Construction Report December 8, 2009. Projects Track replacement and turf In Progress Walking...

10
Construction Report December 8, 2009

Transcript of Construction Report December 8, 2009. Projects Track replacement and turf In Progress Walking...

Construction Report

December 8, 2009

Projects

• Track replacement and turf In Progress• Walking tracks: Redesign • Water wells January 2010• Bleachers January 2010• Stadium seats January 2010

Projects

• Sheldon ECA In close out

• Early Learning Center In close out

• M. R. Null Middle School Punch list

• KMS Phase II In close out

Maintenance, Operations & Transportation Complex (Support

Services)Property purchasedProgramming resumed/completedSurveys• Design development – final phase• Utility Service• Environmental • Geotechnical

Maintenance, Operations & Transportation Complex (Support

Services)• Corps of Engineers• Wetlands• TIA• DOT• Texas Parks & Wildlife• Utilities• Harris County (permits)• Harris County Flood Control

Maintenance, Operations & Transportation Complex (Support

Services)• Storm water

• Detention

• Historical

• Endangered species

Network Operations Center

ArchitectLand• Programming – final phase• Survey• Geotechnical

Developments

•Update•Projections•Enrollment projections•Future projects•Attendance zones

Elementary #5Architect identifiedEngineer identified• Programming• Initial design review• Plan reuse• Sustainability (HVAC)• Enrollment projection