Construction Schedule
description
Transcript of Construction Schedule
![Page 1: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/1.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
FALAJ AL QABIL ROUNDABOUT REV 2FALAJ AL QABIL ROUNDABOUT REV 2 717 30-Oct-13 A 16-Oct-15 743337
PREPARATORY WORKSPREPARATORY WORKS 717 30-Oct-13 A 16-Oct-15 0
GENERALGENERAL 717 30-Oct-13 A 16-Oct-15 0
CONTRACTUAL & PRELIMINARIESCONTRACTUAL & PRELIMINARIES 717 30-Oct-13 A 16-Oct-15 0
MILESTONE & MOBILIZATIONMILESTONE & MOBILIZATION 717 30-Oct-13 A 16-Oct-15 0
MILESTONESMILESTONES 717 30-Oct-13 A 16-Oct-15 0
CONTRACTUAL DATESCONTRACTUAL DATES 717 30-Oct-13 A 16-Oct-15 0
A0000 Contract Award Date 0 30-Oct-13 A 0 0 A6230, A6080, A6670, A6630, A6300, A7290
A6080 Mobilization 60 30-Oct-13 A 28-Dec-13 A 0 0 A0000 A6230, A6240, A6255, A6250, A6260, A6680
A6720 Construction Duration 548 28-Dec-13 A 16-Oct-15 0 0 A6680 A6100
A6100 Project Completion Date 0 16-Oct-15 0 0 A6720, A5780, A10230, A5290, A9830, A9460, A5880, A5930, A9750, A9820, A5490, A5940, A6900, A6960
CONSTRUCTIONAL DATESCONSTRUCTIONAL DATES 717 30-Oct-13 A 16-Oct-15 0
A6670 Project Commencement 0 30-Oct-13 A 0 0 A0000 A6680
A6680 Mobilization Completion 0 28-Dec-13 A 0 0 A6230, A6240, A6255, A6250, A6260, A6080, A6670A6720, A1260, A6110
A6800 Resolution of all Expropriations about SR-2 0 28-Feb-14 A 0 0 A1330, A1340, A1400, A1410
A6700 Commence Traffic Diversions from Existing Roads to Temporary Roads 0 30-Apr-14 0 0 A1010 A9930
A10580 Resolution of Falaj Location under Bridge 0 20-Jul-14 0 0 A11720 A11730
A6710 Complete Traffic Diversion from Temporary Roads to Batinah Highway 0 29-Apr-15 0 0 A5490, A6790, A3940 A9900
A6730 Complete Traffic Diversion from Temporary Roads to Sohar-Buraimi Road 0 28-May-15 0 0 A5640 A1530
A6690 Completion of all works 0 16-Oct-15 0 0 A6740
A6740 Complete Traffic Diversion from Temporary Roads to New Service Roads 0 16-Oct-15 0 0 A5780, A5940, A9640 A6690
MOBILIZATIONMOBILIZATION 60 30-Oct-13 A 28-Dec-13 A 0
GENERALGENERAL 60 30-Oct-13 A 28-Dec-13 A 0
A6230 Obtain NOC's 60 30-Oct-13 A 28-Dec-13 A 0 0 A0000, A6080 A6240, A6260, A6255, A6680,
A6240 Setting-up Engineer's Offices 38 09-Nov-13 A 16-Dec-13 A 0 0 A6230, A6080 A6250, A6680
A6260 Erection of Laboratory & Store 45 14-Nov-13 A 28-Dec-13 A 0 0 A6230, A6080 A6680
A6250 Setting-up Contractor's Offices 38 16-Nov-13 A 23-Dec-13 A 0 0 A6240, A6080 A6680
A6255 Setting-up of Contractor's Camp 35 24-Nov-13 A 28-Dec-13 A 0 0 A6230, A6080 A6680
TRAFFIC MANAGEMENTTRAFFIC MANAGEMENT 53 06-Nov-13 A 28-Dec-13 A 0
GENERALGENERAL 53 06-Nov-13 A 28-Dec-13 A 0
A6630 Submit Traffic Mangement Plans 15 06-Nov-13 A 20-Nov-13 A 0 0 A0000 A6640
A6640 Approve Traffic Mnagement Plans 15 17-Nov-13 A 01-Dec-13 A 0 0 A6630 A6650
A6650 Obtain Traffic NOC's 15 02-Dec-13 A 16-Dec-13 A 0 0 A6640 A6660
A6660 Obtain Approval from ROP Police 12 17-Dec-13 A 28-Dec-13 A 0 0 A6650, A6230 A1260, A1070
SHOP DRAWINGSSHOP DRAWINGS 325 11-Jan-14 A 01-Dec-14 0
BOX CULVERT 3 CELL @ CH 21+260BOX CULVERT 3 CELL @ CH 21+260 30 17-Aug-14 15-Sep-14 0
A12510 Prepare & Submit Shop Drawings 15 17-Aug-14 31-Aug-14 A12520
A12520 Approval of Shop Drawings 15 01-Sep-14 15-Sep-14 A12510 A11780
BOX CULVERT 1 CELL @ CH 21+485BOX CULVERT 1 CELL @ CH 21+485 30 15-Sep-14 14-Oct-14 0
A10800 Prepare & Submit Shop Drawings 15 15-Sep-14 29-Sep-14 A10810
A10810 Approval of Shop Drawings 15 30-Sep-14 14-Oct-14 A10800 A2240
BOX CULVERT 8 CELL @ CH 21+838BOX CULVERT 8 CELL @ CH 21+838 30 25-Aug-14 23-Sep-14 0
A10880 Prepare & Submit Shop Drawings 15 25-Aug-14 08-Sep-14 A10890
A10890 Approval of Shop Drawings 15 09-Sep-14 23-Sep-14 A10880 A2870
BOX CULVERT 44 CELL @ CH 21+985BOX CULVERT 44 CELL @ CH 21+985 30 03-Mar-14 A 01-Apr-14 A 0
A10620 Prepare & Submit Shop Drawings 15 03-Mar-14 A 17-Mar-14 A A6230 A10630, A10640
A10630 Approval of Shop Drawings 15 18-Mar-14 A 01-Apr-14 A A10620 A2940
BOX CULVERT 9 CELL @ CH 22+650BOX CULVERT 9 CELL @ CH 22+650 68 16-Mar-14 A 22-May-14 0
A10640 Prepare & Submit Shop Drawings 15 16-Mar-14 A 30-Mar-14 A A10620 A10650
A10650 Approval of Shop Drawings 15 08-May-14 22-May-14 A10640 A2800
BOX CULVERT 5 CELL @ 23+500BOX CULVERT 5 CELL @ 23+500 30 30-Jun-14 29-Jul-14 0
A10700 Prepare & Submit Shop Drawings 15 30-Jun-14 14-Jul-14 A10710
A10710 Approval of Shop Drawings 15 15-Jul-14 29-Jul-14 A10700 A2660
BOX CULVERT 1 CELL @ CH 23+760BOX CULVERT 1 CELL @ CH 23+760 30 17-Aug-14 15-Sep-14 0
J J J J J J J J J
2014 2015 2016
16-Oct-15, FALAJ AL
16-Oct-15, PREPARAT
16-Oct-15, GENERAL
16-Oct-15, CONTRAC
16-Oct-15, MILESTON
16-Oct-15, MILESTONES
16-Oct-15, CONTRAC
Contract Award Date
Mobilization
Construction DurationProject Completion Date
16-Oct-15, CONSTRU
Project Commencement
Mobilization Completion
Resolution of all Expropriations about SR-2
Commence Traffic Diversions from Existing Roads
Resolution of Falaj Location under Bridge
Complete Traffic Diversion from
Complete Traffic Diversion fro
Completion of all works
Complete Traffic Diver
28-Dec-13 A, MOBILIZATION
28-Dec-13 A, GENERAL
Obtain NOC's
Setting-up Engineer's Offices
Erection of Laboratory & Store
Setting-up Contractor's Offices
Setting-up of Contractor's Camp28-Dec-13 A, TRAFFIC MANAGEMENT
28-Dec-13 A, GENERAL
Submit Traffic Mangement Plans
Approve Traffic Mnagement Plans
Obtain Traffic NOC's
Obtain Approval from ROP Police01-Dec-14, SHOP DRAW INGS
15-Sep-14, BOX CULVERT 3 CELL @ CH 21+260
Prepare & Submit Shop Drawings
Approval of Shop Drawings
14-Oct-14, BOX CULVERT 1 CELL @ CH 21+485
Prepare & Submit Shop Drawings
Approval of Shop Drawings23-Sep-14, BOX CULVERT 8 CELL @ CH 21+838
Prepare & Submit Shop Drawings
Approval of Shop Drawings01-Apr-14 A, BOX CULVERT 44 CELL @ CH 21+985
Prepare & Submit Shop Drawings
Approval of Shop Drawings22-May-14, BOX CULVERT 9 CELL @ CH 22+650
Prepare & Submit Shop Drawings
Approval of Shop Drawings29-Jul-14, BOX CULVERT 5 CELL @ 23+500
Prepare & Submit Shop Drawings
Approval of Shop Drawings15-Sep-14, BOX CULVERT 1 CELL @ CH 23+760
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 1 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 2: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/2.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A10680 Prepare & Submit Shop Drawings 15 17-Aug-14 31-Aug-14 A10690
A10690 Approval of Shop Drawings 15 01-Sep-14 15-Sep-14 A10680 A2590
BOX CULVERT 1 CELL @ CH 23+997BOX CULVERT 1 CELL @ CH 23+997 30 09-Sep-14 08-Oct-14 0
A10760 Prepare & Submit Shop Drawings 15 09-Sep-14 23-Sep-14 A10770
A10770 Approval of Shop Drawings 15 24-Sep-14 08-Oct-14 A10760 A2380
BOX CULVERT 1 CELL @ CH 24+235BOX CULVERT 1 CELL @ CH 24+235 30 29-Sep-14 28-Oct-14 0
A10840 Prepare & Submit Shop Drawings 15 29-Sep-14 13-Oct-14 A10850
A10850 Approval of Shop Drawings 15 14-Oct-14 28-Oct-14 A10840 A2450
BOX CULVERT 1 CELL @ 24+570BOX CULVERT 1 CELL @ 24+570 30 19-Oct-14 17-Nov-14 0
A10860 Prepare & Submit Shop Drawings 15 19-Oct-14 02-Nov-14 A10870
A10870 Approval of Shop Drawings 15 03-Nov-14 17-Nov-14 A10860 A2520
PEDESTRIAN UNDERPASS 1 @ CH 22+800 - SOL1PEDESTRIAN UNDERPASS 1 @ CH 22+800 - SOL1 30 29-May-14 27-Jun-14 0
A12530 Prepare & Submit Drawings 15 29-May-14 12-Jun-14 A12540
A12540 Approval of Shop Drawings 15 13-Jun-14 27-Jun-14 A12530 A11850
PEDESTRIAN UNDERPASS 2 @ CH 23+300 - SOL1PEDESTRIAN UNDERPASS 2 @ CH 23+300 - SOL1 30 27-Aug-14 25-Sep-14 0
A10900 Prepare & Submit Shop Drawings 15 27-Aug-14 10-Sep-14 A10910
A10910 Approval of Shop Drawings 15 11-Sep-14 25-Sep-14 A10900 A1795
PEDESTRIAN UNDERPASS 3 @ CH 00+050- SOL3PEDESTRIAN UNDERPASS 3 @ CH 00+050- SOL3 30 24-Aug-14 22-Sep-14 0
A10940 Prepare & Submit Shop Drawings 15 24-Aug-14 07-Sep-14 A10950
A10950 Approval of Shop Drawings 15 08-Sep-14 22-Sep-14 A10940 A5210
PIER 1 - NBPIER 1 - NB 30 26-Feb-14 A 27-Mar-14 A 0
A10960 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A6230 A10970
A10970 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A10960 A3210
FALAJ RELOCATIONFALAJ RELOCATION 30 19-Mar-14 A 23-Mar-14 A 0
A11470 Prepare & Submit Shop Drawings 15 19-Mar-14 A 22-Mar-14 A A6230 A11480
A11480 Approval of Shop Drawings 15 23-Mar-14 A 23-Mar-14 A A11470 A3160, A999
PIER 2 - NBPIER 2 - NB 30 26-Feb-14 A 27-Mar-14 A 0
A10980 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A6230 A10990
A10990 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A10980 A3160
PIER 3 - NBPIER 3 - NB 30 26-Feb-14 A 27-Mar-14 A 0
A11000 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11010, A11020, A11060
A11010 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11000 A1540
PIER 4 - NBPIER 4 - NB 30 26-Feb-14 A 27-Mar-14 A 0
A11020 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11000 A11030, A11040
A11030 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11020 A3310
PIER 5 - NBPIER 5 - NB 30 26-Feb-14 A 27-Mar-14 A 0
A11040 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11020 A11050
A11050 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11040 A3260
AB1 - NBAB1 - NB 30 26-Feb-14 A 27-Mar-14 A 0
A11060 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11000 A11070, A11080
A11070 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11060 A1590
AB2 - NBAB2 - NB 30 26-Feb-14 A 27-Mar-14 A 0
A11080 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11060 A11090, A11100
A11090 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11080 A3360
PIER 1 - SBPIER 1 - SB 30 26-Feb-14 A 27-Mar-14 A 0
A11100 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11080 A11110, A11120
A11110 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11100 A3750
PIER 2 - SBPIER 2 - SB 30 26-Feb-14 A 27-Mar-14 A 0
A11120 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11100 A11130
A11130 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11120 A4000
PIER 3 - SBPIER 3 - SB 30 26-Feb-14 A 27-Mar-14 A 0
A11140 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A6230 A11150, A11160
A11150 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11140 A4100
PIER 4 -SBPIER 4 -SB 30 26-Feb-14 A 27-Mar-14 A 0
A11160 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11140 A11170, A11180, A11200, A11220
J J J J J J J J J
2014 2015 2016
Prepare & Submit Shop Drawings
Approval of Shop Drawings08-Oct-14, BOX CULVERT 1 CELL @ CH 23+997
Prepare & Submit Shop Drawings
Approval of Shop Drawings28-Oct-14, BOX CULVERT 1 CELL @ CH 24+235
Prepare & Submit Shop Drawings
Approval of Shop Drawings17-Nov-14, BOX CULVERT 1 CELL @ 24+570
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Jun-14, PEDESTRIAN UNDERPASS 1 @ CH
Prepare & Submit Drawings
Approval of Shop Drawings
25-Sep-14, PEDESTRIAN UNDERPASS 2
Prepare & Submit Shop Drawings
Approval of Shop Drawings22-Sep-14, PEDESTRIAN UNDERPASS 3
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, PIER 1 - NB
Prepare & Submit Shop Drawings
Approval of Shop Drawings23-Mar-14 A, FALAJ RELOCATION
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, PIER 2 - NB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, PIER 3 - NB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, PIER 4 - NB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, PIER 5 - NB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, AB1 - NB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, AB2 - NB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, PIER 1 - SB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, PIER 2 - SB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, PIER 3 - SB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, PIER 4 -SB
Prepare & Submit Shop Drawings
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 2 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 3: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/3.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A11170 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11160 A4050
PIER 5 - SBPIER 5 - SB 30 26-Feb-14 A 27-Mar-14 A 0
A11180 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11160 A11190
A11190 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11180 A3950
AB 1 - SBAB 1 - SB 30 26-Feb-14 A 27-Mar-14 A 0
A11200 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11160 A11210
A11210 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11200 A3800
AB2 - SBAB2 - SB 30 26-Feb-14 A 27-Mar-14 A 0
A11220 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11160 A11230
A11230 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11220 A4170
BRIDGE DECK SPAN AB1 & P3 - NBBRIDGE DECK SPAN AB1 & P3 - NB 30 22-Jun-14 21-Jul-14 0
A11240 Prepare & Submit Shop Drawings 15 22-Jun-14 06-Jul-14 A11250
A11250 Approval of Shop Drawings 15 07-Jul-14 21-Jul-14 A11240 A1640
BRIDGE DECK SPAN AB2 & P3 - NBBRIDGE DECK SPAN AB2 & P3 - NB 30 20-Aug-14 18-Sep-14 0
A11260 Prepare & Submit Shop Drawings 15 20-Aug-14 03-Sep-14 A11270
A11270 Approval of Shop Drawings 15 04-Sep-14 18-Sep-14 A11260 A3500
BRIDGE DECK SPAN AB2 & P3 - SBBRIDGE DECK SPAN AB2 & P3 - SB 30 14-Oct-14 12-Nov-14 0
A11280 Prepare & Submit Shop Drawings 15 14-Oct-14 28-Oct-14 A11290
A11290 Approval of Shop Drawings 15 29-Oct-14 12-Nov-14 A11280 A3850
BRIDGE DECK SPAN AB1 & P3- SBBRIDGE DECK SPAN AB1 & P3- SB 30 02-Nov-14 01-Dec-14 0
A11490 Prepare & Submit Shop Drawings 15 02-Nov-14 16-Nov-14 A11500
A11500 Approval of Shop Drawings 15 17-Nov-14 01-Dec-14 A11490 A4310
MSE WALLSMSE WALLS 30 11-Jan-14 A 09-Feb-14 A 0
A11320 Prepare & Submit Shop Drawings 15 11-Jan-14 A 25-Jan-14 A A6230 A11330
A11330 Approval of Shop Drawings 15 26-Jan-14 A 09-Feb-14 A A11320 A5020
PROCUREMENTPROCUREMENT 471 29-Nov-13 A 14-Mar-15 0
MATERIALMATERIAL 452 18-Dec-13 A 14-Mar-15 0
PRECAST MSE WALL PANELSPRECAST MSE WALL PANELS 75 18-Dec-13 A 02-Mar-14 A 0
A6300 Submit Material for Approval 15 18-Dec-13 A 01-Jan-14 A 0 0 A0000 A6310
A6310 Obtain Material Approval 20 02-Jan-14 A 21-Jan-14 A 0 0 A6300 A6320
A6320 Delivery to Site 40 22-Jan-14 A 02-Mar-14 A 0 0 A6310 A5020
POT BEARINGSPOT BEARINGS 172 01-Mar-14 A 19-Aug-14 0
A6450 Submit Material for Approval 20 01-Mar-14 A 20-Mar-14 A 0 0 A6230 A6460
A6460 Obtain Material Approval 30 21-Mar-14 A 21-Apr-14 0 0 A6450 A6470
A6470 Delivery to Site 120 22-Apr-14 19-Aug-14 0 0 A6460 A1640, A3500, A3850, A4310
EXPANSION JOINTEXPANSION JOINT 170 25-Jul-14 10-Jan-15 0
A10590 Submit Material for Approval 20 25-Jul-14 13-Aug-14 0 0 A6230 A10600
A10600 Obtain Material Approval 30 14-Aug-14 12-Sep-14 0 0 A10590 A10610
A10610 Delivery to Site 120 13-Sep-14 10-Jan-15 0 0 A10600 A3570
LIGHTING POLES & LUMINARIESLIGHTING POLES & LUMINARIES 140 26-Jul-14 12-Dec-14 0
A6330 Submit Material for Approval 20 26-Jul-14 14-Aug-14 0 0 A6230 A6340
A6340 Obtain Material Approval 20 15-Aug-14 03-Sep-14 0 0 A6330 A6350
A6350 Delivery to Site 100 04-Sep-14 12-Dec-14 0 0 A6340 A4670, A5990, A5010
PRECAST CONC. BARRIER MOLDSPRECAST CONC. BARRIER MOLDS 75 30-Aug-14 12-Nov-14 0
A6270 Submit Material for Approval 15 30-Aug-14 13-Sep-14 0 0 A6230 A6280
A6280 Obtain Material Approval 20 14-Sep-14 03-Oct-14 0 0 A6270 A6290
A6290 Delivery to Site 40 04-Oct-14 12-Nov-14 0 0 A6280 A4550, A3920, A5400
RC STORM SEWERRC STORM SEWER 50 26-Jun-14 14-Aug-14 0
A6360 Submit Material for Approval 15 26-Jun-14 10-Jul-14 0 0 A6230 A6370
A6370 Obtain Material Approval 15 11-Jul-14 25-Jul-14 0 0 A6360 A6380
A6380 Delivery to Site 20 26-Jul-14 14-Aug-14 0 0 A6370 A5100, A5140
GUARDRAILGUARDRAIL 100 05-Dec-14 14-Mar-15 0
A6420 Submit Material for Approval 20 05-Dec-14 24-Dec-14 0 0 A6230 A6430
A6430 Obtain Material Approval 20 25-Dec-14 13-Jan-15 0 0 A6420 A6440
A6440 Delivery to Site 60 14-Jan-15 14-Mar-15 0 0 A6430 A5460
J J J J J J J J J
2014 2015 2016
Approval of Shop Drawings27-Mar-14 A, PIER 5 - SB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, AB 1 - SB
Prepare & Submit Shop Drawings
Approval of Shop Drawings27-Mar-14 A, AB2 - SB
Prepare & Submit Shop Drawings
Approval of Shop Drawings21-Jul-14, BRIDGE DECK SPAN AB1 & P3 - NB
Prepare & Submit Shop Drawings
Approval of Shop Drawings18-Sep-14, BRIDGE DECK SPAN AB2 & P3 - NB
Prepare & Submit Shop Drawings
Approval of Shop Drawings12-Nov-14, BRIDGE DECK SPAN AB2 & P3 - SB
Prepare & Submit Shop Drawings
Approval of Shop Drawings01-Dec-14, BRIDGE DECK SPAN AB1 & P3- SB
Prepare & Submit Shop Drawings
Approval of Shop Drawings09-Feb-14 A, MSE WALLS
Prepare & Submit Shop Drawings
Approval of Shop Drawings14-Mar-15, PROCUREMENT
14-Mar-15, MATERIAL
02-Mar-14 A, PRECAST MSE WALL PANELS
Submit Material for Approval
Obtain Material Approval
Delivery to Site19-Aug-14, POT BEARINGS
Submit Material for Approval
Obtain Material Approval
Delivery to Site10-Jan-15, EXPANSION JOINT
Submit Material for Approval
Obtain Material Approval
Delivery to Site12-Dec-14, LIGHTING POLES & LUMINARIES
Submit Material for Approval
Obtain Material Approval
Delivery to Site12-Nov-14, PRECAST CONC. BARRIER MOLDS
Submit Material for Approval
Obtain Material Approval
Delivery to Site14-Aug-14, RC STORM SEWER
Submit Material for Approval
Obtain Material Approval
Delivery to Site14-Mar-15, GUARDRAIL
Submit Material for Approval
Obtain Material Approval
Delivery to Site
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 3 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 4: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/4.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
ROAD SIGNSROAD SIGNS 60 14-Jan-15 14-Mar-15 0
A6390 Submit Material for Approval 20 14-Jan-15 02-Feb-15 0 0 A6230 A6400
A6400 Obtain Material Approval 20 03-Feb-15 22-Feb-15 0 0 A6390 A6410
A6410 Delivery to Site 20 23-Feb-15 14-Mar-15 0 0 A6400 A5470, A5930, A5620, A5760
BITUMINOUS PAINTBITUMINOUS PAINT 60 15-Jan-14 A 15-Mar-14 A 0
A11510 Submit Material for Approval 15 15-Jan-14 A 29-Jan-14 A 0 0 A6230 A11520
A11520 Obtain Material Approval 15 30-Jan-14 A 13-Feb-14 A 0 0 A11510 A11530
A11530 Delivery to Site 30 14-Feb-14 A 15-Mar-14 A 0 0 A11520 A1570
WATERSTOPWATERSTOP 116 10-Feb-14 A 05-Jun-14 0
A11540 Submit Material for Approval 15 10-Feb-14 A 24-Feb-14 A 0 0 A6230 A11550
A11550 Obtain Material Approval 15 25-Feb-14 A 11-Mar-14 A 0 0 A11540 A11560
A11560 Delivery to Site 40 27-Apr-14 05-Jun-14 0 0 A11550 A2940
GEOTEXTILEGEOTEXTILE 60 24-May-14 22-Jul-14 0
A11570 Submit Material for Approval 15 24-May-14 07-Jun-14 0 0 A6230 A11580
A11580 Obtain Material Approval 15 08-Jun-14 22-Jun-14 0 0 A11570 A11590
A11590 Delivery to Site 30 23-Jun-14 22-Jul-14 0 0 A11580 A5070
JOINT SEALANTJOINT SEALANT 75 30-Aug-14 12-Nov-14 0
A11600 Submit Material for Approval 15 30-Aug-14 13-Sep-14 0 0 A6230 A11610
A11610 Obtain Material Approval 20 14-Sep-14 03-Oct-14 0 0 A11600 A11620
A11620 Delivery to Site 40 04-Oct-14 12-Nov-14 0 0 A11610 A4550, A3920, A5400
S/CS/C 318 29-Nov-13 A 12-Oct-14 0
ELECTRICAL S/CELECTRICAL S/C 40 02-Feb-14 A 13-Mar-14 A 0
A6510 Select S/C 15 02-Feb-14 A 16-Feb-14 A 0 0 A6230 A6520
A6520 Approve S/C 15 17-Feb-14 A 03-Mar-14 A 0 0 A6510 A6530
A6530 Mobilization to Site 10 04-Mar-14 A 13-Mar-14 A 0 0 A6520 A1360, A1100, A4800, A4910
WATER S/CWATER S/C 35 01-Mar-14 A 04-Apr-14 A 0
A6540 Select S/C 15 01-Mar-14 A 15-Mar-14 A 0 0 A6230 A6550
A6550 Approve S/C 15 16-Mar-14 A 30-Mar-14 A 0 0 A6540 A6560
A6560 Mobilization to Site 5 31-Mar-14 A 04-Apr-14 A 0 0 A6550 A1020
TELEPHONE S/CTELEPHONE S/C 40 05-Feb-14 A 16-Mar-14 A 0
A6570 Select S/C 15 05-Feb-14 A 19-Feb-14 A 0 0 A6230 A6580
A6580 Approve S/C 15 20-Feb-14 A 06-Mar-14 A 0 0 A6570 A6590
A6590 Mobilization to Site 10 07-Mar-14 A 16-Mar-14 A 0 0 A6580 A1450
PILING S/CPILING S/C 75 29-Nov-13 A 11-Feb-14 A 0
A6480 Select S/C 15 29-Nov-13 A 13-Dec-13 A 0 0 A6230 A6490
A6490 Approve S/C 15 14-Dec-13 A 28-Dec-13 A 0 0 A6480 A6500
A6500 Mobilization to Site 45 29-Dec-13 A 11-Feb-14 A 0 0 A6490 A1540, A3160
POST TENSIONING S/CPOST TENSIONING S/C 240 15-Feb-14 A 12-Oct-14 0
A6600 Select S/C 15 15-Feb-14 A 01-Mar-14 A 0 0 A6230 A6610
A6610 Approve S/C 15 14-Aug-14 28-Aug-14 0 0 A6600 A6620
A6620 Mobilization to Site 45 29-Aug-14 12-Oct-14 0 0 A6610 A1670
BATINAH HIGHWAYBATINAH HIGHWAY 657 29-Dec-13 A 16-Oct-15 612512
HIGHWAY & SLIP ROADSHIGHWAY & SLIP ROADS 636 29-Dec-13 A 25-Sep-15 578157
SOL1, SOL5, SOL6SOL1, SOL5, SOL6 489 29-Dec-13 A 01-May-15 483934
TEMPORARY DIVERSION FOR EXISTING NORTHERN SERVICE ROADTEMPORARY DIVERSION FOR EXISTING NORTHERN SERVICE ROAD 23 29-Dec-13 A 20-Jan-14 A 327
SR1 (CH 0+000 to CH 0+797)SR1 (CH 0+000 to CH 0+797) 23 29-Dec-13 A 20-Jan-14 A 327
GENERALGENERAL 23 29-Dec-13 A 20-Jan-14 A 327
A1260 Laying of Asphalt of Temp. Road over SR-1 17 29-Dec-13 A 15-Jan-14 A 327 M3 A6660, A6680 A10330
A10330 Placing Plastic Barriers 5 16-Jan-14 A 20-Jan-14 A 0 0 A1260 A1270
A1270 Shift Traffic from Existing Northern Service Road to Temp. SR-1 0 20-Jan-14 A 0 0 A10330 A1010
TEMPORARY DIVERSION FOR EXISTING HIGHWAY - NORTH BOUNDTEMPORARY DIVERSION FOR EXISTING HIGHWAY - NORTH BOUND 120 05-Jan-14 A 30-Apr-14 655
SOL1-NORTH (CH 21+100 to CH 25+300)SOL1-NORTH (CH 21+100 to CH 25+300) 120 05-Jan-14 A 30-Apr-14 655
GENERALGENERAL 120 05-Jan-14 A 30-Apr-14 655
A1070 Protection of services 40 05-Jan-14 A 13-Feb-14 A 0 0 A6660 A1000, A1080
A1000 Laying of Asphalt on Temp. new Road Adjacent to SOL1-NB 30 13-Jan-14 A 25-Apr-14 655 M3 A1070, A999, A1090 A10490, A1005
J J J J J J J J J
2014 2015 2016
14-Mar-15, ROAD SIGNS
Submit Material for Approval
Obtain Material Approval
Delivery to Site15-Mar-14 A, BITUMINOUS PAINT
Submit Material for Approval
Obtain Material Approval
Delivery to Site05-Jun-14, WATERSTOP
Submit Material for Approval
Obtain Material Approval
Delivery to Site22-Jul-14, GEOTEXTILE
Submit Material for Approval
Obtain Material Approval
Delivery to Site12-Nov-14, JOINT SEALANT
Submit Material for Approval
Obtain Material Approval
Delivery to Site12-Oct-14, S/C
13-Mar-14 A, ELECTRICAL S/C
Select S/C
Approve S/C
Mobilization to Site04-Apr-14 A, WATER S/C
Select S/C
Approve S/C
Mobilization to Site16-Mar-14 A, TELEPHONE S/C
Select S/C
Approve S/C
Mobilization to Site11-Feb-14 A, PILING S/C
Select S/C
Approve S/C
Mobilization to Site12-Oct-14, POST TENSIONING S/C
Select S/C
Approve S/C
Mobilization to Site16-Oct-15, BATINAH HIGHWAY
25-Sep-15, HIGHWAY &
01-May-15, SOL1, SOL5, SOL6
20-Jan-14 A, TEMPORARY DIVERSION FOR EXISTING
20-Jan-14 A, SR1 (CH 0+000 to CH 0+797)
20-Jan-14 A, GENERAL
Laying of Asphalt of Temp. Road over SR-1
Placing Plastic BarriersShift Traffic from Existing Northern Service Road to Temp. SR-1
30-Apr-14, TEMPORARY DIVERSION FOR EXIST
30-Apr-14, SOL1-NORTH (CH 21+100 to CH 25+300)
30-Apr-14, GENERAL
Protection of services
Laying of Asphalt on Temp. new Road Adjacent to SOL1-NB
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 4 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 5: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/5.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A1080 Extension of Existing Drainage under Highway 30 14-Feb-14 A 15-Mar-14 A A1070 A999
A999 Construction of Falaj Under Temp. Diversion 18 12-Mar-14 A 30-Mar-14 A A11480, A1080 A1000, A9910, A1090, A11630
A1090 Repairs due to Heavy Rainfalls on the 26/27 of March 2014 17 30-Mar-14 A 13-Apr-14 A A999 A1000
A1005 Placing of Plastic Barriers 8 23-Apr-14 30-Apr-14 0 0 A1000 A1010
A1010 Shift Traffic from Existing Main Road NB to Temp. diversion 0 30-Apr-14 0 0 A1005, A1270 A6700, A2940, A2800, A1540, A2660, A3160, A5310, A1590
TEMPORARY DIVERSION FOR EXISTING SOUTHERN SERVICE ROADTEMPORARY DIVERSION FOR EXISTING SOUTHERN SERVICE ROAD 56 19-Jan-14 A 15-Mar-14 A 655
SR2 (CH 0+000 to CH 1+450)SR2 (CH 0+000 to CH 1+450) 56 19-Jan-14 A 15-Mar-14 A 655
GENERALGENERAL 56 19-Jan-14 A 15-Mar-14 A 655
A10490 Protection of services 21 19-Jan-14 A 08-Feb-14 A 0 0 A1000 A9940, A10500, A1330, A1340, A1400, A1410
A9940 Laying of Asphalt Adjacent to SR-2 30 09-Feb-14 A 10-Mar-14 A 655 M3 A10490, A1330, A1340, A1400, A1410A9950
A1330 Resolution of expropriation of Fuel Station (SR-2 CH 1+140) 0 28-Feb-14 A 0 0 A10490 A6800, A9940
A1340 Resolution of expropriation of Graveyard (SR-2 CH 0+900) 0 28-Feb-14 A 0 0 A10490 A6800, A9940
A1400 Resolution of expropriation of Al-Falaj Shopping (SR-2 CH 0+380) 0 28-Feb-14 A 0 0 A10490 A6800, A9940
A1410 Resolution of expropriation of Shopping Buildings (SR-2 CH 0+300) 0 28-Feb-14 A 0 0 A10490 A6800, A9940
A9950 Placing Plastic Barriers 5 11-Mar-14 A 15-Mar-14 A 0 0 A9940 A10340
A10340 Shift Traffic from Existing Southern Service Road Temp. SR-2 0 15-Mar-14 A 0 0 A9950 A9910
TEMPORARY DIVERSION FOR EXISTING HIGHWAY - SOUTH BOUNDTEMPORARY DIVERSION FOR EXISTING HIGHWAY - SOUTH BOUND 96 25-Jan-14 A 30-Apr-14 764
SOL1-SOUTH (CH 25+300 to CH 21+100)SOL1-SOUTH (CH 25+300 to CH 21+100) 96 25-Jan-14 A 30-Apr-14 764
GENERALGENERAL 96 25-Jan-14 A 30-Apr-14 764
A10500 Protection of services 15 25-Jan-14 A 05-Mar-14 A 0 0 A10490, A10470 A9910, A10660
A10660 Extension of Existing Drainage under Highway 30 01-Feb-14 A 10-Mar-14 A A10500 A10670
A9910 Laying of Asphalt on Temp. Road Adjacent to SOL-1 SB over SOLs 4&7 35 09-Feb-14 A 23-Apr-14 764 M3 A10340, A10500, A10670, A999A9920
A10470 Construction of Falaj Under Temp Diversion 27 10-Mar-14 A 05-Apr-14 A A10500
A10670 Repairs due to Heavy Rainfalls on the 26/27 of March 2014 15 31-Mar-14 A 15-Apr-14 A10660 A9910
A9920 Placing Plastic Barriers 7 24-Apr-14 30-Apr-14 0 0 A9910 A9930
A9930 Shift Traffic from Existing Main Road SB to Temp. diversion 0 30-Apr-14 0 0 A9920, A6700 A2940, A2800, A2660, A4000, A1360, A4100, A1450, A5020, A11780
INVESTIGATIONINVESTIGATION 45 29-Dec-13 A 11-Feb-14 A 0
GEOTECHNICAL INVESTIGATIONGEOTECHNICAL INVESTIGATION 45 29-Dec-13 A 11-Feb-14 A 0
GENERALGENERAL 45 29-Dec-13 A 11-Feb-14 A 0
A6110 Site Survey 10 29-Dec-13 A 07-Jan-14 A 0 0 A6680 A6120
A6120 Setting up Drilling Rigs 7 08-Jan-14 A 14-Jan-14 A 0 0 A6110 A6130, A1540, A3160, A6140
A6130 Execution of Trial Pits 7 15-Jan-14 A 21-Jan-14 A 0 0 A6120 A6140
A6140 Execution of Boreholes 15 15-Jan-14 A 29-Jan-14 A 0 0 A6130, A6120 A6150
A6150 (SPT) Test 5 30-Jan-14 A 03-Feb-14 A 0 0 A6140 A6160
A6160 Submission of Prelim. Laboratory Testing Report Submission 4 04-Feb-14 A 07-Feb-14 A 0 0 A6150 A6170
A6170 Receipt Confirmation of Pile Length from Engineer 4 08-Feb-14 A 11-Feb-14 A A6160 A1540
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 174 09-May-14 29-Oct-14 11743
CLEARING & EXCAVATIONCLEARING & EXCAVATION 174 09-May-14 29-Oct-14 11743
GENERALGENERAL 174 09-May-14 29-Oct-14 11743
A5310 Clearing & Grubbing 30 09-May-14 07-Jun-14 4259 M2 A1010 A5320, A11850
A5320 Removal of Structures & Obstructures 60 23-May-14 21-Jul-14 1 LS A5310 A5330, A6030
A5330 Utilities Trench Ear thworks 60 22-Jul-14 19-Sep-14 1641 M3 A5320 A5340, A1450
A5340 Structural & Road Way Excavation 100 22-Jul-14 29-Oct-14 5842 M3 A5330 A4580, A5090, A11740
UTILITIESUTILITIES 105 27-Jul-14 08-Nov-14 19317
GENERALGENERAL 105 27-Jul-14 08-Nov-14 19317
FUTURE DUCTS - STAGE 1FUTURE DUCTS - STAGE 1 90 27-Jul-14 24-Oct-14 5117
A11740 Install Electrical Ducts 60 27-Jul-14 24-Sep-14 3854 LM A5340 A11750
A11750 Install Water Ducts 30 05-Sep-14 04-Oct-14 216 LM A11740 A11760
A11760 Install Irrigation Ducts 30 15-Sep-14 14-Oct-14 807 LM A11750 A11770
A11770 Install Telephone Ducst 30 25-Sep-14 24-Oct-14 240 LM A11760 A5030
TELEPHONETELEPHONE 85 11-Aug-14 03-Nov-14 2200
A1450 Installation of New (GTO) Omantal Line 50 11-Aug-14 29-Sep-14 1100 0 A5330, A6590, A9930 A1455, A1360, A1335, A1280
A1455 Obtain Shutdown & Connect to Existing 15 30-Sep-14 14-Oct-14 0 0 A1450 A1457
A1457 Remove & Dispose Existing (GTO) Omantal Line 20 15-Oct-14 03-Nov-14 1100 0 A1455 A5030
ELECTRICAL (11 KV)ELECTRICAL (11 KV) 90 11-Aug-14 08-Nov-14 6400
J J J J J J J J J
2014 2015 2016
Extension of Existing Drainage under Highway
Construction of Falaj Under Temp. DiversionRepairs due to Heavy Rainfalls on the 26/27 of March 2014
Placing of Plastic BarriersShift Traffic from Existing Main Road NB to Temp. diversion
15-Mar-14 A, TEMPORARY DIVERSION FOR EXIST
15-Mar-14 A, SR2 (CH 0+000 to CH 1+450)
15-Mar-14 A, GENERAL
Protection of services
Laying of Asphalt Adjacent to SR-2Resolution of expropriation of Fuel Station (SR-2 CH 1+140)
Resolution of expropriation of Graveyard (SR-2 CH 0+900)
Resolution of expropriation of Al-Falaj Shopping (SR-2 CH 0+380)
Resolution of expropriation of Shopping Buildings (SR-2 CH 0+300)
Placing Plastic BarriersShift Traffic from Existing Southern Service Road Temp. SR-2
30-Apr-14, TEMPORARY DIVERSION FOR EXIST
30-Apr-14, SOL1-SOUTH (CH 25+300 to CH 21+100)
30-Apr-14, GENERAL
Protection of servicesExtension of Existing Drainage under Highway
Laying of Asphalt on Temp. Road Adjacent to SOL-1
Construction of Falaj Under Temp DiversionRepairs due to Heavy Rainfalls on the 26/27 of March 2014
Placing Plastic BarriersShift Traffic from Existing Main Road SB to Temp. diversion
11-Feb-14 A, INVESTIGATION
11-Feb-14 A, GEOTECHNICAL INVESTIGATION
11-Feb-14 A, GENERAL
Site Survey
Setting up Drilling Rigs
Execution of Trial Pits
Execution of Boreholes
(SPT) Test
Submission of Prelim. Laboratory Testing Report Submission
Receipt Confirmation of Pile Length from Engineer29-Oct-14, GENERAL CIVIL WORKS
29-Oct-14, CLEARING & EXCAVATION
29-Oct-14, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Utilities Trench Ear thworks
Structural & Road Way Excavation08-Nov-14, UTILITIES
08-Nov-14, GENERAL
24-Oct-14, FUTURE DUCTS - STAGE 1
Install Electrical Ducts
Install Water Ducts
Install Irrigation Ducts
Install Telephone Ducst
03-Nov-14, TELEPHONE
Installation of New (GTO) Omantal Line
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing (GTO) Omantal Line08-Nov-14, ELECTRICAL (11 KV)
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 5 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 6: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/6.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A1360 Installation of New 11 Kv Overhead Lines 40 11-Aug-14 19-Sep-14 3000 0 A1450, A6530, A9930 A1365, A1376
A1365 Obtain Shutdown & Connect to Existing 15 20-Sep-14 04-Oct-14 0 0 A1360 A1367
A1367 Remove & Dispose Existing 11 Kv Overhead Lines 25 05-Oct-14 29-Oct-14 400 0 A1365 A1376, A1315
A1376 Remove & Dispose Existing 11 Kv Under Ground Lines 25 15-Oct-14 08-Nov-14 3000 0 A1367, A1360 A5030
ELECTRICAL (33 KV)ELECTRICAL (33 KV) 35 15-Sep-14 19-Oct-14 400
A1335 Obtain Shutdown & Connect to Existing 20 15-Sep-14 04-Oct-14 0 0 A1450 A1315
A1315 Remove & Dispose Existing 33 Kv Ovehead Lines 15 05-Oct-14 19-Oct-14 400 0 A1367, A1335 A1300
WATERLINESWATERLINES 82 19-Aug-14 08-Nov-14 5200
A1280 Installation of Water Pipe 60 19-Aug-14 17-Oct-14 2600 0 A1450 A1290
A1290 Obtain Shutdown & Connect to Existing 15 18-Oct-14 01-Nov-14 0 0 A1280 A1300
A1300 Remove & Dispose Existing Irrigation Pipes 7 02-Nov-14 08-Nov-14 2600 0 A1290, A1315 A5030
BOX CULVERTS - STAGE 1BOX CULVERTS - STAGE 1 235 21-May-14 10-Jan-15 31860
GENERALGENERAL 235 21-May-14 10-Jan-15 31860
3 CELL BOX CULVERT AT CH 21+2603 CELL BOX CULVERT AT CH 21+260 29 16-Sep-14 14-Oct-14 1109
A11780 Structural Excavation 3 16-Sep-14 18-Sep-14 117 M3 A9930, A2720, A12520 A11790
A11790 Blinding of Concrete 1 19-Sep-14 19-Sep-14 11 M3 A11780 A11800
A11800 Casting of Base Slab 6 20-Sep-14 25-Sep-14 95 M3 A11790 A11810
A11810 Casting of Walls 12 26-Sep-14 07-Oct-14 190 M3 A11800 A11820, A11830
A11830 Casting of Apron Slab & W ing Walls 10 05-Oct-14 14-Oct-14 30 M3 A11810 A11840
A11820 Casting of Top Slab 6 08-Oct-14 13-Oct-14 95 M3 A11810 A11840
A11840 Backfilling 1 14-Oct-14 14-Oct-14 571 M3 A11820, A11830 A2240
1 CELL BOX CULVERT AT CH 21+4851 CELL BOX CULVERT AT CH 21+485 83 15-Oct-14 05-Jan-15 866
A2240 Structural Excavation 2 15-Oct-14 16-Oct-14 117 M3 A10810, A11840 A2250
A2250 Blinding of Concrete 1 17-Oct-14 17-Oct-14 11 M3 A2240 A2260
A2260 Casting of Base Slab 4 18-Oct-14 21-Oct-14 38 M3 A2250 A2270
A2270 Casting of Walls 8 22-Oct-14 29-Oct-14 76 M3 A2260 A2280
A2280 Casting of Top Slab 4 30-Oct-14 02-Nov-14 38 M3 A2270 A2290, A2300
A2300 Casting of Apron Slab & W ing Walls 4 03-Nov-14 06-Nov-14 15 M3 A2280 A2290
A2290 Backfilling 1 05-Jan-15 05-Jan-15 571 M3 A2280, A2300, A2710 A5350, A2500
8 CELLS BOX CULVERT AT CH 21+8388 CELLS BOX CULVERT AT CH 21+838 109 24-Sep-14 10-Jan-15 3539
A2870 Structural Excavation 6 24-Sep-14 29-Sep-14 351 M3 A3000, A10890 A2880
A2880 Blinding of Concrete 4 28-Sep-14 01-Oct-14 46 M3 A2870 A2890
A2890 Casting of Base Slab 18 30-Sep-14 17-Oct-14 199 M3 A2880 A2900
A2900 Casting of Walls 32 14-Oct-14 14-Nov-14 398 M3 A2890 A2910
A2910 Casting of Top Slab 18 11-Nov-14 28-Nov-14 199 M3 A2900 A2920, A2930
A2930 Casting of Apron Slab & W ing Walls 22 29-Nov-14 20-Dec-14 60 M3 A2910 A2920, A5170
A2920 Backfilling 4 07-Jan-15 10-Jan-15 2286 M3 A2910, A2930, A2570 A5350
44 CELLS BOX CULVERT AT CH 21+98544 CELLS BOX CULVERT AT CH 21+985 135 21-May-14 02-Oct-14 16278
A2940 Structural Excavation 16 21-May-14 05-Jun-14 1110 M3 A1010, A9930, A10630, A11560A2950
A2950 Blinding of Concrete 14 21-May-14 03-Jun-14 194 M3 A2940 A2960
A2960 Casting of Base Slab 80 26-May-14 13-Aug-14 2016 M3 A2950 A2970
A2970 Casting of Walls 77 13-Jun-14 28-Aug-14 4032 M3 A2960 A2980
A2980 Casting of Top Slab 79 29-Jun-14 15-Sep-14 2016 M3 A2970 A2990, A3000
A3000 Casting of Apron Slab & W ing Walls 51 04-Aug-14 23-Sep-14 624 M3 A2980 A2990, A2870
A2990 Backfilling 9 24-Sep-14 02-Oct-14 6286 M3 A2980, A3000 A5350
9 CELLS BOX CULVERT AT CH 22+6509 CELLS BOX CULVERT AT CH 22+650 68 23-May-14 29-Jul-14 4135
A2800 Structural Excavation 6 23-May-14 28-May-14 351 M3 A1010, A9930, A10650 A2810, A2660
A2810 Blinding of Concrete 4 27-May-14 30-May-14 46 M3 A2800 A2820
A2820 Casting of Base Slab 18 29-May-14 15-Jun-14 336 M3 A2810 A2830
A2830 Casting of Walls 32 12-Jun-14 13-Jul-14 672 M3 A2820 A2840, A2860
A2860 Casting of Apron Slab & W ing Walls 22 08-Jul-14 29-Jul-14 108 M3 A2830 A2850
A2840 Casting of Top Slab 18 10-Jul-14 27-Jul-14 336 M3 A2830 A2850
A2850 Backfilling 4 26-Jul-14 29-Jul-14 2286 M3 A2840, A2860 A5350, A2640, A2660
5 CELLS BOX CULVERT AT CH 23+5005 CELLS BOX CULVERT AT CH 23+500 48 30-Jul-14 15-Sep-14 2563
J J J J J J J J J
2014 2015 2016
Installation of New 11 Kv Overhead Lines
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 11 Kv Overhead Lines
Remove & Dispose Existing 11 Kv Under19-Oct-14, ELECTRICAL (33 KV)
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 33 Kv Ovehead Lines08-Nov-14, WATERLINES
Installation of Water Pipe
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing Irrigation Pipes10-Jan-15, BOX CULVERTS - STAGE 1
10-Jan-15, GENERAL
14-Oct-14, 3 CELL BOX CULVERT AT CH 21+260
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Apron Slab & W ing Walls
Casting of Top Slab
Backfilling
05-Jan-15, 1 CELL BOX CULVERT AT CH 21+485
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling10-Jan-15, 8 CELLS BOX CULVERT
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling02-Oct-14, 44 CELLS BOX CULVERT AT CH 21+985
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling29-Jul-14, 9 CELLS BOX CULVERT AT CH 22+650
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Apron Slab & W ing Walls
Casting of Top Slab
Backfilling15-Sep-14, 5 CELLS BOX CULVERT AT CH 23+500
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 6 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 7: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/7.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A2660 Structural Excavation 5 30-Jul-14 03-Aug-14 292 M3 A9930, A1010, A10710, A2800, A2850A2670
A2670 Blinding of Concrete 1 04-Aug-14 04-Aug-14 11 M3 A2660 A2680
A2680 Casting of Base Slab 8 05-Aug-14 12-Aug-14 258 M3 A2670 A2690
A2690 Casting of Walls 14 11-Aug-14 24-Aug-14 517 M3 A2680 A2700
A2700 Casting of Top Slab 8 25-Aug-14 01-Sep-14 258 M3 A2690 A2710, A2720
A2720 Casting of Apron Slab & W ing Walls 14 02-Sep-14 15-Sep-14 84 M3 A2700 A2710, A2590, A11780
A2710 Backfilling 2 14-Sep-14 15-Sep-14 1143 M3 A2700, A2720 A5350, A2290
1 CELLS BOX CULVERT AT CH 23+7601 CELLS BOX CULVERT AT CH 23+760 43 16-Sep-14 28-Oct-14 831
A2590 Structural Excavation 2 16-Sep-14 17-Sep-14 117 M3 A2720, A10690 A2600
A2600 Blinding of Concrete 1 18-Sep-14 18-Sep-14 11 M3 A2590 A2610
A2610 Casting of Base Slab 4 19-Sep-14 22-Sep-14 30 M3 A2600 A2620
A2620 Casting of Walls 8 23-Sep-14 30-Sep-14 60 M3 A2610 A2630, A2650
A2630 Casting of Top Slab 4 01-Oct-14 04-Oct-14 30 M3 A2620 A2650
A2650 Casting of Apron Slab & W ing Walls 4 05-Oct-14 08-Oct-14 12 M3 A2620, A2630 A2640, A2380
A2640 Backfilling 1 28-Oct-14 28-Oct-14 571 M3 A2650, A2850 A5350, A2430
1 CELL BOX CULVERT AT CH 23+9971 CELL BOX CULVERT AT CH 23+997 20 09-Oct-14 28-Oct-14 831
A2380 Structural Excavation 2 09-Oct-14 10-Oct-14 117 M3 A2650, A10770 A2390
A2390 Blinding of Concrete 1 11-Oct-14 11-Oct-14 11 M3 A2380 A2400
A2400 Casting of Base Slab 4 12-Oct-14 15-Oct-14 30 M3 A2390 A2410
A2410 Casting of Walls 8 16-Oct-14 23-Oct-14 60 M3 A2400 A2420, A2440
A2420 Casting of Top Slab 4 24-Oct-14 27-Oct-14 30 M3 A2410 A2430
A2440 Casting of Apron Slab & W ing Walls 4 25-Oct-14 28-Oct-14 12 M3 A2410 A2430, A2450
A2430 Backfilling 1 28-Oct-14 28-Oct-14 571 M3 A2440, A2420, A2640 A5350
1 CELL BOX CULVERT AT CH 24+2351 CELL BOX CULVERT AT CH 24+235 70 29-Oct-14 06-Jan-15 854
A2450 Structural Excavation 2 29-Oct-14 30-Oct-14 117 M3 A2440, A10850 A2460
A2460 Blinding of Concrete 1 31-Oct-14 31-Oct-14 11 M3 A2450 A2470
A2470 Casting of Base Slab 4 01-Nov-14 04-Nov-14 30 M3 A2460 A2480
A2480 Casting of Walls 8 05-Nov-14 12-Nov-14 60 M3 A2470 A2490, A2510
A2490 Casting of Top Slab 4 13-Nov-14 16-Nov-14 30 M3 A2480 A2500
A2510 Casting of Apron Slab & W ing Walls 4 14-Nov-14 17-Nov-14 35 M3 A2480 A2500, A2520
A2500 Backfilling 1 06-Jan-15 06-Jan-15 571 M3 A2490, A2510, A2290 A5350, A2570
1 CELL BOX CULVERT AT CH 24+5701 CELL BOX CULVERT AT CH 24+570 50 18-Nov-14 06-Jan-15 854
A2520 Structural Excavation 2 18-Nov-14 19-Nov-14 117 M3 A2510, A10870 A2530
A2530 Blinding of Concrete 1 20-Nov-14 20-Nov-14 11 M3 A2520 A2540
A2540 Casting of Base Slab 5 21-Nov-14 25-Nov-14 30 M3 A2530 A2550
A2550 Casting of Walls 8 26-Nov-14 03-Dec-14 60 M3 A2540 A2560, A2580
A2560 Casting of Top Slab 5 04-Dec-14 08-Dec-14 30 M3 A2550 A2570
A2580 Casting of Apron Slab & W ing Walls 4 06-Dec-14 09-Dec-14 35 M3 A2550 A2570, A5170
A2570 Backfilling 1 06-Jan-15 06-Jan-15 571 M3 A2560, A2580, A2500 A5350, A2920
PEDESTRIAN UNDERPASS 1 (SOL1 CH 22+800) - STAGE 1PEDESTRIAN UNDERPASS 1 (SOL1 CH 22+800) - STAGE 1 94 28-Jun-14 29-Sep-14 4405
GENERALGENERAL 94 28-Jun-14 29-Sep-14 4405
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 94 28-Jun-14 29-Sep-14 4405
A11850 Structural Excavation 5 28-Jun-14 02-Jul-14 584 M3 A5310, A12540 A11860
A11860 Blinding of Concrete 6 02-Jul-14 07-Jul-14 26 M3 A11850 A11870
A11870 Casting of Base Slab 18 11-Jul-14 28-Jul-14 93 M3 A11860 A11880
A11880 Casting of Walls 35 01-Aug-14 04-Sep-14 180 M3 A11870 A11890
A11890 Casting of Top Slab 30 27-Aug-14 25-Sep-14 93 M3 A11880 A11900, A1795
A11900 Backfilling 4 26-Sep-14 29-Sep-14 3429 M3 A11890 A5050
PEDESTRIAN UNDERPASS 2 (SOL1 CH 23+300) - STAGE 1PEDESTRIAN UNDERPASS 2 (SOL1 CH 23+300) - STAGE 1 129 26-Sep-14 01-Feb-15 4286
GENERALGENERAL 129 26-Sep-14 01-Feb-15 4286
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 129 26-Sep-14 01-Feb-15 4186
A1795 Structural Excavation 10 26-Sep-14 05-Oct-14 584 M3 A10910, A11890 A1800
A1800 Blinding of Concrete 12 29-Sep-14 10-Oct-14 33 M3 A1795 A1810
A1810 Casting of Base Slab 35 08-Oct-14 11-Nov-14 35 M3 A1800 A1820, A11950
J J J J J J J J J
2014 2015 2016
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling28-Oct-14, 1 CELLS BOX CULVERT AT CH 23+760
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling28-Oct-14, 1 CELL BOX CULVERT AT CH 23+997
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling06-Jan-15, 1 CELL BOX CULVERT AT CH 24+235
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling06-Jan-15, 1 CELL BOX CULVERT AT CH 24+570
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling29-Sep-14, PEDESTRIAN UNDERPASS 1
29-Sep-14, GENERAL
29-Sep-14, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling
01-Feb-15, PEDESTRIAN UNDERP
01-Feb-15, GENERAL
01-Feb-15, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 7 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 8: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/8.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A1820 Casting of Walls 70 29-Oct-14 06-Jan-15 70 M3 A1810 A1830
A1830 Casting of Top Slab 50 08-Dec-14 26-Jan-15 35 M3 A1820 A3010
A3010 Backfilling 6 27-Jan-15 01-Feb-15 3429 M3 A1830 A5350
ENTRANCE & EXIT - RHSENTRANCE & EXIT - RHS 77 08-Oct-14 23-Dec-14 100
A11950 Casting of Floor Slab 22 08-Oct-14 29-Oct-14 10 M3 A1810 A11960
A11960 Casting of Walls 35 30-Oct-14 03-Dec-14 30 M3 A11950 A11980, A11970
A11970 Casting of Landing Slabs & Stair Case 35 19-Nov-14 23-Dec-14 50 M3 A11960 A11980
A11980 Casing of Beams & Roof Slab 20 04-Dec-14 23-Dec-14 10 M3 A11960, A11970 A5370
FLYOVER AT FALAJ AL QABIL (NORTH BOUND)FLYOVER AT FALAJ AL QABIL (NORTH BOUND) 347 12-Mar-14 A 27-Feb-15 72649
SUBSTRUCTURESSUBSTRUCTURES 185 12-Mar-14 A 18-Sep-14 68830
PIER P3PIER P3 58 07-Apr-14 A 03-Jun-14 1756
A1540 Boring & Casting of Piles 14 07-Apr-14 A 15-Apr-14 225 LM A6500, A1010, A6120, A11010, A6170A1550, A5020, A3260
A1550 Blinding for Pier Pile Cap 3 16-Apr-14 18-Apr-14 10 M3 A1540 A1560, A3260
A1560 Casting of Pier Pile Cap 15 19-Apr-14 03-May-14 170 M3 A1550 A1570
A1570 Bituminous Paint 3 04-May-14 06-May-14 1221 M2 A1560, A11530 A1580
A1580 Casting of Pier & Pier Cap 28 07-May-14 03-Jun-14 130 M3 A1570 A1640, A3500
PIER P5PIER P5 60 19-Apr-14 17-Jun-14 1756
A3260 Boring & Casting of Piles 11 19-Apr-14 29-Apr-14 225 LM A11050, A1540, A1550 A3270, A1590
A3270 Blinding for Pier Pile Cap 3 30-Apr-14 02-May-14 10 M3 A3260 A3280
A3280 Casting of Pier Pile Cap 15 03-May-14 17-May-14 170 M3 A3270 A3290
A3290 Bituminous Paint 3 18-May-14 20-May-14 1221 M2 A3280 A3300
A3300 Casting of Pier & Pier Cap 28 21-May-14 17-Jun-14 130 M3 A3290 A3500
ABUTMENT AB1ABUTMENT AB1 61 02-May-14 01-Jul-14 29674
A1590 Boring & Casting of Piles 5 02-May-14 06-May-14 115 LM A11070, A1010, A3260 A1600, A3310, A3360
A1600 Blinding for Abutment Pile Cap 7 07-May-14 13-May-14 5 M3 A1590 A1610, A3030
A3030 Fixing of MSE Wall 46 07-May-14 21-Jun-14 0 M2 A1600 A3110, A3410
A1610 Casting of Abutment Pile Cap 42 14-May-14 24-Jun-14 420 M3 A1600 A1620, A1640
A3110 Backfilling 46 17-May-14 01-Jul-14 26286 M3 A3030 A5350, A1620
A1620 Bituminous Paint 7 25-Jun-14 01-Jul-14 2848 M2 A1610, A3110 A5170, A1650
ABUTMENT AB2ABUTMENT AB2 64 07-May-14 09-Jul-14 29749
A3360 Boring & Casting of Piles 5 07-May-14 11-May-14 115 LM A11090, A1590 A3370, A3160
A3370 Blinding for Abutment Pile Cap 7 12-May-14 18-May-14 80 M3 A3360 A3380, A3410
A3410 Fixing of MSE Wall 46 12-May-14 26-Jun-14 0 M2 A3370, A3030 A3420
A3380 Casting of Abutment Pile Cap 42 19-May-14 29-Jun-14 420 M3 A3370 A3390, A3500
A3420 Backfilling 46 22-May-14 06-Jul-14 26286 M3 A3410 A5350, A3390
A3390 Bituminous Paint 7 03-Jul-14 09-Jul-14 2848 M2 A3380, A3420 A5170, A3500
PIER P2PIER P2 60 12-May-14 10-Jul-14 1756
A3160 Boring & Casting of Piles 11 12-May-14 22-May-14 225 LM A6500, A6120, A1010, A10990, A11480, A3360A3170, A3210
A3170 Blinding for Pier Pile Cap 3 23-May-14 25-May-14 10 M3 A3160 A3180
A3180 Casting of Pier Pile Cap 15 26-May-14 09-Jun-14 170 M3 A3170 A3190
A3190 Bituminous Paint 3 10-Jun-14 12-Jun-14 1221 M2 A3180 A3200
A3200 Casting of Pier & Pier Cap 28 13-Jun-14 10-Jul-14 130 M3 A3190 A1640
PIER P1PIER P1 60 23-May-14 21-Jul-14 1756
A3210 Boring & Casting of Piles 11 23-May-14 02-Jun-14 225 LM A10970, A3160 A3220, A4000
A3220 Blinding for Pier Pile Cap 3 03-Jun-14 05-Jun-14 10 M3 A3210 A3230
A3230 Casting of Pier Pile Cap 15 06-Jun-14 20-Jun-14 170 M3 A3220 A3240
A3240 Bituminous Paint 3 21-Jun-14 23-Jun-14 1221 M2 A3230 A3250
A3250 Casting of Pier & Pier Cap 28 24-Jun-14 21-Jul-14 130 M3 A3240 A1640
Falaj RelocationFalaj Relocation 125 12-Mar-14 A 20-Jul-14 627
A11630 Section 1 - Inside Existing Roundabout 45 LM 32 12-Mar-14 A 20-Apr-14 120 M3 A999 A11670, A11720
A11670 Section 5 - RHS (Between Existing Service Roads) - 24 LM 24 10-Apr-14 A 07-May-14 64 M3 A11630 A11640, A11660, A11690, A11720
A11660 Section 4 - LHS(Between Diversion - Existing Service Road) - 55 LM 38 20-Apr-14 28-May-14 146 M3 A11670 A11680, A11720
A11640 Section 2 - LHS (Between Diversion - Existing Service Road) -40 LM 28 08-May-14 04-Jun-14 106 M3 A11670 A11650, A11690, A11720
A11650 Section 3 - RHS (Between Diversion - Roundabout) - 32 LM 25 18-May-14 11-Jun-14 85 M3 A11640 A11720
J J J J J J J J J
2014 2015 2016
Casting of Walls
Casting of Top Slab
Backfilling23-Dec-14, ENTRANCE & EXIT - RHS
Casting of Floor Slab
Casting of Walls
Casting of Landing Slabs & Stair Case
Casing of Beams & Roof Slab
27-Feb-15, FLYOVER AT FALAJ A
18-Sep-14, SUBSTRUCTURES
03-Jun-14, PIER P3
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap17-Jun-14, PIER P5
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap01-Jul-14, ABUTMENT AB1
Boring & Casting of Piles
Blinding for Abutment Pile Cap
Fixing of MSE Wall
Casting of Abutment Pile Cap
Backfilling
Bituminous Paint09-Jul-14, ABUTMENT AB2
Boring & Casting of Piles
Blinding for Abutment Pile Cap
Fixing of MSE Wall
Casting of Abutment Pile Cap
Backfilling
Bituminous Paint10-Jul-14, PIER P2
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap21-Jul-14, PIER P1
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap20-Jul-14, Falaj Relocation
Section 1 - Inside Existing Roundabout 45 LM
Section 5 - RHS (Between Existing Service Roads) - 24 LM
Section 4 - LHS(Between Diversion - Existing Ser
Section 2 - LHS (Between Diversion - Existing Se
Section 3 - RHS (Between Diversion - Roundabout) - 32 LM
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 8 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 9: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/9.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A11690 Section 7 - RHS(Under Service Road) - 10 LM 20 18-May-14 06-Jun-14 26 M3 A11640, A11670 A11700, A11720
A11680 Section 6 - LHS (Under Service Road) - 15 LM 22 07-Jun-14 28-Jun-14 40 M3 A11660, A11700 A11720
A11700 Section 8 - (Under Service Road) - 15 LM 22 07-Jun-14 28-Jun-14 40 M3 A11690 A11680, A11720
A11720 Shifting Water in New Falaj 15 29-Jun-14 13-Jul-14 A11700, A11690, A11680, A11670, A11660, A11650, A11640, A11630A11730, A10580
A11730 Demolition & Removal of Existing Falaj 7 14-Jul-14 20-Jul-14 A11720, A10580 A3310
PIER P4PIER P4 60 21-Jul-14 18-Sep-14 1756
A3310 Boring & Casting of Piles 11 21-Jul-14 31-Jul-14 225 LM A1590, A11030, A11730 A3320, A4050
A3320 Blinding for Pier Pile Cap 3 01-Aug-14 03-Aug-14 10 M3 A3310 A3330
A3330 Casting of Pier Pile Cap 15 04-Aug-14 18-Aug-14 170 M3 A3320 A3340
A3340 Bituminous Paint 3 19-Aug-14 21-Aug-14 1221 M2 A3330 A3350
A3350 Casting of Pier & Pier Cap 28 22-Aug-14 18-Sep-14 130 M3 A3340 A3500
SUPERSTRUCTURESUPERSTRUCTURE 173 22-Jul-14 10-Jan-15 3660
SPAN BETWEEN AB1 & P3SPAN BETWEEN AB1 & P3 114 22-Jul-14 12-Nov-14 1830
A1640 Erection of Scaffold & Shutter 55 22-Jul-14 14-Sep-14 0 0 A3250, A1580, A1610, A3200, A6470, A11250A1650
A1650 Fixing of Pot Bearings 7 15-Sep-14 21-Sep-14 12 NO. A1640, A1620 A1660
A1660 Casting of Box Girder 21 22-Sep-14 12-Oct-14 1818 M3 A1650 A1670
A1670 Prestressing Operation 10 13-Oct-14 22-Oct-14 0 0 A1660, A6620 A6760, A6790, A4550
A6760 Deshuttering of Scaffold 21 23-Oct-14 12-Nov-14 0 0 A1670 A3850
SPAN BETWEEN AB2 & P3SPAN BETWEEN AB2 & P3 114 19-Sep-14 10-Jan-15 1830
A3500 Erection of Scaffold & Shutter 55 19-Sep-14 12-Nov-14 0 0 A1580, A3300, A3380, A3350, A6470, A11270, A3390A3510
A3510 Fixing of Pot Bearings 7 13-Nov-14 19-Nov-14 12 NO. A3500 A3520
A3520 Casting of Box Girder 21 20-Nov-14 10-Dec-14 1818 M3 A3510 A3530
A3530 Prestressing Operation 10 11-Dec-14 20-Dec-14 0 0 A3520 A3570, A4550
A3570 Deshuttering of Scaffold 21 21-Dec-14 10-Jan-15 0 0 A3530, A10610 A4310
FINISHING WORKSFINISHING WORKS 61 29-Dec-14 27-Feb-15 159
GENERALGENERAL 61 29-Dec-14 27-Feb-15 159
A4550 Concrete Bridge Parapet (N.J Barrier) 22 29-Dec-14 19-Jan-15 100 M A6290, A3530, A1670, A5080, A11620A4560
A4560 Laying of Bituminous Wearing Course 6 14-Jan-15 19-Jan-15 0 0 A4550 A4570, A5450, A5430
A4570 Fixing of Expansion Joints 30 29-Jan-15 27-Feb-15 59 M A4560 A3940
FLYOVER AT FALAJ AL QABIL (SOUTH BOUND)FLYOVER AT FALAJ AL QABIL (SOUTH BOUND) 331 03-Jun-14 29-Apr-15 72849
SUBSTRUCTURESSUBSTRUCTURES 119 03-Jun-14 29-Sep-14 68278
PIER P2PIER P2 60 03-Jun-14 01-Aug-14 1756
A4000 Boring & Casting of Piles 11 03-Jun-14 13-Jun-14 225 LM A9930, A11130, A3210 A4010, A3800
A4010 Blinding for Pier Pile Cap 3 14-Jun-14 16-Jun-14 10 M3 A4000 A4020
A4020 Casting of Pier Pile Cap 15 17-Jun-14 01-Jul-14 170 M3 A4010 A4030
A4030 Bituminous Paint 3 02-Jul-14 04-Jul-14 1221 M2 A4020 A4040, A4310
A4040 Casting of Pier & Pier Cap 28 05-Jul-14 01-Aug-14 130 M3 A4030 A4310, A3790
ABUTMENT AB1ABUTMENT AB1 64 14-Jun-14 16-Aug-14 29749
A3800 Boring & Casting of Piles 5 14-Jun-14 18-Jun-14 115 LM A4000, A11210 A3810, A3950
A3810 Blinding for Abutment Pile Cap 7 19-Jun-14 25-Jun-14 80 M3 A3800 A3820, A4150
A4150 Fixing of MSE Wall 46 19-Jun-14 03-Aug-14 0 M2 A3810 A4160
A3820 Casting of Abutment Pile Cap 45 26-Jun-14 09-Aug-14 420 M3 A3810 A3830, A4310
A4160 Backfilling 46 29-Jun-14 13-Aug-14 26286 M3 A4150 A5350
A3830 Bituminous Paint 7 10-Aug-14 16-Aug-14 2848 M2 A3820 A5170, A4310, A4310
PIER P5PIER P5 60 19-Jun-14 17-Aug-14 1756
A3950 Boring & Casting of Piles 11 19-Jun-14 29-Jun-14 225 LM A3800, A11190 A3960, A4100
A3960 Blinding for Pier Pile Cap 3 30-Jun-14 02-Jul-14 10 M3 A3950 A3970
A3970 Casting of Pier Pile Cap 15 03-Jul-14 17-Jul-14 170 M3 A3960 A3980
A3980 Bituminous Paint 3 18-Jul-14 20-Jul-14 1221 M2 A3970 A3990, A4310
A3990 Casting of Pier & Pier Cap 28 21-Jul-14 17-Aug-14 130 M3 A3980 A3850
PIER P3PIER P3 60 30-Jun-14 28-Aug-14 1756
A4100 Boring & Casting of Piles 11 30-Jun-14 10-Jul-14 225 LM A11150, A9930, A3950 A4110, A3750
A4110 Blinding for Pier Pile Cap 3 11-Jul-14 13-Jul-14 10 M3 A4100 A4120
A4120 Casting of Pier Pile Cap 15 14-Jul-14 28-Jul-14 170 M3 A4110 A4130
J J J J J J J J J
2014 2015 2016
Section 7 - RHS(Under Service Road) - 10 LM
Section 6 - LHS (Under Service Road) - 15 LM
Section 8 - (Under Service Road) - 15 LM
Shifting Water in New Falaj
Demolition & Removal of Existing Falaj
18-Sep-14, PIER P4
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap10-Jan-15, SUPERSTRUCTURE
12-Nov-14, SPAN BETWEEN AB1 & P3
Erection of Scaffold & Shutter
Fixing of Pot Bearings
Casting of Box Girder
Prestressing Operation
Deshuttering of Scaffold10-Jan-15, SPAN BETWEEN AB2 & P3
Erection of Scaffold & Shutter
Fixing of Pot Bearings
Casting of Box Girder
Prestressing Operation
Deshuttering of Scaffold27-Feb-15, FINISHING WORKS
27-Feb-15, GENERAL
Concrete Bridge Parapet (N.J Barrier)
Laying of Bituminous Wearing Course
Fixing of Expansion Joints29-Apr-15, FLYOVER AT FALAJ
29-Sep-14, SUBSTRUCTURES
01-Aug-14, PIER P2
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap16-Aug-14, ABUTMENT AB1
Boring & Casting of Piles
Blinding for Abutment Pile Cap
Fixing of MSE Wall
Casting of Abutment Pile Cap
Backfilling
Bituminous Paint17-Aug-14, PIER P5
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap28-Aug-14, PIER P3
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 9 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 10: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/10.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A4130 Bituminous Paint 3 29-Jul-14 31-Jul-14 1221 M2 A4120 A4140
A4140 Casting of Pier & Pier Cap 28 01-Aug-14 28-Aug-14 130 M3 A4130 A3850, A4310
PIER P1PIER P1 60 11-Jul-14 08-Sep-14 1756
A3750 Boring & Casting of Piles 11 11-Jul-14 21-Jul-14 225 LM A4100, A11110 A3760, A4170
A3760 Blinding for Pier Pile Cap 3 22-Jul-14 24-Jul-14 10 M3 A3750 A3770
A3770 Casting of Pier Pile Cap 15 25-Jul-14 08-Aug-14 170 M3 A3760 A3780
A3780 Bituminous Paint 3 09-Aug-14 11-Aug-14 1221 M2 A3770 A3790
A3790 Casting of Pier & Pier Cap 28 12-Aug-14 08-Sep-14 130 M3 A3780, A4040 A4310
ABUTMENT AB2ABUTMENT AB2 64 22-Jul-14 23-Sep-14 29749
A4170 Boring & Casting of Piles 5 22-Jul-14 26-Jul-14 115 LM A11230, A3750 A4180
A4180 Blinding for Abutment Pile Cap 7 27-Jul-14 02-Aug-14 80 M3 A4170 A4190, A4220
A4220 Fixing of MSE Wall 46 27-Jul-14 10-Sep-14 0 M2 A4180 A4230
A4190 Casting of Abutment Pile Cap 45 03-Aug-14 16-Sep-14 420 M3 A4180 A4200, A3850
A4230 Backfilling 46 06-Aug-14 20-Sep-14 26286 M3 A4220 A5350
A4200 Bituminous Paint 7 17-Sep-14 23-Sep-14 2848 M2 A4190 A5170, A3850
PIER P4PIER P4 60 01-Aug-14 29-Sep-14 1756
A4050 Boring & Casting of Piles 11 01-Aug-14 11-Aug-14 225 LM A11170, A3310 A4060
A4060 Blinding for Pier Pile Cap 3 12-Aug-14 14-Aug-14 10 M3 A4050 A4070
A4070 Casting of Pier Pile Cap 15 15-Aug-14 29-Aug-14 170 M3 A4060 A4080
A4080 Bituminous Paint 3 30-Aug-14 01-Sep-14 1221 M2 A4070 A4090
A4090 Casting of Pier & Pier Cap 28 02-Sep-14 29-Sep-14 130 M3 A4080 A3850
SUPERSTRUCTURESUPERSTRUCTURE 133 13-Nov-14 25-Mar-15 3660
SPAN BETWEEN AB2 & P3SPAN BETWEEN AB2 & P3 114 13-Nov-14 06-Mar-15 1830
A3850 Erection of Scaffold & Shutter 55 13-Nov-14 06-Jan-15 0 0 A4140, A4090, A6760, A4190, A3990, A6470, A11290, A4200A3860
A3860 Fixing of Pot Bearings 7 07-Jan-15 13-Jan-15 12 NO. A3850 A3870
A3870 Casting of Box Girder 21 14-Jan-15 03-Feb-15 1818 M3 A3860 A3880
A3880 Prestressing Operation 10 04-Feb-15 13-Feb-15 0 0 A3870 A6770, A3920
A6770 Deshuttering of Scaffold 21 14-Feb-15 06-Mar-15 0 0 A3880 A6790
SPAN BETWEEN AB1 & P3SPAN BETWEEN AB1 & P3 114 02-Dec-14 25-Mar-15 1830
A4310 Erection of Scaffold & Shutter 55 02-Dec-14 25-Jan-15 0 0 A4040, A3570, A4140, A3790, A3820, A6470, A11500, A3830, A4030, A3830, A3980A4320
A4320 Fixing of Pot Bearings 7 26-Jan-15 01-Feb-15 12 NO. A4310 A4330
A4330 Casting of Box Girder 21 02-Feb-15 22-Feb-15 1818 M3 A4320 A4340
A4340 Prestressing Operation 10 23-Feb-15 04-Mar-15 0 0 A4330 A6790, A3920
A6790 Deshuttering of Scaffold 21 05-Mar-15 25-Mar-15 0 0 A4340, A1670, A6770 A6710
FINISHING WORKSFINISHING WORKS 41 20-Mar-15 29-Apr-15 911
GENERALGENERAL 41 20-Mar-15 29-Apr-15 911
A3920 Concrete Bridge Parapet (N.J Barrier) 24 20-Mar-15 12-Apr-15 860 M A6290, A3880, A4340, A11620A3930
A3930 Laying of Bituminous Wearing Course 12 07-Apr-15 18-Apr-15 0 0 A3920 A3940, A5490, A9900
A3940 Fixing of Expansion Joints 11 19-Apr-15 29-Apr-15 51 M A3930, A4570 A6710, A9900
MSE WALL (RAMPS OF FLYOVER)MSE WALL (RAMPS OF FLYOVER) 265 28-May-14 16-Feb-15 10167
MSE RWs & RAMPS OF FLYOVERMSE RWs & RAMPS OF FLYOVER 265 28-May-14 16-Feb-15 10167
GENERALGENERAL 265 28-May-14 16-Feb-15 10167
A5020 Excavation to Reduce Level 80 28-May-14 15-Aug-14 0 0 A1540, A6320, A11330, A9930A5030
A5030 Preparation of Foundations 160 27-Jun-14 03-Dec-14 0 0 A5020, A1457, A1376, A1300, A11770A5040
A5040 Installing & Bracing of MSE Wall Panels 190 04-Jul-14 09-Jan-15 8800 M2 A5030 A5050
A5050 Place & Compact Selected Fill up 190 08-Jul-14 13-Jan-15 0 0 A5040, A11900 A5060
A5060 Connect & Tighten Soil Reinforcement 190 13-Jul-14 18-Jan-15 0 0 A5050 A5070
A5070 Place & Compact Random Backfill 190 23-Jul-14 28-Jan-15 0 0 A5060, A11590 A5080, A4580
A5080 Casting of Coping Beam 200 01-Aug-14 16-Feb-15 1367 M3 A5070 A4550, A5370
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 249 26-Aug-14 01-May-15 9331
GENERALGENERAL 249 26-Aug-14 01-May-15 9331
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 189 26-Aug-14 02-Mar-15 9331
A4580 Trench for Low Voltage Cables 160 26-Aug-14 01-Feb-15 7097 M A5340, A5070 A4590
A4590 Laying of Ducts 160 02-Sep-14 08-Feb-15 2054 M A4580 A4600
J J J J J J J J J
2014 2015 2016
Bituminous Paint
Casting of Pier & Pier Cap08-Sep-14, PIER P1
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap23-Sep-14, ABUTMENT AB2
Boring & Casting of Piles
Blinding for Abutment Pile Cap
Fixing of MSE Wall
Casting of Abutment Pile Cap
Backfilling
Bituminous Paint29-Sep-14, PIER P4
Boring & Casting of Piles
Blinding for Pier Pile Cap
Casting of Pier Pile Cap
Bituminous Paint
Casting of Pier & Pier Cap25-Mar-15, SUPERSTRUCTURE
06-Mar-15, SPAN BETWEEN AB2 & P3
Erection of Scaffold & Shutter
Fixing of Pot Bearings
Casting of Box Girder
Prestressing Operation
Deshuttering of Scaffold25-Mar-15, SPAN BETWEEN AB1 & P3
Erection of Scaffold & Shutter
Fixing of Pot Bearings
Casting of Box Girder
Prestressing Operation
Deshuttering of Scaffold29-Apr-15, FINISHING WORKS
29-Apr-15, GENERAL
Concrete Bridge Parapet (N.J Barrier)
Laying of Bituminous Wearing Course
Fixing of Expansion Joints16-Feb-15, MSE WALL (RAMPS OF FLYOVER)
16-Feb-15, MSE RWs & RAMPS OF FLYOVER
16-Feb-15, GENERAL
Excavation to Reduce Level
Preparation of Foundations
Installing & Bracing of MSE Wall Panels
Place & Compact Selected Fill up
Connect & Tighten Soil Reinforcement
Place & Compact Random Backfill
Casting of Coping Beam01-May-15, ROAD LIGHTING &
01-May-15, GENERAL
02-Mar-15, CIVIL WORKS & CABLING
Trench for Low Voltage Cables
Laying of Ducts
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 10 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 11: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/11.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A4600 Laying of Cables 160 09-Sep-14 15-Feb-15 0 0 A4590 A4610
A4620 High Masts Concrete Foundations 90 03-Dec-14 02-Mar-15 0 0 A4610 A4630, A4670
A4610 Lighting Columns Concrete Foundations 90 03-Dec-14 02-Mar-15 180 NO. A4600 A4620, A5350
A4630 Concrete Foundations for Transformer Stations & Feeder Pillars 60 02-Jan-15 02-Mar-15 0 0 A4620 A4640
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 90 13-Dec-14 12-Mar-15 0
A4670 Fixing of High Masts 90 13-Dec-14 12-Mar-15 0 0 A4620, A6350 A4680
A4680 Fixing of Lighting Poles 90 13-Dec-14 12-Mar-15 0 0 A4670 A5010, A5990
TRANSFORMERS & FEEDER PILLARSTRANSFORMERS & FEEDER PILLARS 110 12-Jan-15 01-May-15 0
A4650 Installation of Feeder Pillar 60 12-Jan-15 12-Mar-15 0 0 A4640 A4660
A4640 33 KV & 11 KV Pad Mounted & Pole Mounted Transformers Substations 60 12-Jan-15 12-Mar-15 0 0 A4630 A4650
A4660 Power Supply Connections to Feeder Pillar 60 03-Mar-15 01-May-15 0 0 A4650 A9460
SLOPE PROTECTION & STABILIZATIONSLOPE PROTECTION & STABILIZATION 100 02-Oct-14 09-Jan-15 19093
RIPRAP, GABIONRIPRAP, GABION 100 02-Oct-14 09-Jan-15 19093
GENERALGENERAL 100 02-Oct-14 09-Jan-15 19093
A5170 Laying of Filter Membrane Fabric for Protection Works 80 02-Oct-14 20-Dec-14 5133 M2 A2580, A2930, A1620, A3390, A3830, A4200A5180
A5180 Fixing of Gabion Cages 90 07-Oct-14 04-Jan-15 2487 M3 A5170 A5190
A5190 Installation of Mortared Stone Riprap 90 07-Oct-14 04-Jan-15 3473 M3 A5180 A5200
A5200 Grouted Stone Ditch Lining 60 11-Nov-14 09-Jan-15 8000 M2 A5190 A5490
DRAINAGE WORKSDRAINAGE WORKS 80 11-Aug-14 29-Oct-14 36197
RC PIPESRC PIPES 80 11-Aug-14 29-Oct-14 36197
GENERALGENERAL 80 11-Aug-14 29-Oct-14 36197
A5090 Trench Excavation Work 60 11-Aug-14 09-Oct-14 1641 M3 A5340 A5100
A5100 Laying of Drainage Pipes (RCC) 60 15-Aug-14 13-Oct-14 250 LM A5090, A6380 A5110
A5110 Construction of Manholes 60 21-Aug-14 19-Oct-14 20 No. A5100 A5120
A5120 Backfilling 60 31-Aug-14 29-Oct-14 34286 M3 A5110 A5350
ROAD FINISHING WORKSROAD FINISHING WORKS 177 04-Nov-14 29-Apr-15 189636
GENERALGENERAL 177 04-Nov-14 29-Apr-15 189636
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 144 04-Nov-14 27-Mar-15 128077
A5350 Backfilling to Embankment 120 04-Nov-14 03-Mar-15 68571 M3 A4610, A3010, A2990, A2920, A2850, A2640, A2430, A2710, A2290, A2500, A2570, A3420, A4230, A3110, A4160, A5120A5370
A5370 Preparation of Granular Subbase 110 20-Nov-14 09-Mar-15 18355 M3 A5350, A5080, A11980 A5380
A5380 Preparation of Aggregate Base Course 120 28-Nov-14 27-Mar-15 41151 M3 A5370 A5390, A5430
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 157 13-Nov-14 18-Apr-15 42833
A5390 Installation of Precast Concrete Curbs 150 13-Nov-14 11-Apr-15 15393 M A5380 A5400
A5400 Installation of Concrete Barriers 150 13-Nov-14 11-Apr-15 6600 M A5390, A6290, A11620 A5410
A5410 Installation of Interlocking Tiles 150 20-Nov-14 18-Apr-15 20840 M2 A5400 A5450
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 82 01-Feb-15 23-Apr-15 17242
A5430 Bituminous Base Course 75 01-Feb-15 16-Apr-15 12483 M3 A5380, A4560 A5450
A5450 Bituminous Wearing Course 38 17-Mar-15 23-Apr-15 4759 M3 A5430, A4560, A5410 A5460, A5490, A9900
GUARDRAILS, HIGHWAY SIGNS & ROAD MARKINGGUARDRAILS, HIGHWAY SIGNS & ROAD MARKING 46 15-Mar-15 29-Apr-15 1484
A5460 Fixing of Guardrails 45 15-Mar-15 28-Apr-15 1415 M A5450, A6440 A5470
A5470 Fixing of Highway Signs Single & Multiple Poles 45 15-Mar-15 28-Apr-15 65 NO. A5460, A6410 A5480
A5480 Fixing of Overhead & Gantry Signs 30 30-Mar-15 28-Apr-15 4 NO. A5470 A5490
A5490 Traffic Lines & Road Studs 30 31-Mar-15 29-Apr-15 0 0 A3930, A5450, A5480, A5200A6710, A6100, A9900
SOL2, SOL4, SOL7SOL2, SOL4, SOL7 149 30-Apr-15 25-Sep-15 94223
SHIFT TRAFFIC TO SOL1- SB & TEMP SERVICE ROAD SR-2SHIFT TRAFFIC TO SOL1- SB & TEMP SERVICE ROAD SR-2 7 30-Apr-15 06-May-15 0
Start (CH 25+300) & End (CH 21+100)Start (CH 25+300) & End (CH 21+100) 7 30-Apr-15 06-May-15 0
GENERALGENERAL 7 30-Apr-15 06-May-15 0
A9900 Placing of Plastic Barriers 7 30-Apr-15 06-May-15 0 0 A6710, A5450, A5490, A3930, A3940A6810
A6810 Shift Traffic from Southern & Northeren Temp. Diversions back to new Main Road 0 06-May-15 0 0 A9900 A9650
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 99 10-May-15 16-Aug-15 11159
CLEARING & EXCAVATIONCLEARING & EXCAVATION 99 10-May-15 16-Aug-15 11159
GENERALGENERAL 99 10-May-15 16-Aug-15 11159
A9650 Clearing & Grubbing 30 10-May-15 08-Jun-15 4259 M2 A6810 A9660, A12060, A12130, A11990, A8300
A9660 Removal of Structures & Obstructures 60 12-May-15 11-Jul-15 1 LS A9650 A9670
A9670 Utilities Trench Ear thworks 60 15-May-15 13-Jul-15 1641 M3 A9660 A9680, A7010
J J J J J J J J J
2014 2015 2016
Laying of Cables
High Masts Concrete Foundations
Lighting Columns Concrete Foundations
Concrete Foundations for Transfor12-Mar-15, COLUMNS, HIGH MASTS
Fixing of High Masts
Fixing of Lighting Poles01-May-15, TRANSFORMERS
Installation of Feeder Pillar
33 KV & 11 KV Pad Mounted & Po
Power Supply Connections to Feeder Pillar09-Jan-15, SLOPE PROTECTION &
09-Jan-15, RIPRAP, GABION
09-Jan-15, GENERAL
Laying of Filter Membrane Fabric for P
Fixing of Gabion Cages
Installation of Mortared Stone Riprap
Grouted Stone Ditch Lining29-Oct-14, DRAINAGE WORKS
29-Oct-14, RC PIPES
29-Oct-14, GENERAL
Trench Excavation Work
Laying of Drainage Pipes (RCC)
Construction of Manholes
Backfilling29-Apr-15, ROAD FINISHING WORKS
29-Apr-15, GENERAL
27-Mar-15, EMBANKMENT, SUB
Backfilling to Embankment
Preparation of Granular Subbase
Preparation of Aggregate Base Course18-Apr-15, MEDIAN & SIDEWALK PAVING
Installation of Precast Concrete Curbs
Installation of Concrete Barriers
Installation of Interlocking Tiles23-Apr-15, NEW BITUMINOUS LAYERS
Bituminous Base Course
Bituminous Wearing Course29-Apr-15, GUARDRAILS, HIG
Fixing of Guardrails
Fixing of Highway Signs Single &
Fixing of Overhead & Gantry Signs
Traffic Lines & Road Studs25-Sep-15, SOL2, SOL4, SOL7
06-May-15, SHIFT TRAFFIC T
06-May-15, Start (CH 25+300)
06-May-15, GENERAL
Placing of Plastic BarriersShift Traffic from Southern & No
16-Aug-15, GENERAL CIVIL WORKS
16-Aug-15, CLEARING &
16-Aug-15, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Utilities Trench Ear thworks
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 11 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 12: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/12.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A9680 Structural & Road Way Excavation 90 19-May-15 16-Aug-15 5258 M3 A9670 A9390
UTILITIESUTILITIES 52 19-May-15 09-Jul-15 14200
GENERALGENERAL 52 19-May-15 09-Jul-15 14200
TELEPHONETELEPHONE 32 19-May-15 19-Jun-15 2200
A7010 Installation of New (GTO) Omantal Line 12 19-May-15 30-May-15 1100 0 A9670 A7030, A6920, A6960
A7030 Obtain Shutdown & Connect to Existing 15 31-May-15 14-Jun-15 0 0 A7010 A7040
A7040 Remove & Dispose Existing (GTO) Omantal Line 5 15-Jun-15 19-Jun-15 1100 0 A7030 A6960
ELECTRICAL (11 KV)ELECTRICAL (11 KV) 52 19-May-15 09-Jul-15 6400
A6920 Installation of New 11 Kv Overhead Lines 30 19-May-15 17-Jun-15 3000 0 A7010 A6890, A6840, A6960, A6900
A6890 Obtain Shutdown & Connect to Existing 15 18-Jun-15 02-Jul-15 0 0 A6920 A6970
A6970 Remove & Dispose Existing 11 Kv Overhead Lines 7 03-Jul-15 09-Jul-15 400 0 A6890 A6960
A6960 Remove & Dispose Existing 11 Kv Under Ground Lines 5 05-Jul-15 09-Jul-15 3000 0 A6970, A6920, A7040, A7010A6100
ELECTRICAL (33 KV)ELECTRICAL (33 KV) 10 11-Jun-15 20-Jun-15 400
A7290 Obtain Shutdown & Connect to Existing 7 11-Jun-15 17-Jun-15 0 0 A0000 A6900
A6900 Remove & Dispose Existing 33 Kv Ovehead Lines 3 18-Jun-15 20-Jun-15 400 0 A6920, A7290 A6100
WATERLINESWATERLINES 37 24-May-15 29-Jun-15 5200
A6840 Installation of New Irrigation Pipes 25 24-May-15 17-Jun-15 2600 0 A6920 A6850
A6850 Obtain Shutdown & Connect to Existing 15 08-Jun-15 22-Jun-15 0 0 A6840 A6860
A6860 Remove & Dispose Existing Irrigation Pipes 7 23-Jun-15 29-Jun-15 2600 0 A6850
BOX CULVERTS - STAGE 2BOX CULVERTS - STAGE 2 64 10-May-15 12-Jul-15 9864
GENERALGENERAL 64 10-May-15 12-Jul-15 9864
8 CELLS BOX CULVERT AT CH 21+8388 CELLS BOX CULVERT AT CH 21+838 23 10-May-15 01-Jun-15 1601
A11990 Structural Excavation 3 10-May-15 12-May-15 175 M3 A9650 A12000, A7950
A12000 Blinding of Concrete 2 13-May-15 14-May-15 23 M3 A11990 A12010
A12010 Casting of Base Slab 4 15-May-15 18-May-15 50 M3 A12000 A12020
A12020 Casting of Walls 7 19-May-15 25-May-15 100 M3 A12010 A12030
A12030 Casting of Top Slab 5 26-May-15 30-May-15 50 M3 A12020 A12040
A12040 Casting of Apron Slab & W ing Walls 4 27-May-15 30-May-15 60 M3 A12030 A12050, A8090
A12050 Backfilling 2 31-May-15 01-Jun-15 1143 M3 A12040 A9690
44 CELL BOX CULVERT AT CH 21+98544 CELL BOX CULVERT AT CH 21+985 63 11-May-15 12-Jul-15 3513
A12060 Structural Excavation 10 11-May-15 20-May-15 175 M3 A9650 A12070
A12070 Blinding of Concrete 8 21-May-15 28-May-15 23 M3 A12060 A12080
A12080 Casting of Base Slab 15 29-May-15 12-Jun-15 504 M3 A12070 A12090
A12090 Casting of Walls 15 10-Jun-15 24-Jun-15 1008 M3 A12080 A12100
A12100 Casting of Top Slab 13 20-Jun-15 02-Jul-15 504 M3 A12090 A12110
A12110 Casting of Apron Slab & W ing Walls 10 03-Jul-15 12-Jul-15 156 M3 A12100 A12120
A12120 Backfilling 6 07-Jul-15 12-Jul-15 1143 M3 A12110 A9690
9 CELL BOX CULVERT AT CH 22+6509 CELL BOX CULVERT AT CH 22+650 25 31-May-15 24-Jun-15 1704
A8090 Structural Excavation 3 31-May-15 02-Jun-15 175 M3 A12040 A8100
A8100 Blinding of Concrete 2 03-Jun-15 04-Jun-15 23 M3 A8090 A8110
A8110 Casting of Base Slab 4 05-Jun-15 08-Jun-15 84 M3 A8100 A8120
A8120 Casting of Walls 7 09-Jun-15 15-Jun-15 168 M3 A8110 A8130
A8130 Casting of Top Slab 5 16-Jun-15 20-Jun-15 84 M3 A8120 A8140
A8140 Casting of Apron Slab & W ing Walls 4 21-Jun-15 24-Jun-15 27 M3 A8130 A9610, A8150
A8150 Backfilling 2 23-Jun-15 24-Jun-15 1143 M3 A8140 A9690
5 CELL BOX CULVERT AT CH 23+5005 CELL BOX CULVERT AT CH 23+500 25 10-May-15 03-Jun-15 1552
A7950 Structural Excavation 2 10-May-15 11-May-15 117 M3 A11990 A7960
A7960 Blinding of Concrete 1 12-May-15 12-May-15 11 M3 A7950 A7970
A7970 Casting of Base Slab 4 13-May-15 16-May-15 65 M3 A7960 A7980
A7980 Casting of Walls 7 17-May-15 23-May-15 130 M3 A7970 A7990
A7990 Casting of Top Slab 4 24-May-15 27-May-15 65 M3 A7980 A8000
A8000 Casting of Apron Slab & W ing Walls 7 28-May-15 03-Jun-15 21 M3 A7990 A8010, A7600
A8010 Backfilling 2 02-Jun-15 03-Jun-15 1143 M3 A8000 A9690
1 CELL BOX CULVERT AT CH 23+7601 CELL BOX CULVERT AT CH 23+760 13 04-Jun-15 16-Jun-15 747
J J J J J J J J J
2014 2015 2016
Structural & Road Way Excavation09-Jul-15, UTILITIES
09-Jul-15, GENERAL
19-Jun-15, TELEPHONE
Installation of New (GTO) Omantal Line
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing (09-Jul-15, ELECTRICAL (11 KV)
Installation of New 11 Kv Overhead Lines
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing
Remove & Dispose Existing20-Jun-15, ELECTRICAL (33 KV)
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 329-Jun-15, WATERLINES
Installation of New Irrigation Pipes
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 12-Jul-15, BOX CULVERTS - STAGE 2
12-Jul-15, GENERAL
01-Jun-15, 8 CELLS BOX CU
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling
12-Jul-15, 44 CELL BOX CU
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling
24-Jun-15, 9 CELL BOX CU
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling03-Jun-15, 5 CELL BOX CUL
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling16-Jun-15, 1 CELL BOX CUL
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 12 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 13: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/13.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A7600 Structural Excavation 2 04-Jun-15 05-Jun-15 117 M3 A8000 A7610
A7610 Blinding of Concrete 1 06-Jun-15 06-Jun-15 11 M3 A7600 A7620
A7620 Casting of Base Slab 2 07-Jun-15 08-Jun-15 9 M3 A7610 A7630
A7630 Casting of Walls 3 09-Jun-15 11-Jun-15 18 M3 A7620 A7640, A7670
A7640 Casting of Top Slab 1 12-Jun-15 12-Jun-15 9 M3 A7630 A7690, A7650
A7650 Casting of Apron Slab & W ing Walls 4 13-Jun-15 16-Jun-15 12 M3 A7640 A7660
A7660 Backfilling 1 16-Jun-15 16-Jun-15 571 M3 A7650 A9690
1 CELL BOX CULVERT AT CH 23+9971 CELL BOX CULVERT AT CH 23+997 14 10-Jun-15 23-Jun-15 747
A7670 Structural Excavation 2 10-Jun-15 11-Jun-15 117 M3 A7630 A7680
A7680 Blinding of Concrete 1 12-Jun-15 12-Jun-15 11 M3 A7670 A7690
A7690 Casting of Base Slab 2 13-Jun-15 14-Jun-15 9 M3 A7680, A7640 A7700
A7700 Casting of Walls 3 15-Jun-15 17-Jun-15 18 M3 A7690 A7710
A7710 Casting of Top Slab 1 18-Jun-15 18-Jun-15 9 M3 A7700 A7720
A7720 Casting of Apron Slab & W ing Walls 4 19-Jun-15 22-Jun-15 12 M3 A7710 A7730
A7730 Backfilling 1 23-Jun-15 23-Jun-15 571 M3 A7720 A9690
PEDESTRIAN UNDERPASS 1 (SOL4 CH 00+435) - STAGE 2PEDESTRIAN UNDERPASS 1 (SOL4 CH 00+435) - STAGE 2 138 11-May-15 25-Sep-15 2583
GENERALGENERAL 138 11-May-15 25-Sep-15 2583
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 64 11-May-15 13-Jul-15 2483
A12130 Structural Excavation 10 11-May-15 20-May-15 584 M3 A9650 A12140
A12140 Blinding of Concrete 12 14-May-15 25-May-15 137 M3 A12130 A12150
A12150 Casting of Base Slab 21 20-May-15 09-Jun-15 12 M3 A12140 A12160
A12160 Casting of Walls 21 30-May-15 19-Jun-15 24 M3 A12150 A12170
A12170 Casting of Top Slab 21 20-Jun-15 10-Jul-15 12 M3 A12160 A12180, A12190
A12180 Backfilling 3 11-Jul-15 13-Jul-15 1714 M3 A12170 A9690
ENTRANCE & EXIT - RHSENTRANCE & EXIT - RHS 77 11-Jul-15 25-Sep-15 100
A12190 Casting of Floor Slab 22 11-Jul-15 01-Aug-15 10 M3 A12170 A12200
A12200 Casting of Walls 35 02-Aug-15 05-Sep-15 30 M3 A12190 A12220, A12210
A12210 Casting of Landing Slabs & Stair Case 35 22-Aug-15 25-Sep-15 50 M3 A12200 A12220
A12220 Casing of Beams & Roof Slab 20 06-Sep-15 25-Sep-15 10 0 A12200, A12210 A5920
PEDESTRIAN UNDERPASS 2 (SOL4 CH 00+935) - STAGE 2PEDESTRIAN UNDERPASS 2 (SOL4 CH 00+935) - STAGE 2 127 10-May-15 13-Sep-15 2769
GENERALGENERAL 127 10-May-15 13-Sep-15 2769
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 65 10-May-15 13-Jul-15 2669
A8300 Structural Excavation 8 10-May-15 17-May-15 584 M3 A9650 A7220, A1510
A7220 Blinding of Concrete 7 16-May-15 22-May-15 137 M3 A8300 A7230
A7230 Casting of Base Slab 15 27-May-15 10-Jun-15 59 M3 A7220 A7240
A7240 Casting of Walls 15 11-Jun-15 25-Jun-15 116 M3 A7230 A7250
A7250 Casting of Top Slab 15 26-Jun-15 10-Jul-15 59 M3 A7240 A8310, A12230
A8310 Backfilling 3 11-Jul-15 13-Jul-15 1714 M3 A7250 A9690
ENTRANCE & EXIT - LHSENTRANCE & EXIT - LHS 65 11-Jul-15 13-Sep-15 100
A12230 Casting of Floor Slab 22 11-Jul-15 01-Aug-15 10 M3 A7250 A12240
A12240 Casting of Walls 35 21-Jul-15 24-Aug-15 30 M3 A12230 A12260, A12250
A12250 Casting of Landing Slabs & Stair Case 35 10-Aug-15 13-Sep-15 50 M3 A12240 A12260
A12260 Casing of Beams & Roof Slab 20 25-Aug-15 13-Sep-15 10 M3 A12240, A12250 A5860
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 56 03-Jun-15 28-Jul-15 1168
GENERALGENERAL 56 03-Jun-15 28-Jul-15 1168
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 41 03-Jun-15 13-Jul-15 1168
A9390 Trench for Low Voltage Cables 20 03-Jun-15 22-Jun-15 887 M A9680 A9400
A9400 Laying of Ducts 20 10-Jun-15 29-Jun-15 257 M A9390 A9410
A9420 Concrete Foundations for Transformer Stations & Feeder Pillars 30 14-Jun-15 13-Jul-15 0 0 A9430 A9470
A9410 Laying of Cables 20 17-Jun-15 06-Jul-15 0 0 A9400 A9440
A9430 High Masts Concrete Foundations 25 19-Jun-15 13-Jul-15 0 0 A9440 A9420, A9480
A9440 Lighting Columns Concrete Foundations 12 02-Jul-15 13-Jul-15 24 NO. A9410 A9430, A9690
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 30 29-Jun-15 28-Jul-15 0
A9480 Fixing of High Masts 30 29-Jun-15 28-Jul-15 0 0 A9430 A9490
J J J J J J J J J
2014 2015 2016
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling23-Jun-15, 1 CELL BOX CU
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling25-Sep-15, PEDESTRIA
25-Sep-15, GENERAL
13-Jul-15, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling
25-Sep-15, ENTRANCE
Casting of Floor Slab
Casting of Walls
Casting of Landing Slab
Casing of Beams & Roof Slab
13-Sep-15, PEDESTRIA
13-Sep-15, GENERAL
13-Jul-15, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling13-Sep-15, ENTRANCE
Casting of Floor Slab
Casting of Walls
Casting of Landing Slabs
Casing of Beams & Roof Slab
28-Jul-15, ROAD LIGHTIN
28-Jul-15, GENERAL
13-Jul-15, CIVIL WORKS & CABLING
Trench for Low Voltage Cables
Laying of Ducts
Concrete Foundations for T
Laying of Cables
High Masts Concrete Foundations
Lighting Columns Concrete Foundations28-Jul-15, COLUMNS, HIGH MASTS
Fixing of High Masts
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 13 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 14: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/14.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A9490 Fixing of Lighting Poles 30 29-Jun-15 28-Jul-15 0 0 A9480 A9730
TRANSFORMERS & FEEDER PILLARSTRANSFORMERS & FEEDER PILLARS 30 24-Jun-15 23-Jul-15 0
A9450 Installation of Feeder Pillar 30 24-Jun-15 23-Jul-15 0 0 A9470 A9460
A9460 Power Supply Connections to Feeder Pillar 30 24-Jun-15 23-Jul-15 0 0 A9450, A4660 A6100
A9470 33 KV & 11 KV Pad Mounted & Pole Mounted Transformers Substations 30 24-Jun-15 23-Jul-15 0 0 A9420 A9450
SLOPE PROTECTION & STABILIZATIONSLOPE PROTECTION & STABILIZATION 55 16-May-15 09-Jul-15 9547
RIPRAP, GABIONRIPRAP, GABION 55 16-May-15 09-Jul-15 9547
GENERALGENERAL 55 16-May-15 09-Jul-15 9547
A9610 Laying of Filter Membrane Fabric for Protection Works 40 16-May-15 24-Jun-15 2567 M2 A8140 A9620
A9620 Fixing of Gabion Cages 45 21-May-15 04-Jul-15 1243 M3 A9610 A9630
A9630 Installation of Mortared Stone Riprap 45 21-May-15 04-Jul-15 1737 M3 A9620 A9640
A9640 Grouted Stone Ditch Lining 30 10-Jun-15 09-Jul-15 4000 M2 A9630 A6740
ROAD FINISHING WORKSROAD FINISHING WORKS 83 12-Jun-15 02-Sep-15 42933
GENERALGENERAL 83 12-Jun-15 02-Sep-15 42933
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 44 12-Jun-15 25-Jul-15 27648
A9690 Backfilling to Embankment 32 12-Jun-15 13-Jul-15 18286 M3 A9440, A8310, A8150, A7660, A7730, A12120, A12050, A8010, A12180A9710
A9710 Preparation of Granular Subbase 15 04-Jul-15 18-Jul-15 2503 M3 A9690 A9720
A9720 Preparation of Aggregate Base Course 20 06-Jul-15 25-Jul-15 6859 M3 A9710 A9730, A9770
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 52 13-Jul-15 02-Sep-15 11383
A9730 Installation of Precast Concrete Curbs 50 13-Jul-15 31-Aug-15 5131 M A9720, A9490 A9750
A9750 Installation of Interlocking Tiles 45 20-Jul-15 02-Sep-15 6252 M2 A9730 A6100
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 17 17-Jul-15 02-Aug-15 3833
A9770 Bituminous Base Course 14 17-Jul-15 30-Jul-15 2330 M3 A9720 A9790
A9790 Bituminous Wearing Course 12 22-Jul-15 02-Aug-15 1503 M3 A9770 A9800, A9830
GUARDRAILS, HIGHWAY SIGNS & ROAD MARKINGGUARDRAILS, HIGHWAY SIGNS & ROAD MARKING 45 24-Jun-15 07-Aug-15 69
A9800 Fixing of Guardrails 45 24-Jun-15 07-Aug-15 0 M A9790 A9810
A9810 Fixing of Highway Signs Single & Multiple Poles 45 24-Jun-15 07-Aug-15 65 NO. A9800 A9820
A9830 Traffic Lines & Road Studs 30 06-Jul-15 04-Aug-15 0 0 A9790 A6100, A1500
A9820 Fixing of Overhead & Gantry Signs 30 09-Jul-15 07-Aug-15 4 NO. A9810 A6100
SERVICE ROADSSERVICE ROADS 77 01-Aug-15 16-Oct-15 34355
SR1, SR2 & SR3SR1, SR2 & SR3 77 01-Aug-15 16-Oct-15 34355
SHIFT TRAFFIC FROM SERVICE ROADS TO NEW SLIP ROADS (SOL 4/5/6/7)SHIFT TRAFFIC FROM SERVICE ROADS TO NEW SLIP ROADS (SOL 4/5/6/7) 4 01-Aug-15 04-Aug-15 0
SR2 - (CH0+0 TO CH1+300) & SR-1(CH0+0 TO CH0+797)SR2 - (CH0+0 TO CH1+300) & SR-1(CH0+0 TO CH0+797) 4 01-Aug-15 04-Aug-15 0
GENERALGENERAL 4 01-Aug-15 04-Aug-15 0
A1500 Placing of Plastic Barriers & Temporary Signs 4 01-Aug-15 04-Aug-15 0 0 A9830 A1510
A1510 Shift Traffic from Existing Southern & Northeren Service Roads to New Main Road 0 04-Aug-15 0 0 A1500, A8300 A6000
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 17 05-Aug-15 21-Aug-15 1421
CLEARING & EXCAVATIONCLEARING & EXCAVATION 17 05-Aug-15 21-Aug-15 1421
GENERALGENERAL 17 05-Aug-15 21-Aug-15 1421
A6000 Clearing & Grubbing 10 05-Aug-15 14-Aug-15 1420 M2 A1510 A6010, A12270
A6010 Removal of Structures & Obstructures 15 07-Aug-15 21-Aug-15 1 LS A6000 A6020
A6020 Road Way Excavation 10 09-Aug-15 18-Aug-15 0 0 A6010 A5950
PEDESTRIAN UNDERPASS 1 (SR2 CH 00+725) - STAGE 3PEDESTRIAN UNDERPASS 1 (SR2 CH 00+725) - STAGE 3 70 05-Aug-15 13-Oct-15 2211
GENERALGENERAL 70 05-Aug-15 13-Oct-15 2211
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 44 05-Aug-15 17-Sep-15 2111
A12270 Structural Excavation 5 05-Aug-15 09-Aug-15 292 M3 A6000 A12280, A12330, A10030
A12280 Blinding of Concrete 5 07-Aug-15 11-Aug-15 57 M3 A12270 A12290
A12290 Casting of Base Slab 12 12-Aug-15 23-Aug-15 12 M3 A12280 A12300
A12300 Casting of Walls 10 24-Aug-15 02-Sep-15 24 M3 A12290 A12310
A12310 Casting of Top Slab 12 03-Sep-15 14-Sep-15 12 M3 A12300 A12320
A12320 Backfilling 3 15-Sep-15 17-Sep-15 1714 M3 A12310 A5830
ENTRANCE & EXIT - LHSENTRANCE & EXIT - LHS 65 10-Aug-15 13-Oct-15 100
A12330 Casting of Floor Slab 22 10-Aug-15 31-Aug-15 10 M3 A12270 A12340
A12340 Casting of Walls 35 20-Aug-15 23-Sep-15 30 M3 A12330 A12360, A12350
A12350 Casting of Landing Slabs & Stair Case 35 09-Sep-15 13-Oct-15 50 M3 A12340 A12360
J J J J J J J J J
2014 2015 2016
Fixing of Lighting Poles23-Jul-15, TRANSFORME
Installation of Feeder Pillar
Power Supply Connections
33 KV & 11 KV Pad Mounte09-Jul-15, SLOPE PROTEC
09-Jul-15, RIPRAP, GABION
09-Jul-15, GENERAL
Laying of Filter Membrane Fa
Fixing of Gabion Cages
Installation of Mortared Stone Riprap
Grouted Stone Ditch Lining02-Sep-15, ROAD FINIS
02-Sep-15, GENERAL
25-Jul-15, EMBANKMENT,
Backfilling to Embankment
Preparation of Granular Subbase
Preparation of Aggregate Base Course02-Sep-15, MEDIAN & S
Installation of Precast Concrete Curbs
Installation of Interlocking Tiles02-Aug-15, NEW BITUMIN
Bituminous Base Course
Bituminous Wearing Course07-Aug-15, GUARDRAILS
Fixing of Guardrails
Fixing of Highway Signs Si
Traffic Lines & Road Studs
Fixing of Overhead & Gantry Signs16-Oct-15, SERVICE ROADS
16-Oct-15, SR1, SR2 & SR3
04-Aug-15, SHIFT TRAFF
04-Aug-15, SR2 - (CH0+0
04-Aug-15, GENERAL
Placing of Plastic Barriers Shift Traffic from Existing S
21-Aug-15, GENERAL CIVIL WORKS
21-Aug-15, CLEARING &
21-Aug-15, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Road Way Excavation13-Oct-15, PEDESTRI
13-Oct-15, GENERAL
17-Sep-15, UNDERPAS
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling
13-Oct-15, ENTRANC
Casting of Floor Slab
Casting of Walls
Casting of Landing Sla
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 14 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 15: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/15.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A12360 Casing of Beams & Roof Slab 20 24-Sep-15 13-Oct-15 10 M3 A12340, A12350 A5940
PEDESTRIAN UNDERPASS 2 (SR2 CH 01+210) - STAGE 3PEDESTRIAN UNDERPASS 2 (SR2 CH 01+210) - STAGE 3 44 10-Aug-15 22-Sep-15 2159
GENERALGENERAL 44 10-Aug-15 22-Sep-15 2159
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 44 10-Aug-15 22-Sep-15 2159
A10030 Structural Excavation 5 10-Aug-15 14-Aug-15 292 M3 A12270 A10040
A10040 Blinding of Concrete 5 12-Aug-15 16-Aug-15 57 M3 A10030 A10050
A10050 Casting of Base Slab 12 17-Aug-15 28-Aug-15 24 M3 A10040 A10060
A10060 Casting of Walls 10 29-Aug-15 07-Sep-15 48 M3 A10050 A10070
A10070 Casting of Top Slab 12 08-Sep-15 19-Sep-15 24 M3 A10060 A10080
A10080 Backfilling 3 20-Sep-15 22-Sep-15 1714 M3 A10070 A5830
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 45 09-Aug-15 22-Sep-15 888
GENERALGENERAL 45 09-Aug-15 22-Sep-15 888
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 30 09-Aug-15 07-Sep-15 888
A5950 Trench for Low Voltage Cables 15 09-Aug-15 23-Aug-15 665 M A6020 A5960
A5960 Laying of Ducts 15 14-Aug-15 28-Aug-15 193 M A5950 A5970
A5970 Laying of Cables 15 19-Aug-15 02-Sep-15 0 0 A5960 A5980
A5980 Lighting Columns Concrete Foundations 19 20-Aug-15 07-Sep-15 30 NO. A5970 A5990, A5830
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 25 29-Aug-15 22-Sep-15 0
A5990 Fixing of Lighting Poles 25 29-Aug-15 22-Sep-15 0 0 A5980, A4680, A6350 A5870
ROAD FINISHING WORKSROAD FINISHING WORKS 47 31-Aug-15 16-Oct-15 27676
GENERALGENERAL 47 31-Aug-15 16-Oct-15 27676
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 34 31-Aug-15 03-Oct-15 19316
A5830 Backfilling to Embankment 23 31-Aug-15 22-Sep-15 13143 M3 A5980, A10080, A12320 A5860
A5860 Preparation of Aggregate Base Course 18 16-Sep-15 03-Oct-15 6173 M3 A5830, A12260 A5870, A5900
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 23 19-Sep-15 11-Oct-15 4831
A5870 Installation of Precast Concrete Curbs 20 19-Sep-15 08-Oct-15 2052 M A5860, A5990 A5880
A5880 Installation of Interlocking Tiles 20 22-Sep-15 11-Oct-15 2779 M2 A5870 A6100
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 18 27-Sep-15 14-Oct-15 3500
A5900 Bituminous Base Course 12 27-Sep-15 08-Oct-15 1997 M3 A5860 A5920
A5920 Bituminous Wearing Course 12 03-Oct-15 14-Oct-15 1503 M3 A5900, A12220 A5930, A5940
HIGHWAY SIGNS & ROAD MARKINGHIGHWAY SIGNS & ROAD MARKING 21 26-Sep-15 16-Oct-15 29
A5930 Fixing of Highway Signs Single & Multiple Poles 20 26-Sep-15 15-Oct-15 29 NO. A5920, A6410 A6100
A5940 Traffic Lines & Road Studs 15 02-Oct-15 16-Oct-15 0 0 A5920, A12360 A6740, A6100
SOHAR-BURAIMI ROADSOHAR-BURAIMI ROAD 470 01-Jul-14 13-Oct-15 130825
MAIN ROADMAIN ROAD 332 01-Jul-14 28-May-15 110535
SOL3 (CH 0+0 to 1+200)SOL3 (CH 0+0 to 1+200) 332 01-Jul-14 28-May-15 110535
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 84 01-Jul-14 22-Sep-14 5736
CLEARING & EXCAVATIONCLEARING & EXCAVATION 84 01-Jul-14 22-Sep-14 5736
GENERALGENERAL 84 01-Jul-14 22-Sep-14 5736
A6030 Clearing & Grubbing 8 01-Jul-14 08-Jul-14 1136 M2 A5320 A6040
A6040 Removal of Structures & Obstructures 15 08-Jul-14 22-Jul-14 1 LS A6030 A6050
A6050 Utilities Trench Excavation & Backfilling 40 15-Jul-14 23-Aug-14 1094 M3 A6040 A6060
A6060 Structural & Road Way Excavation 60 25-Jul-14 22-Sep-14 3505 M3 A6050 A4800, A5130, A1210, A5210
UTILITIESUTILITIES 69 18-Sep-14 25-Nov-14 3000
GENERALGENERAL 69 18-Sep-14 25-Nov-14 3000
TELEPHONETELEPHONE 30 18-Sep-14 17-Oct-14 800
A1210 Installation of New (GTO) Omantal Line 10 18-Sep-14 27-Sep-14 400 0 A6060 A1215, A1100, A1105
A1215 Obtain Shutdown & Connect to Existing 15 28-Sep-14 12-Oct-14 0 0 A1210 A1218
A1218 Remove & Dispose Existing (GTO) Omantal Line 5 13-Oct-14 17-Oct-14 400 0 A1215 A5600
ELECTRICAL (11 KV)ELECTRICAL (11 KV) 30 18-Sep-14 17-Oct-14 1100
A1100 Installation of New 11 Kv Overhead Lines 10 18-Sep-14 27-Sep-14 500 0 A1210, A6530 A1102, A1020
A1102 Obtain Shutdown & Connect to Existing 15 28-Sep-14 12-Oct-14 0 0 A1100 A1105, A1170, A1058, A1105
A1105 Remove & Dispose Existing 11 Kv Overhead Lines 5 13-Oct-14 17-Oct-14 100 0 A1102, A1210, A1102 A1170
A1170 Remove & Dispose Existing 11 Kv Under Ground Lines 2 16-Oct-14 17-Oct-14 500 0 A1105, A1102 A5640, A1065
ELECTRICAL (33 KV)ELECTRICAL (33 KV) 9 17-Nov-14 25-Nov-14 100
J J J J J J J J J
2014 2015 2016
Casing of Beams & Roof Slab
22-Sep-15, PEDESTRIA
22-Sep-15, GENERAL
22-Sep-15, UNDERPAS
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling22-Sep-15, ROAD LIGH
22-Sep-15, GENERAL
07-Sep-15, CIVIL WORK
Trench for Low Voltage Cables
Laying of Ducts
Laying of Cables
Lighting Columns Concre22-Sep-15, COLUMNS,
Fixing of Lighting Poles16-Oct-15, ROAD FIN
16-Oct-15, GENERAL
03-Oct-15, EMBANKM
Backfilling to Embankment
Preparation of Aggrega11-Oct-15, MEDIAN &
Installation of Precast C
Installation of Interlocking Tiles14-Oct-15, NEW BITU
Bituminous Base Course
Bituminous Wearing Course16-Oct-15, HIGHWAY
Fixing of Highway Sign
Traffic Lines & Road Studs13-Oct-15, SOHAR-BU
28-May-15, MAIN ROAD
28-May-15, SOL3 (CH 0+0 to 1+200)
22-Sep-14, GENERAL CIVIL WORKS
22-Sep-14, CLEARING & EXCAVATION
22-Sep-14, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Utilities Trench Excavation & Backfilling
Structural & Road Way Excavation25-Nov-14, UTILITIES
25-Nov-14, GENERAL
17-Oct-14, TELEPHONE
Installation of New (GTO) Omantal Line
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing (GTO) Omantal Line17-Oct-14, ELECTRICAL (11 KV)
Installation of New 11 Kv Overhead Lines
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 11 Kv Overhead Lines
Remove & Dispose Existing 11 Kv Under Ground Lines25-Nov-14, ELECTRICAL (33 KV)
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 15 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 16: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/16.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
A1065 Obtain Shutdown & Connect to Existing 7 17-Nov-14 23-Nov-14 0 0 A1170 A1058
A1058 Remove & Dispose Existing 33 Kv Ovehead Lines 2 24-Nov-14 25-Nov-14 100 0 A1102, A1065 A5630
WATERLINESWATERLINES 30 18-Sep-14 17-Oct-14 1000
A1020 Installation of New Irrigation Pipes 10 18-Sep-14 27-Sep-14 500 0 A1100, A6560 A1030
A1030 Obtain Shutdown & Connect to Existing 15 28-Sep-14 12-Oct-14 0 0 A1020 A1040
A1040 Remove & Dispose Existing Irrigation Pipes 5 13-Oct-14 17-Oct-14 500 0 A1030 A5500
PEDESTRIAN UNDERPASS 3 (SOL3 CH 00+050) - STAGE 1PEDESTRIAN UNDERPASS 3 (SOL3 CH 00+050) - STAGE 1 214 23-Sep-14 24-Apr-15 4484
GENERALGENERAL 214 23-Sep-14 24-Apr-15 4484
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 128 23-Sep-14 28-Jan-15 4384
A5210 Structural Excavation 10 23-Sep-14 02-Oct-14 584 M3 A10950, A6060 A5220
A5220 Blinding of Concrete 12 26-Sep-14 07-Oct-14 137 M3 A5210 A5230
A5230 Casting of Base Slab 35 03-Oct-14 06-Nov-14 59 M3 A5220 A5240
A5240 Casting of Walls 70 24-Oct-14 01-Jan-15 116 M3 A5230 A5250
A5250 Casting of Top Slab 50 04-Dec-14 22-Jan-15 59 M3 A5240 A5260, A4800, A5270, A12370
A5260 Backfilling 6 23-Jan-15 28-Jan-15 3429 M3 A5250 A5500
ENTRANCE & EXIT - RHSENTRANCE & EXIT - RHS 92 23-Jan-15 24-Apr-15 100
A5270 Casting of Floor Slab 22 23-Jan-15 13-Feb-15 10 M3 A5250 A5280
A5280 Casting of Walls 35 14-Feb-15 20-Mar-15 30 M3 A5270 A5290, A5300
A5300 Casting of Landing Slabs & Stair Case 35 06-Mar-15 09-Apr-15 50 M3 A5280 A5290
A5290 Casing of Beams & Roof Slab 20 05-Apr-15 24-Apr-15 10 M3 A5280, A5300 A6100
EXTENSION OF EXISTING BOX CULVERTSEXTENSION OF EXISTING BOX CULVERTS 43 23-Jan-15 06-Mar-15 1604
GENERALGENERAL 43 23-Jan-15 06-Mar-15 1604
BOX CULVERT AT CH 0+300BOX CULVERT AT CH 0+300 23 23-Jan-15 14-Feb-15 802
A12370 Structural Excavation 2 23-Jan-15 24-Jan-15 117 M3 A5250 A12380
A12380 Blinding of Concrete 1 25-Jan-15 25-Jan-15 11 M3 A12370 A12390
A12390 Casting of Base Slab 4 26-Jan-15 29-Jan-15 22 M3 A12380 A12400
A12400 Casting of Walls 8 30-Jan-15 06-Feb-15 44 M3 A12390 A12410
A12410 Casting of Top Slab 4 07-Feb-15 10-Feb-15 22 M3 A12400 A12430, A12420
A12420 Casting of Apron Slab & W ing Walls 4 11-Feb-15 14-Feb-15 15 M3 A12410 A12430, A12440
A12430 Backfilling 1 14-Feb-15 14-Feb-15 571 M3 A12420, A12410 A5500
BOX CULVERT AT CH 0+500BOX CULVERT AT CH 0+500 20 15-Feb-15 06-Mar-15 802
A12440 Structural Excavation 2 15-Feb-15 16-Feb-15 117 M3 A12420 A12450
A12450 Blinding of Concrete 1 17-Feb-15 17-Feb-15 11 M3 A12440 A12460
A12460 Casting of Base Slab 4 18-Feb-15 21-Feb-15 22 M3 A12450 A12470
A12470 Casting of Walls 8 22-Feb-15 01-Mar-15 44 M3 A12460 A12480, A12490
A12480 Casting of Top Slab 4 02-Mar-15 05-Mar-15 22 M3 A12470 A12500
A12490 Casting of Apron Slab & W ing Walls 4 03-Mar-15 06-Mar-15 15 M3 A12470 A12500
A12500 Backfilling 1 06-Mar-15 06-Mar-15 571 M3 A12490, A12480 A5500
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 84 04-Dec-14 25-Feb-15 2920
GENERALGENERAL 84 04-Dec-14 25-Feb-15 2920
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 74 04-Dec-14 15-Feb-15 2920
A4800 Trench for Low Voltage Cables 50 04-Dec-14 22-Jan-15 2218 M A5250, A6060, A6530 A4810
A4810 Laying of Ducts 50 11-Dec-14 29-Jan-15 642 M A4800 A4820
A4820 Laying of Cables 50 18-Dec-14 05-Feb-15 0 0 A4810 A4850
A4850 Lighting Columns Concrete Foundations 30 17-Jan-15 15-Feb-15 60 NO. A4820 A4852
A4852 High Masts Concrete Foundations 30 17-Jan-15 15-Feb-15 0 0 A4850 A4855, A5500
A4855 Concrete Foundations for Transformer Stations & Feeder Pillars 20 27-Jan-15 15-Feb-15 0 0 A4852 A4857, A4890
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 30 27-Jan-15 25-Feb-15 0
A4890 Fixing of High Masts 30 27-Jan-15 25-Feb-15 0 0 A4855 A4900
A4900 Fixing of Lighting Poles 30 27-Jan-15 25-Feb-15 0 0 A4890 A4860
TRANSFORMERS & FEEDER PILLARSTRANSFORMERS & FEEDER PILLARS 20 06-Feb-15 25-Feb-15 0
A4860 Installation of Feeder Pillar 20 06-Feb-15 25-Feb-15 0 0 A4900 A4870
A4870 Power Supply Connections to Feeder Pillar 20 06-Feb-15 25-Feb-15 0 0 A4860 A4857
A4857 33 KV & 11 KV Pad Mounted & Pole Mounted Transformers Substations 20 06-Feb-15 25-Feb-15 0 0 A4855, A4870 A5640
J J J J J J J J J
2014 2015 2016
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing 33 Kv Ovehead Lines
17-Oct-14, WATERLINES
Installation of New Irrigation Pipes
Obtain Shutdown & Connect to Existing
Remove & Dispose Existing Irrigation Pipes24-Apr-15, PEDESTRIAN UNDE
24-Apr-15, GENERAL
28-Jan-15, UNDERPASS STRUCTURE
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling24-Apr-15, ENTRANCE & EXIT - RHS
Casting of Floor Slab
Casting of Walls
Casting of Landing Slabs & Stair Case
Casing of Beams & Roof Slab06-Mar-15, EXTENSION OF EXIS
06-Mar-15, GENERAL
14-Feb-15, BOX CULVERT AT CH 0+300
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling
06-Mar-15, BOX CULVERT AT CH 0+500
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Casting of Apron Slab & W ing Walls
Backfilling
25-Feb-15, ROAD LIGHTING & EL
25-Feb-15, GENERAL
15-Feb-15, CIVIL WORKS & CABLING
Trench for Low Voltage Cables
Laying of Ducts
Laying of Cables
Lighting Columns Concrete Foundations
High Masts Concrete Foundations
Concrete Foundations for Transform25-Feb-15, COLUMNS, HIGH MASTS
Fixing of High Masts
Fixing of Lighting Poles25-Feb-15, TRANSFORMERS & F
Installation of Feeder Pillar
Power Supply Connections to Feeder Pillar
33 KV & 11 KV Pad Mounted & Pole
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 16 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 17: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/17.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
DRAINAGE WORKSDRAINAGE WORKS 40 08-Oct-14 16-Nov-14 11996
RC PIPESRC PIPES 40 08-Oct-14 16-Nov-14 11996
GENERALGENERAL 40 08-Oct-14 16-Nov-14 11996
A5130 Trench Excavation Work 20 08-Oct-14 27-Oct-14 547 M3 A6060 A5140
A5140 Laying of Drainage Pipes (RCC) 20 13-Oct-14 01-Nov-14 0 0 A5130, A6380 A5150
A5150 Construction of Manholes 20 20-Oct-14 08-Nov-14 20 0 A5140 A5160
A5160 Backfilling 20 28-Oct-14 16-Nov-14 11429 M3 A5150 A5500
ROAD FINISHING WORKSROAD FINISHING WORKS 133 16-Jan-15 28-May-15 80795
GENERALGENERAL 133 16-Jan-15 28-May-15 80795
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 74 16-Jan-15 30-Mar-15 60026
A5500 Backfilling to Embankment 50 16-Jan-15 06-Mar-15 28571 M3 A4852, A5260, A5160, A12430, A12500, A1040A5510
A5510 Subgrade Preparation 40 05-Feb-15 16-Mar-15 11064 M2 A5500 A5520
A5520 Preparation of Granular Subbase 40 12-Feb-15 23-Mar-15 6674 M3 A5510 A5530
A5530 Preparation of Aggregate Base Course 40 19-Feb-15 30-Mar-15 13717 M3 A5520 A5540
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 47 07-Mar-15 22-Apr-15 9662
A5540 Installation of Precast Concrete Curbs 40 07-Mar-15 15-Apr-15 4105 M A5530 A5560
A5560 Installation of Interlocking Tiles 40 14-Mar-15 22-Apr-15 5557 M2 A5540 A5570
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 59 21-Mar-15 18-May-15 11084
A5570 Bituminous Prime Coat 38 21-Mar-15 27-Apr-15 0 0 A5560 A5580
A5580 Bituminous Base Course 38 28-Mar-15 04-May-15 6325 M3 A5570 A5590
A5590 Bituminous Tack Coat 38 04-Apr-15 11-May-15 0 0 A5580 A5600
A5600 Bituminous Wearing Course 38 11-Apr-15 18-May-15 4759 M3 A5590, A1218 A5620
HIGHWAY SIGNS & ROAD MARKINGHIGHWAY SIGNS & ROAD MARKING 20 09-May-15 28-May-15 23
A5620 Fixing of Highway Signs Single & Multiple Poles 15 09-May-15 23-May-15 22 NO. A5600, A6410 A5630
A5630 Fixing of Overhead & Gantry Signs 15 09-May-15 23-May-15 1 NO. A5620, A1058 A5640
A5640 Traffic Lines & Road Studs 10 19-May-15 28-May-15 0 0 A5630, A4857, A1170 A1520, A6730
SURVICE ROADSSURVICE ROADS 138 29-May-15 13-Oct-15 20290
SR2 (CH 1+200 to 1+477.488)SR2 (CH 1+200 to 1+477.488) 138 29-May-15 13-Oct-15 20290
TRAFFIC SHIFTINGTRAFFIC SHIFTING 4 29-May-15 01-Jun-15 0
TO NEW MAIN ROADTO NEW MAIN ROAD 4 29-May-15 01-Jun-15 0
GENERALGENERAL 4 29-May-15 01-Jun-15 0
A1520 Placing of Plastic Barriers & Temporary Signs 4 29-May-15 01-Jun-15 0 0 A5640 A1530
A1530 Shift Traffic from Existing Southern & Northeren Service Roads to New Main Road 0 01-Jun-15 0 0 A1520, A6730 A5790
GENERAL CIVIL WORKSGENERAL CIVIL WORKS 16 02-Jun-15 17-Jun-15 711
CLEARING & EXCAVATIONCLEARING & EXCAVATION 16 02-Jun-15 17-Jun-15 711
GENERALGENERAL 16 02-Jun-15 17-Jun-15 711
A5790 Clearing & Grubbing 5 02-Jun-15 06-Jun-15 710 M2 A1530 A5800, A10190
A5800 Removal of Structures & Obstructures 5 04-Jun-15 08-Jun-15 1 LS A5790 A5820
A5820 Road Way Excavation 12 06-Jun-15 17-Jun-15 0 0 A5800 A4910
PEDESTRIAN UNDERPASS 3 (SR2 CH 01+320) - STAGE 2PEDESTRIAN UNDERPASS 3 (SR2 CH 01+320) - STAGE 2 108 22-Jun-15 07-Oct-15 2769
GENERALGENERAL 108 22-Jun-15 07-Oct-15 2769
UNDERPASS STRUCTUREUNDERPASS STRUCTURE 76 22-Jun-15 05-Sep-15 2669
A10190 Structural Excavation 10 22-Jun-15 01-Jul-15 584 M3 A5790 A10150
A10150 Blinding of Concrete 12 25-Jun-15 06-Jul-15 137 M3 A10190 A10160
A10160 Casting of Base Slab 21 02-Jul-15 22-Jul-15 59 M3 A10150 A10170, A10210
A10170 Casting of Walls 21 23-Jul-15 12-Aug-15 116 M3 A10160 A10180
A10180 Casting of Top Slab 21 13-Aug-15 02-Sep-15 59 M3 A10170 A10200
A10200 Backfilling 3 03-Sep-15 05-Sep-15 1714 M3 A10180 A5650
ENTRANCE & EXIT - LHSENTRANCE & EXIT - LHS 77 23-Jul-15 07-Oct-15 100
A10210 Casting of Floor Slab 22 23-Jul-15 13-Aug-15 10 M3 A10160 A10220
A10220 Casting of Walls 35 14-Aug-15 17-Sep-15 30 M3 A10210 A10230, A10240
A10240 Casting of Landing Slabs & Stair Case 35 03-Sep-15 07-Oct-15 50 M3 A10220 A10230
A10230 Casing of Beams & Roof Slab 20 18-Sep-15 07-Oct-15 10 0 A10220, A10240 A6100, A5780
ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 32 28-Jul-15 28-Aug-15 706
GENERALGENERAL 32 28-Jul-15 28-Aug-15 706
J J J J J J J J J
2014 2015 2016
16-Nov-14, DRAINAGE WORKS
16-Nov-14, RC PIPES
16-Nov-14, GENERAL
Trench Excavation Work
Laying of Drainage Pipes (RCC)
Construction of Manholes
Backfilling28-May-15, ROAD FINISHING WORKS
28-May-15, GENERAL
30-Mar-15, EMBANKMENT, SUB
Backfilling to Embankment
Subgrade Preparation
Preparation of Granular Subbase
Preparation of Aggregate Base Course22-Apr-15, MEDIAN & SIDEWALK PAVING
Installation of Precast Concrete Curbs
Installation of Interlocking Tiles18-May-15, NEW BITUMINOUS LAYERS
Bituminous Prime Coat
Bituminous Base Course
Bituminous Tack Coat
Bituminous Wearing Course28-May-15, HIGHWAY SIGNS
Fixing of Highway Signs Single
Fixing of Overhead & Gantry Signs
Traffic Lines & Road Studs13-Oct-15, SURVICE ROADS
13-Oct-15, SR2 (CH 1
01-Jun-15, TRAFFIC SHIFTING
01-Jun-15, TO NEW MAIN ROAD
01-Jun-15, GENERAL
Placing of Plastic Barriers & TShift Traffic from Existing Sout
17-Jun-15, GENERAL CIVIL WORKS
17-Jun-15, CLEARING & EXCAVATION
17-Jun-15, GENERAL
Clearing & Grubbing
Removal of Structures & Obstructures
Road Way Excavation07-Oct-15, PEDESTRI
07-Oct-15, GENERAL
05-Sep-15, UNDERPASS
Structural Excavation
Blinding of Concrete
Casting of Base Slab
Casting of Walls
Casting of Top Slab
Backfilling07-Oct-15, ENTRANC
Casting of Floor Slab
Casting of Walls
Casting of Landing Slab
Casing of Beams & Roof Slab28-Aug-15, ROAD LIGHT
28-Aug-15, GENERAL
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 17 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A
![Page 18: Construction Schedule](https://reader034.fdocuments.in/reader034/viewer/2022042519/55cf9154550346f57b8cae17/html5/thumbnails/18.jpg)
Activity ID Activity Name OriginalDuration
Start Finish Quantity UnitMeasure
Predecessors Successors
CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 27 28-Jul-15 23-Aug-15 706
A4910 Trench for Low Voltage Cables 12 28-Jul-15 08-Aug-15 532 M A5820, A6530 A4920
A4920 Laying of Ducts 12 02-Aug-15 13-Aug-15 154 M A4910 A4930
A4930 Laying of Cables 12 07-Aug-15 18-Aug-15 0 0 A4920 A4960
A4960 Lighting Columns Concrete Foundations 10 14-Aug-15 23-Aug-15 20 NO. A4930 A5010, A5650
COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 10 19-Aug-15 28-Aug-15 0
A5010 Fixing of Lighting Poles 10 19-Aug-15 28-Aug-15 0 0 A4960, A4680, A6350 A5690
ROAD FINISHING WORKSROAD FINISHING WORKS 50 25-Aug-15 13-Oct-15 16104
GENERALGENERAL 50 25-Aug-15 13-Oct-15 16104
EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 24 25-Aug-15 17-Sep-15 12361
A5650 Backfilling to Embankment 12 25-Aug-15 05-Sep-15 6857 M3 A4960, A10200 A5660
A5660 Subgrade Preparation 7 01-Sep-15 07-Sep-15 1936 M2 A5650 A5670
A5670 Preparation of Granular Subbase 7 06-Sep-15 12-Sep-15 1168 M3 A5660 A5680
A5680 Preparation of Aggregate Base Course 7 11-Sep-15 17-Sep-15 2400 M3 A5670 A5690
MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 10 14-Sep-15 23-Sep-15 1691
A5690 Installation of Precast Concrete Curbs 7 14-Sep-15 20-Sep-15 718 M A5680, A5010 A5710
A5710 Installation of Interlocking Tiles 7 17-Sep-15 23-Sep-15 973 M2 A5690 A5720
NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 22 20-Sep-15 11-Oct-15 2042
A5720 Bituminous Prime Coat 7 20-Sep-15 26-Sep-15 0 0 A5710 A5730
A5730 Bituminous Base Course 7 25-Sep-15 01-Oct-15 1165 M3 A5720 A5740
A5740 Bituminous Tack Coat 7 30-Sep-15 06-Oct-15 0 0 A5730 A5750
A5750 Bituminous Wearing Course 7 05-Oct-15 11-Oct-15 877 M3 A5740 A5760
HIGHWAY SIGNS & ROAD MARKINGHIGHWAY SIGNS & ROAD MARKING 7 07-Oct-15 13-Oct-15 10
A5760 Fixing of Highway Signs Single & Multiple Poles 7 07-Oct-15 13-Oct-15 10 NO. A5750, A6410 A5780
A5780 Traffic Lines & Road Studs 5 09-Oct-15 13-Oct-15 0 0 A5760, A10230 A6100, A6740
J J J J J J J J J
2014 2015 2016
23-Aug-15, CIVIL WORKS & CABLING
Trench for Low Voltage Cables
Laying of Ducts
Laying of Cables
Lighting Columns Concre28-Aug-15, COLUMNS, HIGH MASTS
Fixing of Lighting Poles13-Oct-15, ROAD FIN
13-Oct-15, GENERAL
17-Sep-15, EMBANKME
Backfilling to Embankment
Subgrade Preparation
Preparation of Granular Subbase
Preparation of Aggregate23-Sep-15, MEDIAN & S
Installation of Precast C
Installation of Interlocking Tiles11-Oct-15, NEW BITU
Bituminous Prime Coat
Bituminous Base Course
Bituminous Tack Coat
Bituminous Wearing Course13-Oct-15, HIGHWAY
Fixing of Highway Sign
Traffic Lines & Road Studs
CCC OMAN LLC
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
Page 18 of 18
Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM
Date Revision Checked Approved
13-Apr-14 FQI - REV2 18 September 2014
12-Oct-14 FQI - REV3
02-Feb-15 FQI - REV3 A