Construction Fire Safety in British Columbia - FPOA January 2013 Chapter Meeting... · governing...

55
Construction Fire Safety in British Columbia CFT Engineering Inc. Presenters: Katarina Burgess, P.Eng., CP John Bolduc, BASc, EIT Brad Walton, AScT

Transcript of Construction Fire Safety in British Columbia - FPOA January 2013 Chapter Meeting... · governing...

Construction Fire

Safety in British

Columbia

CFT Engineering Inc.

Presenters:

Katarina Burgess, P.Eng., CP

John Bolduc, BASc, EIT

Brad Walton, AScT

Background and Purpose

Background: CFT Engineering Inc. was

contracted by Forestry Innovations

Investments to prepare a report on

construction fire safety in British Columbia.

For this project CFT Engineering

collaborated with members of the Building

Safety Standards Branch, WorkSafe BC

and the Wood Enterprise Coalition

Background and Purpose

Purpose: To review current legislation

regulating construction fire safety and

current industry practice, and to provide

recommendations for potential changes to

legislation and enforcement practices

governing construction fire safety in British

Columbia

Background and Purpose

Context: The report was published prior to

the adoption of the 2012 BC Fire Code

and the 2012 BC Building Code.

Outline for this Presentation

Introduction

Levels of Risk during Construction

Key Legislative Requirements (2006 BCFC & BCBC)

Enforcement

Alberta Perspective

IBC and NFPA Perspective

Reported Fires (2005-2011)

Findings from Site Investigations

Fire Department Response to Construction Fires

Conclusions from Report

Recommendations from Report

Adoption of the 2012 BC Fire Code (Time permitting)

What Makes Construction Fire

Safety Risk Unique?

Incomplete fire separations (passive protection)

Lack of functional/commissioned fire suppression and detection systems (active protection)

Inadequate water supply for manual firefighting

Fire Department response effectiveness

Increased risk of incendiary fires due to periods where the site is unoccupied, and the incompleteness of security devices

Hazardous operations that take place at construction sites (e.g. hot works)

Levels of Risk during Construction

Phased Occupancy:

There is a greater risk when buildings under construction are partially occupied

BC Fire Code requires a 1 hr separation

BC Fire Code requires alarms or watched tours

Water Supply

The water supply needed to fight fires in buildings under construction is often greater than what is needed for completed buildings

Risk Level for Construction

Phases

2006 Legislative Requirements

Objectives: To provide a framework for reducing or eliminating identifiable risks to fire and life safety

BC Fire Code contains the majority of legislative requirements for construction fire safety

BCBC addresses the issue through the requirement in Part 8 of the BC Building Code to conform with the BC Fire Code

BC Occupational Health and Safety Standard contains some supplementary requirements

2006 Legislative Requirements

Fire Safety Plan

Required by the

2006 BC Fire Code

Checklists have

been developed by

the Office of the Fire

Commissioner and

municipalities

including the Surrey

Fire Service

2006 Legislative Requirements

Active System (e.g. detection and fire suppression systems) BC Fire Code requires that a system is provided to

alert site personnel of a fire. Air horns are typically provided.

Does not require a fixed automatic detection system

Passive System (e.g. fire separations) BC Fire Code requires that one usable exit be

maintained

BC Fire Code requires a 1 hour separation between occupied areas and areas under construction.

2006 Legislative Requirements

Manual Suppression Systems

BC Fire Code requires that extinguishers be provided in specific areas

The BC Fire Code requires standpipe systems be installed progressively

Limiting Combustible Materials

Combustible refuse in sufficient quantities to constitute a fire hazard is required to be moved to a safe location

Barricades

BCBC requires perimeter barricades

BC Fire Code requires fencing for outdoor storage

See Appendix A note

2006 Legislative Requirements

Hot Works BC Fire Code requires that hot works be monitored with

a fire watch during hot work and after completion

Smoking BC Fire Code limits smoking to permitted areas.

Heating Equipment The BC Fire Code requires clearances between

combustible materials and temporary heating equipment to conform with Part 6 of the BC Building Code or minimum clearances shown on certified heating equipment.

Enforcement of Legislative

Requirements

The Authority Having Jurisdiction (Fire and

Building Authority) is responsible for auditing

construction fire safety plans and practices

Ultimate responsibility lies with the owner, who

typically delegates the implementation of safety

practices to the general contractor

Many municipalities now require the submission

of a construction fire safety plan before

construction commences

Construction Fire Safety in

Alberta The 2006 Alberta Fire Code has additional or

more detailed “unique to Alberta” requirements. Key requirements that differ from the BC Fire Code are as follows: Requirements for adjacent buildings or facilities to be

protected from buildings under construction.

Additional requirements for access for firefighting. This is also a requirement of the BCBC, but the wording in the Alberta Fire Code is more specific.

Extensive additional requirements for the progressive installation of standpipe systems

Construction Fire Safety in

Alberta

Alberta Standatas have been developed

to address:

Fire Department access

Water supply

Standardization of requirements for

construction fire safety

Construction Fire Safety in the

United States

2012 International Building Code requires:

At least one lit stairway be provided where a building

is at least 50 ft. or four storeys

A specific requirement for standpipe installation

An acceptable water supply be provided as soon as

combustible material is on site

NFPA 241, “Standard for Safeguarding

Construction, Alteration and Demolition

Operations” has additional information for

construction fire safety

Construction Fire Data

CFT Engineering Inc. obtained information

from the Office of the Fire Commissioner

regarding reported construction fires from

2005 to 2009 in BC

Reports are now also available for 2010

and 2011

Construction Fire Data

Reported Fires on Construction/Demolition Sites between 2005 and 2009:

275 were reported

Resulted in 10 injuries and one fatality

Resulted in equipment and property loss valued at over $53 million

Additional fires during 2010 and 2011:

94 additional fires reported (369 total)

One additional injury and one additional fatality

Equipment and property loss valued at over $65 million ($118 million total)

Total Reported Cost of Construction Fires

$0

$50,000,000

$100,000,000

2004 2005 2006 2007 2008 2009 2010 2011 2012

Number of Reported Constuction Fires in British Columbia

0

50

100

2004 2005 2006 2007 2008 2009 2010 2011 2012

Incendiary and Suspicious Fires in Construction

223, 60%

146, 40%Incendiary/Suspicious

Other

Incendiary Fires Occuring vs. Time of Day

0

5

10

15

20

25

0:0

0

1:0

0

2:0

0

3:0

0

4:0

0

5:0

0

6:0

0

7:0

0

8:0

0

9:0

0

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0Nu

mb

er

of

Inc

en

dia

ry

Fir

es

Non Incendiary Fires Occuring vs. Time of

Day

05

10152025

0:0

0

1:0

0

2:0

0

3:0

0

4:0

0

5:0

0

6:0

0

7:0

0

8:0

0

9:0

0

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0N

um

be

r o

f N

on

Inc

en

dia

ry F

ire

s

Site Investigations

CFT Engineering Inc. reviewed construction sites to assess fire protection practices in BC

Legislative requirements were largely adhered to

Hazards specific to construction activities that were noted included: Accumulation of combustibles

Delayed communication with the Fire Department regarding available systems

Delays in charging installed fire protection systems

Delayed installation of fire pumps for highrises Not commissioned prior to occupancy

Fire Department Response to

Construction Fires

The Fire Department’s response to a

construction site which is not anticipated to have

persons in the buildings will typically be less

aggressive

If the site is expected to be vacant and adjacent

properties are at risk, the Fire Department may

prioritize the protection of adjacent properties

Pre-incident response planning can improve the

effectiveness of Fire Department operations

Conclusions from the Report

A key element of fire safety in construction is the development of a working active construction fire safety plan

Current requirements lack sufficient guidance on how to incorporate procedures to mitigate site specific risks

Additional guidance and education for risk mitigation is needed

Mitigating strategies should become industry practice

Recommendations

Linking of BC Building Code and Fire Code:

In order to increase the awareness of the requirements

for construction fire safety of professionals and

contractors involved in the construction industry, it is

recommended that there be a reference to the BC Fire

Code requirements relating to construction fire safety

within Division B, Part 3 and Division B, Part 9, Article

9.10.1.2, of the BC Building Code

Division B, Part 1, Subsection 1.1.4 of the BC Building

Code should be revised to include a reference to the

construction fire safety plan

Recommendations

Assignment of a Fire Safety Coordinator

In order to provide continual monitoring of risks throughout the different construction phases

Should keep workers up to date on with emergency procedures

Should monitor the site with respect to the construction fire safety plan

Should provide a single point of contact to the fire services

Should be trained to identify basic hazards

Recommendations

Fire Warning and Alarm:

BCFC Article 5.6.1.9 should be amended to

include a fire warning system when the site is

not active, such as after hours

A fire warning system may be a fire watch or

active detection systems or a combination of

fixed detection and manual fire watch,

potentially supplemented by lighting and

security cameras

Recommendations

Coordinating Registered Professional:

BC Building Code Part 2, Division C, Article

2.2.7.3 (Appendix A) should provide general

direction to inform the owner and constructor

that as part of the project planning, a CFSP is

required by the BC Fire Code, Section 5.6,

“Construction and Demolition Sites”.

Recommendations

Adequate Water Supply for Fire Fighting:

BCFC Article 5.6.1.4 should be amended to

require the provision of a water supply for

firefighting to the site as soon as combustible

material arrives onsite

This may require early coordination with the

City, Engineering Department, consultants

and trades, or a temporary water supply for

firefighting could be provided

Recommendations

Fire Risk Assessment Management BC Fire Code Division B, Appendix A 5.6 should

add an explanatory note stating that it is essential that a risk assessment of potential fire hazards be carried out

Risk assessment should include risks to adjacent property, facilities and wildland

Findings and recommendations from the risk assessment would form the approach to risk mitigation in the construction fire safety plan

A review and analysis of risks associated with adjacent properties or facilities should be completed by a knowledgeable professional for complex or higher risk sites

Recommendations

Pre-construction Meeting:

There should be a suggestion within the BC

Fire Code, Division B, Appendix A, for a pre-

construction meeting upon issuance of building

permit

The Fire Department and/or local assistant to

the fire commissioner should be invited to this

meeting

Recommendations

Construction Fire Safety Plan Universal and detailed guidelines should be provided to

the industry concerning the development of a construction fire safety plan and the implementation of construction practices

Current minimum requirements should be expanded to include the submission and review of the plan by the Fire Department and/or the Authority Having Jurisdiction

The plan should be required to be updated at regular intervals

The City of Surrey bulletin could be used as an example for other municipalities

Recommendations

Development of Fire Protection Practice to

Mitigate Risk during Construction

Guidelines should be established and

reviewed with WorkSafe BC with respect to

requirements for construction sites in order to

establish industry practice

Recommendations

Development of Fire Protection Practice to Mitigate Risk during Construction Examples may include:

Provision of an unobstructed stair at each floor level

Priority given to fire separation, firewall and closure installation Security measures

Exposure Protection

Charging the sprinkler system where practical

Installation of fire pumps for standpipes, hydrants and hose stations

Industry practice cannot be legislated, but through a combination of legislation, comprehensive guidelines and education, these practices should become the standard practice for all sites

Recommendations

Provision and Maintenance of Fire

Department Access:

A Code conforming Fire Department access

route to the construction site should be

available as soon as work commences at the

site

A drawing showing the layout of the site and

the fire protection features should be available

at the main Fire Department response point

Recommendations

Management of Ignition Source and

Combustible Content:

Procedures should be developed and

implemented to control sources of ignition and

also to prevent accumulation of combustible

materials

Recommendations

Responsibility and Enforcement:

A method should be established for regular

auditing of fire safety at construction sites

Ownership and responsibility for construction

fire safety should be clearly established

This could be achieved through the requirement of

regular field reviews undertaken by either the

Authority Having Jurisdiction or knowledgeable

professional

Adoption of the 2012 BC Fire Code

The 2012 BC Fire Code has included

significant changes to Section 5.6

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code

Adoption of the 2012 BC Fire Code