Birmingham Public Schools 2015 Bond Program Monthly Construction Update
May 2018
Brief Project Description
Bid Pack 6 is wrapping up this year with work at Seaholm and Beverly Elementary. The work at Seaholm
will include a scene shop addition; renovations to the auditorium including new sound systems, stage
flooring and lighting; and upgrades to STEM labs and media center to create a more collaborative learning
environment. At Beverly Elementary epoxy flooring will be installed in the restrooms. Bid Pack 11 will also
take place this summer and includes the replacement of roof top units at West Maple Elementary. This
project will begin when school is released for summer. The auditorium and addition are scheduled to be
completed in October, and all other work will be completed before the 2018/2019 school year.
Construction Schedule Update
Seaholm High School:
Masonry block walls for the addition are completed and vapor barrier installed.
Brick for the addition has begun.
Precast plank for the roof has been set and grouted.
Roof blocking is completed, roofing has started.
Underground plumbing and electrical in the addition is ongoing.
Roof drains have been installed.
Installation of the rigging above the stage has started.
Fire protection and duct work above the stage is completed.
Starter Boxes and Master Control Cabinet on the stage have been installed.
Dimming & controls wiring is 75% complete and sound system conduit is complete.
Auditorium house lighting is 60% complete.
Caliper masonry has been completed. The metal decking was installed and the concrete on the
calipers has been completed.
Demolition of the old boilers in our new dressing room area has been completed, the walls have
been removed and saw cutting of the floor has been completed.
Roof openings and curbs for the Energy Recovery Unit have been completed
Beverly Elementary:
Work will begin when school is dismissed for summer break.
West Maple Elementary:
Work will begin when school is dismissed for summer break.
Safety
All contractors will go through Clark Construction Company’s site‐specific safety orientation
before beginning work on site.
Hard hats, safety glasses and safety vests will be required 100% of the time on site.
Clark’s BRAVO program (Being Resistant Against Violations Openly) is being utilized on this
project. This program is to ensure everyone has their eyes open to potential safety hazards and
is looking out for one another.
Clark has set this project up with a MIOSHA SET Alliance.
Contractors are going through stretch and flex in the morning to get them warmed up for the
tasks they will perform that day.
Logs
Attached is the potential change order log.
To date, for Bid Pack No. 6 there have been 20 bulletins and 7 ASI’s issued by TMP.
To date, for Bid Pack No. 11 there has been 1 ASI issued by TMP.
To date, 246 RFIs have been issued for Bid Pack No. 6, and 1 RFI for Bid Pack No. 11.
Auditorium Stage Caliper
Demolition of old Boiler Room
Starter Boxes and Master Control Cabinet
Painted Stage Ceiling, Walls and Conduit
Scene Shop Addition Looking Northwest
Scene Shop Addition Looking Southeast
Scene Shop Addition