constructed wetland
description
Transcript of constructed wetland
-
621
Environmental Technology, Vol. 28. pp 621-628 Selper Ltd., 2007
PERFORMANCE AND COST COMPARISON OF A FWSAND A VSF CONSTRUCTED WETLAND SYSTEM
V. A. TSIHRINTZIS1*, C. S. AKRATOS1, G. D. GIKAS1, D. KARAMOUZIS2 AND A. N. ANGELAKIS3
1Laboratory of Ecological Engineering and Technology, Department of Environmental Engineering,Democritus University of Thrace, 67100 Xanthi, Greece
2Hydraulics, Soil Science and Agricultural Engineering Division, Department of Agriculture,Aristotle University of Thessaloniki, 54124 Thessaloniki, Greece
3Institute of Iraklio, National Foundation for Agricultural Research, P.O. Box 2229,71307 Iraklio, Greece
(Received 1 February 2006; Accepted 10 January 2007)
ABSTRACT
Two constructed wetland systems, treating domestic wastewater, are compared in terms of performance and costs. One is afree water surface (FWS) wetland system located in Pompia, Crete, south Greece, and the other one is a vertical subsurfaceflow (VSF) wetland system located in Gomati, Chalkidiki, north Greece. The FWS system is designed for 1200 p.e. Itsconstruction cost was 305,000, and the capital, operation and maintenance cost was 22.07 p.e.-1 yr-1 or 0.50 m-3 ofinfluent. The VSF system is designed for 1000 p.e. Its construction cost was 410,850, and the capital, operation andmaintenance cost was 36.81 p.e.-1 yr-1 or 0.56 m-3 of influent. Both systems achieved high removal rates for BOD5, COD,TSS, TKN, phosphorus, TC, and FC, which makes them ideal for small communities in the Mediterranean region.
Keywords: Free-water surface constructed wetland, vertical subsurface flow constructed wetland, treatment performance,
construction cost; operation cost
INTRODUCTION
Constructed wetland (CW) wastewater treatment
systems are considered more reliable compared to
conventional systems [1], and are ideal technologies for small
communities, due to their low construction, operation and
maintenance costs, easy adaptation to the environment and
limited generation of by-products [2,3].
One question however, is which is the optimum CW
type (i.e., free-water surface (FWS), horizontal subsurface flow
(HSF) or vertical subsurface flow (VSF) system) to use in a
specific region, in terms of performance, costs, area
requirements, and other factors. Most studies in the literature
emphasize specific systems in terms of general performance
[4-9]. Other studies examine the effect of various design
parameters [10-13]. Comparisons of various CW types in the
same region are limited (e.g., [14,15]). Construction and other
cost data for CW systems are also limited (e.g., [16]). The
necessity of pretreatment is an issue for discussion, since
modified VSF designs in France operate successfully without
pretreatment [17, 18]. Finally, small-scale on-site CW systems
are now installed for single family use (e.g., [19]).
The aim of this paper is to provide a perspective for
applying constructed wetland technology in the
Mediterranean regions and specifically in Greece.
Descriptions, design considerations, construction cost,
constituent removal performance, and operation and
maintenance (O&M) costs of two constructed wetland
systems (a FWS and a VSF) are presented. Both systems treat
domestic wastewater and were designed for comparable
treatment capacities.
METHODS AND MATERIALS
System Description
Two constructed wetland systems treating domestic
wastewater are compared in terms of costs and performance.
One is a FWS wetland system located in Pompia, Crete, South
Greece, and the other is a VSF wetland system located in
Gomati, Chalkidiki, Macedonia, North Greece.
-
622
FWS system
The main components of the FWS system are [20]: (a) a
septic tank (up-flow reactor simulation) equipped with three
screen vault filters [3]; (b) a FWS constructed wetland
consisting of two basins in series, with surface areas of 4300
m2 and 1200 m2 (the inflow is uniformly distributed across at
the inlet of each basin using manifolds); (c) two chambers, one
in each basin, for regulating the water level; (d) small pumps
and a pipeline for the recirculation of the effluent back to the
inlet of the first basin; (e) a compost filter for odor control in
the septic tank.
Vegetation selection included two species of reeds
(Phragmites australis and Arundo donax). The facility was
constructed in the early months of 1999. The vegetation was
planted late in the winter of the same year, and due to the
favorable climatic conditions prevailing in the area, it
established well very rapidly. By the end of the year, the
vegetation was very dense and more than two meters in
height.
The basic parameters used in the design of the FWS
facility are [20]: population served 1200 p.e.; mean daily flow
rate 144 m3 d-1; maximum daily flow rate 216 m3 d-1;
maximum hourly flow rate 27.7 m3 h-1; influent biochemical
oxygen demand (BOD5) 400 mg l-1; septic tank effluent BOD5250 mg l-1; wetland effluent BOD5 10 mg l-1 and (COD)
-
623
with Phragmites australis. The HSF cell was not planted at the
time of the study and was out of the wastewater stream. The
VSF system was planted in May 2003 and was immediately
put to operation. The plants were dense and nearly fully-
grown by October 2003.
The route of the wastewater through the system is the
following: from the inflow structure to the rotating disk
screen and to the settling tanks. The sludge is collected at the
bottom of the settling tank (estimated volume 4.8 m3 week-1),
it is then pumped to the sludge digestion-stabilization tanks,
and then to the VSF sludge basins. The leachate collected at
the bottom of the VSF sludge basins is pumped back to the
siphon, and together with the wastewater from the settling
basins feed the stage I VSF basin (2 cells operate at a time).
Then, the wastewater is led to the stage II VSF basins (2 cells
operate at a time). In the future, the flow will continue to the
stage III HSF basin (not in operation now). The effluent of the
basin discharges into a nearby stream, approximately 5 km
from the coast.
The main design parameters for this system are
summarized as follows: the design population is 1000 p.e. The
design mean daily flow of the system is 180 m3 d-1. The
maximum hourly flow is 28.5 m3 h-1. The design hydraulic
loading rate is about 36 m yr-1, and the organic loading rate
196 kg ha-1 d-1. Design influent and effluent concentrations are
as follows: for BOD, influent 330 mg l-1, settling tank effluent
196 mg l-1, VSF effluent 12 mg l-1, HSF effluent < 10 mg l-1. For
total suspended solids(TSS), influent 380 mg l-1, settling tank
effluent 80 mg l-1, VSF effluent 12 mg l-1, HSF effluent < 10 mg
l-1.
System Monitoring, Sample Analysis and Statistics
Grab samples were collected regularly at various points
along the FWS system (i.e., inlet, settling tank outflow and
system outflow) over a 3-year monitoring period from August
1999 to August 2003, and along the VSF system (i.e., inlet,
settling tank outflow, siphon, stage I VSF outflow and stage II
VSF outflow over a monitoring period from July 2003 to
August 2004. The samples were analyzed in the laboratory
following APHA standard methods for BOD5, COD, TSS,
Total Kjeldhal Nitrogen (TKN), Total Phosphorus (TP) or PO4,
Total Coliforms (TC) and Faecal Colifoms (FC). Calculations
of statistical parameters of measured constituent
concentrations were performed in a spreadsheet.
Cost Evaluation Method
The actual construction cost of the two systems was
used. Since the FWS system was constructed in 1999 and the
VSF in 2003, for comparison the cost of the FWS was
expressed in 2003 prices using a reported inflation rate of
approximately 3.1%. An economical life of 30 years and a
capital discount factor of 6% were assumed to calculate net-
present-value cost [21]. Operation and maintenance costs
were obtained for the operation time periods from the records
of the local authorities operating the two facilities, and were
expressed in 2003 prices for the FWS system.
RESULTS
System Performance
FWS system
The results during the 3-year period of the FWS facility
monitoring could be summarized as follows: mean BOD5,
COD and TSS removals about 95%, mean TKN and TP
removals about 53%, and TC and FC removals >97% (without
any disinfection). Removal efficiencies of BOD5, COD, TSS,
TKN and TP in the final effluent for the monitoring period are
presented in Table 1. Very high removal rates of BOD5, COD
and TSS (94.4%, 96.1%, and 95.6%, respectively) have been
observed in the septic tank. On the other hand, low removal
rates of TKN and TP of 52.5% and 53.1%, respectively, have
Table 1. Measured concentrations of BOD (mg l-1), COD (mg l-1), TSS (mg l-1), TKN (mg l-1), and TP (mg l-1) in the influent
(IN), the septic tank effluent (SE) and the final effluent (FE), and overall efficiency (TE, %) for the FWS system in
Pompia, Crete, Greece.
Parameter BOD COD TSS TKN TP
IN SE FE TE IN SE FE TE IN SE FE TE IN SE FE TE IN SE FE TE
mg l-1 % mg l-1 % mg l-1 % mg l-1 % mg l-1 %
Average 165 39 7.7 94.4 455 100 18 96.1 191 36 5.6 95.5 38 25 18 52.5 13 9.1 6.2 53.1
Std. Error 31 4.0 1.3 1.0 31 9.8 2.7 0.5 40 5.4 0.8 0.9 3.4 1.7 1.7 4.8 1.5 1.3 1.1 4.7
Min 52 11 2.0 86.5 280 44 2.0 92.7 38 4.0 1.0 86.8 17 8.0 4.0 23.1 4.8 2.3 1.6 10.6
Max 540 60 16 99.1 798 180 40 99.6 720 90 12 99.3 62 36 27 83.1 24 22 21 78.5
# of Data 14 14 15 14 17 18 18 17 17 18 18 17 17 18 18 17 17 18 18 17
-
624
been obtained in the tank. TN and TP removed in the septic
tank were probably in organic form as particulate organic
matter. Lower removal rates of various constituents in similar
septic tanks have been reported [3].
VSF system
The monitoring results of the VSF system during the 13-
month period of operation could be summarized as follows:
BOD5 removals >92%, TKN removals >89%, and TC removal
>99% (without any disinfection). Removal efficiencies of
BOD5, COD, TSS, TKN and TP in the final effluent for the
monitoring period are shown in Table 2. Removals are
satisfactory, considering that the facility was still new and the
plant root system was probably not fully developed yet.
Relatively, high removal rates of BOD5, COD and TSS have
been measured in the settling tanks. On the other hand, lower
removal rates of TKN (77%) were observed, while TP removal
showed fluctuation and some times increased along the
hydraulic path of the system. It is obvious that to improve
nitrogen and phosphorus removals the last stage of the
system should also be planted and be put soon in operation.
System Costs
FWS system
System cost calculations are presented in Table 3. The
actual capital cost for the FWS system was 305,000 (prices of
1999, including 18% VAT). To compare this cost with that of
the VSF system, it was expressed as 344,615 in 2003 prices
(287.18 p.e.-1) using the 3.1 % inflation rate. This cost also
includes 115,000 for access road and administration room
construction and other works. Some of this work was not
actually necessary, such as extra roads outside of the facility.
In addition, the soil used for planting in the treatment cells
was transported from a distance of more than 10 km with a
relatively high cost. This work was also unnecessary. The net-
Table 2. Measured concentrations of BOD (mg l-1), COD (mg l-1), TSS (mg l-1), TKN (mg l-1) and TP(mg l-1) in the influent (IN),
the settling tank effluent (STE), the VSF effluent (VSF) and overall efficiency (TE, %) for the VSF system in Gomati,
Chalkidiki, Greece.
Parameter BOD COD TSS TKN TP
IN STE VSF TE IN STE VSF TE IN STE VSF TE IN STE VSF TE IN STE VSF TE
mg l-1 % mg l-1 % mg l-1 % mg l-1 % mg l-1 %
Average 485 193 39 92 626 243 62 89 1077 208 9 95 77 51 14 77 17.5 8.2 5.6 62
Std. Error 246 111 29 6 260 119 31 6 1784 474 13 8 47 50 6 20 9.0 3.9 3.1 22
Min 62 10 4 78 238 96 0 81 26 23 0 75 0 8 0 31 7.5 4.3 2.4 24
Max 819 355 92 100 1171 465 106 100 7060 2158 47 100 187 251 27 100 29.3 14.9 11.9 89
# of Data 20 20 19 20 20 20 19 20 20 20 19 20 20 20 19 20 8 8 8 8
Table 3. Capital and operating costs () for the two facilities.
Cost ()
Cost category FWS System VSF System
Capital, including VAT (construction cost) 344,615 410,850
Construction cost per p.e. 287.18 410.85
Net-present-value cost 25,036 29,848
Annual average O&M cost 1,445 6,960
O&M cost per p.e. per year 1.20 6.96
O&M cost per m3 per year 0.03 0.11
Total annual cost (capital and O & M) 26,481 36,808
Total annual cost per p.e. 22.07 36.81
Total annual cost per m3 of influent 0.50 0.56
-
625
present-value cost was estimated at 25,036 yr-1 using a 6%
discount factor. The total mean operation and maintenance
(O&M) cost of the FWS system in the first three years of
operation was estimated at 1,445 yr-1 (i.e., 1045 for energy
used, 300 for works, and 100, for miscellaneous expenses)
or 1.20 p.e.-1 yr-1 or 0.03 m-3 of influent. Net-present-value
cost and O&M cost are added to a total annual cost of 26,481,
and the mean figures become 22.07 p.e.-1 yr-1 or 0.50 m-3 of
influent.
VSF system
The total construction cost of the VSF system was
410,850 (prices of 2003, including 18% VAT) or 410.85 p.e.-1
This construction cost also included costs for access road (250
m paved road), construction of 550 m sewer line to bring
wastewater to the facility and 400 m sewer line for effluent
disposal to the final receiver, fencing, landscaping and other
works. These extra works are estimated at about 100,000.
The net-present-value cost was estimated at 29,848 yr-1. The
operation cost for the VSF system (for the first 10 months of
operation) comprises electricity (lighting and operation of 9
pumps, estimated at 67.50 month-1 on the average), salaries
for the operator and maintenance works (500 month-1 on the
average) and miscellaneous other expenses (12.50 month-1).
Therefore, the total operation cost is approximately 580
month-1 or 6,960 yr-1 or 6.96 p.e.-1 yr-1 or 0.11 m-3
of influent. Net-present-value cost and O&M cost are added to
a total cost of 36,808 and the mean figures become 36.81
p.e.-1yr-1 or 0.56 m-3 of influent.
Design, Construction and Operation Problems
No major problems were observed in the FWS
constructed wetland. It seems that this CW has been
designed, constructed and is operated very successfully. The
VSF constructed wetland achieves a high removal efficiency
for all pollutants. Nevertheless, it is believed that its
performance could be even better if some design, construction
and operation problems were resolved. These can be
summarized as follows.
Design problems
A major design problem is the sizing of the siphon that
feeds the first stage of the VSF cells (Fig. 1). The dimensions of
this siphon are 10x4.2x0.8m or 3.2m3 of flooding volume. The
siphon floods two cells at a time, i.e., 320 m2, therefore, the
average flooding depth is 1.0 cm. If one considers surface
irregularities of the planted cells, it is obvious that this depth
is small. Usually, 4 to 5 cm of flooding depth are
recommended. This problem was obvious in this facility. The
flooding was limited to about a 1 m wide area around the
perforated feeding pipes (Fig. 2), something seen by denser
plant growth in this area. Therefore, a major part of the
available facility area was not used, reducing active treatment
area and performance. To fix this problem, it is recommended
that the siphon is replaced to one of a larger size that would
provide at least 4 cm of flooding.
Figure 2. View of the stage I distribution pipe.
-
626
Constructions problems
A construction problem was the proper placing of the
porous media and the installation of filtering material. Some
porous media was washed out from the drainage pipe at the
bottom of the wetland cells. Obviously, this was a result of not
placing proper filtering material. As a result, seepage holes
developed at areas of the cells from where wastewater could
seep out untreated. Another construction problem was in the
last stage (HSF), which was not perfectly level in the lateral to
the flow direction, resulting in preferential flow (and plant
growth) on one side (Fig. 3). Again, this resulted in reduction
in total active treatment area and perfomance.
Operation and maintenance problems
Operation and maintenance problems were also
observed in some of our visits. For example, plants were
grown (and not removed) inside the outlet overflow pipe of
the last HSF stage, obstructing outflow and resulting in
flooding of the system.
It is recommended that these problems are addressed to
improve the system treatment performance.
DISCUSSION AND CONCLUSIONS
In general, selection of the appropriate constructed
wetland system depends on wastewater characteristics,
experience gained, local conditions and site constraints. FWS
systems are less expensive to construct, to operate and to
maintain, are less sensitive and susceptible to problems, and
have greater potential for wildlife support. VSF systems
generally require less land area, are less susceptible to
freezing, mosquitoes and odor problems, and do not have
wastewater exposed at the surface, thus providing minimal
human contact and health risks. These systems are considered
more susceptible to clogging of the media. However,
neither odor nor clogging problem in either system has
been observed so far. It is noted that a possible problem
of mosquitoes in the FWS project was faced effectively by
Figure 3. View of the HSF constructed wetland cell.
-
627
planting from the start Gambusia spp. fish.
In terms of performance, the organic loading rates were
slightly higher in the VSF than in the FWS system.
Furthermore, ambient temperatures in the VSF system,
located in Northern Greece, are 5 to 10oC lower. Nevertheless,
the high efficiency of both systems has been observed. The
cost analysis, incorporating both capital and operation and
maintenance costs, also suggested a low cost for both systems.
The FWS system was less expensive to construct and to
operate. However, the VSF system required considerably less
land area (in this economic analysis the price of land was not
considered). In terms of construction and O&M problems, the
VSF system, which is more complex in design, construction
and operation, showed most problems, which, however, could
have been predicted and avoided from the beginning. Finally,
the FWS system may freeze for a few days in the winter, if
installed in areas where the temperature drops below 0oC
(e.g., North Greece).
More specifically, the following can be drawn from the
comparison of the FWS and VSF systems:
a. Constructed wetlands are considered appropriate
wastewater treatment systems for the Mediterranean
environment, generating excellent quality of effluent at
the secondary treatment level. In this comparative
study, BOD5, COD and TSS reductions of about 95%
were observed for the FWS CW. BOD5 and TSS
reductions were similar for the VSF system, while COD
reduction was about 89% for this system. In addition,
for the FWS system reductions of TKN and TP of about
53% were measured, and removal rates of TC and FC of
98.7% and 97.1%, respectively. For the VSF system, TKN
removal was 77% on average, while mean phosphorus
removal efficiency was 62%.
b. Reasons for the lower efficiency of the VSF system in
COD removal may be that it was new at the time of the
study and the plant roots were probably not fully
developed. Furthermore, the HSF basin of the system
was not in operation during the study. Nevertheless, the
two systems seem to be very promising in producing a
high effluent quality.
c. The total wetland area (after pre-treatment) of the FWS
system is 5500 m2 (4.58 m2 p.e.-1), while that of the VSF
system is 2040 m2 (including 240 m2 for sludge drying
and storage) or 2.04 m2 p.e.-1 Thus, as expected, the VSF
system provides comparable treatment at significantly
less area (less than half), for slightly higher average
design flow rate (180 m3 d-1 vs. 144 m3 d-1), and at lower
operational temperatures (north vs. south Greece).
d . When comparing the construction costs of the two
systems, it seems that the VSF is slightly more
expensive, probably due to the fact that this system
contains more concrete and several pumps. Generally,
the FWS system construction is much simpler. In terms
of the capital and operation cost, it also seems that the
FWS system is less expensive. Both systems are
considered less expensive, both in construction and
operation, when compared to equivalent conventional
treatment systems operating in the same areas.
e. When comparing design, construction operation and
maintenance problems it seems that, the VSF was more
susceptible to problems since it is a more complex
system. For both systems, careful design and
construction, and proper maintenance are very
important.
In conclusion, the treatment efficiencies of the two
systems are comparable (except for TKN and TP where the
VSF system had higher removal efficiencies), costs seem to be
less for the FWS system, and land requirements are quite
lower for the VSF system. Thus, one can select either system
in terms of treatment efficiency. When land is available, the
FWS system would be preferable because of its simplicity, less
expensive construction, and more reliable and problem-free
operation. If land availability is a problem or land value is
high, then the VSF system would be more preferable. A
careful design and construction, and proper maintenance are
necessary in any case to avoid operational problems.
ACKNOWLEDGEMENTS
We thank G. Dialynas, N. Kefalakis and K. Tsagarakis
for providing information on the study. Sample collection and
analyses for the VSF constructed wetland system were
performed by A. Paltsoglou, K. Vragalas and J.N.E.
Papaspyros. The evaluation of the VSF system was co-funded
by the European Social Fund & National Resources EPEAEK
II PYTHAGORAS II.
REFERENCES
1. Ansola G., Gonzlez J.M., Cortijo R. and de Luis E., Experimental and full-scale pilot plant constructed wetlands for
municipal wastewaters treatment. Ecol. Eng., 21, 43-52 (2003).
2. Kadlec R. and Knight R., Treatment Wetlands, CRC Press, USA, Boca Raton, Fl., (1996).
3. Crites R. and Tchobanoglous G., Small and Decentralized Wastewater Management Systems, WCB and McGraw-Hill. New
York. USA (1998).
4. Andersson J.L., Kallner Bastviken S. and Tonderski K.S., Free water surface wetlands for wastewater treatment in Sweden
nitrogen and phosphorus removal. In: Proc. of the 9th International Conference on Wetland Systems for Water Pollution Control,
-
628
IWA, Avignon, France, September 26-30, Vol. 1, pp. 39-47 (2004).
5. Koottatep T., Surinkul N., Polprasert C., Kamal A.S. and Srauss M., Treatment of septage in constructed wetlands in
tropical climate Lessons learnt after seven years of operation. In: Proc. of the 9th International Conference on Wetland Systems
for Water Pollution Control, IWA, Avignon, France, September 26-30, Vol. 1, pp. 249-257 (2004).
6. Cooper D., Griffin P. and Cooper P., Factors affecting the longevity of sub-surface horizontal flow systems operating as
tertiary treatment for sewage effluent. In: Proc. of the 9th International Conference on Wetland Systems for Water Pollution
Control, IWA, Avignon, France, September 26-30, Vol. 1, pp. 259-267 (2004).
7. Solano M.L., Soriano P. and Ciria M.P., Constructed wetlands as a sustainable solution for wastewater treatment in small
villages. Biosystems Eng., 87, 109-118 (2004).
8. Cameron K., Madramootoo C., Crolla A. and Kinsley C., Pollutant removal from municipal sewage lagoon effluents with a
free-surface wetland. Water Res., 37, 2803-2812 (2003).
9. Ran N., Agami M. and Oron G., A pilot study of constructed wetlands using duckweed (Lemna gibba L.) for treatment of
domestic primary effluent in Israel. Water Res., 38, 2241-2248 (2004).
10. He Q. and Mankin K., Performance variations of COD and nitrogen removal by vegetated submerged bed wetlands. J. Am.
Water Resour. Assoc., 38, 1679-1689 (2002).
11. Mayo A. W. and Mutamba J., Effect of HRT on nitrogen removal in a coupled HRP and unplanted subsurface flow gravel
bed constructed wetland. Phys. Chem. Earth, 29, 1253-1257 (2004).
12. Korkusuz E. A., Beklioglu M. and Demirer G.N., Comparison of gravel and slag based vertical flow reed bed performance
in Turkey. In: Proc. of the 9th International Conference on Wetland Systems for Water Pollution Control, IWA, Avignon, France,
September 26-30, Vol. 1, pp. 173-181 (2004).
13. Akratos C. and Tsihrintzis V.A., Pilot-scale constructed wetlands for wastewater treatment studies. In: Proc. of the
International Conference on Protection and Restoration of the Environment VII, Technical University of Athens, Greece and
Sterens Institute of Technology, USA. June 28-July 1, 2004, Mykonos, Greece, CD-Rom Section IV (Ecological Engineering
Applications), #1 (2004).
14. Rousseau D.P.L., Vanrolleghem P.A. and De Pauw N., Constructed wetlands in Flanders: a performance analysis. Ecol.
Eng., 23, 151-163 (2004).
15. Luederitz V., Eckert E., Lange-Weber M., Lange A. and Gersberg R.M., Nutrient removal efficiency and resource
economics of vertical and horizontal flow constructed wetlands. Ecol. Eng., 18, 157-171 (2001).
16. Sderqvist T., Constructed wetlands as nitrogen sinks in southern Sweden: An empirical analysis of cost determinants.
Ecol. Eng., 19, 161-173 (2002).
17. Molle P., Linard A., Boutin C., Merlin G. and Iwema A., How to treat raw sewage with constructed wetlands: An
overview of the French systems. In: Proc. of the 9th International Conference on Wetland Systems for Water Pollution Control,
IWA, Avignon, France, September 26-30, Vol. 1, pp. 11-19 (2004).
18. Paing J. and Voisin J., Vertical flow constructed wetlands for municipal wastewater and septage treatment in French rural
area. In: Proc. of the 9th International Conference on Wetland Systems for Water Pollution Control, IWA, Avignon, France,
September 26-30, Vol. 1, pp. 315-323 (2004).
19. Brix H., Danish guidelines for small-scale constructed wetland systems for onsite treatment of domestic sewage. In: Proc. of
the 9th International Conference on Wetland Systems for Water Pollution Control, IWA, Avignon, France, September 26-30, Vol.
1, pp. 1-9 (2004).
20. Dialynas G.E., Kefalakis N., Dialynas M.G. and Angelakis A.N., Performance of the first free-water surface constructed
wetland system in Crete, Greece. Water Sci. Technol., 46, 355-360 (2002).
21. Tsagarakis K.P., Mara D.D. and Angelakis A.N., Application of cost criteria for selection of municipal wastewater
treatment systems. Water, Air Soil Pollut., 142, 187-210 (2003).