    315Building Permit Series

    Development Services

    www.denvergov.org/residentialpermits

    201 W. Colfax Ave., Dept. 205

    Denver, CO 80202

    phone: 720.865.2710 fax: 720.865.3020

    Advisory

    CONTRACTORS/HOMEOWNERS INFORMATION SHEET

    1.22.10

    Completed construction work must be inspected and approved

    at various stages, not to exceed 60 days between inspections,

    or as approved by your inspector. The Permit and the Inspec-

    tion Record Card, containing the names of the homeowner,

    and all licensed subcontractors, shall be posted at the site at

    all times, and visible from the street. The city-approved plans

    must be on the site, and available to the inspectors at all times.

    The general procedure for order of inspections is as follows:

    1. Pre-Construction Inspection (113) Used for Large Com-mercial Projects or Shoring Permits.

    2. Footing Inspection - (100) - Conducted just prior to pouring

    concrete footings. The footing excavation, formwork, and any

    reinforcing steel, must be complete and in place. Any clay soil

    pipe encountered must be replaced, by a licensed plumber,

    to schedule 40 PVC, ABS/DWV piping, or cast iron, under

    separate permit (#4 Plumbing), and approved by the plumbing

    inspector prior to footing inspection. Any pipe replaced more

    that 2 from the new foundation must also be permitted and

    inspected by Wastewater Management Division. Caisson foun-dations require the submittal of a eld report, by the engineer

    of record, to the Department, in lieu of inspection.

    3. Foundation Inspections - Conducted on foundation walls at

    four stages:

    (101) - Formwork and reinforcing steel, prior to placement

    of concrete.

    (115) - Setback Inspection

    (103) - Finished walls, with damproong applied, when required.

    (104) - Exterior foundation wall insulation, when required.

    (102) - Perimeter drain, when installed. Backlling followscompletion of these inspections.

    4. Rough Inspections - When shell or alteration framing

    is completed, with utilities installed, rough inspections are

    required of: Zoning, Electrical, Plumbing, Mechanical System

    Piping, Ductwork, and Vents for Gas Fired Equipment or Metal

    Fireplaces. Each requires a separate permit, with subcontrac-

    tors scheduling inspections of their own work. All subcon-

    tractors shall have the proper license issued by the Building

    Inspection Division (BID). Unlicensed subcontractors are not

    allowed. Corrections required must be completed, reinspect-

    ed, and signed-off by the inspector involved.

    (114) - Bulk Plane Inspection - Zoning

    (105) - Exterior Sheathing Inspection - Nail inspection

    (112) - Basement Structural Floor Inspection Partial frame

    inspection performed before installing oor deck or sheathing.

    (111)- Exterior Paper/ Exterior Lath Inspection of exteriorweather-resistive barrier (building paper, etc, as required by

    section 1402.1 & 1402.2) before installation of exterior nishes

    such as siding, brick or any stucco. Metal and wire is inspect-

    ed at the same time prior to the installation of stucco.

    5. Frame Inspection - (112) - Conducted when frame construc-

    tion is completed, following sign-off of all rough inspections.

    Roof and wall sheathing must be complete with at least roong

    felt and roof jacks installed. Doors & Windows must be in-

    stalled, and all framing must be exposed; bafes should be in

    place, also. (Air inltration Barrier Method # A, foam and caulkis inspected with frame.)

    6. 2nd Story Attachment Inspection - (112) - Partial frame

    inspection for 2nd story additions only. Have all connectors

    that attach the 2nd story to the existing building in place. Floor

    framing shall be in place without oor sheathing installed. All

    rough suboor utilities must be installed and passed inspection

    before requesting a Partial Frame Inspection.

    7. Insulation/Moisture Vapor Retarding Inspection Moisture

    vapor retarder is installed Batt insulation (106), or blown-ininsulation (200) -- in place, following frame inspection.

    8. Drywall Inspection - (107) - Drywall installations prior to

    jointing or taping work.

  • 8/8/2019 Construction Steps

    2/3

    Denver Advisory No. 315 Contractors/Homeowners Information Sheet

    LEGAL DISCLAIMER: This Advisory should not be used as a substitute for codes and regulations. The applicant is responsible forcompliance with all code and rule requirements, whether or not described in this Advisory.

    9. Final Sub Inspection - Final inspections of roong, gut-

    ters, electrical, plumbing, mechanical, heating, ductwork, etc.

    (rough and nal sign-offs required on each sub permit) are

    required prior to nal construction inspection.

    10. Final Construction Inspection - (108) - Job is completed,

    including shingling, siding, gutters, downspouts, splashblocks,

    steps, handrails, etc. Energy compliance certicate that shows

    a pass rating of 83 by a recognized energy rating program

    when a builder signed the Energy Rating Program Agree-

    ment. Painting and carpeting do not require inspection.

    If intervals between inspections exceed 60 days, the inspector

    must be contacted for an extension. Inspectors are available

    daily by phone, between 7:30 a.m. to 8:30 a.m.

    SEE THE LIST OF PHONE NUMBERS BELOW.

    NOTE: The numbers, in parenthesizes (XXX), are the inspec-

    tion code number required when setting up your inspections

    for work allowed under the 1R or 1C permit. Information may

    also be found on back of the green paper copy of each permit.

    AUTOMATED INSPECTION REQUEST SYSTEMCALL 720-865-25011. The Automated Inspection Request System is de

    signed to dispatch inspection requests for the next

    working day. It will be available 24 hours daily. Torequest an inspection the next business day call

    before 12:00 a.m. (Midnight). Occasionally an in

    spection will be scheduled for a later date due to

    workload problems.

    z When you request an inspection, you must know

    the permit number. This is the number printed

    on the bottom of your permit beginning with

    the year. For example, 92123456 would be the

    permit number which must be entered from your

    touch-tone telephone pad when requested bythe system.

    z You will need to know the three-digit code for the

    type of inspection you want. This can be seen in

    the following Inspections Type Directory.

    z The inspection code number listed below must

    match the permit type (#1-R thru #12) in order to

    request an inspection.

    z Subcontractor permits (#2 thru #12 permits) must

    be issued and the job site card must be posted

    before requesting an inspection for work that is

    performed under a subcontractor permit.

    2. Enter the permit number and inspection type code

    by using the buttons of your telephone. Remember

    to press the pound key (#) after each set of numbers

    entered. NOTE: You can call for two or more inspec-

    tions with a single phone call, provided the work to be

    inspected is ready for inspection. Press the asterisk

    key (*) between inspections with different permit

    numbers. If all of the information you enter is

    correct, you will be given a verication number

    and the inspection date at the end of your call.

    Please stay on the line until you get that number.

    TYPE OF INSPECTION FOR WORK PERFORMEDUNDER #1-R OR #1-C PERMIT:Footing ...................... (100) Frost Wall Insulation .............(104)

    Final .......................... (108) Setback ............................... (115)

    Frame ....................... (112) Other ....................................(109)

    Foundation Wall ........ (101) Bulk Plane ............................ (114)

    Ext. Lath Stucco ....... (111) Batt Insulation ......................(106)

    Blown Insulation .......(200) Waterproong ......................(103)Drywall ................................................................................(107)

    Foundation Perimeter Drain ................................................(102)

    ***WARNING: REINSPECTION FEES MAY BE CHARGED IF

    WORK IS NOT READY, OR IF ENTRY CANNOT BE MADE.

  • 8/8/2019 Construction Steps

    3/3

    Denver Advisory No. 315 Contractors/Homeowners Information Sheet

    LEGAL DISCLAIMER: This Advisory should not be used as a substitute for codes and regulations. The applicant is responsible forcompliance with all code and rule requirements, whether or not described in this Advisory.

    BUILDING INSPECTION DIVISION - SECTIONS LIST PHONE NUMBERS

    Cashier - Payments for Reinspection/2nd Half of Double Fee ......................................................................................... 720-865-2780

    Contractors Licenses & Certicates ............................................................................................................................... 720-865-2770

    Inspection Section (Inspection Administrator) ................................................................................................................ 720-865-2500

    Boiler/Refrigeration ................................................................................................................................................ 720-865-2550

    Construction .......................................................................................................................................................... 720-865-2520

    Electrical ................................................................................................................................................................ 720-865-2580

    Elevator ..................................................................................................................................................................720-865-2610

    Mechanical ............................................................................................................................................................ 720-865-2560

    Plumbing ............................................................................................................................................................... 720-865-2620

    Public Safety.......................................................................................................................................................... 720-865-2630

    Roong, Gutters, Insulation, Fences ..................................................................................................................... 720-865-2540

    Zoning (Neighborhood Inspection Services) ........................................................................................................ 720-865-3200

    Commercial - Phone hours are 8 to 11:30 a.m./Walk-thru hours are 7:30 to 11:30 a.m. ....................................... 720-865-2705

    Residential - Single Family and Duplex, Hours: 7:30 a.m. to 4:00 p.m. ..................................................................720-865-2710

    Records - Building Permit Files ....................................................................................................................................... 720-865-2790

    INSPECTION CODE DIRECTORY

    CONSTRUCTION: Permits 1R & 1C

    Pre Construction Meeting ................. 113

    (for Large Commercial or

    Shoring permits)

    Footing ............................................... 100

    Foundation Wall ................................. 101

    Setback Inspection ............................ 115

    Foundation Perimeter Drain ............... 102

    Waterproong .................................... 103

    Frost Wall Insulation ........................... 104

    Exterior Sheathing ............................. 105

    Bulk Plane .......................................... 114

    Batt Insulation .................................... 106

    Drywall ............................................... 107

    Final ................................................... 108

    Other.................................................. 109

    Exterior Lath ...................................... 111

    Frame ................................................ 112

    Blown Insulation ................................ 200

    DEMOLITION: Permit 1D

    Final ................................................... 110

    SIGNS: Permit 5

    Rough ................................................ 500

    Final ................................................... 501

    PLUMBING: Permit 4

    Groundwork ....................................... 400

    Rough ................................................ 401

    Pressure Test ..................................... 403

    Water Service ....................................404

    Final ................................................... 402

    BOILER/REFRIGERATION:

    Permits 7, 8, 9, 11, 12

    Groundwork ....................................... 700

    Pressure Test ..................................... 701Partial Rough ..................................... 702

    Rough ................................................ 703

    Final ................................................... 704

    GENERAL CONSTRUCTION: Permit 2

    Blown Insulation ................................ 200

    Roof ................................................... 201

    Gutter................................................. 202

    Siding ................................................ 203

    Fence ................................................. 204

    PRE-INSPECTION COMMERCIAL

    Flat Roof ............................................ 205Other.................................................. 206

    MECHANICAL: Permits 9, 11, 12

    Groundwork ....................................... 900

    Pressure Test ..................................... 901

    Partial Rough ..................................... 902

    Rough ................................................ 903

    Final ................................................... 904

    ELECTRICAL: Permits 3, 3A, 3B

    Slab ................................................... 300

    Underground ..................................... 301

    Partial Rough ..................................... 302

    Full Rough ......................................... 303

    Partial Final ........................................ 304

    Full Final ............................................ 305

    Fire Alarm .......................................... 306

    Service Equipment ............................ 307

    Ceiling ............................................... 308

    Walls .................................................. 309Card Access ...................................... 310

    Temporary Service ............................ 311

    UFER (ground rod) ............................ 312

    ELEVATORS: Permit 6

    Safety Test ......................................... 600

    Buffer Test ......................................... 601

    Pressure Test ..................................... 602

    Temporary Operation ........................ 603

    Final ................................................... 604

    FIRE PROTECTION: Permit 10

    Underground ..................................... 410Rough ................................................ 411

    Final ................................................... 412