Graduation project consist of two parts :
The first part include preparing a theoretical research.
The second part includes the
application of the principle in
construction project management.
What is a Project?
A project is a temporary endeavor undertaken to accomplish a unique product or service with a defined start and end point and specific objectives .
PMBOK definition
Project management is the application of knowledge, skills, tools, and techniques applied to project activities in order to meet or exceed stakeholder needs and expectations from a project.
PMBOK definition
The PMI has identified nine topic areas to define The PMI has identified nine topic areas to define the scope of project management knowledge as the scope of project management knowledge as follows:follows:
Project Integration ManagementProject Integration ManagementProject Scope ManagementProject Scope ManagementProject Time ManagementProject Time ManagementProject Cost ManagementProject Cost ManagementProject Quality ManagementProject Quality ManagementProject Human Resource ManagementProject Human Resource ManagementProject Communication ManagementProject Communication ManagementProject Risk ManagementProject Risk ManagementProject Procurement ManagementProject Procurement Management
2
The project The project Consists ofConsists of
11--Ground Floor Ground Floor 263.92 m263.92 m22..
22--First First basementbasement
349.10349.10 mm22..33 - -second second
basementbasement236.28236.28 mm22..
44--EntranceEntrance5m5m22
4
Location:
NablusRafedia
1
Residential Building (Villa)
.
3
Owner:
By Private sector
( individual )
Funded by :
The owner himself
Working day = 8 hours Working days are all days except Fridays and
holidays. The electrical and mechanical work done by sub
contractor. All money paid by New Israeli Shekel (NIS) and the
fixed value of Dollar according to local coin was (1$=4 NIS).
100 (%) Description .
18.6% Excavations
25.7% Concrete works
17.5% Stone works
3.4% Plaster.
5.7% Tiles.
3.2% Blocks
25.9 %Finishing