Mainz, 20. May 2019 Johannes Köck, Head of Mobility an Product Construction of „Mainzelbahn“ Best pactices and lessons learned

Transcript of Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons...

Page 1: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

Mainz, 20. May 2019

Johannes Köck, Head of Mobility an Product

Construction of „Mainzelbahn“

Best pactices and lessons learned

Page 2: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

agenda

project profile und description

urban design

citizen participation

220.05.2019

Page 3: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

project-profile

City of Mainzland-use-plan 1999

urban development1992 – 2010

20.05.2019 3

Page 4: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

project-profile

streetcar-network of MVGexisting and planned

20.05.2019 4

Page 5: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

5

Federal Gov. /

state

economic benefit

MVG / MSW

no further increase

of deficit

City of Mainz

no charges on

municipal budget

efficient

PT System

stakeholder

20.05.2019

Page 6: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

aims and pros for the streetcar extension

aims of the network extension

• Further improvement of Public Transport (PT)• Strenghtening of ecomobility• Infrastructure development and urban development• Permanently securing streetcars in Mainz• Neutral economic earnings

pro-arguments for extending the streetcar network, traffic and environment

• Additional passengers in PT• Reduction of car use• Reduction of transit by car and bus• Reduction of parking pressure in the city center• Fully accessible mobility through modern stop-architecture and low-floor-streetcars• Reduction of CO2 emission

20.05.2019 6

Page 7: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

project despriction – “Mainzelbahn“

tight time schedule

• 2009 cost-benefit analysis and preliminary planning

• 2010 beginning of design planning and initiation of citizen participation

• 2012 – 2013 planning approval procedure (application: Jan. 2012, permission: Aug. 2013)

• 2014 start of construction (ground-braeking ceremony: May 2014)

• 2014 – 2016 construction phase

• 2016 opening ceremony and first day of service: 11. Dec. 2016

20.05.2019 7

Page 8: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

project despriction – “Mainzelbahn“

Trend of costs

Estimate 2009 70 Mio.€ Cost calculation 2013 84 Mio.€Cost increase 2018 98 Mio.€ (+15%)

Financing partners

Federal State of Germany share of building costs ~41 Mio.€State of Rhineand-Palatinate share of building costs ~10 Mio.€MVG (own contribution) share of building costs ~25 Mio.€

ancillary building costs ~8 Mio.€

based on cost calculation

20.05.2019 8

Page 9: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

project despriction – “Mainzelbahn“

Important factors of cost increase

• Until cost calculation− Price trend− Adaption of plans

(citizen participation process, …)− New insights (cable network)

• During building− Cables, pibes and cable-pibes− consistency of the soil despite expert‘s reports− Stringent official conditions, approval costs− External influences

20.05.2019 9

Page 10: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

project despriction – “Mainzelbahn“

technical facts

3,3 km1,9 km4,0 km

• length: 9,2 km

• Superstructure- green tracks- combined tram/bus/car- tracks with railway ballast

• max. gradient: 8,0 %

• 3 turn loops

• 15 Stations

• 5 Bridges

• 5 transformer substations

1020.05.2019

Page 11: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

project despriction – “Mainzelbahn“

Urban Design

• New design of:− City entrances− Spaces− Transport areas− Landscapes

• Development through:− Track-design− Buildings− Furnishings− Greenery

→ urban design manual

20.05.2019 11

Page 12: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

project despriction – “Mainzelbahn“

Urban Design

streetcar stop

planning implementation

20.05.2019 12

Page 13: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

citizen participation – initial situation

representative telephone survey (2010) for tram-expansion

majority of citizens support the “Mainzelbahn“ project different acceptance in discricts

positive negative undecided

20.05.2019 13

Page 14: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

citizen participation – initial situation

critical votes at the beginning

“NIMBY-symptom“

• too expensive, wasting public money

• no necessity, uneconomical, harmful to the environment and

cityscape

• it is better to invest in a zero-emission bus service

• health hazard because of airborne noise and surface shaking

• depreciation for neerby properties

→additional specific challenges

20.05.2019 14

Page 15: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

citizen participation – concept

methods of partizipation and communication during the planning phase

• voluntary public participation and information events

• participation and information during the construction liceningprocedure

• offer for talk with politicians, public-administration, business representatives, interest groups, …

• public relation activities

activities in public relation

• “Mainzelbahn“ branding for a positive project image

• developing a internet presence

• print media

20.05.2019 15

Page 16: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

citizen participation – concept

schedule of citizen participation during the planning phase

conception consolidation elaboration

application of the construction licening procedure

Public inspection of the planning area

Citizen information

20.05.2019 16

Page 17: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

citizen participation – workshops

task / challange

• objectification of discussion

• early realization and reduction of conflict situations

• transparency of planning and decision proceses

• confirming acceptance for the project and the project executing company(MVG)

• learn about determing factors in different districts and environments and making the planning better by knowing them

• knowledge about arguments for the construction liceningprocedure

20.05.2019 17

Page 18: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

citizen participation – workshops

dialog between planners, MVG representatives and citizens

requirement / prerequisite

• external moderator

• seperate workshop in every district

• all workshop members discuss in an open and unbiasedway

• no replacement of workshop members → continuity

• no debates on principles

• “what is the best design of the line, when the city council votes for the project“

• citizen participation is not a referendum

20.05.2019 18

Page 19: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

citizen participation – conclusion

• more proximity to citizens

• more quality and sustainability in planning

• synergy between the different methods of communication and participation

• the willingness of the MVG for modification of the planning

• great majority for realising the project in the city council

• only 50 objections during the construction liceningprocedure

• no dispossession although 300 realties were needed

risks

• different political majorities during the project / planningphase

• citizen paticipation leads to a debate of principles

• politicians do not accept the undependence of the citizen participation process

• the project executing company is not willing to compromise on alternatives

20.05.2019 19

Page 20: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation

communication during construction phase

permanent and iterating communication of positive project aspects

tranparent communication about the constuctionprogress

public event when critical milestones were reached

https://www.youtube.com/watch?v=9tMQ6W4PM94

flyer with advantages of “Mainzelbahn“

20.05.2019 20

Page 21: Construction of Mainzelbahn Best pactices and lessons learned€¦ · Best pactices and lessons learned. agenda project profile und description urban design citizen participation