Construction Project Briefing - transitchicago.com – Installation of track level platforms and...

21
Construction Project Briefing November 13, 2013

Transcript of Construction Project Briefing - transitchicago.com – Installation of track level platforms and...

Construction

Project Briefing

November 13, 2013

Today’s Presentation

• Traction Power - Farwell/Armitage/Hill Substations

• Red Line South Reconstruction Project (Track & Station)

• Bus Hoist Replacement Program

Phase 1 – Forest Glen, South Shops, 77th Street Bus Garage

Phase 2 – Kedzie Bus Garage

Phase 3 – North Park Garage

Phase 4 – Chicago and 103rd Garage

2

Project Title: Traction Power Systems Upgrades and Improvements

Managing Department: Power & Way Construction

Justification of Need: Substation equipment is obsolete and has exceeded its current lifespan

Priority of Project: High

Total Project Budget: $56,918,563.00

Construction Contract Value: $46,684,000.00

Earned to Date: 4%

Percent Change Orders to Construction

Contract: 0%

Percent Time Used to Date: 34.69%

Funding Source: State Capital Program

Estimated Start Date/Estimated Length of

Project: NTP issued September 30, 2012

Designer of Record: Laramore, Douglass and Popham(LDP)

Construction Manager/General Contractor: STV (CM), F.H. Paschen (GC)

Project Manager: Barney Gray (GM); David Heard (PM)

Detailed Overview of Scope:

Construct Three (3) New Traction Power Substations namely, Farwell, Armitage, Hill

Modify Orleans Switch Room

Modify Weed Switch Room

Modify Sedgwick Substation

3

Project Title: Traction Power Systems Upgrades and Improvements

Managing Department: Power & Way Construction

Impact on Customers: 9 Single Tracks, and 6 Reroutes. Street and lane closures around worksites, curtailed

access to resident garages (at Armitage).

Benefit to System: Additional traction power capacity reduced traction power related train defects,

improved reliability for revenue service, and improved safety.

Benefit to Community: Improved safety.

Impact on Accessibility: None.

Estimated # of Jobs Created: 89

Customer Communication Need: Construction Activity Notices will be needed to alert businesses and residents to

weekend, night work and power outages.

Comparable Projects:

• NA

4

Project Title: Traction Power Systems Upgrades and Improvements

Managing Department: Power & Way Construction

Construction Progress

Delay Explanation:

• CDOT OUC reviewing earth retention permit requirements for Armitage. FHP has received OUC permit.

Phase Description Status

Construction Farwell – 1st Floor Concrete Walls have been completed. Installation of rebar and

formwork is continuing for the 2nd Floor Slab with the concrete pour scheduled for mid-

month. Rebar and Formwork for the 2nd Floor Walls is underway with associated

concrete pours scheduled for the end of the month. Site Utility work and Building

Masonry will follow.

Armitage – Installation of track level platforms and cable supports continues. Site work

has begun to regrade and excavate 18 inches in preparation for Earth Retention System

(ERS) installation. CTA Track Structure Column Replacement work will continue into next

year.

Hill – Foundation walls and columns have been completed. 1st Floor Slab Rebar and

Formwork installation are continuing for the concrete pour over the Cable Vault Area. The

Exterior Foundation Walls are being waterproofed and the Transformer Area is currently

being backfilled to prepare for the 1st Floor Transformer Area rebar installation and

concrete pour.

Sedgwick- Cable Support Brackets and Switch Platforms have been installed

ahead of schedule.

Ongoing

5

6

Project Title: Traction Power Systems Upgrades and Improvements

Managing Department: Power & Way Construction

Farwell substation interior with east wall framed

7

Project Title: Traction Power Systems Upgrades and Improvements

Managing Department: Power & Way Construction

Farwell substation 2nd floor rebar installation

Updates are due at noon on

Tuesday, October 15, 2013

8

Project Title: Traction Power Systems Upgrades and Improvements

Managing Department: Power & Way Construction

Hill Substation foundation wall concrete pour

9

Project Title: Traction Power Systems Upgrades and Improvements

Managing Department: Power & Way Construction

Hill Substation 1st floor formwork and rebar installation

Updates are due at noon on

Tuesday, October 15, 2013

10

Project Title: Traction Power Systems Upgrades and Improvements

Managing Department: Power & Way Construction

Armitage Substation excavation and column replacement preparation

Project Title: Red Line South Reconstruction Project

Managing Department: Power & Way Construction

Justification of Need:

The existing ties, rail and track components, as well the underlying ballast and

drainage systems have reached or exceeded their useful life. In addition, this

project is necessary to provide accessibility at all of the Dan Ryan stations and to

improve customer experience at these stations.

Priority of Project: High

Total Project Budget: $425M

Funding Source: RTA/IDOT CTA-2012-LI; City of Chicago TIF

Designer of Record: T.Y. Lin International; TranSystems Corporation

Construction Manager: Parsons Brinckerhoff

Project Manager: Robert Wittmann (GM); Brittany Dyra (PM)

Track Renewal Station Improvements

Construction Contract Value: $220,166,000 $43,875,000

Earned to Date: $178.1M (as of September 15th) $36.6M (as of September 20th)

Percent Change Orders to Construction Contract: (-2.1%) 0.0%

Percent Time Used to Date: 52.2% (as of October) 100.0%

Estimated Start Date/Estimated Length of Project:

Notice To Proceed: October 4, 2012

Substantial Completion: October 24,

2014

Notice To Proceed: December 21, 2012

Substantial Completion: October 6,

2013

General Contractor: Kiewit Infrastructure Co. F.H. Paschen, S. N. Nielsen &

Associates, LLG

11

Project Title: Red Line South Reconstruction Project

Managing Department: Power & Way Construction

Impact on Customers:

The Dan Ryan Red Line branch from Cermak to 95th will be shutdown for 154 days

from May 19th, 2013 to October 20, 2013. There may be single track outages prior to

the line cut to perform preparatory work.

Benefit to System: Reduced maintenance costs; Improved reliability; New infrastructure

Benefit to Community: Improved customer travel times by eliminating slow zones; New elevators at Garfield,

63rd and 87th

Impact on Accessibility: Garfield, 63rd and 87th stations will be accessible.

Estimated # of Jobs Created: 1150

Customer Communication Need:

Preliminary outreach started last fall. A comprehensive outreach plan will be

implemented to ensure all customers clearly understand travel alternatives and

construction impacts.

12

Detailed Overview of Scope:

• The limits of the project are the South subway portal near 16th/Clark on the north to approximately 95th Street on the south and

including portions of the 18th Connector.

• Replacement of deteriorated track components, including new running rail, ties, fasteners, ballast, and drainage improvements.

Structural work includes expansion joint replacement, new waterproofing, concrete repairs. Systems work includes contact rail

replacement, new supplemental negative return, temporary relocation and/or replacement of existing signal and

communications infrastructure.

• Rehabilitation of various architectural, civil, structural, mechanical and electrical elements at eight (8) stations along the Dan

Ryan Red Line branch: Cermak/Chinatown, Sox/35th, 47th, Garfield, 63rd, 69th, 79th, and 87th. This work includes interior and

exterior painting, platform canopy repairs, lighting and window repairs, and station cleaning.

• Construction of new elevators at Garfield, 63rd and 87th stations.

• New railing at the 69th St. bus bridge.

Project Title: Red Line South Reconstruction Project

Managing Department: Power & Way Construction

Construction Progress

Delay Explanation:

• N/A

Phase Description Status

Construction Substantial completion for the track work was achieved on October 20th, 2013.

Substantial completion for the station work was achieved on October 6th, 2013.

Ongoing

13

Project Title: Red Line South Reconstruction Project

Managing Department: Power & Way Construction

14

87th Station

Project Title: Red Line South Reconstruction Project

Managing Department: Power & Way Construction

15

Cermak-Chinatown Station

Project Title: Red Line South Reconstruction Project

Managing Department: Power & Way Construction

16

New Trackwork

Project Title: Bus Hoist Replacement Program

Managing Department: Facilities Construction Justification of Need: The existing bus hoists are beyond their useful life and many are not functioning.:

Priority of Project: High

Construction Phase Phase 1: 77th/SS/

Forest Glen Phase 2: Kedzie Phase 3: North Park

Phase 4:

Chicago/103rd

Bus Hoist Equipment

Contract Value: $1,668,052 $1,163,892 $779,769 $1,066,901

Construction Contract Value: $2,663,345 $3,135,143 $1,869,630 $2,820,651

Value Earned to Date

(Construction and Hoists): $4,133,816 $2,653,521 $1,197,510 $0

Percent Change Orders to

Construction Contract: 25% 0% 0% 0%

Percent Time Used to Date: 95% 80% 50% 0%

Estimated Start and

Completion Date:

NTP 11/21/12

Projected completion

10/18/13.

NTP 3/4/13

Projected completion

12/20/13.

NTP 6/24/13

Projected completion

3/05/14.

NTP 9/10/13

Projected

completion

7/09/14.

Designer of Record: TranSystems Corporation

Contractor Paul Borg Kiewit F.H. Paschen F.H. Paschen

Project Manager: Steve Mascheri (GM); Shawn Riley (PM); Jacobs (CM)

Funding Source: FTA and RTA Grants

17

Detailed Overview of Scope:

Replacement of bus maintenance lifts including drainage, electrical work, and maintenance pads.

Project has been sequenced to mitigate interference to CTA Bus Operations.

Project Title: Bus Hoist Replacement Program – Phase 1

Managing Department: Facilities Construction

Impact on Customers: N/A

Benefit to System: Improved capacity for maintenance facilities and reliable equipment for bus

operations.

Benefit to Community: N/A

Impact on Accessibility: N/A

Estimated # of Jobs Created: 80 (phases 1 thru 4)

Customer Communication Need: N/A

Comparable Projects:

• N/A

18

Project Title: Bus Hoist Replacement Program – Phase 1

Managing Department: Facilities Construction

Construction Progress

Delay Explanation:

Phase 1: Elevation differential in underground drainage has resulted in the requirement to place new drainage lines as

opposed to tying into existing drainage lines

Phase 2: Phase 2 date extended to better accommodate installation of hoists and minimize impact to bus operations.

Phase 3: Phase 3 dates extended to better accommodate installation of hoists and minimize impact to bus operations.

Phase 4: Phase 4 dates extended to better accommodate installation of hoists and minimize impact to bus operations.

Phase Description Status

Phase 1:

Phase 2:

Phase 3:

Phase 4:

Project has been sequenced to minimize impact to Bus Operations and Maintenance.

Forest Glen – 7 lifts installed. Close out in progress. Underground piping repairs are

complete.

South Shops – 4 lifts installed and operational. Close out in progress. Repairs on

4 additional pits underway.

77th Garage – 7 lifts installed. Work at 4 of the 11 remaining pits in progress.

Kedzie Garage – 12 lifts total: 8 lifts installed, working on the last 4 lifts.

Work on the wash pit and inspection pit are in progress.

North Park Garage – 13 lifts total: 5 lifts installed, work ongoing at 4 more lifts.

103rd and Chicago Garages – NTP issued 9/10/13. Contractor mobilizing

Construction

Construction

Construction

Construction

19

20

Project Title: Bus Hoist Replacement Program

Managing Department: Facilities Construction

North Park – Bays 1 – 5 North Park – Bays 6 – 9 Demolition

21

Project Title: Bus Hoist Replacement Program

Managing Department: Facilities Construction

Kedzie – Wash/Inspection Bay Masonry Kedzie – Bays 1 - 4 Demolition