Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work...

8
Construction Update of for The Month of March, 2020

Transcript of Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work...

Page 1: Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work completed and 40% RCC work complete •• Compound Wall and Retaining Wall - Brickwork

Construction Update of

for The Month of March, 2020

Page 2: Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work completed and 40% RCC work complete •• Compound Wall and Retaining Wall - Brickwork

Keshav Nagar, Pune

Page 3: Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work completed and 40% RCC work complete •• Compound Wall and Retaining Wall - Brickwork

• ‘A’ BUILDING:

• • RCC work completed for all floors

• • Block work completed for all floors

• • Electrical wall conducting completed for all floors

• • Internal plaster work completed

• • Gypsum work completed

• • Internal toilet concealed plumbing work completed

• • External plaster work completed

• • Bath Dado tiles, kitchen platform and bath granite frames work completed

• • Tile flooring work completed

• • Waterproofing work completed

• • 85% work done for UPVC window

• • 45% work complete of internal painting

• • 50% work complete for external painting

• • 80% work complete for external duct and terrace plumbing

• • 52% work complete for door fixing & 50% work complete for SS railing

• • Fire fighting work completed

Florida Riverwalk– March’20

Page 4: Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work completed and 40% RCC work complete •• Compound Wall and Retaining Wall - Brickwork

• ‘B’ BUILDING:

• • RCC work completed for 1st to 7th slab

• • Brick work complete for 1st and 3rd floor

• INFRASTRUCTURE:

• • Work completed for Underground Water Tank RCC

• • Club House - Excavation work completed and 55% RCC work complete

• • Transformer Room – Excavation, RCC work, brickwork and plaster completed. Painting 80% complete

• • Swimming Pool - Excavation work completed and 40% RCC work complete

• • Compound Wall and Retaining Wall - Brickwork 80% complete

• • Underground Services Drainage + Storm + Electrical - RCC piping work 90% complete

• • Fire fighting work completed

• • Road Trimix – 85% complete for A Building surrounding area

• Genset – 80% work complete

Florida Riverwalk– March’20

Page 5: Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work completed and 40% RCC work complete •• Compound Wall and Retaining Wall - Brickwork

A BUILDING

Page 6: Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work completed and 40% RCC work complete •• Compound Wall and Retaining Wall - Brickwork
Page 7: Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work completed and 40% RCC work complete •• Compound Wall and Retaining Wall - Brickwork
Page 8: Construction Update of Our Projects · Painting 80% complete •• Swimming Pool - Excavation work completed and 40% RCC work complete •• Compound Wall and Retaining Wall - Brickwork

Thank you!

-Team