Construction Update of
for The Month of March, 2020
Keshav Nagar, Pune
• ‘A’ BUILDING:
• • RCC work completed for all floors
• • Block work completed for all floors
• • Electrical wall conducting completed for all floors
• • Internal plaster work completed
• • Gypsum work completed
• • Internal toilet concealed plumbing work completed
• • External plaster work completed
• • Bath Dado tiles, kitchen platform and bath granite frames work completed
• • Tile flooring work completed
• • Waterproofing work completed
• • 85% work done for UPVC window
• • 45% work complete of internal painting
• • 50% work complete for external painting
• • 80% work complete for external duct and terrace plumbing
• • 52% work complete for door fixing & 50% work complete for SS railing
• • Fire fighting work completed
Florida Riverwalk– March’20
• ‘B’ BUILDING:
• • RCC work completed for 1st to 7th slab
• • Brick work complete for 1st and 3rd floor
• INFRASTRUCTURE:
• • Work completed for Underground Water Tank RCC
• • Club House - Excavation work completed and 55% RCC work complete
• • Transformer Room – Excavation, RCC work, brickwork and plaster completed. Painting 80% complete
• • Swimming Pool - Excavation work completed and 40% RCC work complete
• • Compound Wall and Retaining Wall - Brickwork 80% complete
• • Underground Services Drainage + Storm + Electrical - RCC piping work 90% complete
• • Fire fighting work completed
• • Road Trimix – 85% complete for A Building surrounding area
• Genset – 80% work complete
Florida Riverwalk– March’20
A BUILDING