CONSTRUCTION NEWS Issue #15 1 | Page CT DOT Project No. 0092-0522 Construction News ARIAL VIEW OF I-95 NB & SB OVER WEST RIVER BRIDGE Bi-Weekly Project Update August 18, 2014 to August 30, 2014 INTERSTATE IMPACTS: Night time work on I-95 Northbound and Southbound to facilitate bridge and roadway construction. LOCAL ROAD IMPACTS: Daytime construction of Ella T. Grasso Boulevard and Sea Street including drainage. Daytime work for the installation of preload embankments along I-95 SB Exit 45 off- ramp to Ella T. Grasso Boulevard. Daytime work for excavation of new Ramp C to I-95 NB. Daytime work for widening of I-95 SB to Exit 45 in shoulder area. Installation of piles for West River Bridge. Monday - Friday between the hours of 7:00 AM & 4:00 PM. POTENTIAL VIBRATION/NOISE CONSTRUCTION ACTIVITIES: Daytime and nighttime activities that may create vibrations and/or noise are scheduled to occur throughout the period from Monday, August 18, 2014 through Saturday, August 30, 2014. Rehabilitation of Bridge No. 00163A, I-95 over West River and SR 745 in the Towns of West Haven and New Haven. DOT Project No: 0092-0522

Transcript of Construction News - I-95 West River Bridge Project: Home …i95westriver.com/Flyers/August 18 2014...

Page 1: Construction News - I-95 West River Bridge Project: Home …i95westriver.com/Flyers/August 18 2014 to August 30 2014.pdf · CT DOT Project No. 0092-0522 Construction News ... in the

CONSTRUCTION NEWS Issue #15

1 | P a g e CT DOT Project No. 0092-0522

Construction News

ARIAL VIEW OF I-95 NB & SB OVER WEST RIVER BRIDGE

Bi-Weekly Project Update August 18, 2014 to August 30, 2014

INTERSTATE IMPACTS:

Night time work on I-95 Northbound and Southbound to facilitate bridge and roadway construction.

LOCAL ROAD IMPACTS:

Daytime construction of Ella T. Grasso Boulevard and Sea Street including drainage.

Daytime work for the installation of preload embankments along I-95 SB Exit 45 off- ramp to Ella T. Grasso

Boulevard.

Daytime work for excavation of new Ramp C to I-95 NB.

Daytime work for widening of I-95 SB to Exit 45 in shoulder area.

Installation of piles for West River Bridge.

Monday - Friday between the hours of 7:00 AM & 4:00 PM.

POTENTIAL VIBRATION/NOISE CONSTRUCTION ACTIVITIES:

Daytime and nighttime activities that may create vibrations and/or noise are scheduled to occur throughout

the period from Monday, August 18, 2014 through Saturday, August 30, 2014.

Rehabilitation of Bridge No. 00163A, I-95 over West River and SR 745

in the Towns of West Haven and New Haven.

by [Article Author]

DOT Project No: 0092-0522

Page 2: Construction News - I-95 West River Bridge Project: Home …i95westriver.com/Flyers/August 18 2014 to August 30 2014.pdf · CT DOT Project No. 0092-0522 Construction News ... in the

CONSTRUCTION NEWS Issue #15

2 | P a g e CT DOT Project No. 0092-0522

Rehabilitation of Bridge No. 00163A

The West River Bridge is one of the longest and most heavily traveled bridges in the State of

Connecticut. The ConnDOT project will widen the existing bridge from 92 feet wide to 136 feet wide

while maintaining the existing six-lane highway and adding four full-width shoulders.

The presence of full-width highway shoulders allows for fewer lane closures caused by vehicle incidents or police activity. The entire replacement of this bridge and associated improvements in this section of the I-95 corridor is expected to be completed by November 2018.

Major items of work include:

Temporary trestles in the West River for access to pile supported pier locations, erection of structural steel and demolition of the existing bridge

Temporary highway construction to accommodate traffic shifts Reconstructing highway approaches & exit ramps to access Ella Grasso Blvd. & Kimberly Ave. Constructing the new West River bridge piers and superstructure Demolishing the existing West River Bridge Replacing I-95 Bridge over Ella T. Grasso Blvd. Constructing drainage improvements Removing the construction trestle and finger piers

Page 3: Construction News - I-95 West River Bridge Project: Home …i95westriver.com/Flyers/August 18 2014 to August 30 2014.pdf · CT DOT Project No. 0092-0522 Construction News ... in the

CONSTRUCTION NEWS Issue #15

3 | P a g e

CT DOT Project No. 0092-0522

FOR MORE INFORMATION PLEASE VISIT OUR WEBSITE AT WWW.I95WESTRIVER.COM

Below are photos of work performed on the new Exit 45 Interchange.

Taken 7.24.14 and 7.30.14

West trestle, South of I-95 NB

Taken 4.3.14

East trestle, South of I-95 NB

Taken 4.3.14

Construction crew installing vibrating wire & piezometer at soil pre-load area South of I-95 NB

PLA 1… what kind of machine is this?

New pavement for new Exit 45 NB off ramp New pavement installed for Ella T. Grasso Blvd. extension

Concrete Piles prepped for West River Bridge West approach footing.

Page 4: Construction News - I-95 West River Bridge Project: Home …i95westriver.com/Flyers/August 18 2014 to August 30 2014.pdf · CT DOT Project No. 0092-0522 Construction News ... in the

CONSTRUCTION NEWS Issue #15

4 | P a g e CT DOT Project No. 0092-0522

Service Cabinet for traffic signals.

The Connecticut Department of Transportation is working to inform local residents of current and upcoming construction activities through bulletins such as this. For additional information on this project and other projects, please visit the Connecticut Department of Transportation Project website

(www.i95westriver.com). Please feel free to contact [email protected] with any questions, concerns, or to add your contact information to our distribution list.

FOR MORE INFORMATION

Project Contact: George Cooper

Resident Engineer Office: 475-238-8538

Project Contact: Ghazi Alsaqri

CT DOT Project Engineer Office: 475-238-8538