COnstruciton Operation Manual
-
Upload
shankey-bafna -
Category
Documents
-
view
222 -
download
0
description
Transcript of COnstruciton Operation Manual
VARDHMAN GROUP
OPERATION MANUAL
VARDHMAN FLORA
SUBMITTED BY CHECKED BY
PROJECT MANAGER H.O.D (CONSTRUCTION)
FOR THE MONTH OF
INDEX
Sr. No. Description
1 INTRODUCTION – FLORA
2 COMPLIANCE BEFORE STARTING THE WORK
3 HOW MANY CONTRACTORS REQUIRED OF THE BUILDING
4 NOTES
5 ORGANISATION CHART
6 MATERIALS TO BE PURCHASED
7 FILES TO BE OPENED
8 ARCHITECTS DRAWINGS REQUIRED
9 RCC DRAWINGS REQUIRED
10 PLUMBING DRAWINGS REQUIRED
11 ELECTRIC DRAWINGS REQUIRED
12 SAMPLE MATERIAL TO BE APPROVED
13`GODOWNS BUILT AT SITE FOR STORAGE OF MATERIALS
14 CONSULTANTS REQUIRED
16 REQUISITION FORMAT LIST
17 CHECK LIST CERTIFICATE LIST
18 CONSTRUCTION FORMATS LIST
19 CHECK LIST INTIMATION LIST
20 WORK PROCEDURE FOR EXECUTION OF CONSTRUCTION ITEMS
21 SPECIFICATIONS FOR CONSTRUCTION ITEMS
22 CONSULTANT INFORMATION
23 CONTRACTOR INFORMATION
24 STATUS OF PROGRESS
INTRODUCTION
COMPLIANCE BEFORE STARTING THE WORK
Sr. No. Name of the Compliance
1 Check the boundaries of the Plot having been fixed by the Contractor
2 Check the complete infrastructure like labour camp & its toilet facilities
3 Check for builders staff and other staff facilities
4 Check the site office for Builders staff and contractors staff
5 Check for the temporary water and power supply
6 Check for Bore well provision for construction purpose by Contractor (To check portability of water)
7 Check for lighting arrangement by the contractor
8 Check for safety measures from zero to top
9 Check for security staff from contractor side and builders side
10 Check for demarcation of places for stacking of material like aggregates, cement….etc.
11 Check for number of staff required for supervision from contractor side
12 Check for all ID Cards of staff, contractor side with color codes
HOW MANY CONTRACTORS REQUIRED FOR THE BUILDING
Ö - Yes X - NoSr. No. Type of Contractor With material Without material
1 Civil works - Appointed
2 Electrical works-
a) Internal Wiring for Flats.
b) Main line wiring in the Elec. Ducts.
c) Lift lobby
d) Stair case.
e) Terrace level
f) Meter rooms.
g) Pump rooms.
h) Cable trays.
i) Sub-Station.
j) Fire fighting.
k) Compd. Wall.
l)Paneling- main, D.G. pumproom,Lifts,common areas, pole lights,
m) Land scapes.
n) Entrance. Lobby.
o) Water features & water fountains.
p) Lightening arrester.
3 Plumbing Sanitary & Drainage works(except CP, Sanitary ware & pump)
4 Fire Fighting work- Internal & External
5 Internal painting works.
a) Internal painting of Flats. All areas
Sr.No Type of Contractor With material Without material
b) Lift lobby areas. All
c) Staircase areas.
d) Machine room, O.H. & Terrace areas.
e) Entrance. Lobby.
f) Utility rooms.
g) Plumbing Pipes.
h) Door shutter Molding.
i) POP Ceiling.
6 External painting.
a) Ext. walls & Elevations & features
b) Balcony areas Inside walls & ceilings.
c) Open to Sky Ducts ( inside walls)
d) Terrace level works, pergolas.
e) Podium & stilt areas.
f) Compound Walls.
g) Planter areas.
7 Tiling works.( Tiles to be supplied by us)With sand & cement from Contractor
a) Internal floor areas of Flats & skirting’s.
b) Toilet areas floors & in Dado.
c) i) Window sills & Jambs.
ii) Toilet plus Kitchen Door Jambs
d) Lift lobby, Flooring, Dado, and Lift Facia.
e) Entrance. Lobby all areas.
f) Water body-Basins,wall,all
Sr. No. Type of Contractor With material Without material h) Land scape areas- Pathways, sit-outs, wall Tops. Planter box.
i) compound wall tops & Planter walls
j) Compound areas/open space chequered Tiles / paver blocks.
k) Utility areas rooms. Floors.
l) Utility areas toilets.
8 Aluminum windows.
9 GRC Grill.
10 Structural glazing & Aluminum composite Panel (ACP) cladding.
11 Lift Elevators.
12 Water Features.
13 S.S. / M.S Railings-Grills.
14 P.O.P. work
15 Structural steel Canopy.
16 Modular Kitchen.
17 Sample flat.
18 Signage.
19 C.C.TV/Cable TV/dish TV/internet/intercom/MTNLWork
20 MAHANAGAR Gas ( MGL )
21 Glass Mirror & Partitions
22 Cleaning work.
23 D.G. sets & installations /commissioning.
NOTES:
1) Any requisition to be prepared & sent to Purchase Department, H.O. addressed to Purchase Manager at e-mail ID __________________ _____ phone no. _____________
2) Any Contractor or Contractor Agreement required, write e-mail to DGM at e-mail ID, ___________________________ phone no. ______________________
3) If your project require helmet, file, calculator, tape then e-mail DGM at e-mail ID ___________________________ phone no. ______________________
4) Punch your attendance daily at Project Office.
5) Printer cartridge requires replacement or computer problems are encountered then contact Hardware Engineer at e-mail ID ___________________________ phone no. ______________________
6) If you require site security, then e-mail your detailed requirement to DGM at e-mail ID ___________________________ phone no. ______________________
7) In spite of follow up with DGM, if a Contractor requested is still not appointed, then write e-mail to Management Co-coordinator at e-mail ID ___________________________ phone no. ______________________
8) In spite of follow up with Purchase Manager, if material is not received at site, then write e-mail to Management Coordinator at e-mail ID ___________________________ phone no. ______________________
9) In spite of follow up with Management Co-coordinator, if Contractor is not appointed or material is not received then write e-mail to grievance cell at e-mail ID e-mail ID ___________________________ phone no. ______________________
10) If drawings are required then write e-mail to Planning Architect at e-mail ID e-mail ID ___________________________ phone no. ______________________
11) In case BMC Approvals copy is required, then send e-mail to BMC Architect Mr. ____________ at e-mail ID ___________________________ phone no. ______________________
12) If any query with Consultants then contact them directly.
13) For site security problems, contact Management Co-coordinator (________________) at e-mail ID ___________________________ phone no. ______________________
14) In case Contractor is not working properly at site, planning not giving drawings or consultant not giving decisions, then write e-mail to Management Co-coordinator at e-mail ID ___________________________ phone no. ______________________
15) For Contractor payment related issue, write e-mail to G.M. Accounts at e-mail ID ___________________________
16) In case of queries relating to salary, contact Accounts Manager at e-mail ID ___________________________, phone No. _______________________
17) Call for drawings as per Operation Manual.
18) As per Organization Chart, assign duties to your subordinates.
19) Get requisite check list, certificates etc. loaded in your PC from Hardware Engineer, e-mail ID ___________________________, phone No. _______________________
20) Collect printed certificate books from Hardware engineer for issuance to contractors.
21) Issue intimation and certificates to Contractors as per Contract.
22) Fix up weekly meetings with Contractors at site and prepare Minutes of the Meeting. All points of meeting unresolved to be continued in future minutes until resolved.
23) E-mail Work Progress Report to Sales Department every week at e-mail ID ___________________________
24) Daily MIS to be e-mailed daily to e-mail ID ___________________________
25) Inform Document Department at e-mail ID __________________________about every slab cast, brick masonry floor wise & POP, concealed fittings for Plumbing & Wiring flat wise. After this information is given to Document Department, they will issue a Demand Letter to customer for payment.
<><><><><><>
ORGANISATION CHART
MATERIALS TO BE PURCHASED Ö - Yes X – No
Project Manager
1 Engineer perBuildings
1 Supervisor per Building
Security
Sr. No.
Materials Name Required Status of Delivery
Not Required
1 Tiles & Marblea) Flooring Tilesb) Lift Lobby Tilesc) Lift Lobby marbled) Kitchen Tilese) Window Sillsf) Toilet Door Frames
2 Electricalsa) Electrical Fitting for Flat
3 Plumbing Fittinga) Flush Wash / Diverter / Chair Bracket
4 CP Fitting / Sanitary ware5 Fire Doors & Fire Door Fittings6 Bathroom accessories7 Entrance Hall Marble8 Entrance Hall Air Conditioner9 Entrance Hall Furniture
10 Entrance Hall Electrical Fitting11 Lift Lobby Electrical Fitting12 Staircase Light13 Lift Lobby Light14 Terrace Light15 Terrace Doors16 Terrace Door Fitting17 Fire Fighting Materials – GI Pipes &
Accessories18 Fire Fighting pump19 Domestic Pump20 Pump Room Door21 Common WC Door22 Common Utility Room Fitting- Carpentry23 Utility Room Door Fitting – Carpentry24 Utility Room Door Lighting25 Compound Poll & Light Fixing26 Compound Marble27 Terrace Light28 Terrace Door29 Entrance Hall Light30 Paver Blocks in Compound
Sr. No.
Materials Name Required Status of Delivery
Not Required
31 Boom Barrier32 Cable Trays33 Door fittings34 Landscape equipments (Plants, drain cells,
Pavers etc.)35 Children’s equipment
ANNEXTURE “A”
FILE INDEX – YVONNE
File No. Name of File Remarks
YV 1A ARCHITECTURAL DRAWINGS
YV 1B STRUCTURAL DRAWINGS
YV 1C ELECTRICAL DRAWINGS
YV 1D PLUMBING DRAWINGS
YV 1E FIRE FIGHTING DRAWINGS
YV 1F BMC APPROVALYV 3A1 CIVIL CONTRACTOR
INTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/GRN/TEST REPORTS-CUBES/RE-BAR/ MIX DESIGNAPPROVAL/MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A2 TILING CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A3 FALSE CEILING CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
File No. Name of File Remarks
YV 3A4 PLUMBING CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE
ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A5 MARBLE FIXING CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A6 CARPENTRY & DOOR SHUTTERS CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A7 M.S. WORK/RAILING/S.S. RAILING CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A8 FIRE FIGHTING CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
File No. Name of File Remarks
YV 3A9 ELECTRICAL WORK CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE
ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A10 ALUMINIUM WINDOW CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A11 GLAZING & ACP CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A12 WINDOW CILLS FIXING CONTRACTOR INTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A13 GARDENING/LAND SCAPE WORK CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
File No. Name of File Remarks
YV 3A14 WATER BODY & WATER FOUNTAIN CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A15 LIFT ELEVATOR WORK CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A16 COMPOUND PAVING & INLAY CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A17 GRC GRILL CONTRACTOR INTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 3A18 IRRIGATION WORK CONTRACTOR INTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
File No. Name of File Remarks
YV 3A19 PAINTING CONTRACTORINTIMATIONS/ CERTIFICATES/ CONTRACTORS BILLS/ CONTRACTOR CORRESPONDENCE/ QUANTITY/QUANTITY/ REQUISITION/PURCHASE ORDER/ GRN/ RE-BAR/ MOM WITH CONSULTANTS/ MOM WITH CONTRACTORS/FLAT ALTERATIONS/BAR CHART/ AGREEMENT COPY/ GATE PASS ISSUES
YV 4A CORRESPONDENCE WITH CONSULTANTS
YV 4B DEPARTMENTAL CORRESPONDENCE
YV 5A WEEKLY MIS
1) PROGRESS REVIEW BOOK - 3 NOS.2) DAILY WORK RECORD BOOK - 1 NO.
ARCHITECT DRAWINGS REQUIRED
Ö - Yes
Sr. No.
Type of Drawing Received on Dated
Drawing No. (Revision) Required
1 Foundation Layout
2 Plinth floor drawing
3 Lower Basement Plan4 Upper Basement Plan5 Stilt floor @ 24.30m lvl6 Podium floor @28.05m lvl7 Lower Basement Plan (Entrance
Revised)8 Upper Basement Plan (Entrance
Revised)9 Terrace floor plan
Typical floor drawing10 1st floor layout drawing11 2nd floor layout drawing12 3rd floor layout drawing13 4th floor layout drawing14 5th floor layout drawing15 6th floor layout drawing16 7th floor layout drawing17 8th floor layout drawing18 9th floor layout drawing19 10th floor layout drawing20 11th floor layout drawing21 12th floor layout drawing22 13th floor layout drawing23 14th floor layout drawing24 Terrace floor drawing
25 O.H. Tank & Lift Machine Room 26 O.H. Tank & Lift Machine Room 27 O.H. Tank & LMR Terrace
Sectional details / drawing
28 Section-A-A
29 Section-B-B, Part-1 & 2
30 Section-C-C
31 Section-D-D
32 Section-E-E
33 Section-F-F
34 Section-G-G
35 Section-H-H
36 Section-I-I
37 Section-J-J
38 Section-K-K
39 Section-L-L
40 Section-M-M, Part-1 & 2
41 Section-N-N, Part-1 & 2
42 Section-O-OElevation drawing
43 Elevation Garden Side
44 Elevation Road Side
45 Elevation North Side
46 Elevation South Side
47 Toilet layout drawing
48 Fire Fighting duct details
49 Plumbers duct drawing
50 Canopy details
51 Staircase Details drawing
52 Balcony S.S Railing drawing (A&B,C&D,E &G)
53 Compound wall lay out drawing
54 Refuge area drawing
55 Door /window details.
56 Internal & External Masonry Details.
57 Lift well drawing
58 Lift Pit details.
59 Utility room location plan
60 Parking layout
61 Stilt floor Entrance Lobby Ele.-A
62 Stilt floor Entrance Lobby Ele.-B
63 Stilt floor Entrance Lobby Ele.-C
64 Stilt floor Entrance Lobby Ele.-D
65 Entrance Lobby –False Ceiling Layout
66 Entrance Lobby –Flooring Layout
67 Entrance Lobby –Dimension Layout
68 Entrance Lobby –Furniture Layout
69 Typical Floor Lift lobby Ele.-C
70 Typical Floor Lift lobby Ele.-D
71 Typical Floor Lift lobby –Flooring Layout
72 Typical Floor Lift lobby – False Ceiling Layout
73 Typical Floor Lift lobby – Furniture Layout
74 Typical Floor Lift lobby – Dimension Layout
75 Elevation Garden Side
Elevation Road Side
75 Elevation North Side
76 Elevation South Side
77 Fins Detail
Room tiles lay out details
78 2BHK Common Toilet Detail (Flat no. 1&6)
79 2BHK Common Toilet Detail (flat no. 2&5)
80 2BHK Common Toilet Detail (flat no. 3&4)
81 3BHK Common Toilet Detail (flat no. 7&8)
82 2BHK Master Toilet Detail (flat no. 1&6)
83 2BHK Master Toilet Detail (flat no. 2&5)
84 2BHK Master Toilet Detail (flat no. 3&4)
85 3BHK Master Toilet Detail (flat no. 7&8)
86 2BHK Flooring Detail (flat no.1&6)87 2BHK Flooring Detail (flatno.2&5)88 2BHK Flooring Detail (flat no.3&4)89 3BHK Flooring Detail (flat no.7&8)90 Refuge Flooring91 Parapet Wall Drawings92 Watchman’s Cabin – layout,
location & finished93 Utility rooms finishing details
94. Elevation pins sections √
RCC DRAWINGS REQUIREDÖ - Yes
Sr. No.
Type of Drawing Received on
Dated
Drawing No. (Revision)
Required
1 Foundation lay out drawing. with RCC Column details
2 Details of RCC combined footing
3 Index Plan of RCC column/tie beam up to plinth
4 Schedule of RCC column/tie beam up to plinthRCC for Typical slab
Index Plan5 Upper Basement Plan6 Stilt floor @ 24.30m lvl7 Podium floor @28.05m lvl8 1st floor layout drawing9 2nd floor layout drawing
10 3rd floor layout drawing11 4th floor layout drawing12 5th floor layout drawing13 6th floor layout drawing14 7th floor layout drawing15 8th floor layout drawing16 9th floor layout drawing17 10th floor layout drawing18 11th floor layout drawing19 12th floor layout drawing20 13th floor layout drawing21 14th floor layout drawing22 Terrace slab layout drawing
23 RCC details for lift m/c room
RCC schedule for typical reinforcement placement for each RCC details
24 Upper Basement Plan25 Stilt floor @ 24.30m lvl26 Podium floor @28.05m lvl27 1st floor layout drawing28 2nd floor layout drawing29 3rd floor layout drawing30 4th floor layout drawing31 5th floor layout drawing32 6th floor layout drawing33 7th floor layout drawing34 8th floor layout drawing35 9th floor layout drawing36 10th floor layout drawing37 11th floor layout drawing38 12th floor layout drawing39 13th floor layout drawing
40 14th floor layout drawing41 Terrace slab layout drawing
42 RCC details for lift m/c room
43 RCC details for U.G tank
44 RCC details for entrance canopy
45 Sectional details for toilet sunk portion
46 RCC details for Parapet
PLUMBING DRAWINGS REQUIRED Ö - Yes
Sr. No.
Type of Drawing Received on
Dated
Drawing No. (Revision)
Required
1 Plumbing layout Typical floor plan (1st, 3rd,7th,9th & 11th)
2 Plumbing layout Typical floor plan (2nd, 4th, 8th & 10th)
3 Plumbing layout 5th floor plan4 Plumbing layout Podium floor @28.05m lvl5 Plumbing layout Stilt floor @ 24.30m lvl6 Podium floor @28.05m lvl7 Plumbing layout 1st floor8 Plumbing layout 2nd floor9 Plumbing layout 3rd floor plan
10 Plumbing layout 4th floor plan11 Ext. drainage layout with invert levels and
manholes12 Ext. plumbing layout from BMC main to
U.G tank13 U.G tank details14 O.H tank details15 Internal toilet layout plumbing for – EWC,
washbasin, shower area, flush valve 16 Plumbing duct and down take layout –
supply and delivery17 Pump room and pump room layout for
pumps, pump rating18 Rainwater pipe layout and details at
balcony19 Rainwater layout at main terrace20 Plumbing looping at main terrace 21 Details of manhole22 Details of Gully traps 23 Water supply layout
24 Shaft Detail25 Plumbing layout Lower Basement Plan 26 Plumbing layout Upper Basement Plan27 Plumbing layout Podium floor @28.05m lvl28 Plumbing layout 12th floor29 Plumbing layout 13th floor30 Plumbing layout 14th floor plan31 O.H. Tank & Lift Machine Room Plan
LIFT DRAWINGS REQUIREDÖ - Yes
Sr. No.
Type of Drawing
Received on Dated
Drawing No. (Revision)
Required
1 General arrangement drawing (Passenger lift) (Landing entrance detail, plan on lift well for builder)
2 General arrangement drawing (Passenger lift) (Plan on machine room, machine room cutout details)
3 General arrangement drawing (Passenger lift) (Plan on lift well-for erection)
4 General arrangement drawing (For goods lift) (Landing entrance detail, plan on lift well for builder)
5 General arrangement drawing (For goods lift) (Plan on machine room, machine room cutout details)
6 General arrangement drawing (For goods lift)
ELECTRIC DRAWINGS REQUIRED Ö - Yes
Sr. Type of Drawing Received
on Drawing No.
(Revision)Required
No. Dated1 Elec. wiring layout – Flat wise for
conducting drawing RCC2 Elect. Wiring layout flat wise – Switch
Board location,D.B location, Light fitting/Accessories location
3 Elect. Duct layout for mainline, L.V H.T4 Cable tray layout from substation to each
service 5 Lift lobby electrical layout6 Entrance. Lobby electrical layout7 Elect. Cabling and details for lighting
arrestor8 Elect Layout for Firefighting work in
podium areas 9 Details panel locations
10 Typical lighting layout for staircase11 Main Single line Diagram
12 Electrical layout for Typical flat for 1,3,7,9,11 & 13 floor
13 Conduit layout for Typical 2BHK Flat-114 Conduit layout for Typical 2BHK Flat-215 Conduit layout for Typical 2BHK Flat-3
16 Single line Schematic Diagram17
FIRE FIGHTING DRAWINGS REQUIRED Ö - Yes
Sr. No.
Type of DrawingReceived on Dated
Drawing No.
(Revision)
Required
1 Fire protection system Layout at Lower basement
2 Fire protection system Layout at Upper basement
3 Fire protection system Layout at Stilt floor
4 Fire protection system Layout at 1st, 3rd,7th,9th, & 11th floor
5 Fire protection system Layout at 5th Refuge floor
6 Fire protection system Layout at 6th floor
7 Fire protection system Layout at 12th Refuge floor
8 Fire protection system Layout at 12th floor
9 Fire protection system Layout at 14th floor
SAMPLE MATERIAL TO BE APPROVED
Sr. No. Name of the Material First Approved by Architect
Second Approved by Management
INSIDE FLAT
1 Tiling (Floor, Bathroom/Toilet Kitchen, Balcony tiles, dado)
2 Window Sills
3 Toilet/Kitchen Door frame
4 Toilet Counter
5 Plumbing (CP Fittings, Sanitary ware, Sink, Glass Partition....etc.)
6 Electrical Fittings (All fittings, switches, wiring etc.)
7 Aluminum Windows, Glass and other fittings
8 A.C. Approval (Brand, make, etc.)
9 Flush Door shutter with hardware fixtures (Main and internal doors with hardware fittings, handle, latches, eye piece, door stoppers etc.)
10 Internal Paint material approval (shade of paint....etc.)
11 External Paint material approval (shade of paint....etc.)
12 Approval of cornices
13 Approval of furniture layout & furniture material
LIFT LOBBY & COMMON AREA
14 Approval of Lift facia material
15 Approval of floor finish
16 Approval of Wall finish
17 Approval of door shutter
18 Approval of signage
19 Approval of false ceiling material and lighting fixtures
20 Approval of staircase – (Tread, Riser, grooves, etc...)
GODOWNS BUILT AT SITE FOR
STORAGE OF MATERIALSSr. No. Name of the Contractor Area of Type of material
Godown –Sq.ft. Stored at Godown
1 Tiling work
2 MS & SS Railing Material
3 Electrical
4 Lift Elevators Material
5 Fire Fighting material
6 Plumbing material
7 Aluminum Windows material
8 Painting material
9 External Painting Material (NITCO)
10 False ceiling material
11 Modular Kitchen
12 Marble Frames
13
14
15
CONSULTANTS REQUIRED
Sr. No.
Type of the Consultant Status Name
1 Main Architect
2 B.M.C. Architect
3 RCC Consultant
4 Electrical Consultant
5 Plumbing Consultant
6 Fire Fighting Consultant
7 Lift Consultant
8 Landscape Consultant
9 Water Fall/Fountain Consultant
10 Interior Architects/Consultants
11 Traffic Consultants
12 Automation/Security Consultants
13 Irrigation Consultant
14 Electrical Power Consultant
15 Plumbing Liaison consultants
16 ACP Cladding & Structural Glazing Consultant
17 BMC Liaison Consultant
18 STP Consultant
19 Signage
20
GENERAL INFORMATION FOR SITE
Sr. No. Type of Information
A) Site Book Nos. 1, 2 & 3 is to be regularly & daily filled up correctly and appropriately duly signed by PM with overall information and details given in each book
1
Book 1:
Book No.1 is related to complete construction activities starting from site setup up to flat wise progress of work of each items listed up to 51 serially
2 Book 2:
3 Book 3
4 Book 4
It comprises of daily activity having been supervised throughout the day. All these books have to be signed by the PM once in a month before salary has to be signed by the Project Management Co-coordinator. It is for all.
B) All intimations and certificates issued shall be finally signed by QC-DGM before certifying any bill.
LIST OF REQUISITION
SR No
Form No Type Of Requisition
1 FORM NO. 012 FORM NO. 023 FORM NO. 02A4 FORM NO. 035 FORM NO. 03 A
6 FORM NO. 03 B7 FORM NO. 03 C8 FORM NO. 03 D9 FORM NO. 03 E10 FORM NO. 0411 FORM NO. 0512 FORM NO. 05 A13 FORM NO. 05 B14 FORM NO. 05 C15 FORM NO. 05 D16 FORM NO. 0617 FORM NO. 06 A18 FORM NO. 0719 FORM NO. 07 A20 FORM NO. 0821 FORM NO. 0922 FORM NO. 1023 FORM NO. 1124 FORM NO. 11 A25 FORM NO. 1226 FORM NO. 12 A27 FORM NO. 12 B28 FORM NO. 12 C29 FORM NO. 12 D30 FORM NO. 1331 FORM NO. 1432 FORM NO. 14 A33 FORM NO. 1534 FORM NO. 15 A35 FORM NO. 15 B36 FORM NO. 15 C37 FORM NO. 15 D38 FORM NO. 15 E39 FORM NO. 15 F40 FORM NO REQ -15G 41 FORM NO. 15 H42 FORM NO. REQ - 15I43 FORM NO. 15 J44 FORM NO. 15 K45 FORM NO. 15 L46 FORM NO. 15 M47 FORM NO. 15 N48 FORM NO. 1649 FORM NO. 1750 FORM NO. 1851 FORM NO. 18 A52 FORM NO. 1953 FORM NO. 2054 FORM NO. 21
55 FORM NO. 2256 FORM NO. 2357 FORM NO. 2458 FORM NO. 2559 FORM NO. 2660 FORM NO. 2761 FORM NO. 2862 FORM NO. 2963 FORM NO. 3064 FORM NO. 3165 FORM NO. 3266 FORM NO. 3367 FORM NO. 3468 FORM NO. 35
STATEMENT OF MATERIAL REQUISITION
Sr. No.
Description of Item Requisition no. Requisition Date
Quantity
1 Steel
2 CementOPC 53 GradeOPC 43 GradeOPC 53 GradeOPC 53 Grade Loose CementPPCOPC 53OPC 53 Grade Loose CementPPCOPC 53OPC 53 Grade Loose CementPPCOPC 53OPC 53 Grade Loose CementOPC 53OPC 53 Grade Loose CementOPC 53 GradePPCPPCPPC
3 Electrical Materiala. 50 x 6 GI earthing Strip Hot
dip600mm x 600mm x 6mm GI Earthing Plate3/4" GI Funnel with GI Pipe 5 feet25 x 8 GI Nut Bolt with Double Washer35 x 10 GI Nut Bolt with Double Washer50 x 6 GI saddle35*8 ScrewSaltCoal
4 Plumbing Materiala. C.I. Chair Bracket
Concealed Flush Tank
Concealed Divertor body with partsConcealed Body mixer
5 Door Shutter for Sample Flata. Main door
Internal doorToilet door
6 Electric material for Sample Flat
a 1 module plate2 module plate3 module plate4 module plate6 module plate8 module plate (Square)8 module plate (Rectangle)12 module plate10 amp switch10amp socket20 amp switch without indicator 16/20 heavy duty socket25 amp switch heavy duty with indicator.TV socketTEL jack doubleIntercom socketFan regulator (double)RJ 45 Internet socketBell PushDing ding bellBlank plate 1 module4’’Round plateCeiling Rose35X6 Screw38X6 Screw60X6 Screw35X8 ScrewPVC tape16amp SP MCB25amp SP MCB40amp 4pole RCCB1.5 sq mm pin lugs2.5 sq mm pin lugs4 sq mm pin lugs6 sq mm pin lugs1.5 sq mm red colour wires1.5 sq mm yellow colour wires1.5 sq mm blue colour wires
1.5 sq mm black colour wires1.5 sq mm green colour wires2.5 sq mm red colour wires2.5 sq mm yellow colour wires2.5 sq mm blue colour wires2.5 sq mm black colour wires2.5 sq mm green colour wires4 sq mm red colour wires4 sq mm yellow colour wires4 sq mm blue colour wires4 sq mm black colour wires4 sq mm green colour wires2 pair telephone wire4 pair telephone wireRG 6TV cableInternet 6line wire6 sq mm (Red)6 sq mm (Yellow)6 sq mm (Blue)6 sq mm (Black)8’’ X 10’’ Acrylic sheetSteel Wire 16GAnchor fastener (2 PIN TYPE) for ceiling fan
7 Plumbing Material for sample flat
a. Escale Wall-Hung Toilet With Quiet- Close Seat And Cover19045IN-00 - ESCALE WALLHUNG BOWL with4417T-00 ESCALE SOFT CLOSE SEATSingular Angle Valve G1/2"With FlangeHealth Faucet W/Sdspray, Metal Hose and BracketHydro-Tower 300 Inwall Tank Without Iron Rack, 3/6L, 88mm with Inlet GasketBevel Inwall Tank Face Plate (Hydro- Tower 300)CONNECTOR ACCESSORY PACK For WCRack BoltForefront Square Vessel (Wash Basin)Singular Wm Sgl Control Lav Faucet with Concealed Diverter (Basin Mixer)
Grid Drain (Waste Coupling)
Bottle Trap (Heavy)-12" & 15" Pipe8" Square Rain Showerhead Katayst Spray with put shower armMaster shower Elbow Shower Arm with FlangeSingular Bath And Shower TrimValve, 1 Handle, Recessed W/DiverterSingular Wall Mount Bath Spout With Diverter For Hand shower with flangeRain Duet Mf Hand spray W/HoseHand shower BracketCamary Nahani Trap Jali 5" (Square)Angle cock - with Flange Presqu'Ile Wall-Hung Toilet With Quiet- Close Seat And Cover19080IN-0 : PRESQUILE WALL-HUNG BOWL with8798T-0 : PRESQUILE SOFT CLOSE SEATJuly Angle Valve G1/2" with flangeHealth Faucet W/Sd spray, Metal Hose & BracketHydro-Tower 300 Inwall Tank Without Iron Rack, 3/6L, 88mm with Inlet GasketInwall Tank Face Plate (For Hydro- Tower 300)CONNECTOR ACCESSORY PACK For WCRack BoltCaxton Small Under counter Lavatory 489*413 mm ( (Wash Basin)Nateo Monobloc Sgl Control Lav Faucet with Connector Pipe (Basin Mixer)Angle cock - with Flange Grid Drain (Waste Coupling)
Bottle Trap (Heavy)-12" & 15" PipePurist Mf Showerhead, W/Arm & FlangeNateo Bath And Shower TrimValve, 1 Handle, Recessed W/DiverterBath Spout, W/O Diverter, Flat Face,160 without flangeCamary Nahani Trap Jali 5" (Square)Angle cock - with Flange Camary Nahani Trap Jali 5" (Square)Camary Nahani Trap Jali 5" with Hole (Square)Single Lever Sink Mixer with Swinging Spout (Table Mounted) with 450mm Long Braided Hoses
8 Tiling Material for Sample Flat
a. Kajaria Travertino Bernini (Polished) First quality (2Pcs/Box - 1.44 Sq.mtr. - 15.50 Sqft.)Kajaria Imperial Bianca Premium quality (4 Pcs/Box - 1.08 Sq.mtr. - 11.625 Sqft.)Kajaria Jacaranda Premium quality (4 Pcs/Box - 1.44 Sq.mtr. - 15.50 Sqft.)Johnson make European Beech First quality (6 Pcs/Box - 1.08 Sq.mtr. - 11.63 Sqft.)Johnson make Marina Beige Ij Lp First quality (2 Pcs/Box - 1.28 Sq.mtr. - 13.77 Sqft.)Johnson make Lenox Verde Matt First quality (4 Pcs/Box - 1.44 Sq.mtr. - 15.5 Sqft.)
b. Kajaria Make Imperial Bianca Premium quality (4 Pcs/Box - 11.625 Sqft.) (As per previous Supplied )
c. Digital Glazed Vitrified Tiles 600mm X 1200mm = 2 Nos. Per Box (15.50 Sqft. Per Box) Shade-Traventine Verde Premium Quality.
Master Bathroom- Ceramic Tiles European Beech First quality (6 Pcs/Box - 11.63 Sqft.)Master Bathroom- Vitrified Tiles Marina Beige First quality (2 Pcs/Box - 13.77 Sqft.)Common Bathroom-Ceramic Tiles Lenox Verde First quality (4 Pcs/Box - 15.5 Sqft.)Ceramic Tiles Imperial Bianca (Standard Quality) = 4 Nos. Per Box (11.625 Sqft. Per Box)
Digital Glazed Vitrified Tiles 600mm X 146mm = 12 Nos. Per Box (11.31 Sqft. Per Box) Shade-Hugo Teakwood Croma Premium Quality.
d. Composite marble for toilet door frame
e. PVC Corrugated sheet9 Kitchen Material for sample
flata SS Kitchen Sink
Kitchen Spout (Brass with Chrome finish)Built-in Gas HobBuilt-in-MicrowaveBuilt-in-OvenChimney Refrigerator
10 Bathroom Accessories for Sample Flat
a Loure™ Covered Toilet Paper HolderEolia Double Robe Hook
11 Exhaust fan
12 Domestic & Flushing pump
13 Flat flush door shutter
a. Main door
b. Internal Door
c. Toilet door
14 Common area Flush door
shutter
a. Servant toilet door
b. Utility room toilet door
c. Common room door
15 Staircase & LV HV duct flush door shutter
a. Staircase door
b. LV.HV duct door
c. Fire fighting duct door
d. Electric duct door
e. Terrace door
f. Lift lobby door
16 Flat door Hardware fitting
A) Main Door
a. Lock
b. Handle
c. Door Stopper
d. Eye viewer
e. S.S. Hinges with screw
B) Internal Door
a. Lock
b. Door stopper
c. S.S. Hinges with screw
C) Toilet Door
a. Lock
b. S.S. Hinges with screw
D) Refuge flat toilet door
a. Lock
b. S.S. Hinges with screw
E) Refuge flat door
a. Door Closer
b. S.S. Hinges with screw
17 Common area door Hardware fitting
A) Servant toilet door
a. Lock
b. Brass Hinges
B) Utility room toilet Door
a. Lock
b. Brass Hinges
C) Common Room Door
a. Lock
b. Door Stopper
c. Brass Hinges
18 Staircase & LV HV duct hardware fitting
A) Staircase Door
a. Staircase Door Hinges
b. Handle
c. Door Closer
B) LV,HV Duct Door
a. Door Hinges
b. Allen key
C) Fire fighting duct door
c. Door Hinges
d. Allen key
D) Terrace door
a. Door Hinges
b. Lock
c. Handle
E) Lift lobby door
a. Door Hinges
b. Lock
c. Handle
F) Electric duct Door
a. Lock
b. Door Hinges
19 Servant toilet CP & sanitary fittings
a. Presqu'lle Wall-Hung Toilet with Quiet-close Seat and Cover 19080IN-0:PRESQUILE WALL-HUNG BOWL with 8798T-0:PRESQUILE SOFT CLOSET SEAT
b. W.C. Washer
c. Inwall Tank Face Plate (For Hydro-Tower 300)
d. Wash Basin (22'' x 18'')
e. Two way Bib cock
f. Health Faucet W/Sdspray, Metal Hose & Bracket
g. PVC 2' Flexible pipe
h. Piller cock
i. Grid Drain (Waste Coupling)
j. Copper Connector 2'
k. Camary Nahani Trap Jali 5'' (Squar)
l. Angle Cock-with Flange
m. Urinal
n. Urinal push buttan
o. Copper Connector 2'
20 Servant toilet Chair bracket & flush tank.Staircase light fitting
a. Chair bracket
b. Flush tank
21 Flat & common room light fitting
22 Terrace & Parking area light fitting
a. Parking
b. Terrace
23 Lift lobby light fitting
24 Staircase light fitting
25 Flat toilet light fitting
26 Bathroom accessories
a. Towel Rod
b. Towel Ring
c. Soap Dish Holder
d. Toilet Paper Holder
e. Tooth Brush Holder
27 A) Entrance lobby Marble
a. Crema marfil Marble
b. Black Merquini marble
c. Belgium white marble
B) Typical lift lobby
a. Black Merquini marble
C) Staircase
a. Crema marfil Marble
D) LV,HV duct
a. Crema marfil Marble
E) Lift Cabin
a. Crema marfil Marble
b. Black Merquini marble
CHECK LIST INTIMATION LIST
Intimation for work commencement to be given to the contractor based on the Contract Agreement. Corresponding completion Certificate of the work as per Intimation shall be Issued & signed by Sr.Engg /
Proj.Mgr.on satisfactory completion of the said work & having inspected the work physically visiting the work site.
Following list of Intimation & certificates shall be issued for the respective contractors. However, intimations for ‘Auxiliary’ works such as ‘site cleaning, debris removals may be issued by the concerned ‘site supervisors’.
1) Beam and slab at Podium level2) Random Rubble soiling3) Footings4) Column and plinth beams under plinth5) PCC in plinth6) Anti Termite Treatment7) Backfill and carting away8) Damp Proof Course9) Beam and slab at Podium Level10) Beams and Slabs11) Columns12) Internal and External (brick work)13) Plaster up to skirting14) Beams & slab at terrace level15) Columns for Lift machine room, Staircase room, OH Tank16) Brick work for Lift Machine room, Staircase room, OH Tank, parapet17) Plaster of Lift Machine Room, Staircase room, OH Tank, parapet18) Toilet waterproof plaster19) Toilet concealed plumbing20) Terrace water proofing21) OH Tank, Staircase, Lift Machine room slab water proofing22) Kitchen platform with tiles23) D Bracket, Backing Board and molding for mirror and glass partition in toilet24) Kitchen dado tiles above platform25) Flooring tiles26) POP in flats27) POP in skirting28) Main door fixing with temp lock29) Fixing of internal doors30) Fixing of window Sills & Marble door frames for toilets31) Floor polishing32) D B in flats33) Internal wiring in Flats34) Threshold35) Stilt area plaster36) Stilt area painting37) Stilt area flooring38) Stilt area lighting39) Stilt area marking parking spaces40) Lift Lobby Plaster
41) Lift Lobby Flooring42) Lift Lobby plaster in skirting43) Lift Lobby painting 1st & 2nd coat44) Lift Lobby Lipainting 1st & 2nd coat45) Lift Lobby Lighting46) Lift Lobby Final Painting47) Cover Molding on doors48) Staircase plaster up to skirting49) Staircase flooring50) Staircase plaster in skirting51) Staircase Railing52) Staircase T.W. Handrail53) Staircase Lighting54) Staircase Painting Final coat55) Lift door frame56) Lift door57) Lift erection & Commissioning #158) Lift erection & Commissioning #259) Entrance Lobby POP Plaster up to skirting60) Entrance Lobby flooring & cladding61) Entrance Lobby plaster i9n skirting62) Entrance Lobby false ceiling63) Entrance Lobby lighting64) Entrance Lobby Painting 1st and 2nd coat65) Entrance Lobby polishing of flooring66) Entrance Lobby final painting67) Entrance Lobby Name board68) Intercom wiring69) Cable TV wiring70) Telephone wiring71) Door & window fittings72) Door main lock final73) El. Fittings74) Sanitary ware & C.P. Fittings75) Final coat painting in flats76) RCC work for U.G. Tank & pump room77) Brick work for U.G. Tank & pump room78) Plaster work for U.G. Tank & pump room79) Water proofing of U.G. Tank80) Painting of Pump room81) Pump fitting & erection commissioning82) Lighting in pump room83) Windows in pump room84) Pump room door with frame & fittings85) Meter room brick work86) Meter room brick plaster87) Meter room door with fittings88) Meter room painting/white wash89) Meter room lighting90) Meter room plywood fixing91) Meter fixing & wiring in Meter room
92) Wiring from Meter room to DB’s93) Terrace flooring IPS/China Mosaic94) Terrace loop GI work95) Duct plaster96) GI Work in ducts97) CI work in ducts98) Stoneware work in ducts99) PVC pipes in ducts100) Expansion joints101) Terrace door with Frame & fittings102) O.H. Tank piping103) Staircase room brick work104) Staircase room plaster105) Staircase room Painting106) Staircase room Lighting107) Lift machine room brickwork108) Lift machine room plaster109) Lift machine room painting110) Lift machine room lighting111) Lift machine room windows112) Service room R.C.C. Jali113) Fire fighting work from UG Tank to OH Tank114) Wet riser work115) Fire extinguishers116) Siamese connection117) Fire door frame fixing118) Fire doors shutters with fittings119) Entrance Canopy RCC120) Entrance Canopy Plaster121) Entrance Canopy painting122) Entrance Canopy water proofing123) Entrance Canopy lighting124) Entrance Canopy spouts125) Compound wall126) Compound gate127) Compound paving128) Compound lighting129) Compound IC’s130) Compound SWD131) Compound watchman’s cabin132) Compound landscape133) Marking Parking spaces134) Contractors godowns135) Labour hutments136) Toilet in stilt area137) Site office138) Duct painting139) Duct door140) Beams and slab at stilt level141) Garbage chute142) Brickbat coba and waterproofing
143) Kitchen tiles flooring144) Basement145) Flooring inside rooms146) Staircase painting 2nd coat147) P.O.P. Scrapping148) 1st coat primer149) 1st coat Lambi150) Beams & slabs at Podium Level151) 2nd coat Lambi152) 2nd coat Primer153) 1st coat Paint154) 2nd coat Paint155) PU Molding156) Modular Kitchen units157) M.S. Railing for balconies158) Toilet dado159) Random Rubble Masonry160) R.C,C. cap slab161) Painting for internal doors & shutters162) R.C.C. pergola163) Activities’ for glazing & M.S. Structure for elevation164) Civil work – Landscape related165) Plum Concrete166) Staircase flooring167) Lift Lobby POP168) Counter fixing in toilet/bathroom169) Lift fascia dado170) Podium floor brickwork171) Lift installation172) Paver tile flooring at stilt/Podium level173) Beam and slab at Podium level174) Ruff and tuff base coat175) Ruff and tuff 1st top coat176) Ruff and tuff 2nd top coat177) Nifco cem paint for external wall and duct178) Excavation
CONSTRUCTION FORMATS LIST
Day to Day activities of constructions at site shall be duly followed as per the Format
Given below
Form No. Description
Const-1 Helmet Issue
Const-2 Contractor required
Const-3 Contractor document required
Const-4 Work held up due to material
Const-5 Requirement of assets
Const-6 Purchase Order copy not received
Const-7 Defective material
Const-8 Temporary water connection
Const-9 Disconnection of Temporary Electric Meter
Const-10 Take away excess material at site
Const-11 Fixing of rolling shutters
Const-12 Reporting sheet
Const-13 Contractor workmanship not proper
Const-14 Flat door key handover
Const-15 Common area keys handover
Const-16 Handover of assets
Const-17 Reminder for material
Const-18 Documents to Purchase Department
Const-19 Security problem
Const-20 Permission for late night work
Const-21 Gate Pass
Const-22 Call contractor for meeting
Const-23 Labor/Manpower required
Const-24 Contractor not attending meeting
Const-25 Labor insurance copy
Const-26 Meter fixing
Const-27 Additional/Fresh drawing required from Architect
Const-28 Additional/Fresh drawing required from RCC Consultant
Const-29 Additional/Fresh drawing required from Electrical Consultant
Const-30 Additional/Fresh drawing required from Plumbing Consultant
Const-31 Architect Site visit
Const-33 RCC Site visit
Const-34 Electrical Consultant Site visit
Const-35 Plumbing consultants – site visit
Const-36 Call consultants for meeting
Const-37 Lift certificates Enclosures
Const-38 Request for approved BMC Plans/remarks
Const-39 Electric Meter connection
Const-40 Department Labor request
Const-41 Reminder for material
Const-42 Debris removal
Const-43 Daily Labor report
Const-44 Staff required from HR Department
CHECK LIST CERTIFICATE LIST
1) Certificates of completion of work shall be released to the contractors by project manager concerned on satisfactory completion of the work against the intimation issued by physically & carefully inspecting the work quality /quantity wise
2) Certificates shall be signed only by the project manager concerned.3) Records of the certificates shall be maintained by the project manager concerned. & shall be
entered in the site progress book provided for daily up-dates.
All Intimations & Completion certificates shall be attached while R.A. Bill submission by the contractor.
1) Beam and slab at Podium level2) Random Rubble soiling3) Footings4) Column and plinth beams under plinth5) PCC in plinth6) Anti Termite Treatment7) Backfill and carting away8) Damp Proof Course9) Beam and slab at Podium Level10) Beams and Slabs11) Columns12) Internal and External (brick work)13) Plaster upto skirting14) Beams & slab at terrace level15) Columns for Lift machine room, Staircase room, OH Tank16) Brick work for Lift Machine room, Staircase room, OH Tank, parapet17) Plaster of Lift Machine Room, Staircase room, OH Tank, parapet18) Toilet waterproof plaster19) Toilet concealed plumbing20) Terrace water proofing21) OH Tank, Staircase, Lift Machine room slab water proofing22) Kitchen platform with tiles23) D Bracket, Backing Board and molding for mirror and glass partition in toilet24) Kitchen dado tiles above platform25) Flooring tiles26) POP in flats27) POP in skirting28) Main door fixing with temp lock29) Fixing of internal doors30) Fixing of window Sills & Marble door frames for toilets31) Toilet BK Bat Coba & water proofing32) Toilet Nahani Trap fixing on33) External plaster North side34) External plaster East side35) External plaster West side36) External plaster South side37) External painting North side38) External painting East side39) External painting West side
40) External painting South side41) Aluminum Window fixing42) Floor polishing43) D B in flats44) Internal wiring in Flats45) Threshold46) Stilt area plaster47) Stilt area painting48) Stilt area flooring49) Stilt area ramp50) Stilt area lighting51) Stilt area marking parking spaces52) Lift Lobby Plaster53) Lift Lobby Flooring54) Lift Lobby plaster in skirting55) Lift Lobby painting 1st & 2nd coat56) Lift Lobby Lipainting 1st & 2nd coat57) Lift Lobby Lighting58) Lift Lobby Final Painting59) Cover Moulding on doors60) Staircase plaster up to skirting61) Staircase flooring62) Staircase plaster in skirting63) Staircase Railing64) Staircase T.W. Handrail65) Staircase Lighting66) Staircase Painting 1st coat67) Staircase Painting Final coat68) Lift door frame69) Lift door70) Lift erection & Commissioning #171) Lift erection & Commissioning #272) Entrance Lobby POP Plaster upto skirting73) Entrance Lobby flooring & cladding74) Entrance Lobby plaster i9n skirting75) Entrance Lobby false ceiling76) Entrance Lobby lighting77) Entrance Lobby Painting 1st and 2nd coat78) Entrance Lobby polishing of flooring79) Entrance Lobby final painting80) Entrance Lobby Name board81) Intercom wiring82) Cable TV wiring83) Telephone wiring84) Door & window fittings85) Door main lock final86) El. Fittings87) Sanitary ware & C.P. Fittings88) Final coat painting in flats89) RCC work for U.G. Tank & pump room90) Brick work for U.G. Tank & pump room
91) Plaster work for U.G. Tank & pump room92) Water proofing of U.G. Tank93) Painting of Pump room94) Pump fitting & erection commissioning95) Lighting in pump room96) Windows in pump room97) Pump room door with frame & fittings98) Meter room brick work99) Meter room brick plaster100) Meter room door with fittings101) Meter room painting/white wash102) Meter room lighting103) Meter room plywood fixing104) Meter fixing & wiring in Meter room105) Wiring from Meter room to DB’s106) Terrace flooring IPS/China Mosaic107) Terrace loop GI work108) Duct plaster109) GI Work in ducts110) CI work in ducts111) Stoneware work in ducts112) PVC pipes in ducts113) Expansion joints114) Terrace door with Frame & fittings115) O.H. Tank piping116) Staircase room brick work117) Staircase room plaster118) Staircase room Painting119) Staircase room Lighting120) Lift machine room brickwork121) Lift machine room plaster122) Lift machine room painting123) Lift machine room lighting124) Lift machine room windows125) Service room R.C.C. Jali126) Fire fighting work from UG Tank to OH Tank127) Wet riser work128) Fire extinguishers129) Siamese connection130) Fire door frame fixing131) Fire doors shutters with fittings132) Entrance Canopy RCC133) Entrance Canopy Plaster134) Entrance Canopy painting135) Entrance Canopy water proofing136) Entrance Canopy lighting137) Entrance Canopy spouts138) Compound wall139) Compound gate140) Compound paving141) Compound lighting
142) Compound IC’s143) Compound SWD144) Compound watchman’s cabin145) Compound landscape146) Marking Parking spaces147) Contractors godowns148) Labor hutments149) Toilet in stilt area150) Site office151) Duct painting152) Duct door153) Beams and slab at stilt level154) Garbage chute155) Brickbat coba and waterproofing156) Kitchen tiles flooring157) Basement158) Flooring inside rooms159) Staircase painting 2nd coat160) P.O.P. Scrapping161) 1st coat primer162) 1st coat Lambi163) Beams & slabs at Podium Level164) 2nd coat Lambi165) 2nd coat Primer166) 1st coat Paint167) 2nd coat Paint168) PU Molding169) Modular Kitchen units170) M.S. Railing for balconies171) Toilet dado172) Random Rubble Masonry173) R.C,C. cap slab174) Painting for internal doors & shutters175) R.C.C. pergola176) Activities’ for glazing & M.S. Structure for elevation177) Civil work – Landscape related178) Plum Concrete179) Staircase flooring180) Lift Lobby POP181) Counter fixing in toilet/bathroom182) Lift fascia dado183) Podium floor brickwork184) Lift installation185) Paver tile flooring at stilt/Podium level186) Beam and slab at Podium level187) Ruff and tuff base coat188) Ruff and tuff 1st top coat189) Ruff and tuff 2nd top coat190) Nitcocem paint for external wall and duct191) Excavation
INTIMATION & CERTIFICATER ISSUE TO CONTRACTORS
Sr. No. Description of Item Intimation Date Certificate Date
Remark
A.1 Site office for staff with toilet facility2 Security arrangement for site3 Providing temporary lighting
arrangement
R.C.C. Work1 Layout for Building2 Excavation 3 Footing4 Stub Column5 Plinth Beam6 Back filling7 Anti Termite Treatment8 Soling & PCC9 Column above plinth
10 1st Slab @ 20.85m Lvl.11 2nd Slab + conduits @ 24.30m Lvl.12 20.85m Lvl. above column13 3rd Slab + conduits @ 28.05m Lvl.14 Deshuttering 1st slab & Preparing
surface for plaster15 4th Slab + conduits @ 31.35m Lvl.16 Deshuttering 2nd slab & Preparing
surface for plaster
17 Staircase temporary light at lower basement
18 Curing to 3rd slab19 5th Slab concreting + conduits20 Deshuttering 3rd slab & Preparing
surface for plaster21 Staircase temporary light at upper
basement22 Curing to 4th slab23 6th Slab concreting + conduits24 Deshuttering 4th slab & Preparing
surface for plaster25 Staircase temporary light at podium
floor26 Curing to 5th slab27 7th Slab concreting + conduits28 Deshuttering 5th slab & Preparing
surface for plaster29 Staircase temporary light at 1st floor
30 Curing to 6th slab31 8th Slab concreting + conduits32 Deshuttering 6th slab & Preparing
surface for plaster33 Staircase temporary light at 2nd floor34 Curing to 7th slab35 9th Slab concreting + conduits36 Deshuttering 7th slab & Preparing
surface for plaster37 Staircase temporary light at 3rd floor38 Curing to 8th slab & masonry on 1st
floor39 10th Slab concreting + conduits40 Deshuttering 8th slab & Preparing
surface for plaster41 Staircase temporary light at 4th floor42 Curing to 9th slab & masonry on 2nd
floor43 Service lift44 11th Slab concreting + conduits44 Deshuttering 9th slab & Preparing
surface for plaster45 Staircase temporary light at 5th floor46 Curing to 10th slab & masonry on 3rd
floor & plaster on 1st floor.47 12th Slab concreting + conduits48 Deshuttering 10th slab & Preparing
surface for plaster49 Staircase temporary light at 6th floor50 Curing to 11th slab & masonry on 4th
floor & plaster on 2nd floor.51 13th Slab concreting + conduits52 Deshuttering 11th slab & Preparing
surface for plaster53 Staircase temporary light at 7th floor54 Curing to 12th slab & masonry on 5th
floor & plaster on 3rd floor55 14th Slab concreting + conduits56 Deshuttering 12th slab & Preparing
surface for plaster57 Staircase temporary light at 8th floor58 Curing to 13th slab & masonry on 6th
floor & plaster on 4th floor59 15th Slab concreting + conduits60 Deshuttering 13th slab & Preparing
surface for plaster61 Staircase temporary light at 9th floor62 Temporary godawans 3 nos. in brick
work 63 Open platform for storage of tiles
64 Curing to 14th slab & masonry on 7th floor & plaster on 5th floor
65 16th Slab concreting + conduits66 Deshuttering 14th slab & Preparing
surface for plaster67 Staircase temporary light at 10th
floor68 Curing to 15th slab & masonry on 8th
floor & plaster on 6th floor69 17th Slab concreting + conduits70 Deshuttering 15th slab & Preparing
surface for plaster71 Staircase temporary light at 11th
floor72 Curing to 16th slab & masonry on 9th
floor & plaster on 7th floor73 18th Slab concreting + conduits74 Deshuttering 16th slab & Preparing
surface for plaster75 Staircase temporary light at 12th
floor76 Curing to 17th slab & masonry on 10th
floor & plaster on 8th floor77 Bottom slab for lift M/C Room &
staircase room (Mumty)78 Deshuttering 17th slab & Preparing
surface for plaster79 Staircase temporary light at 13th
floor80 Curing to 18th slab & masonry on 11th
floor & plaster on 9th floor81 Completion of RCC pardi work in flat
up to 12th floor82 Fixing of electrical pipe junction &
D.B. box at 11th floor83 Fixing of electrical pipe junction &
D.B. box at 12th floor84 Handing over tiling agency 1st to 6th
floor85 Top slab for lift M/C Room &
staircase room (Mumty)86 Deshuttering 18th slab & Preparing
surface for plaster87 Staircase temporary light at 14th
floor88 Fixing of electrical pipe junction &
D.B. box at 14th floor89 Temporary godawans 4 nos. in brick
work90 Fixing of electrical pipe junction &
D.B. box on podium floor91 RCC railing for staircase & plaster92 MS Spiral stair for access to upper
roof93 Curing to bottom slab of Lift m/c
room & mumty, masonry on 12th floor & plaster on 9th & 10th floor
94 Fixing of electrical pipe junction & D.B. box at 13th floor
95 Submission of labour insurance96 Deshuttering bottom slab for lift M/C
Room & staircase room (Mumty) & preparing surface for plaster
97 Curing to top slab of Lift m/c room & mumty, masonry on 13th floor & plaster on 10th & 11th floor
98 Deshuttering top slab of lift M/C Room & staircase room (Mumty) & preparing surface for plaster
99 Curing masonry on 14th floor & plaster on 11th & 12th floor
100 OH Tank 101 Curring masonry on terrace , plaster
on 12th & 13th floor102 Deshuttering of OH Tank103 Curring to OH Tank, Plaster on 13th &
14th floor 104 Curring to plaster on 14th & terrace
floor105 Curring to masonry on podium floor106 Civil work for lift
Brick Work1 Rangat for masonry on 1st floor2 Masonry on 1st floor including door
frame3 Rangat for masonry on 2nd floor4 Masonry on 2nd floor including door
frame5 Rangat for masonry on 3rd floor6 Masonry on 3rd floor including door
frame7 Rangat for masonry on 4th floor8 Masonry on 4th floor including door
frame9 Rangat for masonry on 5th floor
10 Masonry on 5th floor including door frame
11 Rangat for masonry on 6th floor12 Masonry on 6th floor including door
frame13 Rangat for masonry on 7th floor14 Masonry on 7th floor including door
frame15 Rangat for masonry on 8th floor16 Masonry on 8th floor including door
frame17 Rangat for masonry on 9th floor18 Masonry on 9th floor including door
frame19 Rangat for masonry on 10th floor20 Masonry on 10th floor including door
frame21 Rangat for masonry on 11th floor22 Masonry on 11th floor including door
frame23 Rangat for masonry on 12th floor24 Masonry on 12th floor including door
frame25 Rangat for masonry on 13th floor26 Masonry on 13th floor including door
frame27 Rangat for masonry on 14th floor28 Masonry on 14th floor including door
frame29 Rangat for masonry on terrace floor30 Masonry on terrace floor including
door frame
31 Rangat for masonry on podium floor32 Masonry on podium floor including
door frame33 Rangat for masonry on lower
basement 34 Masonry on lower basement
Internal Plaster1 Internal plaster (Kitchen, Toilet &
Lobby) for 1st floor
2 Internal plaster in service slab on 1st floor
3 Internal plaster (Kitchen, Toilet & Lobby) for 2nd floor
4 Internal plaster in service slab on 2nd floor
5 Internal plaster (Kitchen, Toilet & Lobby) for 3rd floor
6 Internal plaster in service slab on 3rd floor
7 Internal plaster (Kitchen, Toilet & Lobby) for 4th floor
8 Internal plaster in service slab on 4th floor
9 Internal plaster (Kitchen, Toilet & Lobby) for 5th floor
10 Internal plaster in service slab on 5th floor
11 Internal plaster (Kitchen, Toilet & Lobby) for 6th floor
12 Internal plaster in service slab on 6th floor
13 Internal plaster (Kitchen, Toilet & Lobby) for 7th floor
14 Internal plaster in service slab on 7th floor
15 Internal plaster (Kitchen, Toilet & Lobby) for 8th floor
16 Internal plaster in service slab on 8th floor
17 Internal plaster (Kitchen, Toilet & Lobby) for 9th floor
18 Internal plaster in service slab on 9th floor
19 Internal plaster (Kitchen, Toilet & Lobby) for 10th floor
20 Internal plaster in service slab on 10th floor
21 Staircase plaster 1st to 7th floor22 Internal plaster (Kitchen, Toilet &
Lobby) for 11th floor23 Internal plaster in service slab on
11th floor 24 Internal plaster (Kitchen, Toilet &
Lobby) for 12th floor25 Internal plaster in service slab on
12th floor 26 Internal plaster (Kitchen, Toilet &
Lobby) for 13th floor27 Internal plaster in service slab on
13th floor 28 Meter room 29 Service slab jail up to 8th floor30 Internal plaster (Kitchen, Toilet &
Lobby) for 14th floor
31 Internal plaster in service slab on 14th floor
32 RCC grill in service area up to 7th floor
33 Plaster at terrace level34 Staircase plaster 8th to 14th floor
35 Internal plaster for lift m/c room & mumty
36 Internal plaster (Kitchen, Toilet & Lobby) for Podium floor
37 Service slab jail 8th to 14th floor38 Electric duct plaster39 Plaster work at stilt floor40 Plaster work at upper basement
External Plaster1 External plaster 1st floor
Balcony/Terrace2 External plaster 2nd floor
Balcony/Terrace3 External plaster 3rd floor
Balcony/Terrace4 External plaster 4th floor
Balcony/Terrace5 External plaster 5th floor
Balcony/Terrace6 External plaster 6th floor
Balcony/Terrace7 External plaster 7th floor
Balcony/Terrace8 External plaster 8th floor
Balcony/Terrace9 External plaster 9th floor
Balcony/Terrace10 External plaster 10th floor
Balcony/Terrace11 External plaster 11th floor
Balcony/Terrace12 External plaster 12th floor
Balcony/Terrace13 External plaster 13th floor
Balcony/Terrace14 External plaster 14th floor
Balcony/Terrace15 Dhada for external plaster up to 8th
floor16 External plaster up to 8th floor17 External plaster in duct up to 8th
floor18 Curring of plaster19 Dhada for external plaster 9th floor
to terrace20 External plaster 9th floor to terrace21 Curring of plaster
22 Balance External plaster23 RCC grill in service area 8th to 14th
floor.
Temporary Door1 Temporary Entrance door on 1st
floor2 Temporary Entrance door on 2nd
floor3 Temporary Entrance door on 3rd
floor4 Temporary Entrance door on 4th
floor5 Temporary Entrance door on 5th
floor6 Temporary Entrance door on 6th
floor7 Temporary Entrance door on 7th
floor8 Temporary Entrance door on 8th
floor9 Temporary Entrance door on 9th
floor10 Temporary Entrance door on 10th
floor11 Temporary Entrance door on 11th
floor12 Temporary Entrance door on 12th
floor13 Temporary Entrance door on 13th
floor14 Temporary Entrance door on 14th
floor 15 Cleaning & ghadai for flooring on 1st
floor16 Cleaning & ghadai for flooring on 2nd
floor17 Cleaning & ghadai for flooring on 3rd
floor18 Cleaning & ghadai for flooring on 4th
floor19 Cleaning & ghadai for flooring on 5th
floor20 Cleaning & ghadai for flooring on 6th
floor21 Cleaning & ghadai for flooring on 7th
floor
22 Cleaning & ghadai for flooring on 8th floor
23 Cleaning & ghadai for flooring on 9th floor
24 Cleaning & ghadai for flooring on 10th floor
25 Cleaning & ghadai for flooring on 11th floor
26 Cleaning & ghadai for flooring on 12th floor
POP/Gypsum Work1 Dhada for POP in Kitchen on 1st floor2 POP in kitchen on 1st floor3 Dhada for POP in Kitchen on 2nd floor4 POP in kitchen on 2nd floor5 Dhada for POP in Kitchen on 3rd floor6 POP in kitchen on 3rd floor7 Dhada for POP in Kitchen on 4th floor8 POP in kitchen on 4th floor9 Dhada for POP in Kitchen on 5th floor
10 POP in kitchen on 5th floor11 Dhada for POP in Kitchen on 6th floor12 POP in kitchen on 6th floor13 Dhada for POP in Kitchen on 7th floor14 POP in kitchen on 7th floor15 Dhada for POP in Kitchen on 8th floor16 POP in kitchen on 8th floor17 Dhada for POP in Kitchen on 9th floor18 POP in kitchen on 9th floor19 Dhada for POP in Kitchen on 10th
floor20 POP in kitchen on 10th floor21 Dhada for POP in Kitchen on 11th
floor22 POP in kitchen on 11th floor23 Dhada for POP in Kitchen on 12th
floor24 POP in kitchen on 12th floor25 Dhada for POP in Kitchen on 13th
floor26 POP in kitchen on 13th floor27 Dhada for POP in Kitchen on 14th
floor28 POP in kitchen on 14th floor29 Dhada for POP in Kitchen on podium
floor30 POP in kitchen on podium floor31 Lift lobby patra finish POP up to 8th
floor32 Lift lobby patra finish POP 9th floor
14th floor33 Dhada for Gypsum on 1st floor34 Gypsum on 1st floor35 Dhada for Gypsum on 2nd floor36 Gypsum on 2nd floor37 Dhada for Gypsum on 3rd floor38 Gypsum on 3rd floor39 Dhada for Gypsum on 4th floor40 Gypsum on 4th floor41 Dhada for Gypsum on 5th floor42 Gypsum on 5th floor43 Dhada for Gypsum on 6th floor44 Gypsum on 6th floor45 Dhada for Gypsum on 7th floor46 Gypsum on 7th floor47 Dhada for Gypsum on 8th floor48 Gypsum on 8th floor49 Dhada for Gypsum on 9th floor50 Gypsum on 9th floor51 Dhada for Gypsum on 10th floor52 Gypsum on 10th floor53 Dhada for Gypsum on 11th floor54 Gypsum on 11th floor55 Dhada for Gypsum on 12th floor56 Gypsum on 12th floor57 Dhada for Gypsum on 13th floor58 Gypsum on 13th floor59 Dhada for Gypsum on 14th floor60 Gypsum on 14th floor61 Dhada for Gypsum on podium floor62 Gypsum on podium floor63 Gypsum jud finishing at 1st floor64 Gypsum jud finishing at 2nd floor65 Gypsum jud finishing at 3rd floor
Water proofing work1 Internal water proofing for OH Tank2 IPS on top of OH Tank3 Toilet & balcony water proofing
work ( 1st to 7th floor)4 Terrace water proofing 5 Toilet & balcony Base coat water
proofing work ( 8th to 14th floor) 6 Balcony Brick bat water proofing
work ( 8th to 14th floor)7 IPS for Balcony (8th to 14th floor)
8 IPS in lift machine room
9 Toilet brick bat water proofing work (8th to 11th floor)
Sr. No. Description of Item
B. M/S Jainuine Marble
1 Staircase no.1 & 2 spotted & composite marble at window sill patti at lower basement
2 Staircase no.1 & 2 spotted & composite marble at window sill patti at upper basement
3 Staircase no.1 & 2 spotted & composite marble at window sill patti at stilt floor
4 Staircase no.1 & 2 spotted & composite marble at window sill patti at podium floor
5 Staircase no.1 & 2 spotted & composite marble at window sill patti at 1st floor
6 Spotted & Composite marble at window sill patti at 1st floor
7 Staircase no.1 & 2 spotted & composite marble at window sill patti at 2nd floor
8 Spotted & Composite marble at window sill patti at 2nd floor
9 Staircase no.1 & 2 spotted & composite marble at window sill patti at 3rd floor
10 Spotted & Composite marble at window sill patti at 3rd floor
11 Staircase no.1 & 2 spotted & composite marble at window sill patti at 4th floor
12 Spotted & Composite marble at window sill patti at 4th floor
13 Staircase no.1 & 2 spotted & composite marble at window sill patti at 5th floor
14 Spotted & Composite marble at window sill patti at 5th floor
15 Staircase no.1 & 2 spotted & composite marble at window sill patti at 6th floor
16 Spotted & Composite marble at
window sill patti at 6th floor17 Staircase no.1 & 2 spotted &
composite marble at window sill patti at 7th floor
18 Spotted & Composite marble at window sill patti at 7th floor
19 Staircase no.1 & 2 spotted & composite marble at window sill patti at 8th floor
20 Spotted & Composite marble at window sill patti at 8th floor
21 Staircase no.1 & 2 spotted & composite marble at window sill patti at 9th floor
22 Spotted & Composite marble at window sill patti at 9th floor
23 Staircase no.1 & 2 spotted & composite marble at window sill patti at 10th floor
24 Spotted & Composite marble at window sill patti at 10th floor
25 Staircase no.1 & 2 spotted & composite marble at window sill patti at 11th floor
26 Spotted & Composite marble at window sill patti at 11th floor
27 Staircase no.1 & 2 spotted & composite marble at window sill patti at 12th floor
28 Spotted & Composite marble at window sill patti at 12th floor
29 Staircase no.1 & 2 spotted & composite marble at window sill patti at 13th floor
30 Spotted & Composite marble at window sill patti at 13th floor
31 Staircase no.1 & 2 spotted & composite marble at window sill patti at 14th floor
32 Spotted & Composite marble at window sill patti at 14th floor
33 Spotted & Composite marble at window sill patti at Podium floor
34 1st floor Room & Balcony flooring work
35 1st floor Toilet flooring & dado tiling work.
36 2nd floor Toilet flooring & dado tiling work.
37 3rd floor Toilet flooring & dado tiling work.
38 4th floor Toilet flooring & dado tiling work
39 5th floor Toilet flooring & dado tiling work
40 2nd floor Room & Balcony flooring work
41 3rd floor Room & Balcony flooring work
42 1st floor Toilet Door Frame fixing work
43 2nd floor Toilet Door Frame fixing work
44 3rd floor Toilet Door Frame fixing work
45 4th floor Room & Balcony flooring work
46 4rd floor Toilet Door Frame fixing work
47 5th floor Toilet Door Frame fixing work
48 6th floor Toilet Door Frame fixing work
49 7th floor Toilet Door Frame fixing work
50 8th floor Toilet Door Frame fixing work
51 5th floor Room & Balcony flooring work
52 6th floor Room & Balcony flooring work
53 7th floor Room & Balcony flooring work
54 8th floor Room & Balcony flooring work
55 9th floor Room & Balcony flooring work
56 10th floor Room & Balcony flooring work
57 6th floor Toilet flooring & dado tiling work
58 7th floor Toilet flooring & dado tiling work
59 11th floor Room & Balcony flooring work
60 12th floor Room & Balcony flooring
work61 Protection sheet fixing at 1st floor
62 Protection sheet fixing at 2nd floor
63 13th floor Room & Balcony flooring work
64 14th floor Room & Balcony flooring work
65 China mosaic tiles fixing for service duct area at 1st floor
66 China mosaic tiles fixing for service duct area at 2nd floor
67 China mosaic tiles fixing for service duct area at 3rd floor
68 China mosaic tiles fixing for service duct area at 4th floor
69 Podium floor Room & Balcony flooring work
70 China mosaic tiles fixing for service duct area at 5th floor
71 China mosaic tiles fixing for service duct area at 6th floor
72 9th floor Toilet Door Frame fixing work
73 10th floor Toilet Door Frame fixing work
74 8th floor Toilet flooring & dado tiling work
75 Lift lobby flooring work at 1st floor
76 Lift lobby flooring work at 3rd floor
77 Lift lobby flooring work at 2nd floor
78 Lift lobby flooring work at 4th floor
79 Lift lobby flooring work at 5th floor
80 Lift lobby flooring work at 6th floor
81 Lift lobby flooring work at 7th floor
82 Lift lobby flooring work at 8th floor
83 China mosaic tiles fixing for service duct area at 7th floor
84 China mosaic tiles fixing for service duct area at 8th floor
85 9th floor Toilet flooring & dado tiling work
86 10th floor Toilet flooring & dado tiling work
87 11th floor Toilet Door Frame fixing work
88 Lift lobby flooring work at 9th floor
89 Lift lobby flooring work at 10th floor
Sr. No. Description of Item
C. Sai Siddhi Sanitation
1 Drainage work with chamber-East side
2 Drainage work with chamber-West side
3 Drainage work with chamber-North side
4 Drainage work with chamber-South side
5 Verification and approval of material6 Verification and approval of material7 Internal concealed water supply
(Podium to 7th floor)8 External water supply piping (Up to
7th floor) for flat no.1,2,3 &49 External water supply piping (Up to
7th floor) for flat no.5,6,7 & 810 External R/W piping ( up to 7th
floor) for flat no. 1,2,3 & 411 External R/W piping ( up to 7th
floor) for flat no.5,6,7 & 812 External & Internal concealed drain
piping (up to 7th floor) for flat no. 1,2,3,4,5,6,7 & 8.
13 Domestic & Flushing pump Delivery from Pump room to OH Tank
14 Verification and approval of material
15 External R/W piping ( 8th to 14th floor) for flat no. 1,2,3 & 4
16 External R/W piping ( 8th to 14th floor) for flat no.5,6,7 & 8
17 External water supply piping (8th to 14th floor) for flat no.1,2,3 &4
18 External water supply piping (8th to 14th floor) for flat no.5,6,7 & 8
19 External Drainage shaft piping (8th to 14th floor) for flat no.1 to 4
20 External Drainage shaft piping (8th to 14th floor) for flat no. 5 to 8
21 Pressure testing work at 1st floor
22 Cutting of groves for concealed plumbing work at 1st floor
23 Cutting of groves for concealed plumbing work at 2nd floor
24 Cutting of groves for concealed plumbing work at 3rd floor
25 Cutting of groves for concealed plumbing work at 4th floor
26 Cutting of groves for concealed plumbing work at 5th floor
27 Cutting of groves for concealed plumbing work at 6th floor
28 Cutting of groves for concealed plumbing work at 7th floor
29 Pressure testing work at 2nd floor
30 Pressure testing work at 3rd floor
31 Pressure testing work at 4th floor
32 Pressure testing work at 5th floor
33 Pressure testing work at 6th floor
34 Pressure testing work at 7th floor
35 Pressure testing work at podium floor
36 Internal concealed water supply 1st floor
37 Internal concealed water supply 2nd floor
38 Internal concealed water supply 3rd floor
39 Internal concealed water supply 4th floor
40 Internal concealed water supply 5th floor
41 Internal concealed water supply 6th floor
42 Internal concealed water supply 7th floor
Sr. No. Description of Item
D. Sai D.B. Enterprises
Sample Flat no.206
1 POP Scraping
1a 1st Coat Putty
1b 2nd Coat Putty
1c One coat primer
1d 1st Coat acrylic emulsion paint
1e 2nd Coat acrylic emulsion paint
1f 3rd Coat acrylic emulsion paint
2 Passenger lift-1 1st coat paint
3 Passenger lift-2 1st coat paint
4 1st coat distemper paint in LMR
5 Final coat distemper paint in LMR
6 L.V. Duct one coat primer paint
7 Fire Fighting duct 1 & 2 One coat Primer paint
8 Electric service duct one coat Primer paint
9 Meter room one coat primer
10 Meter room 1st coat (Distemper) primer
11 Meter room 2nd coat (Distemper) primer
Sr. No. Description of Item
E. Ravindra Electrical
1 Staircase point wiring work
2 Flat internal wiring work flat no.106
Sr. No. Description of Item
F. Naren Engineers India Pvt. Ltd.
1 Supplying & fixing of SS railing work 1st floor.
2 Supplying & fixing of SS railing work 2nd floor.
CONTRACTOR INFORMATIONSr. No. Name of the Contractor/Contact person Type of Contractor
1 Vishwakarma Construction/Mr.A.C.Roy-9820902141 / Mr. Deepak Wagh-9223399272
Civil
2 Jay Enterprises/Mr. Ramesh-9869035323/Mr.Jay-9768577222
Tiling
3 Sai Siddhi Sanitation/Mr. Ranjit Singh-9892326045/Mr.Datta-8097257674
Plumbing & Drainage
4 Noon Consultancy/Mr. Ali Asgar-9867900789/Mr.Pravin- Aluminum Window Contractor
5 Januine Marble/Mr. Jawanth Kothari -9820446953/Mr.Akhil Kotari-9833003885
Window Sills
6 Narendra Engineering/Mr. Narendra-9819844109/Mr.Roshan-9773358294
SS Glass Railing
7 Narendra Engineering/Mr. Narendra-9819844109/Mr.Roshan-9773358294
Fabrication
8 Vishwakarma & Aluminium/Mr.Brijraj-9324408089 Carpentry
9 Mr. Ikramuddin/9920338214 False ceiling
10 High Cool/Mr. Satnam Singh-9820147121/Mr.Ranjit Singh-8108197680
AC Contractor
12 Ajay Engineering/Mr. Kailash-9820491369 Fire Fighting
13 Sai D.B Enterprise/Mr. Praveen-9594891333/Mr.Vijay-9769303004
Internal Painting
14 Alno/Mr.Amit Kawa-9821923018 Modular Kitchen
15 Damani & Dyestuff/Mr.Anand Damani-9820210643 External Painting
16 Ravindra Electricals/Mr.Ravindra Palande-9821145420 Electrical works
17 Kone Elevators/Mr.Vaibhav-9619775989/Mr.Sijoy-9769027360
Lift Elevators
CONSULTANT INFORMATIONSr. No. Name of the Consultant/Contact Person Type of Consultant
1 AHC/Mr. Hiten-9820056974/Mr. Mohnish-02222661920 Architect
2 Mr. Ravibhai Kapadia BMC Architect
3 J+W Consultant/Mr. Nandkumar Patil-9822043912/Mr.Vinayak-9619493291
RCC
4 AECOM/Mr.Nadkarni-9867504201/Mr. Niraj Trivedi-9004050134
Electrical
5 D. Bhave Consultants /Mr. Bhave-9820100272/Mr.Rohidas-9221514688
Plumbing
6 D. Bhave Consultants /Mr. Fire Fighting
Bhave-9820100272/Mr.Rohidas-9221514688
7 Mr. Tak Mathew/William Rebello Lifts elevators
8 Taib Studio/Ms. Saidah-9886039458/Mr.Aneesh-9964462370
Landscape
9 Mr. Hema Kumar, Bangalore Waterfall/Fountain
10 AHC/Mr. Sunil Ghambani/Ashish Kanungo-9664040122 Interior Architect
11 Aakar Abhinav Consultant Pvt.Ltd Traffic Consultant
12 Mr. Hema Kumar, Bangalore Irrigation
13 Power Post/Mr. Sunil Shroff-9821289599 Electrical Power
14 Mr. Niranjan Mehta-9820032672 Plumbing & Liaisoning
15 Devekar Consultant ACP Cladding/Structural Glazing
16 Safe treat/Mr. Dalal STP