GB is also based on the RIIO (Revenue = Incentives +

Innovation + Outputs) regulation model where the assumed depreciation lifetime better reflects likely useful

economic life. However, Ofgem also notes that the longer useful life of the assets needs to be balanced with

the cashflow requirements of the companies as longer depreciation lifetimes implies slower recovery of capital

costs. The result was that Ofgem subsequently increased the economic life of new electricity network assets

from 20 to 45 years despite their longer technical lives.

97 file:///C:/Users/lwoolhouse/Documents/CER%20Depreciation/ed-asset-lives-consultation-21000114.pdf

Page 266: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 261

D.1.3 Experience in other countries

The approach to network asset lives in other countries varies – with relatively few adopting an ‘average’ asset

life. For example:

In the Netherlands each asset type is allocated a depreciation life ranging from 5-50 years and straight line

depreciation is used.

In Norway depreciation is determined by assuming a linear profile over 30 years98

.

In Germany transmission and distribution asset lives range from 25 to 50 years99.

In Australia 35 to 51 years is used as a range for distribution assets100.

Few countries employ an ‘average’ asset life for the entire asset base, with most adopting individual asset lives

for each asset class.

A report undertaken by EURELECTRIC expert Task Force ‘DSO Investment Action Plan’ reviewed the impact of

current European regulatory frameworks on investments in the distribution network. It concluded that European

electricity network operators have to cope with demanding investment requirements driven by three main

factors:

The need to integrate renewable energy sources into the electricity system

The need to replace existing assets in order to ensure continued quality of supply, and

The development of smart grids.

The report concluded that regulated rate of return should be set in a forward-looking way and be consistent with

the long lifetime of distribution assets. The risk-free rate and debt premium should reflect the typical network

asset lifetime of 30 to 55 years101.

While the technical life of network assets has risen, the age profile of the network asset base across Europe

also indicates that additional investment will be required, not only to replace aging assets, but also to adapt to

the challenges of accommodating increasing volumes of renewable generation and smarter grids. The result

will be some uncertainty, particularly vis-à-vis asset lives and asset ‘usefulness’ as patterns of useage change.

Uncertainty surrounds the future rate of asset replacement and also the rate of investment required to

accommodate increasing renewables and smarter grids, and although it appears that overall electricity networks

will continue to be well utilised as we move towards a lower carbon future – the patterns of use is likely to

change.

Significant investment in new network assets also raises issues of intergeneration equity – assuming relatively

short assets lives may unfairly bias the allocation of costs to current consumers and is not appropriate if the

assets are expected to have a longer useful life. On the other hand, while older assets have been shown to

have a technical longer life than initially assumed, some new technologies, such as plastic cables, may have

shorter lives than older technologies, such as paper lead cables. In Ireland this is particularly relevant given the

large growth in network assets over the past 20 years using newer technologies. In addition some technologies

associated with the move to ‘smarter grids’ may have shorter asset lives that will influence the overall age of the

asset base.

We can conclude that, for regulatory purposes, it appears unlikely that the average depreciation life of the asset

base will extend to the length of the average technical life, despite the regulatory trend for adopting asset lives

that more accurately reflects their useful lives. Uncertainty over the pattern of network use, despite increasing

electricity demand and the addition of shorter lived assets into the asset base will result in the economic life of

assets reflecting a more cautionary timescale.

98 Trends in electricity distribution network regulation in North West Europe. A report for Energy Norway, August 2012 99 Issue Paper: Determination of the Regulatory Asset Base after Revaluation of License Holder’s Assets. Chart of Accounts, Energy Regulators

Regional Association, 2009 100 https://www.ofgem.gov.uk/ofgem-publications/50643/ed-asset-lives-consultation-21000114.pdf 101 http://www.eurelectric.org/media/131742/dso_investment_final-2014-030-0328-01-e.pdf

Page 267: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 262

D.2 Determining the Asset Lives and Depreciation for PR4

In Ireland the CER PR2 decision papers increased average transmission asset lives from 40 to 50 years and

distribution from 40 to 45 years. Under the existing price control the CER reiterated these average asset lives

of 50 years for transmission and 45 years for distribution network assets. The CER decision to increase asset

lives was based largely on the structure of the RAB at that time, i.e. that is predominantly made up of

switchgear, transformers and overhead lines and the experience of network operators that showed equipment

that has been correctly specified, installed and maintained will last longer than had been previously assumed.

In order to determine the appropriate asset lives to be used in PR4 we have evaluated the asset base of the

DSO and TAO and determined a single weighted technical life for each using MEAV as the weighting. Our

analysis replicates that undertaken for Ofgem in 2010 to determine the weighted average technical life of the

asset base. We also consider factors that will influence the future useage of the network and changes to the

asset base in order to determine an appropriate economic life (and therefore depreciation life) of distribution and

transmission assets that can be applied in PR4.

D.2.1 DSO

The depreciation life of the distribution asset base in Ireland is influenced by the structure of the asset base.

Figure D.1 and Figure D.2 below show the configuration of the DSO RAB in 2006 and 2013 based on

determination of the MEAV102.

Figure D.1 : Composition of DSO Network RAB in 2006 (MEAV Basis)

102 Based on unit costs used in PR3 together with Jacob’s analysis where unit costs not available

Page 268: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 263

Figure D.2 : Composition of DSO Network RAB in 2013 (MEAV Basis)

The charts show that the DSO RAB is dominated by underground cables and overhead lines (accounting for 69-

70%). Changes in the network environment in Ireland, including greater urbanisation and a move against

overhead line construction, have led to an increasing proportion of underground cables within the asset base –

with the proportion of underground cabling growing since 2006 from 41% to 44%.

Table D.4 shows the asset lives outlined in PR2. These asset lives are based on UK power industry average

weighted asset lives for each asset class. Based on these asset lives CER concluded that the existing policy of

depreciating DSO network assets over an average 40 year life should be modified. Of particular relevance to

ESBN is the predominance of relatively long lived underground cables in the asset base with expected asset

lives ranging from 71-94 years.

Table D.4 : UK Network Asset Lives

Asset Category Technical Life

PR2

Overhead lines Low Voltage 52

Overhead Lines Medium Voltage 43

Overhead Lines High Voltage 46

Overhead lines EHV 67

Underground cables LV 92

Underground cables MV 94

Underground cables HV 71

Switchgear LV 73

Switchgear HV 47

Switchgear EHV 52

Transformers 56

However, as outlined above, the asset life assessment outlined in PR2 was based on UK assets. Figure D.3

shows the relative replacement costs of the distribution and transmission networks in the UK and clearly shows

that the peak of electrification activity was undertaken in the 1950s and 1960s – and therefore the relatively high

age of the UK’s network asset base.

Page 269: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 264

Figure D.3 : Age and Replacement MEAV of UK Electricity Network103

In Ireland the age profile of the asset base is different, with a far greater proportion of investment undertaken

after 1995 – as shown in Figure D.4 – with a consequently younger asset base.

103 Consultation on strategy for the next transmission and gas distribution price controls - RIIO-T1 and GD1Financial issues. Ofgem, December 2010

Page 270: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 265

Figure D.4 : Investment in DSO Network Assets (2009 Prices) 104

Given that the DSO asset base is dominated by underground cables, the assumed technical life of these

particular assets is of fundamental importance when determining a single weighted technical life of the asset

base. Traditionally, underground cables have been proven to have relatively long lives compared to other

network components – with the UK’s network experience (and that elsewhere) providing empirical evidence that

underground cables have a relatively long technical life. However cable technology has changed since the

peak of electrification in much of Western Europe in the 1950s and 1960s. Some new cable technologies now

used, such as plastic cables, may have a shorter life than the older underground cable technologies (paper lead

cables) that make up the majority of the UK’s underground distribution network cables. In Ireland this is

particularly relevant given the large growth in the network over the past 20 years using newer cable

technologies with more limited operational experience and a subsequently smaller database of empirical

evidence regarding asset life. As a result there is a degree of uncertainty surrounding asset life with modern

cost effective cable constructions versus the traditional, long life paper/lead cables.

Therefore, given the younger age profile of much of the underground cabling in Ireland and the use of different

cabling technology, the assumed life for this asset class could be lower rather than the 71-94 years suggested

in PR2. ESBN has estimated that the actual lifetime of ‘newer’ technology cables is longer and points to some

of its LV plastic cables that are currently 40 - 50 years old and performing satisfactorily. ESB has endurance

tested some of its MV and 38kV cables that are currently 30 years old, with the tests indicating a considerable

remaining life estimated to be 20 – 40 years. Overall ESBN’s analysis suggests a technical life for its cables of

between 60-80 years. In our analysis we have adopted a conservative asset life for DSO underground cables

of 70 years, reflecting the midpoint of ESBN estimates.

On the other hand we have extended the life of medium and high voltage overhead lines to 63 years – reflecting

overhead line lives used by Ofgem105, in addition to the assumed asset life implied by ESB’s asset replacement

programme outlined for PS4.

The revised assets lives (for use in PR4) are provided alongside the asset lives assumed for PR2 in Table D.5

below.

104 ESB Networks, PR4 Submission DH02 PR3 Load Driven Programme, October 2014 105 DPCR5 – recognising that as these are treated as “perpetual assets” the concept of an actual replacement life is theoretical.

Page 271: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 266

Table D.5 : PR4 Assumed Asset Lives

Asset Category Technical Life

PR2

PR4

Overhead lines Low Voltage 52 52

Overhead Lines Medium Voltage 43 63

Overhead Lines High Voltage 46 63

Overhead lines EHV 67 67

Underground cables LV 92 70

Underground cables MV 94 70

Underground cables HV 71 70

Switchgear LV 73 73

Switchgear HV 47 47

Switchgear EHV 52 52

Transformers 56 56

Based on our revised asset lives assumed for PR4 we have determined the single weighted technical life of the

DSO asset based using MEAV as the weighting. We have calculated a technical life based on the UK asset

lives outlined in PR2 and shown in Table D.4 (71-94 years), plus unit costs provided by ESB for PR4. In

addition we have calculated a weighted average asset life based on a shorter life for underground cables of

between 50 and 70 years.

The results of our analysis are shown in Table D.6.

Table D.6 : Weighted Average Technical Life of DSO Asset Life (Years)

Technical Asset

Life

Distribution 61

The resulting weighted average technical asset life of the DSO network is some 61 years.

D.2.2 TAO

The depreciation life of the transmission asset base in Ireland is influenced by the structure of the asset base.

Figure D.5 below shows the configuration of the TAO RAB in 2013 based on determination of the MEAV106. It is

clear that overhead lines dominate the transmission network’s asset base and therefore the assumed life of

overhead line assets will have a highly influential impact on the weighted average technical life of the TSO’s

asset base.

106 Based on unit costs used in PR3 together with Jacob’s analysis where unit costs not available

Page 272: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 267

Figure D.5 : Composition of TSO Network RAB 2013 (MEAV Basis)

Unlike the underground cable technology used in the distribution network, the technology used for overhead

lines has changed relatively little since the peak of electrification in much of Western Europe in the 1950’s and

1960’s. As a result the technical life outlined in PR2 (Table D.4) is broadly applicable to the TAO’s asset base.

We have calculated a technical life based on the UK asset lives outlined in PR2 and unit costs provided by ESB

for PR4. The results of our analysis are shown in Table D.7. The weighted average technical life of the TAO

asset base is some 64 years.

Table D.7 : Weighted Average Technical Life of TAO Asset Base (Years)

Technical Asset

Life

Transmission 64

D.2.3 Economic lives

The CER has stated that depreciation of the transmission and distribution RABs reflects the cost of using the

assets during the period. The CER has also stated (CER 05/143 and CER 05/138) that the depreciation

method should reflect, as fairly as possible, the pattern in which an asset’s economic benefits are consumed.

Therefore implicit within this is the economically useful life of an asset which may be shorter than its technical

life.

As outlined above, work undertaken for Ofgem considered the economic life of network assets based on a

number of future energy scenarios over the period to 2050. Overall, as the energy networks move towards to

demands of a lower carbon economy, long term electricity demand increases, but the pattern of use of the

network may change. The uncertainties highlighted include the impact from technological changes with the

move to a smarter grid, increases in raw material prices and policy decisions by government affecting the speed

of change. Projecting forward, the mix of electricity assets is likely to change, which could mean greater

volumes of short-life technology assets for monitoring and controlling the network. On the other hand more

short lived assets may be balanced if the proportion of underground cables increases as existing infrastructure

is replaced.

Page 273: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 268

Recognising the uncertainties that still exist over the how the electricity network will develop into the future, the

work commissioned for Ofgem proposed it adopt a conservative approach to economic asset lives with the

economic asset lives set significantly below the average technical lives at between 45-55 years.

The drivers in Ireland are similar to those in the UK, in particular the move towards a lower carbon economy and

uncertainty over future patterns of energy usage and network flows – therefore we can conclude that the

economic life of ESB’s network assets will be lower than the weighted average technical life of the asset base.

However, in Ireland it appears that many of the shorter lived assets associated with smarter girds may not be

included in the overall asset base, but assessed separately. The impact of shorter lived assets in the asset

base, in particular smart meters and smarter grids, is explored below.

D.3 The impact of smart grids and smart meters

D.3.1 Smart grids

‘Smart grid’ assets vary by asset class and include conventional asset groups (breakers, transformers, switches,

etc.) with relatively long lives and also assets that are less conventional with shorter lives, such as software and

communications systems. At present, IT and telecoms equipment are assessed separately to ‘network assets’

for depreciation purposes, with lower depreciation lives (5-7 years for IT and 15 years for telecoms). Therefore

smart grid assets that can be categorised as IT or telecoms will not be included in the network asset base and

will have subsequently shorter depreciation lives.

Many ‘network’ related smart grid assets are not fundamentally different from existing network assets (breakers,

transformers, switches, etc.) and will have similar asset lives. For example an arc suppression coil is

considered as part of standard network assets in other jurisdictions and where initiatives include conversion of

lines from one voltage to another then asset lives will be the same. Therefore for the purposes depreciation,

such smart grids network assets will have a similar technical life to ones used on the ‘conventional’ network.

As a result we do not consider smart grid assets will have a material impact on the weighted technical life of the

DSO network asset base and that the existing classifications of IT, Telecoms and Network provide a suitable

mechanism for RAB deprecation.

D.3.2 Smart meters

The EU has called for 80% of citizens to be equipped with smart meters by 2020, subject to a positive national

cost benefit analysis. In May 2011 the European Commission undertook an economic assessment of long-term

costs and benefits associated with smart metering rollout in Ireland and concluded that the CBA was positive.

As a result Ireland has laid out plans for a large-scale smart metering roll-out107. The metering activity in Ireland

is regulated by the CER and the DSO is the owner and responsible party for the meter installation and for

granting third-party access to metering data. The European Commission smart grid study suggests a 17 year

life for a smart meter installed in Ireland and an a cost per unit of some €473108. Smart meter assets comprise

the meter itself, an electronic device with a technical life of around15 years, and the communications and IT

equipment that process the smart meter data, with a technical life of some 5 years. The volumes of smart

meters will be high compared to the low volumes of IT equipment.

Smart meters are currently excluded from the DSO RAB – and are evaluated based on an assumed asset life of

10 years. Conversely conventional meters are currently included in the DSO asset base, again with an asset

life of 10 years.

Going forward we have considered the impact of including smart meters within the DSO network asset base,

assuming they replace existing conventional meters in PR4. In order to do so we have adjusted the 2014 DSO

asset base to consider the impact of some 2.2m smart meters at an average cost of €500 per unit and a 10 year

107 http://eur-lex.europa.eu/legal-content/EN/TXT/PDF/?uri=CELEX:52014SC0188&qid=1416241421987&from=EN 108 ibid

Page 274: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 269

economic life replacing all existing meters. We have also assessed the impact of excluding all meters from the

asset base.

The results of our analysis are shown in Table D.8. Excluding all meters from the asset base has a very

moderate impact on the weighted average life, increasing it from 61 to 62 years. Including 2.2m smart meters

reduces the weighted life of the asset base by 2.5 years to 59 years.

Table D.8 : Impact of Smart Meters on DSO Average Technical Asset Life

Technical asset

life including

conventional

meters

Technical asset

life excluding

ALL meters

With Technical

asset life

including 2.2m

replacement

smart meters

Distribution 61 62 59

In summary, the addition of shorter lived assets into the asset base will reduce the weighted average technical

life of the asset base.

The role of shorter lived assets in the RAB has also been acknowledged by Ofgem – who also use a variation of

the average asset life approach. Ofgem notes that it has allowed for the expected increasing importance of

shorter asset lives in adopting the 45 year asset lives for new investment which was at the lower end of the 45-

55 year range determined for the economic life of network asserts. Ofgem notes: ‘we have taken into account

several factors in determining the appropriate economic asset life. These include … the technical life of the

assets (54–60 years), which were not disputed by companies, and the clear expectation of increased electricity

usage in the plausible scenarios of future energy demand. In determining the economic asset life we have also

allowed for a reasonable increase in shorter life assets as networks become smarter and for some early

retirement of assets as generation locations change.’

One concern with adopting a blanket asset life is that it may reduce incentives to invest in short lived assets in

favour of longer lived assets. Ofgem suggests that its use of a weighted average asset life for all capex for

depreciation purposes removes the bias towards against capex on short life assets that would otherwise exist.

In Ireland the short lived telecoms and IT assets associated with smart meters are already excluded from the

network asset base and depreciated over a shorter life. In addition smart meters are currently also assessed as

a separate asset class with a 10 year depreciation life. ESBN has committed to rolling out smart meters to

some 80% of its customers in PR4 – if these assets are assessed as a separate class with a 10 year

depreciation life, then some €1bn of RAV will be depreciated over 10 years, rather than the current 45 years.

Ofgem adopted a depreciation life of 45 years that was at the lower end of the 45-55 year economic life

identified for network assets and it was intended to reflect the impact of shorter lived assets in the overall asset

base, together with other uncertainties. If smart meters are excluded from the asset base than all remaining

assets have weighted average technical life of 61 years. Under such circumstances it may be difficult to argue

that the technical life of the DSO asset base fundamentally differs to that of the transmission network and that

both should be depreciated over a similar life.

D.4 Conclusion

The CER’s PR2 decision papers increased average transmission asset lives from 40 to 50 years and

distribution from 40 to 45 years. Under the existing price control the CER reiterated these average asset lives.

The CER’s decision to increase asset lives was largely based on the structure of the RAB at that time, i.e. the

predominance of switchgear, transformers and overhead lines and the experience of network operators that

showed equipment that has been correctly specified, installed and maintained will last longer than had been

previously assumed.

In order to determine the appropriate asset lives to be used in PR4 we have evaluated the asset base of the

DSO and TAO and determined a single weighted technical life for each using MEAV as the weighting. Our

Page 275: Consultancy Support for Electricity Transmission … Consultancy Support for Electricity Transmission and Distribution Revenue Controls (2016-2020) COMMISSION FOR ENERGY REGULATION

DSO

Page 270

analysis concludes that the weighted average technical life of the distribution network is 61 years and that of the

transmission network is slightly longer at some 64 years.

However, while the technical life of the asset base is longer than the asset lives applied in PR3, depreciation life

is intended to reflect the economically useful life of the network assets. Factors to be considered when

assessing the future economically useful life of the network include technological changes with the move to a

smarter grid, increases in raw material prices and policy decisions by government affecting the speed of

change. Such uncertainty suggests that the economic life of network assets should be lower than their

technical lives. In the UK, the increasing impact of shorter lived assets in the network asset base, particularly

those associated with smart grids, together with the substantial change from the prevailing depreciation life of

20 years, contributed to Ofgem adopting a depreciation life for network assets of 45 years, towards the lower

end of the economic life identified of 45-55 years.

In Ireland short lived smart grid assets (such as smart meters and associated telecoms) are currently assessed

as separate asset classes with a lower depreciation life. However conventional meters are included in the

network asset base – also with a low asset life. Including smart meters within the asset base will reduce the

weighted average technical life by around three years – widening the gap between the technical life of the DSO

and TAO assets. We conclude that, if smart meters are included in the DSO asset base, then it may be

appropriate to continue to have a depreciation life for the DSO network asset base that is lower than that of the

transmission asset base.

However, if smart meters are assessed as a separate asset class, along with other shorter lived assets such as

IT and telecoms, then we consider that there becomes significantly less rationale for the depreciation life of the

DSO asset base to differ to that of the transmission asset base given that the weighted average technical life is

very similar. The question then becomes whether a reasonable depreciation life for PR4 should be 45 or 50

years which will need to be determined based on current regulatory practice and financeability.

A summary of the proposed PR4 technical asset lives is provided below in Table D.9.

Table D.9 : Technical Asset Lives for PR4

Technical

weighted

average asset

lives

Technical

weighted

average asset

lives including

smart meters

Distribution 61 59

Transmission 63 64