Construction Materials E-Book

download Construction Materials E-Book

of 32

Transcript of Construction Materials E-Book

  • 7/26/2019 Construction Materials E-Book

    1/98

    Go To Contents

  • 7/26/2019 Construction Materials E-Book

    2/98

    Go To Contents

    All rights reserved to Civil EngineeringDepartment Ports, Customs & Free Zone

    Corporation, Dubai. No parts of this

    publication may be reproduced, stored

    in any retrieval system, or transmitted in

    any form or by any means, electronic,

    mechanical, photocopying, recording orotherwise, without the prior consent of

    the copyright owner.

  • 7/26/2019 Construction Materials E-Book

    3/98

    Go To Contents

    CONSTRUCTION MATERIALS

    QUALITY CONTROL GUIDELINES

    Ports, Customs & Free Zone Corporation, DubaiUnited Arab Emirates

  • 7/26/2019 Construction Materials E-Book

    4/98

    2

    Go To Contents

    Al rights reserved to Civil Engineering Department Ports, Customs & Free Zone Corporation, Dubai. No parts of this publication may

    be reproduced, stored in any retrieval system, or transmitted in any form or by any means, electronic, mechanical, photocopying,recording or otherwise, without the prior consent of the copyright owner.

    First Edition-2007

    Construction Materials Quality Control Guidelines

    This edition was issued in March 2007

    Jebel Ali, Dubai, United Arab Emirates

    P.O. Box 17000, Ports, Customs & Free Zone Corporation, DubaiTel.: 00971 4 8819444E-mail: [email protected]://ced.dubaitrade.ae

  • 7/26/2019 Construction Materials E-Book

    5/98

    3

    Go To Contents

    CONSTRUCTIONMATERIALS

    QUALITY

    CONTROL

    GUIDELINES

    First Edition-2007

    Ports, Customs & Free Zone Corporation, DubaiUnited Arab Emirates

  • 7/26/2019 Construction Materials E-Book

    6/98

    4

    Go To Contents

    ACKNOWLEDGEMENT

  • 7/26/2019 Construction Materials E-Book

    7/98

    5

    Go To Contents

    ACKNOWLEDGEMENT

    The publication of this book could not have been possible but

    for the ungrudging efforts put in by the Quality Section of the

    Civil Engineering Department. We would like to acknowledge

    contributions made by Group Internal Audit and Quality

    Director, Nakheel Contracts and Procurement Manager,

    Nakheel Quality Assurance Manager, Concrete Readymix

    Suppliers, Materials Testing laboratories and many engineers

    from different organizations.

    Our thanks go out to all of those who contributed, whether

    through their comments, feedbacks, edits or suggestions.

    As there is always room for improvement, Civil Engineering

    Department welcomes comments on this Book, and will

    consider all that are received. Your comments will continue the

    development of this book leading to its ultimate acceptance.

    As always it has been a great joint effort..

    Nazek Al Sabbagh

    Chief, Civil Engineering Officer

    Ports, Customs & Free Zone Corporation CED

  • 7/26/2019 Construction Materials E-Book

    8/98

    6

    Go To Contents

  • 7/26/2019 Construction Materials E-Book

    9/98

    7

    Go To Contents

    Page

    Chairman Quality Policy Statement-------------------------------------------- 11

    Section 1: Introduction------------------------------------------------------------------ 13

    Section 2: Quality Control (General)----------------------------------------------- 15

    2.01 Quality Policy -------------------------------------------------------- 15

    2.02 Submittals ---------------------------------------------------------------- 15

    2.03 General Quality Control Requirements------------------------------- 16

    2.04 Quality Control Plans--------------------------------------------------- 19

    2.05 Inspection Procedures--------------------------------------------------- 20

    2.06 Inspection and Test Plan------------------------------------------------ 222.07 Document and Submittal Control------------------------------------- 22

    2.08 Identification and Control of Items and Materials------------------- 23

    2.09 Inspections and Tests---------------------------------------------------- 24

    2.10 Measuring and Test Equipment---------------------------------------- 26

    2.11 Non-Conformance Monitoring---------------------------------------- 26

    2.12 Personnel Qualifications------------------------------------------------ 28

    2.13 Quality Control Reports/Audits---------------------------------------- 28

    2.14 Equipment/Material Handling and Storage-------------------------- 29

    2.15 Quality Control Records------------------------------------------------ 292.16 Workmanship------------------------------------------------------------ 30

    2.17 Protection of Property--------------------------------------------------- 31

    2.18 QA/QC Induction Training--------------------------------------------- 32

    Section 3: Recommended Practices Before and During Concreting----- 33

    3.01 Formwork ---------------------------------------------------------------- 33

    3.02 Concrete Consolidation ----------------------------------------------- 33

    3.03 Concreting -------------------------------------------------------------- 333.04 Hot Weather Concreting----------------------------------------------- 34

    Section 4: Schedule of Tests and Inspections-------------------------------- 37

    a. Cast In-Situ Concrete (Ready-Mixed Concrete) ----------------------- 37

    Laboratory and Plant Trial Mixes ------------------------------------ 37

    Concrete Production & Site Deliveries ------------------------------- 39

    Site Laboratories ------------------------------------------------------- 42

    Aggregates ------------------------------------------------------------- 44

    Water --------------------------------------------------------------- 46

    Cementitious Materials and Admixtures ---------------------------- 47

    TABLE OF CONTENTS

  • 7/26/2019 Construction Materials E-Book

    10/98

    8

    Go To Contents

    b. Bored In-Situ Piles & Drilled Shafts ------------------------------------- 48

    c. Reinforcing Steel -------------------------------------------------------- 49

    d. Epoxy-Coated Steel ------------------------------------------------------- 50

    e. Earthwork ------------------------------------------------------------------ 51

    f. Precast Concrete -------------------------------------------------------- 52

    g. Glass Reinforced Cement (GRC) Elements ---------------------------- 53

    h. Blocks ---------------------------------------------------------------------- 54

    Concrete Blocks-------------------------------------------------------- 54

    Autoclaved Aerated Concrete Blocks -------------------------------- 55

    Normal Weight Polystyrene Sandwich Blocks----------------------- 56

    Light Weight Masonry Units ------------------------------------------ 57 Clay Masonry Blocks with Polystyrene Insert ----------------------- 58

    i. Lath and Plaster ----------------------------------------------------------- 59

    j. Polystyrene Thermal Insulation ------------------------------------------ 60

    k. Painting -------------------------------------------------------------------- 61

    Section 5: QC Forms ------------------------------------------------------------- 63

    a. Non-Conformance Report ----------------------------------------------- 63

    b. Status of Non-Conformance Reports ----------------------------------- 64

    c. Field Memorandum ------------------------------------------------------- 65d. Material Inspection Report ----------------------------------------------- 66

    e. Notification of Material Receipt ---------------------------------------- 67

    f. Inspection and Test Plan------------------------------------------------- 68

    g. Concrete Pour Record --------------------------------------------------- 69

    h. Inspection Record for Structural Repairs ------------------------------- 70

    i. Pile Record ----------------------------------------------------------------- 71

    Section 6: QC Checklists -------------------------------------------------------- 73

    Introduction -------------------------------------------------------------------- 73

    a. Pre-Concrete Checklist --------------------------------------------------- 74

    b. Pile Cap -------------------------------------------------------------------- 75

    c. Footings -------------------------------------------------------------------- 76

    d. Tie Beams ------------------------------------------------------------------ 77

    e. Slab on Grade ------------------------------------------------------------ 78

    f. Walls ----------------------------------------------------------------------- 79

    g. Columns ------------------------------------------------------------------- 80

    h. Slabs ----------------------------------------------------------------------- 81

    i. Reinforced Concrete Water Tanks--------------------------------------- 82

    j. Water Proofing ------------------------------------------------------------ 83

    TABLE OF CONTENTS

  • 7/26/2019 Construction Materials E-Book

    11/98

    9

    Go To Contents

    k. Back Fill ------------------------------------------------------------------- 84

    l. Block Work --------------------------------------------------------------- 85

    m. Plastering ----------------------------------------------------------------- 86

    n. Roof Water Proofing ----------------------------------------------------- 87

    o. Swimming Pool ----------------------------------------------------------- 88

    p. Ceramic Tiles ------------------------------------------------------------- 89

    q. Marble/Granite ---------------------------------------------------------- 90

    r. Aluminium ---------------------------------------------------------------- 91

    s. Painting (Metal Surfaces)------------------------------------------------ 92

    t. Painting (Concrete/Plaster Surfaces) ----------------------------------- 93

    u. Painting (Timber Surfaces) ---------------------------------------------- 94

    v. False Ceiling ------------------------------------------------------------- 95w. False Ceiling Closure ---------------------------------------------------- 96

    TABLE OF CONTENTS

  • 7/26/2019 Construction Materials E-Book

    12/98

    10

    Go To Contents

  • 7/26/2019 Construction Materials E-Book

    13/98

    11

    Go To Contents

    CHAIRMAN QUALITY POLICY STATEMENT

  • 7/26/2019 Construction Materials E-Book

    14/98

    12

    Go To Contents

  • 7/26/2019 Construction Materials E-Book

    15/98

    13

    Go To Contents

    The need for and use of a Quality control function can not be

    overemphasized. Quality cannot be tested nor inspected into a product,

    it must be built in. This manual outlines the basic and minimumrequirements for building a simple but effective system for controlling

    the quality of work and basic materials used in construction. This manual

    is based on the belief that:

    Quality is controlled by adequate advance planning, coordination,

    supervision, and technical direction; proper definition and a

    clear understanding of job requirements and procedures; and

    the employment of appropriately skilled personnel.

    Quality is verified through checking, reviewing and monitoring

    of work activities, with documentation by experienced, qualified

    individuals who are not directly responsible for performing the

    work.

    Quality is achieved by providing proper training of personnel

    and ensuring that all personnel remain current on the knowledge

    and skills needed for their positions.

    Quality is achieved by focusing on preventing problems or errors

    rather than reacting to them.

    Quality control should ensure that the work is done correctly the

    first time.

    This manual requires the attention and cooperation of all consultants,

    contractors and production personnel to assure quality production and

    material. It shall be implemented by all concerned parties in the field of

    construction. All involved parties shall comply with quality issues in other

    regulatory agencies having jurisdiction over the project.

    Section 1: INTRODUCTION

  • 7/26/2019 Construction Materials E-Book

    16/98

    14

    Go To Contents

  • 7/26/2019 Construction Materials E-Book

    17/98

    15

    Go To Contents

    2.01 QUALITY POLICY

    A. The Port, Customs and Free Zone Corporation Quality Policystatement signed by the Chairman will be adopted for allProjects.

    B. The Project shall prepare a Statement of Commitment to thePort, Customs and Free Zone Corporation Quality Policy thatshall be signed by the Project Manager/Contractor Managerand Sub-Contractor Manager.

    2.02 SUBMITTALSA. Contractors Quality Control Plan (QCP).

    1. Submit to Employer Representative no later than 7 calendardays from issue of the commencement date.

    2. No work covered by the Contractors QCP shall beginuntil the plan has been approved.

    3. Plan shall describe all of the Contractors quality controlprocedures that will be used throughout the project.

    4. Include an Internal and External Audit Schedule

    a. Minimum requirements shall be as specified herein.

    B. Quality Control Organization Plan

    1. Show organization of Contractors quality control team.

    2. Provide the name, qualifications, and experience of theQuality Control Manager and key QC support staff forapproval by the Employers Representative.

    a. Once approved, the Contractors Quality ControlManager shall have full authority to represent and act forthe Contractor on all quality related matters.

    b. Notify the Employer Representative in writing priorto re-assigning any of the designated quality control

    personnel.c. Obtain Employer Representatives approval for

    replacement prior to re-assigning or re-locating approvedquality control personnel.

    C. List of Proposed Suppliers and Sub-Contractors QC Staff

    1. List shall include the following:

    a. Items to be supplied by each supplier and sub-contractor

    b. Model or catalogue numbersc. Specifications

    d. Inspection and test requirements

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    18/98

    16

    Go To Contents

    e. Performance data

    f. Anticipated inspection and test dates

    g. Name and location of quarries and procedures forwork in quarries

    2. List other pertinent information as appropriate.

    D. Submit inspection and test results, certificates of compliance, andcertified material test reports to the Employer Representative.

    E. Inspection and Test Plan

    1. Submit to Employer Representative no later than 7 calendardays from the commencement date.

    2. No work covered by the inspection and test plan shallbegin until the plan has been approved.

    F. Quality Control Procedures and Instructions

    1. Submit to Employer Representative no later than 3 calendardays prior to using such procedures or instructions.

    2. Do not begin work governed by Quality Control Proceduresuntil such procedures have been approved by the EmployerRepresentative.

    G. Records Index

    1. Prepare an index of all project records which will bedeveloped and maintained during progress of the Work.

    2. Submit to Employer Representative no later than 7 calendardays from the commencement date.

    H. Inspection and Test Results

    1. All materials delivered to the site shall be sampled andtested; test results to be submitted at least 7 calendar daysprior to incorporating items into the Work.

    2. Report results to the Employer Representative indicatingcompliance or failure immediately upon receipt.

    2.03 GENERAL QUALITY CONTROL REQUIREMENTS

    A. Develop, implement and maintain a quality control programconsistent with the requirements of this Section.

    1. Ensure equipment and material conform to applicablerequirements of each section of the specifications.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    19/98

    17

    Go To Contents

    2. Maintain specified quality in all areas of the Work includingbut not limited to:

    a. Design and construction of temporary structures

    b. Inspection

    c. Testing

    d. Packaging, shipping, handling and storage ofequipment and materials

    e. Site construction activities

    B. Establish procedures to prevent deficiencies from occurring.

    1. Identify discrepancies when they do occur and then takecorrective action.

    2. Instruct workmen, sub-contractors, material suppliers,and other personnel involved in the project on the correctprocedures to follow.

    C. Assign specific responsibility for implementing the qualitycontrol program.

    D. Systematically verify compliance with the specified requirementsusing quality control audits for sub-contractors and suppliers.

    1. Record results in formal reports.

    2. Establish corrective action logs to track all actions.

    E. Assist Employer Representative in auditing quality controlactivities.

    1. Employer Representatives audits may be either pre-

    planned or random as warranted by general qualitytrends.

    F. Inspect and test all work under this Contract.

    1. Maintain records of such inspections and tests.

    2. Prepare and submit signed checklists for all work offeredfor the approval of the Employers Representative.

    G. Arrange for factory inspections and tests when required by theContract Documents.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    20/98

    18

    Go To Contents

    H. Provide equipment, instruments, qualified personnel, andfacilities necessary to inspect the work and perform the testsrequired by the Contract Documents.

    I. Repeat tests and inspections after correcting non-conformingwork until all work complies with the contract requirements.

    1. All re-testing and re-inspections shall be performed at noadditional cost to the Employer.

    J. The Employer Representative may elect to perform additionalinspections and tests at the place of the manufacture, the

    shipping point, or at the destination, to verify compliance withapplicable Specifications.

    1. Inspections and tests performed by the EmployerRepresentative shall not relieve the Contractor of hisresponsibility to meet the Specifications.

    2. Inspections and tests by the Employer Representative shallnot be considered a guarantee that materials delivered ata later time will be acceptable.

    K. Non-conforming materials, whether in place or not, will berejected by the Employer Representative.

    1. Contractor shall be notified in writing to correct or removethe defective material from the Works.

    2. If the Contractor fails to respond, the EmployerRepresentative may order correction, removal, and/orreplacement of defective materials by others.

    a. Contractor shall bear all costs for such work.

    L. Materials accepted on the basis of a Certificate of Compliancemay be sampled and inspected/tested by the EmployerRepresentative at any time.

    1. The fact that the materials were accepted on the basis ofa certificate of compliance shall not relieve the Contractorof his responsibility to use materials which comply with theSpecifications.

    M. Contractor shall impose all of the specified QCP requirements(including inspection and test procedures) upon Suppliers andSub-Contractors.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    21/98

    19

    Go To Contents

    N. Failure to Perform

    1. In the event the Contractor fails to adequately performany or all of the provisions of this Section, the Employer, athis sole discretion, reserves the right to have the EmployerRepresentative perform any or all of the provisions of thisSection and back-charge the Contractor for the actualcost of such work and any administrative charges deemednecessary.

    2. This remedy for Contractors failure to perform shall be inaddition to any other right or remedy available under theContract.

    2.04 QUALITY CONTROL PLAN

    A. Provides detailed description of procedures, instructions,and reports used to ensure compliance with the ContractDocuments.

    B. No construction shall begin and no requests for payment shallbe processed until the Contractors Quality Control Plan isapproved.

    C. Contractors QCP shall include the following as a minimum:

    1. Statement of Commitment to Ports, Customs & Free ZoneCorporation Quality Policy signed by all parties in theproject.

    2. Organization chart identifying all personnel responsiblefor quality control.

    a. Identify the manager of the QC program showing thatthe position is independent of the job supervisory staff

    with clear lines of authority.

    b. The QC manager shall report directly to the Contractorscorporate management and he shall liaise andcoordinate directly with the Employer Representative.

    c. Show area of responsibility and authority of eachindividual in the quality control system.

    d. Describe in detail the area of responsibility and authorityof each individual in the quality control system.

    e. The QC manager or designated substitute shallbe present at the project site at any time work is inprogress.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    22/98

    20

    Go To Contents

    3. Procedures for reviewing shop drawings, samples,certificates, and other submittals necessary for contractcompliance.

    a. Include the name of all personnel authorized to signthe submittals for the Contractor certifying that theycomply with the Contract requirements.

    4. Procedures used to ensure compliance with the ContractDocuments, as well as problem identification, reportingand resolution.

    a. Include a copy of forms and reports used to documentquality control operations.

    b. Include a submittal status log listing required submittals

    and action required by the Contractor and EmployerRepresentative or Project Manger.

    5. A description of the services provided by outsideorganizations such as testing laboratories, architects, andconsulting engineers.

    6. A test and inspection schedule keyed to the constructionschedule and following the order of the Specification.

    Indicate the following:

    1. Inspections and tests required.

    2. Names of responsible personnel for each segment ofthe Work.

    3. Schedule for each inspection and test.

    4. Acceptance criteria for any tests carried out.

    7. Document and submittal control procedures.

    8. Procedures to identify and control use of items andmaterials.

    9. Sample forms to be used (Stop Work Order, NCR, etc.)10. A control chart for both production facilities and field

    operation to provide a visual indication of whether aprocess is under control.

    11. Internal and External Audit Program for the duration of theproject.

    2.05 INSPECTION PROCEDURES

    A. As a minimum, inspect work before beginning each worksegment and after completing a representative portion of thework.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    23/98

    21

    Go To Contents

    B. Perform follow up inspections as necessary to ensure compliancewith the contract documents.

    C. Preparatory inspection shall include:

    1. Review of the contract requirements

    2. Review of approved shop drawings and submittal data.

    3. Check availability of required control testing.

    4. Ensure materials and equipment conform to approvedshop drawings and submittal data.

    5. Ensure the necessary preparatory work has been completedand is of acceptable quality.

    D. Perform an initial inspection as soon as a representativesegment of the particular item of Work has been completed.

    1. This inspection shall include the following:

    a. Conduct scheduled tests.

    1. Results shall cite the Contract requirements, the testor analytical procedures used, and the actual testresults.

    2. State whether item tested or analyzed conforms orfails to conform.

    3. Test reports shall be signed by the laboratoryrepresentative authorized to sign certified testreports.

    4. Immediately deliver all documents to the EmployerRepresentative.

    b. Examine quality of workmanship.

    c. Check for omissions or dimensional errors.

    d. Approve or reject initial work.

    E. Provide follow-up inspections as necessary.

    1. Include continued testing and examinations to ensurecontinued compliance with the Contract requirements.

    F. Prepare and attach to the Inspection procedures copies of

    checklists to be used to cover all aspects of the works.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    24/98

    22

    Go To Contents

    2.06 INSPECTION AND TEST PLAN

    A. Contractor shall develop an Inspection and Test Plan foreach Specification Section and for the design/production/testprocesses for each item of manufactured equipment.

    1. Identify the following:

    a. All required inspections and tests required by thatSpecification Section

    b. Required testing frequency

    c. The accept/reject criteria

    d. Records required to document compliance

    e. Procedures or instruction to be used for control of eachactivity

    g. Establish procedures to ensure that test results aresubmitted on time

    B. Provide sufficient detail to allow the Employer Representativeand other agencies having jurisdictional authority over thework to identify operations to be inspected by that organization(i.e. Ports, Customs & Free Zone Corporation - CED, DubaiMunicipality, etc).

    1. Such operations shall not be bypassed by the Contractor,unless a written waiver is given by the witnessingorganization.

    2.07 DOCUMENT AND SUBMITTAL CONTROL

    A. Establish written procedures for processing all documents andsubmittals associated with this project.

    1. Procedures shall address receipt, filing, safe guarding,processing and transmitting.

    2. Establish procedures to ensure documents are preparedand transmitted or distributed in a timely manner.

    3. Procedures shall also ensure documents contain therequired technical information.

    B. Provide quality control procedures, methods, and currentdocuments at the locations where they are to be used.

    C. Maintain separate files for quality related documents andmake such files available to the Employer Representative uponrequest.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    25/98

    23

    Go To Contents

    1. Retain all quality related records for not less than tenyears.

    2. Protect all records from damage, deterioration, and loss.

    D. Contractor shall not change or alter approved submittals,procedures, shop drawings or any other pertinent documentationwithout the Employer Representatives written authorization.

    E. Establish document registers to verify the approval status ofITPs, Method Statements and Drawings.

    2.08 IDENTIFICATION AND CONTROL OF ITEMS AND

    MATERIALS

    A. Contractor shall establish control procedures to ensure thatitems or materials accepted through shipping or receivinginspection are properly used and installed.

    B. Contractor shall identify all items and materials so that theyare traceable throughout all inspections, test activities, andrecords.

    1. For stored items, the identification method shall beconsistent with the expected duration and type of storage.

    C. Contractor shall record equipment and material identificationsand ensure that they are traceable to the location where theyare incorporated into the work.

    D. Contractor shall develop and maintain a receiving/inspectionlog containing at least the information itemized below:

    1. Purchase order number

    2. Item number

    3. Suppliers name

    4. Quantity

    5. Item description

    6. Reference to applicable Contract requirements

    7. Date received

    8. Heat number, serial number or other Identification, asapplicable

    9. Verification of receipt of all required supportingdocumentation

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    26/98

    24

    Go To Contents

    10. QC acceptance sign-off and date

    11. Non-conformance number, if applicable.

    2.09 INSPECTIONS AND TESTS

    A. Contractor shall use an approved material testing laboratoryfor testing required by these specifications.

    1. An on-site approved independent laboratory accreditedby Dubai Municipality Construction Quality Control &Research Section (DM CQC & RS) and staffed by qualifiedpersonnel shall be used.

    a. Submit name and qualifications of independent testinglaboratories to Employer Representative for approvalnot less than 7 calendar days prior to the date thelaboratories are to be used.

    b. Once approved, dismissal and replacement of theapproved independent testing laboratory shall requirewritten authorization by the Employer Representative.

    B. All inspections, sampling and testing of materials shall beconducted in accordance with the specified standards.

    1. Contractor shall have adequate QC personnel on siteduring all production shift operations.

    2. Test procedures submitted for approval shall include thefollowing, as a minimum:

    a. Prerequisites for the given test

    b. Required tools, equipment, and instrumentation

    c. Necessary environmental conditions

    d. Acceptance criteria

    e. Data to be recordedf. Test results reporting forms

    g. Identification of items tested

    C. Inspection work shall be performed by personnel designatedby the Contractor.

    1. Such personnel shall not be the same as those performingthe work.

    D. Approved procedures and instructions shall be on hand andused by inspection and test personnel at the time of inspectionor test.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    27/98

    25

    Go To Contents

    1. All revisions shall be approved prior to being used toinspect or test the work.

    2. No deviations from approved work procedures and

    instructions shall be allowed without written authorizationfrom the Employer Representative.

    E. Provide the Employer Representative with not less than 24 hourswritten notice of the occurrence of an assigned hold point.

    1. Any hold point inspected by outside agencies shall requirea minimum of 14 days prior written notification.

    F. Submit inspection/test results to the Employer Representativeprior to incorporating the item(s) into the work.

    1. Report inspection/test failures to the EmployerRepresentative immediately upon receipt.

    2. Submit certificates of compliance 7 days prior toincorporating a product to the Works.

    G. Inspections and tests conducted by persons or agencies otherthan the Contractor shall not in any way relieve the Contractorof his responsibility and obligation to meet all Specificationsand referenced standards.

    H. Inspection and test records shall, as a minimum, identify thefollowing:

    1. Name of items inspected/tested

    2. Quantity of items

    3. Inspection/test procedure reference

    4. Date

    5. Name of inspector/tester

    6. Observations/comments

    7. Specified requirements

    8. Acceptability

    9. Deviations/non-conformances

    10. Corrective action

    11. Evaluation of results

    12. Signature of authorized evaluator

    I. Inspection and Test Status

    1. Contractor shall clearly document and identify theinspections and test status of materials and equipment

    throughout construction.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    28/98

    26

    Go To Contents

    2. Identification may be by means of stamps, tags, or other

    control devices attached to, or accompanying, the material

    or equipment.

    2.10 MEASURING AND TEST EQUIPMENT

    A. Provide measuring and test equipment necessary to ensureconstruction conforms to the requirements of the specification.

    B. Maintain the accuracy of all measuring and test equipment.

    1. Provide a unique identification number or markpermanently affixed to each item of measuring and test

    equipment.2. Calibrate each item of measuring and test equipment at

    intervals recommended by the manufacturer and submitcalibration certificates.

    3. Develop a log of all measuring and test equipment andrecord:

    a. Equipment description

    b. Identification number

    c. Date of the last calibration

    d. Due date of the next calibration

    2.11 NON-CONFORMANCE MONITORING

    A. Contractor shall develop a system to identify, document, controland process non-conforming material and equipment.

    1. A non-conformance exists when either material andequipment, documentation, or construction do not complywith the requirements of the Contract Documents.

    2. The monitoring system shall apply to material andequipment as well as documentation, installation andconstruction which fail to conform to the ContractDocuments.

    B. Contractor shall provide the Employer Representative with thefollowing information for each non-conformance:

    1. Identification of non-conformance

    2. Description of non-conformance

    3. Evaluation of non-conformance to establish the cause4. Recommended corrective action

    5. Date non-conformance was identified

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    29/98

    27

    Go To Contents

    6. Date corrective action was completed

    7. Description of final corrective action

    8. Consultants Approval

    C. Contractor shall develop and maintain a non-conformanceaction tracking log to track all non-conformances.

    1. Log shall contain the following information as a

    minimum:

    a. Sequential reference number

    b. Date issued

    c. Originator

    d. Description of item deemed to be in non-conformance

    f. Description of non-conformance

    g. Recommended and final disposition

    h. Date closed

    i. QC Managers initials

    j. Remarks, as applicable

    D. Contractors QC personnel shall have the authority to stop thatportion of the work which does not comply with the Contractrequirements.

    E. The dispositions for non-conforming items and materials shallbe subject to approval by the Employer Representative.

    F. Contractor shall clearly identify each non-conforming item witha status tag or other distinguishing mark.

    1. Establish procedures for installing, monitoring, and

    removing these status tags.2. Identify personnel authorized to remove status tags.

    G. Corrective Actions

    1. Contractor shall take prompt action to identify the causesof each non-conformance and the corrective actionnecessary to prevent recurrence.

    a. The results of failure and discrepancy report summaries,supplier evaluations, and any other pertinent applicable

    data shall be used for determining corrective action.

    b. Information developed during construction, tests, andinspections that support the implementation of required

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    30/98

    28

    Go To Contents

    improvements and corrections shall be used to supportthe adequacy of corrective action taken.

    2.12 PERSONNEL QUALIFICATIONS

    A. Contractor shall identify activities requiring qualified production,inspection, and test personnel and establish their minimumcompetence level.

    B. Personnel inspecting and testing special operations (e.g.,welding, brazing, etc.) shall have the experience, training, andcurrent certification commensurate with the scope, complexity,or nature of the activity.

    1. Such personnel shall be approved by the EmployerRepresentative.

    C. Contractor shall submit the following for all such production,inspection and test personnel:

    1. Qualifications description

    2. Orientation

    3. Skill evaluation

    4. Certification credentials

    D. Contractor shall maintain records of personnel qualifications asquality records.

    2.13 QUALITY CONTROL REPORTS/AUDITS

    A. The Contractors Quality Control Manager shall provide adaily Quality Control Report to the Employer Representative.This report shall be comprehensive and it should include all

    Q.C. activities on the project.

    B. Contractor shall perform regularly scheduled internal audits toverify that his quality control procedures ensure total compliancewith the Specifications and referenced standards.

    1. Schedule quality control audits not less than monthly anddocument findings in a report.

    2. Maintain records of internal audits as quality records andmake them available to the Employer Representative uponrequest.

    3. Provide the Employer Representative with access to theaudit records upon request.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    31/98

    29

    Go To Contents

    4. Allow the Employer Representative to observe theContractors internal audit upon request.

    5. Provide the Employer Representative with a copy of theaudit report.

    C. Contractor shall perform regularly scheduled external auditson his main Suppliers and Sub-Contractors to verify that theirquality control procedures ensure total compliance with thespecifications and referenced standards.

    1. Schedule quality control audits not less than monthly.

    2. Maintain records of internal audits of contractors andsubcontractors as quality records and make them available

    to the Employer Representative upon request.3. Provide the Employer Representative with access to the

    audit records upon request.

    4. Allow the Employer Representative to observe theContractors internal audit upon request.

    5. Provide the Employer Representative with a copy of theaudit report.

    2.14 EQUIPMENT/MATERIAL HANDLING AND STORAGEA. Contractor shall be responsible for handling, storing and

    preserving equipment and material from the time of receipt tothe time of acceptance by the Employer.

    B. Contractors storage and handling procedures shall bedesigned to prevent damage, deterioration, distortion of shapeor dimension, loss, degradation, loss of identification, orsubstitution.

    C. The handling procedures shall address the use, inspection

    and maintenance of special devices such as crates, boxes,containers, dividers, slings, material handling and transportationequipment and other facilities.

    D. Contractor shall identify equipment and material requiringspecial handling or testing.

    2.15 QUALITY CONTROL RECORDS

    A. Contractor shall develop a complete records index based onthe requirements for document and data submittals in each

    Section of the Specifications.1. Indicate all quality control records, documentation,

    submittals and data required by the Contract.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    32/98

    30

    Go To Contents

    2. Supplement these records as necessary to monitor qualitythroughout the project.

    3. The records identified in the index shall provide objective

    evidence that quality control program activities conform tothe contract requirements.

    a. Include evidence that required verifications have beenperformed

    b. Establish the basis for key project decisions.

    B. Authenticate all records.

    1. Only complete and properly authenticated documentsshall be maintained as records of material and equipment

    quality.

    C. Quality records shall be indexed, filed and maintained in amanner that provides for timely retrieval; traceability, easyidentification and the latest status (acceptability) of equipmentand material.

    D. Protect Quality Control records from deterioration anddamage.

    E. As a minimum, records shall include:1. Name of equipment/material inspected/ tested

    2. Specification reference by section and paragraph (whereapplicable)

    3. Quantity of items

    4. Location and installation

    5. Inspection/test procedure reference

    6. Date

    7. Signature of inspector

    8. Observations/comments

    2.16 WORKMANSHIP

    A. Comply with industry standards except when more restrictivetolerances or specified requirements indicate more rigidstandards or more precise workmanship.

    B. Perform work by persons qualified to produce workmanship ofthe specified quality.

    C. Secure products in place with positive anchorage devicesdesigned and sized to withstand stresses, vibration, andracking.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    33/98

    31

    Go To Contents

    D. Comply with manufacturers published installation instructionsin full detail, including each step in sequence.

    1. Should instructions conflict with Contract Documents,

    request clarification from Employer Representative beforeproceeding.

    2.17 PROTECTION OF PROPERTY

    A. Do not load or permit a structure to be loaded in a manner thatwill endanger the structure.

    B. Do not subject Work or adjacent property to stresses or pressures

    that will endanger it.

    C. Existing Surfaces and Facilities:

    1. Take positive action to protect existing surfaces and facilitiesfrom damage resulting from construction operations unlessmodifications to the surfaces or facilities are required aspart of the Contract.

    2. Protect paving, landscaping, and utility facilities fromdamage caused by mobile and stationary equipment,including vehicles delivering materials to the project site.

    3. Protect finished surfaces, including jambs and soffits ofopenings used as passageways through which materialsare handled, against possible damage resulting form theconduct of the work by trades.

    4. Provide and maintain adequate protection for adjacentstructures.

    a. When required by law or for the safety of the Work;shore, brace, underpin, or otherwise protect thoseportions of adjacent structures that may be affected by

    the Work.

    D. Utilities

    1. Known utilities and related facilities are shown on thedrawings.

    a. Location of these facilities are not guaranteed, noris there any guarantee that other utilities are notpresent.

    b. Unless otherwise specifically provided, protect utilitiesand related facilities from damage and cause nointerruption of service.

    2. Establish and maintain direct contact with the Employer

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    34/98

    32

    Go To Contents

    Representative or operator of each utility that may beaffected by the Work.

    a. Proceed with Work that may affect a utility only withthe cooperation and approval of the EmployerRepresentative or operator of the utility.

    b. Immediately inform the Employer Representative ofany agreement with the utility operator concerning the

    Work under this Contract.

    3. Verify the location of all utilities in the vicinity of the workbefore commencing construction.

    a. Submit a plan for performing the work to the EmployerRepresentative for approval.

    b. Include evidence of approval by the utility owner oroperator.

    E. New Work

    1. All finished surfaces shall be clean and un-marred uponacceptance of the area.

    2. Do not permit traffic or material storage on finishedsurfaces.

    a. Where some activity must take place on the finishedsurface in order to perform the Work, provide andmaintain adequate protection.

    3. Provide and maintain adequate protection against theweather at all times so as to preserve Work, materials,equipment, apparatus, and fixtures free from damage.

    4. Do not use items of equipment that are intended to forma part of the completed work as construction equipmentwithout specific approval from the Employer Representativein each instance.

    2.18 QA/QC INDUCTION TRAINING

    A. Prepare and carry out QA/QC Induction Training for all QCstaff, Engineers, Inspectors and Foremen on the project QCplan, procedures, Inspection and Test Plan, method statementsand checklists to be used during the construction of theproject.

    B. Prepare and carry out QA/QC Induction Training for all Sub-Contractors staff as noted in A.

    Section 2 : QUALITY CONTROL (GENERAL)

  • 7/26/2019 Construction Materials E-Book

    35/98

    33

    Go To Contents

    Section 3 : RECOMMENDED PRACTICES BEFORE AND DURING CONCRETING

    3.01 FORMWORK

    All forms should be perfectly cleaned

    Release agent applied correctly Correct position

    Line and level

    Accuracy within tolerances

    Verticality (plumb)

    Correct angles for batters

    Finishing heights (mark off)

    Joints flush and tight

    Joints sealed as required

    No nails protruding into the concrete

    3.02 CONCRETE CONSOLIDATION

    Make sure you can see the concrete surface

    When inserting the poker, its head should be put in quickly andallowed to penetrate to the bottom of the layer as quickly as

    possible under its own weight. If done slowly, the top layer willbe compacted first, making it more difficult for the entrappedair in the lower part of the layer to escape to the surface.

    The head should be inserted vertically. This minimizes the voidscreated by inserting the head, and allows air bubbles to rise upunimpeded by a sloping vibrator.

    The poker should be left in the concrete for about 10 seconds,and withdrawn slowly.

    The poker should not touch the form face.

    The poker should extend 100mm into any previous layer.

    The maximum depth of the new layer equals the vibrator headlength minus 100mm. If the depth of concrete is greater, thenthe new part will not be fully compacted.

    It should be noted that where finish is important, extra vibrationcan reduce the number of blowholes.

    3.03 CONCRETING Someone experienced in the construction of formwork should

    always be present at site when the concrete is being placed.

  • 7/26/2019 Construction Materials E-Book

    36/98

    34

    Go To Contents

    Grout loss is an indication that joints were not tight or somemovements have occurred during placing.

    In walls and columns no layer should be more than about450mm thick. With layers thicker than 450mm, the weight ofconcrete on top makes it impossible even with vibration to getthe air out from the bottom of the layer.

    Make sure that each layer of concrete has been fully compactedbefore placing the next one.

    Fully compacted concrete will be dense, strong, durable andimpermeable. Badly compacted concrete will be weak, nondurable, honeycombed and porous. The air must be removed.

    For maximum compaction, preferance should be given to the

    use of self compacting concrete.

    3.04 HOT WEATHER CONCRETING

    The American Concrete Institute Hot Weather Concreting, ACI305R-99, defines hot weather as any combination of high ambienttemperature, high concrete temperature, low relative humidity,high wind speed, and excessive solar radiation that can impair thequality of fresh or hardened concrete. These factors individually orcombined, can accelerate moisture loss and cement hydration.

    Concrete mixed and placed during hot weather is subject toconditions that can adversely affect the properties and serviceabilityof the hardened concrete. Some of these conditions are:

    Increased water demand

    Increased rate of slump loss

    Increased rate of setting

    Increased tendency of plastic shrinkage cracking anddrying shrinkage cracking

    Low ultimate strength

    Decreased durability Increased permeability

    Increased potential for reinforcing steel corrosion

    Successful hot weather concreting requires careful planning andclose coordination among all members of the construction team.Best results will be achieved if the following important proceduresare recognized.

    A. Production at Batching Plants

    1. Shading the aggregates.

    2. Cooling the mixing water before use.3. Approved water cementitous material ratio should be

    respected.

    Section 3 : RECOMMENDED PRACTICES BEFORE AND DURING CONCRETING

  • 7/26/2019 Construction Materials E-Book

    37/98

    35

    Go To Contents

    4. Set retarding admixtures can be added to slow setting ofconcrete and reduce water demand.

    5. Cement extenders, such as Fly Ash and GGBS.

    B. Transport

    1. Steady flow of concrete

    2. Drum rotation should be at the lowest agitating speed

    3. Major placement of concrete should be scheduled duringevening or night times and periods of lower traffic.

    4. The dispatching of trucks should be coordinated with therate of placement to avoid delays in arrival or long waiting

    periods.5. Traffic arrangement at site should ensure easy access of

    delivery units to the unloading points.

    6. Site traffic should be coordinated for a quick turnaroundof concrete truck.

    C. Placement of Concrete

    1. Have adequate manpower and equipment (plus stand-byunits) available to handle the concrete at the desired rate

    of placement and to unload the concrete trucks promptly.2. Water should be available in sufficient quantities. The

    temperature of water used for curing must be as close aspossible to that of the concrete to avoid thermal shock (notmore than 11 C than that of concrete).

    3. Erect temporarily windbreaks and shades to protect freshconcrete from hot sun and drying winds.

    4. Arrangement should be made for the ready availability ofbackup equipment for placing, vibrating and material for

    curing.5. Dampen the sub grade, forms and reinforcing steel the

    night before, do this again thoroughly before placingconcrete.

    6. Cover concrete as soon as it is placed, until final finishingcan be started.

    7. Water curing should start immediately after finishing andit should be continuous as per specified period of curing.

    8. Temperature of concrete should be as per specified limit.

    9. For mass concrete a method statement should be givenaddressing the logistical and technical issues.

    Section 3 : RECOMMENDED PRACTICES BEFORE AND DURING CONCRETING

  • 7/26/2019 Construction Materials E-Book

    38/98

    36

    Go To Contents

    D. Testing

    1. An approved trained technician should perform all tests.

    2. Leaving the samples of fresh concrete exposed to sun,wind or dry air is not acceptable.

    3. Samples of fresh concrete shall be provided withan impervious cover, cured and stored in a shadedenvironment (temperature of shaded environment shouldbe as per relevant standards). Record temperature usingmaximum minimum thermometer.)

    4. Prevent moisture loss of samples during transportationby wrapping them in plastic wet burlap. Be sure to avoidexcessive rough handling during transportation to the

    laboratory.

    Section 3 : RECOMMENDED PRACTICES BEFORE AND DURING CONCRETING

  • 7/26/2019 Construction Materials E-Book

    39/98

    37

    Go To Contents

    Section 4 : SCHEDULE OF TESTS AND INSPECTIONS

    CAST IN-SITU CONCRETE

    Ready-Mixed Concrete

    LABORATORY & PLANT TRIAL MIXES

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    A. Composition/Selection Each Grade Before Production Starts

    Concrete Temperature ASTM C 1064 Each grade

    Slump

    BS 1881-102,

    EN 12350-2 Initially and every 15 minutes

    Flow Table(1) EN 12350-5 Initially and every 15 minutes

    Slump Flow(2) ASTM C 1611 Each grade

    T-50 cm Slump Flow(2) ASTM C 1611 Each grade

    V-Funnel(2)European Guidelines

    for SCCEach grade

    V-Funnel at T5minutes(2)

    European Guidelinesfor SCC

    Each grade

    L-Box (h2/h

    1)(2)

    European Guidelinesfor SCC

    Each grade

    J-Ring(2) ASTM C 1621 Each grade

    Fresh Concrete Density& Yield

    BS 1881-107, EN12350-6, ASTM C 138

    Each grade

    Air ContentBS 1881-106,

    EN 12350-7Each grade

    Bleeding ASTM C 232 Each grade

    Setting Time ofConcrete

    ASTM C 403 Each grade

    Compressive StrengthBS 1881-116,EN 12390-3

    At 7 and 28 days for eachgrade

    Tensile/FlexuralStrength

    EN 12390-5&6At 7 and 28 days for grades

    where flexural govern

    Drying Shrinkage ASTM C 596 Each grade of structuralconcrete

  • 7/26/2019 Construction Materials E-Book

    40/98

    38

    Go To Contents

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    Sulfate and Chloride

    ContentBS 1881-124 Each grade (3)

    Rapid ChloridePenetration

    ASTM C 1202At 28 days for each grade of

    structural concrete

    Water Absorption BS 1881-122At 28 days for each grade of

    structural concrete

    Water Permeability EN 12390-8At 28 days for each grade of

    structural concrete

    Initial SurfaceAbsorption Test

    BS 1881-208At 28 days for each grade of

    structural concrete

    (1) Where flowable concrete is used

    (2) Where Self Compacting Concrete is used

    (3) Whenever the source of any ingredient changes

    Notes:

    1. Designed concrete shall conform to the requirements specifiedin EN 206 and BS 8500

    2. Additional testing will be conducted at the request of theEngineer and/or Authority

    3. Contract Specifications are to be implemented if more or othertests are required

    4. Follow the recommendations of the following codes/standards:

    ACI 311.5: Guide for concrete plant inspection and testing ofready-mixed concrete

    ACI 304R: Guide for measuring, mixing, transporting and

    placing concreteASTM C94/C94M: Standard Specification for Ready MixedConcrete

    The European Guidelines for Self Compacting Concrete

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    41/98

    39

    Go To Contents

    CAST IN-SITU CONCRETE

    Ready-Mixed Concrete

    CONCRETE PRODUCTION & SITE DELIVERIES

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    A. Composition/Selection Structural Concrete

    Concrete Temperature ASTM C 1064 Each load

    SlumpBS 1881-102,EN 12350-2

    Each load

    Flow Table(1) EN 12350-5 Each load

    Slump Flow (2) ASTM C 1611 Each Delivery650 - 750 mm

    and visually

    J-Ring (2) ASTM C 1621As per projectspecifications

    0 - 10 mm

    Fresh Concrete Density& Yield

    BS 1881-107,EN 12350-6,ASTM C 138

    With each set of compressivestrength cubes

    Air Content (3)BS 1881-106,

    EN 12350-7

    Each load

    Compressive StrengthBS 1881-116,EN 12390-3

    1. Critical Structures (columns, cantilevers...): One set every 10m3or

    fraction thereof

    A setconsistsof atleast 6cubes

    2. Intermediate Structures: One set every 50m3or

    fraction thereof

    3. Mass Concrete (rafts): One set every 100m3for

    pours less than 2000m3

    One set every 150m3forpours less than 2000m3

    Tensile/FlexuralStrength

    EN 12390-5&6At 7 and 28 days for grades where

    flexural govern

    Evaluation of StrengthTest Results of Concrete

    ACI 214,ACI 363.2R

    Biweekly for each grade of structuralconcrete:1. The overall variation class of

    operation for general constructiontesting shall be at least Good.

    2. The within-test variation class ofoperation for field control testingshall be at least Very Good.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    42/98

    40

    Go To Contents

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    Visual Examination of

    Aggregates (by washing)

    Project Specifications At the request of the Engineer

    Sulfate and ChlorideContent

    BS 1881-124 As per project specifications

    Rapid ChloridePenetration

    ASTM C 1202 As per project specifications

    Water Absorption BS 1881-122 As per project specifications

    Water Permeability EN 12390-8 As per project specifications

    Initial SurfaceAbsorption Test

    BS 1881-208 As per project specifications

    (1) Where flowable concrete is used

    (2)Where Self Compacting Concrete is used

    (3) Where air-entrained concrete is used

    Notes:

    1. A strength test is the average strength of concrete specimens sampled

    from the same batch or load.2. A load is the quantity of concrete transported in a vehicle comprising

    one or more batches.

    3. A batch is the quantity of fresh concrete produced in one cycle ofoperations of a mixer or the quantity discharged during one minutefrom a continuous mixer.

    4. Follow the recommendations of ACI 305R during hot weather.

    5. Follow the recommendations of the following codes/standards:

    ACI 311.5: Guide for concrete plant inspection and testing of ready-

    mixed concrete

    ACI 304R: Guide for measuring, mixing, transporting and placingconcrete

    ASTM C94/C94M: Standard Specification for Ready Mixed Concrete

    6. Each load shall be accompanied by a computer controlled nonsimulated printout listing all the information related to the mix.

    7. Each truck mixer/agitator, when it arrives at site, shall have its watercontainer full. If that container is not full or field test results are outsidethe specified limits, the load shall be rejected.

    8. Additional testing will be conducted at the request of the Engineer and/or Authority

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    43/98

    41

    Go To Contents

    9. Contract Specifications are to be implemented if more or other tests arerequired.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    44/98

    42

    Go To Contents

    CAST IN-SITU CONCRETE

    SITE LABORATORIES

    Requirements for Concrete Testing Laboratories

    A. Human Resources:

    a. The testing lab services shall be provided under the technicaldirection of a professional engineer with relevant experiencein construction material testing, or a supervising lab technicianwith relevant experience in construction material testing andcurrent technician certification.

    b. The testing field and/or lab technician shall possess currenttechnician certification or have undergone a training programcovering all the relevant tests performed by the technician.

    B. Test Methods and Procedures:

    a. The site testing laboratory shall be capable of performing therequired tests as per standard methords, guides or practices.

    b. The laboratory shall use the latest version of each referencedmethod within one year of its publication unless an earlier

    version of the standard is required by the client.

    c. Laboratory personnel shall have convenient access to applicablestandards.

    C. Facilities, Equipment and Supplemental Procedures:

    a. The laboratory shall have facilities and equipment conformingto the requirements of the applicable test methods.

    b. All equipment and instruments shall be verified and calibrated

    before being placed in service and at the frequency set by thepertinent standards and local regulations.

    c. All balances and scales shall be calibrated annually or wheneveraccuracy is in doubt.

    D. Preparations and Conditions:

    a. Proper sampling of fresh concrete shall be conductedin accordance with the pertinent standards and project

    specifications.b. The required field tests shall be performed at the frequencies

    stated in the project specifications.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    45/98

    43

    Go To Contents

    c. The floor, where tests are preformed and compressive strengthspecimens are stored, shall be levelled and free of anyvibrations.

    d. Concrete test specimens shall be protected from evaporationand damage.

    e. Proper tagging of the specimens shall be done specifying thedate, time, location, grade of concrete and name of technicianmoulding the specimens.

    f. Initial curing temperatures for the concrete specimens shall bemaintained between the limits set in the pertinent standards.

    g. De-moulding of the concrete specimens shall be done withinthe time limitations stated in the relevant standards.

    h. Curing tanks shall be of sufficient size and controlledtemperature. Temperature shall be verified with recordingthermometers.

    E. Laboratory Records and Reports:

    The laboratory shall maintain a system of records that permitsverification of any issued report. The records shall include:

    a. Standard operating procedures

    b. Calibration certificates of the equipment and instrumentsused

    c. Records on laboratory personnel that document workexperience, competency and certification

    d. Current standard test methods

    All testing reports shall include the information requiredand stated by the pertinent standards and test methods.

    All testing reports shall state the acceptance criteria of the testbeing carried out as well as a statement on whether the test

    results passed or failed.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    46/98

    44

    Go To Contents

    CAST IN-SITU CONCRETEReady-Mixed Concrete

    AGGREGATESSchedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY/ NOTES

    A Composition/Selection Coarse Aggregate Fine Aggregate

    Grading EN 933-1, BS 812-103

    Daily Daily Material finer than0.075mm sieve

    EN 933-1, BS 812-103

    Water Absorption andSpecific Gravity

    ASTM C 127, C 128,EN 1097-6

    Twice a month

    Elongation and FlakinessEN 933-3&4,BS 812-105

    Monthly

    Moisture Content in Sandby Moisture Tester (Speedy)

    To be carriedout by

    batching plant

    Cleaning ofmoisture tester

    regularly

    Moisture Content ofwashed aggregates and ofaggregates in rainy seasons

    ASTM C 566 At least three times a day

    Clay Lumps and FriableParticles

    ASTM C 14 Monthly

    Light Weight Particles ASTM C 123 Every 3 months

    Organic Impurities ASTM C 40 Monthly

    Sand Equivalent ASTM D 2419 Monthly

    Water Soluble Chlorides(Quantitative)

    BS 812-117 Every three months

    Acid Soluble Sulfates BS 812-118 Every three months

    Soundness (MgSO4) - 5

    cyclesASTM C 88 Every two months

    Potential Reactivity ofAggregates

    ASTM C 289, C 227 Every six months

    Aggregate DryingShrinkage

    EN 1367-4 Every six months

    10% Fines Value (TFV)BS 812-111, EN

    1097-2Every two months

    Los Angeles Abrasion Test ASTM C 131 Every two months

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    47/98

    45

    Go To Contents

    Notes:

    1. All the tests shall be done before the start of the work and whenever

    the source is changed.

    2. Additional testing will be conducted at the request of the Engineerand/or Authority.

    3. Contract Specifications are to be implemented if more or other testsare required.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    48/98

    46

    Go To Contents

    CAST IN-SITU CONCRETEReady-Mixed Concrete

    WATERSchedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY/ NOTES

    A Composition/Selection

    Chlorides (Cl) ASTM D 512

    Initially, everythree

    months, andwhenever

    source changes

    It shall complywith the

    requirements ofASTM C1602 /

    EN 1008

    Sulfates (SO4) ASTM D 516

    Alkali Carbonates andBicarbonates ASTM D 513

    Total Dissolved Ions ASTM D 1888

    pH value ASTM D 1293

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    49/98

    47

    Go To Contents

    CAST IN-SITU CONCRETEReady-Mixed Concrete

    CEMENTITIOUS MATERIALS & ADMIXTURESSchedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY/ NOTES

    Cement EN 197, ASTM C 150 Initially and every three months

    GGBS BS 6699, ASTM C 989 Initially and every one month

    Pozzolanic Fly ash BS EN 450S Initially and every three months

    Silica Fume ASTM C 1240 Initially and every three months

    Liquid Admixtures ASTM C 494, C 260, C 1017 Initially and every three months

    Notes:

    1. All the cementitious materials shall conform to the physical andchemical requirements of the pertinent standard specifications. Therequired tests shall be made to verify compliance.

    2. For cementitious materials, regular sampling shall be made fromeach delivery for random testing. All samples are to be stored until

    28 or 56 day results are obtained and satisfactory.3. Additional testing will be conducted at the request of the Engineer

    and/or Authority.

    4. Contract Specifications are to be implemented if more or other testsare required.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    50/98

    48

    Go To Contents

    BORED IN-SITU PILES AND DRILLED SHAFTS

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY / NOTES

    A Composition/Selection

    Reinforcing Steel BS EN 10080Refer to frequency of testing of Steel in

    this Manual

    Concrete Concrete SpecificationsRefer to frequency of testing of Cast-

    in-place Concrete in this Manual

    Pile Load Test ASTM D 1143

    Minimum 1% for each type (Dimensionof Piles Diameter and Length) or as

    per project specifications ifmore tests are required

    Pile Load Test ASTM D 4945Minimum 5% of Piles or as per

    project specifications if more tests arerequired

    Pile Integrity Test ASTM D 5882 All Piles

    Cross Hole LoggingAnalyzer

    ASTM D 6760Minimum 10% of Piles or as per

    project specifications if more tests arerequired

    Calliper Logging ASTM D 6167Minimum 10% of Piles or as per

    project specifications if more tests arerequired (To be selected randomly)

    Ultimate Load Test ASTM D 1143A minimum of one non-working pile

    to be tested according to projectspecifications

    Notes:

    1. Additional testing will be conducted at the request of the Engineer

    and/or Authority.2. Contract Specifications are to be implemented if more or other tests

    are required.

    3. For Diaphragm Wall the following instruments are to be fixed formonitoring purpose:

    Inclinometer, Steel Strain gauges, concrete stress gauges, andpressure cells.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    51/98

    49

    Go To Contents

    REINFORCING STEEL

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVEDOCUMENT

    FREQUENCY NOTES

    A Composition/Selection

    Grade 460 B & Other Grades BS EN 10080

    Mechanical Properties

    Yield Strength

    Ultimate Strength

    Elongation of Fracture

    Mass / meter

    Nominal Cross-sectionalArea

    Bending

    Re-bending

    Chemical Properties

    One (1) set of tests

    for Mechanicaland ChemicalProperties for eachbar diameter at thestart of the job andevery 100 tons ofsteel delivered tothe site.(Refer to Notes)

    1. Every consignmentof Steel shall haveMill Certificates tobe attached to theMaterial InspectionRequest for theEngineers review.Steel tags havingheat number are tobe provided with thesteel.

    2. Tests are to berepeated wheneverthere is a change inthe source of supply.

    Notes:

    1. All steel reinforcement specified shall comply with BS 4449 or BS4483, and shall be cut and bent in compliance with BS 8666.

    2. Additional testing will be conducted at the request of the Engineerand/or Authority.

    3. Contract Specifications are to be implemented if more or other tests

    are required.4. Reinforcing steel, supplied by Cares or equivalent accredited

    certification body approved mills, shall be tested at the start of theproject and every 200 tons delivered to site.

    5. Reinforcing steel, supplied and processed by Cares or equivalentaccredited certification body approved steel mills and cutting &bending companies, shall be tested at the start of the work andevery 400 tons delivered to site.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    52/98

    50

    Go To Contents

    EPOXY-COATED STEEL

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    Coating Thickness

    BS 7295 /ASTM A775

    As per standard/project

    specifications

    Every consignment ofSteel shall have Mill& Test Certificates tobe attached to theMaterial Inspection

    Request for theEngineers review.

    Steel tags having heatnumber are to be

    provided with the steel

    Coating Continuity

    Coating Flexibility

    Coating Adhesion

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    53/98

    51

    Go To Contents

    EARTHWORK

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    Particle Size Analysisand Determination ofSoil Constants(Dry and Wet)

    BS 1377 part 2

    All tests shall becarried out at a

    minimum rate of 3tests for every 300m3

    of material

    ProjectSpecifications

    Atterberg Limits (LL,PL & PI)

    BS 1377 part 2

    Sand Equivalent ASTM D 2419

    Chlorides andSulfates in Soil BS 1377 part 3

    In-Situ Density of Soil

    a. Trenches

    BS 1377

    a) Make at selected locations at leastone field density test for every 200m2area/layer, but in no case less thanthree(3) tests per day operation.

    b. Walkways

    b) Make at selected locations at least

    one field density test of subgrade orfinish grade for every 200m2area,but in no case less than three (3) testsper day operation.

    c. Pavement Layer(Subgrade, Subbaseand Base)

    c) Make at selected locations at leastone field density test for every 200m2area/layer, but in no case less thanthree (3) tests per day operation

    Moisture - DensityRelations of Soil using4.5 kg Rammer, 457mm Drop Method D

    BS 1377 part 4 All required testsshall be carried outfor every 400 m3of

    material

    ProjectSpecifications

    California Bearing

    Ratio Test

    BS 1377

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    54/98

    52

    Go To Contents

    PRECAST CONCRETE

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    1 Material TestingRefer to the requirements of the Cast-

    in-place Concrete and Reinforcing Steelsections of this Manual

    ProjectSpecifications

    2 Testing finished Material

    CompressiveStrength

    BS 1881,BS EN 12390-3

    As directed by theEngineer (Cores fromprecast units) Project

    SpecificationsDurabilityRequirements

    As directed by theEngineer (Cores fromprecast units)

    3 Joint Sealant and Fillers

    Cement Grout(Portland Cement)

    BS EN 197As directed by theEngineer

    ProjectSpecifications

    Natural Sand BS EN 13139

    Non-shrink GroutAs directed by theEngineer

    Elastomeric SealantsASTM C 962,

    ACI 504

    4Inserts and OtherHardware

    ASTM A 307, A 325,A490, A 108, A 496

    ProjectSpecifications

    Corrosion Protection ASTM A 276Project

    SpecificationsExpansion Anchors ASTM E 448

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    3. Follow the recommendations of the manuals published by pci,Precast/Prestressed Concrete Institute.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    55/98

    53

    Go To Contents

    GLASS REINFORCED CEMENT (GRC) ELEMENTS

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    1 Composition of GRC Elements

    Glass ContentProject

    Specifications

    At the start of the

    job, once a month

    or as requested by

    the EngineerWet Bulk Density

    2 Testing finished Material

    Modulus of RuptureProject

    Specifications

    At the start of thejob, once a month

    or as requested by

    the Engineer

    ProjectSpecificationsLimit of Proportionality

    JJ the EngineerLloyd T 5000/SS

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other tests

    are required.

    3. Works and Material shall comply with the following requirements:

    a. PCI MNL 117 - Manual for Quality Control for Plants andProduction of Architectural Pre-cast Construction Products

    b. PCI MNL 128 - Recommended Practice for Glass Fibre ReinforcedConcrete Panels

    c. PCI MNL 130 - Manual for Quality Control

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    56/98

    54

    Go To Contents

    CONCRETE BLOCKS

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVEDOCUMENT

    FREQUENCY NOTES

    1 Masonry Blocks

    Dimensions and CompressiveStrength

    DubaiMunicipality

    StandardEvery 20,000 blocksDensity

    Chloride and Sulfate Content

    2 Paving Blocks

    Dimensions and CompressiveStrength

    DubaiMunicipality

    StandardEvery 20,000 blocksDensity

    Chloride and Sulfate Content

    3 Filler Blocks (Normal Weight)

    Dimensions and CompressiveStrengthDubai

    MunicipalityStandard

    Every 20,000 blocksDensity

    Chloride and Sulfate Content

    4 Filler Blocks (Light Weight)

    Dimensions and CompressiveStrength

    Dubai

    MunicipalityStandard Every 20,000 blocksDensity

    Chloride and Sulfate Content

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other tests

    are required.3. Works and Material shall conform to Dubai Municipality and

    International Standards.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    57/98

    55

    Go To Contents

    AUTOCLAVED AERATED CONCRETE BLOCKS

    Schedule of Tests and Inspections

    DESIGNATIONNORMATIVE

    DOCUMENTFREQUENCY NOTES

    A Composition/Selection

    AAC Blocks

    Dimensions and CompressiveStrength

    Dubai Municipality

    Standard

    Every 20,000

    blocks

    Thermal Conductivity and DryDensity

    Chloride and Sulfate Content

    Drying Shrinkage

    Fire Rating ASTM E 119Project

    Specifications

    MortarProject

    Specifications

    As recommendedby the

    manufacturer

    Portland Cement:

    Works below Ground Slab (SRC) BS 4248

    Project SpecificationsWorks above Ground Slab (OPC) BS EN 197-1

    Sand BS EN 13139 Project Specifications

    AccessoriesAs directed bythe Engineer

    Project Specifications

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    3. Works and Material shall conform to Dubai Municipality andInternational Standards.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    58/98

    56

    Go To Contents

    NORMAL WEIGHT CONCRETE POLYSTYRENE SANDWICH BLOCKS

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    A Composition/Selection

    Dimensions and CompressiveStrength

    Dubai MunicipalityStandard

    Every 20,000blocks

    Thermal Conductivity

    Chloride and Sulfate Content

    Apparent Density

    Polystyrene Dimensions andDensity

    Polystyrene Core ThermalConductivity

    Fire Rating (Polystyrene)ASTM D 2863,BS EN 11925-2

    As directedby the

    Engineer

    ProjectSpecifications

    Mortar Project SpecificationsAs recommended

    by the

    manufacturer

    Portland Cement:

    Works below Ground Slab (SRC) BS 4248

    Project SpecificationsWorks above Ground Slab (OPC) BS EN 197-1

    Sand BS EN 13139 Project Specifications

    AccessoriesAs directed by

    the EngineerProject Specifications

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    3. Works and Material shall conform to Dubai Municipality andInternational Standards.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    59/98

    57

    Go To Contents

    LIGHT WEIGHT MASONRY UNITS

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    A Composition/Selection

    Dimensions and CompressiveStrength

    Dubai MunicipalityStandard

    Every 20,000blocks

    Thermal Conductivity

    Gross Density

    Chloride and Sulfate Content

    Drying Shrinkage

    Fire Rating ASTM E 119As directed

    by theEngineer

    ProjectSpecifications

    Mortar Project SpecificationsAs recommended

    by themanufacturer

    Portland Cement:

    Works below Ground Slab (SRC) BS 4248

    Project SpecificationsWorks above Ground Slab (OPC) BS EN 197-1

    Sand BS EN 13139 Project Specifications

    AccessoriesAs directed by

    the EngineerProject Specifications

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    3. Works and Material shall conform to Dubai Municipality andInternational Standards.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    60/98

    58

    Go To Contents

    CLAY MASONRY BLOCKS WITH POLYSTYRENE INSERT

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    A Composition/Selection

    Dimensions and CompressiveStrength

    Dubai MunicipalityStandard

    Every 20,000blocks

    Thermal Conductivity of Block

    Thermal Conductivity ofThermal Insulation

    Density of Thermal Insulation

    Water Absorption

    Apparent Density

    Block Efflorescence

    Fire Rating (Polystyrene)ASTM D 2863,BS EN 11925-2

    As directedby the

    Engineer

    ProjectSpecifications

    Mortar Project SpecificationsAs recommended

    by themanufacturer

    Portland Cement:

    Works below Ground Slab (SRC) BS 4248

    Project SpecificationsWorks above Ground Slab (OPC) BS EN 197-1

    Sand BS EN 13139 Project Specifications

    Accessories As directed bythe Engineer Project Specifications

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    3. Works and Material shall conform to Dubai Municipality andInternational Standards.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    61/98

    59

    Go To Contents

    LATH AND PLASTER

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    Cement Plaster

    Portland CementBS 12, 146, 215,

    4027 and BS 5224

    As directedby the

    Engineer

    ProjectSpecifications

    Lime BS 890

    Sand BS 1199

    Aggregates BS 882

    Water BS 3148

    Ready Mix RenderingMaterial

    BS 4721

    Bagged RenderingMaterial

    BS 5262

    Plaster Accessories BS 5262

    Pull-Off Test BS 1881-207

    Notes:

    1. Additional testing will be conducted at the request of the Engineerand/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    3. Works and Material shall conform to the following codes:

    Code of practice for External Rendered Finishes BS 5262Code of practice for Internal Plastering BS 5492

    Code of practice for Plastering and Rendering BS 8000 Part 10

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    62/98

    60

    Go To Contents

    POLYSTYRENE THERMAL INSULATION

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY NOTES

    Compressive Strength andDimensions

    Project SpecificationsAs directed

    by the

    Engineer

    Thermal Conductivity

    Density

    Water Absorption

    Flexural Strength

    Water Vapour Permeance

    Dimensional Stability

    Oxygen Index

    Notes:

    1. Additional testing will be conducted at the request of the Engineer

    and/or Authority.

    2. Contract Specifications are to be implemented if more or other testsare required.

    3. Works and Material shall conform to Dubai Municipality andInternational Standards.

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    63/98

    61

    Go To Contents

    PAINTING

    Schedule of Tests and Inspections

    DESIGNATION NORMATIVE DOCUMENT FREQUENCY / NOTES

    Specific Gravity ASTM D 1650

    Project Specification / asrequired by the Engineer

    Solid Content ASTM D 2139

    Drying Time ASTM D 1650

    Adhesion Strength ASTM D 4541

    Abrasive Strength ASTM D 4060

    Impact ASTM D 2794

    Hardness ASTM D 2240

    Crack Bridgeability ASTM D 836

    Non Volatile Matter ASTM D 2939

    Fungus Resistance ASTM D 2734

    UV Resistance ASTM 653

    Salt Spray Resistance ASTM B117

    SECTION 4 : SCHEDULE OF TESTS AND INSPECTIONS

  • 7/26/2019 Construction Materials E-Book

    64/98

    62

    Go To Contents

  • 7/26/2019 Construction Materials E-Book

    65/98

    63

    Go To Contents

    SECTION 5 : QC FORMS

    NON-CONFORMANCE REPORT

    Project : ___________________________________________________________________________

    Client : _________________________________________ NCR No. : _____________________

    Project Manager : _________________________________________ Date : _____________________

    Consultant : _________________________________________

    Contractor : _________________________________________ Location : _____________________

    Sub-Contractor : _________________________________________ Category : _____________________

    Non-Conformance:

    ____________________________________________________________________________________________

    ____________________________________________________________________________________________

    ____________________________________________________________________________________________

    ____________________________________________________________________________________________

    Issued by: _________________ Signature: ___________________

    Requirements

    Specifications : ___________________________________________________________________________

    Standards : ___________________________________________________________________________

    Drawings : ___________________________________________________________________________

    Other : ___________________________________________________________________________

    Received by Contractor/Sub-Contractor:Name: ________________ Position: ________________ Signature: _____________ Date: ______________

    Cause of Non-Conformance:

    ____________________________________________________________________________________________

    Name: ________________ Position: ________________ Signature: _____________ Date: ______________

    Proposed Corrective Action by Contractor/Subcontractor:

    ____________________________________________________________________________________________

    ____________________________________________________________________________________________

    ____________________________________________________________________________________________

    Name: ________________ Position: ________________ Signature: _____________ Date: ______________

    Comments by Project Manager/Consultant:

    Accept: Accept with comments: Reject:

    ____________________________________________________________________________________________

    ____________________________________________________________________________________________

    ____________________________________________________________________________________________

    Name: ________________ Position: ________________ Signature: _____________ Date: ______________

    Corrective Action Completed/Verified:

    QA/QC Manager Name: ________________ Signature: _____________ Date: ______________

  • 7/26/2019 Construction Materials E-Book

    66/98

    64

    Go To Contents

    STATUSOFNON-

    CON

    FORMANCEREPORTS

    Proje

    ct

    :______________________________________________________

    _________________________________

    ____________________________________

    Clien

    t

    :______________________________________________________

    _

    NCRReportNo.:________________________________

    Proje

    ctManager:______________________________________________________

    _

    Date

    :_

    ____________________________________

    Cons

    ultant

    :______________________________________________________

    _

    Cont

    ractor

    :______________________________________________________

    _

    Location

    :_

    ____________________________________

    Sub-Contractor:______________________________________________________

    _

    Category

    :_

    ____________________________________

    NC

    RRef.

    No.

    Date

    Issued

    Description

    Contractor

    Consultant/ProjectManag

    er

    Date

    Received

    Date

    Returned

    Accepted/

    Date

    Rejected

    /

    Date

    SECTION 5 : QC FORMS