Construction Schedule

18
Activity ID Activity Name Original Duration Start Finish Quantity Unit Measure Predecessors Successors FALAJ AL QABIL RO FALAJ AL QABIL ROUNDABOUT REV 2 717 30-Oct-13 A 16-Oct-15 743337 PREPARATORY WO PREPARATORY WORKS 717 30-Oct-13 A 16-Oct-15 0 GENERAL GENERAL 717 30-Oct-13 A 16-Oct-15 0 CONTRACTUAL & PR CONTRACTUAL & PRELIMINARIES 717 30-Oct-13 A 16-Oct-15 0 MILESTONE & MO MILESTONE & MOBILIZATION 717 30-Oct-13 A 16-Oct-15 0 MILESTONES MILESTONES 717 30-Oct-13 A 16-Oct-15 0 CONTRACTU CONTRACTUAL DATES 717 30-Oct-13 A 16-Oct-15 0 A0000 Contract Award Date 0 30-Oct-13 A 0 0 A6230, A6080, A6670, A6630 A6080 Mobilization 60 30-Oct-13 A 28-Dec-13 A 0 0 A0000 A6230, A6240, A6255, A6250 A6720 Construction Duration 548 28-Dec-13 A 16-Oct-15 0 0 A6680 A6100 A6100 Project Completion Date 0 16-Oct-15 0 0 A6720, A5780, A10230, A CONSTRUCT CONSTRUCTIONAL DATES 717 30-Oct-13 A 16-Oct-15 0 A6670 Project Commencement 0 30-Oct-13 A 0 0 A0000 A6680 A6680 Mobilization Completion 0 28-Dec-13 A 0 0 A6230, A6240, A6255, A6 A6720, A1260, A6110 A6800 Resolution of all Expropriations about SR-2 0 28-Feb-14 A 0 0 A1330, A1340, A1400, A1 A6700 Commence Traffic Diversions from Existing Roads to Temporary Roads 0 30-Apr-14 0 0 A1010 A9930 A10580 Resolution of Falaj Location under Bridge 0 20-Jul-14 0 0 A11720 A11730 A6710 Complete Traffic Diversion from Temporary Roads to Batinah Highway 0 29-Apr-15 0 0 A5490, A6790, A3940 A9900 A6730 Complete Traffic Diversion from Temporary Roads to Sohar-Buraimi Road 0 28-May-15 0 0 A5640 A1530 A6690 Completion of all works 0 16-Oct-15 0 0 A6740 A6740 Complete Traffic Diversion from Temporary Roads to New Service Roads 0 16-Oct-15 0 0 A5780, A5940, A9640 A6690 MOBILIZATION MOBILIZATION 60 30-Oct-13 A 28-Dec-13 A 0 GENERAL GENERAL 60 30-Oct-13 A 28-Dec-13 A 0 A6230 Obtain NOC's 60 30-Oct-13 A 28-Dec-13 A 0 0 A0000, A6080 A6240, A6260, A6255, A6680 A6240 Setting-up Engineer's Offices 38 09-Nov-13 A 16-Dec-13 A 0 0 A6230, A6080 A6250, A6680 A6260 Erection of Laboratory & Store 45 14-Nov-13 A 28-Dec-13 A 0 0 A6230, A6080 A6680 A6250 Setting-up Contractor's Offices 38 16-Nov-13 A 23-Dec-13 A 0 0 A6240, A6080 A6680 A6255 Setting-up of Contractor's Camp 35 24-Nov-13 A 28-Dec-13 A 0 0 A6230, A6080 A6680 TRAFFIC MANA TRAFFIC MANAGEMENT 53 06-Nov-13 A 28-Dec-13 A 0 GENERAL GENERAL 53 06-Nov-13 A 28-Dec-13 A 0 A6630 Submit Traffic Mangement Plans 15 06-Nov-13 A 20-Nov-13 A 0 0 A0000 A6640 A6640 Approve Traffic Mnagement Plans 15 17-Nov-13 A 01-Dec-13 A 0 0 A6630 A6650 A6650 Obtain Traffic NOC's 15 02-Dec-13 A 16-Dec-13 A 0 0 A6640 A6660 A6660 Obtain Approval from RO P Police 12 17-Dec-13 A 28-Dec-13 A 0 0 A6650, A6230 A1260, A1070 SHOP DRAWING SHOP DRAWINGS 325 11-Jan-14 A 01-Dec-14 0 BOX CULVER BOX CULVERT 3 CELL @ CH 21+260 30 17-Aug-14 15-Sep-14 0 A12510 Prepare & Submit Shop Drawings 15 17-Aug-14 31-Aug-14 A12520 A12520 Approval of Shop Drawings 15 01-Sep-14 15-Sep-14 A12510 A11780 BOX CULVER BOX CULVERT 1 CELL @ CH 21+485 30 15-Sep-14 14-Oct-14 0 A10800 Prepare & Submit Shop Drawings 15 15-Sep-14 29-Sep-14 A10810 A10810 Approval of Shop Drawings 15 30-Sep-14 14-Oct-14 A10800 A2240 BOX CULVER BOX CULVERT 8 CELL @ CH 21+838 30 25-Aug-14 23-Sep-14 0 A10880 Prepare & Submit Shop Drawings 15 25-Aug-14 08-Sep-14 A10890 A10890 Approval of Shop Drawings 15 09-Sep-14 23-Sep-14 A10880 A2870 BOX CULVER BOX CULVERT 44 CELL @ CH 21+985 30 03-Mar-14 A 01-Apr-14 A 0 A10620 Prepare & Submit Shop Drawings 15 03-Mar-14 A 17-Mar-14 A A6230 A10630, A10640 A10630 Approval of Shop Drawings 15 18-Mar-14 A 01-Apr-14 A A10620 A2940 BOX CULVER BOX CULVERT 9 CELL @ CH 22+650 68 16-Mar-14 A 22-May-14 0 A10640 Prepare & Submit Shop Drawings 15 16-Mar-14 A 30-Mar-14 A A10620 A10650 A10650 Approval of Shop Drawings 15 08-May-14 22-May-14 A10640 A2800 BOX CULVER BOX CULVERT 5 CELL @ 23+500 30 30-Jun-14 29-Jul-14 0 A10700 Prepare & Submit Shop Drawings 15 30-Jun-14 14-Jul-14 A10710 A10710 Approval of Shop Drawings 15 15-Jul-14 29-Jul-14 A10700 A2660 BOX CULVER BOX CULVERT 1 CELL @ CH 23+760 30 17-Aug-14 15-Sep-14 0 J J J J J J J J J 2014 2015 2016 16-Oct-15, FALAJ AL 16-Oct-15, PREPARA 16-Oct-15, GENERAL 16-Oct-15, CONTRAC 16-Oct-15, MILESTO 16-Oct-15, MILESTO 16-Oct-15, CONTRAC Contract Award Date Mobilization Construction Duration Project Completion Da 16-Oct-15, CONSTRU Project Commencement Mobilization Completion Resolution of all Expropriations about SR-2 Commence Traffic Diversions from Existing Roads Resolution of Falaj Location under Bridge Complete Traffic Diversion from Complete Traffic Diversion fro Completion of all work Complete Traffic Dive 28-Dec-13 A, MOBILIZATION 28-Dec-13 A, GENERAL Obtain NOC's Setting-up Engineer's Offices Erection of Laboratory & Store Setting-up Contractor's Offices Setting-up of Contractor's Camp 28-Dec-13 A, TRAFFIC MANAGEMENT 28-Dec-13 A, GENERAL Submit Traffic Mangement Plans Approve Tr affic Mnagement Plans Obtain Traffic NOC's Obtain Appr oval from RO P Police 01-Dec-14, SHOP DRAW ING S 15-Sep-14, BOX CULVERT 3 CELL @ CH Prepare & Submit Shop Drawings Approval of Shop Drawings 14-Oct-14, BOX CULVERT 1 CELL @ CH Prepare & Submit Shop Drawings Approval of Shop Drawings 23-Sep-14, BOX CULVERT 8 CELL @ CH Prepare & Submit Shop Drawings Approval of Shop Drawings 01-Apr-14 A, BOX CULVERT 44 CELL @ CH 21+98 Prepare & Submit Shop Drawings Approval of Shop Drawings 22-May-14, BOX CULVERT 9 CELL @ CH 22+65 Prepare & Submit Shop Drawings Approval of Shop Drawings 29-Jul-14, BOX CULVERT 5 CELL @ 23+500 Prepare & Submit Shop Drawings Approval of Shop Drawings 15-Sep-14, BOX CULVERT 1 CELL @ CH CCC OMAN LLC Primary Baseline Actual Work Remaining Work Critical Remaining Work Milestone Summary UPGRADING OF FALAJ AL QABAIL ROUNDABOUT Page 1 of 18 Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM Date Revision Checked Approved 13-Apr-14 FQI - REV2 18 September 2014 12-Oct-14 FQI - REV3 02-Feb-15 FQI - REV3 A

description

Execution programme for Flyover Interchange construction.

Transcript of Construction Schedule

Page 1: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

FALAJ AL QABIL ROUNDABOUT REV 2FALAJ AL QABIL ROUNDABOUT REV 2 717 30-Oct-13 A 16-Oct-15 743337

PREPARATORY WORKSPREPARATORY WORKS 717 30-Oct-13 A 16-Oct-15 0

GENERALGENERAL 717 30-Oct-13 A 16-Oct-15 0

CONTRACTUAL & PRELIMINARIESCONTRACTUAL & PRELIMINARIES 717 30-Oct-13 A 16-Oct-15 0

MILESTONE & MOBILIZATIONMILESTONE & MOBILIZATION 717 30-Oct-13 A 16-Oct-15 0

MILESTONESMILESTONES 717 30-Oct-13 A 16-Oct-15 0

CONTRACTUAL DATESCONTRACTUAL DATES 717 30-Oct-13 A 16-Oct-15 0

A0000 Contract Award Date 0 30-Oct-13 A 0 0 A6230, A6080, A6670, A6630, A6300, A7290

A6080 Mobilization 60 30-Oct-13 A 28-Dec-13 A 0 0 A0000 A6230, A6240, A6255, A6250, A6260, A6680

A6720 Construction Duration 548 28-Dec-13 A 16-Oct-15 0 0 A6680 A6100

A6100 Project Completion Date 0 16-Oct-15 0 0 A6720, A5780, A10230, A5290, A9830, A9460, A5880, A5930, A9750, A9820, A5490, A5940, A6900, A6960

CONSTRUCTIONAL DATESCONSTRUCTIONAL DATES 717 30-Oct-13 A 16-Oct-15 0

A6670 Project Commencement 0 30-Oct-13 A 0 0 A0000 A6680

A6680 Mobilization Completion 0 28-Dec-13 A 0 0 A6230, A6240, A6255, A6250, A6260, A6080, A6670A6720, A1260, A6110

A6800 Resolution of all Expropriations about SR-2 0 28-Feb-14 A 0 0 A1330, A1340, A1400, A1410

A6700 Commence Traffic Diversions from Existing Roads to Temporary Roads 0 30-Apr-14 0 0 A1010 A9930

A10580 Resolution of Falaj Location under Bridge 0 20-Jul-14 0 0 A11720 A11730

A6710 Complete Traffic Diversion from Temporary Roads to Batinah Highway 0 29-Apr-15 0 0 A5490, A6790, A3940 A9900

A6730 Complete Traffic Diversion from Temporary Roads to Sohar-Buraimi Road 0 28-May-15 0 0 A5640 A1530

A6690 Completion of all works 0 16-Oct-15 0 0 A6740

A6740 Complete Traffic Diversion from Temporary Roads to New Service Roads 0 16-Oct-15 0 0 A5780, A5940, A9640 A6690

MOBILIZATIONMOBILIZATION 60 30-Oct-13 A 28-Dec-13 A 0

GENERALGENERAL 60 30-Oct-13 A 28-Dec-13 A 0

A6230 Obtain NOC's 60 30-Oct-13 A 28-Dec-13 A 0 0 A0000, A6080 A6240, A6260, A6255, A6680,

A6240 Setting-up Engineer's Offices 38 09-Nov-13 A 16-Dec-13 A 0 0 A6230, A6080 A6250, A6680

A6260 Erection of Laboratory & Store 45 14-Nov-13 A 28-Dec-13 A 0 0 A6230, A6080 A6680

A6250 Setting-up Contractor's Offices 38 16-Nov-13 A 23-Dec-13 A 0 0 A6240, A6080 A6680

A6255 Setting-up of Contractor's Camp 35 24-Nov-13 A 28-Dec-13 A 0 0 A6230, A6080 A6680

TRAFFIC MANAGEMENTTRAFFIC MANAGEMENT 53 06-Nov-13 A 28-Dec-13 A 0

GENERALGENERAL 53 06-Nov-13 A 28-Dec-13 A 0

A6630 Submit Traffic Mangement Plans 15 06-Nov-13 A 20-Nov-13 A 0 0 A0000 A6640

A6640 Approve Traffic Mnagement Plans 15 17-Nov-13 A 01-Dec-13 A 0 0 A6630 A6650

A6650 Obtain Traffic NOC's 15 02-Dec-13 A 16-Dec-13 A 0 0 A6640 A6660

A6660 Obtain Approval from ROP Police 12 17-Dec-13 A 28-Dec-13 A 0 0 A6650, A6230 A1260, A1070

SHOP DRAWINGSSHOP DRAWINGS 325 11-Jan-14 A 01-Dec-14 0

BOX CULVERT 3 CELL @ CH 21+260BOX CULVERT 3 CELL @ CH 21+260 30 17-Aug-14 15-Sep-14 0

A12510 Prepare & Submit Shop Drawings 15 17-Aug-14 31-Aug-14 A12520

A12520 Approval of Shop Drawings 15 01-Sep-14 15-Sep-14 A12510 A11780

BOX CULVERT 1 CELL @ CH 21+485BOX CULVERT 1 CELL @ CH 21+485 30 15-Sep-14 14-Oct-14 0

A10800 Prepare & Submit Shop Drawings 15 15-Sep-14 29-Sep-14 A10810

A10810 Approval of Shop Drawings 15 30-Sep-14 14-Oct-14 A10800 A2240

BOX CULVERT 8 CELL @ CH 21+838BOX CULVERT 8 CELL @ CH 21+838 30 25-Aug-14 23-Sep-14 0

A10880 Prepare & Submit Shop Drawings 15 25-Aug-14 08-Sep-14 A10890

A10890 Approval of Shop Drawings 15 09-Sep-14 23-Sep-14 A10880 A2870

BOX CULVERT 44 CELL @ CH 21+985BOX CULVERT 44 CELL @ CH 21+985 30 03-Mar-14 A 01-Apr-14 A 0

A10620 Prepare & Submit Shop Drawings 15 03-Mar-14 A 17-Mar-14 A A6230 A10630, A10640

A10630 Approval of Shop Drawings 15 18-Mar-14 A 01-Apr-14 A A10620 A2940

BOX CULVERT 9 CELL @ CH 22+650BOX CULVERT 9 CELL @ CH 22+650 68 16-Mar-14 A 22-May-14 0

A10640 Prepare & Submit Shop Drawings 15 16-Mar-14 A 30-Mar-14 A A10620 A10650

A10650 Approval of Shop Drawings 15 08-May-14 22-May-14 A10640 A2800

BOX CULVERT 5 CELL @ 23+500BOX CULVERT 5 CELL @ 23+500 30 30-Jun-14 29-Jul-14 0

A10700 Prepare & Submit Shop Drawings 15 30-Jun-14 14-Jul-14 A10710

A10710 Approval of Shop Drawings 15 15-Jul-14 29-Jul-14 A10700 A2660

BOX CULVERT 1 CELL @ CH 23+760BOX CULVERT 1 CELL @ CH 23+760 30 17-Aug-14 15-Sep-14 0

J J J J J J J J J

2014 2015 2016

16-Oct-15, FALAJ AL

16-Oct-15, PREPARAT

16-Oct-15, GENERAL

16-Oct-15, CONTRAC

16-Oct-15, MILESTON

16-Oct-15, MILESTONES

16-Oct-15, CONTRAC

Contract Award Date

Mobilization

Construction DurationProject Completion Date

16-Oct-15, CONSTRU

Project Commencement

Mobilization Completion

Resolution of all Expropriations about SR-2

Commence Traffic Diversions from Existing Roads

Resolution of Falaj Location under Bridge

Complete Traffic Diversion from

Complete Traffic Diversion fro

Completion of all works

Complete Traffic Diver

28-Dec-13 A, MOBILIZATION

28-Dec-13 A, GENERAL

Obtain NOC's

Setting-up Engineer's Offices

Erection of Laboratory & Store

Setting-up Contractor's Offices

Setting-up of Contractor's Camp28-Dec-13 A, TRAFFIC MANAGEMENT

28-Dec-13 A, GENERAL

Submit Traffic Mangement Plans

Approve Traffic Mnagement Plans

Obtain Traffic NOC's

Obtain Approval from ROP Police01-Dec-14, SHOP DRAW INGS

15-Sep-14, BOX CULVERT 3 CELL @ CH 21+260

Prepare & Submit Shop Drawings

Approval of Shop Drawings

14-Oct-14, BOX CULVERT 1 CELL @ CH 21+485

Prepare & Submit Shop Drawings

Approval of Shop Drawings23-Sep-14, BOX CULVERT 8 CELL @ CH 21+838

Prepare & Submit Shop Drawings

Approval of Shop Drawings01-Apr-14 A, BOX CULVERT 44 CELL @ CH 21+985

Prepare & Submit Shop Drawings

Approval of Shop Drawings22-May-14, BOX CULVERT 9 CELL @ CH 22+650

Prepare & Submit Shop Drawings

Approval of Shop Drawings29-Jul-14, BOX CULVERT 5 CELL @ 23+500

Prepare & Submit Shop Drawings

Approval of Shop Drawings15-Sep-14, BOX CULVERT 1 CELL @ CH 23+760

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 1 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 2: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A10680 Prepare & Submit Shop Drawings 15 17-Aug-14 31-Aug-14 A10690

A10690 Approval of Shop Drawings 15 01-Sep-14 15-Sep-14 A10680 A2590

BOX CULVERT 1 CELL @ CH 23+997BOX CULVERT 1 CELL @ CH 23+997 30 09-Sep-14 08-Oct-14 0

A10760 Prepare & Submit Shop Drawings 15 09-Sep-14 23-Sep-14 A10770

A10770 Approval of Shop Drawings 15 24-Sep-14 08-Oct-14 A10760 A2380

BOX CULVERT 1 CELL @ CH 24+235BOX CULVERT 1 CELL @ CH 24+235 30 29-Sep-14 28-Oct-14 0

A10840 Prepare & Submit Shop Drawings 15 29-Sep-14 13-Oct-14 A10850

A10850 Approval of Shop Drawings 15 14-Oct-14 28-Oct-14 A10840 A2450

BOX CULVERT 1 CELL @ 24+570BOX CULVERT 1 CELL @ 24+570 30 19-Oct-14 17-Nov-14 0

A10860 Prepare & Submit Shop Drawings 15 19-Oct-14 02-Nov-14 A10870

A10870 Approval of Shop Drawings 15 03-Nov-14 17-Nov-14 A10860 A2520

PEDESTRIAN UNDERPASS 1 @ CH 22+800 - SOL1PEDESTRIAN UNDERPASS 1 @ CH 22+800 - SOL1 30 29-May-14 27-Jun-14 0

A12530 Prepare & Submit Drawings 15 29-May-14 12-Jun-14 A12540

A12540 Approval of Shop Drawings 15 13-Jun-14 27-Jun-14 A12530 A11850

PEDESTRIAN UNDERPASS 2 @ CH 23+300 - SOL1PEDESTRIAN UNDERPASS 2 @ CH 23+300 - SOL1 30 27-Aug-14 25-Sep-14 0

A10900 Prepare & Submit Shop Drawings 15 27-Aug-14 10-Sep-14 A10910

A10910 Approval of Shop Drawings 15 11-Sep-14 25-Sep-14 A10900 A1795

PEDESTRIAN UNDERPASS 3 @ CH 00+050- SOL3PEDESTRIAN UNDERPASS 3 @ CH 00+050- SOL3 30 24-Aug-14 22-Sep-14 0

A10940 Prepare & Submit Shop Drawings 15 24-Aug-14 07-Sep-14 A10950

A10950 Approval of Shop Drawings 15 08-Sep-14 22-Sep-14 A10940 A5210

PIER 1 - NBPIER 1 - NB 30 26-Feb-14 A 27-Mar-14 A 0

A10960 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A6230 A10970

A10970 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A10960 A3210

FALAJ RELOCATIONFALAJ RELOCATION 30 19-Mar-14 A 23-Mar-14 A 0

A11470 Prepare & Submit Shop Drawings 15 19-Mar-14 A 22-Mar-14 A A6230 A11480

A11480 Approval of Shop Drawings 15 23-Mar-14 A 23-Mar-14 A A11470 A3160, A999

PIER 2 - NBPIER 2 - NB 30 26-Feb-14 A 27-Mar-14 A 0

A10980 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A6230 A10990

A10990 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A10980 A3160

PIER 3 - NBPIER 3 - NB 30 26-Feb-14 A 27-Mar-14 A 0

A11000 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11010, A11020, A11060

A11010 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11000 A1540

PIER 4 - NBPIER 4 - NB 30 26-Feb-14 A 27-Mar-14 A 0

A11020 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11000 A11030, A11040

A11030 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11020 A3310

PIER 5 - NBPIER 5 - NB 30 26-Feb-14 A 27-Mar-14 A 0

A11040 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11020 A11050

A11050 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11040 A3260

AB1 - NBAB1 - NB 30 26-Feb-14 A 27-Mar-14 A 0

A11060 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11000 A11070, A11080

A11070 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11060 A1590

AB2 - NBAB2 - NB 30 26-Feb-14 A 27-Mar-14 A 0

A11080 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11060 A11090, A11100

A11090 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11080 A3360

PIER 1 - SBPIER 1 - SB 30 26-Feb-14 A 27-Mar-14 A 0

A11100 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11080 A11110, A11120

A11110 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11100 A3750

PIER 2 - SBPIER 2 - SB 30 26-Feb-14 A 27-Mar-14 A 0

A11120 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11100 A11130

A11130 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11120 A4000

PIER 3 - SBPIER 3 - SB 30 26-Feb-14 A 27-Mar-14 A 0

A11140 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A6230 A11150, A11160

A11150 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11140 A4100

PIER 4 -SBPIER 4 -SB 30 26-Feb-14 A 27-Mar-14 A 0

A11160 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11140 A11170, A11180, A11200, A11220

J J J J J J J J J

2014 2015 2016

Prepare & Submit Shop Drawings

Approval of Shop Drawings08-Oct-14, BOX CULVERT 1 CELL @ CH 23+997

Prepare & Submit Shop Drawings

Approval of Shop Drawings28-Oct-14, BOX CULVERT 1 CELL @ CH 24+235

Prepare & Submit Shop Drawings

Approval of Shop Drawings17-Nov-14, BOX CULVERT 1 CELL @ 24+570

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Jun-14, PEDESTRIAN UNDERPASS 1 @ CH

Prepare & Submit Drawings

Approval of Shop Drawings

25-Sep-14, PEDESTRIAN UNDERPASS 2

Prepare & Submit Shop Drawings

Approval of Shop Drawings22-Sep-14, PEDESTRIAN UNDERPASS 3

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, PIER 1 - NB

Prepare & Submit Shop Drawings

Approval of Shop Drawings23-Mar-14 A, FALAJ RELOCATION

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, PIER 2 - NB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, PIER 3 - NB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, PIER 4 - NB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, PIER 5 - NB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, AB1 - NB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, AB2 - NB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, PIER 1 - SB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, PIER 2 - SB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, PIER 3 - SB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, PIER 4 -SB

Prepare & Submit Shop Drawings

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 2 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 3: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A11170 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11160 A4050

PIER 5 - SBPIER 5 - SB 30 26-Feb-14 A 27-Mar-14 A 0

A11180 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11160 A11190

A11190 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11180 A3950

AB 1 - SBAB 1 - SB 30 26-Feb-14 A 27-Mar-14 A 0

A11200 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11160 A11210

A11210 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11200 A3800

AB2 - SBAB2 - SB 30 26-Feb-14 A 27-Mar-14 A 0

A11220 Prepare & Submit Shop Drawings 15 26-Feb-14 A 12-Mar-14 A A11160 A11230

A11230 Approval of Shop Drawings 15 13-Mar-14 A 27-Mar-14 A A11220 A4170

BRIDGE DECK SPAN AB1 & P3 - NBBRIDGE DECK SPAN AB1 & P3 - NB 30 22-Jun-14 21-Jul-14 0

A11240 Prepare & Submit Shop Drawings 15 22-Jun-14 06-Jul-14 A11250

A11250 Approval of Shop Drawings 15 07-Jul-14 21-Jul-14 A11240 A1640

BRIDGE DECK SPAN AB2 & P3 - NBBRIDGE DECK SPAN AB2 & P3 - NB 30 20-Aug-14 18-Sep-14 0

A11260 Prepare & Submit Shop Drawings 15 20-Aug-14 03-Sep-14 A11270

A11270 Approval of Shop Drawings 15 04-Sep-14 18-Sep-14 A11260 A3500

BRIDGE DECK SPAN AB2 & P3 - SBBRIDGE DECK SPAN AB2 & P3 - SB 30 14-Oct-14 12-Nov-14 0

A11280 Prepare & Submit Shop Drawings 15 14-Oct-14 28-Oct-14 A11290

A11290 Approval of Shop Drawings 15 29-Oct-14 12-Nov-14 A11280 A3850

BRIDGE DECK SPAN AB1 & P3- SBBRIDGE DECK SPAN AB1 & P3- SB 30 02-Nov-14 01-Dec-14 0

A11490 Prepare & Submit Shop Drawings 15 02-Nov-14 16-Nov-14 A11500

A11500 Approval of Shop Drawings 15 17-Nov-14 01-Dec-14 A11490 A4310

MSE WALLSMSE WALLS 30 11-Jan-14 A 09-Feb-14 A 0

A11320 Prepare & Submit Shop Drawings 15 11-Jan-14 A 25-Jan-14 A A6230 A11330

A11330 Approval of Shop Drawings 15 26-Jan-14 A 09-Feb-14 A A11320 A5020

PROCUREMENTPROCUREMENT 471 29-Nov-13 A 14-Mar-15 0

MATERIALMATERIAL 452 18-Dec-13 A 14-Mar-15 0

PRECAST MSE WALL PANELSPRECAST MSE WALL PANELS 75 18-Dec-13 A 02-Mar-14 A 0

A6300 Submit Material for Approval 15 18-Dec-13 A 01-Jan-14 A 0 0 A0000 A6310

A6310 Obtain Material Approval 20 02-Jan-14 A 21-Jan-14 A 0 0 A6300 A6320

A6320 Delivery to Site 40 22-Jan-14 A 02-Mar-14 A 0 0 A6310 A5020

POT BEARINGSPOT BEARINGS 172 01-Mar-14 A 19-Aug-14 0

A6450 Submit Material for Approval 20 01-Mar-14 A 20-Mar-14 A 0 0 A6230 A6460

A6460 Obtain Material Approval 30 21-Mar-14 A 21-Apr-14 0 0 A6450 A6470

A6470 Delivery to Site 120 22-Apr-14 19-Aug-14 0 0 A6460 A1640, A3500, A3850, A4310

EXPANSION JOINTEXPANSION JOINT 170 25-Jul-14 10-Jan-15 0

A10590 Submit Material for Approval 20 25-Jul-14 13-Aug-14 0 0 A6230 A10600

A10600 Obtain Material Approval 30 14-Aug-14 12-Sep-14 0 0 A10590 A10610

A10610 Delivery to Site 120 13-Sep-14 10-Jan-15 0 0 A10600 A3570

LIGHTING POLES & LUMINARIESLIGHTING POLES & LUMINARIES 140 26-Jul-14 12-Dec-14 0

A6330 Submit Material for Approval 20 26-Jul-14 14-Aug-14 0 0 A6230 A6340

A6340 Obtain Material Approval 20 15-Aug-14 03-Sep-14 0 0 A6330 A6350

A6350 Delivery to Site 100 04-Sep-14 12-Dec-14 0 0 A6340 A4670, A5990, A5010

PRECAST CONC. BARRIER MOLDSPRECAST CONC. BARRIER MOLDS 75 30-Aug-14 12-Nov-14 0

A6270 Submit Material for Approval 15 30-Aug-14 13-Sep-14 0 0 A6230 A6280

A6280 Obtain Material Approval 20 14-Sep-14 03-Oct-14 0 0 A6270 A6290

A6290 Delivery to Site 40 04-Oct-14 12-Nov-14 0 0 A6280 A4550, A3920, A5400

RC STORM SEWERRC STORM SEWER 50 26-Jun-14 14-Aug-14 0

A6360 Submit Material for Approval 15 26-Jun-14 10-Jul-14 0 0 A6230 A6370

A6370 Obtain Material Approval 15 11-Jul-14 25-Jul-14 0 0 A6360 A6380

A6380 Delivery to Site 20 26-Jul-14 14-Aug-14 0 0 A6370 A5100, A5140

GUARDRAILGUARDRAIL 100 05-Dec-14 14-Mar-15 0

A6420 Submit Material for Approval 20 05-Dec-14 24-Dec-14 0 0 A6230 A6430

A6430 Obtain Material Approval 20 25-Dec-14 13-Jan-15 0 0 A6420 A6440

A6440 Delivery to Site 60 14-Jan-15 14-Mar-15 0 0 A6430 A5460

J J J J J J J J J

2014 2015 2016

Approval of Shop Drawings27-Mar-14 A, PIER 5 - SB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, AB 1 - SB

Prepare & Submit Shop Drawings

Approval of Shop Drawings27-Mar-14 A, AB2 - SB

Prepare & Submit Shop Drawings

Approval of Shop Drawings21-Jul-14, BRIDGE DECK SPAN AB1 & P3 - NB

Prepare & Submit Shop Drawings

Approval of Shop Drawings18-Sep-14, BRIDGE DECK SPAN AB2 & P3 - NB

Prepare & Submit Shop Drawings

Approval of Shop Drawings12-Nov-14, BRIDGE DECK SPAN AB2 & P3 - SB

Prepare & Submit Shop Drawings

Approval of Shop Drawings01-Dec-14, BRIDGE DECK SPAN AB1 & P3- SB

Prepare & Submit Shop Drawings

Approval of Shop Drawings09-Feb-14 A, MSE WALLS

Prepare & Submit Shop Drawings

Approval of Shop Drawings14-Mar-15, PROCUREMENT

14-Mar-15, MATERIAL

02-Mar-14 A, PRECAST MSE WALL PANELS

Submit Material for Approval

Obtain Material Approval

Delivery to Site19-Aug-14, POT BEARINGS

Submit Material for Approval

Obtain Material Approval

Delivery to Site10-Jan-15, EXPANSION JOINT

Submit Material for Approval

Obtain Material Approval

Delivery to Site12-Dec-14, LIGHTING POLES & LUMINARIES

Submit Material for Approval

Obtain Material Approval

Delivery to Site12-Nov-14, PRECAST CONC. BARRIER MOLDS

Submit Material for Approval

Obtain Material Approval

Delivery to Site14-Aug-14, RC STORM SEWER

Submit Material for Approval

Obtain Material Approval

Delivery to Site14-Mar-15, GUARDRAIL

Submit Material for Approval

Obtain Material Approval

Delivery to Site

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 3 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 4: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

ROAD SIGNSROAD SIGNS 60 14-Jan-15 14-Mar-15 0

A6390 Submit Material for Approval 20 14-Jan-15 02-Feb-15 0 0 A6230 A6400

A6400 Obtain Material Approval 20 03-Feb-15 22-Feb-15 0 0 A6390 A6410

A6410 Delivery to Site 20 23-Feb-15 14-Mar-15 0 0 A6400 A5470, A5930, A5620, A5760

BITUMINOUS PAINTBITUMINOUS PAINT 60 15-Jan-14 A 15-Mar-14 A 0

A11510 Submit Material for Approval 15 15-Jan-14 A 29-Jan-14 A 0 0 A6230 A11520

A11520 Obtain Material Approval 15 30-Jan-14 A 13-Feb-14 A 0 0 A11510 A11530

A11530 Delivery to Site 30 14-Feb-14 A 15-Mar-14 A 0 0 A11520 A1570

WATERSTOPWATERSTOP 116 10-Feb-14 A 05-Jun-14 0

A11540 Submit Material for Approval 15 10-Feb-14 A 24-Feb-14 A 0 0 A6230 A11550

A11550 Obtain Material Approval 15 25-Feb-14 A 11-Mar-14 A 0 0 A11540 A11560

A11560 Delivery to Site 40 27-Apr-14 05-Jun-14 0 0 A11550 A2940

GEOTEXTILEGEOTEXTILE 60 24-May-14 22-Jul-14 0

A11570 Submit Material for Approval 15 24-May-14 07-Jun-14 0 0 A6230 A11580

A11580 Obtain Material Approval 15 08-Jun-14 22-Jun-14 0 0 A11570 A11590

A11590 Delivery to Site 30 23-Jun-14 22-Jul-14 0 0 A11580 A5070

JOINT SEALANTJOINT SEALANT 75 30-Aug-14 12-Nov-14 0

A11600 Submit Material for Approval 15 30-Aug-14 13-Sep-14 0 0 A6230 A11610

A11610 Obtain Material Approval 20 14-Sep-14 03-Oct-14 0 0 A11600 A11620

A11620 Delivery to Site 40 04-Oct-14 12-Nov-14 0 0 A11610 A4550, A3920, A5400

S/CS/C 318 29-Nov-13 A 12-Oct-14 0

ELECTRICAL S/CELECTRICAL S/C 40 02-Feb-14 A 13-Mar-14 A 0

A6510 Select S/C 15 02-Feb-14 A 16-Feb-14 A 0 0 A6230 A6520

A6520 Approve S/C 15 17-Feb-14 A 03-Mar-14 A 0 0 A6510 A6530

A6530 Mobilization to Site 10 04-Mar-14 A 13-Mar-14 A 0 0 A6520 A1360, A1100, A4800, A4910

WATER S/CWATER S/C 35 01-Mar-14 A 04-Apr-14 A 0

A6540 Select S/C 15 01-Mar-14 A 15-Mar-14 A 0 0 A6230 A6550

A6550 Approve S/C 15 16-Mar-14 A 30-Mar-14 A 0 0 A6540 A6560

A6560 Mobilization to Site 5 31-Mar-14 A 04-Apr-14 A 0 0 A6550 A1020

TELEPHONE S/CTELEPHONE S/C 40 05-Feb-14 A 16-Mar-14 A 0

A6570 Select S/C 15 05-Feb-14 A 19-Feb-14 A 0 0 A6230 A6580

A6580 Approve S/C 15 20-Feb-14 A 06-Mar-14 A 0 0 A6570 A6590

A6590 Mobilization to Site 10 07-Mar-14 A 16-Mar-14 A 0 0 A6580 A1450

PILING S/CPILING S/C 75 29-Nov-13 A 11-Feb-14 A 0

A6480 Select S/C 15 29-Nov-13 A 13-Dec-13 A 0 0 A6230 A6490

A6490 Approve S/C 15 14-Dec-13 A 28-Dec-13 A 0 0 A6480 A6500

A6500 Mobilization to Site 45 29-Dec-13 A 11-Feb-14 A 0 0 A6490 A1540, A3160

POST TENSIONING S/CPOST TENSIONING S/C 240 15-Feb-14 A 12-Oct-14 0

A6600 Select S/C 15 15-Feb-14 A 01-Mar-14 A 0 0 A6230 A6610

A6610 Approve S/C 15 14-Aug-14 28-Aug-14 0 0 A6600 A6620

A6620 Mobilization to Site 45 29-Aug-14 12-Oct-14 0 0 A6610 A1670

BATINAH HIGHWAYBATINAH HIGHWAY 657 29-Dec-13 A 16-Oct-15 612512

HIGHWAY & SLIP ROADSHIGHWAY & SLIP ROADS 636 29-Dec-13 A 25-Sep-15 578157

SOL1, SOL5, SOL6SOL1, SOL5, SOL6 489 29-Dec-13 A 01-May-15 483934

TEMPORARY DIVERSION FOR EXISTING NORTHERN SERVICE ROADTEMPORARY DIVERSION FOR EXISTING NORTHERN SERVICE ROAD 23 29-Dec-13 A 20-Jan-14 A 327

SR1 (CH 0+000 to CH 0+797)SR1 (CH 0+000 to CH 0+797) 23 29-Dec-13 A 20-Jan-14 A 327

GENERALGENERAL 23 29-Dec-13 A 20-Jan-14 A 327

A1260 Laying of Asphalt of Temp. Road over SR-1 17 29-Dec-13 A 15-Jan-14 A 327 M3 A6660, A6680 A10330

A10330 Placing Plastic Barriers 5 16-Jan-14 A 20-Jan-14 A 0 0 A1260 A1270

A1270 Shift Traffic from Existing Northern Service Road to Temp. SR-1 0 20-Jan-14 A 0 0 A10330 A1010

TEMPORARY DIVERSION FOR EXISTING HIGHWAY - NORTH BOUNDTEMPORARY DIVERSION FOR EXISTING HIGHWAY - NORTH BOUND 120 05-Jan-14 A 30-Apr-14 655

SOL1-NORTH (CH 21+100 to CH 25+300)SOL1-NORTH (CH 21+100 to CH 25+300) 120 05-Jan-14 A 30-Apr-14 655

GENERALGENERAL 120 05-Jan-14 A 30-Apr-14 655

A1070 Protection of services 40 05-Jan-14 A 13-Feb-14 A 0 0 A6660 A1000, A1080

A1000 Laying of Asphalt on Temp. new Road Adjacent to SOL1-NB 30 13-Jan-14 A 25-Apr-14 655 M3 A1070, A999, A1090 A10490, A1005

J J J J J J J J J

2014 2015 2016

14-Mar-15, ROAD SIGNS

Submit Material for Approval

Obtain Material Approval

Delivery to Site15-Mar-14 A, BITUMINOUS PAINT

Submit Material for Approval

Obtain Material Approval

Delivery to Site05-Jun-14, WATERSTOP

Submit Material for Approval

Obtain Material Approval

Delivery to Site22-Jul-14, GEOTEXTILE

Submit Material for Approval

Obtain Material Approval

Delivery to Site12-Nov-14, JOINT SEALANT

Submit Material for Approval

Obtain Material Approval

Delivery to Site12-Oct-14, S/C

13-Mar-14 A, ELECTRICAL S/C

Select S/C

Approve S/C

Mobilization to Site04-Apr-14 A, WATER S/C

Select S/C

Approve S/C

Mobilization to Site16-Mar-14 A, TELEPHONE S/C

Select S/C

Approve S/C

Mobilization to Site11-Feb-14 A, PILING S/C

Select S/C

Approve S/C

Mobilization to Site12-Oct-14, POST TENSIONING S/C

Select S/C

Approve S/C

Mobilization to Site16-Oct-15, BATINAH HIGHWAY

25-Sep-15, HIGHWAY &

01-May-15, SOL1, SOL5, SOL6

20-Jan-14 A, TEMPORARY DIVERSION FOR EXISTING

20-Jan-14 A, SR1 (CH 0+000 to CH 0+797)

20-Jan-14 A, GENERAL

Laying of Asphalt of Temp. Road over SR-1

Placing Plastic BarriersShift Traffic from Existing Northern Service Road to Temp. SR-1

30-Apr-14, TEMPORARY DIVERSION FOR EXIST

30-Apr-14, SOL1-NORTH (CH 21+100 to CH 25+300)

30-Apr-14, GENERAL

Protection of services

Laying of Asphalt on Temp. new Road Adjacent to SOL1-NB

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 4 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 5: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A1080 Extension of Existing Drainage under Highway 30 14-Feb-14 A 15-Mar-14 A A1070 A999

A999 Construction of Falaj Under Temp. Diversion 18 12-Mar-14 A 30-Mar-14 A A11480, A1080 A1000, A9910, A1090, A11630

A1090 Repairs due to Heavy Rainfalls on the 26/27 of March 2014 17 30-Mar-14 A 13-Apr-14 A A999 A1000

A1005 Placing of Plastic Barriers 8 23-Apr-14 30-Apr-14 0 0 A1000 A1010

A1010 Shift Traffic from Existing Main Road NB to Temp. diversion 0 30-Apr-14 0 0 A1005, A1270 A6700, A2940, A2800, A1540, A2660, A3160, A5310, A1590

TEMPORARY DIVERSION FOR EXISTING SOUTHERN SERVICE ROADTEMPORARY DIVERSION FOR EXISTING SOUTHERN SERVICE ROAD 56 19-Jan-14 A 15-Mar-14 A 655

SR2 (CH 0+000 to CH 1+450)SR2 (CH 0+000 to CH 1+450) 56 19-Jan-14 A 15-Mar-14 A 655

GENERALGENERAL 56 19-Jan-14 A 15-Mar-14 A 655

A10490 Protection of services 21 19-Jan-14 A 08-Feb-14 A 0 0 A1000 A9940, A10500, A1330, A1340, A1400, A1410

A9940 Laying of Asphalt Adjacent to SR-2 30 09-Feb-14 A 10-Mar-14 A 655 M3 A10490, A1330, A1340, A1400, A1410A9950

A1330 Resolution of expropriation of Fuel Station (SR-2 CH 1+140) 0 28-Feb-14 A 0 0 A10490 A6800, A9940

A1340 Resolution of expropriation of Graveyard (SR-2 CH 0+900) 0 28-Feb-14 A 0 0 A10490 A6800, A9940

A1400 Resolution of expropriation of Al-Falaj Shopping (SR-2 CH 0+380) 0 28-Feb-14 A 0 0 A10490 A6800, A9940

A1410 Resolution of expropriation of Shopping Buildings (SR-2 CH 0+300) 0 28-Feb-14 A 0 0 A10490 A6800, A9940

A9950 Placing Plastic Barriers 5 11-Mar-14 A 15-Mar-14 A 0 0 A9940 A10340

A10340 Shift Traffic from Existing Southern Service Road Temp. SR-2 0 15-Mar-14 A 0 0 A9950 A9910

TEMPORARY DIVERSION FOR EXISTING HIGHWAY - SOUTH BOUNDTEMPORARY DIVERSION FOR EXISTING HIGHWAY - SOUTH BOUND 96 25-Jan-14 A 30-Apr-14 764

SOL1-SOUTH (CH 25+300 to CH 21+100)SOL1-SOUTH (CH 25+300 to CH 21+100) 96 25-Jan-14 A 30-Apr-14 764

GENERALGENERAL 96 25-Jan-14 A 30-Apr-14 764

A10500 Protection of services 15 25-Jan-14 A 05-Mar-14 A 0 0 A10490, A10470 A9910, A10660

A10660 Extension of Existing Drainage under Highway 30 01-Feb-14 A 10-Mar-14 A A10500 A10670

A9910 Laying of Asphalt on Temp. Road Adjacent to SOL-1 SB over SOLs 4&7 35 09-Feb-14 A 23-Apr-14 764 M3 A10340, A10500, A10670, A999A9920

A10470 Construction of Falaj Under Temp Diversion 27 10-Mar-14 A 05-Apr-14 A A10500

A10670 Repairs due to Heavy Rainfalls on the 26/27 of March 2014 15 31-Mar-14 A 15-Apr-14 A10660 A9910

A9920 Placing Plastic Barriers 7 24-Apr-14 30-Apr-14 0 0 A9910 A9930

A9930 Shift Traffic from Existing Main Road SB to Temp. diversion 0 30-Apr-14 0 0 A9920, A6700 A2940, A2800, A2660, A4000, A1360, A4100, A1450, A5020, A11780

INVESTIGATIONINVESTIGATION 45 29-Dec-13 A 11-Feb-14 A 0

GEOTECHNICAL INVESTIGATIONGEOTECHNICAL INVESTIGATION 45 29-Dec-13 A 11-Feb-14 A 0

GENERALGENERAL 45 29-Dec-13 A 11-Feb-14 A 0

A6110 Site Survey 10 29-Dec-13 A 07-Jan-14 A 0 0 A6680 A6120

A6120 Setting up Drilling Rigs 7 08-Jan-14 A 14-Jan-14 A 0 0 A6110 A6130, A1540, A3160, A6140

A6130 Execution of Trial Pits 7 15-Jan-14 A 21-Jan-14 A 0 0 A6120 A6140

A6140 Execution of Boreholes 15 15-Jan-14 A 29-Jan-14 A 0 0 A6130, A6120 A6150

A6150 (SPT) Test 5 30-Jan-14 A 03-Feb-14 A 0 0 A6140 A6160

A6160 Submission of Prelim. Laboratory Testing Report Submission 4 04-Feb-14 A 07-Feb-14 A 0 0 A6150 A6170

A6170 Receipt Confirmation of Pile Length from Engineer 4 08-Feb-14 A 11-Feb-14 A A6160 A1540

GENERAL CIVIL WORKSGENERAL CIVIL WORKS 174 09-May-14 29-Oct-14 11743

CLEARING & EXCAVATIONCLEARING & EXCAVATION 174 09-May-14 29-Oct-14 11743

GENERALGENERAL 174 09-May-14 29-Oct-14 11743

A5310 Clearing & Grubbing 30 09-May-14 07-Jun-14 4259 M2 A1010 A5320, A11850

A5320 Removal of Structures & Obstructures 60 23-May-14 21-Jul-14 1 LS A5310 A5330, A6030

A5330 Utilities Trench Ear thworks 60 22-Jul-14 19-Sep-14 1641 M3 A5320 A5340, A1450

A5340 Structural & Road Way Excavation 100 22-Jul-14 29-Oct-14 5842 M3 A5330 A4580, A5090, A11740

UTILITIESUTILITIES 105 27-Jul-14 08-Nov-14 19317

GENERALGENERAL 105 27-Jul-14 08-Nov-14 19317

FUTURE DUCTS - STAGE 1FUTURE DUCTS - STAGE 1 90 27-Jul-14 24-Oct-14 5117

A11740 Install Electrical Ducts 60 27-Jul-14 24-Sep-14 3854 LM A5340 A11750

A11750 Install Water Ducts 30 05-Sep-14 04-Oct-14 216 LM A11740 A11760

A11760 Install Irrigation Ducts 30 15-Sep-14 14-Oct-14 807 LM A11750 A11770

A11770 Install Telephone Ducst 30 25-Sep-14 24-Oct-14 240 LM A11760 A5030

TELEPHONETELEPHONE 85 11-Aug-14 03-Nov-14 2200

A1450 Installation of New (GTO) Omantal Line 50 11-Aug-14 29-Sep-14 1100 0 A5330, A6590, A9930 A1455, A1360, A1335, A1280

A1455 Obtain Shutdown & Connect to Existing 15 30-Sep-14 14-Oct-14 0 0 A1450 A1457

A1457 Remove & Dispose Existing (GTO) Omantal Line 20 15-Oct-14 03-Nov-14 1100 0 A1455 A5030

ELECTRICAL (11 KV)ELECTRICAL (11 KV) 90 11-Aug-14 08-Nov-14 6400

J J J J J J J J J

2014 2015 2016

Extension of Existing Drainage under Highway

Construction of Falaj Under Temp. DiversionRepairs due to Heavy Rainfalls on the 26/27 of March 2014

Placing of Plastic BarriersShift Traffic from Existing Main Road NB to Temp. diversion

15-Mar-14 A, TEMPORARY DIVERSION FOR EXIST

15-Mar-14 A, SR2 (CH 0+000 to CH 1+450)

15-Mar-14 A, GENERAL

Protection of services

Laying of Asphalt Adjacent to SR-2Resolution of expropriation of Fuel Station (SR-2 CH 1+140)

Resolution of expropriation of Graveyard (SR-2 CH 0+900)

Resolution of expropriation of Al-Falaj Shopping (SR-2 CH 0+380)

Resolution of expropriation of Shopping Buildings (SR-2 CH 0+300)

Placing Plastic BarriersShift Traffic from Existing Southern Service Road Temp. SR-2

30-Apr-14, TEMPORARY DIVERSION FOR EXIST

30-Apr-14, SOL1-SOUTH (CH 25+300 to CH 21+100)

30-Apr-14, GENERAL

Protection of servicesExtension of Existing Drainage under Highway

Laying of Asphalt on Temp. Road Adjacent to SOL-1

Construction of Falaj Under Temp DiversionRepairs due to Heavy Rainfalls on the 26/27 of March 2014

Placing Plastic BarriersShift Traffic from Existing Main Road SB to Temp. diversion

11-Feb-14 A, INVESTIGATION

11-Feb-14 A, GEOTECHNICAL INVESTIGATION

11-Feb-14 A, GENERAL

Site Survey

Setting up Drilling Rigs

Execution of Trial Pits

Execution of Boreholes

(SPT) Test

Submission of Prelim. Laboratory Testing Report Submission

Receipt Confirmation of Pile Length from Engineer29-Oct-14, GENERAL CIVIL WORKS

29-Oct-14, CLEARING & EXCAVATION

29-Oct-14, GENERAL

Clearing & Grubbing

Removal of Structures & Obstructures

Utilities Trench Ear thworks

Structural & Road Way Excavation08-Nov-14, UTILITIES

08-Nov-14, GENERAL

24-Oct-14, FUTURE DUCTS - STAGE 1

Install Electrical Ducts

Install Water Ducts

Install Irrigation Ducts

Install Telephone Ducst

03-Nov-14, TELEPHONE

Installation of New (GTO) Omantal Line

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing (GTO) Omantal Line08-Nov-14, ELECTRICAL (11 KV)

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 5 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 6: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A1360 Installation of New 11 Kv Overhead Lines 40 11-Aug-14 19-Sep-14 3000 0 A1450, A6530, A9930 A1365, A1376

A1365 Obtain Shutdown & Connect to Existing 15 20-Sep-14 04-Oct-14 0 0 A1360 A1367

A1367 Remove & Dispose Existing 11 Kv Overhead Lines 25 05-Oct-14 29-Oct-14 400 0 A1365 A1376, A1315

A1376 Remove & Dispose Existing 11 Kv Under Ground Lines 25 15-Oct-14 08-Nov-14 3000 0 A1367, A1360 A5030

ELECTRICAL (33 KV)ELECTRICAL (33 KV) 35 15-Sep-14 19-Oct-14 400

A1335 Obtain Shutdown & Connect to Existing 20 15-Sep-14 04-Oct-14 0 0 A1450 A1315

A1315 Remove & Dispose Existing 33 Kv Ovehead Lines 15 05-Oct-14 19-Oct-14 400 0 A1367, A1335 A1300

WATERLINESWATERLINES 82 19-Aug-14 08-Nov-14 5200

A1280 Installation of Water Pipe 60 19-Aug-14 17-Oct-14 2600 0 A1450 A1290

A1290 Obtain Shutdown & Connect to Existing 15 18-Oct-14 01-Nov-14 0 0 A1280 A1300

A1300 Remove & Dispose Existing Irrigation Pipes 7 02-Nov-14 08-Nov-14 2600 0 A1290, A1315 A5030

BOX CULVERTS - STAGE 1BOX CULVERTS - STAGE 1 235 21-May-14 10-Jan-15 31860

GENERALGENERAL 235 21-May-14 10-Jan-15 31860

3 CELL BOX CULVERT AT CH 21+2603 CELL BOX CULVERT AT CH 21+260 29 16-Sep-14 14-Oct-14 1109

A11780 Structural Excavation 3 16-Sep-14 18-Sep-14 117 M3 A9930, A2720, A12520 A11790

A11790 Blinding of Concrete 1 19-Sep-14 19-Sep-14 11 M3 A11780 A11800

A11800 Casting of Base Slab 6 20-Sep-14 25-Sep-14 95 M3 A11790 A11810

A11810 Casting of Walls 12 26-Sep-14 07-Oct-14 190 M3 A11800 A11820, A11830

A11830 Casting of Apron Slab & W ing Walls 10 05-Oct-14 14-Oct-14 30 M3 A11810 A11840

A11820 Casting of Top Slab 6 08-Oct-14 13-Oct-14 95 M3 A11810 A11840

A11840 Backfilling 1 14-Oct-14 14-Oct-14 571 M3 A11820, A11830 A2240

1 CELL BOX CULVERT AT CH 21+4851 CELL BOX CULVERT AT CH 21+485 83 15-Oct-14 05-Jan-15 866

A2240 Structural Excavation 2 15-Oct-14 16-Oct-14 117 M3 A10810, A11840 A2250

A2250 Blinding of Concrete 1 17-Oct-14 17-Oct-14 11 M3 A2240 A2260

A2260 Casting of Base Slab 4 18-Oct-14 21-Oct-14 38 M3 A2250 A2270

A2270 Casting of Walls 8 22-Oct-14 29-Oct-14 76 M3 A2260 A2280

A2280 Casting of Top Slab 4 30-Oct-14 02-Nov-14 38 M3 A2270 A2290, A2300

A2300 Casting of Apron Slab & W ing Walls 4 03-Nov-14 06-Nov-14 15 M3 A2280 A2290

A2290 Backfilling 1 05-Jan-15 05-Jan-15 571 M3 A2280, A2300, A2710 A5350, A2500

8 CELLS BOX CULVERT AT CH 21+8388 CELLS BOX CULVERT AT CH 21+838 109 24-Sep-14 10-Jan-15 3539

A2870 Structural Excavation 6 24-Sep-14 29-Sep-14 351 M3 A3000, A10890 A2880

A2880 Blinding of Concrete 4 28-Sep-14 01-Oct-14 46 M3 A2870 A2890

A2890 Casting of Base Slab 18 30-Sep-14 17-Oct-14 199 M3 A2880 A2900

A2900 Casting of Walls 32 14-Oct-14 14-Nov-14 398 M3 A2890 A2910

A2910 Casting of Top Slab 18 11-Nov-14 28-Nov-14 199 M3 A2900 A2920, A2930

A2930 Casting of Apron Slab & W ing Walls 22 29-Nov-14 20-Dec-14 60 M3 A2910 A2920, A5170

A2920 Backfilling 4 07-Jan-15 10-Jan-15 2286 M3 A2910, A2930, A2570 A5350

44 CELLS BOX CULVERT AT CH 21+98544 CELLS BOX CULVERT AT CH 21+985 135 21-May-14 02-Oct-14 16278

A2940 Structural Excavation 16 21-May-14 05-Jun-14 1110 M3 A1010, A9930, A10630, A11560A2950

A2950 Blinding of Concrete 14 21-May-14 03-Jun-14 194 M3 A2940 A2960

A2960 Casting of Base Slab 80 26-May-14 13-Aug-14 2016 M3 A2950 A2970

A2970 Casting of Walls 77 13-Jun-14 28-Aug-14 4032 M3 A2960 A2980

A2980 Casting of Top Slab 79 29-Jun-14 15-Sep-14 2016 M3 A2970 A2990, A3000

A3000 Casting of Apron Slab & W ing Walls 51 04-Aug-14 23-Sep-14 624 M3 A2980 A2990, A2870

A2990 Backfilling 9 24-Sep-14 02-Oct-14 6286 M3 A2980, A3000 A5350

9 CELLS BOX CULVERT AT CH 22+6509 CELLS BOX CULVERT AT CH 22+650 68 23-May-14 29-Jul-14 4135

A2800 Structural Excavation 6 23-May-14 28-May-14 351 M3 A1010, A9930, A10650 A2810, A2660

A2810 Blinding of Concrete 4 27-May-14 30-May-14 46 M3 A2800 A2820

A2820 Casting of Base Slab 18 29-May-14 15-Jun-14 336 M3 A2810 A2830

A2830 Casting of Walls 32 12-Jun-14 13-Jul-14 672 M3 A2820 A2840, A2860

A2860 Casting of Apron Slab & W ing Walls 22 08-Jul-14 29-Jul-14 108 M3 A2830 A2850

A2840 Casting of Top Slab 18 10-Jul-14 27-Jul-14 336 M3 A2830 A2850

A2850 Backfilling 4 26-Jul-14 29-Jul-14 2286 M3 A2840, A2860 A5350, A2640, A2660

5 CELLS BOX CULVERT AT CH 23+5005 CELLS BOX CULVERT AT CH 23+500 48 30-Jul-14 15-Sep-14 2563

J J J J J J J J J

2014 2015 2016

Installation of New 11 Kv Overhead Lines

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing 11 Kv Overhead Lines

Remove & Dispose Existing 11 Kv Under19-Oct-14, ELECTRICAL (33 KV)

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing 33 Kv Ovehead Lines08-Nov-14, WATERLINES

Installation of Water Pipe

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing Irrigation Pipes10-Jan-15, BOX CULVERTS - STAGE 1

10-Jan-15, GENERAL

14-Oct-14, 3 CELL BOX CULVERT AT CH 21+260

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Apron Slab & W ing Walls

Casting of Top Slab

Backfilling

05-Jan-15, 1 CELL BOX CULVERT AT CH 21+485

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling10-Jan-15, 8 CELLS BOX CULVERT

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling02-Oct-14, 44 CELLS BOX CULVERT AT CH 21+985

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling29-Jul-14, 9 CELLS BOX CULVERT AT CH 22+650

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Apron Slab & W ing Walls

Casting of Top Slab

Backfilling15-Sep-14, 5 CELLS BOX CULVERT AT CH 23+500

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 6 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 7: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A2660 Structural Excavation 5 30-Jul-14 03-Aug-14 292 M3 A9930, A1010, A10710, A2800, A2850A2670

A2670 Blinding of Concrete 1 04-Aug-14 04-Aug-14 11 M3 A2660 A2680

A2680 Casting of Base Slab 8 05-Aug-14 12-Aug-14 258 M3 A2670 A2690

A2690 Casting of Walls 14 11-Aug-14 24-Aug-14 517 M3 A2680 A2700

A2700 Casting of Top Slab 8 25-Aug-14 01-Sep-14 258 M3 A2690 A2710, A2720

A2720 Casting of Apron Slab & W ing Walls 14 02-Sep-14 15-Sep-14 84 M3 A2700 A2710, A2590, A11780

A2710 Backfilling 2 14-Sep-14 15-Sep-14 1143 M3 A2700, A2720 A5350, A2290

1 CELLS BOX CULVERT AT CH 23+7601 CELLS BOX CULVERT AT CH 23+760 43 16-Sep-14 28-Oct-14 831

A2590 Structural Excavation 2 16-Sep-14 17-Sep-14 117 M3 A2720, A10690 A2600

A2600 Blinding of Concrete 1 18-Sep-14 18-Sep-14 11 M3 A2590 A2610

A2610 Casting of Base Slab 4 19-Sep-14 22-Sep-14 30 M3 A2600 A2620

A2620 Casting of Walls 8 23-Sep-14 30-Sep-14 60 M3 A2610 A2630, A2650

A2630 Casting of Top Slab 4 01-Oct-14 04-Oct-14 30 M3 A2620 A2650

A2650 Casting of Apron Slab & W ing Walls 4 05-Oct-14 08-Oct-14 12 M3 A2620, A2630 A2640, A2380

A2640 Backfilling 1 28-Oct-14 28-Oct-14 571 M3 A2650, A2850 A5350, A2430

1 CELL BOX CULVERT AT CH 23+9971 CELL BOX CULVERT AT CH 23+997 20 09-Oct-14 28-Oct-14 831

A2380 Structural Excavation 2 09-Oct-14 10-Oct-14 117 M3 A2650, A10770 A2390

A2390 Blinding of Concrete 1 11-Oct-14 11-Oct-14 11 M3 A2380 A2400

A2400 Casting of Base Slab 4 12-Oct-14 15-Oct-14 30 M3 A2390 A2410

A2410 Casting of Walls 8 16-Oct-14 23-Oct-14 60 M3 A2400 A2420, A2440

A2420 Casting of Top Slab 4 24-Oct-14 27-Oct-14 30 M3 A2410 A2430

A2440 Casting of Apron Slab & W ing Walls 4 25-Oct-14 28-Oct-14 12 M3 A2410 A2430, A2450

A2430 Backfilling 1 28-Oct-14 28-Oct-14 571 M3 A2440, A2420, A2640 A5350

1 CELL BOX CULVERT AT CH 24+2351 CELL BOX CULVERT AT CH 24+235 70 29-Oct-14 06-Jan-15 854

A2450 Structural Excavation 2 29-Oct-14 30-Oct-14 117 M3 A2440, A10850 A2460

A2460 Blinding of Concrete 1 31-Oct-14 31-Oct-14 11 M3 A2450 A2470

A2470 Casting of Base Slab 4 01-Nov-14 04-Nov-14 30 M3 A2460 A2480

A2480 Casting of Walls 8 05-Nov-14 12-Nov-14 60 M3 A2470 A2490, A2510

A2490 Casting of Top Slab 4 13-Nov-14 16-Nov-14 30 M3 A2480 A2500

A2510 Casting of Apron Slab & W ing Walls 4 14-Nov-14 17-Nov-14 35 M3 A2480 A2500, A2520

A2500 Backfilling 1 06-Jan-15 06-Jan-15 571 M3 A2490, A2510, A2290 A5350, A2570

1 CELL BOX CULVERT AT CH 24+5701 CELL BOX CULVERT AT CH 24+570 50 18-Nov-14 06-Jan-15 854

A2520 Structural Excavation 2 18-Nov-14 19-Nov-14 117 M3 A2510, A10870 A2530

A2530 Blinding of Concrete 1 20-Nov-14 20-Nov-14 11 M3 A2520 A2540

A2540 Casting of Base Slab 5 21-Nov-14 25-Nov-14 30 M3 A2530 A2550

A2550 Casting of Walls 8 26-Nov-14 03-Dec-14 60 M3 A2540 A2560, A2580

A2560 Casting of Top Slab 5 04-Dec-14 08-Dec-14 30 M3 A2550 A2570

A2580 Casting of Apron Slab & W ing Walls 4 06-Dec-14 09-Dec-14 35 M3 A2550 A2570, A5170

A2570 Backfilling 1 06-Jan-15 06-Jan-15 571 M3 A2560, A2580, A2500 A5350, A2920

PEDESTRIAN UNDERPASS 1 (SOL1 CH 22+800) - STAGE 1PEDESTRIAN UNDERPASS 1 (SOL1 CH 22+800) - STAGE 1 94 28-Jun-14 29-Sep-14 4405

GENERALGENERAL 94 28-Jun-14 29-Sep-14 4405

UNDERPASS STRUCTUREUNDERPASS STRUCTURE 94 28-Jun-14 29-Sep-14 4405

A11850 Structural Excavation 5 28-Jun-14 02-Jul-14 584 M3 A5310, A12540 A11860

A11860 Blinding of Concrete 6 02-Jul-14 07-Jul-14 26 M3 A11850 A11870

A11870 Casting of Base Slab 18 11-Jul-14 28-Jul-14 93 M3 A11860 A11880

A11880 Casting of Walls 35 01-Aug-14 04-Sep-14 180 M3 A11870 A11890

A11890 Casting of Top Slab 30 27-Aug-14 25-Sep-14 93 M3 A11880 A11900, A1795

A11900 Backfilling 4 26-Sep-14 29-Sep-14 3429 M3 A11890 A5050

PEDESTRIAN UNDERPASS 2 (SOL1 CH 23+300) - STAGE 1PEDESTRIAN UNDERPASS 2 (SOL1 CH 23+300) - STAGE 1 129 26-Sep-14 01-Feb-15 4286

GENERALGENERAL 129 26-Sep-14 01-Feb-15 4286

UNDERPASS STRUCTUREUNDERPASS STRUCTURE 129 26-Sep-14 01-Feb-15 4186

A1795 Structural Excavation 10 26-Sep-14 05-Oct-14 584 M3 A10910, A11890 A1800

A1800 Blinding of Concrete 12 29-Sep-14 10-Oct-14 33 M3 A1795 A1810

A1810 Casting of Base Slab 35 08-Oct-14 11-Nov-14 35 M3 A1800 A1820, A11950

J J J J J J J J J

2014 2015 2016

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling28-Oct-14, 1 CELLS BOX CULVERT AT CH 23+760

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling28-Oct-14, 1 CELL BOX CULVERT AT CH 23+997

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling06-Jan-15, 1 CELL BOX CULVERT AT CH 24+235

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling06-Jan-15, 1 CELL BOX CULVERT AT CH 24+570

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling29-Sep-14, PEDESTRIAN UNDERPASS 1

29-Sep-14, GENERAL

29-Sep-14, UNDERPASS STRUCTURE

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Backfilling

01-Feb-15, PEDESTRIAN UNDERP

01-Feb-15, GENERAL

01-Feb-15, UNDERPASS STRUCTURE

Structural Excavation

Blinding of Concrete

Casting of Base Slab

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 7 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 8: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A1820 Casting of Walls 70 29-Oct-14 06-Jan-15 70 M3 A1810 A1830

A1830 Casting of Top Slab 50 08-Dec-14 26-Jan-15 35 M3 A1820 A3010

A3010 Backfilling 6 27-Jan-15 01-Feb-15 3429 M3 A1830 A5350

ENTRANCE & EXIT - RHSENTRANCE & EXIT - RHS 77 08-Oct-14 23-Dec-14 100

A11950 Casting of Floor Slab 22 08-Oct-14 29-Oct-14 10 M3 A1810 A11960

A11960 Casting of Walls 35 30-Oct-14 03-Dec-14 30 M3 A11950 A11980, A11970

A11970 Casting of Landing Slabs & Stair Case 35 19-Nov-14 23-Dec-14 50 M3 A11960 A11980

A11980 Casing of Beams & Roof Slab 20 04-Dec-14 23-Dec-14 10 M3 A11960, A11970 A5370

FLYOVER AT FALAJ AL QABIL (NORTH BOUND)FLYOVER AT FALAJ AL QABIL (NORTH BOUND) 347 12-Mar-14 A 27-Feb-15 72649

SUBSTRUCTURESSUBSTRUCTURES 185 12-Mar-14 A 18-Sep-14 68830

PIER P3PIER P3 58 07-Apr-14 A 03-Jun-14 1756

A1540 Boring & Casting of Piles 14 07-Apr-14 A 15-Apr-14 225 LM A6500, A1010, A6120, A11010, A6170A1550, A5020, A3260

A1550 Blinding for Pier Pile Cap 3 16-Apr-14 18-Apr-14 10 M3 A1540 A1560, A3260

A1560 Casting of Pier Pile Cap 15 19-Apr-14 03-May-14 170 M3 A1550 A1570

A1570 Bituminous Paint 3 04-May-14 06-May-14 1221 M2 A1560, A11530 A1580

A1580 Casting of Pier & Pier Cap 28 07-May-14 03-Jun-14 130 M3 A1570 A1640, A3500

PIER P5PIER P5 60 19-Apr-14 17-Jun-14 1756

A3260 Boring & Casting of Piles 11 19-Apr-14 29-Apr-14 225 LM A11050, A1540, A1550 A3270, A1590

A3270 Blinding for Pier Pile Cap 3 30-Apr-14 02-May-14 10 M3 A3260 A3280

A3280 Casting of Pier Pile Cap 15 03-May-14 17-May-14 170 M3 A3270 A3290

A3290 Bituminous Paint 3 18-May-14 20-May-14 1221 M2 A3280 A3300

A3300 Casting of Pier & Pier Cap 28 21-May-14 17-Jun-14 130 M3 A3290 A3500

ABUTMENT AB1ABUTMENT AB1 61 02-May-14 01-Jul-14 29674

A1590 Boring & Casting of Piles 5 02-May-14 06-May-14 115 LM A11070, A1010, A3260 A1600, A3310, A3360

A1600 Blinding for Abutment Pile Cap 7 07-May-14 13-May-14 5 M3 A1590 A1610, A3030

A3030 Fixing of MSE Wall 46 07-May-14 21-Jun-14 0 M2 A1600 A3110, A3410

A1610 Casting of Abutment Pile Cap 42 14-May-14 24-Jun-14 420 M3 A1600 A1620, A1640

A3110 Backfilling 46 17-May-14 01-Jul-14 26286 M3 A3030 A5350, A1620

A1620 Bituminous Paint 7 25-Jun-14 01-Jul-14 2848 M2 A1610, A3110 A5170, A1650

ABUTMENT AB2ABUTMENT AB2 64 07-May-14 09-Jul-14 29749

A3360 Boring & Casting of Piles 5 07-May-14 11-May-14 115 LM A11090, A1590 A3370, A3160

A3370 Blinding for Abutment Pile Cap 7 12-May-14 18-May-14 80 M3 A3360 A3380, A3410

A3410 Fixing of MSE Wall 46 12-May-14 26-Jun-14 0 M2 A3370, A3030 A3420

A3380 Casting of Abutment Pile Cap 42 19-May-14 29-Jun-14 420 M3 A3370 A3390, A3500

A3420 Backfilling 46 22-May-14 06-Jul-14 26286 M3 A3410 A5350, A3390

A3390 Bituminous Paint 7 03-Jul-14 09-Jul-14 2848 M2 A3380, A3420 A5170, A3500

PIER P2PIER P2 60 12-May-14 10-Jul-14 1756

A3160 Boring & Casting of Piles 11 12-May-14 22-May-14 225 LM A6500, A6120, A1010, A10990, A11480, A3360A3170, A3210

A3170 Blinding for Pier Pile Cap 3 23-May-14 25-May-14 10 M3 A3160 A3180

A3180 Casting of Pier Pile Cap 15 26-May-14 09-Jun-14 170 M3 A3170 A3190

A3190 Bituminous Paint 3 10-Jun-14 12-Jun-14 1221 M2 A3180 A3200

A3200 Casting of Pier & Pier Cap 28 13-Jun-14 10-Jul-14 130 M3 A3190 A1640

PIER P1PIER P1 60 23-May-14 21-Jul-14 1756

A3210 Boring & Casting of Piles 11 23-May-14 02-Jun-14 225 LM A10970, A3160 A3220, A4000

A3220 Blinding for Pier Pile Cap 3 03-Jun-14 05-Jun-14 10 M3 A3210 A3230

A3230 Casting of Pier Pile Cap 15 06-Jun-14 20-Jun-14 170 M3 A3220 A3240

A3240 Bituminous Paint 3 21-Jun-14 23-Jun-14 1221 M2 A3230 A3250

A3250 Casting of Pier & Pier Cap 28 24-Jun-14 21-Jul-14 130 M3 A3240 A1640

Falaj RelocationFalaj Relocation 125 12-Mar-14 A 20-Jul-14 627

A11630 Section 1 - Inside Existing Roundabout 45 LM 32 12-Mar-14 A 20-Apr-14 120 M3 A999 A11670, A11720

A11670 Section 5 - RHS (Between Existing Service Roads) - 24 LM 24 10-Apr-14 A 07-May-14 64 M3 A11630 A11640, A11660, A11690, A11720

A11660 Section 4 - LHS(Between Diversion - Existing Service Road) - 55 LM 38 20-Apr-14 28-May-14 146 M3 A11670 A11680, A11720

A11640 Section 2 - LHS (Between Diversion - Existing Service Road) -40 LM 28 08-May-14 04-Jun-14 106 M3 A11670 A11650, A11690, A11720

A11650 Section 3 - RHS (Between Diversion - Roundabout) - 32 LM 25 18-May-14 11-Jun-14 85 M3 A11640 A11720

J J J J J J J J J

2014 2015 2016

Casting of Walls

Casting of Top Slab

Backfilling23-Dec-14, ENTRANCE & EXIT - RHS

Casting of Floor Slab

Casting of Walls

Casting of Landing Slabs & Stair Case

Casing of Beams & Roof Slab

27-Feb-15, FLYOVER AT FALAJ A

18-Sep-14, SUBSTRUCTURES

03-Jun-14, PIER P3

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

Bituminous Paint

Casting of Pier & Pier Cap17-Jun-14, PIER P5

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

Bituminous Paint

Casting of Pier & Pier Cap01-Jul-14, ABUTMENT AB1

Boring & Casting of Piles

Blinding for Abutment Pile Cap

Fixing of MSE Wall

Casting of Abutment Pile Cap

Backfilling

Bituminous Paint09-Jul-14, ABUTMENT AB2

Boring & Casting of Piles

Blinding for Abutment Pile Cap

Fixing of MSE Wall

Casting of Abutment Pile Cap

Backfilling

Bituminous Paint10-Jul-14, PIER P2

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

Bituminous Paint

Casting of Pier & Pier Cap21-Jul-14, PIER P1

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

Bituminous Paint

Casting of Pier & Pier Cap20-Jul-14, Falaj Relocation

Section 1 - Inside Existing Roundabout 45 LM

Section 5 - RHS (Between Existing Service Roads) - 24 LM

Section 4 - LHS(Between Diversion - Existing Ser

Section 2 - LHS (Between Diversion - Existing Se

Section 3 - RHS (Between Diversion - Roundabout) - 32 LM

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 8 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 9: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A11690 Section 7 - RHS(Under Service Road) - 10 LM 20 18-May-14 06-Jun-14 26 M3 A11640, A11670 A11700, A11720

A11680 Section 6 - LHS (Under Service Road) - 15 LM 22 07-Jun-14 28-Jun-14 40 M3 A11660, A11700 A11720

A11700 Section 8 - (Under Service Road) - 15 LM 22 07-Jun-14 28-Jun-14 40 M3 A11690 A11680, A11720

A11720 Shifting Water in New Falaj 15 29-Jun-14 13-Jul-14 A11700, A11690, A11680, A11670, A11660, A11650, A11640, A11630A11730, A10580

A11730 Demolition & Removal of Existing Falaj 7 14-Jul-14 20-Jul-14 A11720, A10580 A3310

PIER P4PIER P4 60 21-Jul-14 18-Sep-14 1756

A3310 Boring & Casting of Piles 11 21-Jul-14 31-Jul-14 225 LM A1590, A11030, A11730 A3320, A4050

A3320 Blinding for Pier Pile Cap 3 01-Aug-14 03-Aug-14 10 M3 A3310 A3330

A3330 Casting of Pier Pile Cap 15 04-Aug-14 18-Aug-14 170 M3 A3320 A3340

A3340 Bituminous Paint 3 19-Aug-14 21-Aug-14 1221 M2 A3330 A3350

A3350 Casting of Pier & Pier Cap 28 22-Aug-14 18-Sep-14 130 M3 A3340 A3500

SUPERSTRUCTURESUPERSTRUCTURE 173 22-Jul-14 10-Jan-15 3660

SPAN BETWEEN AB1 & P3SPAN BETWEEN AB1 & P3 114 22-Jul-14 12-Nov-14 1830

A1640 Erection of Scaffold & Shutter 55 22-Jul-14 14-Sep-14 0 0 A3250, A1580, A1610, A3200, A6470, A11250A1650

A1650 Fixing of Pot Bearings 7 15-Sep-14 21-Sep-14 12 NO. A1640, A1620 A1660

A1660 Casting of Box Girder 21 22-Sep-14 12-Oct-14 1818 M3 A1650 A1670

A1670 Prestressing Operation 10 13-Oct-14 22-Oct-14 0 0 A1660, A6620 A6760, A6790, A4550

A6760 Deshuttering of Scaffold 21 23-Oct-14 12-Nov-14 0 0 A1670 A3850

SPAN BETWEEN AB2 & P3SPAN BETWEEN AB2 & P3 114 19-Sep-14 10-Jan-15 1830

A3500 Erection of Scaffold & Shutter 55 19-Sep-14 12-Nov-14 0 0 A1580, A3300, A3380, A3350, A6470, A11270, A3390A3510

A3510 Fixing of Pot Bearings 7 13-Nov-14 19-Nov-14 12 NO. A3500 A3520

A3520 Casting of Box Girder 21 20-Nov-14 10-Dec-14 1818 M3 A3510 A3530

A3530 Prestressing Operation 10 11-Dec-14 20-Dec-14 0 0 A3520 A3570, A4550

A3570 Deshuttering of Scaffold 21 21-Dec-14 10-Jan-15 0 0 A3530, A10610 A4310

FINISHING WORKSFINISHING WORKS 61 29-Dec-14 27-Feb-15 159

GENERALGENERAL 61 29-Dec-14 27-Feb-15 159

A4550 Concrete Bridge Parapet (N.J Barrier) 22 29-Dec-14 19-Jan-15 100 M A6290, A3530, A1670, A5080, A11620A4560

A4560 Laying of Bituminous Wearing Course 6 14-Jan-15 19-Jan-15 0 0 A4550 A4570, A5450, A5430

A4570 Fixing of Expansion Joints 30 29-Jan-15 27-Feb-15 59 M A4560 A3940

FLYOVER AT FALAJ AL QABIL (SOUTH BOUND)FLYOVER AT FALAJ AL QABIL (SOUTH BOUND) 331 03-Jun-14 29-Apr-15 72849

SUBSTRUCTURESSUBSTRUCTURES 119 03-Jun-14 29-Sep-14 68278

PIER P2PIER P2 60 03-Jun-14 01-Aug-14 1756

A4000 Boring & Casting of Piles 11 03-Jun-14 13-Jun-14 225 LM A9930, A11130, A3210 A4010, A3800

A4010 Blinding for Pier Pile Cap 3 14-Jun-14 16-Jun-14 10 M3 A4000 A4020

A4020 Casting of Pier Pile Cap 15 17-Jun-14 01-Jul-14 170 M3 A4010 A4030

A4030 Bituminous Paint 3 02-Jul-14 04-Jul-14 1221 M2 A4020 A4040, A4310

A4040 Casting of Pier & Pier Cap 28 05-Jul-14 01-Aug-14 130 M3 A4030 A4310, A3790

ABUTMENT AB1ABUTMENT AB1 64 14-Jun-14 16-Aug-14 29749

A3800 Boring & Casting of Piles 5 14-Jun-14 18-Jun-14 115 LM A4000, A11210 A3810, A3950

A3810 Blinding for Abutment Pile Cap 7 19-Jun-14 25-Jun-14 80 M3 A3800 A3820, A4150

A4150 Fixing of MSE Wall 46 19-Jun-14 03-Aug-14 0 M2 A3810 A4160

A3820 Casting of Abutment Pile Cap 45 26-Jun-14 09-Aug-14 420 M3 A3810 A3830, A4310

A4160 Backfilling 46 29-Jun-14 13-Aug-14 26286 M3 A4150 A5350

A3830 Bituminous Paint 7 10-Aug-14 16-Aug-14 2848 M2 A3820 A5170, A4310, A4310

PIER P5PIER P5 60 19-Jun-14 17-Aug-14 1756

A3950 Boring & Casting of Piles 11 19-Jun-14 29-Jun-14 225 LM A3800, A11190 A3960, A4100

A3960 Blinding for Pier Pile Cap 3 30-Jun-14 02-Jul-14 10 M3 A3950 A3970

A3970 Casting of Pier Pile Cap 15 03-Jul-14 17-Jul-14 170 M3 A3960 A3980

A3980 Bituminous Paint 3 18-Jul-14 20-Jul-14 1221 M2 A3970 A3990, A4310

A3990 Casting of Pier & Pier Cap 28 21-Jul-14 17-Aug-14 130 M3 A3980 A3850

PIER P3PIER P3 60 30-Jun-14 28-Aug-14 1756

A4100 Boring & Casting of Piles 11 30-Jun-14 10-Jul-14 225 LM A11150, A9930, A3950 A4110, A3750

A4110 Blinding for Pier Pile Cap 3 11-Jul-14 13-Jul-14 10 M3 A4100 A4120

A4120 Casting of Pier Pile Cap 15 14-Jul-14 28-Jul-14 170 M3 A4110 A4130

J J J J J J J J J

2014 2015 2016

Section 7 - RHS(Under Service Road) - 10 LM

Section 6 - LHS (Under Service Road) - 15 LM

Section 8 - (Under Service Road) - 15 LM

Shifting Water in New Falaj

Demolition & Removal of Existing Falaj

18-Sep-14, PIER P4

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

Bituminous Paint

Casting of Pier & Pier Cap10-Jan-15, SUPERSTRUCTURE

12-Nov-14, SPAN BETWEEN AB1 & P3

Erection of Scaffold & Shutter

Fixing of Pot Bearings

Casting of Box Girder

Prestressing Operation

Deshuttering of Scaffold10-Jan-15, SPAN BETWEEN AB2 & P3

Erection of Scaffold & Shutter

Fixing of Pot Bearings

Casting of Box Girder

Prestressing Operation

Deshuttering of Scaffold27-Feb-15, FINISHING WORKS

27-Feb-15, GENERAL

Concrete Bridge Parapet (N.J Barrier)

Laying of Bituminous Wearing Course

Fixing of Expansion Joints29-Apr-15, FLYOVER AT FALAJ

29-Sep-14, SUBSTRUCTURES

01-Aug-14, PIER P2

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

Bituminous Paint

Casting of Pier & Pier Cap16-Aug-14, ABUTMENT AB1

Boring & Casting of Piles

Blinding for Abutment Pile Cap

Fixing of MSE Wall

Casting of Abutment Pile Cap

Backfilling

Bituminous Paint17-Aug-14, PIER P5

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

Bituminous Paint

Casting of Pier & Pier Cap28-Aug-14, PIER P3

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 9 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 10: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A4130 Bituminous Paint 3 29-Jul-14 31-Jul-14 1221 M2 A4120 A4140

A4140 Casting of Pier & Pier Cap 28 01-Aug-14 28-Aug-14 130 M3 A4130 A3850, A4310

PIER P1PIER P1 60 11-Jul-14 08-Sep-14 1756

A3750 Boring & Casting of Piles 11 11-Jul-14 21-Jul-14 225 LM A4100, A11110 A3760, A4170

A3760 Blinding for Pier Pile Cap 3 22-Jul-14 24-Jul-14 10 M3 A3750 A3770

A3770 Casting of Pier Pile Cap 15 25-Jul-14 08-Aug-14 170 M3 A3760 A3780

A3780 Bituminous Paint 3 09-Aug-14 11-Aug-14 1221 M2 A3770 A3790

A3790 Casting of Pier & Pier Cap 28 12-Aug-14 08-Sep-14 130 M3 A3780, A4040 A4310

ABUTMENT AB2ABUTMENT AB2 64 22-Jul-14 23-Sep-14 29749

A4170 Boring & Casting of Piles 5 22-Jul-14 26-Jul-14 115 LM A11230, A3750 A4180

A4180 Blinding for Abutment Pile Cap 7 27-Jul-14 02-Aug-14 80 M3 A4170 A4190, A4220

A4220 Fixing of MSE Wall 46 27-Jul-14 10-Sep-14 0 M2 A4180 A4230

A4190 Casting of Abutment Pile Cap 45 03-Aug-14 16-Sep-14 420 M3 A4180 A4200, A3850

A4230 Backfilling 46 06-Aug-14 20-Sep-14 26286 M3 A4220 A5350

A4200 Bituminous Paint 7 17-Sep-14 23-Sep-14 2848 M2 A4190 A5170, A3850

PIER P4PIER P4 60 01-Aug-14 29-Sep-14 1756

A4050 Boring & Casting of Piles 11 01-Aug-14 11-Aug-14 225 LM A11170, A3310 A4060

A4060 Blinding for Pier Pile Cap 3 12-Aug-14 14-Aug-14 10 M3 A4050 A4070

A4070 Casting of Pier Pile Cap 15 15-Aug-14 29-Aug-14 170 M3 A4060 A4080

A4080 Bituminous Paint 3 30-Aug-14 01-Sep-14 1221 M2 A4070 A4090

A4090 Casting of Pier & Pier Cap 28 02-Sep-14 29-Sep-14 130 M3 A4080 A3850

SUPERSTRUCTURESUPERSTRUCTURE 133 13-Nov-14 25-Mar-15 3660

SPAN BETWEEN AB2 & P3SPAN BETWEEN AB2 & P3 114 13-Nov-14 06-Mar-15 1830

A3850 Erection of Scaffold & Shutter 55 13-Nov-14 06-Jan-15 0 0 A4140, A4090, A6760, A4190, A3990, A6470, A11290, A4200A3860

A3860 Fixing of Pot Bearings 7 07-Jan-15 13-Jan-15 12 NO. A3850 A3870

A3870 Casting of Box Girder 21 14-Jan-15 03-Feb-15 1818 M3 A3860 A3880

A3880 Prestressing Operation 10 04-Feb-15 13-Feb-15 0 0 A3870 A6770, A3920

A6770 Deshuttering of Scaffold 21 14-Feb-15 06-Mar-15 0 0 A3880 A6790

SPAN BETWEEN AB1 & P3SPAN BETWEEN AB1 & P3 114 02-Dec-14 25-Mar-15 1830

A4310 Erection of Scaffold & Shutter 55 02-Dec-14 25-Jan-15 0 0 A4040, A3570, A4140, A3790, A3820, A6470, A11500, A3830, A4030, A3830, A3980A4320

A4320 Fixing of Pot Bearings 7 26-Jan-15 01-Feb-15 12 NO. A4310 A4330

A4330 Casting of Box Girder 21 02-Feb-15 22-Feb-15 1818 M3 A4320 A4340

A4340 Prestressing Operation 10 23-Feb-15 04-Mar-15 0 0 A4330 A6790, A3920

A6790 Deshuttering of Scaffold 21 05-Mar-15 25-Mar-15 0 0 A4340, A1670, A6770 A6710

FINISHING WORKSFINISHING WORKS 41 20-Mar-15 29-Apr-15 911

GENERALGENERAL 41 20-Mar-15 29-Apr-15 911

A3920 Concrete Bridge Parapet (N.J Barrier) 24 20-Mar-15 12-Apr-15 860 M A6290, A3880, A4340, A11620A3930

A3930 Laying of Bituminous Wearing Course 12 07-Apr-15 18-Apr-15 0 0 A3920 A3940, A5490, A9900

A3940 Fixing of Expansion Joints 11 19-Apr-15 29-Apr-15 51 M A3930, A4570 A6710, A9900

MSE WALL (RAMPS OF FLYOVER)MSE WALL (RAMPS OF FLYOVER) 265 28-May-14 16-Feb-15 10167

MSE RWs & RAMPS OF FLYOVERMSE RWs & RAMPS OF FLYOVER 265 28-May-14 16-Feb-15 10167

GENERALGENERAL 265 28-May-14 16-Feb-15 10167

A5020 Excavation to Reduce Level 80 28-May-14 15-Aug-14 0 0 A1540, A6320, A11330, A9930A5030

A5030 Preparation of Foundations 160 27-Jun-14 03-Dec-14 0 0 A5020, A1457, A1376, A1300, A11770A5040

A5040 Installing & Bracing of MSE Wall Panels 190 04-Jul-14 09-Jan-15 8800 M2 A5030 A5050

A5050 Place & Compact Selected Fill up 190 08-Jul-14 13-Jan-15 0 0 A5040, A11900 A5060

A5060 Connect & Tighten Soil Reinforcement 190 13-Jul-14 18-Jan-15 0 0 A5050 A5070

A5070 Place & Compact Random Backfill 190 23-Jul-14 28-Jan-15 0 0 A5060, A11590 A5080, A4580

A5080 Casting of Coping Beam 200 01-Aug-14 16-Feb-15 1367 M3 A5070 A4550, A5370

ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 249 26-Aug-14 01-May-15 9331

GENERALGENERAL 249 26-Aug-14 01-May-15 9331

CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 189 26-Aug-14 02-Mar-15 9331

A4580 Trench for Low Voltage Cables 160 26-Aug-14 01-Feb-15 7097 M A5340, A5070 A4590

A4590 Laying of Ducts 160 02-Sep-14 08-Feb-15 2054 M A4580 A4600

J J J J J J J J J

2014 2015 2016

Bituminous Paint

Casting of Pier & Pier Cap08-Sep-14, PIER P1

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

Bituminous Paint

Casting of Pier & Pier Cap23-Sep-14, ABUTMENT AB2

Boring & Casting of Piles

Blinding for Abutment Pile Cap

Fixing of MSE Wall

Casting of Abutment Pile Cap

Backfilling

Bituminous Paint29-Sep-14, PIER P4

Boring & Casting of Piles

Blinding for Pier Pile Cap

Casting of Pier Pile Cap

Bituminous Paint

Casting of Pier & Pier Cap25-Mar-15, SUPERSTRUCTURE

06-Mar-15, SPAN BETWEEN AB2 & P3

Erection of Scaffold & Shutter

Fixing of Pot Bearings

Casting of Box Girder

Prestressing Operation

Deshuttering of Scaffold25-Mar-15, SPAN BETWEEN AB1 & P3

Erection of Scaffold & Shutter

Fixing of Pot Bearings

Casting of Box Girder

Prestressing Operation

Deshuttering of Scaffold29-Apr-15, FINISHING WORKS

29-Apr-15, GENERAL

Concrete Bridge Parapet (N.J Barrier)

Laying of Bituminous Wearing Course

Fixing of Expansion Joints16-Feb-15, MSE WALL (RAMPS OF FLYOVER)

16-Feb-15, MSE RWs & RAMPS OF FLYOVER

16-Feb-15, GENERAL

Excavation to Reduce Level

Preparation of Foundations

Installing & Bracing of MSE Wall Panels

Place & Compact Selected Fill up

Connect & Tighten Soil Reinforcement

Place & Compact Random Backfill

Casting of Coping Beam01-May-15, ROAD LIGHTING &

01-May-15, GENERAL

02-Mar-15, CIVIL WORKS & CABLING

Trench for Low Voltage Cables

Laying of Ducts

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 10 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 11: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A4600 Laying of Cables 160 09-Sep-14 15-Feb-15 0 0 A4590 A4610

A4620 High Masts Concrete Foundations 90 03-Dec-14 02-Mar-15 0 0 A4610 A4630, A4670

A4610 Lighting Columns Concrete Foundations 90 03-Dec-14 02-Mar-15 180 NO. A4600 A4620, A5350

A4630 Concrete Foundations for Transformer Stations & Feeder Pillars 60 02-Jan-15 02-Mar-15 0 0 A4620 A4640

COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 90 13-Dec-14 12-Mar-15 0

A4670 Fixing of High Masts 90 13-Dec-14 12-Mar-15 0 0 A4620, A6350 A4680

A4680 Fixing of Lighting Poles 90 13-Dec-14 12-Mar-15 0 0 A4670 A5010, A5990

TRANSFORMERS & FEEDER PILLARSTRANSFORMERS & FEEDER PILLARS 110 12-Jan-15 01-May-15 0

A4650 Installation of Feeder Pillar 60 12-Jan-15 12-Mar-15 0 0 A4640 A4660

A4640 33 KV & 11 KV Pad Mounted & Pole Mounted Transformers Substations 60 12-Jan-15 12-Mar-15 0 0 A4630 A4650

A4660 Power Supply Connections to Feeder Pillar 60 03-Mar-15 01-May-15 0 0 A4650 A9460

SLOPE PROTECTION & STABILIZATIONSLOPE PROTECTION & STABILIZATION 100 02-Oct-14 09-Jan-15 19093

RIPRAP, GABIONRIPRAP, GABION 100 02-Oct-14 09-Jan-15 19093

GENERALGENERAL 100 02-Oct-14 09-Jan-15 19093

A5170 Laying of Filter Membrane Fabric for Protection Works 80 02-Oct-14 20-Dec-14 5133 M2 A2580, A2930, A1620, A3390, A3830, A4200A5180

A5180 Fixing of Gabion Cages 90 07-Oct-14 04-Jan-15 2487 M3 A5170 A5190

A5190 Installation of Mortared Stone Riprap 90 07-Oct-14 04-Jan-15 3473 M3 A5180 A5200

A5200 Grouted Stone Ditch Lining 60 11-Nov-14 09-Jan-15 8000 M2 A5190 A5490

DRAINAGE WORKSDRAINAGE WORKS 80 11-Aug-14 29-Oct-14 36197

RC PIPESRC PIPES 80 11-Aug-14 29-Oct-14 36197

GENERALGENERAL 80 11-Aug-14 29-Oct-14 36197

A5090 Trench Excavation Work 60 11-Aug-14 09-Oct-14 1641 M3 A5340 A5100

A5100 Laying of Drainage Pipes (RCC) 60 15-Aug-14 13-Oct-14 250 LM A5090, A6380 A5110

A5110 Construction of Manholes 60 21-Aug-14 19-Oct-14 20 No. A5100 A5120

A5120 Backfilling 60 31-Aug-14 29-Oct-14 34286 M3 A5110 A5350

ROAD FINISHING WORKSROAD FINISHING WORKS 177 04-Nov-14 29-Apr-15 189636

GENERALGENERAL 177 04-Nov-14 29-Apr-15 189636

EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 144 04-Nov-14 27-Mar-15 128077

A5350 Backfilling to Embankment 120 04-Nov-14 03-Mar-15 68571 M3 A4610, A3010, A2990, A2920, A2850, A2640, A2430, A2710, A2290, A2500, A2570, A3420, A4230, A3110, A4160, A5120A5370

A5370 Preparation of Granular Subbase 110 20-Nov-14 09-Mar-15 18355 M3 A5350, A5080, A11980 A5380

A5380 Preparation of Aggregate Base Course 120 28-Nov-14 27-Mar-15 41151 M3 A5370 A5390, A5430

MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 157 13-Nov-14 18-Apr-15 42833

A5390 Installation of Precast Concrete Curbs 150 13-Nov-14 11-Apr-15 15393 M A5380 A5400

A5400 Installation of Concrete Barriers 150 13-Nov-14 11-Apr-15 6600 M A5390, A6290, A11620 A5410

A5410 Installation of Interlocking Tiles 150 20-Nov-14 18-Apr-15 20840 M2 A5400 A5450

NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 82 01-Feb-15 23-Apr-15 17242

A5430 Bituminous Base Course 75 01-Feb-15 16-Apr-15 12483 M3 A5380, A4560 A5450

A5450 Bituminous Wearing Course 38 17-Mar-15 23-Apr-15 4759 M3 A5430, A4560, A5410 A5460, A5490, A9900

GUARDRAILS, HIGHWAY SIGNS & ROAD MARKINGGUARDRAILS, HIGHWAY SIGNS & ROAD MARKING 46 15-Mar-15 29-Apr-15 1484

A5460 Fixing of Guardrails 45 15-Mar-15 28-Apr-15 1415 M A5450, A6440 A5470

A5470 Fixing of Highway Signs Single & Multiple Poles 45 15-Mar-15 28-Apr-15 65 NO. A5460, A6410 A5480

A5480 Fixing of Overhead & Gantry Signs 30 30-Mar-15 28-Apr-15 4 NO. A5470 A5490

A5490 Traffic Lines & Road Studs 30 31-Mar-15 29-Apr-15 0 0 A3930, A5450, A5480, A5200A6710, A6100, A9900

SOL2, SOL4, SOL7SOL2, SOL4, SOL7 149 30-Apr-15 25-Sep-15 94223

SHIFT TRAFFIC TO SOL1- SB & TEMP SERVICE ROAD SR-2SHIFT TRAFFIC TO SOL1- SB & TEMP SERVICE ROAD SR-2 7 30-Apr-15 06-May-15 0

Start (CH 25+300) & End (CH 21+100)Start (CH 25+300) & End (CH 21+100) 7 30-Apr-15 06-May-15 0

GENERALGENERAL 7 30-Apr-15 06-May-15 0

A9900 Placing of Plastic Barriers 7 30-Apr-15 06-May-15 0 0 A6710, A5450, A5490, A3930, A3940A6810

A6810 Shift Traffic from Southern & Northeren Temp. Diversions back to new Main Road 0 06-May-15 0 0 A9900 A9650

GENERAL CIVIL WORKSGENERAL CIVIL WORKS 99 10-May-15 16-Aug-15 11159

CLEARING & EXCAVATIONCLEARING & EXCAVATION 99 10-May-15 16-Aug-15 11159

GENERALGENERAL 99 10-May-15 16-Aug-15 11159

A9650 Clearing & Grubbing 30 10-May-15 08-Jun-15 4259 M2 A6810 A9660, A12060, A12130, A11990, A8300

A9660 Removal of Structures & Obstructures 60 12-May-15 11-Jul-15 1 LS A9650 A9670

A9670 Utilities Trench Ear thworks 60 15-May-15 13-Jul-15 1641 M3 A9660 A9680, A7010

J J J J J J J J J

2014 2015 2016

Laying of Cables

High Masts Concrete Foundations

Lighting Columns Concrete Foundations

Concrete Foundations for Transfor12-Mar-15, COLUMNS, HIGH MASTS

Fixing of High Masts

Fixing of Lighting Poles01-May-15, TRANSFORMERS

Installation of Feeder Pillar

33 KV & 11 KV Pad Mounted & Po

Power Supply Connections to Feeder Pillar09-Jan-15, SLOPE PROTECTION &

09-Jan-15, RIPRAP, GABION

09-Jan-15, GENERAL

Laying of Filter Membrane Fabric for P

Fixing of Gabion Cages

Installation of Mortared Stone Riprap

Grouted Stone Ditch Lining29-Oct-14, DRAINAGE WORKS

29-Oct-14, RC PIPES

29-Oct-14, GENERAL

Trench Excavation Work

Laying of Drainage Pipes (RCC)

Construction of Manholes

Backfilling29-Apr-15, ROAD FINISHING WORKS

29-Apr-15, GENERAL

27-Mar-15, EMBANKMENT, SUB

Backfilling to Embankment

Preparation of Granular Subbase

Preparation of Aggregate Base Course18-Apr-15, MEDIAN & SIDEWALK PAVING

Installation of Precast Concrete Curbs

Installation of Concrete Barriers

Installation of Interlocking Tiles23-Apr-15, NEW BITUMINOUS LAYERS

Bituminous Base Course

Bituminous Wearing Course29-Apr-15, GUARDRAILS, HIG

Fixing of Guardrails

Fixing of Highway Signs Single &

Fixing of Overhead & Gantry Signs

Traffic Lines & Road Studs25-Sep-15, SOL2, SOL4, SOL7

06-May-15, SHIFT TRAFFIC T

06-May-15, Start (CH 25+300)

06-May-15, GENERAL

Placing of Plastic BarriersShift Traffic from Southern & No

16-Aug-15, GENERAL CIVIL WORKS

16-Aug-15, CLEARING &

16-Aug-15, GENERAL

Clearing & Grubbing

Removal of Structures & Obstructures

Utilities Trench Ear thworks

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 11 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 12: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A9680 Structural & Road Way Excavation 90 19-May-15 16-Aug-15 5258 M3 A9670 A9390

UTILITIESUTILITIES 52 19-May-15 09-Jul-15 14200

GENERALGENERAL 52 19-May-15 09-Jul-15 14200

TELEPHONETELEPHONE 32 19-May-15 19-Jun-15 2200

A7010 Installation of New (GTO) Omantal Line 12 19-May-15 30-May-15 1100 0 A9670 A7030, A6920, A6960

A7030 Obtain Shutdown & Connect to Existing 15 31-May-15 14-Jun-15 0 0 A7010 A7040

A7040 Remove & Dispose Existing (GTO) Omantal Line 5 15-Jun-15 19-Jun-15 1100 0 A7030 A6960

ELECTRICAL (11 KV)ELECTRICAL (11 KV) 52 19-May-15 09-Jul-15 6400

A6920 Installation of New 11 Kv Overhead Lines 30 19-May-15 17-Jun-15 3000 0 A7010 A6890, A6840, A6960, A6900

A6890 Obtain Shutdown & Connect to Existing 15 18-Jun-15 02-Jul-15 0 0 A6920 A6970

A6970 Remove & Dispose Existing 11 Kv Overhead Lines 7 03-Jul-15 09-Jul-15 400 0 A6890 A6960

A6960 Remove & Dispose Existing 11 Kv Under Ground Lines 5 05-Jul-15 09-Jul-15 3000 0 A6970, A6920, A7040, A7010A6100

ELECTRICAL (33 KV)ELECTRICAL (33 KV) 10 11-Jun-15 20-Jun-15 400

A7290 Obtain Shutdown & Connect to Existing 7 11-Jun-15 17-Jun-15 0 0 A0000 A6900

A6900 Remove & Dispose Existing 33 Kv Ovehead Lines 3 18-Jun-15 20-Jun-15 400 0 A6920, A7290 A6100

WATERLINESWATERLINES 37 24-May-15 29-Jun-15 5200

A6840 Installation of New Irrigation Pipes 25 24-May-15 17-Jun-15 2600 0 A6920 A6850

A6850 Obtain Shutdown & Connect to Existing 15 08-Jun-15 22-Jun-15 0 0 A6840 A6860

A6860 Remove & Dispose Existing Irrigation Pipes 7 23-Jun-15 29-Jun-15 2600 0 A6850

BOX CULVERTS - STAGE 2BOX CULVERTS - STAGE 2 64 10-May-15 12-Jul-15 9864

GENERALGENERAL 64 10-May-15 12-Jul-15 9864

8 CELLS BOX CULVERT AT CH 21+8388 CELLS BOX CULVERT AT CH 21+838 23 10-May-15 01-Jun-15 1601

A11990 Structural Excavation 3 10-May-15 12-May-15 175 M3 A9650 A12000, A7950

A12000 Blinding of Concrete 2 13-May-15 14-May-15 23 M3 A11990 A12010

A12010 Casting of Base Slab 4 15-May-15 18-May-15 50 M3 A12000 A12020

A12020 Casting of Walls 7 19-May-15 25-May-15 100 M3 A12010 A12030

A12030 Casting of Top Slab 5 26-May-15 30-May-15 50 M3 A12020 A12040

A12040 Casting of Apron Slab & W ing Walls 4 27-May-15 30-May-15 60 M3 A12030 A12050, A8090

A12050 Backfilling 2 31-May-15 01-Jun-15 1143 M3 A12040 A9690

44 CELL BOX CULVERT AT CH 21+98544 CELL BOX CULVERT AT CH 21+985 63 11-May-15 12-Jul-15 3513

A12060 Structural Excavation 10 11-May-15 20-May-15 175 M3 A9650 A12070

A12070 Blinding of Concrete 8 21-May-15 28-May-15 23 M3 A12060 A12080

A12080 Casting of Base Slab 15 29-May-15 12-Jun-15 504 M3 A12070 A12090

A12090 Casting of Walls 15 10-Jun-15 24-Jun-15 1008 M3 A12080 A12100

A12100 Casting of Top Slab 13 20-Jun-15 02-Jul-15 504 M3 A12090 A12110

A12110 Casting of Apron Slab & W ing Walls 10 03-Jul-15 12-Jul-15 156 M3 A12100 A12120

A12120 Backfilling 6 07-Jul-15 12-Jul-15 1143 M3 A12110 A9690

9 CELL BOX CULVERT AT CH 22+6509 CELL BOX CULVERT AT CH 22+650 25 31-May-15 24-Jun-15 1704

A8090 Structural Excavation 3 31-May-15 02-Jun-15 175 M3 A12040 A8100

A8100 Blinding of Concrete 2 03-Jun-15 04-Jun-15 23 M3 A8090 A8110

A8110 Casting of Base Slab 4 05-Jun-15 08-Jun-15 84 M3 A8100 A8120

A8120 Casting of Walls 7 09-Jun-15 15-Jun-15 168 M3 A8110 A8130

A8130 Casting of Top Slab 5 16-Jun-15 20-Jun-15 84 M3 A8120 A8140

A8140 Casting of Apron Slab & W ing Walls 4 21-Jun-15 24-Jun-15 27 M3 A8130 A9610, A8150

A8150 Backfilling 2 23-Jun-15 24-Jun-15 1143 M3 A8140 A9690

5 CELL BOX CULVERT AT CH 23+5005 CELL BOX CULVERT AT CH 23+500 25 10-May-15 03-Jun-15 1552

A7950 Structural Excavation 2 10-May-15 11-May-15 117 M3 A11990 A7960

A7960 Blinding of Concrete 1 12-May-15 12-May-15 11 M3 A7950 A7970

A7970 Casting of Base Slab 4 13-May-15 16-May-15 65 M3 A7960 A7980

A7980 Casting of Walls 7 17-May-15 23-May-15 130 M3 A7970 A7990

A7990 Casting of Top Slab 4 24-May-15 27-May-15 65 M3 A7980 A8000

A8000 Casting of Apron Slab & W ing Walls 7 28-May-15 03-Jun-15 21 M3 A7990 A8010, A7600

A8010 Backfilling 2 02-Jun-15 03-Jun-15 1143 M3 A8000 A9690

1 CELL BOX CULVERT AT CH 23+7601 CELL BOX CULVERT AT CH 23+760 13 04-Jun-15 16-Jun-15 747

J J J J J J J J J

2014 2015 2016

Structural & Road Way Excavation09-Jul-15, UTILITIES

09-Jul-15, GENERAL

19-Jun-15, TELEPHONE

Installation of New (GTO) Omantal Line

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing (09-Jul-15, ELECTRICAL (11 KV)

Installation of New 11 Kv Overhead Lines

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing

Remove & Dispose Existing20-Jun-15, ELECTRICAL (33 KV)

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing 329-Jun-15, WATERLINES

Installation of New Irrigation Pipes

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing 12-Jul-15, BOX CULVERTS - STAGE 2

12-Jul-15, GENERAL

01-Jun-15, 8 CELLS BOX CU

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling

12-Jul-15, 44 CELL BOX CU

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling

24-Jun-15, 9 CELL BOX CU

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling03-Jun-15, 5 CELL BOX CUL

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling16-Jun-15, 1 CELL BOX CUL

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 12 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 13: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A7600 Structural Excavation 2 04-Jun-15 05-Jun-15 117 M3 A8000 A7610

A7610 Blinding of Concrete 1 06-Jun-15 06-Jun-15 11 M3 A7600 A7620

A7620 Casting of Base Slab 2 07-Jun-15 08-Jun-15 9 M3 A7610 A7630

A7630 Casting of Walls 3 09-Jun-15 11-Jun-15 18 M3 A7620 A7640, A7670

A7640 Casting of Top Slab 1 12-Jun-15 12-Jun-15 9 M3 A7630 A7690, A7650

A7650 Casting of Apron Slab & W ing Walls 4 13-Jun-15 16-Jun-15 12 M3 A7640 A7660

A7660 Backfilling 1 16-Jun-15 16-Jun-15 571 M3 A7650 A9690

1 CELL BOX CULVERT AT CH 23+9971 CELL BOX CULVERT AT CH 23+997 14 10-Jun-15 23-Jun-15 747

A7670 Structural Excavation 2 10-Jun-15 11-Jun-15 117 M3 A7630 A7680

A7680 Blinding of Concrete 1 12-Jun-15 12-Jun-15 11 M3 A7670 A7690

A7690 Casting of Base Slab 2 13-Jun-15 14-Jun-15 9 M3 A7680, A7640 A7700

A7700 Casting of Walls 3 15-Jun-15 17-Jun-15 18 M3 A7690 A7710

A7710 Casting of Top Slab 1 18-Jun-15 18-Jun-15 9 M3 A7700 A7720

A7720 Casting of Apron Slab & W ing Walls 4 19-Jun-15 22-Jun-15 12 M3 A7710 A7730

A7730 Backfilling 1 23-Jun-15 23-Jun-15 571 M3 A7720 A9690

PEDESTRIAN UNDERPASS 1 (SOL4 CH 00+435) - STAGE 2PEDESTRIAN UNDERPASS 1 (SOL4 CH 00+435) - STAGE 2 138 11-May-15 25-Sep-15 2583

GENERALGENERAL 138 11-May-15 25-Sep-15 2583

UNDERPASS STRUCTUREUNDERPASS STRUCTURE 64 11-May-15 13-Jul-15 2483

A12130 Structural Excavation 10 11-May-15 20-May-15 584 M3 A9650 A12140

A12140 Blinding of Concrete 12 14-May-15 25-May-15 137 M3 A12130 A12150

A12150 Casting of Base Slab 21 20-May-15 09-Jun-15 12 M3 A12140 A12160

A12160 Casting of Walls 21 30-May-15 19-Jun-15 24 M3 A12150 A12170

A12170 Casting of Top Slab 21 20-Jun-15 10-Jul-15 12 M3 A12160 A12180, A12190

A12180 Backfilling 3 11-Jul-15 13-Jul-15 1714 M3 A12170 A9690

ENTRANCE & EXIT - RHSENTRANCE & EXIT - RHS 77 11-Jul-15 25-Sep-15 100

A12190 Casting of Floor Slab 22 11-Jul-15 01-Aug-15 10 M3 A12170 A12200

A12200 Casting of Walls 35 02-Aug-15 05-Sep-15 30 M3 A12190 A12220, A12210

A12210 Casting of Landing Slabs & Stair Case 35 22-Aug-15 25-Sep-15 50 M3 A12200 A12220

A12220 Casing of Beams & Roof Slab 20 06-Sep-15 25-Sep-15 10 0 A12200, A12210 A5920

PEDESTRIAN UNDERPASS 2 (SOL4 CH 00+935) - STAGE 2PEDESTRIAN UNDERPASS 2 (SOL4 CH 00+935) - STAGE 2 127 10-May-15 13-Sep-15 2769

GENERALGENERAL 127 10-May-15 13-Sep-15 2769

UNDERPASS STRUCTUREUNDERPASS STRUCTURE 65 10-May-15 13-Jul-15 2669

A8300 Structural Excavation 8 10-May-15 17-May-15 584 M3 A9650 A7220, A1510

A7220 Blinding of Concrete 7 16-May-15 22-May-15 137 M3 A8300 A7230

A7230 Casting of Base Slab 15 27-May-15 10-Jun-15 59 M3 A7220 A7240

A7240 Casting of Walls 15 11-Jun-15 25-Jun-15 116 M3 A7230 A7250

A7250 Casting of Top Slab 15 26-Jun-15 10-Jul-15 59 M3 A7240 A8310, A12230

A8310 Backfilling 3 11-Jul-15 13-Jul-15 1714 M3 A7250 A9690

ENTRANCE & EXIT - LHSENTRANCE & EXIT - LHS 65 11-Jul-15 13-Sep-15 100

A12230 Casting of Floor Slab 22 11-Jul-15 01-Aug-15 10 M3 A7250 A12240

A12240 Casting of Walls 35 21-Jul-15 24-Aug-15 30 M3 A12230 A12260, A12250

A12250 Casting of Landing Slabs & Stair Case 35 10-Aug-15 13-Sep-15 50 M3 A12240 A12260

A12260 Casing of Beams & Roof Slab 20 25-Aug-15 13-Sep-15 10 M3 A12240, A12250 A5860

ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 56 03-Jun-15 28-Jul-15 1168

GENERALGENERAL 56 03-Jun-15 28-Jul-15 1168

CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 41 03-Jun-15 13-Jul-15 1168

A9390 Trench for Low Voltage Cables 20 03-Jun-15 22-Jun-15 887 M A9680 A9400

A9400 Laying of Ducts 20 10-Jun-15 29-Jun-15 257 M A9390 A9410

A9420 Concrete Foundations for Transformer Stations & Feeder Pillars 30 14-Jun-15 13-Jul-15 0 0 A9430 A9470

A9410 Laying of Cables 20 17-Jun-15 06-Jul-15 0 0 A9400 A9440

A9430 High Masts Concrete Foundations 25 19-Jun-15 13-Jul-15 0 0 A9440 A9420, A9480

A9440 Lighting Columns Concrete Foundations 12 02-Jul-15 13-Jul-15 24 NO. A9410 A9430, A9690

COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 30 29-Jun-15 28-Jul-15 0

A9480 Fixing of High Masts 30 29-Jun-15 28-Jul-15 0 0 A9430 A9490

J J J J J J J J J

2014 2015 2016

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling23-Jun-15, 1 CELL BOX CU

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling25-Sep-15, PEDESTRIA

25-Sep-15, GENERAL

13-Jul-15, UNDERPASS STRUCTURE

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Backfilling

25-Sep-15, ENTRANCE

Casting of Floor Slab

Casting of Walls

Casting of Landing Slab

Casing of Beams & Roof Slab

13-Sep-15, PEDESTRIA

13-Sep-15, GENERAL

13-Jul-15, UNDERPASS STRUCTURE

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Backfilling13-Sep-15, ENTRANCE

Casting of Floor Slab

Casting of Walls

Casting of Landing Slabs

Casing of Beams & Roof Slab

28-Jul-15, ROAD LIGHTIN

28-Jul-15, GENERAL

13-Jul-15, CIVIL WORKS & CABLING

Trench for Low Voltage Cables

Laying of Ducts

Concrete Foundations for T

Laying of Cables

High Masts Concrete Foundations

Lighting Columns Concrete Foundations28-Jul-15, COLUMNS, HIGH MASTS

Fixing of High Masts

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 13 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 14: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A9490 Fixing of Lighting Poles 30 29-Jun-15 28-Jul-15 0 0 A9480 A9730

TRANSFORMERS & FEEDER PILLARSTRANSFORMERS & FEEDER PILLARS 30 24-Jun-15 23-Jul-15 0

A9450 Installation of Feeder Pillar 30 24-Jun-15 23-Jul-15 0 0 A9470 A9460

A9460 Power Supply Connections to Feeder Pillar 30 24-Jun-15 23-Jul-15 0 0 A9450, A4660 A6100

A9470 33 KV & 11 KV Pad Mounted & Pole Mounted Transformers Substations 30 24-Jun-15 23-Jul-15 0 0 A9420 A9450

SLOPE PROTECTION & STABILIZATIONSLOPE PROTECTION & STABILIZATION 55 16-May-15 09-Jul-15 9547

RIPRAP, GABIONRIPRAP, GABION 55 16-May-15 09-Jul-15 9547

GENERALGENERAL 55 16-May-15 09-Jul-15 9547

A9610 Laying of Filter Membrane Fabric for Protection Works 40 16-May-15 24-Jun-15 2567 M2 A8140 A9620

A9620 Fixing of Gabion Cages 45 21-May-15 04-Jul-15 1243 M3 A9610 A9630

A9630 Installation of Mortared Stone Riprap 45 21-May-15 04-Jul-15 1737 M3 A9620 A9640

A9640 Grouted Stone Ditch Lining 30 10-Jun-15 09-Jul-15 4000 M2 A9630 A6740

ROAD FINISHING WORKSROAD FINISHING WORKS 83 12-Jun-15 02-Sep-15 42933

GENERALGENERAL 83 12-Jun-15 02-Sep-15 42933

EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 44 12-Jun-15 25-Jul-15 27648

A9690 Backfilling to Embankment 32 12-Jun-15 13-Jul-15 18286 M3 A9440, A8310, A8150, A7660, A7730, A12120, A12050, A8010, A12180A9710

A9710 Preparation of Granular Subbase 15 04-Jul-15 18-Jul-15 2503 M3 A9690 A9720

A9720 Preparation of Aggregate Base Course 20 06-Jul-15 25-Jul-15 6859 M3 A9710 A9730, A9770

MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 52 13-Jul-15 02-Sep-15 11383

A9730 Installation of Precast Concrete Curbs 50 13-Jul-15 31-Aug-15 5131 M A9720, A9490 A9750

A9750 Installation of Interlocking Tiles 45 20-Jul-15 02-Sep-15 6252 M2 A9730 A6100

NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 17 17-Jul-15 02-Aug-15 3833

A9770 Bituminous Base Course 14 17-Jul-15 30-Jul-15 2330 M3 A9720 A9790

A9790 Bituminous Wearing Course 12 22-Jul-15 02-Aug-15 1503 M3 A9770 A9800, A9830

GUARDRAILS, HIGHWAY SIGNS & ROAD MARKINGGUARDRAILS, HIGHWAY SIGNS & ROAD MARKING 45 24-Jun-15 07-Aug-15 69

A9800 Fixing of Guardrails 45 24-Jun-15 07-Aug-15 0 M A9790 A9810

A9810 Fixing of Highway Signs Single & Multiple Poles 45 24-Jun-15 07-Aug-15 65 NO. A9800 A9820

A9830 Traffic Lines & Road Studs 30 06-Jul-15 04-Aug-15 0 0 A9790 A6100, A1500

A9820 Fixing of Overhead & Gantry Signs 30 09-Jul-15 07-Aug-15 4 NO. A9810 A6100

SERVICE ROADSSERVICE ROADS 77 01-Aug-15 16-Oct-15 34355

SR1, SR2 & SR3SR1, SR2 & SR3 77 01-Aug-15 16-Oct-15 34355

SHIFT TRAFFIC FROM SERVICE ROADS TO NEW SLIP ROADS (SOL 4/5/6/7)SHIFT TRAFFIC FROM SERVICE ROADS TO NEW SLIP ROADS (SOL 4/5/6/7) 4 01-Aug-15 04-Aug-15 0

SR2 - (CH0+0 TO CH1+300) & SR-1(CH0+0 TO CH0+797)SR2 - (CH0+0 TO CH1+300) & SR-1(CH0+0 TO CH0+797) 4 01-Aug-15 04-Aug-15 0

GENERALGENERAL 4 01-Aug-15 04-Aug-15 0

A1500 Placing of Plastic Barriers & Temporary Signs 4 01-Aug-15 04-Aug-15 0 0 A9830 A1510

A1510 Shift Traffic from Existing Southern & Northeren Service Roads to New Main Road 0 04-Aug-15 0 0 A1500, A8300 A6000

GENERAL CIVIL WORKSGENERAL CIVIL WORKS 17 05-Aug-15 21-Aug-15 1421

CLEARING & EXCAVATIONCLEARING & EXCAVATION 17 05-Aug-15 21-Aug-15 1421

GENERALGENERAL 17 05-Aug-15 21-Aug-15 1421

A6000 Clearing & Grubbing 10 05-Aug-15 14-Aug-15 1420 M2 A1510 A6010, A12270

A6010 Removal of Structures & Obstructures 15 07-Aug-15 21-Aug-15 1 LS A6000 A6020

A6020 Road Way Excavation 10 09-Aug-15 18-Aug-15 0 0 A6010 A5950

PEDESTRIAN UNDERPASS 1 (SR2 CH 00+725) - STAGE 3PEDESTRIAN UNDERPASS 1 (SR2 CH 00+725) - STAGE 3 70 05-Aug-15 13-Oct-15 2211

GENERALGENERAL 70 05-Aug-15 13-Oct-15 2211

UNDERPASS STRUCTUREUNDERPASS STRUCTURE 44 05-Aug-15 17-Sep-15 2111

A12270 Structural Excavation 5 05-Aug-15 09-Aug-15 292 M3 A6000 A12280, A12330, A10030

A12280 Blinding of Concrete 5 07-Aug-15 11-Aug-15 57 M3 A12270 A12290

A12290 Casting of Base Slab 12 12-Aug-15 23-Aug-15 12 M3 A12280 A12300

A12300 Casting of Walls 10 24-Aug-15 02-Sep-15 24 M3 A12290 A12310

A12310 Casting of Top Slab 12 03-Sep-15 14-Sep-15 12 M3 A12300 A12320

A12320 Backfilling 3 15-Sep-15 17-Sep-15 1714 M3 A12310 A5830

ENTRANCE & EXIT - LHSENTRANCE & EXIT - LHS 65 10-Aug-15 13-Oct-15 100

A12330 Casting of Floor Slab 22 10-Aug-15 31-Aug-15 10 M3 A12270 A12340

A12340 Casting of Walls 35 20-Aug-15 23-Sep-15 30 M3 A12330 A12360, A12350

A12350 Casting of Landing Slabs & Stair Case 35 09-Sep-15 13-Oct-15 50 M3 A12340 A12360

J J J J J J J J J

2014 2015 2016

Fixing of Lighting Poles23-Jul-15, TRANSFORME

Installation of Feeder Pillar

Power Supply Connections

33 KV & 11 KV Pad Mounte09-Jul-15, SLOPE PROTEC

09-Jul-15, RIPRAP, GABION

09-Jul-15, GENERAL

Laying of Filter Membrane Fa

Fixing of Gabion Cages

Installation of Mortared Stone Riprap

Grouted Stone Ditch Lining02-Sep-15, ROAD FINIS

02-Sep-15, GENERAL

25-Jul-15, EMBANKMENT,

Backfilling to Embankment

Preparation of Granular Subbase

Preparation of Aggregate Base Course02-Sep-15, MEDIAN & S

Installation of Precast Concrete Curbs

Installation of Interlocking Tiles02-Aug-15, NEW BITUMIN

Bituminous Base Course

Bituminous Wearing Course07-Aug-15, GUARDRAILS

Fixing of Guardrails

Fixing of Highway Signs Si

Traffic Lines & Road Studs

Fixing of Overhead & Gantry Signs16-Oct-15, SERVICE ROADS

16-Oct-15, SR1, SR2 & SR3

04-Aug-15, SHIFT TRAFF

04-Aug-15, SR2 - (CH0+0

04-Aug-15, GENERAL

Placing of Plastic Barriers Shift Traffic from Existing S

21-Aug-15, GENERAL CIVIL WORKS

21-Aug-15, CLEARING &

21-Aug-15, GENERAL

Clearing & Grubbing

Removal of Structures & Obstructures

Road Way Excavation13-Oct-15, PEDESTRI

13-Oct-15, GENERAL

17-Sep-15, UNDERPAS

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Backfilling

13-Oct-15, ENTRANC

Casting of Floor Slab

Casting of Walls

Casting of Landing Sla

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 14 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 15: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A12360 Casing of Beams & Roof Slab 20 24-Sep-15 13-Oct-15 10 M3 A12340, A12350 A5940

PEDESTRIAN UNDERPASS 2 (SR2 CH 01+210) - STAGE 3PEDESTRIAN UNDERPASS 2 (SR2 CH 01+210) - STAGE 3 44 10-Aug-15 22-Sep-15 2159

GENERALGENERAL 44 10-Aug-15 22-Sep-15 2159

UNDERPASS STRUCTUREUNDERPASS STRUCTURE 44 10-Aug-15 22-Sep-15 2159

A10030 Structural Excavation 5 10-Aug-15 14-Aug-15 292 M3 A12270 A10040

A10040 Blinding of Concrete 5 12-Aug-15 16-Aug-15 57 M3 A10030 A10050

A10050 Casting of Base Slab 12 17-Aug-15 28-Aug-15 24 M3 A10040 A10060

A10060 Casting of Walls 10 29-Aug-15 07-Sep-15 48 M3 A10050 A10070

A10070 Casting of Top Slab 12 08-Sep-15 19-Sep-15 24 M3 A10060 A10080

A10080 Backfilling 3 20-Sep-15 22-Sep-15 1714 M3 A10070 A5830

ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 45 09-Aug-15 22-Sep-15 888

GENERALGENERAL 45 09-Aug-15 22-Sep-15 888

CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 30 09-Aug-15 07-Sep-15 888

A5950 Trench for Low Voltage Cables 15 09-Aug-15 23-Aug-15 665 M A6020 A5960

A5960 Laying of Ducts 15 14-Aug-15 28-Aug-15 193 M A5950 A5970

A5970 Laying of Cables 15 19-Aug-15 02-Sep-15 0 0 A5960 A5980

A5980 Lighting Columns Concrete Foundations 19 20-Aug-15 07-Sep-15 30 NO. A5970 A5990, A5830

COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 25 29-Aug-15 22-Sep-15 0

A5990 Fixing of Lighting Poles 25 29-Aug-15 22-Sep-15 0 0 A5980, A4680, A6350 A5870

ROAD FINISHING WORKSROAD FINISHING WORKS 47 31-Aug-15 16-Oct-15 27676

GENERALGENERAL 47 31-Aug-15 16-Oct-15 27676

EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 34 31-Aug-15 03-Oct-15 19316

A5830 Backfilling to Embankment 23 31-Aug-15 22-Sep-15 13143 M3 A5980, A10080, A12320 A5860

A5860 Preparation of Aggregate Base Course 18 16-Sep-15 03-Oct-15 6173 M3 A5830, A12260 A5870, A5900

MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 23 19-Sep-15 11-Oct-15 4831

A5870 Installation of Precast Concrete Curbs 20 19-Sep-15 08-Oct-15 2052 M A5860, A5990 A5880

A5880 Installation of Interlocking Tiles 20 22-Sep-15 11-Oct-15 2779 M2 A5870 A6100

NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 18 27-Sep-15 14-Oct-15 3500

A5900 Bituminous Base Course 12 27-Sep-15 08-Oct-15 1997 M3 A5860 A5920

A5920 Bituminous Wearing Course 12 03-Oct-15 14-Oct-15 1503 M3 A5900, A12220 A5930, A5940

HIGHWAY SIGNS & ROAD MARKINGHIGHWAY SIGNS & ROAD MARKING 21 26-Sep-15 16-Oct-15 29

A5930 Fixing of Highway Signs Single & Multiple Poles 20 26-Sep-15 15-Oct-15 29 NO. A5920, A6410 A6100

A5940 Traffic Lines & Road Studs 15 02-Oct-15 16-Oct-15 0 0 A5920, A12360 A6740, A6100

SOHAR-BURAIMI ROADSOHAR-BURAIMI ROAD 470 01-Jul-14 13-Oct-15 130825

MAIN ROADMAIN ROAD 332 01-Jul-14 28-May-15 110535

SOL3 (CH 0+0 to 1+200)SOL3 (CH 0+0 to 1+200) 332 01-Jul-14 28-May-15 110535

GENERAL CIVIL WORKSGENERAL CIVIL WORKS 84 01-Jul-14 22-Sep-14 5736

CLEARING & EXCAVATIONCLEARING & EXCAVATION 84 01-Jul-14 22-Sep-14 5736

GENERALGENERAL 84 01-Jul-14 22-Sep-14 5736

A6030 Clearing & Grubbing 8 01-Jul-14 08-Jul-14 1136 M2 A5320 A6040

A6040 Removal of Structures & Obstructures 15 08-Jul-14 22-Jul-14 1 LS A6030 A6050

A6050 Utilities Trench Excavation & Backfilling 40 15-Jul-14 23-Aug-14 1094 M3 A6040 A6060

A6060 Structural & Road Way Excavation 60 25-Jul-14 22-Sep-14 3505 M3 A6050 A4800, A5130, A1210, A5210

UTILITIESUTILITIES 69 18-Sep-14 25-Nov-14 3000

GENERALGENERAL 69 18-Sep-14 25-Nov-14 3000

TELEPHONETELEPHONE 30 18-Sep-14 17-Oct-14 800

A1210 Installation of New (GTO) Omantal Line 10 18-Sep-14 27-Sep-14 400 0 A6060 A1215, A1100, A1105

A1215 Obtain Shutdown & Connect to Existing 15 28-Sep-14 12-Oct-14 0 0 A1210 A1218

A1218 Remove & Dispose Existing (GTO) Omantal Line 5 13-Oct-14 17-Oct-14 400 0 A1215 A5600

ELECTRICAL (11 KV)ELECTRICAL (11 KV) 30 18-Sep-14 17-Oct-14 1100

A1100 Installation of New 11 Kv Overhead Lines 10 18-Sep-14 27-Sep-14 500 0 A1210, A6530 A1102, A1020

A1102 Obtain Shutdown & Connect to Existing 15 28-Sep-14 12-Oct-14 0 0 A1100 A1105, A1170, A1058, A1105

A1105 Remove & Dispose Existing 11 Kv Overhead Lines 5 13-Oct-14 17-Oct-14 100 0 A1102, A1210, A1102 A1170

A1170 Remove & Dispose Existing 11 Kv Under Ground Lines 2 16-Oct-14 17-Oct-14 500 0 A1105, A1102 A5640, A1065

ELECTRICAL (33 KV)ELECTRICAL (33 KV) 9 17-Nov-14 25-Nov-14 100

J J J J J J J J J

2014 2015 2016

Casing of Beams & Roof Slab

22-Sep-15, PEDESTRIA

22-Sep-15, GENERAL

22-Sep-15, UNDERPAS

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Backfilling22-Sep-15, ROAD LIGH

22-Sep-15, GENERAL

07-Sep-15, CIVIL WORK

Trench for Low Voltage Cables

Laying of Ducts

Laying of Cables

Lighting Columns Concre22-Sep-15, COLUMNS,

Fixing of Lighting Poles16-Oct-15, ROAD FIN

16-Oct-15, GENERAL

03-Oct-15, EMBANKM

Backfilling to Embankment

Preparation of Aggrega11-Oct-15, MEDIAN &

Installation of Precast C

Installation of Interlocking Tiles14-Oct-15, NEW BITU

Bituminous Base Course

Bituminous Wearing Course16-Oct-15, HIGHWAY

Fixing of Highway Sign

Traffic Lines & Road Studs13-Oct-15, SOHAR-BU

28-May-15, MAIN ROAD

28-May-15, SOL3 (CH 0+0 to 1+200)

22-Sep-14, GENERAL CIVIL WORKS

22-Sep-14, CLEARING & EXCAVATION

22-Sep-14, GENERAL

Clearing & Grubbing

Removal of Structures & Obstructures

Utilities Trench Excavation & Backfilling

Structural & Road Way Excavation25-Nov-14, UTILITIES

25-Nov-14, GENERAL

17-Oct-14, TELEPHONE

Installation of New (GTO) Omantal Line

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing (GTO) Omantal Line17-Oct-14, ELECTRICAL (11 KV)

Installation of New 11 Kv Overhead Lines

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing 11 Kv Overhead Lines

Remove & Dispose Existing 11 Kv Under Ground Lines25-Nov-14, ELECTRICAL (33 KV)

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 15 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 16: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

A1065 Obtain Shutdown & Connect to Existing 7 17-Nov-14 23-Nov-14 0 0 A1170 A1058

A1058 Remove & Dispose Existing 33 Kv Ovehead Lines 2 24-Nov-14 25-Nov-14 100 0 A1102, A1065 A5630

WATERLINESWATERLINES 30 18-Sep-14 17-Oct-14 1000

A1020 Installation of New Irrigation Pipes 10 18-Sep-14 27-Sep-14 500 0 A1100, A6560 A1030

A1030 Obtain Shutdown & Connect to Existing 15 28-Sep-14 12-Oct-14 0 0 A1020 A1040

A1040 Remove & Dispose Existing Irrigation Pipes 5 13-Oct-14 17-Oct-14 500 0 A1030 A5500

PEDESTRIAN UNDERPASS 3 (SOL3 CH 00+050) - STAGE 1PEDESTRIAN UNDERPASS 3 (SOL3 CH 00+050) - STAGE 1 214 23-Sep-14 24-Apr-15 4484

GENERALGENERAL 214 23-Sep-14 24-Apr-15 4484

UNDERPASS STRUCTUREUNDERPASS STRUCTURE 128 23-Sep-14 28-Jan-15 4384

A5210 Structural Excavation 10 23-Sep-14 02-Oct-14 584 M3 A10950, A6060 A5220

A5220 Blinding of Concrete 12 26-Sep-14 07-Oct-14 137 M3 A5210 A5230

A5230 Casting of Base Slab 35 03-Oct-14 06-Nov-14 59 M3 A5220 A5240

A5240 Casting of Walls 70 24-Oct-14 01-Jan-15 116 M3 A5230 A5250

A5250 Casting of Top Slab 50 04-Dec-14 22-Jan-15 59 M3 A5240 A5260, A4800, A5270, A12370

A5260 Backfilling 6 23-Jan-15 28-Jan-15 3429 M3 A5250 A5500

ENTRANCE & EXIT - RHSENTRANCE & EXIT - RHS 92 23-Jan-15 24-Apr-15 100

A5270 Casting of Floor Slab 22 23-Jan-15 13-Feb-15 10 M3 A5250 A5280

A5280 Casting of Walls 35 14-Feb-15 20-Mar-15 30 M3 A5270 A5290, A5300

A5300 Casting of Landing Slabs & Stair Case 35 06-Mar-15 09-Apr-15 50 M3 A5280 A5290

A5290 Casing of Beams & Roof Slab 20 05-Apr-15 24-Apr-15 10 M3 A5280, A5300 A6100

EXTENSION OF EXISTING BOX CULVERTSEXTENSION OF EXISTING BOX CULVERTS 43 23-Jan-15 06-Mar-15 1604

GENERALGENERAL 43 23-Jan-15 06-Mar-15 1604

BOX CULVERT AT CH 0+300BOX CULVERT AT CH 0+300 23 23-Jan-15 14-Feb-15 802

A12370 Structural Excavation 2 23-Jan-15 24-Jan-15 117 M3 A5250 A12380

A12380 Blinding of Concrete 1 25-Jan-15 25-Jan-15 11 M3 A12370 A12390

A12390 Casting of Base Slab 4 26-Jan-15 29-Jan-15 22 M3 A12380 A12400

A12400 Casting of Walls 8 30-Jan-15 06-Feb-15 44 M3 A12390 A12410

A12410 Casting of Top Slab 4 07-Feb-15 10-Feb-15 22 M3 A12400 A12430, A12420

A12420 Casting of Apron Slab & W ing Walls 4 11-Feb-15 14-Feb-15 15 M3 A12410 A12430, A12440

A12430 Backfilling 1 14-Feb-15 14-Feb-15 571 M3 A12420, A12410 A5500

BOX CULVERT AT CH 0+500BOX CULVERT AT CH 0+500 20 15-Feb-15 06-Mar-15 802

A12440 Structural Excavation 2 15-Feb-15 16-Feb-15 117 M3 A12420 A12450

A12450 Blinding of Concrete 1 17-Feb-15 17-Feb-15 11 M3 A12440 A12460

A12460 Casting of Base Slab 4 18-Feb-15 21-Feb-15 22 M3 A12450 A12470

A12470 Casting of Walls 8 22-Feb-15 01-Mar-15 44 M3 A12460 A12480, A12490

A12480 Casting of Top Slab 4 02-Mar-15 05-Mar-15 22 M3 A12470 A12500

A12490 Casting of Apron Slab & W ing Walls 4 03-Mar-15 06-Mar-15 15 M3 A12470 A12500

A12500 Backfilling 1 06-Mar-15 06-Mar-15 571 M3 A12490, A12480 A5500

ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 84 04-Dec-14 25-Feb-15 2920

GENERALGENERAL 84 04-Dec-14 25-Feb-15 2920

CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 74 04-Dec-14 15-Feb-15 2920

A4800 Trench for Low Voltage Cables 50 04-Dec-14 22-Jan-15 2218 M A5250, A6060, A6530 A4810

A4810 Laying of Ducts 50 11-Dec-14 29-Jan-15 642 M A4800 A4820

A4820 Laying of Cables 50 18-Dec-14 05-Feb-15 0 0 A4810 A4850

A4850 Lighting Columns Concrete Foundations 30 17-Jan-15 15-Feb-15 60 NO. A4820 A4852

A4852 High Masts Concrete Foundations 30 17-Jan-15 15-Feb-15 0 0 A4850 A4855, A5500

A4855 Concrete Foundations for Transformer Stations & Feeder Pillars 20 27-Jan-15 15-Feb-15 0 0 A4852 A4857, A4890

COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 30 27-Jan-15 25-Feb-15 0

A4890 Fixing of High Masts 30 27-Jan-15 25-Feb-15 0 0 A4855 A4900

A4900 Fixing of Lighting Poles 30 27-Jan-15 25-Feb-15 0 0 A4890 A4860

TRANSFORMERS & FEEDER PILLARSTRANSFORMERS & FEEDER PILLARS 20 06-Feb-15 25-Feb-15 0

A4860 Installation of Feeder Pillar 20 06-Feb-15 25-Feb-15 0 0 A4900 A4870

A4870 Power Supply Connections to Feeder Pillar 20 06-Feb-15 25-Feb-15 0 0 A4860 A4857

A4857 33 KV & 11 KV Pad Mounted & Pole Mounted Transformers Substations 20 06-Feb-15 25-Feb-15 0 0 A4855, A4870 A5640

J J J J J J J J J

2014 2015 2016

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing 33 Kv Ovehead Lines

17-Oct-14, WATERLINES

Installation of New Irrigation Pipes

Obtain Shutdown & Connect to Existing

Remove & Dispose Existing Irrigation Pipes24-Apr-15, PEDESTRIAN UNDE

24-Apr-15, GENERAL

28-Jan-15, UNDERPASS STRUCTURE

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Backfilling24-Apr-15, ENTRANCE & EXIT - RHS

Casting of Floor Slab

Casting of Walls

Casting of Landing Slabs & Stair Case

Casing of Beams & Roof Slab06-Mar-15, EXTENSION OF EXIS

06-Mar-15, GENERAL

14-Feb-15, BOX CULVERT AT CH 0+300

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling

06-Mar-15, BOX CULVERT AT CH 0+500

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Casting of Apron Slab & W ing Walls

Backfilling

25-Feb-15, ROAD LIGHTING & EL

25-Feb-15, GENERAL

15-Feb-15, CIVIL WORKS & CABLING

Trench for Low Voltage Cables

Laying of Ducts

Laying of Cables

Lighting Columns Concrete Foundations

High Masts Concrete Foundations

Concrete Foundations for Transform25-Feb-15, COLUMNS, HIGH MASTS

Fixing of High Masts

Fixing of Lighting Poles25-Feb-15, TRANSFORMERS & F

Installation of Feeder Pillar

Power Supply Connections to Feeder Pillar

33 KV & 11 KV Pad Mounted & Pole

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 16 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 17: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

DRAINAGE WORKSDRAINAGE WORKS 40 08-Oct-14 16-Nov-14 11996

RC PIPESRC PIPES 40 08-Oct-14 16-Nov-14 11996

GENERALGENERAL 40 08-Oct-14 16-Nov-14 11996

A5130 Trench Excavation Work 20 08-Oct-14 27-Oct-14 547 M3 A6060 A5140

A5140 Laying of Drainage Pipes (RCC) 20 13-Oct-14 01-Nov-14 0 0 A5130, A6380 A5150

A5150 Construction of Manholes 20 20-Oct-14 08-Nov-14 20 0 A5140 A5160

A5160 Backfilling 20 28-Oct-14 16-Nov-14 11429 M3 A5150 A5500

ROAD FINISHING WORKSROAD FINISHING WORKS 133 16-Jan-15 28-May-15 80795

GENERALGENERAL 133 16-Jan-15 28-May-15 80795

EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 74 16-Jan-15 30-Mar-15 60026

A5500 Backfilling to Embankment 50 16-Jan-15 06-Mar-15 28571 M3 A4852, A5260, A5160, A12430, A12500, A1040A5510

A5510 Subgrade Preparation 40 05-Feb-15 16-Mar-15 11064 M2 A5500 A5520

A5520 Preparation of Granular Subbase 40 12-Feb-15 23-Mar-15 6674 M3 A5510 A5530

A5530 Preparation of Aggregate Base Course 40 19-Feb-15 30-Mar-15 13717 M3 A5520 A5540

MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 47 07-Mar-15 22-Apr-15 9662

A5540 Installation of Precast Concrete Curbs 40 07-Mar-15 15-Apr-15 4105 M A5530 A5560

A5560 Installation of Interlocking Tiles 40 14-Mar-15 22-Apr-15 5557 M2 A5540 A5570

NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 59 21-Mar-15 18-May-15 11084

A5570 Bituminous Prime Coat 38 21-Mar-15 27-Apr-15 0 0 A5560 A5580

A5580 Bituminous Base Course 38 28-Mar-15 04-May-15 6325 M3 A5570 A5590

A5590 Bituminous Tack Coat 38 04-Apr-15 11-May-15 0 0 A5580 A5600

A5600 Bituminous Wearing Course 38 11-Apr-15 18-May-15 4759 M3 A5590, A1218 A5620

HIGHWAY SIGNS & ROAD MARKINGHIGHWAY SIGNS & ROAD MARKING 20 09-May-15 28-May-15 23

A5620 Fixing of Highway Signs Single & Multiple Poles 15 09-May-15 23-May-15 22 NO. A5600, A6410 A5630

A5630 Fixing of Overhead & Gantry Signs 15 09-May-15 23-May-15 1 NO. A5620, A1058 A5640

A5640 Traffic Lines & Road Studs 10 19-May-15 28-May-15 0 0 A5630, A4857, A1170 A1520, A6730

SURVICE ROADSSURVICE ROADS 138 29-May-15 13-Oct-15 20290

SR2 (CH 1+200 to 1+477.488)SR2 (CH 1+200 to 1+477.488) 138 29-May-15 13-Oct-15 20290

TRAFFIC SHIFTINGTRAFFIC SHIFTING 4 29-May-15 01-Jun-15 0

TO NEW MAIN ROADTO NEW MAIN ROAD 4 29-May-15 01-Jun-15 0

GENERALGENERAL 4 29-May-15 01-Jun-15 0

A1520 Placing of Plastic Barriers & Temporary Signs 4 29-May-15 01-Jun-15 0 0 A5640 A1530

A1530 Shift Traffic from Existing Southern & Northeren Service Roads to New Main Road 0 01-Jun-15 0 0 A1520, A6730 A5790

GENERAL CIVIL WORKSGENERAL CIVIL WORKS 16 02-Jun-15 17-Jun-15 711

CLEARING & EXCAVATIONCLEARING & EXCAVATION 16 02-Jun-15 17-Jun-15 711

GENERALGENERAL 16 02-Jun-15 17-Jun-15 711

A5790 Clearing & Grubbing 5 02-Jun-15 06-Jun-15 710 M2 A1530 A5800, A10190

A5800 Removal of Structures & Obstructures 5 04-Jun-15 08-Jun-15 1 LS A5790 A5820

A5820 Road Way Excavation 12 06-Jun-15 17-Jun-15 0 0 A5800 A4910

PEDESTRIAN UNDERPASS 3 (SR2 CH 01+320) - STAGE 2PEDESTRIAN UNDERPASS 3 (SR2 CH 01+320) - STAGE 2 108 22-Jun-15 07-Oct-15 2769

GENERALGENERAL 108 22-Jun-15 07-Oct-15 2769

UNDERPASS STRUCTUREUNDERPASS STRUCTURE 76 22-Jun-15 05-Sep-15 2669

A10190 Structural Excavation 10 22-Jun-15 01-Jul-15 584 M3 A5790 A10150

A10150 Blinding of Concrete 12 25-Jun-15 06-Jul-15 137 M3 A10190 A10160

A10160 Casting of Base Slab 21 02-Jul-15 22-Jul-15 59 M3 A10150 A10170, A10210

A10170 Casting of Walls 21 23-Jul-15 12-Aug-15 116 M3 A10160 A10180

A10180 Casting of Top Slab 21 13-Aug-15 02-Sep-15 59 M3 A10170 A10200

A10200 Backfilling 3 03-Sep-15 05-Sep-15 1714 M3 A10180 A5650

ENTRANCE & EXIT - LHSENTRANCE & EXIT - LHS 77 23-Jul-15 07-Oct-15 100

A10210 Casting of Floor Slab 22 23-Jul-15 13-Aug-15 10 M3 A10160 A10220

A10220 Casting of Walls 35 14-Aug-15 17-Sep-15 30 M3 A10210 A10230, A10240

A10240 Casting of Landing Slabs & Stair Case 35 03-Sep-15 07-Oct-15 50 M3 A10220 A10230

A10230 Casing of Beams & Roof Slab 20 18-Sep-15 07-Oct-15 10 0 A10220, A10240 A6100, A5780

ROAD LIGHTING & ELECTRICAL INSTALLATIONROAD LIGHTING & ELECTRICAL INSTALLATION 32 28-Jul-15 28-Aug-15 706

GENERALGENERAL 32 28-Jul-15 28-Aug-15 706

J J J J J J J J J

2014 2015 2016

16-Nov-14, DRAINAGE WORKS

16-Nov-14, RC PIPES

16-Nov-14, GENERAL

Trench Excavation Work

Laying of Drainage Pipes (RCC)

Construction of Manholes

Backfilling28-May-15, ROAD FINISHING WORKS

28-May-15, GENERAL

30-Mar-15, EMBANKMENT, SUB

Backfilling to Embankment

Subgrade Preparation

Preparation of Granular Subbase

Preparation of Aggregate Base Course22-Apr-15, MEDIAN & SIDEWALK PAVING

Installation of Precast Concrete Curbs

Installation of Interlocking Tiles18-May-15, NEW BITUMINOUS LAYERS

Bituminous Prime Coat

Bituminous Base Course

Bituminous Tack Coat

Bituminous Wearing Course28-May-15, HIGHWAY SIGNS

Fixing of Highway Signs Single

Fixing of Overhead & Gantry Signs

Traffic Lines & Road Studs13-Oct-15, SURVICE ROADS

13-Oct-15, SR2 (CH 1

01-Jun-15, TRAFFIC SHIFTING

01-Jun-15, TO NEW MAIN ROAD

01-Jun-15, GENERAL

Placing of Plastic Barriers & TShift Traffic from Existing Sout

17-Jun-15, GENERAL CIVIL WORKS

17-Jun-15, CLEARING & EXCAVATION

17-Jun-15, GENERAL

Clearing & Grubbing

Removal of Structures & Obstructures

Road Way Excavation07-Oct-15, PEDESTRI

07-Oct-15, GENERAL

05-Sep-15, UNDERPASS

Structural Excavation

Blinding of Concrete

Casting of Base Slab

Casting of Walls

Casting of Top Slab

Backfilling07-Oct-15, ENTRANC

Casting of Floor Slab

Casting of Walls

Casting of Landing Slab

Casing of Beams & Roof Slab28-Aug-15, ROAD LIGHT

28-Aug-15, GENERAL

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 17 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A

Page 18: Construction Schedule

Activity ID Activity Name OriginalDuration

Start Finish Quantity UnitMeasure

Predecessors Successors

CIVIL WORKS & CABLINGCIVIL WORKS & CABLING 27 28-Jul-15 23-Aug-15 706

A4910 Trench for Low Voltage Cables 12 28-Jul-15 08-Aug-15 532 M A5820, A6530 A4920

A4920 Laying of Ducts 12 02-Aug-15 13-Aug-15 154 M A4910 A4930

A4930 Laying of Cables 12 07-Aug-15 18-Aug-15 0 0 A4920 A4960

A4960 Lighting Columns Concrete Foundations 10 14-Aug-15 23-Aug-15 20 NO. A4930 A5010, A5650

COLUMNS, HIGH MASTSCOLUMNS, HIGH MASTS 10 19-Aug-15 28-Aug-15 0

A5010 Fixing of Lighting Poles 10 19-Aug-15 28-Aug-15 0 0 A4960, A4680, A6350 A5690

ROAD FINISHING WORKSROAD FINISHING WORKS 50 25-Aug-15 13-Oct-15 16104

GENERALGENERAL 50 25-Aug-15 13-Oct-15 16104

EMBANKMENT, SUBBASE & AGGREGATE BASEEMBANKMENT, SUBBASE & AGGREGATE BASE 24 25-Aug-15 17-Sep-15 12361

A5650 Backfilling to Embankment 12 25-Aug-15 05-Sep-15 6857 M3 A4960, A10200 A5660

A5660 Subgrade Preparation 7 01-Sep-15 07-Sep-15 1936 M2 A5650 A5670

A5670 Preparation of Granular Subbase 7 06-Sep-15 12-Sep-15 1168 M3 A5660 A5680

A5680 Preparation of Aggregate Base Course 7 11-Sep-15 17-Sep-15 2400 M3 A5670 A5690

MEDIAN & SIDEWALK PAVINGMEDIAN & SIDEWALK PAVING 10 14-Sep-15 23-Sep-15 1691

A5690 Installation of Precast Concrete Curbs 7 14-Sep-15 20-Sep-15 718 M A5680, A5010 A5710

A5710 Installation of Interlocking Tiles 7 17-Sep-15 23-Sep-15 973 M2 A5690 A5720

NEW BITUMINOUS LAYERSNEW BITUMINOUS LAYERS 22 20-Sep-15 11-Oct-15 2042

A5720 Bituminous Prime Coat 7 20-Sep-15 26-Sep-15 0 0 A5710 A5730

A5730 Bituminous Base Course 7 25-Sep-15 01-Oct-15 1165 M3 A5720 A5740

A5740 Bituminous Tack Coat 7 30-Sep-15 06-Oct-15 0 0 A5730 A5750

A5750 Bituminous Wearing Course 7 05-Oct-15 11-Oct-15 877 M3 A5740 A5760

HIGHWAY SIGNS & ROAD MARKINGHIGHWAY SIGNS & ROAD MARKING 7 07-Oct-15 13-Oct-15 10

A5760 Fixing of Highway Signs Single & Multiple Poles 7 07-Oct-15 13-Oct-15 10 NO. A5750, A6410 A5780

A5780 Traffic Lines & Road Studs 5 09-Oct-15 13-Oct-15 0 0 A5760, A10230 A6100, A6740

J J J J J J J J J

2014 2015 2016

23-Aug-15, CIVIL WORKS & CABLING

Trench for Low Voltage Cables

Laying of Ducts

Laying of Cables

Lighting Columns Concre28-Aug-15, COLUMNS, HIGH MASTS

Fixing of Lighting Poles13-Oct-15, ROAD FIN

13-Oct-15, GENERAL

17-Sep-15, EMBANKME

Backfilling to Embankment

Subgrade Preparation

Preparation of Granular Subbase

Preparation of Aggregate23-Sep-15, MEDIAN & S

Installation of Precast C

Installation of Interlocking Tiles11-Oct-15, NEW BITU

Bituminous Prime Coat

Bituminous Base Course

Bituminous Tack Coat

Bituminous Wearing Course13-Oct-15, HIGHWAY

Fixing of Highway Sign

Traffic Lines & Road Studs

CCC OMAN LLC

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT

Page 18 of 18

Data Date: 13-Apr-14 UPDATES TO CLAUSE 14 PROGRAM

Date Revision Checked Approved

13-Apr-14 FQI - REV2 18 September 2014

12-Oct-14 FQI - REV3

02-Feb-15 FQI - REV3 A