Construction Inspection of Concrete Dams and Spillway

50
Inspection of Construction of Concrete Dams & Spillways Autoridad del Canal de Panama (ACP) 1

description

Construction Inspection Best Practices

Transcript of Construction Inspection of Concrete Dams and Spillway

Page 1: Construction Inspection of Concrete Dams and Spillway

Inspection of Construction of Concrete Dams & Spillways

Autoridad del Canal de Panama (ACP) 1

Page 2: Construction Inspection of Concrete Dams and Spillway

Day 2 - Session 4Construction Inspection Best

Practices

Autoridad del Canal de Panama (ACP) 2

Page 3: Construction Inspection of Concrete Dams and Spillway

Construction Inspection Best Practices

• Initial Inspection

• Daily Reports

• Inspection Checklists

• Worksheets

• Construction Closeout

• Open Discussion

Autoridad del Canal de Panama (ACP) 3

Page 4: Construction Inspection of Concrete Dams and Spillway

Initial Inspection

• Prior to beginning work:– Contractor must receive signed NTP– Approved safety officer and safety plan– Safety meeting must be conducted prior to

beginning work– At least one person from each foreman’s crew

must hold a current first-aid card– Hard hat sign must be prominently displayed

at all construction site entrances

Autoridad del Canal de Panama (ACP) 4

Page 5: Construction Inspection of Concrete Dams and Spillway

Initial Inspection

• Prior to beginning work: (continued)– A National Pollution Discharge Elimination

System (NPDES) permit notice poster must typically be prominently displayed at all construction site entrances

– Stormwater Pollution Prevention Plan (SWPPP) must be implemented and other NPDES requirements addressed

Autoridad del Canal de Panama (ACP) 5

Page 6: Construction Inspection of Concrete Dams and Spillway

Initial Inspection

• Prior to beginning work: (continued)– Emergency contact information must be

posted on the contractor’s bulletin board– Sanitation facilities must be operational – Utilities and existing works must be identified

and protected – Utility owners must be notified whenever there

are utilities in the area that may be affected by the construction activity

Autoridad del Canal de Panama (ACP) 6

Page 7: Construction Inspection of Concrete Dams and Spillway

Daily Reports

• One of the most overlooked parts of construction inspection

• Inspector’s primary responsibility is to verify work is being completed according to the specifications

• Primary importance of inspector’s daily report is to advise supervisors of the day’s work and to report pay quantities

Autoridad del Canal de Panama (ACP) 7

Page 8: Construction Inspection of Concrete Dams and Spillway

Daily Reports

• Daily reports should be:– Clear– Effective– Factual– Readable– Usable by others

• Will be reviewed by people who are not there, not on the job

Autoridad del Canal de Panama (ACP) 8

Page 9: Construction Inspection of Concrete Dams and Spillway

Daily Reports

• Properly Document:– Construction Activities– Procedures– Schedules– Materials– Quantities– Test Results– Problems– Other

Autoridad del Canal de Panama (ACP) 9

Page 10: Construction Inspection of Concrete Dams and Spillway

Daily Reports

• Purpose:– Inform supervisor– Inform other inspectors– Calculating payments– Settling claims– Closing out contract– Review of structural failures– Design process of future projects

Autoridad del Canal de Panama (ACP) 10

Page 11: Construction Inspection of Concrete Dams and Spillway

Daily Report

• Use “concrete terms” and “lowest rung on the ladder”

• Abstraction ladder example

pipe

metal pipe

corrugated metal pipe

600-mm diameter corrugated metal pipe

600-mm diameter corrugated metal pipe, No. 16-gage

Autoridad del Canal de Panama (ACP) 11

Page 12: Construction Inspection of Concrete Dams and Spillway

Daily Reports

General Terms

“Poor weather conditions” could mean rain, or it could mean snow, or even intense heat. It could mean any variations between these extremes. So in describing the weather, you should say specifically what kind of weather was experienced; such as “rain started to fall at 11 a.m. and continued steadily for two hours. The sun broke through at 1:30 p.m. The temperature was about 28 degrees for the rest of the day.”

Autoridad del Canal de Panama (ACP) 12

Page 13: Construction Inspection of Concrete Dams and Spillway

Daily Reports

General Terms

The workforce started the day late and didn’t really get much done. For some reason the pump broke and that caused us some problems. The foreman added more men to the already large crew to help with the pump problem. The weather didn’t help either; it was bad.

Autoridad del Canal de Panama (ACP) 13

Page 14: Construction Inspection of Concrete Dams and Spillway

The workforce started the day late and didn’t really get much done. For some reason the pump broke and that caused us some problems. The foreman added more men to the already large crew to help with the pump problem. The weather didn’t help either; it was bad.

Daily Reports

General Terms

Autoridad del Canal de Panama (ACP) 14

Page 15: Construction Inspection of Concrete Dams and Spillway

Daily Reports

• Organize your thoughts

• Daily reports must be clear and simple

• Writing must be simple, direct and easy to understand

• Avoid being indirect and wordy

• First step – systematic organization of your thinking

• Fix your ideas in your own mindAutoridad del Canal de Panama (ACP) 15

Page 16: Construction Inspection of Concrete Dams and Spillway

Daily Reports

WHO – WHAT – WHERE – WHEN – HOW

EQUIPMENT – WEATHER - SAFETY

Autoridad del Canal de Panama (ACP) 16

Page 17: Construction Inspection of Concrete Dams and Spillway

Daily Reports

Autoridad del Canal de Panama (ACP) 17

Page 18: Construction Inspection of Concrete Dams and Spillway

Daily Reports

Autoridad del Canal de Panama (ACP) 18

Page 19: Construction Inspection of Concrete Dams and Spillway

Daily Reports

• Communications with the Contractor– What did the contractor complain about?– What questions did the contractor ask me?– What did I tell the contractor?

Autoridad del Canal de Panama (ACP) 19

Page 20: Construction Inspection of Concrete Dams and Spillway

Daily Reports

Autoridad del Canal de Panama (ACP) 20

Page 21: Construction Inspection of Concrete Dams and Spillway

Daily Reports

Autoridad del Canal de Panama (ACP) 21

Page 22: Construction Inspection of Concrete Dams and Spillway

Daily Reports

• Manpower & Equipment Report

Autoridad del Canal de Panama (ACP) 22

Page 23: Construction Inspection of Concrete Dams and Spillway

Daily Reports• Drilling Report

Autoridad del Canal de Panama (ACP) 23

Page 24: Construction Inspection of Concrete Dams and Spillway

Daily Reports• Water Pressure Test Report

Autoridad del Canal de Panama (ACP) 24

Page 25: Construction Inspection of Concrete Dams and Spillway

Daily Reports• Grouting Report

Autoridad del Canal de Panama (ACP) 25

Page 26: Construction Inspection of Concrete Dams and Spillway

Daily Reports• Grouting Record Plot

Autoridad del Canal de Panama (ACP) 26

Page 27: Construction Inspection of Concrete Dams and Spillway

Daily Reports

• Photographs– Unusual conditions or situations– Completed projects– Dated & location noted (photographer name)– Include person or object for scale– Changed conditions, damaged equipment or

materials– General work progress periodically– Captions required in reports

Autoridad del Canal de Panama (ACP) 27

Page 28: Construction Inspection of Concrete Dams and Spillway

Inspection Checklists

• Assist inspectors in performing inspections

• May not include all items

• Provide guidance only

• Not a comprehensive list

• Customize for each project and specs

• Document in daily report when checklist is completed

Autoridad del Canal de Panama (ACP) 28

Page 29: Construction Inspection of Concrete Dams and Spillway

Inspection Checklists

• Examples checklists included in workbook– Quality Assurance Inspection– Construction Safety– Construction Surveying– Quantity Computations– Construction Erosion and Pollution Control– Foundation Preparation– Removal of Water– Excavation– RCC Construction

Autoridad del Canal de Panama (ACP) 29

Page 30: Construction Inspection of Concrete Dams and Spillway

Inspection Checklists

Concrete Forms

Autoridad del Canal de Panama (ACP) 30

Page 31: Construction Inspection of Concrete Dams and Spillway

Inspection Checklists

Reinforcement

Autoridad del Canal de Panama (ACP) 31

Page 32: Construction Inspection of Concrete Dams and Spillway

Inspection Checklists

Finishing Concrete Surfaces

Autoridad del Canal de Panama (ACP) 32

Page 33: Construction Inspection of Concrete Dams and Spillway

Inspection Checklists

Joints & Waterstops

Autoridad del Canal de Panama (ACP) 33

Page 34: Construction Inspection of Concrete Dams and Spillway

Inspection Checklists

Curing Concrete

Autoridad del Canal de Panama (ACP) 34

Page 35: Construction Inspection of Concrete Dams and Spillway

Inspection Checklist

RCC Construction

Autoridad del Canal de Panama (ACP) 35

Page 36: Construction Inspection of Concrete Dams and Spillway

Inspection ChecklistSpillway Gates

Autoridad del Canal de Panama (ACP) 36

Page 37: Construction Inspection of Concrete Dams and Spillway

Inspection ChecklistSpillway Gates

Autoridad del Canal de Panama (ACP) 37

Page 38: Construction Inspection of Concrete Dams and Spillway

Concrete ConstructionRecords and Reports

Autoridad del Canal de Panama (ACP) 38

• Documents to place in contract files:– Mix Computations

• Trial mix computations and adjustments• Selection of job mixture

– Batching and mixing records• Records of daily batching operations• Summary of batching and mixing records• Summary of volume of each class placed

Page 39: Construction Inspection of Concrete Dams and Spillway

Concrete ConstructionRecords and Reports

Autoridad del Canal de Panama (ACP) 39

• Documents to place in contract files:– Placing and Curing Records

• Amount of concrete placed in individual parts of the structures each day

• Time curing medium was applied, forms were removed, defective surfaces were repaired and curing was applied

Page 40: Construction Inspection of Concrete Dams and Spillway

Concrete ConstructionRecords and Reports

Autoridad del Canal de Panama (ACP) 40

• Documents to place in contract files:– Strength Tests

• Reference test results report in job diary• Report numbers assigned to all test specimens

shipped to the laboratory• Report location and amount of concrete

represented by each strength test

Page 41: Construction Inspection of Concrete Dams and Spillway

Concrete ConstructionRecords and Reports

Autoridad del Canal de Panama (ACP) 41

• Documents to place in contract files:– Inplace concrete

• Further tests may be needed If tests indicate inadequate concrete compressive strength

• Core samples from structure• “Swiss Hammer” can help determine extent of

questionable concrete • Do not use to determine strength for acceptance or

earliest time forms can be stripped

Page 42: Construction Inspection of Concrete Dams and Spillway

Worksheets

• Designed to assist inspectors

• Document in daily report when worksheet is completed

• Include worksheet with daily report

• Examples:– NRCS NEH Part 645 App A– USACE Quality Assurance Representatives

Guide EP 415-1-261

Autoridad del Canal de Panama (ACP) 42

Page 43: Construction Inspection of Concrete Dams and Spillway

Worksheets

Autoridad del Canal de Panama (ACP) 43

Page 44: Construction Inspection of Concrete Dams and Spillway

Worksheets

Autoridad del Canal de Panama (ACP) 44

Page 45: Construction Inspection of Concrete Dams and Spillway

Site Cleanup

• Worksite and surrounding areas used by contractor kept in orderly condition at all times during work

• All areas properly restored before the completed work is accepted

• Cleanup requirements are stated in the contract

Autoridad del Canal de Panama (ACP) 45

Page 46: Construction Inspection of Concrete Dams and Spillway

Site Cleanup

• Plant, buildings, unused materials, cleared material and other debris – removed from site

• Access and haul roads – appropriately restored

• Fences, utilities and other facilities temporarily removed - restored

Autoridad del Canal de Panama (ACP) 46

Page 47: Construction Inspection of Concrete Dams and Spillway

Construction Closeout

• Records and materials– Name, make, and model number of each piece of

equipment– All equipment test records– Approved shop drawings– Operating and maintenance instructions– Spare parts and tools– Keys– Guarantees with required contact and expiration date– Record Drawings

Autoridad del Canal de Panama (ACP) 47

Page 48: Construction Inspection of Concrete Dams and Spillway

Open Discussion

Autoridad del Canal de Panama (ACP) 48

Page 49: Construction Inspection of Concrete Dams and Spillway

Acknowledgements

• Natural Resource Conservation Service– National Engineering Handbook Part 645 –

Construction Inspection– National Engineering Handbook Section 19 –

Construction Inspection

Autoridad del Canal de Panama (ACP) 49

Page 50: Construction Inspection of Concrete Dams and Spillway

Acknowledgements

• U.S. Bureau of Reclamation– Construction Inspector Training Program

• U.S. Army Corps of Engineers– Quality Assurance Representative's Guide

EP 415-1-261 (Vol 1-5)

Autoridad del Canal de Panama (ACP) 50