Construction Big Room : Creating Reliable Workflow Using Visual Management Linbeck: Jason Becker, Jennifer Oliverio, Keyan Zandy

Transcript of Construction Big Room – Creating Reliable Workflow · PDF fileConstruction Big Room :...

Construction Big Room :

Creating Reliable Workflow Using Visual Management

Linbeck: Jason Becker, Jennifer Oliverio, Keyan Zandy

The Journey: Genesis

The Beginning: Linbeck Implements the Last Planner System at Rice Chemistry Building In 1998

Original Schedule 14 MonthsRice Schedule 11 MonthsCompleted in 9 Months/Under Budget

Lessons Learned:Better CommunicationHigher ProductivityTrustLess Rework

Last Planner System is rolled on all projects.

The Journey: The Current Condition

• Management of paperwork is tedious• Lean packets become outdated shortly after the meeting• Meetings are too long• Not enough emphasis on root causes for work not

completed• System is not visual• Trade Partner communication could use improvement

The Journey: Goal/Target Condition

•Meet daily•15-20 minutes•Less paper work•Improved Communication•Improved Coordination•Less Excuses•Increased Accountability•Higher Planned Percent Complete scores

The Journey: The Lean Boards

The Journey: The Lean Boards

2 Week Look-AheadBoard

•Milestones

•Tasks

•Constraints

•Man hours Per Task

•Workable Backlog

•Safety/QC/Inspections

The Journey: The Lean Boards

Constraint/Resolution

Board

•Capture Daily Constraints

•Keeps the meeting focused

•Follow-up as a breakout meeting

•Consensus when items are closed out

The Journey: The Lean Boards

Issue/Action Board

•Tracks complicated constraints•Assigns Accountability and a due dates

•Allows the team to understand the actions being taken•Allows the team to understand the status of the issue

The Journey: The Lean Boards

Delivery Board

•Helps Trade partners plan•Just in Time Delivery method

•Interacts with the 2 week board•Improves reliability

The Journey: The Lean Boards

Inspection Board

•Communicates Inspection dates•Updates the team

•Interacts with the 2 Week Board

The Journey: The Lean Boards

The Journey: The Lean Boards

Floor plans/Elevations

•Visually Communicate

•Collaborate & Plan

•Work Flow Leveling

•Improves Coordination

• Disciplined discussions lasting 15 minutes

• Allow Trade Partners to facilitate the meeting

• Discuss only key issues effecting milestones

• Recognize what is a side conversation and what is not

Lessons Learned:

Continuous Improvement - Going Beyond Last Planner

• Milestone Pull Planning Wall• Video Display PPC• “The Big Room”

Milestone Pull Planning Wall

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

END

Mech

Elec

Plumb

Blank

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

END

Mech

Elec

Plumb

BlankLeft Blank for Day-to-Day Pull Planning, Change Assessments

Video Display PPC

Multiple Uses:• Hi-Res BIM Coordination on site• View Safety Videos for Jobsite Orientation• Display for iPad/iPhone Jobsite Photos at Daily Huddles

“The Big Room”

Construction Big Room :

Creating Reliable Workflow Using Visual Management

Linbeck: Jason Becker, Jennifer Oliverio, Keyan Zandy